You are on page 1of 8

the increased maintenance even made things

worse!
The Value of RCM in
Business Today Stan Nowlan and Howard Heap1 studied aircraft
failures looking for correlations between those
failures and the maintenance that was being
Summary performed. They recognized that maintenance
Reliability-Centered Maintenance (RCM) is the was a contributing factor to many of the failures
world’s dominant proactive method for but in some other cases maintenance was able to
determining maintenance requirements for improve the situation. They looked for patterns
physical assets. It is a thorough methodology and found them. There were actually six patterns
that produces well documented and fully of Conditional Probability of Failure2.
justified decisions on asset management
strategies. It has been highly successful at
improving reliability and safety while reducing A 4%
overall maintenance costs and increasing
capacity for increased revenue generation. RCM

Conditional Probability of Failure


had its beginnings in the commercial airline B 2%
sector and has spread to virtually every other
capital intensive industry. In many cases, it has
a substantial payback on its initial investment in C 5%
addition to several benefits that are not as easily
quantified: safety, environmental compliance and
product quality. RCM provides great benefit and D 7%
is worthy of consideration if reliability is truly
important to your business.
E 14%

The Value of RCM in Business


Today F 68%
Reliability-Centered Maintenance (RCM) is the
world’s dominant proactive method for Operating Age
determining the maintenance requirements for
physical assets. It is of particular value to capital • Pattern A is the well-known bathtub curve.
intensive industries where business success It begins with a high incidence of failure
depends heavily on the use of its assets operating (known as in infant mortality) followed by a
reliably and safely. constant or gradually increasing conditional
probability of failure, then a wear-out zone.
RCM was developed in the commercial airline This pattern appears in biological systems
sector in the 1970’s. At the time, the commercial (like us) and in simple systems that have
aircraft industry was experiencing some 60 only a few dominant failure modes.
crashes per million take-offs. Roughly 40 of
those were attributed to equipment failure. The • Pattern B – classic wear out, shows constant
industry was in the early stages of design of its or slowly increasing conditional probability
jumbo jets – the Boeing 747, McDonald Douglas of failure, ending in a wear-out zone. Prior
DC-10 and Lockheed L-1011. It feared that if 1
airliners continued to crash at the same rate it Nowlan, F. Stanley, and Howard F. Heap,
would not attract many customers, ultimately “Reliability-Centered Maintenance,” Department
failing to reach its growth potential. They of Defense, Washington, DC, 1978. Report
attempted to cure the problem by increasing the number AD-A066579.
2
amount of maintenance they were doing – after Conditional Probability of Failure is the
all, many failures were equipment related. To probability of failure of an asset at any instant in
their dismay, they discovered that in many cases time given the condition that it has survived to
that point in time.

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 1
to the Nowlan and Heap study, this was the
dominant view of equipment failure. It These findings contradicted the then-current
occurs in assets that are in contact with belief that there was a connection between
product, process fluids and slurry’s and reliability and operating age. This belief led to
drive components. the idea that the more often an item is over-
• Pattern C – gradual aging, shows slowly hauled, the less likely it would be to fail.
Nowadays, this is seldom true. Unless there is a
increasing conditional probability of failure,
but there is no identifiable wear-out age. dominant age-related failure mode, age limits do
This occurs where there is erosion, corrosion little or nothing to improve the reliability of
or fatigue. complex items. In fact scheduled overhauls often
increase overall failure rates by introducing
• Pattern D – best new, shows low conditional infant mortality into otherwise stable systems.
probability of failure when the item is new
or just out of the shop, then a rapid increase To make practical use of this information,
to a constant level. This occurs in systems, Nowlan and Heap developed the RCM process
usually complex, that are maintained and put and their findings were published by the US
into service by highly qualified technicians Department of Defense (1978). Various military
before being turned over to less qualified standards4 (in the US and UK) and an aerospace
operators. Examples are hydraulic, fluid industry standard5 (international) were then
power and pneumatic systems. published. Two other excellent reference books
• Pattern E – totally random, shows a constant on RCM soon followed for commercial
conditional probability of failure at all ages. application. John Moubray published the first
This pattern appears in many systems or edition of his book6 in 1991, followed by
components that are, on their own, not Anthony M. Smith7 in 1993. Smith focused
typically subject to maintenance work. primarily on the electric generation industry
Rolling element bearings and incandescent while Moubray’s work was more general in
light bulbs are examples of this type of nature and has broader application. Throughout
failure. the 1990’s a proliferation of various maintenance
program development methods arose, all of them
• Pattern F – starts with high infant mortality, claiming to be RCM. For reasons of improved
dropping to a constant or slowly decreasing economy, the US military then decided to
conditional probability of failure. This is eliminate the requirement for use of its stringent
common in complex systems that are subject MIL-STDs if suitable commercial alternative
to start up and shut down cycles, frequent
overhaul type maintenance work and
product cycle fluctuations. studies there were far fewer pattern F failures but
more of patterns E and B. This is attributed to
Nowlan and Heap’s study on civil aircraft maintenance programs that include “run in” of
showed that 4% of the items conformed to assets after they are maintained in order to
pattern A, 2% to B, 5% to C, 7% to D, 14% to E eliminate infant mortality once the asset is put
and no fewer than 68% to pattern F. The number into service.
4
of times these patterns occur in aircraft is not US DOD: MIL-STD 2173(AS), NAVAIR 00-
necessarily the same as in industry. But there is 25-403, S9081-AB-GIB-010/MAINT (The
no doubt that as assets become more complex, USN’s RCM Handbook) and UK MOD: NES
we see more and more of patterns E and F. Later 45.
5
studies3 have shown the same patterns with MSG-3, “Maintenance Program Development
somewhat different (but similar) distributions. Document”, Air Transport Association,
Washington, DC
6
Moubray, John, “Reliability-centred
3
Broberg (1973) also studied aircraft and two Maintenance II”, 1991, Butterworth-Heinemann,
studies were performed on submarine failures Oxford, UK (now in 2005, it is in its 2nd edition).
7
(MSP in 1982 and SUBMEPP in 2001). All Smith, Anthony M., “Reliability-Centered
show similar patterns with somewhat different Maintenance”, 1993, McGraw-Hill, Inc., New
percentage distributions. In the submarine York, NY

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 2
were available. To clear the confusion that computerized data base systems to track their
existed in the commercial market, and at the analyses, but print the worksheets for review
encouragement of the US DOD, the SAE purposes.
developed its standard, JA10118. The remainder
of this paper discusses RCM as described in the Successful RCM analysis requires a detailed
SAE standard. knowledge of the physical assets, what they are
intended to do for the company along with
RCM has proven to be highly successful. In performance standards, how the fail, what
commercial airlines it has reduced the crashes happens when they fail, how to repair them and
from 60 per million to only 2 per million, a 30- of a variety of maintenance approaches that can
fold improvement and reduced the proportion of be used. RCM requires a team effort. Teams are
equipment related causes from 40 per million to typically comprised of 3 to 4 operators and
0.3 per million. Commercial air travel today is maintainers plus a facilitator. The knowledge
extremely safe with an average of one required to do RCM analysis is found in
commercial airliner crashing per month. That operators and maintainers of the assets.
may seem high, but relative to the industry’s Periodically they are supported by engineers and
performance in the 1960’s and 70’s it is a vast other specialists in the design, construction, use
improvement. Your chances of being hit by and maintenance of the assets. The teams are
lightning are 5 times greater! facilitated by an analyst who is trained to a great
depth in RCM and in how to facilitate the
The RCM process requires the answering of 7 analysis.
questions in sequence:
1. What are the functions and associated RCM analyses are conducted in small projects.
desired standards of performance of the Each project deals with a system or piece of
asset in its present operating context equipment. The projects are chosen so that they
(functions)? can be completed in no more than 15 three-hour
2. In what ways can it fail to fulfill its meetings by the analysis team. Analysis of all
functions (functional failures)? the assets at a particular facility can take several
3. What causes each functional failure months to a few years depending on the size and
(failure modes)? complexity of the facility and its systems.
4. What happens when each failure occurs Toronto Hydro, the electric distribution utility
(failure effects)? for Canada’s largest city, did approximately 100
5. In what ways does each failure matter projects covering most of their assets within a 2
(failure consequences)? year period. GE Plastics in the Netherlands
6. What should be done to predict or analyzed critical assets in some 32 projects over
prevent each failure (proactive tasks and 2 ½ years. The Canadian Navy analyzed all
task intervals)? systems (nearly 250) on its then new ships (in
7. What should be done if a suitable the late 1980’s) in a four year period.
proactive task cannot be found (default
actions)? RCM is a proactive analysis process. It is used
to determine what will happen when failures
These seem simple enough, but answering these occur and to decide on appropriate measures to
questions satisfactorily requires a deep mitigate the consequences BEFORE they
understanding of RCM that goes beyond the happen. The alternative to RCM is to allow the
scope of this paper. failures to happen, to suffer the consequences
and then to decide on what to do to avoid them
The results of RCM analyses are documented on in the future. There are a variety of approaches
Information Worksheets and Decision Logic that are used: Root Cause Failure Analysis,
Worksheets. Many companies opt for Preventive Maintenance Optimization and
various engineering statistical analysis methods
8 all deal with the failures after the fact. With the
SAE JA1011, “Evaluation Criteria for
exception of PMO, they require statistical data
Reliability-Centered Maintenance (RCM)
that can only be collected for your facility after
Processes”, Aug 1999.

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 3
you have experienced the failures. These dealing with minute details tended to
methods all work very well and they are, in the get bogged down in details. This
opinion of the author, excellent as enhancements problem proved to be temporary –
to any existing maintenance program, but they eventually they became very good
are not a replacement for proactively avoiding system analysts.
the problems in the first place. Only RCM • They found that they didn’t know their
attempts and succeeds at doing that own systems as well as they thought. A
economically, yet even RCM has its weakness. great deal of time was spent discovering
how some of their assets, particularly
RCM cannot detect multiple-independent failure the older ones, really worked.
events that, when combined, lead to undesirable • Potential cost savings mean reductions
(often catastrophic) consequences. Fault-tree in labor and materials use. As they
analysis deals with this successfully but it is very were seeing many opportunities to save,
complicated and expensive to perform. Fault- they realized that it could mean loss of
tree analysis is usually reserved only for highly jobs. This led to increased resistance to
critical systems such as nuclear power plants, implementing the results of the
avionics systems, high-tech weapons, potentially analyses. Eventually they got past this
hazardous chemical and biological processes. problem.
• RCM looks like a lot of work but the
One company shared its lessons from applying use of “templates” can substantially
RCM publicly in a conference in late 2002. reduce the effort for fleets or “classes”
Toronto Hydro acknowledged that RCM was of assets.
tougher to perform than they originally • Getting some analysts to participate
anticipated: proved problematic due to the time
• Dealing with hidden failures proved commitment it required. The analysis
challenging for many analysts not time competed with their other job
familiar with the concept. responsibilities. Management
• They found that their data collection intervention was sometimes needed to
wasn’t sufficient to support many of the resolve the conflicting priorities.
calculations they had to make. A recent • Project estimations were initially low
benchmarking study in the US9 revealed and time commitments for individuals
that over 50% of the 800 participants were greater than expected. Some
did not trust their data systems enough schedule delays occurred as a result.
to perform reliability calculations. Over time the experience gained
Although RCM doesn’t require accurate through doing analyses helps in
statistical data it helps improve to estimating new projects.
improve the results. • For hidden failures RCM uses “risk-
• The use of untrained analysts slowed based” decision criteria. For an electric
progress substantially on a few of their utility where there is a great deal of
projects. redundancy there are many hidden
• Careful planning is critical to success. failures with purely operational
Analysts needed the training. It was consequences. Electrical equipment
important to make sure the people with and systems are often designed to “fail
the greatest knowledge of specific safe” so the risk-based approach was
assets were trained in time for their confusing. Additional operational
scheduled projects. criteria were developed for use in these
• They found it challenging for unique, but plentiful circumstances.
equipment specialists to begin looking
at systems from a systems’ perspective. For all the effort and the learning curve there is a
Engineers and technicians used to substantial payback. The commercial airline
industry saw huge gains in reliability and safety.
9 Toronto Hydro saw an average of 22% cost
Terry Wireman, Genesis Solutions, presented at
MARTS, 2005. reductions over their two years of analysis work.

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 4
Initially they experienced 34% from their 10 equipment from water drips. The guard had
pilot projects – of course they had picked “high been installed early in the life of the plant when
value” targets in order to really test the value of the air conditioning system used chilled water
RCM. The Canadian Navy, using an earlier and un-insulated pipes. Condensate drips were a
military-version of RCM experienced substantial problem in those early days. The air
gains in ship availability from 60% to 70%, conditioning system had been replaced some 10
maintenance cost reductions estimated by the years prior to the analysis and the drips
author to be on the order of CAD 200 million eliminated. Unfortunately they didn’t eliminate
and the avoidance of CAD 2 billion in capital the guard at the same time! No one had
costs. They replaced 14 ships with only 12 due questioned its function. For 10 years, they
to the increase in ship availability that RCM continued removing and replacing it in order to
delivered. GE Plastics in the Netherlands saw do maintenance work on the towel line. That
MTBF on their critical manufacturing systems added 8 hours of downtime to each repair and it
increase from 8 hours to 80 days, 50% cost happened about once every two weeks. Over 10
reductions and a 30% staff reduction in years that amounted to roughly 2,080 hours of
maintenance (they were clearly over- downtime on an otherwise very profitable
maintaining). production line. There were also several other
towel lines with the same sort of guard. They
Note that staff reductions don’t necessarily mean removed all the guards after their first RCM
layoffs and job losses. In the author’s team meeting and never replaced them! There
experience, employees are usually re-assigned to are other examples like this. Nearly everyone
other valuable work that was not being done due the author has met who has done RCM analysis
to the pressures to keep the formerly unreliable work, has had a similar experience from learning
assets running. In North America the ability of more about their installed assets.
RCM to reduce the amount of work required is
part of the solution to an increasingly serious RCM is not cheap. Training is provided to
problem with demographics. The pending analysts and facilitators. The pilot projects must
retirement of much of its aging work force will be planned carefully. The analysts’ time must be
leave many companies scrambling for talent that scheduled and in some cases replacements for
is increasingly unavailable and poorly qualified those analysts must be found – at least part of the
for the available jobs. There are fewer people in time. Facilitators can work on RCM full time
the younger generations and they have largely but then their replacements are required on a full
opted out of careers in the trades. time basis, at least for the time when the analysis
projects are in progress. Once the facilitators are
RCM takes time. A large facility such as a fossil trained they require mentoring. Most facilitators
fuel power plant (e.g.: Castle Peak in Hong are not comfortable in their new roles until they
Kong) required 18 months to analyze all of its have done one or two full analyses backed up by
systems in a concerted effort. Toronto Hydro an experienced mentor who trained them. The
has taken 2 years for most of its assets, GE training, planning support and mentoring are all
Plastics took 2.5 years, the Canadian Naval provided by consultants, highly trained
project was almost 4 years but it ran in parallel specialists who are in demand and don’t come
with the design effort. Fortunately, the benefits cheaply. And then there is the cost of the time
and payback begin to materialize early. As required to do the analysis work. For example, a
Toronto Hydro discovered, it is common for large facility with over 100 system projects, each
companies to discover a great deal about their requiring 10 to 15 meetings (average 12.5) of 3
physical assets that they didn’t already know. hours each and a team of 4 people requires
This can lead to substantial savings and other 15,000 man hours (about 8 man years) of effort.
benefits. Toronto Hydro paid approximately CAD
272,000 for the external support, training and
The author worked with one paper making their analysts’ time. Their payback was large –
company in the southern USA on a paper towel they had an internal rate of return on that
converting line. They discovered that the investment of 180% over 10 years. The costs
function of a large guard was to protect the

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 5
were covered in a few months and the benefits those assets running well and within product
are returned over many years. quality standards and limits. Those limits on
say, control systems and tolerances, are used as
The most obvious benefit or value to business is desired standards of performance when defining
generated by the increased reliability and system functions. Failure to meet those
availability of the physical assets that are standards, no matter how minor, is treated as a
analyzed. Assets running longer and with fewer functional failure and proactive steps are taken to
breakdowns produce more. If you can sell avoid the consequences. Where product quality
everything you can make, then you generate problems can lead to product liability issues
more revenue. If you are market constrained, RCM helps avoid them. Pharmaceutical and
then you can’t sell any more produce (or food companies use highly automated processes
service). You can still benefit from reducing the to maintain stringent product quality tolerances.
total capacity of physical assets required to Keeping to tolerances on packaging lines means
deliver what you can sell. In the case of several that you won’t deliver less than you are stating
mining companies it has been possible to “park” on the packaging and it keeps the over-fill to an
haul trucks that were no longer needed because absolute minimum. That keeps you from giving
the remaining fleet availability provided the away product for free. Keeping product within
needed hauling capacity. This saved them both its spec limits means less scrap, less waste and
operating and maintenance costs and brought in less risk of product that is out of spec (and
revenue from the resale of their excess fleet. In a potentially dangerous) from making its way into
plant environment where it is practical to shut the market place. This can also help to reduce
down for one or more shifts, it may be possible product risk liability and insurance premiums.
to increase shift production and reduce the
number of required shifts. Utilities delivering electricity, gas and water to
customers strive keep their product within
RCM reduces the overall maintenance effort. If tolerances on voltage, cycles and pressure.
you are over-maintaining, as utilities and others Imagine the insurance payout if a water utility
with a strong reliability culture often do, then over-pressurized water mains in a large city or
you can reduce your Preventive Maintenance failed to deliver water in the event of a major
program budget. If you are under-maintaining, fire. What if a gas utility over-pressurized its
then you are probably doing more repairs than mains? Electrical voltage spikes can also
you need to. By determining the right amount of damage a great deal of equipment. Keeping
proactive maintenance you can eliminate failures within these various tolerances is important –
and the repair costs associated with them. For RCM helps.
example, elimination of overhaul work where
failure pattern F is present will eliminate A business operating reliably is able to forecast
premature failures. Doing more condition its revenues more accurately. The financial
monitoring where random failures are most industry appreciates this consistency and
common (patterns D, E and F) will catch failures predictability. Banks will provide more
that have begun, but not yet progressed to the favorable loan conditions to reliable businesses.
fully functional failed state. This will eliminate The author knows one Canadian bank that
costly breakdown repairs. The discovery of already makes these offers if RCM is used.
hidden failures through regular testing will Stock market analysts treat reliable businesses
eliminate situations where the backup or safety more favorably making it easier to raise capital
system fails to operate. This invariably means a in the investment markets. Insurance companies
less expensive repair and avoidance of the cost will see the reduced claims potential and reduce
of downtime when the primary device eventually premiums. The author knows of at least two
fails. major global insurers who have done this for
major global clients. In one case the premium
RCM also reduces other, less quantifiable reduction for a global mining company was $US
business risks. Product quality and continuity of 2 million per year on their business loss
service is often highly dependent on the smooth insurance. And in some other cases, previously
running of your physical assets. RCM keeps uninsurable risks can become insurable.

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 6
result in reductions in insurance premiums for
Warranties are another area of benefit to workers’ compensation coverage.
business. Manufacturers usually offer a warranty
on materials and workmanship for new assets Environmental non-compliance can result in
and the cost of that is built into their products. fines, partial or total shut down of operations. In
They also offer, for an additional cost, an some extreme cases the license to operate can be
extended warranty that covers a wider range of revoked. RCM helps to avoid these fines and
potential problems. Those warranties can cost shutdown related losses and to keep you in
on the order of 2 – 3 % of the capital outlay for business. Like safety, environmental
the asset. If RCM is used to develop your consequences are dealt with proactively and
maintenance program, then the asset is far less strictly – run-to-failure is not an option. It is no
likely to fail and therefore it is far less likely you accident that the nuclear power industry uses
will have an opportunity to make a warranty RCM extensively!
claim. If you don’t mind accepting the risk, you
can negotiate you’re your suppliers and save Regulatory agencies enforce rules that are meant
your company 2 – 3 % on the capital costs of to ensure compliance to minimum standards.
new asset acquisitions. That’s usually enough to They are society’s way of telling us what it will
pay for the RCM analysis effort for a Greenfield tolerate before taking punitive action against
application and the risks are largely eliminated. your company. Regulations are most commonly
applied where safety and the environment are
In other cases, you might choose to pay the concerned. Even product safety considerations,
warranty costs and negotiate with the as in the pharmaceuticals and food, give rise to
manufacturer to allow you to use your extensive regulations. For example, in those
maintenance program rather than the one they industries calibration programs are mandated and
recommend while they still honor the warranty if strictly enforced. Typically, the regulations
you make any claims. One coal mining require you to meet a certain minimum standard
company did this and the manufacturer was but fall short of specifying what to do to and how
happy to comply with their request. The mining to do it. Those choices are left up to you.
company used their RCM maintenance program Inspectors for the regulatory agencies, like those
and they never made a claim! for insurance companies and safety agencies,
have a great deal of discretion in judging how
Safety is where RCM got started and it is an area well you are complying with the regulations.
where RCM excels. Safety is built into the RCM RCM is a very solid methodology for
decision logic criteria and the “run-to-failure” determining how to meet regulatory
option is not available if safety is in jeopardy. requirements. Those requirements are treated as
Most industrial accidents happen during functions of the asset and any failure to comply
maintenance or due to failures of physical assets. is handled in the analysis quite easily. RCM
Failures resulting in safety hazards are dealt with produces extensive documentation that can be
proactively. The overall reduction of used to back up your maintenance program. It
maintenance work that is required and the enables you to show deliberate proactive effort to
emphasis that RCM gives to condition comply backed up with a bullet-proof logic for
monitoring techniques (which are usually non- the choices you make. Regulators seldom have
intrusive) means less exposure to risk for the knowledge to disagree with your program.
maintainers. The reductions in failures mean In the unlikely and unfortunate event that
fewer repairs and again, less exposure to risk. something does go wrong, you can also use the
Safety performance is enhanced over time documentation as evidence that you did
following the implementation of programs everything you could to avoid the problem. Of
developed using RCM. The experience of the course you must also show that you complied
airline industry is perhaps the most graphic with the maintenance program requirements you
example of the safety benefits of RCM. The developed using RCM for this to work!
benefits to safety do not go un-noticed.
Improved safety performance over time will also

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 7
In summary, RCM is a well proven methodology cycle management and analysis, diagnostic
to deliver a great deal of value to business in a assessments, benchmarking for best practices,
wide range of areas: business process design and enterprise asset
• Increased output management systems. James has been published
• Reduced maintenance costs in several books as a co-author, a contributing
• Reduction of production loss author and is the author of numerous articles
(opportunity costs) published in several periodicals. He is presently
• Improved product quality and service authoring the 2nd edition of the popular book on
level compliance maintenance management, “Uptime, Strategies
• More predictable business performance for Excellence in Maintenance Management”.
• Favorable treatment by lending
institutions – better loan terms Prior to founding his company, James was leader
• Favorable treatment by insurers – of the global Enterprise Asset Management
reduce premiums practice of IBM Business Consulting Services
• Favorable treatment by manufacturers – (formerly known as PwC Consulting,
reduce or eliminate extended warranty PricewaterhouseCoopers and Coopers &
costs Lybrand). He has worked as a Marine Engineer
• Improved safety performance in the Canadian Navy, a specialist machinery
• Improved environmental compliance engineer with Exxon Chemicals in Canada, the
• Defensible and auditable maintenance Maintenance and Support Planning Manager for
program to satisfy regulators a large warship design and construction project
and Logistics Support Manager for both
RCM delivers. The reader is encouraged to Helicopter and Microwave Landing Systems
explore the topic further and to consider RCM as projects. His industry experience includes:
a key strategic initiative for any company that aerospace, automotive, brewing, computers,
relies on physical assets in carrying out its consumer goods manufacturing, defense, electric
business. power utility (generation, transmission,
distribution), facilities management, forest
About the Author products, gas processing and transmission, health
care, higher education, marine, metals, mining,
James V. Reyes-Picknell, P.Eng. oil & gas (upstream, refining), petrochemical,
pharmaceutical and postal services and water /
James V. Reyes-Picknell is founder and waste water utilities.
President of Conscious Asset Management of
Toronto, Canada. He provides consulting in the
field of physical asset / maintenance
management. His services span strategy,
operations, process improvement and executive
development. James is a licensed professional
engineer, an Aladon certified RCM II
practitioner, honors graduate of the University of
Toronto in Mechanical engineering (1977). He
has studied at the Royal Navy Engineering
College, Technical University of Nova Scotia
and Dalhousie University. His career in
operations and maintenance spans 28 years, 10
of those in physical asset and maintenance
management consulting.

James’ experience includes plant, fleet and


facility maintenance, strategy development and
implementation, reliability management and
engineering, spares and operating supplies, life

© 2006, Conscious Asset Management


+1-705-431-6598 www.consciousasset.com james@consciousasset.com 8

You might also like