ERECTION WORKS
INQUIRY SHEET
////////////
HYOSUNG CORPORATION
450, Gongduk-dong, Mapo-ku, Seoul 121 - 020, Korea + 82- 2 - 707- 62908 Ref. No. Date FAX + 82- 2 - 714 - 9324 SITE TEST AND COMMISSIONING HOP - 7M - ET01 Sep. 21, 2007 ACCORDING TO ATTACHED PRICE SCHEDULE AND QUOTATION FOR UNIT RATE BASIS Document to be submitted from Vendor PRICE QUOTATION Quotation acc. to attached Price schedule
Java-Bali Acceleration Project Associated with 10,000 MW Steam Coal Power Plant Project Package 1,2 & 3
Quotation for Unit rate basis Quotation for Measured Works QUALIFICATION DOCUMENT Power of Attorney Certified/Verified Experience List of similar Construction and Magnitude Check Sheet for Scope of Works Company Profile Others required in the Tender Documents Document Evidence Registered in Origin country List of Owned Erection Equipmnet
Submittal Date Set of Quotation Validity of Quotation Completion Period Payment Term
Not later than Oct. 17, '2007 Original + (2) Copies Until Apr. 17, '2007 3 Months after Order 90% Interim Certificate 10% after Taking-over
Scope of Works
ALL THE WORKS STIPULATED IN THE ATTACHED TENDER PRICE SCHEDULE AND GENERAL REQUIREMENTS. TECHNICAL DOCUMENT Completely filled-in Technical Data Schedule Technical Specification and Drawing Supporting Catalog & Brochures Deviation Sheet (Departures from Specification) or Item-by-Item Commentary OTHERS Attached Document Price Schedule acc. to Tender Document * for each Package & Substations Including : -Summary of Price Schedule -Schedule of Prices for Erection -Schedule of Prices for Test & Commissioning General Requirements Check Sheet for Scope of Works Technical Specification ------------------------------------------M.S.Shim Very truly yours, Tentative Project Implementation Schedule If any queries take place for this INQUIRY, please do not hesitate to contact us, Hyosung.
@OPT-Library #2210
@OPT-Library #2220
Page 3/7
2)
3)
4) 5)
6)
2,
1) 2)
3,
1)
2)
3)
A sufficient supply of water, compressed air, gas, electricity, telephone facilities and temporary lighting needed by Subcontractor and Hyosung on or about the site during the contract period shall be provided by the Subcontractor including usage bills. The Subcontractor shall provide site office comprising all necessary office facilities for his personnel and Hyosung's representative. The site office shall be maintained until the completion date of contract. INSURANCE The Subcontractor shall furnish all necessary insurance in acc. with the requirements of the Laws prevailing in the Country to cover his own personnel. The Subcontractor shall also furnish separate insurance policies to ensure that all temporary workers employed by him who may not be covered by Social Security of the State Authorities of the Country are also adequately covered.
4,
OPT
HYOSUNG
Gen_RQMT_E+78210670.xls.ms_office
@OPT-Library #2220 5,
PERFORMANCE BOND
Page 4/7
For the due execution and proper performance of the works to be performed under this subcontract, the Subcontractor shall submit to Hyosung a performance guarantee of an amount of 10% of the subcontract value. (within one month after this subcontract comes into force.)
6,
1)
PRICE QUOTATION Notwithstanding that any details, descriptions, etc. required for the complete installation/assembly of the plant/ equipment specified in the Tender Price Schedule and Bill of Material are not specifically mentioned in Subcontractor's quotation, such minor cost is to be considered as included in the quoted price, unless otherwise specified.
2)
In addition to submission of Price Schedule after duly filling-in his best and competitive price, the Subcontractor shall furnish the following documents ; (A subcontractor's failure to submit any of the document listed in the below may influence the course of the Evaluation.) - a Quotation for unit rate basis - a Quotation for Measured works - completely filled-in Check Sheet for Scope of Works.
7,
1) 2) 3) 4)
150kv GIS EQUIPMENT Assembly of all components and docking including gas bushing, bus duct & its supports. Leveling with wedge, anchoring by bolt or welding. Change of ZEOLITE, piping works for gas & air line. Vacuuming, charging and evacuating (de-gassing) of SF6 Gas during assembly/erection and testing of GIS, inspection of internal assembly & supporting the test & commissioning. The above works may be repeated several times, if necessary. Spray finishing paint for whole equipment, grounding, sealing works for weatherproof. Holding of gland plate and cable duct, painting and/or tinning of earthing bond. Cable-head works (dis-assembling, re-assembling, gassing, de-gassing) for HV cable sealing end works. The Subcontractor shall provide necessary manpower, tools and equipment. POWER TRANSFORMER/AUTO TRANSFORMER For Transformer installation and assembly, the filtering/vacuuming machine, electric power supply, tools for installation & assembly, and ancillaries shall be provided by Subcontractor. In addition to above, the Subcontractor shall also install neutral CT with supporting structure on or beside Transformer. NCT connection, grounding of NCT & Transformer, cable termination for MV side cable shall also be done by Subcontractor. PANEL, CUBICLE AND SWITCHBOARD Installation & assembly of the equipment including connection between equipment. Supply and install all necessary anchor bolt. Termination works in-between or between equipment.
5) 6) 7) 8)
8,
1) 2) 3)
9,
1) 2) 3)
OPT
HYOSUNG
Gen_RQMT_E+78210670.xls.ms_office
@OPT-Library #2220
1) 2) Installation of the equipment including cabling, junction box and connection.
Page 5/7
Supply and installation of conduit pipe between equipment/fixture and trench or cable tray shall be provided by Subcontractor, at his own expenses.
12, BATTERY
1) 2) Installation of battery & battery rack and inter-cell connection shall be done by Subcontractor. The Subcontractor shall provide the distilled water, mixing the electrolyte and fixing to battery electrolyte. Initial charging of batteries and numbering of cells & bank shall be provided by the Subcontractor.
14, EARTHING
1) 2) 3) The Earthing works, the main & branch earthing conductor and design/ construction drawings will be provided by Hyosung. Supply of all consumable materials including welding materials, non-ferrous clamps and installation and connection of all earthing conductor shall be done by the Subcontractor. Black painting & tinning the outside grounding copper tapes acc. to Purchaser standard shall be included in the scope of work.
OPT
HYOSUNG
Gen_RQMT_E+78210670.xls.ms_office
@OPT-Library #2220
Page 6/7
NAME OF SUB-CONTRACTOR :
WORK DESCRIPTION
GENERAL
provide necessary man-power for performance of complete erection works provide necessary tools,vehicles, cranes, lorry etc. for completion erection works daily/weekly/monthly progress report performance bond guarantee/warranty bond workmen's compensation policy for sub-contractor's personnel accommodation & transportation for sub-contractor's personnel safety control
INCLUDED
EXCLUDED
B
1 2
OFFICE
provide site office for Hyosung provide site office for sub-contractor
C
1 2 3 4 5 6
TEMPORARY FACILITIES
installation & removal of temporary electricity supply installation & removal of temporary water supply installation & removal of temporary telephone facilities installation & removal of temporary lighting facilities monthly charge of usage of electricity, water & telephone provide portable fire extinguishers
D
1 2 3 4 5
E
1 2 3 4 5
OPT
HYOSUNG
Check+78210670.xls.ms_office
@OPT-Library #2220
Page 7/7
NAME OF SUB-CONTRACTOR :
WORK DESCRIPTION
ERECTION WORKS
provide oil filtering/purification plant include vacuum & oil filteration works assisting unloading main body of power x-former to plinth fixing all x-former accessories pilot cable laying assisting 150kv power cable seaing ends works 150kv power cable laying LV cable laying & termination fixing,installation/assembly & setting for cable rack, cable tray & ladder installation/assembly & setting for substation computer-based control system provide all fixing & anchor bolt,support and base channel for installation of equipment, SWGR & panels etc.
INCLUDED
EXCLUDED
12 13 14
provide touch-up paint for all equipments touch-up painting works for all equipments provided special provision as mentioned in the General Requirements
G
1 2
H
1 2 3
OTHERS
site/equipment cleaning & waste disposal
OPT
HYOSUNG