ARCHN305 Building Construction III

BUILDING CONSTRUCTION III


ARCHN305

QUANTITIES CALCULATION
HESHAM KHAIRY

Sunday, May 21, 2010 Sunday,March16, 2010

Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS

ARCHN305 Building Construction III

Example in Quantities Calculation Guard room

Room 4.00 4.00 m Cl. To Cl. Room 4.25 4.25 m Total Total Height = 3.00 m Wood Door 1.00 2.20 m Alum. Window 1.20 1.00 m
D1 W1

Sunday, May 21, 2010 Sunday,March16, 2010

Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS

ARCHN305 Building Construction III

Example in Quantities Calculation Guard room

Slab Thickness = 12 cm Beams = 25 60 cm Columns 25 25 cm

Sunday, May 21, 2010 Sunday,March16, 2010

Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS

ARCHN305 Building Construction III

Example in Quantities Calculation Guard room

Sunday, May 21, 2010 Sunday,March16, 2010

Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS

ARCHN305 Building Construction III

Calculations
Excavation Footing Excavation = 4 1.25 1.25 2.00 = 12.500 m Smells Excavation = 4 2.75 1.30 0.25 = 3.575 m Total Excavation = 16.075 m Plain Concrete Footings = 4 1.25 1.25 0.40 = 2.500 m Total P.C.= 2.500 m Reinforced Concrete for Foundations Footing = 4 0.75 0.75 0.30 = 0.675 m Smells = 4 0.25 0.40 3.75 = 1.500 m Columns Necks = 4 0.25 0.25 1.30 = 0.325 m Total Foundation R.C. = 2.500 m
Sunday, May 21, 2010 Sunday,March16, 2010 Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 5

ARCHN305 Building Construction III

Calculations
Fill Fill = 16.075 2.5 2.5 = 11.075 m Total Fill = 11.075 m Reinforced Concrete for Skelton Columns = 4 0.25 0.25 2.40 = 0.600 m Beams = 4 3.75 0.25 (0.60 0.12) = 1.800 m Slab = 4.25 4.25 0.12 = 2.1675 m Brick works Total Skelton R.C. = 4.5675 m

Brick = (4 3.75 2.40 ) (1.00 1.20) (1.00 2.20) = 32.600 m Floor Tiles Total Brick works= 32.600 m

Floor Tiles = (4 4) (4 0.125 0.125) = 15.9375 m Total Floor Tiles = 15.9375 m


Sunday, May 21, 2010 Sunday,March16, 2010 Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 6

ARCHN305 Building Construction III

Calculations
Plaster Ceiling Plaster = (4 4) (4 0.125 0.125) = 15.9375 m Walls Plaster = 4 4 (3 0.12) (1.20 1.00) (2.20 1.00) = 42.68 m Total Plaster = 58.6175 m Painting Ceiling Painting = (4 4) (4 0.125 0.125) = 15.9375 m Walls Painting = 4 4 (3 0.12) (1.20 1.00) (2.20 1.00) = 42.68 m Corniche ( ) Corniche = 4 4 = 16.000 m Cill ( ) Cill = (4 4) 1.00 = 15.000 m Corniche = 15.000 m
Sunday, May 21, 2010 Sunday,March16, 2010 Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS 7

Total Painting = 58.6175 m

Corniche = 16.000 m

ARCHN305 Building Construction III

Very important notes


In External work: Brick works: in case of flat openings....Deduct all openings. in case of Curved openings..Deduct half openings only.

Plaster works: in case of openings less than 4m......No Deduction. in case of openings more than 4m....Deduct half openings only.

Sunday, May 21, 2010 Sunday,March16, 2010

Lecture 4, 5 - Lecture 10 Quantities Calculation CONSTRUCTION MANAGEMENT & BUILDING ECONOMICS