Handing Over Checklist ( Erection to Commissioning )

Index 1) Civil foundation 2) Tanks / vessels 3) Pumps/Motor/Alignment 4) Hydro test 5) Battery bank 6) Transformer 7) Bus duct erection 8) Panel erection 9) Cable tray 10) Raw water system 11) DM system 12) Chemical laboratory 13) Neutralizing pit/ Effluent treatment 14) Cooling tower system, CWP, ACWP 15) Instrument compressor 16) Air conditioning system 17) Distributed control system ( DCS ) 18) Main & Auxiliary steam line 19) Chimney completeness 20) Pegging system 21) Chemical dosing 22) Feed water system 23) Fire water system 24) Fire alarm system 25) Boiler commissioning 26) SWAS panel 27) Condensate system (water cooled) 28) STG

civil foundation
1) 2) 3) 4) 5) 6) Inspect the foundation for visual check, unevenness Alignment of foundation from reference line Foundation level difference ( datum point check ) Max. difference in foundation level w.r.t. ref. level Height of bolt above foundation level Alignment checked for foundation bolts/pockets w.r.t. ref. line ( horizontal / diagonal ) 7) Pocket size, depth & verticality 8) Drawing ref. no.

Tanks
1) 2) 3) 4) 5) 6) 7) Orientation as per drg. Structures completeness and welding Cleanliness of internal leveling Verticality Rediness of foundation Name of equipment Drawing no.

Pumps
1) Inspect for visual damage to pumps 2) All piping, check valves, controls and structural supports for equipments are installed 3) All debris is removed from work site and all equipments including casing sumps are cleaned 4) Safety devices are installed relief v/v, pr. Gauge 5) i/t & discharge line flanges are correctly installed and securely gasketed 6) pump leveling checked 7) Pump orientation checked 8) Coupling hub fitted on pump 9) Pump lubrication

10) 11) 12) 13) 14)

Suction and discharge pipes are not in tension Pump coupled with prime mover Pumps serial no. Equipment description Reference drg. No.

Motors
1) Available motor is as per norms 2) Check motors elevation and leveling as per drg. 3) Motor pulley/coupling fitment/tightness checked 4) All foundation bolts are tight 5) Check motors base frame all bolts are used for alignment 6) Check full length shims have been provided for alignment 7) Motor serial no. 8) Reference drg. No. 9) Motor lubrication 10) Motor ear thing and merger done 11) Motor orientation 12) Power supply availability 13) Motor earthing/meger 14) Relay setting 15) Direction checking & no load trial

Pump & Motor alignment


1) 2) 3) 4) 5) 6) 7) 8) 9) Location Pump serial no. Motor serial no. Civil foundation protocols prepared Pump/motor orientation checked Pre alignment of pump/motor checked Coupling hub fitted on pump/motor shaft Distance Between shaft end checked Motor and pump checked for lubrication

10)

Axial and radial alignment reading

Hydro test
1) System name 2) Drawing refn. No. 3) Line details 4) Joint details 5) Pipe size 6) NDT for the line report 7) Hydro test pressure as per drg. 8) Hydro test pr. 9) Holding time 10) Flushing media 11) No. of times flushing carried out 12) End result of flushing

Battery bank
a) Civil 1) Room readiness acid lining bricks 2) House keeping 3) Room closing doors 4) Opening for exhaust fan 5) Grouting of battery bank 6) Flooring 7) Opening for cable b) Mechanical 1) Installation of battery bank 2) Installation of exhaust fan 3) Cell alignment 4) Tightness of inter cell connected links 5) Battery set alignment

6) Sealing of each cell c) Electrical 1) Exhaust fan supply and starter 2) Lighting of room 3) Reading of charging current, voltage, gravity and temp. of cells taken 4) Size of incoming cable as per spec 5) Cable laying incoming & outgoing

Transformer
a) civil 1) foundation completion b) mechanical 1) base frame erection 2) leveling 3) erection of radiators, breather vent, oil temp. indicator, winding temp. 4) wheel fixing arrangement

Bus duct erection


a) civil 1) wall opening as per drg. 2) Insert plates mounting for supports 3) Wall sealing b) Mechanical 1) Bus duct supporting 2) Erection of bus duct 3) Erection of loose supplied material 4) Bus bar coupling plates

5) 6) 7) 8)

Bimetallic plate inserted between two different metals All nut/bolt tightness Inside/outside cleaning Earthing of bus

Panel erection
a) Civil 1) Room readiness plastering, white wash 2) House keeping 3) Room closing doors 4) Opening for exhaust fan 5) Opening for cable laying 6) Flooring 7) Cut outs at floor 8) Floor opening dimensions

b) Mechanical 1) Panel placement 2) Alignment and leveling 3) Base frame support

c) Electrical 1) Cable laying 2) Inter panel connection 3) Bus bar 4) Control/power wiring 5) Earth bus bar 6) Supply and testing 7) Exhaust fan connection and trial

Cable tray
a) civil 1) wall opening as per drg. 2) Insert plates mounting for supports 3) Wall sealing b) Mechanical 1) Supporting 2) Tray laying 3) Alignment and leveling 4) Covering 5) Painting c) Electrical 1) Earthing 2) Cable laying

Raw water system


a) Civil 1) Completion of pump/motor foundation as per drg. 2) Grouting of base frame 3) Room readiness (completion of brick work, plastering,flooring, window glass and door fit up) 4) Checking for insert plate if any 5) Approach/ladder for roof 6) Hydro test of reservoir/sump tank 7) Drainage system 8) House keeping and removing of all debris 9) Priming tank grouting 10) Reservoir readiness hydro fill test 11) Sump tank readiness hydro fill test 12) Any opening to raw water reservoir are closed by plates/gratings

13) Covers across piping going to raw water reservoirs are covered by plates 14) Rung ladders to raw water tank is provided 15) Epoxy coating to raw water reservoir is provided 16) Cleaning of raw water reservoir before water filling b) Mechanical 1) Installation of motor and pump 2) Completion of all piping and tapping works as per P & ID 3) Supports completion 4) Alignment checking 5) O & M feasibility check 6) Approach for operating v/vs etc 7) Monorail installation 8) Gland rain provision 9) Coupling guard and cover 10) Hydro test of piping 11) Installation of priming tank 12) Completion of i/t / o/t piping from priming tank 13) Checking of pump & motor installation as per drg. 14) Specification 15) Check motors base frame all bolts are used for alignment 16) Check full length shims have been provided for alignment 17) Cut shims are not allowed 18) Operation of sluice gate v/vs and availability of wheels at the v/vs 19) Complete installation of fire diesel pump at raw water pump house including silencer, tank, battery 20) Proper sized bolts & nuts have been used, extra length bolts/short bolts are not allowed

c) Electrical 1) Power supply availability 2) Area illumination 3) Motor earthing/meger

4) Relay setting 5) Direction checking & no load trial 6) Checking of feeder rating/overload 7) Relay rating as per specs d) Control & instrumentation 1) Completion/installation of tappings for Pg/Pt/Lt/Fs 2) Installation of all gauges as per P & ID 3) Setting and calibration 4) Trail from DCS 5) Proper impulse tube routine & its support

DM Plant
a) Civil 1) Construction of clarifier and storage tank 2) Hydro fill test 3) Inside plastering 4) Inside ground floor leveling 5) Inside coating 6) Opening for DM/CW M/U Pumps, drain overflow and vents 7) Opening for going inside and provisions of riggers 8) V notch fixing 9) Opening for chemical treatment discharge lines 10) CS to CST outer area covering 11) Foundation for chemical dozing pumps and tanks 12) Ladder provision 13) Foundation for DMF/SAC/SBA/DEGRASSER/Pumps at CST o/l 14) DM plant flooring 15) Drainage 16) Acid proof tiling 17) Flow measuring devices 18) DM plant roofing 19) Side sheeting

20) Construction and readiness of chemical laboratory 21) DM control room readiness/flooring/ceiling 22) A/C provisions 23) MCC constructions 24) Flooring 25) House keeping 26) Doors/window/glass placement 27) Opening for cable tray 28) Foundation for DM tanks and coal tar provisions 29) Ground leveling 30) House keeping 31) Acid and alkali dosing cum transfer pumps and tank foundation completion 32) Completion of acid/alkali dyke

b) Mechanical 1) Piping from raw water pump house to CS 2) Completions of tank related piping like drain, overflow, suction piping, manhole covering, vents, hand railing 3) Placement of CW M/U, DM Feed, DM back wash and MB blowers and recirculation line as per P & ID 4) Placement of DM plant vessels 5) Completion of piping from and to vessels with all drains, vents as specified in drawing 6) Supports and groutings 7) Acid and alkali dosing cum transfer pumps and tank erection and completion of related all piping 8) DM storage tanks erection and completion of all piping 9) DM tank inside epoxy coating 10) Hydro fill test 11) Completion of piping from DM tank outlet to boiler/Deareator/HP/LP dozing/Condenser with proper supports / Orifice

12) Chemical dozing system erection and completion of piping as per P & ID 13) Laying of pipe lines keeping in view of O & M 14) Cable tray laying with proper supports

c) Electrical 1) Power supply availability 2) Motor earthing/meger 3) Relay setting 4) Direction checking/ no-load trial 5) Area illumination 6) Proper routing of cables 7) MCC panels erection and charging 8) Cabling from MCC to all equipments 9) Power supply availability

d) Control & Instrumentation 1) Installation of all gauges, switch, transmitter as per P & ID 2) Setting and calibration 3) Trial from DCS 4) Completion/Installation of tappings for PG/PT/LT/FS 5) Tank lvl switch and transmitter 6) Cabling from MCC to DCS of all equipments 7) Solenoid vlvs/jb/db placement 8) Cabling from jb to equipment and jb to DCS

Chemical lab
a) Civil 1) Room readiness plastering, white wash 2) House keeping

3) 4) 5) 6) 7) 8) 9)

Room doors Opening for exhaust fan Wash basin and drain Flooring Opening for cable Water supply taps Racks and shelf

b) Mechanical 1) Exhaust fan installation 2) Lab testing equipments supply as per list 3) Lab testing equipments supply from client/ O & M 4) Ventilation fans

c) Electrical 1) Supply of 220V & 440V to furnace / oven 2) Room lightening 3) MLDB & MCB installation 4) Exhaust fan supply and trial

Neutralizing Pit & Effluent Treatment Plant


a) Civil 1) Completion of NP & EP tanks 2) Acid resistance coating 3) House keeping and removing of all debris 4) Cleaning of tank 5) Grouting of E pumps and NP 6) Rung ladder on neutralizing pit and effluent treatment plant

b) Mechanical

1) Motor & pump alignment 2) Completion of all piping and tapping works as per P & ID 3) Supports completion 4) Alignment and orientation checking 5) O & M feasibility check 6) Approach for operating v/vs etc 7) Coupling guard and cover 8) Hydro test of piping 9) Removing of temp. supports 10) Tank all accessories and mounting installation 11) Gland drain

c) Electrical 1) Power supply availability 2) Motor earthing /meger 3) Relay setting 4) Direction checking & no load trial 5) Area illumination 6) Proper routing of cables

d) Control & Instrumentation 1) Completion / installation of tappings for PG/PT/IT/FS 2) Installation of all gauges as per P & ID 3) Setting and calibration 4) Trial from DCS 5) Tank level switch and transmitter

Cooling Tower, CWP & ACWP


a) Civil

1) Completion of foundation for motor, pumps, gear box, CT fans spec. as per drawing 2) Completion of fore bay / basin 3) Inside partition wall 4) Opening for screens 5) Opening for chemical dozing, instrument tappings 6) Inside drain location 7) Top deck completion 8) Approach for fore bay / cell / basin 9) Hydro fill test 10) Inside cleaning 11) House keeping 12) Stair case & railings 13) CT structure grouting 14) Base frame grouting 15) Mono rails pillars 16) Line pedestal supports 17) Staircase 18) Railing 19) Drainage system

b) Mechanical 1) Completion of all piping with gaskets as per P & ID 2) Screens placement 3) Supports 4) M/U line C/V installation 5) Coating and height of under ground pipe line 6) Pump & motor installation 7) Alignment and coupling 8) Gland leakage drain 9) Strainer dismantling provision 10) Suction strainer and discharge drain provision 11) MOVS installation and orientation check 12) Disc. Line ht.

13) Gear box, fan motor placement and alignment 14) Clearance of blade w.r.t. hub 15) Oil and vibration line installation 16) Line flushing and looping arrangement 17) Nozzle/ De installation 18) Removing of temp. supports c) Electrical 1) Power supply availability 2) Motor earthing / meger 3) Relay setting 4) Direction checking & no load trial 5) Area illumination 6) Full load trial and setting 7) MOVS supply and termination 8) MOV settings and trial 9) Proper routing of cabls

d) Control & instrumentation 1) Installation of all gauges, FE and switch as per P & ID 2) Setting and calibration of switch / gauges / FE 3) Control v/v tubing and stroke checking 4) Trial from DCS

Instrument compressor
a) Civil 1) Foundation of motor, compressor, air drying plant, control panel, receivers, inter cooler and after cooler as per drg. 2) Completion of flooring 3) Opening for exhaust fan 4) Room readiness plastering, white wash 5) Insert plates for monorail ( optional) 6) House keeping

7) Grouting of compressor and motor 8) Closing of room by shutters

b) Mechanical a) Civil 1) Completion of all piping with gaskets as per P & ID 2) Compressor and motor alignment and clearance to civil for grouting 3) Safety guard 4) Intercooler and after cooler alignment and grouting clearance 5) Supports 6) Temp. supports removal 7) Monorail erection (optional) 8) Compressor / ADP /receivers all accessories and mounting placing 9) ADP placement and alignment and grouting clearance 10) Receivers tanks placement and alignment and grouting clearance 11) Leak test of all pipe lines at different location 12) Provision of service and root v/vs in all pipelines as per drg. 13) Line flushing and looping arrangement 14) Auto drain trap piping and drain arrangement b) Electrical 1) Power supply availability 2) Motor earthing / meger 3) Relay setting 4) Direction checking & no load trial 5) Area illumination 6) Full load trial 7) Proper routing of cables 8) Supply to compressor const panel 9) Air drying plant connection 10) Auto drain trap supply

c) Control & instrumentation 1) Availability of inst. Tapping points as per P & ID 2) Installation of all gauges, FE and switch as per P & ID 3) Setting and calibration of switch / gauges / FE 4) Control v/v tubing and stroke checking 5) Trial from DCS 6) Wiring of control panel 7) Adt air tubing

Air conditioning system


a) civil 1) foundation of unit supplied and humidifier as per drg. 2) Foundation of motor, compressor, air drying plant, control panel, receivers, inter cooler and after cooler as per drg. 3) Completion of flooring 4) Opening for exhaust fan 5) Room readiness plastering, white wash 6) House keeping 7) Grouting of unit 8) Closing of room 9) Control room ceiling 10) Control room flooring 11) Doors / windows fitting 12) Insert plate for ducts supports b) mechanical 1) completion of all piping with gaskets as per P & ID 2) supports 3) temp. supports removal 4) line flushing and looping arrangement 5) humidifier unit placement and its piping 6) conditioner drain arrangement 7) air supply line & fire dampers 8) completion of delivery and return duct with supports

9) exhaust fan installation & trail run 10) cleaning of ducts c) electrical 1) power supply availability 2) relay setting 3) direction checking & no load trail 4) area illumination 5) full load trail 6) proper routing of cables 7) thermostat connection 8) humidifier control panel completion 9) supply to fire damper

d) control & instrumentation 1) erection & installation of all gauges, FE & SWITCH as per P & ID 2) setting and calibration of switch / gauges / FE 3) interlock with fire alarm

DCS
a) civil 1) control room readiness 2) all openings to be closed 3) flooring of control room 4) fittings of doors and window 5) readiness of engineering station b) mechanical 1) panel placement 2) A/C system readiness 3) Readiness of ducts and ventilation system

c) Electrical 1) Cabling from panel to DCS 2) Control room lightening 3) Readiness of UPS

d) Control & instrumentation 1) Cabling from panel to DCS 2) Control cable 3) Cabling from DCS panel to MCC 4) Cabling from field to DCS panel

Main & auxiliary steam


a) Civil 1) Completion of RCC structure 2) Completion of pedestals supports 3) Grouting of supports 4) Inserts on floor for pipe line supports 5) Anchor fastening of supports

b) Mechanical 1) Laying of main steam and aux. steam line as per P & ID 2) Supports as per P & ID 3) Springs supports provisions as per drg. 4) Tappings for drains, vents, strainers, instrument connection 5) Hydro test / RD / stress reliving 6) Installation of NRV, isolation v/vs , MOVS as per P & ID 7) Platform and approach 8) Cladding 9) Insulation 10) Drains to safe locations

11) 12) 13)

Blowing arrangement with supports as per drg. Target plate fixture Air supply provision to control v/v

c) Electrical 1) MOVS connections and settings 2) MOVS supply and trail from local

d) Control & instrumentation 1) Installation of all gauges and control v/vs as per P & ID 2) Setting and calibration 3) Trail from DCS 4) Completion / installation of tappings for PG/PT/LT/FS 5) Taking all PT/LT/FT in line

Chimney
a) Mechanical 1) Ends connection with boiler ducts 2) Air supply pipes

b) Electrical 1) Illumination aviation light installation and supply 2) Cable laying 3) Lightning arrestor

c) Control & instrumentation 1) Supply & installation of SPM/ OPOCITY meter

Pegging system
a) Civil 1) Completion of RCC structures / roofing of STG room 2) Completion of pedestals supports 3) Grouting of supports 4) Inserts on floor for pipe line supports 5) Anchor fastening of supports 6) Opening for steam line

b) Mechanical 1) Laying of pegging steam line as per P & ID 2) Supports as per P & ID 3) Springs supports provisions as per drg. 4) Tappings for drains, vents, strainers, instrument connections 5) Hydro test / RD / stress reliving 6) Installation of NRV, isolation v/vs, MOVS as per P & ID 7) Platform and approach 8) Cladding 9) Insulation 10) Drains to safe locations 11) Blowing arrangement with supports as per drg. 12) Air supply provision to control v/v 13) Feed water line for De superheating

c) Control & instrumentation 1) Installation of all gauges and control v/vs as per P & ID 2) Setting and calibration 3) Trail from DCS 4) Completion / installation of tappings for PG/PT/LT/FS 5) Taking all PT/LT/FT in line

Chemical dosing
a) Civil 1) Completion of base plate foundation as per drg. 2) Grouting of base frame 3) Drainage system 4) House keeping and removing of all debris

b) Mechanical 1) Installation base frame and leveling 2) Completion of all piping and tapping works as per P & ID 3) Supports completion 4) Alignment and orientation checking 5) O & M feasibility check 6) Approach for operating v/vs etc 7) Monorail installation ( optional) 8) Coupling guard and cover 9) Hydro test of piping 10) Removing of temp. supports 11) Completion of internal piping 12) Cleaning of tank 13) Tank all accessories and mounting installation

c) Electrical 1) Power supply availability 2) Motor earthing / meger 3) Relay setting 4) Direction checking & no load trail 5) Area illumination 6) Proper routing of cables

d) Control & instrumentation 1) Completion / installation of tappings for PG/PT/LT/FS 2) Installation of all gauges as per P & ID 3) Setting and calibration 4) Trail from DCS

Feed water system


a) Civil 1) Completion of foundation of BFP 2) Deareator foundation pedestals 3) Foundation bolts 4) Grouting of de-areator at one side only 5) Deareator to BFP suction pipe support 6) Inserts plates 7) Approach to deareator 8) Cable trench for cable laying 9) Trench cleaning 10) Opening for suction pipes

b) Mechanical 1) Deareator installation 2) Motor & pump alignment, packer plates installation 3) Completion of all piping and tapping works as per P & ID 4) Supports completion 5) Alignment and orientation checking 6) Operation and maintenance feasibility check 7) Approach for operating v/vs etc 8) Coupling guard and cover 9) Hydro test of piping 10) Removing of temp. supports 11) Tank all accessories and mounting installation

12) Gland drain 13) Cooling water line, M/U line to deareator balancing and leak off line with supports 14) Deareator inside welding 15) Springs and hanger supports and cold setting 16) Coupling guard and cover 17) Hydro test of piping 18) Vent, drain, C & I, tappings 19) MOVS, V/VS Installation 20) DP switch tapping

c) Electrical 1) Power supply availability 2) Motor earthing / meger 3) Relay setting 4) Area illumination 5) Direction checking & no load trail 6) Proper routing of cables 7) MOVS supply and termination 8) MOV settings and trail

d) Control & instrumentation 1) Completion / installation of tappings for PG/PT/IT/FS/DP switch 2) Installation of all gauges as per P & ID 3) Setting and calibration 4) Trail from DCS 5) Control cable laying and termination

Fire water system


a) Civil

1) Completion of pump / motor foundation as per drg. 2) Grouting of base frame 3) Room readiness 4) Checking for insert plate if any 5) Approach / ladder for roof 6) Hydro test of reservoir / sump tank 7) Drainage system 8) House keeping and removing of all debris 9) Priming tank grouting 10) Reservoir readiness hydro fill test 11) Sump tank readiness hydro fill test 12) Raggers on sump tank / pump house

b) Mechanical 1) Installation of motor and pump 2) Completion of all piping and tapping works as per P & ID 3) Supports completion 4) Alignment checking 5) O & M feasibility check 6) Approach for operating v/vs etc 7) Monorail installation 8) Gland rain provision 9) Coupling guard and cover 10) Hydro test of piping 11) Installation of priming tank 12) Completion of i/t / o/t piping from priming tank 13) Completion of all instrument tappings upto battery limit 14) Removing of temp. supports 15) For diesel pump fitting of diesel tank & its connection, battery

c) Electrical 1) Power supply availability 2) Area illumination

3) 4) 5) 6)

Motor earthing / meger Relay setting Direction checking & no load trail Proper routing of cables

d) Control & instrumentation a) Completion / installation of tapping for PG/PT/LT/FS b) Installation of all gauges as per P & ID c) Setting and calibration d) Trail from DCS

Fire alarm system


a) Civil 1) Completion of roofing / false ceiling

b) Mechanical 1) Installation of fire alarm sensors as per drg. 2) Laying of GI conduit piping for cabling 3) Installation for fire alarm panel

c) Electrical 1) Fire alarm panel readiness 2) Cabling from fire alarm points to panel 3) Loop checking 4) Power supply availability 5) Setting 6) Area illumination 7) Proper routing of cables

Boiler pre commissioning ( control v/vs checking )


a) Civil 1) Completion of foundation of BFP 2) Deareator foundation pedestals 3) Foundation bolts 4) Grouting of deareator at one side only 5) Deareator to BFP suction pipe supports 6) Inserts plates 7) Approach to deareator 8) Cable trench for cable laying 9) Trench cleaning 10) Opening for suction pipes

b) Mechanical 1) Deareator installation 2) Motor & pump alignment, packer plates installation 3) Completion of all piping and tapping works as per P & ID 4) Supports completion 5) Alignment and orientation checking 6) O & M feasibility check 7) Approach for operating v/vs 8) Hydro test of piping 9) Removing of temp. supports 10) Tank all accessories and mounting installation 11) Gland drain 12) Cooling water line, M/U line to deareator, balancing and leak off line with supports 13) Deareator inside welding 14) Springs and hangers supports and cold setting 15) Vent, drain, C & I tappings 16) MOVS, v/vs installation 17) Dp switch tapping

c) Electrical 1) MOVS supply and termination 2) MOV setting and trail

d) Control & instrumentation 1) Completion / installation of tappings for PG/PT/LT/FS/DP switch 2) Installation of all gauges as per P & ID 3) Setting and calibration 4) Trial from DCS 5) Control cable laying and termination

Boiler light up
1) Water system readiness 2) Compressed air system 3) Fuel firing system readiness 4) Boiler punch list completion 5) Feed water system readiness 6) Aux. cooling water system readiness 7) DCS readiness 8) Control room readiness 9) Chimney readiness 10) Electrical system readiness 11) Chemical lab readiness

SWAS Panel
a) Mechanical 1) Placing of SWAS panel at diff. locations and grouting 2) Completion of cooling water i/t / o/t piping and connection to wet panel

3) Sample tapping from various location is done 4) Drain line connection from sample cooler panel is complete 5) Blow down from SWAS panel is complete

b) Electrical 1) Power supply is available to wet & dry panel

c) Control & instrumentation 1) Impulse tubing upto i/t of all wet panel is completed

Condenser
a) Civil 1) Construction of CEP pit, provision for sump for dewatering pump, Opening for suction and discharge line. 2) Hydro field test 3) Flooring /housekeeping of CEP pit 4) CEP pumps foundation and grouting after motor pump alignment 5) Riggers for CEP pit. 6) Insert plate for piping supports 7) Foundations for CEP, Ejector, GSC, LPH and HPH, CST tank, Surface condenser 8) Opening at various floor for condensate and return condensate piping 9) Columns and beams for ejector and insert plates on pillers 10) Approach for ejector 11) Debris removal 12) Flash Tank foundation 13) Housekeeping

b) Mechanical 1) CEP pumps and Motors placement alignments and coupling. 2) Completion of all piping from to CEP 3) Dewatering pumps installation and its piping 4) Completion of all condensate and return condensate piping from CEP to Deareator with drain vents, MOVs, flow orifice, instrument fittings 5) Hydro test of pipe lines 6) Air line Erection 7) Proper gaskets and packing 8) Connection of turbine exhaust with condenser 9) Alignment and parrellity 10) Surface condenser placement and alignment 11) Completion of all piping from and to condenser, tube expansion, leak test from both sides, inside cleaning 12) Installation of all mountings and accessories 13) Sliding support, approach to vacuum breaker C) Control and instrumentation 1) Installation of all gauges as per P & ID 2) Setting and calibration 3) Trial from DCS of MOV and Valves 4) Completion / installation of tapings for PG/ PT/ LT/ FS/ DP switch 5) Control cable laying and termination 6) Cabling from DCS to MCC

STG
a) Civil 1) Turbine and generator deck preparation 2) Gap between deck and Floor to be clear 3) Pedastal support for MS piping

4) Insert plate for supports 5) Opening for MS line 6) Flooring and Plastering of Turbine House 7) Roofing of turbine house 8) Readiness of loading/unloading bay 9) Pedestal support for extension lines 10) Insert plate Ext. Line supports 11) Turbine hall side walls readiness 12) Foundation for AOP, GOP, lub oil skid, oil purifier 13) Grouting of above 14) Opening for lub oil piping 15) Overhead foundation b) Mechanical 1) Completion of Msp with all supports as per drawing 2) RD/SR and hydro test of MS 1 3) Erection of warm up line / dump line, turbine drains as per drawing 4) Lub oil flushing 5) Removal of mess and dummy from lub oil piping 6) Roofing of turbine halls 7) MS1 insulation and cladding 8) Turbine alignments and grouting, coupling 9) Line alignment and parralletity 10) Springs supports cold settings 11) Floor nuzzle Fixing 12) Steam blowing arrangement with supports as per drawing 13) Over head tank placement completion of all lub oil piping as per drawing 14) AOP/GOP/COP/Oil purifier pumps placement and alignment 15) Cooling water line to coolers

c) Electrical 1) STG MCC readiness 2) Cabling from MCC to all equipments 3) Direction checking and no load trial

4) Power supply availability 5) Motor earthling/ megger 6) Relay setting 7) Area illumination 8) Proper routing of cables 9) MCC panels erection and charging 10) Bus duct completion with supports 11) N grand lapt panels erection and trial 12) Generator phase sequence checking/ back charging D) Control and Instrumentation 1) Installation of all gauges, switch , transmitter as per p & id 2) Setting and calibration 3) Trial from DCS 4) Completion/ Installation of tappings for PG/ PT/ LT/ FS 5) Vibration probes settings and trial run 6) Cabling from MCC to DCS of all equipments 7) Solenoid valves/ JB/DB placement 8) Cabling from JB to equipment and JB to DCS