You are on page 1of 19

Strengthening Nuclear Safety in Canada:

Regulatory Perspective Post Fukushima


Ramzi Jammal
Executive Vice-President and Chief Regulatory Operations Officer Canadian Nuclear Safety Commission IAEA International Experts Meeting March 20, 2012

Canadian Nuclear Safety Commission

Regulates the use of nuclear energy and materials to protect the health, safety and security of Canadians and the environment; and to implement Canadas international commitments on the peaceful use of nuclear energy.

65 years of nuclear safety!

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 2

Fukushima: CNSC Regulatory Actions


On March 17, 2011, the CNSC issued an order to all Canadian Class I nuclear facilities licensees to:
Review initial lessons learned and re-examine safety cases

CNSC Task Force convened to evaluate operational, technical and regulatory implications: Canadian Stress Test
Short-term actions to confirm readiness of installed equipment Long-term measures to update safety case of nuclear power plants (NPPs)

CNSC carried out focused inspections at all nuclear power plants on: seismic qualification, fire, flooding, backup power and hydrogen igniters and passive recombiners CNSC staff updates to Commission members through public commission meetings On August 5, 2011, External Advisory Committee established
Independent review of CNSC actions in response to the Fukushima event Independent reporting to the President of the CNSC
IEM Vienna 2012.03.20 - 3

Canadian Nuclear Safety Commission

IRRS Follow-up Mission

The 2011 Integrated Regulatory Review Service (IRRS) mission Follow-up to the 2009 report CNSCs actions after Fukushima were prompt, robust and comprehensive IRRS Report and Management Response are publicly available on the CNSC Web site http://www.nuclearsafety.gc.ca/eng/about/international/irrt/

Strong support of Canadas nuclear regulatory framework


Canadian Nuclear Safety Commission IEM Vienna 2012.03.20 - 4

CNSC Safety Review Criteria

Considered all available international reports on lessons learned Structured along the lines of defence in depth: Station design for external hazards - Confirmation of design basis - Protection against external hazard of lower frequency and higher magnitude than assumed in design basis Impact of beyond design basis events (BDBEs) - Availability of emergency water and power systems - Hydrogen mitigation - Irradiated fuel bay (IFB) cooling Severe accident management measures Emergency preparedness and response CNSC regulatory framework and processes

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 5

CNSC Task Force Conclusions and Recommendations

Conclusion:
Canadian NPPs are safe and the risk posed to the health and safety of Canadians or to the environment is small

Task Force made 13 recommendations subdivided into 3 main categories:


Strengthening defence-in-depth of Canadian NPPs to withstand events of very low probability Enhancing emergency preparedness/response in Canada Improving CNSC regulatory framework and processes

Intended to further enhance the safety of NPPs in Canada and will reduce associated risk to as low as reasonably practicable

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 6

CNSC Task Force Recommendations Strengthen Defence in Depth

Containment filtered venting at Point Lepreau

Seismic route to SCA

Emergency power generator

PARS

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 7

CNSC Task Force Recommendations

Enhance offsite emergency preparedness/ response:


Ensure emergency response organizations will be capable of responding effectively in a severe event and/or multi-unit accident(s) Conduct sufficiently challenging emergency exercises Review federal and provincial multi-jurisdictions nuclear emergency plans and programs

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 8

CNSC Action Plan - Public and Stakeholder Input

Two rounds of consultation with the public and stakeholders on the:


Task Force Report Action plan arising from the Task Force (TF) Report CNSC Fukushima Task Force Report and Management Response Draft CNSC staff action plan and disposition of comments on the TF Report Disposition of comments and revision of the draft CNSC Staff Action Plan Licensees notified of site-specific Fukushima action items (FAIs) Posting of Commission Member Document for public comment on the CNSC Staff Action Plan and disposition report of comments Commission public meeting on the revised CNSC Staff Action Plan
IEM Vienna 2012.03.20 - 9

October 28, 2011 December 1, 2011 (completed) December 21, 2011 February 03, 2012 (completed) February 03, 2012 March 03, 2012 (completed) February 17, 2012 March 02, 2012 April 03, 2012 (completed)

May 03, 2012

Canadian Nuclear Safety Commission

Implementation of Task Force Recommendations

Site-specific actions will be implemented:


Short term: 12 months started, to be completed by December 2012 Medium term: 24 months by December 2013 Long term: 48 months by December 2015 Implementation by NPPs has commenced for all actions

Fukushima action items (FAIs):


Generic elements Site-specific items

Tracking of implementation will be monitored by staff Once the action plan is endorsed by the Commission:
CNSC staff will report annually to the Commission on the status of implementation

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 10

Canadian Industry Response

Responded with diligence


Identified lessons learned, performed reviews to identify gaps and opportunities for improvement, made progress One Canadian operator (OPG/Pickering) awarded a strength by WANO for the response All licensees responded by April 1, 2011, on short term actions All licensees submitted comprehensive assessments to the CNSC in July 2011

Strong cooperation domestically and internationally

Timely response to CNSC orders


Assessments structured along the lines of defence-in-depth, as per CNSC safety review criteria:
Station design for external hazards Impacts of beyond design basis events (BDBEs) Severe accident management measures for BDBEs including severe accidents (SAs) Emergency planning and response
IEM Vienna 2012.03.20 - 11

Canadian Nuclear Safety Commission

Canadian Industry Response

Assessments confirmed safety of NPPs


Identified opportunities to further improve defences for beyond design basis events Physical improvements to NPPs have commenced Focus of improvements is on severe accident prevention, in addition to severe accident mitigation and emergency response

Augmented flood protection

Emergency mitigation equipment for alternate cooling to stand-by generators IEM Vienna 2012.03.20 - 12

Canadian Nuclear Safety Commission

What We Have Learned

Nuclear events are no longer considered a local event A global event affecting regulators, operators and all levels of government Global safety is a must: starting with the IAEA

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 13

The Path Forward

IAEA:
Commendation to the IAEA on the progress to date and its action plan Time to review the role of the IAEA When was the last time BoG discussed safety issues such as IRRS findings?

Real, transparent peer reviews


Consistent and transparent stress tests with objective and technology neutral approach to lessons learned No commercial competition on basis of nuclear safety

Safety standards to include governance and independence of regulator Reporting of non-responsive regulator to highest levels nationally and internationally, similarly to non-proliferation and security Recognition of important role of INPO and WANO, especially in exposing non-responding operators and regulators
Canadian Nuclear Safety Commission IEM Vienna 2012.03.20 - 14

The Path Forward

Public trust
Regaining of public trust in safety through communication, openness and transparency

Challenges facing the international regulatory community in the recovery phase


Occupational dose limits are not adequate for recovery - rehabilitation Need to develop international/national regulatory limits for recovery phase IAEA, ICRP

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 15

The Path Forward

Redefining design basis - design extension conditions


Guidance on Requirement 20 in IAEA SSR-2/1
Additional scenarios to be addressed Severe accident phenomena to be addressed in containment designs

As part of the life extension in Canada, all licensees have to meet modern safety goals
Complementary design features for selected beyond design basis and severe accidents Containment filtered venting (already installed at Point Lepreau), PARS for hydrogen mitigation, multiple connection points for coolant addition

PARS

Canadian Nuclear Safety Commission

IEM Vienna 2012.03.20 - 16

Conclusions

CNSCs response to events in Japan


Timely, transparent and comprehensive Identified by the Integrated Regulatory Review Service (IRRS) mission as a good practice that should be used by other regulatory bodies

Canadian industry response


Timely response to CNSC directive
All licensees responded by April 1, 2011, on short term actions

One Canadian operator (OPG) awarded a strength by WANO for the response Several key actions in the CNSC Action Plan are already complete

Canadas nuclear power plants are safe


Canadian Nuclear Safety Commission IEM Vienna 2012.03.20 - 17

Conclusions

Role of the IAEA


Mandatory safety standards Design extension conditions More explicit extension of the design basis with inclusion of selected beyond design basis and severe accidents in the design Enhancement to IRRS modules pertaining to the extension of the design basis Safety reporting to the BoG

Role of nuclear industry in continuation of safety


Sharing industry trends with external organizations

Public trust
Canadian Nuclear Safety Commission IEM Vienna 2012.03.20 - 18

We Will Never Compromise Safety

Thank You
nuclearsafety.gc.ca

You might also like