Professional Documents
Culture Documents
Capital Budgeting
IM-605 Financial Management - II
Key Points for MBA (MS) 5 Years VI Sem. Session: Jan. 2012 Apr. 2012
Outline
Meaning of Capital Budgeting Significance of Capital Budgeting Analysis Traditional Capital Budgeting Techniques
Payback and Post Payback Period Approach Discounted Payback and Post Discounted Payback Period Approach
Capital Rationing
3/20/2012
What is the difference between independent and mutually exclusive projects? Projects are: independent, if the cash flows of one are unaffected by the acceptance of the other. mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other.
3/20/2012
2
12 K
3
15 K
4
10 K
5
7K
PBP is the period of time required for the cumulative expected cash flows from an investment project to equal the initial cash outflow.
3
15 K 37 K
(a)
0
-40 K -40 K
1
10 K -30 K
2
12 K -18 K
3
15 K -3 K
4
10 K 7K
5
7K 14 K
10 K (c) 47 K
PBP
PBP
Cumulative Cash Flows
Note: Take absolute value of last negative cumulative cash flow value.
Weaknesses: Weaknesses:
Does not account for TVM Does not consider cash flows beyond the PBP Cutoff period is subjective
3/20/2012
CFn (1+k)n
- ICO
NPV Solution
Basket Wonders has determined that the
appropriate discount rate (k) for this project is 13%. $10,000 $12,000 $15,000 NPV = + + + (1.13)1 (1.13)2 (1.13)3 $10,000 $7,000 + (1.13)4 (1.13)5 - $40,000
Managers like rates--prefer IRR to NPV comparisons. Can we give them a better IRR?
Yes, MIRR is the discount rate which causes the PV of a projects terminal value (TV) to equal the PV of costs. TV is found by compounding inflows at WACC. Thus, MIRR assumes cash inflows are reinvested at WACC. [ See last slides for details)
3/20/2012
Weaknesses: Weaknesses:
Assumes all cash flows reinvested at the IRR Difficulties with project rankings and Multiple IRRs
PI Acceptance Criterion
PI = $38,572 / $40,000 = .9643 (Method #1, 13-34)
Should this project be accepted? No! The PI is less than 1.00. This means that the project is not profitable. [Reject as PI < 1.00 ]
ICO
<< OR >>
Method #2:
PI = 1 + [ NPV / ICO ]
3/20/2012
Weaknesses: Weaknesses:
Same as NPV Provides only relative profitability Potential Ranking Problems
Capital Rationing
Capital Rationing occurs when a constraint
(or budget ceiling) is placed on the total size of capital expenditures during a particular period.
Example: Julie Miller must determine what investment opportunities to undertake for Basket Wonders (BW). She is limited to a maximum expenditure of $32,500 only for this capital budgeting period.
ICO
IRR
NPV
$
ICO
IRR
NPV
PI
Projects C, F, and E have the three largest IRRs. The resulting increase in shareholder wealth is $27,000 with a $32,500 outlay.
3/20/2012
ICO
IRR
NPV
ICO
IRR
NPV
PI
$15,000 28% $21,000 2.40 5,000 25 6,500 2.30 C 5,000 37 5,500 2.10 D 7,500 20 5,000 1.67 G 17,500 19 7,500 1.43 Projects F, B, C, and D have the four largest PIs. The resulting increase in shareholder wealth is $38,000 with a $32,500 outlay.
Summary of Comparison
Method Projects Accepted PI F, B, C, and D NPV F and G IRR C, F, and E Value Added $38,000 $28,500 $27,000
PI generates the greatest increase in shareholder wealth when a limited capital budget exists for a single period.
3/20/2012
1 5,000
2 -5,000
Enter CFs in CFLO, enter I = 10. NPV = -386.78 IRR = ERROR. Why?
Capital Rationing
If external funds will be raised, then the NPV of all projects should be estimated using this higher marginal cost of capital. Capital rationing occurs when a company chooses not to fund all positive NPV projects. The company typically sets an upper limit on the total amount of capital expenditures that it will make in the upcoming year.
(More...)
3/20/2012
Reason: Companies want to avoid the direct costs (i.e., flotation costs) and the indirect costs of issuing new capital. Solution: Increase the cost of capital by enough to reflect all of these costs, and then accept all projects that still have a positive NPV with the higher cost of capital.
(More...)
Reason: Companies dont have enough managerial, marketing, or engineering staff to implement all positive NPV projects. Solution: Use linear programming to maximize NPV subject to not exceeding the constraints on staffing.
(More...)
Reason: Companies believe that the projects managers forecast unreasonably high cash flow estimates, so companies filter out the worst projects by limiting the total amount of projects that can be accepted. Solution: Implement a post-audit process and tie the managers compensation to the subsequent performance of the project.