henever a power system is supplied by multiple sources, such as a main-tie-main configuration, special consideration should be given as to how the sources are phased or matched to each other. Obviously, both sources will have to be connected with the same phase rotation. In a traditional open-transition system, matched rotation of the sources may be sufficient. However, if a system is closed transition (the two sources may be tied together for some duration of time) it is critical that the two sources be phase matched. This means that the phase voltages on either side of the open point are in phase with each other. Additionally, high-speed open transition type systems may also need to be phase matched. With high-speed systems, it is possible that the collapsing magnetic fields of motor loads may maintain the bus voltage through the duration of the transfer. If this voltage is present and out of phase, closing the second source may cause a large spike of an apparent short-circuit current, resulting in possible nuisance tripping or other complications. Once any multisource system is initially energized, the phase matching must be verified.
cuits. Traditionally, this measurement has been accomplished by using a handheld voltmeter or high voltage tester, depending on the system voltages. However, due to various concerns such as additional exposure to arc-flash hazards, it may not be practical or safe to measure the voltages directly. Determining that it is not practical to measure the voltages directly makes it necessary to verify the phasing by making voltage measurements on the secondary of PT circuits.
Figure 2
Performing Measurements
Once the PT connections have been verified, the next step is to proceed with energizing the PTs by the two different sources. This is accomplished by opening the tie breaker and closing the other main. Until the phasing has been verified as being correct, all of these transfers must be opentransition, taking care not to tie the two sources together. For simplicity, source #1 will be set as the reference, with any suggested wiring changes being made to the source #2 connections. When dealing with three cables or conductors, there are six possible orders to connect them to the equipment, with only one being correct. Assuming that the two sources can be matched, the following table lists the voltages measured for the six possible connections of source #2. If dealing with a system that has a nominal secondary value other than 115 V, the number listed in parentheses is the multiple of nominal. It is worth noting, with one exception, that all of the incorrect connections yield the same voltage measurements, just in different orders: 1.0x; 3x; 3x; 2.0x
Figure 1
Conn. 1 2 3 4 5 6
Changes to Source 2 Connections The sources are correctly matched. Exchange B and C Exchange A and B Move A to B, B to C, and C to A Move A to C, B to A, and C to B Exchange A and C
There are several other transformer connections, some of which will not produce secondary voltages that can be matched. If any measurements are made that are not consistent with the previously listed tables, the sources and transformers should be investigated to determine what can be done to permit phasing of the secondaries.
Conclusions
Whenever possible and safe, it is best to verify phase matching by measuring the voltages to be phased directly. If PTs are to be relied on to determine phasing, the following must be verified: Both sets of PTs must be connected to the bus with the same configuration and with the same ratio and polarity. For open-delta connections, the B-phase secondary on each PT is grounded. Prior to paralleling the two sources, measure the various combinations of voltages to assure that phasing is correct. The addition of the PTs adds more potential for human error. Anyone performing this type of test must be competent and methodical in verifying the system.
After necessary measurements have been made, the system should be de-energized to make the necessary corrections. Once the system has been corrected, the system should be re-energized and the phasing verified.
Kevin Miller received his Bachelor of Electrical Engineering from The Georgia Institute of Technology. He works as a field service engineer with Electrical Equipment Upgrading, a NETA Full Member Company, in Savannah, Georgia. His primary responsibilities revolve around project management. Kevin is a Registered Professional Engineer with the state of Georgia and is a NETA Certified Level IV Technician.