Loading the ALHD Canberra Canberra on M/V Blue Marlin

Agenda
1. Domestic A 1 D i Arrangements 2. 2 Safety Moment 3. Dockwise Short Introduction 4. Dockwise Navantia ALHD project 5. Dockwise Float on operations 6. Follow on actions

1. Instructions in Case of Emergency g y Domestic Arrangements


Evacuation Other Emergencies g Breaks Telephones p Introductions

Photo

Photo

2. Safety Moment y

What do you do? What can go wrong? How to prevent?

SAFETY MOMENT TRAVEL SAFETY SWITCH OFF MOBILE WHILE DRIVING


4

3. 3 Dockwise Short Introduction


Dockwise operates a fleet of 18 semisubmersible h b ibl heavy transport vessels. l
Heavy Marine Transport Transport & Installation Logistical Management Yacht Transport

World-Wide Offices:
Breda The Netherlands Houston USA Fort Lauderdale - USA Shanghai China Singapore Perth Australia Moscow Russia Busan South Korea Rio de Janeiro - Brasil
5

3. 3 Dockwise Short Introduction

Open deck ships

Dock-type ships

3. Dockwise Sh t Introduction 3 D k i Short I t d ti

Blue Marlin
Open-deck vessel
Length overall Breadth Depth Draft sailing Draft submerged Gross tonnage Deadweight Deck space Deck load Service speed p Maximum speed Range 224.50 m 63.00 m 13.30 m 10.08 m 28.40 28 40 m 51,821 t 76,061 t 63 x 178.2 m 178 2 27.5 t/sq.m 12 kn 13.3 kn 65 days

10

4. Dockwise Navantia ALHD P j t 4 D k i - N ti Project

Contracts signed July 2008 Risk Mitigation by ongoing State of the Art Engineering. Sea state Structural Integrity Float on Float off method Transport ALHD Canberra July 2012 September 2012 Canberra 2012. Transport ALHD Adelaide January 2014 March 2014.

11

4. Dockwise Navantia ALHD P j t 4 D k i - N ti Project

12

Loading L di llocation: ti

La C (P t L L Corua (Punta Langosteira) t i )

Bullet text number one Bullet text number two Bullet text number three Bullet text number four Bullet text number five Bullet text number six

Photo

Photo

Photo

min. water depth in deep hole : 23 m (from LAT) deep hole min. length deep hole : 250 m min. width deep hole : 75 m

13

Loading operation :
Preparation of Blue Marlins deck: Cribbing installed on deck Guideposts installed on deck (Part of) bow support frame pre -installed on deck, height depending on required static support after loading (Rest of) bow support frame temporarily stowed on deck, well away from ALHD loading/stowage area Sea fastening equipment laid out on Blue Marlins deck Duration: 2 to 3 days MWS supplies CoA for loading

Blue Marlin along quayside

Photo

Photo

Photo

14

Loading operation :

Typical Calculations

Photo

Photo

Photo

15

Loading operation :

Typical Schedule

Photo

Photo

Photo

16

Loading operation :

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

17

Loading operation :
Go/No go meeting held with Navantia, Harbour master, tugboat operators MWS and operators, Dockwise Communications tested. All aware of responsibilities. Weather/sea state window W th / t t i d agreed to be within limits for next 48 hours Around midnight Blue Marlin to start submerging Daybreak ALHD brought towards Blue Marlin with assistance of tugs g

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

18

Loading operation :
ALHD brought close to the stern of the Blue Marlin with assistance of tugs Vessels first tugger-wires connected to ALHD. Dockwise Superintendent from now in charge of operations operations. ALHD brought towards Blue Marlin with assistance of tugs More tugger-wires (aft) connected to ALHD Forward tug dismissed

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

19

Loading operation :
ALHD brought over Blue Marlins deck by means of tugger wires tugger-wires Tugs forward stand-by for assistance

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

20

Loading operation :
ALHD brought over Blue Marlins deck by means of tugger wires tugger-wires Cross wires connected with help of the vessels workboat Tugs forward stand-by for assistance i t

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

21

Loading operation :
ALHD brought over Blue Marlins deck by means of tugger wires tugger-wires Tugs forward stand-by for assistance

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

22

Loading operation :
ALHD in position above Blue Marlins deck Tugs forward stand-by for stand by assistance

Blue Marlin submerged to 22 m draft

Photo

Photo

Photo

23

Loading operation :
Tugs dismissed ALHD on cribbing / support on Blue Marlin s deck Marlins

Blue Marlin de-ballasting

Photo

Photo

Photo

24

Loading operation :
ALHD on cribbing / support on Blue Marlins deck Deck dry typically early afternoon, Late evening - sailing draft reached Prepare for seafastening Prepare to go alongside

Blue Marlin at sailing draft

Photo

Photo

Photo

25

Typical examples of sea fastening with bracings to be installed

Photo

Photo

Photo

26

Seafastening operation :
Installation work for sea fastening to start MWS to issue certificate of approval Customs clearance of ALHD cleared (Navantia) Port Authorities: Health, customs and immigration cleared (Dockwise) Departure Daily reporting via Dockwise Head Office to all relevant addressees. addressees

Blue Marlin along the quay

Photo

Photo

Photo

27

6. Follow up actions:
Assistance Shipping Agent In- and outward clearances Ordering pilot Assistance La Coruna Port Authorities Availability of the quay Availability f h A il bili of the anchor position h ii Port security Notices to Mariners Assistance Navantia Crew on board Canberra Assisting tugs

Photo

Photo

Photo

28