ERECTION WORKS

INQUIRY SHEET

////////////

HYOSUNG CORPORATION
450, Gongduk-dong, Mapo-ku, Seoul 121 - 020, Korea + 82- 2 - 707- 62908 Ref. No. Date FAX + 82- 2 - 714 - 9324 SITE TEST AND COMMISSIONING HOP - 7M - ET01 Sep. 21, 2007 ACCORDING TO ATTACHED PRICE SCHEDULE AND QUOTATION FOR UNIT RATE BASIS Document to be submitted from Vendor PRICE QUOTATION Quotation acc. to attached Price schedule

: Applicable Project Name

: Not Applicable Price Schedule

Java-Bali Acceleration Project Associated with 10,000 MW Steam Coal Power Plant Project Package 1,2 & 3

Tender No. Client

ADB LOAN NO. 1983-INO


PT PLN(PERSERO)

Quotation for Unit rate basis Quotation for Measured Works QUALIFICATION DOCUMENT Power of Attorney Certified/Verified Experience List of similar Construction and Magnitude Check Sheet for Scope of Works Company Profile Others required in the Tender Documents Document Evidence Registered in Origin country List of Owned Erection Equipmnet

Submittal Date Set of Quotation Validity of Quotation Completion Period Payment Term

Not later than Oct. 17, '2007 Original + (2) Copies Until Apr. 17, '2007 3 Months after Order 90% Interim Certificate 10% after Taking-over

Scope of Works

ALL THE WORKS STIPULATED IN THE ATTACHED TENDER PRICE SCHEDULE AND GENERAL REQUIREMENTS. TECHNICAL DOCUMENT Completely filled-in Technical Data Schedule Technical Specification and Drawing Supporting Catalog & Brochures Deviation Sheet (Departures from Specification) or Item-by-Item Commentary OTHERS Attached Document Price Schedule acc. to Tender Document * for each Package & Substations Including : -Summary of Price Schedule -Schedule of Prices for Erection -Schedule of Prices for Test & Commissioning General Requirements Check Sheet for Scope of Works Technical Specification ------------------------------------------M.S.Shim Very truly yours, Tentative Project Implementation Schedule If any queries take place for this INQUIRY, please do not hesitate to contact us, Hyosung.

@OPT-Library #2210

General Technical Specification Reference Drawings

Deputy Senior Manager Overseas Project Team.

@OPT-Library #2220

Page 3/7

GENERAL REQUIREMENTS for Erection


1,
1)

GENERAL SCOPE OF WORKS


The Subcontractor shall perform all works in connection with the assembly and installation of supplied equipment according to Tender Specification, including the necessary works according to Hyosung's drawings and instructions. It generally comprises taking over the material from forwarder/supplier, storing , material/equipment handling within site area, complete erection of indoor and outdoor equipment, cable installation and termination, touchup painting, equipment & site cleaning/waste disposal etc. as stipulated in the relevant documents and drawings. However, unless otherwise mentioned, all consumable materials including wiring accessories, welding material, anchor bolts for installation of equipment conduit pipes for cabling in-between or between equipment and trench or cable trays and terminal lug for grounding etc. shall be provided by Subcontractor at his own expenses. The subcontractor shall perform remove the equipment from storage place to installation point, including unloading & unpacking of all equipment/materials. All the civil works shall be done by others. The Subcontractor shall be cooperate with civil contractor in every respect and in case that some minor modification is required, it shall be carried out by subcontractor at his own expenses. The other necessary works in completion the contract scope with Purchaser shall be followed the Tender Price Schedule and Bill of Material. STORE-KEEPING, SECURITY AND PROTECTION Adequate storage space shall be provided at the site by Hyosung, however Subcontractor shall, at his own cost, provide store building and fences around the storage area, if necessary. The Subcontractor is required to employ a sufficient number of watchmen and is responsible for guarding and maintenance of security on and about site until the completion date of contract. SUBCONTRACTOR'S EQUIPMENT The Subcontractor shall provide, at his own expenses, all erection /installation /assembly technicians, labors, tools, lifting devices, lorries, cranes, safety equipment and indirect & consumable materials, temporary bracing & scaffolding required for the completion of his works. (All necessary rent charge shall be paid by the Subcontractor, if any.)

2)

3)

4) 5)

6)

2,
1) 2)

3,
1)

2)

3)

A sufficient supply of water, compressed air, gas, electricity, telephone facilities and temporary lighting needed by Subcontractor and Hyosung on or about the site during the contract period shall be provided by the Subcontractor including usage bills. The Subcontractor shall provide site office comprising all necessary office facilities for his personnel and Hyosung's representative. The site office shall be maintained until the completion date of contract. INSURANCE The Subcontractor shall furnish all necessary insurance in acc. with the requirements of the Laws prevailing in the Country to cover his own personnel. The Subcontractor shall also furnish separate insurance policies to ensure that all temporary workers employed by him who may not be covered by Social Security of the State Authorities of the Country are also adequately covered.

4,

OPT

HYOSUNG

Gen_RQMT_E+78210670.xls.ms_office

@OPT-Library #2220 5,
PERFORMANCE BOND

Page 4/7

For the due execution and proper performance of the works to be performed under this subcontract, the Subcontractor shall submit to Hyosung a performance guarantee of an amount of 10% of the subcontract value. (within one month after this subcontract comes into force.)

6,
1)

PRICE QUOTATION Notwithstanding that any details, descriptions, etc. required for the complete installation/assembly of the plant/ equipment specified in the Tender Price Schedule and Bill of Material are not specifically mentioned in Subcontractor's quotation, such minor cost is to be considered as included in the quoted price, unless otherwise specified.

2)

In addition to submission of Price Schedule after duly filling-in his best and competitive price, the Subcontractor shall furnish the following documents ; (A subcontractor's failure to submit any of the document listed in the below may influence the course of the Evaluation.) - a Quotation for unit rate basis - a Quotation for Measured works - completely filled-in Check Sheet for Scope of Works.

7,
1) 2) 3) 4)

150kv GIS EQUIPMENT Assembly of all components and docking including gas bushing, bus duct & its supports. Leveling with wedge, anchoring by bolt or welding. Change of ZEOLITE, piping works for gas & air line. Vacuuming, charging and evacuating (de-gassing) of SF6 Gas during assembly/erection and testing of GIS, inspection of internal assembly & supporting the test & commissioning. The above works may be repeated several times, if necessary. Spray finishing paint for whole equipment, grounding, sealing works for weatherproof. Holding of gland plate and cable duct, painting and/or tinning of earthing bond. Cable-head works (dis-assembling, re-assembling, gassing, de-gassing) for HV cable sealing end works. The Subcontractor shall provide necessary manpower, tools and equipment. POWER TRANSFORMER/AUTO TRANSFORMER For Transformer installation and assembly, the filtering/vacuuming machine, electric power supply, tools for installation & assembly, and ancillaries shall be provided by Subcontractor. In addition to above, the Subcontractor shall also install neutral CT with supporting structure on or beside Transformer. NCT connection, grounding of NCT & Transformer, cable termination for MV side cable shall also be done by Subcontractor. PANEL, CUBICLE AND SWITCHBOARD Installation & assembly of the equipment including connection between equipment. Supply and install all necessary anchor bolt. Termination works in-between or between equipment.

5) 6) 7) 8)

8,
1) 2) 3)

9,
1) 2) 3)

10, STEEL STRUCTURE & BUSBAR CONDUCTOR


1) 2) Assembly of all steel structure such as gantry post, beam, earth mast, supporting structure for outdoor equipment and power cable. Installation of all overhead earth wire and busbar conductor for slack span & between equipment & line to equipment, together with connection and termination.

11, OUTDOOR EQUIPMENT SUCH AS CVT, LA, ETC.

OPT

HYOSUNG

Gen_RQMT_E+78210670.xls.ms_office

@OPT-Library #2220
1) 2) Installation of the equipment including cabling, junction box and connection.

Page 5/7

Supply and installation of conduit pipe between equipment/fixture and trench or cable tray shall be provided by Subcontractor, at his own expenses.

12, BATTERY
1) 2) Installation of battery & battery rack and inter-cell connection shall be done by Subcontractor. The Subcontractor shall provide the distilled water, mixing the electrolyte and fixing to battery electrolyte. Initial charging of batteries and numbering of cells & bank shall be provided by the Subcontractor.

13, HV & MV CABLE AND LV AUXILIARY & CONTROL CABLE


1) 2) Installation, laying, connection, termination, marking and fixing for all equipment shall be done by Subcontractor. Installation of cable gland, hole opening of cable gland plate, supply & install of cable marker, cable tie & numbering ferrules shall be done by Subcontractor.

14, EARTHING
1) 2) 3) The Earthing works, the main & branch earthing conductor and design/ construction drawings will be provided by Hyosung. Supply of all consumable materials including welding materials, non-ferrous clamps and installation and connection of all earthing conductor shall be done by the Subcontractor. Black painting & tinning the outside grounding copper tapes acc. to Purchaser standard shall be included in the scope of work.

15, LIGHTING SYSTEM


1) 2) 3) The building fence lighting shall be done by others. The lighting material (lighting fixture, lamp bulb & sun switch only) shall be provided by Hyosung. The Subcontractor shall install of all necessary lighting material for complete lighting system at switchyard or on steel structure or specific points as per Tender schedule.

16, TEST AND COMMISSIONING


Test and Commissioning will be carried out by Hyosung and other subcontractor. The subcontractor shall provide all necessary tools, man-power including engineer, technician, labor to assist the abovesaid test & commissioning at site.

17, SUBCONTRACTOR'S EXPERIENCE


The Subcontractor who wants to get the order from Hyosung shall have experiences the following works as minimum ; : Installation and project management of at least 3(three) substations of rating not less than 275kv and 132kv class and the substations must have been in operation for at least 1(one) year. The copies of each aforesaid contract certified/verified subcontractor's experience shall be submitted with the quotation.

OPT

HYOSUNG

Gen_RQMT_E+78210670.xls.ms_office

@OPT-Library #2220

Page 6/7

NAME OF SUB-CONTRACTOR :

CHECK SHEET FOR SCOPE OF WORKS


NO
A
1 2 3 4 5 6 7 8

WORK DESCRIPTION
GENERAL
provide necessary man-power for performance of complete erection works provide necessary tools,vehicles, cranes, lorry etc. for completion erection works daily/weekly/monthly progress report performance bond guarantee/warranty bond workmen's compensation policy for sub-contractor's personnel accommodation & transportation for sub-contractor's personnel safety control

INCLUDED

EXCLUDED

B
1 2

OFFICE
provide site office for Hyosung provide site office for sub-contractor

C
1 2 3 4 5 6

TEMPORARY FACILITIES
installation & removal of temporary electricity supply installation & removal of temporary water supply installation & removal of temporary telephone facilities installation & removal of temporary lighting facilities monthly charge of usage of electricity, water & telephone provide portable fire extinguishers

D
1 2 3 4 5

STORAGE & KEEPING


provide portable cabin storage provide covered storage (indoor) provide fencing & gate for open yard storage provide store keeper provide security guard

E
1 2 3 4 5

UNLOADING & UNPACKING AT SITE


handling & transportation of all equipment & materials within the site provide unloading facilities provide unloading works at site provide unpacking of all crates/packages general checking & inspection of equipment at site

OPT

HYOSUNG

Check+78210670.xls.ms_office

@OPT-Library #2220

Page 7/7

NAME OF SUB-CONTRACTOR :

CHECK SHEET FOR SCOPE OF WORKS


NO
F
1 2 3 4 5 6 7 8 9 10 11

WORK DESCRIPTION
ERECTION WORKS
provide oil filtering/purification plant include vacuum & oil filteration works assisting unloading main body of power x-former to plinth fixing all x-former accessories pilot cable laying assisting 150kv power cable seaing ends works 150kv power cable laying LV cable laying & termination fixing,installation/assembly & setting for cable rack, cable tray & ladder installation/assembly & setting for substation computer-based control system provide all fixing & anchor bolt,support and base channel for installation of equipment, SWGR & panels etc.

INCLUDED

EXCLUDED

12 13 14

provide touch-up paint for all equipments touch-up painting works for all equipments provided special provision as mentioned in the General Requirements

G
1 2

SITE TEST & COMMISSIONING


provide site test & commissioning provide site test & commissioning assistance

H
1 2 3

OTHERS
site/equipment cleaning & waste disposal

OPT

HYOSUNG