You are on page 1of 1

JP CULLENS & SONS 9/17/07 8:42 AM Page 26

J.P. CULLEN & SONS

explains. Five high- Since the project’s inception and as a


WORK IT OUT speed lifts hoist part of its quality management process,
Here’s a look at how J.P. Cullen & Sons had met material to the J.P. Cullen has hosted monthly partnering
upper levels. In lunches where the craftsman, contractor
work force participation requirements for the restora-
addition, 1.2 million and even city officials can converse about
tion of Milwaukee City Hall as of July: pounds of scaffold- the project.
■ 31.3 percent – Total project construction hours worked by ing anchored to the Based on the company’s proprietary
minorities exterior ensures the methods, J.P. Cullen also taught subcon-
■ 26.8 percent – Amount of participation by the city’s residence
safety of the pedes- tractors process improvement on the job
preference program trians as well as the site. To catch crews in action, J.P. Cullen
contractors. video recorded subcontractors in various
■ 77 percent – Minorities who represented the total number of
Given the magni- stages of construction between two and
apprentice hours
tude of the project, three hours. Management then reviewed
■ 23 percent – Total project construction dollars contracted by J.P. Cullen relied on the video with the owners of the trade
emerging business enterprises its close working companies to determine where mistakes
Source: Prism Technical
relationship with a were being made and where productivity
skilled team of sub- could be improved. In many cases, boost-
lem,” Watson explains. As a result, J.P. contractors. Hitting tight delivery sched- ing efficiency on the job site was a mat-
Cullen rented a nearby storage facility ules, although challenging, is made possi- ter of getting workers the right tools. After
for the subcontractors to keep tools and a ble by emphasizing productivity. At the it reviewed the video of onsite perform-
limited amount of material. The next project’s peak, Watson estimates 15 sub- ance, productivity almost doubled for
step was to display a large calendar at contractors will be on site at one time. As one subcontractor on the project.
the site office where the team could see the state of Wisconsin’s only ISO “Instead of looking at how to make the
when material deliveries would be made 9001:2000 certified contractor, it is bank- schedules more productive, we look at
and how the project would progress. ing on is quality methodologies to deftly how to make the worker more produc-
“A lot of the time the materials being manage the trade participation process, tive,” Rocole explains. If the project pro-
delivered will go right up to the scaffold- as it did for the multi-phased State gresses as anticipated, the renovation will
ing where work is being done,” Watson Capitol restoration project. be completed in November 2008. ■

DIVERSE IN contractor must ensure that by


project’s end in November 2008,
viduals who have not had opportu-
nities to gain employment [in con-
attract more minorities and
younger workers to the trades.
SO MANY the following requirements are met: struction] that opportunity,” Rocole
says.
Many referrals are based on
word-of-mouth or through commu-
WAYS ■ A minimum of 18 percent of the “If you’re going to get involved in nity groups, church and other
contractual and change-order dol- something like this, you don’t do it organizations, Rocole notes.
The Milwaukee City Hall renovation lars paid to J.P. Cullen must be to create numbers; you’re in it to Prism Technical, a Milwaukee-
represents more than the typical awarded to businesses certified as create jobs and careers.” based consulting and marketing
renovation. Along with customized emerging business enterprises With experience completing group, is the firm responsible for
work, the project is also investing (EBEs) by the city’s emerging busi- jobs for Milwaukee Public Schools, tracking J.P. Cullen’s progress in
in and revitalizing a new set of con- ness enterprise program. which had similar work force par- meeting the participation goals.
tractors within the Milwaukee com- ticipation goals, J.P. Cullen was President Randy Crump says that
munity. ■ A minimum of 25 percent of the more than confident that it would as of April 30, 15.7 percent of pay-
According to the 2005 estimates hours worked on the renovation on be able to meet and exceed such ments received had gone to EBE
by the U.S. Census Bureau, of the site must be completed by those goals. The firm is required to sub- contractors; 26.8 percent of the
city’s population, an estimated certified under the residence pref- mit monthly EBE payment reports work done was completed by RPP
37.3 percent are African-American, erence program (RPP). and quarterly RPP participation contractors; 31.3 percent of the
12 percent are Hispanic, 2.9 per- reports. J.P. Cullen has also agreed total project construction hours
cent are Asian and 0.9 percent are ■ At least six apprenticeships, to collect, measure and share the were completed by minorities; and
American Indian. In many cases, working a minimum of 10,000 restoration’s RPP performance on minorities represented 77 percent
minorities are underrepresented in hours, must be employed from a monthly basis, ensuring accurate of all apprenticeships.
the construction industry. trades such as bricklayers, glazers and tight control over the participa- J. P. Cullen sees diversity per-
Recognizing the need to provide and roofers. tion performance. formance as something that is in
opportunity to the local and minori- Working with BIG STEP, the everyone’s best interest. “In order
ty work force, Mayor Barrett along J.P. Cullen is proving that it, too, Building Industry Group Skilled for the Milwaukee metro area to be
with the city’s Common Council is committed to the project’s diver- Trades Employment Program, J.P. successful, we need to have a
were committed to requiring local sity, and has made significant Cullen was able to recruit a diverse successful inner city,” Rocole
participation from key groups of strides in meeting and thus far, subcontractor work force for the asserts. “It is that kind of attitude
subcontractors. The City of even exceeding the participation restoration. BIG STEP was which makes a restoration project
Milwaukee Department of Public goals, says Larry Rocole, vice launched in 1976 as a joint effort like the Milwaukee City Hall an
Works identified work force partici- president of its Milwaukee division. between the Milwaukee Building & opportunity for personal and pro-
pation requirements for the “The whole reason for the Construction Trades Council and fessional success in so many peo-
restoration project. The general RPP/EBE program is to give indi- Milwaukee Public Schools to help ple’s lives.”

26 ■ CONSTRUCTION TODAY ■ OCTOBER 2007

You might also like