Implementing Best Practice Planning & Programming

May 2003

T004 Planning Production Output Rates


Notes on Output Rates
GENERAL Outputs are for carrying out major works with clear access and large enough areas to permit ease of material deliveries and rubbish away with no double handling, and sufficient work volumes for continuous employment of plant and labour. For contracts where conditions differ from those stated above, additional time needs to be added into the individual time outputs. Outputs reflect the actual man operative time taken to carry out the works inclusive of material deliveries and rubbish away, if any, but account for the operative time only. Therefore they should not be used for pricing purposes before applying a gang factor. DEMOLITION Exclusions: Removal of asbestos or other contaminants. Production and approval of method statements by Local Authority. Erecting temporary works or hand balling around temporary works. Making good. Comments "Dealing with hard materials" - some buildings take longer due to their individually constructed peculiarities e.g. grillage reinforced concrete/setting aside special listed features/underground bunkers/restrictions to city centre sites to working hours/retaining backgrounds that may collapse due to the age of the building. Removal of floor boarding includes for de-nailing joists. Removal of staircase is for a floor to ceiling height of 2.70 metres in timber. Soft stripping of offices assumes an open plan type of arrangement. EXCAVATE AND FILL Comments Outputs are per excavator/excavation gang. Strip topsoil assumes topsoil for setting aside for re-use. If removed as a bulk dig exercise, outputs would be as per reduce level excavation. Basement excavation assumes a traditional "bottom up" dig. Basement and large dig exercises are significantly dependant upon the volume of soil that can be removed from Site -. eg. County Hall basement (size 140mx40m with access to one long side total 50,000m3 approx 9m deep) peaked at 4,000m3 per week removal from Site in a continual operation. - averaged 2,500m3 week due to wet weather etc. Soil capacity on one lorry load = 10m3/load as dug. Excavation in underpinning by hand shallow - 6 hours/m3; deep - 10hr/m3 DRAINAGE Outputs are per excavator/excavation gang. Trench excavation (page 4 excavate and fill) - outputs are to open trench "continuous" style service trenches with no time allowed to set aside or dispose of soil or to sheet up sides. Manholes and gullies (page 5 drainage) - outputs are for the elements only shown ie manhole rings/bricks etc. and do not include for excavation, jointing in pipes, benchings, channels.

Page 51

Implementing Best Practice Planning & Programming

May 2003

ROADS/EXTERNAL WORKS Sub base - weight of Type 1 fill: 2.2tonnes/m3. Road surfacing/kerbs/paviors - reduce by half -ie double the time for areas to building projects. Fencing/streetlighting/landscaping - reduce by half - ie double the time for areas to building projects. PILING AND GROUND ENGINEERING Piling - outputs are per piling rig. Secant piling outputs exclude time taken for constructing a guide wall - guide wall time same as in Diaphragm Walling. Pile trimming - outputs are per man Vibrocompaction output is per nett treated floor area, based on vibro columns at 2.20m ctrs both ways for stone columns up to 8m deep. FOUNDATIONS/CONCRETE STRUCTURES Formwork outputs are per m2 nett area of formwork per shuttering carpenter Holorib decking/concrete topping - see suspended slabs/formwork Placing concrete by tower crane - outputs dependant on hook time cycle and are per crane/gang STRUCTURAL STEELWORK Outputs include for use of a crane on a crane/gang resource. WALLS AND SCAFFOLDS Outputs for masonry are for quantities per bricklayer trowel. Outputs are for general masonry. Walls incorporating cutting to accommodate different types of bricks/small areas/protruding or recessed panels/contrasting bands/building in white mortar/laying blocks flat on face are excluded. Outputs are for building in stretcher bond (half brick) English bond (I brick). Reduce outputs by 10% for building in dpc/expansion jointing/head structural restraints. Adjust precast lintol outputs for large boot lintols to 0.50 per hour. EXTERNAL CLADDING Stone/cladding restoration outputs are totally dependant on works to be carried out ie stitch new stones or bricks in, resin repair cracks - advice needed from specialists for job in question. Stone cladding outputs are for a gang hour and include for structural fixings. Carpentry carcassing/roof carcassing/carpentry second fix outputs are per Carpenter. Roof trusses are assumed to be in timber. Large trusses (exceeding 6m span) 0.5 per hour. Timber staircases assume per 2.60m-storey height in one single flight. Stud partitioning outputs for gyproc to ceilings assume areas of rooms in a domestic location. Toilet partitioning outputs assume outputs per Carpenter and exclude back panelling (1m per hour)
2

Page 52

Implementing Best Practice Planning & Programming ROOF FINISHES Outputs for roof tiling include for felt and battening and are per tiler. BUILDING FINISHES Outputs for raised access flooring assume large open plan arrangement

May 2003

Demolition
Task / Description Slow 3.2 2.1 1.5 Ave 4.6 3.1 2.5 3.0 2.0 4.0 1.5 1.0 2.0 8.0 Fast 5.0 5.9 -

Strip Out Finishes


Remove & Cart away, Lathe and Plaster Ceilings Remove & Cart away, Plaster to Walls Remove & Cart away, External Render Remove & Cart away, sand & cement Floor Screed Remove & Cart away, grano or reinforced Floor Screed Remove & Cart away, Concrete Paving Remove & Cart away, Brickwork Walls, 1.0 brick thick Remove & Cart away, Brickwork Walls, 0.5 brick thick Remove & Cart away, Floor Boards Remove & Cart away, Staircase

Units per man m2/Mhr m2/Mhr m2/Mhr m2/Mhr m2/Mhr m2/Mhr m2/Mhr m2/Mhr m2/Mhr hrs/no

Soft Strip Rule of Thumb Rates


Office Block 1000m2 Flr Plate 2000m2 Flr Plate 1 1.5 per gang weeks/flr weeks/flr

Hard Demolition Rule of Thumb Rates


Office Block 1000m2 Flr Plate 2000m2 Flr Plate 1.5 1.5 per gang weeks/flr weeks/flr

Removal of Pavings
Concrete Slabs Non reinforced up to 200mm thick (using excavator) Reinforced up to 200mm thick (using excavator) 20.0 5.0 m2/hr 10.0 m2/hr

Page 53

Implementing Best Practice Planning & Programming

May 2003

Excavate & Fill


Task / Description Slow Ave 10 Fast

Strip Top Soil


Excavate & Load Lorry

Units per excavator m3/hr

General Bulk Excavation & Load Lorry


Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.7m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.7m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.7m3 bucket, Hard Ground 18.0 35.0 16.0 30.0 13.0 20.0 m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Large Volume Excavation


Hydraulic Excavator,>2m3 bucket, gravel/clay ground 2500.0 m3/day

Basement Excavation and Load Lorry


Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Clay/Gravel Hydraulic Excavator, 0.7m3 bucket, Clay/Gravel Hydraulic Excavator, >1m3 bucket, Clay/Gravel Bottom Up Excavation By Hand 18.0 16.0 25.0 35.0 6.0 m3/hr m3/hr m3/hr m3/hr m2/hr overall 5,000 m3/Week 7,500 m3/Week per excavator m3/hr m3/hr

Excavate & Remove From Site


Central London (Large Project) London Perimeter (Large Project) 4000.0 5000.0

Excavate Foundations
Hydraulic Excavator, 0.5m3 bucket, Pits Hydraulic Excavator, 0.5m3 bucket, Trenches 5.0 6.0

Soil Bulking Factors & Densities


Excavation Bulking Factor, Sand/Soil Excavation Bulking Factor, Gravel Excavation Bulking Factor, Clay/Chalk Excavation Bulking Factor, Boulder Clay Excavation Bulking Factor, Rock Spoil Weight, Rock Spoil Weight, Concrete Spoil Weight, Landfill/CDG Spoil Weight, Sand Spoil Weight, Clay 15.0 33.0 40.0 45.0 60.0 2.5 2.4 1.9 1.8 2.0 % % % % % Te/m3 Te/m3 Te/m3 Te/m3 Te/m3

Page 54

Implementing Best Practice Planning & Programming

May 2003

Task / Description

Slow

Ave

Fast

Units

Breaking Out (By Machine) Concrete


Concrete Slabs, unreinforced 50-150mm Concrete Slabs, unreinforced 150-300mm Concrete Slabs, reinforced 50-150mm Concrete Slabs, reinforced 150-300mm Concrete Walls, reinforced Concrete Foundations, unreinforced Concrete Foundations, reinforced Concrete Beams Concrete Columns Grillage Reinforced Foundation 30.0 20.0 10.0 8.0 8.0 1.5 2.0 2.8 3.0 6.0 per excavator m2/hr m2/hr m2/hr m2/hr m2/hr hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3

Tarmac
Tarmac paving 50-100mm thick Tarmac roadway 150mm thick 0.3 0.4 hrs/m3 hrs/m3

Concrete Crushing On-Site


Concrete down to a General Hardcore Concrete down to Type 1 800.0 500.0 1000 Te/Day 600 Te/day

Breaking Out (By Hand) Concrete


Concrete Slabs, unreinforced 50-150mm Concrete Slabs, unreinforced 150-300mm Concrete Slabs, reinforced 50-150mm Concrete Slabs, reinforced 150-300mm Concrete Walls, reinforced Concrete Foundations, unreinforced Concrete Foundations, reinforced Concrete Beams Concrete Columns Grillage Reinforced Foundation 5.5 6.5 6.5 8.0 8.0 6.0 9.0 8.0 8.0 10.0 per man hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3

Tarmac
Tarmac paving 50-100mm thick Tarmac roadway 150mm thick 3.0 3.5 hrs/m3 hrs/m3

Brickwork
Brickwork, walls and columns Brickwork, foundations 3.0 3.5 hrs/m3 hrs/m3

Dewatering System
Setup large 15 hole system 21.0 days

Page 55

Implementing Best Practice Planning & Programming

May 2003

Task / Description

Slow 5.0

Ave 6.0

Fast

Units

Spread & Level Fill


Hardcore Layers 100-150mm Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore

per excavator 10.0 m3/hr

13.9 11.6 23.8 19.6 47.6

20.4 16.9 28.5 24.5 51.6

25.0 m3/hr 21.3 m3/hr 35.7 m3/hr 30.3 m3/hr 55.6 m3/hr

Trench Excavation
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide 18.2 26.3 3.0 6.2 22.2 28.6 4.2 6.7 26.0 m3/hr 33.2 m3/hr 6.5 m2/hr 9.2 m2/hr

Page 56

Implementing Best Practice Planning & Programming

May 2003

Drainage
Task / Description Slow Ave Fast Units per gang m/day m/day m/day m/day

Excavate Drain Trenches


Small-Medium Sized Projects Up to 2m deep for Pipes up to 225mm Up to 4m deep for Pipes up to 225mm Up to 2m deep for Pipes up to 450mm Up to 4m deep for Pipes up to 450mm Large Road Projects 250-450mm pipes 20 10 6 3

35

m/day

Drain Laying
Small-Medium Sized Projects Lay Small Diameter Pipes up to 150mm Lay Large Diameter Pipes up to 225mm Lay large Diameter Pipes up to 450mm Large Road Projects 250-450mm pipes 30 20 8 per gang m/day m/day m/day

70

m/day

Connecting Drainage
PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run Hepsleve Rubber Joint System, over 375mm dia, 5-30m run 10.6 2.3 -

per gang m/hr m/hr

Land Drains
Concrete, butt jointed, under 150mm dia, 5-30m run Concrete, butt jointed, under 150mm dia, over 30m run Concrete, butt jointed, 150-225mm dia, 5-30m run Concrete, butt jointed, 150-225mm dia, over 30m run 6.0 10.0 4.0 6.0 14.0 19.0 10.0 12.0 m/hr m/hr m/hr m/hr

Manholes & Gullies


Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm Brickwork Manhole, 1.0 brick engineering Brickwork Manhole, 1.5 brick engineering Benching to Manhole, under 0.5m2 Benching to Manhole, 0.5-0.75m2 Brickwork Manhole, build in pipes, under 150mm dia Brickwork Manhole, build in pipes, 150-225mm dia Brickwork Manhole, build in cast iron covers Yard Gulleys, 75-150mm dia pipes, bed and level Yard Gulleys, 150-225mm dia pipes, bed and level Road Gulleys, 600mm deep, bed and level Road Gulleys, 750mm deep, bed and level Road Gulleys, 1,200mm deep, bed and level Road Gulleys, install gratings 1.2 1.6 0.3 0.2 0.9 1.2 0.1 0.2 0.6 2.2 1.8 1.2 0.8 0.3 5.0 hrs/no hrs/no m2/hr m2/hr hrs/no hrs/no hrs/no hrs/no hrs/no no/hr no/hr no/hr no/hr no/hr no/hr

Page 57

Implementing Best Practice Planning & Programming

May 2003

Roads & External Works


Task / Description Slow Ave Fast Units

Sub Base
Large Road Job Spread & level Granular Material Trim Fill gang day 1200 T/day 1500 m2/day per gang m2/hr m2/hr m2/hr per gang

Concrete Road Surfacing


Concrete Road surfacing, 150mm thick Concrete Road surfacing, 200mm thick Concrete Road surfacing, 300mm thick 12.5 7.7 6.7 -

Tarmac Road Surfacing

Barbour Greene Large Sized Project Road Base Winter Working Summer Working Wearing Course

300 700

1200 m2/day 2500 m2/day 500 Te/day 12,000 m2/day

Barbour Greene Medium Sized Project Tarmacadam Asphalt Manual Laying Tarmacadam Asphalt Road Markings

160 145

m2/hr m2/hr

8.0 5.0 180

m2/hr m2/hr 500 m/day per man m/hr m/hr m/hr m/hr m/hr m/hr m/hr

Kerbs & Haunching


Concrete Kerbs or Channels, laid straight Concrete Kerbs or Channels, laid to 5m radius Concrete Kerbs or Channels, laid to 10m radius Stone/Granite Kerbs or Channels, laid straight Concrete Edging, laid straight Concrete Edging, laid to 5m radius Concrete Edging, laid to 10m radius 4.0 2.5 3.0 2.5 6.0 4.0 4.5 -

Page 58

Implementing Best Practice Planning & Programming

May 2003

Task / Description

Slow

Ave 2.0 1.5 2.0 0.3 0.2 1.3 1.0 10.5

Fast 4.0 2.3 2.8 1.9 1.2 -

Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Pavings & Paviors


Concrete Slabs, laid on bedding, to slight falls Concrete Slabs, laid in mortar, to falls Concrete Slabs, laid on sand, to falls Cobble Stones, laid in mortar, no patterns Cobble Stones, laid in mortar, with patterns Brick Paviors, in mortar, straight joints Brick Paviors, in mortar, herringbone pattern Gravel Paths, including preparation of sub-base

Fencing

Small/Medium sized Project Fence Erection, Chainlink, posts at 2.0m Post Erection, Timber / Metal, dig, erect, fix Fence Erection, Chestnut Pailings, posts at 2.0m

3.3 -

4.4 4.5 33.3

per gang m/hr no/hr m/hr

Safety Fencing - (Large Road Project) - Driven Posts - Augered Posts

400 m/day 200 m/day

Streetlighting & U/Ground Services


Lay Street Lighting Cables and connect Communications Duct & pit Installation Lighting Columns Commissioning 6 60 3 2 8 m/hr 100 m/day 4 no/day weeks

Landscaping
Top Soil, spread, level and prepare for turf or seeding Top Soil, rake in fertilizer for seeding Planting, Shrubs and Hedges, under 750mm high Planting, Shrubs and Hedges, over 750mm high Planting, Saplings, under 3.0m high 2.5 25.0 4.0 1.5 1.7 m2/hr m2/hr no/hr no/hr no/hr

Page 59

Implementing Best Practice Planning & Programming

May 2003

Piling & Grnd Eng.


Task / Description Slow 6.0 5.0 Ave 8.0 7.0 15.0 7.0 3.0 1.5 9.0 4.0 7.0 8 Fast Unit/rig

Bored Concrete Piling


CFA Piling <15m Long CFA Piling 15 - 25m Long Short augered piles <6m long <750mm dia Rotary Bored Piling < 750mm Dia Rotary Bored Piling 750 - 1200mm Dia Rotary Bored Piling 1200 - 2000mm Dia Contiguous Pile Wall 15-20m long Secant Wall Piling 15-20m long Hard/Hard Secant Wall Piling 15-20m long Hard/soft Tripod Piling

per rig 10.0 no/day 8.0 no/day no/day 9.0 no/day 4.0 no/day 2.0 no/day 10.0 no/day 5.0 no/day 8.0 no/day m/day

6.0 2.0 1.0 8.0 2.0 6.0

Precast & Steel Piling


West Piling, pre-cast concrete shells Balken Piling, pre-cast concrete piles H Piles, driven steel H-beams 75.0 80.0 200.0 100.0 120.0 350.0 120.0 m/day 135.0 m/day 500.0 m/day

Precast Concrete Piling


West Piling, pre-cast concrete shells Balken Piling, pre-cast concrete piles 75.0 80.0 100.0 120.0 120.0 m/day 135.0 m/day

Steel Sheet Piling


Vibro/Drop Hammer, 10m deep Sand Vibro/Drop Hammer, 35m deep Sand 3.5 55.0 32.0 60.0 m/day 10.5 m/day

King Post Temporary Wall


Posts at 3m Centres 58 m2/wk

Mini Piling
Mini Piles, driven 235mm dia, 35m deep 2.5 3 m/hr per man m/hr m/hr m/hr hrs/no hrs hrs hrs

Hand Dug Piling


Excave shaft by grab, general fill/uppr levels Excave shaft by grab, sand/minor rubble Excave shaft by grab, marinve/aluvium Install reinforcement cages Shaft cleaning, air lifting after excavation Shaft cleaning, air lifting after cage installed Shaft concreting/extract casing 5-70m deep 3.5 2.1 2.5 2.0 8.0 2.0 12.0 -

Page 60

Implementing Best Practice Planning & Programming

May 2003

Task / Description

Slow

Ave 2.0 5.0

Fast

Unit/rig hrs/no hrs/no

Cut Down Piles


Concrete Piles, 300-750mm deep and 0.6m dia Concrete Piles 300-750mm deep and 1.1m dia

Diaphram Walls
Guide Walls, construction Construct Diaphram Wall - retained face 0.3 0.5 70.0 0.8 m/Mhr m2/rigday

Ground Anchors
Drill 30m shaft Install strands/setup anchor Grout in strands 7.0 6.0 2.0 hrs hrs hrs

Soil Nailing
-

Ground Improvement
Vibrocompaction (8m long 2.2m ctrs) Dynamic Compaction 1000 m2/rig/wk m2/rig/wk

Sundry Activities
Grout curtain installation Dig Caisson 800mm dia, 26m deep 55.0 6.2 33.0 - hrs/m run 25.0 days/no

Site Investigation
Pre Drilling, Rercussive or Rotary, soft deposits Pre Drilling, Wash Boring, grade V/IV rock Pre Drilling, Triple Tube Sampling, grade V/IV rock Pre Drilling, Rotary, grade III/II rock 8.0 2.5 0.4 0.2 10.0 3.2 0.8 0.5 14.0 3.9 0.9 0.7 m/hr m/hr m/hr m/hr

Page 61

Implementing Best Practice Planning & Programming

May 2003

Tunnelling
Task / Description Slow 0.4 0.5 Ave 0.6 0.7 Fast Units

Conventional Tunneling
Excavate vertical access shaft, 6m diameter Excavate vertical access shaft, 10m diameter 0.8 m/day 0.9 m/day

Cut & Cover


Formwork Tunnel Forms, Wall and Slab poured as one 15.6 17.5 m2/hr

NATM
Excavation, London Clay, internal diameter under 7.0m Excavation, London Clay, internal diameter 7.0-10.0m Excavation, London Clay, internal diameter over 10.0m Excavation, Woolwich/Reading Beds, internal diameter 2.07.0m Excavation, Woolwich/Reading Beds, internal diameter 7.010.0m Excavation, Woolwich/Reading Beds, internal diameter over 10.0m Mucking Capacity, 1 access with 2 crews Mucking Capacity, 1 access with 4 crews Mucking Capacity, 2 access with 4 crews Sprayed Secondary Lining, Tunnels, diameter under 6.5m Sprayed Secondary Lining, Tunnels, diameter over 6.5m Sprayed Secondary Lining, Vertical Shafts, diameter over 6.5m Sprayed Secondary Lining, Tunnel Junctions Insitu Permanent Lining, 12m bays, 350-400mm reinforced with PCV backing Excavate and Line Cycle Time , Running Tunnels Excavate and Line Cycle Time, Station Access Adits Excavate and Line Cycle Time, Concourse Tunnels Excavate and Line Cycle Time, Escalator Tunnels 2.5 1.5 1.0 1.5 190.0 255.0 382.0 2.1 1.5 2.2 3.2 3.3 2.2 1.2 2.9 2.0 1.3 1.8 1.5 1.0 225.0 300.0 450.0 2.5 2.0 2.5 0.2 3 4.0 3.9 2.5 1.5 3.2 m/day 2.5 m/day 1.5 m/day 2.0 m/day m/day

1.5 m/day 279.0 366.0 549.0 2.8 2.4 m3/day m3/day m3/day m/day m/day

3.1 m/day 0.3 m/day 4 4.9 4.2 2.7 1.7 m/day m/day m/day m/day m/day

Rock Tunnelling
Excavation, non explosive chemical method, cycle time Excavation, non explosive chemical method, Class I Granite Excavation, non explosive chemical method, Class II Granite Excavation, non explosive chemical method, Class III Granite 8.0 0.3 2.0 1.2 6.0 0.9 2.6 1.4 5.5 mins 1.2 m3/cycle 2.9 m3/cycle 1.8 m3/cycle

Page 62

Implementing Best Practice Planning & Programming

May 2003

Foundations
Task / Description Slow Ave 0.7 1.0 1.3 0.8 1 1.2 Fast Unit/man per man m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Formwork
Pilecaps, small Pilecaps, medium-large Pilecaps, large Ground Beams, < 0.7m2 Ground Beams, 0.7-1.5m2 Ground Beams, 3.0-5.0m2

Reinforcement
40mm 32mm 20mm 16mm 8 10 14 12 9 12 18 15 12 14 20 20 hrs/tonne hrs/tonne hrs/tonne hrs/tonne

Concrete Placing
large Sized Pours (pump) Medium Sized Pours (direct discharge) Small Pours (Backactor) 20.0 8.0 3.0 40.0 m3/hr 12.0 m3/hr 4.0 m3/hr

Underpinning
Concrete Pinning, every 4th/5th pin cycle Brickwork Pinning, 1.0 brick thick Brickwork Pinning, 1.5 brick thick Brickwork Pinning, 2.0 brick thick Wedge and Pin Method, 102mm wall Wedge and Pin Method, 215mm wall Wedge and Pin Method, 317mm wall 0.1 1.2 0.4 0.3 0.2 0.8 0.7 0.5 2.2 m/day 0.7 m2/hr m2/hr m2/hr m/hr m/hr m/hr

Trench Support
Open Boarding Close Boarding 4 3 m2/hr m2/hr

Page 63

Implementing Best Practice Planning & Programming

May 2003

Concrete Structures
Task / Description Slow Ave Fast Units/man

Formwork
Walls Including Stop-ends etc Walls,1.0-2.0m2 Walls, 2.0-5.0m2 Walls, over 5.0m2 Walls, StoriForm Shutters, 5.0-15.0m2 Walls, StoriForm Shutters, over 15.0m2 Columns Columns, Square Timber csa < 0.1m2 Columns, Square Timber csa 0.1-0.4m2 Slabs & Beams Suspended Plain Slab Soffit Beams, on falsework, width 300-500mm Beams, on falsework, width over 750mm Troughed/Waffle Slabs Table Form, Aluminum System, 400m2 bays Stop Ends, no perforations Stop Ends, minor perforations Stop Ends, dense perforations Box Outs, 0.01-0.05m2 Box Outs, over 0.05m2 Staircases Staircases, Stair Soffit, Sloping Staircases, Stair Soffit, Flat Landing Staircases, Wall Strings 0.8 0.8 0.8 1.0 1.0 per man m2/manhr m2/manhr m2/manhr m2/manhr m2/manhr

0.65 0.65

m2/manhr m2/manhr

1 0.5 0.5 0.65 100 2.5 1.2 0.6 6 3

m2/manhr m2/manhr m2/manhr m2/manhr 150 m2/gangday 3 m2/manhr 1.6 m2/manhr 0.9 m2/manhr 8 no/manhr 5 no/manhr

0.6 0.8 0.4

0.8 m2/manhr 1 m2/manhr - m2/manhr

Page 64

Implementing Best Practice Planning & Programming

May 2003

Task / Description

Slow

Ave

Fast

Units/man

Reinforcement
Reinforcement Ratios Pile Cap, Concrete m3 x Ratio = Rebar Tonnes Base Slab, Concrete m3 x Ratio = Rebar Tonnes Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes Columns, Concrete m3 x Ratio = Rebar Tonnes Walls, Concrete m3 x Ratio = Rebar Tonnes General Steelfixing rates Links 10mm 12mm 16mm 20mm 25mm 32mm 40mm 13.0 15.8 14.7 14.8 13.2 18.0 18.7 15.0 14.1 23.0 28.7 % ratio % ratio % ratio % ratio % ratio

30.0 30.0 25.0 20.0 18.0 15.0 12.0 12.0

25.0 20.0 16.0 15.0 13.0 12.0 11.0 9.0

hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne

General Column Construction rate


Formwork, Reinforcement & Concrete (3man gang) 2 6 No/day

Slip Forming
Shaft Slip Forming 300 400 mm/hr

Post Tensioned Concrete


Lag for Initial Stress Tensioning after 1st bay cast Lag for Final Stress Tensioning after Initial Stress 48.0 120.0 hrs hrs

Concrete Placing
Hollorib Decking, concrete topping Hollorib concrete topping, incl PowerFloat Tower Crane & Skip, Slabs over 150mm thick Tower Crane & Skip Beams over 150mm thick Tower Crane & Skip Walls Tower Crane & Skip Columns Tower Crane & Skip Stairs and Landings Pumping To Slabs Pumping To Walls with Tremie Pipe 2000 50.0 4 4 3 2.5 2 20 6 2500 m2/week 70.0 m2/hr 4 5 4 4 4 40 8 m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Page 65

Implementing Best Practice Planning & Programming

May 2003

Task / Description

Slow

Ave 20 30 25

Fast

Units/man

Concrete Finishing
Wood Float By Hand Power Float Wire Brush, expose aggregate 30 m2/hr 40 m2/hr 35 m2/hr

Precast Concrete
Precast Floor Planks Precast Stair units Beams,Columns & Slabs Car Park Precast elements 0.4 0.2 0.5 500 70 0.1 hrs/plank 0.3 hrs/plank 600 m2/week 75 No/Week

Sundry Information
Concrete Weight, 1m3 Readymix Lorry, Length Readymix Lorry, Width Readymix Lorry, Height Readymix Lorry, Turning Circle Readymix Lorry, Allowable Ramp Gradient Lorry Weight 2.4 8.3 2.5 3.7 16.4 17.0 24 20.0 Tonnes m m m m degrees Tonnes

Page 66

Implementing Best Practice Planning & Programming

May 2003

Structural Steelwork
Task / Description Slow Ave 10.0 9.0 4.0 1.6 Fast Units/gang Tons/day Tons/day Tons/day Tons/day

Structural Steel Frames


Heavy Structural Steel Frame Medium Sized Structural Steel Frame Light Steel Frame and Roof Members Wall Frame, Bow String Truss and Frame

Metal Deck Flooring


Hollorib Decking, lay deck Hollorib Decking, shear connecting studs 300 225 350 m2/day 250 m2/day

General Guides
Tonnage of steel in a building Office Building 43 60 54 Kg/m2 Kg/m2

Fire Protection
Sprayed Fire protection Spray Protection to Steelwork Board Fire Protection Intumescent Paint 40 200 150 250 50 tonnes/week - m2/week m2/week m2/week

Page 67

Implementing Best Practice Planning & Programming

May 2003

Walls & Scaffolds


Task / Description Slow Ave 0.75 0.42 0.28 0.2 1.5 1.5 incl 0.3 2.0 1.3 2.7 1.0 0.5 0.35 Fast Units/Mn

Brickwork Fairfaced
Stretcher Bond, 0.5 Brick thick Stretcher Bond, 1 Brick thick Stretcher Bond, 1.5 Brick thick Stretcher Bond, 2 Brick thick Building Brick on Edge Coping Building Brick on Edge Canted Cills Face finish as work proceeds Special Bricks Face Finish after completion, Flush and Rubbed Face Finish after completion, Struck Pointing Face Finish after completion, Bucket Handle Common Bricks 0.5 Brick Common Bricks 1 Brick Common Bricks 1.5 Brick

per man m2/hr m2/hr m2/hr m2/hr - m/hr - m/hr

m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Blockwork
Lightweight Concrete Blockwork, under 100mm thick Lightweight Concrete Blockwork, under 100-150mm thick Lightweight Concrete Blockwork, over 150mm thick Dense Concrete Blockwork, under 100mm thick Dense Concrete Blockwork, under 100-150mm thick Dense Concrete Blockwork, over 150mm thick 1.50 1.30 1.00 1.25 1.00 0.65 m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Metal Angle Restraints


Vertical Posts Head Restraints Ext Support Angle 2.0 3.0 2.0 no/hr m/hr m/hr

Sundries
Concrete Lintels Steel lintels 1.0 2.0 no/hr no/hr

Access Scaffolding
Metal KwikStage, 5 Boards with 2m lifts Metal KwikStage, 5 Boards with 3m lifts Metal Tube and Fittings, 5-6 Boards wide Fix Hop-ups Kwickstage Re-position Hop-ups Kwickstage 5.0 4.0 3.5 14.0 20.0 m run/hr m run/hr m run/hr m run/hr m run/hr

Birdcage Scaffolding
Tube and Fitting Platforms, 50-250m3 Tube and Fitting Platforms, 250-1000m3 Tube and Fitting Platforms, over 1000m3 Tube and Fitting Platforms, striking 14.0 16.0 18.0 200.0 m3/hr m3/hr m3/hr % x erect

Page 68

Implementing Best Practice Planning & Programming

May 2003

External Cladding
Task / Description Slow Ave 20.0 15.0 3.0 Fast 30.0 25.0 Units Per gang m2/day m2/day wks/Flr per gang m2/day m2/day m2/day m2/day m2/wk m2/manhr per gang m2/day m2/day m2/day per man m2/day m2/day m2/day

Curtain Walling
Glazed Curtain Wall High Quality Glazed Curtain Walling Rule of Thumb- Multi-Storey Office Block

Windows & Glazing


Vertical Glazed Lights, 6m x 2.5m Vertical Glazed Walls, large scale Clerestory Frame/Glazing, 3m x 4m Oriel Window Frame/Glazing, 4m x 2m Patent Glazing Windows general 15.0 50.0 28.0 35.0 90.0 1.0 -

Metal Cladding
Sub-Frame Installation, 1.5x0.5m panels VE Panel Installation, 1.5x0.5m panels Flat Metal Cladding Panels (eg Kingspan) 12.2 1.0 50 15.0 1.4 70.0 17.5 1.9 80.0

Stone Facade Restoration


Faade Cleaning, Water Jetting Faade Cleaning, Acid Etching Faade Cleaning, Grit Blasting Cladding Restoration, Brickwork Cladding Restoration, Stonework courses 25.0 9.0 12.0 seek specialist advice seek specialist advice

Stone Cladding
Fix 0.5m2 Stones to Metal Support Frame Fix 0.5-0.75m2 Stones to Metal Support Frame Fix 0.75-1.0m2 Stones to Metal Support Frame Fix Curved Stone Cladding Fix Stone Edge Beams/Window Reveals Fix Stone Soffits Stone Floors Granite/Marble Wall Panels Portland Stone Final Wash down 0.3 0.3 0.4 0.2 0.25 0.3 1.0 0.6 300.0 0.3 0.35 0.4 0.3 0.3 0.4 1.5 0.8 350.0

per gang m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/week

Precast Concrete Cladding


Large storey height panels (Largely Dependant on Deliveries) 2.0 3.0 No/day

Profiled Metal Sheet Cladding


Large areas factory bldg 400.0 m2/gangwk

Specialist Ext Wall Finishes


Terracotta Tiles Sto Render (with insulation) 30.0 2.0 m2/gangday m2/hr

Page 69

Implementing Best Practice Planning & Programming

May 2003

Dry Int. Carcassing


Ref Task / Description Windows, Timber Frames for Bricklaying Windows, Drill, Screw & Plug extra over Door Frames, Softwood, 1.0-3.0m2 Door Frames, Softwood, 3.0-7.0m2 Cut Access Hatch Floor Joists, Ceiling Joists Floor Boards, Butt Jointed Floor Boards, T&G Boards Plywood Sheeting, Butt Jointed, screwed Chipboard Sheeting, Butt Jointed, screwed Windows, Softwood, 3.0-7.0m2 Windows, Softwood, 7.0-10.0m2 Fix Metal and Timber Windows After Wall Complete Window Glazing Slow Ave 0.5 0.1 1.8 2.5 0.3 26 30 2.5 3 4 5.1 0.4 0.9 2.0 1.3 Fast 0.1 30 35 3 3.5 5 5.8 0.3 0.6 -

Carpentry Carcassing

Units per man hrs/no hrs/no hrs/no hrs/no no/hr m/hr m/hr m2/hr m2/hr m2/hr m2/hr hrs/no hrs/no m2/hr m2/hr per man no/hr m/hr m/hr m/hr m/hr m/hr m/hr m/hr m/hr m/hr

Roof Carcassing
Roof Trusses Wall Plates Roof Rafters Ceiling Joists Roof Carcass, Common Rafters, 3-6mm Roof Carcass, Common Rafters, over 6m Roof Carcass, Jack Rafters, 3-6mm Roof Carcass, Purlins, 3-6mm Roof Carcass, Purlins, over 6m Roof Soffits, Softwood, screwed 1.3 3.0 1.2 8.0 8.0 6.0 8.0 8.0 6.0 4.0 -

Carpentry 2nd Fix


Window Boards, screwed Mouldings, Softwood, Screwed Mouldings, Hardwood, Screwed Mouldings, Hardwood, Gun Nailed Skirting Architrave Mouldings Architrave, Fix to Doors Door Stop Mouldings Glazed Bead Mouldings Hanging Doors, Softwood, Single Pair Butts Cut Mortice to Receive Lock, Softwood Cut Mortice to Receive Lock, Hardwood 0.3 6.0 4.0 6.0 6.0 6.0 1.0 6.0 6.0 1.5 0.5 0.6

per man hrs/m m/hr m/hr m/hr m/hr m/hr hrs/door m/hr m/hr hrs/no hrs/no hrs/no

Page 70

Implementing Best Practice Planning & Programming

May 2003

Ref

Task / Description General Door & Frame Fixing Rates(per Pair) External Double Leaf Internal Double Leaf Internal Single Leaf Fix Bath Panel Kitchen Cupboards, Floor Units Kitchen Cupboards, Wall Units Kitchen Cupboards, Shelf Units Staircase, pre-made, simple, straight flight Staircase, pre-made, 2 straight flights, 1 landing Staircase, Balustrades/Handrails, fix horizontal Staircase, Balustrades/Handrails, fix raking Timber Panelling Pine Timber Panelling Hardwood

Slow

Ave

Fast

Units per man

Carpentry 2nd Fix


1.5 2 3 0.4 1.0 1.0 1.0 1.5 2.9 0.6 0.5 1 0.5 -

No/day No/day No/day hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no m2/hr m2/hr

Stud Partitioning/Dry Lining


Gyproc Partitions (single layer) Gyproc Partitions (double layer) Gyproc Shaftwall (single layer) Gyproc Shaftwall (double layer) Boarding to Stud-work/Metal Lathes Boarding 19mm nailed to studding Tape, Joint Sand and Top Coat Plasterboard Skimming to Plasterboard Gyproc Dry Lining System - Walls Gyproc Boarding to Ceilings (single layer) Gyproc Boarding to Ceilings (double layer) Acoustic Ceiling Lining Acoustic Wall Lining Steelwork Encasement (single layer) Steelwork Encasement (double layer) 1 0.5 1 0.5 4.0 6.0 1.5 6.1 5 6 3 170 200 2 1 m2/manhr m2/manhr m2/manhr m2/manhr 6.0 m2/manhr 10.0 m2/manhr m2/manhr m2/manhr 7 m2/manhr 10 m2/manhr 5 m2/manhr 250 m2/wk 330 m2/wk m2/manhr m2/manhr

Proprietary Partitions
Fix Toilet Partition System, Separation panels Fix Toilet Partition System, Wall Front Panels Fix Toilet Partition System, End Front Panels Fix Toilet Partition System, Hang Door to Panel 100mm Pine Paneling, excluding studding time General rate for Toilet Cubicle Demountable Partitions (Full Height) 0.8 1.5 1.5 1.5 0.4 1.1 2 1 hrs/no hrs/no hrs/no hrs/no

1.4 m2/hr No/manday m/manhour

Page 71

Implementing Best Practice Planning & Programming

May 2003

Bldg Services
Ref Task / Description Deduct 15% for OH&P Labour Cost on Systems Electrical Mechanical & sprinklers Plumbing Hot Water Ventillation Air Conditioning Slow Ave Fast Units

Rule of Thumb
33 30 33 25 17 9 % % % % % %

Divide amount by anticipated weekly gross labour rate to derive No of man weeks

Plumbing
Cast Iron TimeSaver 100mm Pipes Cast Iron TimeSaver 100mm Branches Cast Iron Spigot Joint Pipes, 100mm 1.2 2.2 1.1 m/hr hrs/no m/hr

Water Mains, 150-200mm dia Water Mains, 1,050mm dia Gas Mains, 200mm dia Gas Mains, 300mm dia

2.1 0.4 1.8 1.2

m/hr m/hr m/hr m/hr

UPVC Downpipes, 75mm UPVC Guttering, 75mm Cast Iron Downpipes, 75mm Cast Iron Guttering, 75mm Cast Iron RWP Fittings, 75mm

3.3 3.1 2.1 2.5 2.2

m/hr m/hr m/hr m/hr no/hr

Page 72

Implementing Best Practice Planning & Programming

May 2003

Bldg Services
Ref Task / Description Slow Ave Fast Units

Mechanical
Major Plant Pumps Pipework Large Dia Pipework Small Dia Insulation Ductwork Grills/Diffusers 30 6 10 20 35 8 3

Per Man - days each - days each - m/day m/day m/day 12 m/day 4 No/day per man days 15 m/day 40 m/day 8 no/day

Electrical
Substation/Switchroom HV Cables LV Cables Light Fittings 40 10 25 6

Structured Cabling Installation in new Building

250

300 No/day

Test & commissioning Radiator & Convector System Simple ventillation System Full Air Conditioning System Hospital/laboratory Systems

4 8 12 16

7 weeks weeks 16 weeks 24 weeks

Page 73

Implementing Best Practice Planning & Programming

May 2003

Roof Finishes
Ref Task / Description Asphalt Roof in layers Felt Roofs, large areas Felt Roofs, small or complicated Asphalt coatings, horizontal surfaces Asphalt coatings, vertical surfaces Bituminous Brushed application, 2 coats Bituminous Brushed application, 3 coats Bituminous Sheets, horizontal surfaces Polythene Sheets, horizontal surfaces Slow 3.5 1.2 4.8 3.3 3.8 Ave 50 35 20 4.2 1.7 5.0 3.5 4.0 20.0 Fast 52 30 5.8 2.2 6.3 4.4 4.8 -

Asphalt & Felt Roofing

Units per gang m2/day m2/day m2/day m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr per gang m2/day m2/day

Roof Screeding
Laid in Medium sized Bays to falls Laid in Large Bays (pumped) 50 100 -

Membrane Roof Sheeting


Trocal Single Ply Membrane 300 400 m2/wk

Metal Decking & Roofing


Metal Decking, large areas Metal Decking, small or complicated Titanium Sheeted Roofs Copper Roofs, flat work Copper Roofs, sloping work Zinc Roofs, flat work Zinc Roofs, sloping work Aluminium Roofs, flat work Aluminium Roofs, sloping work Lead Roofs, flat work Lead Roofs, sloping work Lead Roofs, dormer cheeks Lead Roofs, flat gutters Lead Roofs, flat copings Lead Roofs, stepped gutters Lead Roofs, shaped copings Lead Roofs, cover step flashings Lead Roofs, rooflight flashings Lead Roofs, domed roof coverings Sub-Frame Installation, 1.5x0.5m panels 12.2 70.0 28.0 9.5 3.0 2.7 2.4 2.1 2.8 1.9 2.5 2.1 1.3 88.0 76.0 3.5 3.3 3.2 0.8 0.7 15.0 17.5

per gang m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m/day m/day m/day m/day m/day no/day m2/day m2/day

Insulation
Polystyrene Boards Glass Fibre, low pitch 8.5 12.0 m2/hr m2/hr

Page 74

Implementing Best Practice Planning & Programming

May 2003

Ref

Task / Description Slate Roofs, Welsh Slate 3-5mm Slate Roofs, Cumbrian Slate 8-11mm Slate Roofs, Asbestos Slates Tiled Roofs, Concrete Tiles Tiled Roofs, Clay Pan Tiles

Slow -

Ave 12.0 8.5 24.0 40.0 12.0

Fast 18.0 36.0 52.0 20.0

Units per man m2/day m2/day m2/day m2/day m2/day

Slates & Tiles

Roof Windows & Atrium


Rooflights Velux Type windows Atrium Roof Glazing 1 2 60

per gang - no/day no/day 70 m2/wk per man 2.5 m/hr 3 m/hr

Rainwater Goods
Gutters Downpipes 2 2.5

Page 75

Implementing Best Practice Planning & Programming

May 2003

Wet Bldg Trades


Ref Task / Description Browning (undercoat), Internal Walls under 2.5m high Browning (undercoat), Internal Walls over 2.5m high Covings Skimming (topcoat), Internal Walls under 2.5m high Skimming (topcoat), Internal Walls over 2.5m high General Plastering rate - (2+1 gang) Fibrous Plaster -General Slow Ave 2.8 2.6 4.0 6.7 6.1 150 25 Fast 3.1 2.8 7.3 6.7 200 Units m2/hr m2/hr m/hr m2/hr m2/hr m2/week m2/week

Plastering

Rendering
Large Wall Areas, applied in 2 coats Small Wall Areas, applied in 2 coats Narrow Widths, applied in 2 coats 2.2 1.5 1.2 2.7 m2/hr 1.7 m2/hr 1.4 m2/hr

Floor Screed
Hoist & Barrow (2+1 Gang) Sand/Cement Floor Screed, 20-40mm thick Sand/Cement Floor Screed, 40-65mm thick Sand/Cement Floor Screed, 65-100mm thick Pumped Screed (large areas) (2+1 Gang) 35 30 25 170 50 m2/day 40 m2/day 30 m2/day m2/day

Cutting Chases
Concrete, cutting by hand, 50-75mm wide Concrete, cutting by machine, 25-50mm wide Concrete, cutting by machine, 75-100mm wide Brickwork, cutting by hand, 25-50mm wide Brickwork, cutting by hand, 75-100mm wide Brickwork, cutting by machine, 25-50mm wide Brickwork, cutting by machine, 75-100mm wide 1.0 2.5 1.8 1.6 1.2 3.3 2.5 1.4 3.3 2.4 2.3 1.6 4.5 3.3 2.1 5.0 3.7 3.5 2.5 6.7 5.0 m/hr m/hr m/hr m/hr m/hr m/hr m/hr

Cutting Switchboxes
Cutting in Concrete, small box Cutting in Concrete, large box Cutting in Brickwork, small box Cutting in Brickwork, large box 7.1 3.6 6.6 4.2 9.5 4.5 9.5 5.3 12.5 5.6 12.5 6.3 no/hr no/hr no/hr no/hr

Page 76

Implementing Best Practice Planning & Programming

May 2003

Building Finishes
Ref Task / Description Suspended Ceilings, office situations Suspended Ceilings, First Fix Suspended Ceilings, Second Fix Slow Ave 2.6 1.4 1.2 Fast Units

Suspended Ceilings
3.5 m2/hr - m2/hr - m2/hr

Flooring Finishes
Raised Flooring, metal system Granolithic Flooring Terrazzo Flooring, in-situ Terrazzo Flooring, pre-cast Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, small areas, much cutting Clay, quarry Tiles, large areas, little cutting Linolium/Thermo-Plastic Flooring Thermo-Plastic Floor Tiles Wood Block Flooring, lay blocks Wood Block Flooring, sand and polish Underlay & Grippers Carpeting, Fully Fitted Hardboard Sheeting Coverings, small areas Hardboard Sheeting Coverings, large areas 7.0 3.1 3.6 4.6 1.5 0.8 2.2 3.1 3.3 1.5 3.1 5.0 2.0 3.7 6.6 8.0 m2/hr 5.1 2.2 1.1 2.8 5.0 5.6 2.1 6.0 3.0 4.1 7.2 m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Metalwork
Install Metal Door and Frame Install Balustrade & Railings General Rate - (Flights) 0.2 1.5 4 no/hr m/hr No/wk

Ceramic Tiling
Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, Window Cills, setout and level Clay, quarry Tiles, Window Cills, fix, grout and clean Ceramic Tiles 150x150mm, Ledges/Upstands Ceramic Tiles 150x150mm, Areas under 1.5m2 per room Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 150x150mm, Areas over 2.5m2 per room Ceramic Tiles, Grouting Works 20.4 0.9 1.4 1.5 2.2 1.3 55.5 1.5 27.1 1.0 1.6 1.7 2.5 1.5 32.0 1.2 1.9 2.1 2.6 no/hr m/hr m2/hr no/hr m2/hr m2/hr m2/hr m2/hr

Page 77

Implementing Best Practice Planning & Programming

May 2003

Ref

Task / Description Prepare Walls Prepare Doors Prepare Door Frames Burn Off / Heat Strip Paintwork Timber, knot, 1 primer, stop, 2 undercoat, 1 gloss Timber, touchup primer, 1 undercoat, 1 coat gloss Internal Timber, polyurethane varnish, 2 coats External Timber, 2 coats wood preservative External Timber, 3 coats polyurethane varnish (For all the above take 50% of rate if for frames) Internal Walls, 2 coats emulsion to plaster Internal Walls, 2 coats emulsion to brick/blockwork Internal Walls, 1 mist, 2 coats emulsion to plaster Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster Portaflec Spray External Walls, 2 coats sandtex to render/concrete External Walls, 2 coats sandtex to brick/blockwork Floors, epoxy paint Ceilings, emulsion paint, 2 coats Ceilings, emulsion paint, 3 coats Internal Steelwork, 1 primer, 1 undercoat, 1 gloss External Steelwork, 1 primer, 2 undercoats, 1 gloss

Slow -

Ave 14.2 12.5 25.0 1.1 1.7 3.1 3.3 4.0 2.0

Fast 2.1 3.8 -

Units m2/hr m2/hr m/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Painting

8.0 6.0 6.0 2.3 10

m2/hr m2/hr m2/hr m2/hr m2/hr

1.3 0.9

2.5 2.0 2.9 6.1 5.0 2.4 1.7

m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Wallpapering
Strip Existing Wallpaper (3 layers) & Prepare Walls Fix Wallpaper and lining paper Fix Vinyl and Washable paper Fix Ceiling Lining Paper 4.0 6.0 4.2 4.0 m2/hr m2/hr m2/hr m2/hr

Page 78

Implementing Best Practice Planning & Programming

May 2003

Lifts & Escalators


Task / Description Slow 75.0 Ave 3.0 2.0 1.0 18 65.0 Fast Units wks/floor wks/floor day/floor

Lift Installations
Install 2 to 3 storeys Install 4 storeys and above Testing allow 2 wks plus Standard Lift, Manufacture, test and deliver Non-Standard Lift, Manufacture, test and deliver

26 wks 52.0 wks

Escalator Installations
Develop concept design and gain client approval Prepare preliminary design and gain approval Assemble truss , position/level Install decking and glazing etc Performance testing Full load testing Final test and inspection 16.0 12.0 1.0 3.0 1.0 1.0 1.0 wks wks wks wks wks wks wks

Fitting Out
Task / Description Slow Ave 3.0 5.0 Fast Units wks wks

Kitchen Fit Out


Overall Installation for 100 persons or 50m2 Overall Installation for 500 persons or 150m2

Page 79