Professional Documents
Culture Documents
250 MW hydropower project to double Ugandas generation capacity US$900 million non-recourse/largest IPP project financing in SSA US$700 million long-term debt: 16-year facility from EIB, AfDB, DEG & IDA PROG Covered: Barclays/Absa & Standard Charted 20-year facility from IFC, Proparco & FMO US$180 million private equity (Blackstone & Aga Khan Foundation) & US$20 million public equity investment
cont
cont.
30 year BOT concession with availability-based PPA - full & capped pass-through elements within PPA tariff
Comprehensive government guarantees of the obligations of government agencies within the concession arrangements
Multi-competency government team negotiated the deal with the private sector and DFI lenders
Low High
None High Low None High High
Low High
None High Moderate Moderate High High
High High
Low None Low Weak Weak None
High High
Moderate Moderate Low Weak Weak None
C U S T O M E R S
MIGA
IDA PRG
DFI Lenders:
(IFC, EIB, AFDB, Proparco, DEG, FMO, KfW)
GOU Guarantee
Offtaker:
UETCL
EPC
O&M
EPC Contractor:
Salini/Alstom
Operator:
(Union Fenosa)
Regulatory Risk
Operational Strength of Sector Sustainability of Power Tariffs Unmet Electricity Demand
Level of Investments
Hydrology (Uganda)/Gas (Nigeria) Risk Fuel Risk Diversification Implementation (Largely Political) Risk
10
Private
Public
7. Financing of Investments
6. Bankability
11
Blackstone
GoU
PRG Project Agreement
Implementation
Agreement
1. 2. 3. 4. 5. 6.
Guarantee Agreement
Power Purchase Agreement
UETCL
Other DFIs
EPC Contract
O&M Contract
8. Construction
Operations/ Maintenance
12
Benefits to the country through Governments commitment to PPP Doubling of Ugandas electricity supply first power in late-2011 Sustainable boost to economic development of a land-locked country with limited alternative energy sources Dedication to sector reform and the BOT structure paid off Demonstration of private sector development of large scale hydropower investment is possible in riskier investment climate
cont
13
Private sector investors commitment on the strength of the PPP Investment of US$20 million pre-financing development capital as part of US$180 million in long-term equity investment US$700 million in ultra long-term debt investment Nearly on-schedule delivery of the project within expected cost Proven track record paves the way for other private sector involvement in riskier markets on the basis of a suitable PPP structure
Bold power expansion programs in riskier market places with limited track record are at least initially going to require a proactive PPP structure to achieve the objectives
14
Thank You
16