You are on page 1of 3

I.

A. 1.

Generating Stations Evacuation of Power linked Transmission Works Mahatma Gandhi Thermal Power Project (MGTPP), Jhajjar (Case-2) (2x660MW)
400KV substation Dhanonda(New)
3x315MVA, 400/220kV
Covered in 220 kV substation 100 100 58 42 7 65 100 10 90 10 30 70 30 65 35 10 75 20 75 20 2 64 56 12.168 8.468 38 8 8.632 12.332 4 2 64 60 12.168 8.468

Ateli
Mohindergarh

2008-09

12.4.10

11.10.11 11.10.11

6367.79

Funding : REC-087 Mode : Turnkey

400 kV D/C line from Jhajjar-2 (TPS)400kV substation Dhanonda -20.8km Loc.-64 Mode: Turnkey 400 kV D/C Daultabad Dhanonda line72.979 km Loc.- 229 Funding : REC-099 Mode : Turnkey

Mohindergarh

2008-09

24.7.09

19.11.10

30.9.11

1669.93

S/H building S/Stn. tower foundation Equipment foundations Cable trenches Misc. civil activity Earthing Erection of tower & beam Erection equipment supporting Structures Erection of IDSG Erection of ODSG Erection of transformer Cabling, testing & comm.. Stub settings (Nos.) Tower erection (in No.) S&S of Conductor (in km) S&S of Earthwire (in km)

1454.75

Turnkey contractor: M/s ABB Ltd. Contract awarded on : 31.3.2010

Work in progress by the firm but not as per schedule for which the firm has been requested to expedite the same.

1868.88

Turnkey contractor : M/s Cobra Instalaciones Y. Servicios, S.A, Madrid (Spain) Contract awarded on :27.2.09 Work in progress. The firm has assured to complete the work by 30.9.2011 in the meeting held on 8.8.2011. Turnkey contractor :M/s Cobra Instalaciones Y. Servicios, S.A, Madrid (Spain) Contract awarded on :7.4.2010 M/s Fedders Llyod has been directed to increase the no of foundations gangs & erection gangs for the early completion especially at Daultabad end. The firm has assured to complete the work by 31.12.2011 in the meeting held on 8.8.2011.

2.

Mahindergarh

2009-10 24.7.09

15.9.11 31.12.11 13518.01

Stub setting (No.) Tower erection (in No.) S&S of Condt. (in km) S&S of E/Wire (in km)

145
67 -

74
162 72.98 72.98

6
9 -

151 76 -

7866.93

3.

400KV Substation Kabulpur (Rohtak) 2x315 MVA, 400/220 kV + 2x100 MVA, 220/132kV Mode : PPP

Rohtak

2009-10

9.9.10

2.1.12

2.1.12

38200.00
including associated trans. Lines

S/H building S/Stn. tower foundation Equipment foundations Cable trenches Misc. civil activity Earthing Erection of tower & beam Erection equipment supporting Structures Erection of IDSG

70 100 100 35 30 55 100 80 -

15 54 30 10 10 -

10 54 30 10 10 -

80 100 100 89 60 65 100 90 -

27600.00

PPP Project allotted to Concessionaire M/s Jhajjar KT Transco Pvt. Ltd. (Agreement signed on 28.5.2010) Both 100MVA, 220/132 transformers received at site. kV

4.

400kV Substation Deepalpur (Sonepat) 2x315 MVA, 400/220kV + 2x100 MVA, 220/132kV Mode : PPP

Sonepat

2009-10

9.9.10

2.1.12

2.1.12

Erection of ODSG Erection of transformer Cabling, testing & comm.. S/H building S/Stn. tower foundation Equipment foundations Cable trenches Misc. civil activity Earthing Erection of tower & beam Erection equipment supporting Structures Erection of IDSG Erection of ODSG Erection of transformer Cabling, testing & comm..

70 100 100 91 40 90 100 95 20 59 -

13 5 35 6 4 10 12 -

10 5 35 6 4 6 12 -

80 100 100 96 75 96 100 99 26 71 -

Work in progress. PPP Project allotted to Concessionaire M/s Jhajjar KT Transco Pvt. Ltd. (Agreement signed on 28.5.2010) One 100MVA, 220/132 transformer received at site. Work in progress. kV

5.

400kV D/C Line from MGTPP Jhajjar to 400kV Substation Kabulpur -35km Mode : PPP 400 kV D/C Line from 400 kV Substation Kabulpur (Rohtak) to 400 kV Substation Deepalpur (Sonepat)64 km. Mode : PPP LILO of one circuit of 400 kV Abdullapur Bawana Line at 400 KV Substation Deepalpur (Sonepat)1 km. Mode : PPP

Rohtak/ Sonepat

2009-10

9.9.10

2.1.12

2.1.12

Stub settings (Nos.) Tower erection (in No.) S&S of Conductor (in km) S&S of Earthwire (in km)

259 131 18.154 18.154

27 -

259 158 18.154 18.154

PPP Project allotted to Concessionaire M/s Jhajjar KT Transco Pvt. Ltd. (Agreement signed on 28.5.2010) Work in progress.

Rohtak

2009-10

9.9.10

2.1.12

2.1.12 Total Location-285

Sonepat

2009-10

9.9.10

2.1.12

2.1.12

You might also like