MINISTRY OF PUBLIC WORKS ARCHITECTURAL DEPARTMENT PROJECT INFORMATION. A. ADMINISTRATION OF CONTRACT. Client: Project: Client Representative: W.P.

Item No. : Project Manager: Main Contractor: SUB-CONTRACTORS: (i) Electrical: (ii) Mechanical: B. CONTRACT DETAILS. Mobilization Period: Site possession date: Commencement date: Contract period: Intended completion date: Extension of time: Revised completion date: C. COST. 48,766,941.00 22,023,638.82 Nil Nil 45.16% 22,023,638.82 1 Week 16th May, 2011 23th May, 2011 36 Weeks 27th January, 2012 Nil Nil County Works Officer - KILIFI Dantax Enterprises Limited Tudor Engineering ltd Anthopi Mechanical Engineering ltd PWANI UNIVERSITY COLLEGE
PROPOSED CONSTRUCTION OF LECTURE THEATRES AT PWANI UNIVERSITY COLLEGE.

The Principal

Contract Sum Total Amount certified to Date Advance payment Advance payment recovered % fund Expenditure Total Amount paid to Date D. PROGRESS. Contract Period Period Elapsed % of time Elapsed % of work Done

36 Weeks 17 Weeks 47.2% 60%


SM/1

Lecture Theatre -Site meeting No.1

DISTRIBUTION The Principal, Pwani University College Kilifi. Chief Architect Chief Quantity Surveyor Chief Structural Engineer Chief Elect./Mech. Eng. All present. MINUTES OF SITE MEETING NO.01 HELD ON 29th September ,2011 IN THE PWANI UNIVERSITY COLLEGE BOARD OFFICE. Chairman: PRESENT. County Works officer

MOPW, Nairobi

NAMES
1. Arch. Allan Nyaga 2. Q.S. Alex K.Mwita 3.John Mwaura 4.Thomas Mwangudza 5. Prof. M.S. Rajab 6. Abdulrahman Mwinyifaki 7. Charles Nakulo 8. Paul Kiraka 9. Rimba Tunje 10. Timothy Kimotho 11.Jane Wanja

DESIGNATION
County Works officer County Quantity Surveyor Clerk of Works Snr. Insp. Electrical MOPW Principal - Pwani University College Registrar-Pwani University College Head of Procurement - Pwani University College

CELL PHONE
0722-369494 0724-628628 0722-904048 0712-500073 0733-730301 0721-312513 0721-312658 0722-172727

Anthopi Mechanical Engineering ltd


Tudor Engineering ltd Main Contractor- Dantax Ent. Main Contractor- Dantax Ent.

0722-713721

AGENDA. 1. 2. 3. 4. 5. Preamble Site inspection. Reports. A.O.B Next site meeting

Lecture Theatre -Site meeting No.1

SM/2

Lecture Theatre -Site meeting No.1

SM/3

ITEM 01.01.00

DESCRIPTION Preamble.

ACTION

1 Meeting started at 11.50 Am noon with a word of prayer. 01.02.00 Site Inspection. 1 Earlier before sitting for the meeting a site Inspection was conducted. The following was noted from the site Inspection:i. All substructure works ii. R.C Superstructure works iii. Walling iv. Plasterwork to Internally v. Plaster to Roof vii.Door Frames viii. Mechanical Plumbing Works viii. Electrical Works 01.03.00 Project Manager's Report 1 Reported that project started on 23th May ,2011 2 Reported that contract period elapsed was 17 weeks out of the 36weeks of the contract period. Encourage the M.C to utilize full force towards the completion of the project. Reported that financial appraisals of the project will be done by the project Quantity Surveyor M.C - 100 % - 90 % - 100 % - 60% - 80% - 50% - 30 % - 30 %

P.Q.S

5 Reported the total amount paid was Kshs. 22,023,638.82 6 Reported that financial appraisals of the project will be done by the project Q.S. P.Q.S

Reported that the M.C should ensure that finishes are accurate and 7 plumbness. 8 Reported that the M.C has yet to submit the concrete test certificates.

M.C M.C

9 Instructed the M.C to fully cordinate with the sub-contractors 10 Matters on site i) Repositioning of staircase from the front area to adjoining toilet wing ii) Additional backfilling materials due to difference in level i.e 2.7 metres to 1.30metres
Lecture Theatre -Site meeting No.1

M.C

SM/4

ITEM

DESCRIPTION iii) Tank Area - Additional structural instruction and details iv) Changes of Toilet cistern flush system and plumbing system v) Introduced additional reinforced beam to the roof structure due building height and wind loads. Reported that the M.C to provide a revised program of works for the project. Project Quantity Surveyor Report 1 Promised to study and co-operate with the M.C on all matters relating the project.

ACTION P.Q.S

11

MC

01.04.00

P.Q.S P.Q.S

2 Promised to prepare financial appraisal. 01.05.00 1 Clerk of Works Report Reported that the M.C to deploy a competitive supervisor/foreman on site at all time. Reported that the concrete cubes test for all concrete works were as taken.

M.C

3 Noted good co-operation between the M.C and the sub-contractors.

01.06.00

Client 1 Encouraged M.C to finish the project as soon as possible. M.C

2 Urged the M.C to kindly oversee all the works. 3 Reminded the M.C to submit concrete cube test certificates. 4 Reported that workmanship on finishes need to be improved. 5 Welcomed the new Quantity Surveyor and encouraged him to assist the institution.

M.C M.C M.C P.Q.S

6 Reported that all payment certificate have been honoured. 7 Commended the M.C for good progress. 8 Pleaded with the M.C to finalize with the ground floor classrooms due to the current pressure. M.C

Lecture Theatre -Site meeting No.1

SM/5

ITEM 01.07.00

DESCRIPTION Main Contractor 1 Accepted and promised to address all issues raised. 2 Promised to complete the project in 2 months time. 3 Thanked client and P.M for support and co-operation. 4 Promised to improve on workmanship.

ACTION

MC

01.08.00

A.O.B 1 There being no other business the meeting ended at 12.55 PM Next Meeting

01.13.00

1 The date of the next site meeting was to be set later.

Minute Compiled by:

Arch. A.N. Nyaga COUNTY WORKS OFFICER Date : ........................................

Minute Proposed by: Sign : Name :

Date... Minute Confirmed by: Sign :

Name :

Date...
Lecture Theatre -Site meeting No.1 SM/6

PROPOSED CONSTRUCTION OF BOUNDARY WALL (Overall Length 620Metres) AT PWANI UNIVERSITY COLLEGE.
SITE MEETING NO.1

DATE:

29TH ,SEPT. 2011


TIME:

ATTENDANCE
NAME

DESIGNATION

SIGN

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15