Professional Documents
Culture Documents
10/ 6/2011
Presentation Outline
Establishing Phase
the Trail
10/6/2011
Success Factors
Tireless
Promotion Patience and Persistence Maintain Flexibility Face Challenges Plan Ahead for Impact
10/6/2011
GBG - There will be challenges, be patient persistent flexible and plan ahead Introduce Supervisor Ray Costantino with brief bio.
1980
1985
1990
1995
2000
2005
2010
2015
1997 - First 2.5 miles of the Huds on Valley Rail Trail Opens
10/6/2011
Ray
HVRT Phase I
10/6/2011
Highland Hamlet
10/6/2011
10/6/2011
10/6/2011
10/6/2011
10/6/2011
10
10
10/6/2011
11
11
http://www.hudsonvalleyrailtrail.net/photos/
10/6/2011 12
12
10/6/2011
13
13
Phase II
HVRT Phase I
HVRT Phase II
10/6/2011
14
14
Phase II
HVRT Phase I
Close up of Phase 2
15
Budget
Phase
I Budget
Phase
II Budget
(120 Span)
Pedestrian Bridge over NYS 44/55 Replace Underpass at Mile Hill Road
10/6/2011
16
First phase was somewhat inexpensive, using funds from agreement to located FiberOptic in the corridor, volunteers and donations. This next phase, we needed a bridge and an underpass, we needed lots more money and could not be done by volunteers
16
Budget
10/6/2011
17
We were not sitting on a stack of money, so we needed some big time help.
17
Growth Pains
Ulster
2006
10/6/2011
2007
2008
2009
2010
2011
18
18
Prerequisites
10/6/2011
19
Next we needed to follow the procurement guidelines that went with the funding to select a consultant team
19
Design Contract
Contract
Reporter Ad Date November 2006 Proposal Evaluation and Interviews December 2006 Quality Based Selection January 2007 Award Letter January 15, 2007
2006
10/6/2011
2007
2008
2009
2010
2011
20
20
Phase 2
Takes Time and Money
10/ 6/2011
21
21
Paved extension of the HVRT from Commercial Avenue to Haviland Road. Install a pedestrian bridge over Vineyard Ave./NYS Route 44-45. 44Enhance the Route 9W Railroad underpass and connect the sidewalk to the HVRT. Excavate a buried structure at Mile Hill Road to re-establish the former railroad underpass with a new passageway.
22
10/6/2011
22
Connect to Rte 9W
10/6/2011
23
23
Design Approval
Because the project was federally funded, the Locally Administered Federal Aid Program process had to be followed
24
10/6/2011
25
25
Photo: Walkway.org
10/6/2011 26
As Ray mentioned earlier, the idea of actually creating the walkway was thought to be in the distant future, but the future came in 2007, the trail project changed in response.
26
Original Concept
10/6/2011
27
The original concept was to direct trail users down Haviland Road to the Mid Hudson Bridge and on to Poughkeepsie.
27
Mid-Course Correction
Initial
Project would not Connect to the Walkway During Preliminary Design, Town urged to fill the gap by DOT Required Revision to Contracts, Work in Progress (Design Approval Documents)
2006
10/6/2011
2007
2008
2009
2010
2011
28
As a result, the Town agreed to re-scope the HVRT project and add a connection to the bridge, which was already under design.
28
requests additional funds DOT Approves Agreements June 2008 Design Approval Document Revised Additional Site Investigations and Survey Acquire an Easement from CHGE Coordinate with the Walkway Designers
2006
10/6/2011
2007
2008
2009
2010
2011
29
29
to Region 8 in September 2008 Expedited Review to Construct for October 2009 Walkway Opening
2007 2008 2009 2010 2011
30
Requested
2006
10/6/2011
30
Month Turnaround by Region 8 Presented Options for Funding Gap Right-of-Way concerns Right-ofWalkway Parking Lot Easement with CHGE
2006
10/6/2011
2007
2008
2009
2010
31
Town decided to avoid potential delays and fund the easements with Walkway and CHGE on their own.
31
10/6/2011
32
32
Schedule to meet Deadlines Anticipated $$, but not guaranteed Additional Contract Language and Reporting Construction Funding ARRA Continued to Evolve
10/6/2011
33
The HVRT is put on the list of potential projects, but design approval was needed by June 29th
33
Outstanding Issues
CHGE Utility
Required Mandatory 90 Day Wait Adesta assets now owned by NYS OFT
2006
10/6/2011
2007
2008
2009
2010
34
34
Authorization to Proceed
August
2009 Detailed Design and ROW Acquisition New Stimulus Deadline Met (October 30, 2009)
2006
10/6/2011
2007
2008
2009
2010
35
35
Design Standards
Widths
and Clearances
10/6/2011
36
36
Design Standards
Typical
Sections
10/6/2011
37
37
Design Standards
Drainage
10/6/2011
38
38
Design Standards
Slopes
10/6/2011
39
39
Design Standards
Erosion
Control
10/6/2011
40
40
Design Standards
Signage
10/6/2011
41
41
Design Standards
MPT
10/6/2011
42
42
Design Standards
Trailheads,
10/6/2011
43
43
Design Standards
Final
10/6/2011
44
44
of Activity
2006
10/6/2011
2007
2008
2009
2010
45
The months of September and October required a frenetic series of meetings, phone conferences, emails and juggling
45
opened in December Low Bid 14% under Estimate ARRA Funding Secured Construction start early 2010
2006
10/6/2011
2007
2008
2009
2010
2011
46
46
Construction is Easy!?
10/ 6/2011
47
47
March 2010
10/6/2011
48
Might be hard to imagine, but last year construction work started in early March.
48
March 2010
10/6/2011
49
One early issue was the amount of discarded material found along the corridor
49
March 2010
10/6/2011
50
Then the Town received a complaint that the trail was being built on private property
50
April 2010
10/6/2011
51
A big unknown was the old bridge structure under Mile Hill. Utility work included relocation of Town water lines, fiber optic lines, and overhead electric
51
April 2010
10/6/2011
52
52
May 2010
10/6/2011
53
The approach to 9W was cleared, under this segment the Town had installed a major sanitary trunk line.
53
May 2010
10/6/2011
54
54
June 2010
10/6/2011
55
The old Mile Hill bridge removed, the new structure quickly took shape.
55
June 2010
10/6/2011
56
A precast structure was lowered into place creating the underpass in a few hours.
56
July 2010
10/6/2011
57
With the abutments ready, the new pedestrian bridge was delivered
57
July 2010
10/6/2011
58
58
July 2010
10/6/2011
59
59
July 2010
10/6/2011
60
60
July 2010
10/6/2011
61
And as the sun set, the bridge was in place and Vineyard was opened to traffic again.
61
July 2010
10/6/2011
62
62
August 2010
10/6/2011
63
With the major structures in place, the trail itself began to take shapeand get used
63
September 2010
10/6/2011
64
64
September 2010
10/6/2011
65
65
September 2010
10/6/2011
66
Pavement work progressed quickly in September, this stretch showing the Route 9W underpass
66
October 2010
10/6/2011
67
67
October 2010
10/6/2011
68
A few finishing touches remained as the trail was opened for business.
68
October 2010
10/6/2011
69
A formerly overgrown, refuse strewn former rail corridor is now a scenic public recreation amenity
69
October 2010
10/6/2011
70
70
November 2010
10/6/2011
71
71
10/ 6/2011
72
The Ribbon cutting on the first anniversary of the opening of the Walkway
72
What Now?
Plans
were in place
In many ways the Town and the Rail Trail Association had been prepared for the opening of the West segment and Walkway.
73
Local Promotion
10/6/2011
74
74
Local Promotion
10/6/2011
75
A new Brochure was in the works and unveiled shortly after the trail ribbon cutting
75
Community Response
10/6/2011
76
The trail was an established and valued part of the community prior to the West extension. These are newsletter articles
76
Town Response
Outreach
10/6/2011
77
77
Town Response
Outreach
http://www.lewbryson.com
10/6/2011 78
78
Town Response
Outreach
10/6/2011
79
79
Town Response
Planning
10/6/2011
80
80
Town Response
Planning
10/6/2011
81
81
Town Response
Planning
10/6/2011
82
82
10/6/2011
83
83
Economic Impacts
During
Completion
10/6/2011
84
84
10/6/2011
85
85
Road Project
10/6/2011
86
86
10/6/2011
87
87
Perception of Place
10/6/2011
88
88
Perception of Place
Photo by David Rocco
10/6/2011
http://blogs.artvoice.com/avdaily/tag/walkway-over-the-hudson/
89
89
Perception of Place
10/6/2011
90
90
Perception of Place
10/6/2011
91
91
Perception of Place
10/6/2011
92
92
Perception of Place
10/6/2011
93
93
Perception of Place
10/6/2011
94
94
Perception of Place
10/6/2011
95
95
Perception of Place
10/6/2011
96
96
Economic Impacts
10/6/2011
97
An economic impact study prepared prior to the opening of the bridge predicted about 250,000 users per year. The actual count was 760,000.
97
Economic Impacts
Trail
10/6/2011
98
98
have found an average of around 275 users per mile/month The HVRT would add about 12,000 users per year. Economic impacts from user spending would be between $120,000 and $360,000
10/6/2011
99
Based on a similar methodology employed in the Walkway Economic Impact Study. These are extremely conservative projections. They could obviously be at least tripled
99
The Future
HVRT
to WVRT Link
Colleges (SUNY New Paltz, Marist, Vassar) Paltz, Vassar Journey to Work (Park and Bike, Bike and Ride MTA/Amtrak) Special Event Commutes (UC Fair, Trail/Walkways Events, River Ramble )
10/6/2011
100
100
The Future
Link
to Dutchess Rail Trail and Harlem Valley Rail Trail via Walkway
100s of miles of contiguous Trailways
10/6/2011
101
101
Pop Quiz
Q.
A bikeway physically separated from motorized traffic and available for use by a variety of nonnonmotorized users is called a...? A. Shared Use Path Q. What is the recommended width for a shared use path? A. 10 with 2 shoulders. 10 2 Q. What is the maximum grade for a Shared Use Path? A. 12.5% for up to 10
10/6/2011 102
102
10/6/2011
103
103
10/ 6/2011
104
104