You are on page 1of 5

CONVEYANCE CHARGES AS PER SOR 2011-12

KM

SAND/
GRAVEL

METAL

BRICKS

KM

SAND/GRAVEL/
METAL

BRICKS

KM

SAND/GRAVEL
/METAL

23.80

21.40

35.68

41

387.90

582.69

81

703.90

33.30

30.00

49.95

42

395.80

594.58

82

711.80

44.50

44.50

66.61

43

403.70

606.47

83

719.70

54.00

54.00

80.88

44

411.60

618.36

84

727.60

63.50

63.50

95.15

45

419.50

630.25

85

735.50

73.00

73.00

109.42

46

427.40

642.14

86

743.40

82.50

82.50

123.69

47

435.30

654.03

87

751.30

92.00

92.00

137.96

48

443.20

665.92

88

759.20

101.50

101.50

152.23

49

451.10

677.81

89

767.10

10

111.00

111.00

166.50

50

459.00

689.70

90

775.00

11

120.50

120.50

180.77

51

466.90

701.59

91

782.90

12

130.00

130.00

195.04

52

474.80

713.48

92

790.80

13

139.50

139.50

209.31

53

482.70

725.37

93

798.70

14

149.00

149.00

223.58

54

490.60

737.26

94

806.60

15

158.50

158.50

237.85

55

498.50

749.15

95

814.50

16

168.00

168.00

252.12

56

506.40

761.04

96

822.40

17

177.50

177.50

266.39

57

514.30

772.93

97

830.30

18

187.00

187.00

280.66

58

522.20

784.82

98

838.20

19

196.50

196.50

294.93

59

530.10

796.71

99

846.10

20

206.00

206.00

309.20

60

538.00

808.60

100

854.00

21

215.50

215.50

323.47

61

545.90

820.49

101

861.90

22

225.00

225.00

337.74

62

553.80

832.38

102

869.80

23

234.50

234.50

352.01

63

561.70

844.27

103

877.70

24

244.00

244.00

366.28

64

569.60

856.16

104

885.60

25

253.50

253.50

380.55

65

577.50

868.05

105

893.50

26

263.00

263.00

394.82

66

585.40

879.94

106

901.40

27

272.50

272.50

409.09

67

593.30

891.83

107

909.30

28

282.00

282.00

423.36

68

601.20

903.72

108

917.20

29

291.50

291.50

437.63

69

609.10

915.61

109

925.10

30

301.00

301.00

451.90

70

617.00

927.50

110

933.00

31

308.90

308.90

463.79

71

624.90

939.39

111

940.90

32

316.80

316.80

475.68

72

632.80

951.28

112

948.80

33

324.70

324.70

487.57

73

640.70

963.17

113

956.70

34

332.60

332.60

499.46

74

648.60

975.06

114

964.60

35

340.50

340.50

511.35

75

656.50

986.95

115

972.50

36

348.40

348.40

523.24

76

664.40

998.84

116

980.40

37

356.30

356.30

535.13

77

672.30

1010.73

117

988.30

38

364.20

364.20

547.02

78

680.20

1022.62

118

996.20

39

372.10

372.10

558.91

79

688.10

1034.51

119

1004.10

40

380.00

380.00

570.80

80

696.00

1046.40

120

1012.00

75945805.xls.ms_office

BRICKS

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS


(including idle hire charges of trucks )

Sl No.

Rubble/
Earth /
size
Sand
stone/ cut
brick
/Gravel
Descriptio
stone/ cement in steel in
work
n of item Murrum/ Coarse Rs/tonne Rs./tonne Rs/1000
No
/ Surki/ aggregate
, Lime in
Rs / cum Rs/cum
2
3
4
5
6
7

Loading

76.50

88.00

109.90

117.60

149.90

Unloading

27.40

44.00

109.90

117.60

149.90

Note: The lead & lift charges are inclusive of 14% Contractor Profit and
Over Head charges.

E.LOADING AND UNLOADING CHARGES BY MECHANICAL


MEANS (including idle hire charges of trucks)

Sl No.

Earth / Sand
Descriptio
/Gravel/Murrum/ /
n of item
Surki/ Rs / cum

Rubble/ size stone/


cut stone/ Coarse
aggregate, Lime in
Rs/cum

Loading

38.10

75.70

Unloading

12.00

12.00

Note: The lead & lift charges are inclusive of 14% Contractor Profit and
Over Head charges

75945805.xls.ms_office

HIRE CHARGES OF PLANT& MACHNIERY FOR


ROAD & BRIDGE WORKS FOR THE YEAR 2011-12
Description

Sl. No.
1
1

Machine
2
Dozer( D 80 )

Mortor Grader

Hydraulic Excavator

Front end loader

Tipper- 5.5 Cum

Vibratory roller 8 tonne

Smooth wheeled roller 8


tonne
Water tanker 6 Kilolitre
Tractor
Tractor with rotavator
Tractor with ripper
attachment
Air Compressor
Wet mix plant 60 TPH
Mechanical broom
Hydraulic
Bitumen Pressure
Distributor

8
9
10
11
12
13
14
15
16
17

Emulsion Pressure
Distributor
Hot mix Plant 120 TPH
capacity

18

Hot mix Plant 100 TPH


capacity

19

Hot mix Plant 60 TPH


capacity

20

Hot mix Plant 40 to 60


TPH capacity

Unit

Activity
3
Spreading
Cutting
Cleaning
Clearing
Spreading
GSB
WMM
Soil Ordinary
Soil Marshy
Soil unsuitable
Soil loading
Aggregate loading
Transportation of soil,
GSB,WMM, Hot mix
etc

SoRate for
2011-12
( Rupees)

4
Per Hour

5
1881.00

Per Hour

2600.00

Per Hour

2009.50

Per Hour
Per Hour
Per Hour
Per tonne
Km
Per Km
Per Hour

1320.00

Per Hour

844.40

Per
Per
Per
Per

Hour
Hour
Hour
Hour

345.00
345.00
345.00
345.00

General purpose
Wet mix
Surface cleaning

Per Hour
Per Hour
Per Hour

370.00
1320.00
290.00

Applying bitumen tack


coat

Per Hour

940.00

Applying emulsion
tack coat
DBM/BM/SDC
/Premix
DBM/BM/SDC
/Premix
DBM/BM/SDC
/Premix
DBM/BM/SDC
/Premix

Per Hour

690.00

Per Hour

23000.00

Per Hour

19550.00

Per Hour

17250.00

Per Hour

15525.00

Earth/Soil, GSB,
WMM
Soil compaction ,BM
compaction
Water transport
Pulling
Scarifying
Scarifying

Page 3 of 5

696.40

1886.90

HIRE CHARGES OF PLANT& MACHNIERY FOR


ROAD & BRIDGE WORKS FOR THE YEAR 2011-12
Description

Sl. No.

23
24

Machine
2
Paver Finisher Hydrostatic
with sensor control 100
TPH
Paver finisher Mechanical
100
Hydraulic Chip Spreader
Tandem Road roller

25

Pneumatic Road roller

26
27
28
29
30

Pot-Hole repair machine


Bitumen boiler oil fired
GSB Plant 50 Cum
Mastic Cooker
Batching and Mixing Plant
(a) 30 Cum capacity

1
21

Unit

Activity
3
DBM/BM/SDC
/Premix

SoRate for
2011-12
( Rupees)

4
Per Hour

5
2530.00

Paving of WMM,
paving of DLC
Surface dressing
Rolling of Asphaltic
surface
Rolling of Asphaltic
surface
Repair of pot-holes
Bitumen Spraying
Producing GSB
Mastic wearing coat
Concrete mixing

Per Hour

1090.00

Per Hour
Per Hour

2070.00
1320.00

Per Hour

1035.00

Per
Per
Per
Per
Per

Hour
Hour
Hour
Hour
Hour

750.00
170.00
920.00
52.00
2130.00

(b) 15 - 20 Cum capacity

Concrete mixing

Per Hour

1670.00

31

Transit mixer

Per Hour

1467.20

32

Concrete pump of 45 and


30 cum
Cranes
(a) 80 tonnes
(b) 35 tonnes
(c) 3 tonnes
(d)Crane with grab bucket
0.75 cum
(e)Crane with grab bucket
1 cum
Concrete bucket
Kerb casting machine

Transportation of
concrete mix
Pumping of Concrete

Per Hour

630.00

Lifting purpose

Per Hour

Well foundation

Per Hour

950.00
630.00
280.00
1725.00

Well foundation

Per Hour

2875.00

For pouring concrete


Kerb making

Per Hour
Per Hour

12.80
250.00

Concrete mixing
Concrete mixing
0.75 m dia to 1.20 m
dia boring attachment

Per Hour
Per Hour
Per Hour

345.00
520.00
4485.00

Paving of concrete
Per Hour
surface
Crushing of spalls 100 Per Hour
TPH
Crushing of spalls 200 Per Hour
TPH
Stressing of steel
Per Hour
wires/ stands

2360.00

22

33

34
35
36

37
38
39

40

Concrete mixer
(a)0.28 cum
(b) 1.0 cum
Piling rig with bantonite
pump
Concrete paver finisher
with 40 HP motor
Integrated stone crusher

Pre stressing jack with


pump and access

Page 4 of 5

7070.00
14880.00
110.00

HIRE CHARGES OF PLANT& MACHNIERY FOR


ROAD & BRIDGE WORKS FOR THE YEAR 2011-12
Sl. No.
1
41

42
43

44
45

Description
Machine
2
Generator
250 KVA
125 KVA
100 KVA
35 KVA
Pneumatic sinking of
Plants
Truck 5.5 cum per 10
tonnes

Unit
Activity
3

Generation of electric
energy

Pneumatic sinking of
wells
Material transport
Material transport

Road marking machine


Mobile slurry seal
equipment
Plate compacter

SoRate for
2011-12
( Rupees)

4
per
per
per
per
Per

hour
hour
hour
hour
K.m.

Per Km.
Per tonne
per km
Per Hour
Per Hour

5
1550.00
1090.00
920.00
620.00
3740.00
45.00
4.50

90.00
Road marking
920.00
Mixing and laying
slurry seal
40.00
46
For compacting in
Per Hour
medians
1035.00
47
Drilling equipment
For drilling
Per Hour
Note: The above hire charges of machinery & plant includes crew, oils, conveyance
of machinery to site and all other incidental charges.

Page 5 of 5