You are on page 1of 164

THDCINDIA LIMITED

Environmental Studies for Vishnugad Pipalkoti Hydro Electric Project

Final Report

Environmental Management Plan (EMP)


(Volume II)

November 2009
CONSULTING ENGINEERING SERVICES ( INDIA ) PRIVATE LIMITED
57, Manjusha Building (5th Floor), Nehru Place New Delhi - 110 019

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Table of Contents

Page:1 Date: Nov 2009 Revision: R4

TABLE OF CONTENTS
Page #

Volume II
4.0 Environmental Management Plan (EMP) ................................................................... 1 to 135 4.1 4.2 4.3 Objective of the EMP ...................................................................................................4-2 Environmental Management process ...........................................................................4-2 Institutional & Implementation Arrangement ................................................................4-3 4.3.1 Activities within Project Area.............................................................................4-3 4.3.2 Activities in the Project Influence Area .............................................................4-5 4.3.3 Activities in the Catchment ..............................................................................4-6 Biodiversity Management..............................................................................................4-9 4.4.1 Conservation Plan of Project Influence Area ....................................................4-9 4.4.2 Conservation Plan of Project Affected Area ...................................................4-10 4.4.3 Compensatory Afforestation Plan ...................................................................4-11 4.4.4 Budget for Biodiversity Management..............................................................4-12 Catchment Area Treatment Plan ................................................................................4-13 4.5.1 Need for Catchment Area Treatment..............................................................4-13 4.5.2 Project area in the CAT Plan ..........................................................................4-13 4.5.3 Objective of the CAT Plan ..............................................................................4-14 4.5.4 Plantation in the Reserved Forest Areas ........................................................4-16 4.5.5 Plantation in the Civil Soyam and Van Panchayat Areas ...............................4-16 4.5.6 Drainage Line Treatment & Soil Conservation Work ......................................4-17 4.5.7 Wildlife/ Biodiversity Protection Works ...........................................................4-17 4.5.8 Responsibility of Forest Department.............................................................. 4-18 4.5.9 Responsibility of THDC ..................................................................................4-19 4.5.10 Financial Provision for CAT Plan ....................................................................4-19 4.5.11 Agencies involved in the Implementation of the Plan .....................................4-20 Muck Disposal Management Plan ..............................................................................4-22 4.6.1 Introduction.....................................................................................................4-22 4.6.2 Excavation of Muck and its Disposal ..............................................................4-22 4.6.3 Muck Disposal Sites .......................................................................................4-23 4.6.4 Conclusion......................................................................................................4-26 4.6.5 Planning & Management of Muck Disposal ....................................................4-29 4.6.6 Budget ...........................................................................................................4-32 4.6.7 Recommendations .........................................................................................4-33 Fish Management Plan ...............................................................................................4-33 4.7.1 Characteristics of Endangered Fish................................................................4-33 4.7.2 Sustenance of Fisheries .................................................................................4-33 4.7.3 Management Measures ..................................................................................4-33 4.7.4 Proposed Budget for Fish Management .........................................................4-35 4.7.5 Recommendations..........................................................................................4-36 Greenbelt Development Plan.....................................................................................4-37

4.4

4.5

4.6

4.7

4.8

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Table of Contents

Page:2 Date: Nov 2009 Revision: R4

Page #

Volume II
4.8.1 Species Suggested for Plantation ..................................................................4-37 4.8.2 Precautionary Measures.................................................................................4-38 4.8.3 Budget for Greenbelt Development Plan ........................................................4-38 Soil Erosion & Sediment Control.................................................................................4-40 Quarry & Borrow Area Management...........................................................................4-41 Solid Waste Management...........................................................................................4-43 Management Measures for Road Construction ..........................................................4-45 Construction Camp & Construction Workers ..............................................................4-50 4.13.1 Sanitation Facilities.........................................................................................4-50 4.13.2 Provision of Fuel.............................................................................................4-51 4.13.3 Other Facilities................................................................................................4-51 Public Health Delivery System....................................................................................4-52 4.14.1 Development of Medical Facilities ..................................................................4-52 4.14.2 Proposed Health Facilities at Construction Sites & Labour Camp ..................4-52 4.14.3 Health Extension Activities .............................................................................4-53 4.14.4 Budget for Public Health Delivery System ......................................................4-53 Responsibility Matrix ...................................................................................................4-55 Environmental Monitoring Plan ..................................................................................4-75 4.16.1 Introduction.....................................................................................................4-75 4.16.2 Water Quality .................................................................................................4-75 4.16.3 Ambient Air Quality & Meteorology.................................................................4-76 4.16.4 Noise ..............................................................................................................4-77 4.16.5 Ecology...........................................................................................................4-77 4.16.6 Soil Erosion & Siltation ...................................................................................4-77 4.16.7 Incidence of Water Related Diseases.............................................................4-78 4.16.8 Land Use ........................................................................................................4-78 4.16.9 Environmental Monitoring Budget...................................................................4-79 4.16.10 Adaptive Environmental Management Requirement .....................................4-80 Good Practices ...........................................................................................................4-82 4.17.1 Landscaping & Re-vegetation.........................................................................4-82 4.17.2 Vegetation Clearing ........................................................................................4-82 4.17.3 Loading & Removal of Waste Forestry Products ............................................4-83 4.17.4 Storage, Handling & Emergency Response for Hazardous Chemical ......................................................................................4-84 4.17.5 Emission & Dust Control.................................................................................4-86 4.17.6 Environmental Training for Construction Workers ..........................................4-86 4.17.7 On-site Traffic & Access Management ...........................................................4-87 4.17.8 HIV/AIDS Prevention Measures .....................................................................4-88 Capacity Building of THDC .........................................................................................4-89 4.18.1 Environmental Management measures taken by THDC ..................................4-89 4.18.2 ISO 14001 Environment Management System ................................................4-90 4.18.3 OHSAS 18001..................................................................................................4-98

4.9 4.10 4.11 4.12 4.13

4.14

4.15 4.16

4.17

4.18

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Table of Contents

Page:3 Date: Nov 2009 Revision: R4

Page #

Volume II
4.18.4 Safety Manual of THDC....................................................................................4-98 4.18.5 Corporate Social Responsibility......................................................................4-104 4.18.6 Disaster Management Plan ............................................................................4-107 4.18.7 Adaptive Capacity Development ....................................................................4-112 4.18.8 Institutional Setup and Capacity Building .......................................................4-115 4.18.9 Training for Environmental Staff .....................................................................4-123 4.18.10 Budget for Capacity Building ........................................................................4-130 4.18.11 Lesson Learnt by THDC ..............................................................................4-133 4.19 Budget for Implementation of EMP.....................................................................................4-135

LIST OF ANNEXES Annex-4.15.1 Annex-4-18.1 Annex-4-18.2 Annex-4-18.3 Annex-4.19.1 Forms for Environmental Management Plan ISO 14001:2004 Requirements Organizational Setup of THDC Details of Training Program attended by VPHEP Staff EMP Implementation Schedule

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Table of Contents

Page:4 Date: Nov 2009 Revision: R4

LIST OF TABLES
Table-4.4.1 Table-4.4.2 Table-4.5.1 Table-4.5.2 Table-4.5.3 Table-4.6.1 Table-4.6.2 Table 4.7.1 Table 4.7.2 Table 4.7.3 Table-4.8.1 Table-4.8.2 Table-4.10.1 Table-4.10.2 Table-4.11.1 Table-4.12.1 Table-4.13.1 Table-4.13.2 Table-4.13.3 Table-4.14.1 Table-4.15.1 Table-4.15.2 Table-4.15.3 Table-4.16.1 Table-4.16.2 Table-4.16.3 Table 4.17.1 Table-4.18.1 Table-4.18.2 Table 4.18.3 Table-4.18.4 Table-4.18.5 Table-4.18.6 Species Suggested for Plantation under Compensatory Afforestation Plan Year wise Budget for Biodiversity Management Land Use Classification in Revised Catchment Area Treatment Plan (in Ha) Financial Provision for Eco-restoration Year wise Financial Target for Ecorestoration Capacity and Location of Disposal Area Budget for Implementation of Muck Disposal Plan Components for Hatchery Development for VPHEP Proposed budget by Dept of Fisheries, Govt. of Uttarakhand Budget for Fish Management Species Suggested for Plantation under Greenbelt Development Plan Budget for Greenbelt Development Plan Species Suggested for Slope Stabilization Cost Estimate for Restoration of Quarry Sites Budget for Solid Waste Management Budget for Implementation of EMP Measures for Road Construction Budget for Sanitary Facilities for Labour Camps Cost Estimate for LPG Distribution Cost Estimate for Kerosene Distribution Budget for Public Health Delivery System Environmental Management Measures & Responsibilities - Pre-construction Stage Environmental Management Measures & Responsibilities - Construction Stage Environmental Management Measures & Responsibilities Operation Stage Summary of Environmental Monitoring Programme during Construction Phase Summary of Environmental Monitoring Programme during Operation Phase Budget for Environmental Monitoring Programme Responsibility for AIDS/HIV Protection Water Depth and Spread Downstream of Dam in the event of Dam Break List of Villages which will be affected in case of Dam Failure Budget for Adaptive Capacity Development Projects under THDC within India Overseas Projects under THDC Comparative Strength of THDC with National & International Hydropower Companies Table-4.18.7 Qualification of Environmental Staff in the five units in Corporate Division in S&E Department Table-4.18.8 Future Environmental Manpower required for various Projects Table-4.18.9 Trainings Identified for Environmental Management Table-4.18.10 List of the Power Sector Training Institutes Recognized by CEA Table-4.18.11 Training Institutions that can be contacted for Capacity Building Table-4.18.12 Year wise Estimate for Environmental Training Table-4.18.13 Proposed Tentative Capacity Building Budget for VPHEP Table-4.18.14 Tentative Estimate for Environmental Training Table-4.19.1 Summary of EMP Budget

Environmental Management Plan


4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9

Objective of the EMP ..................................................................................2 Environmental Management Process.......................................................2 Institutional & Implementation Arrangement .....................................3 Biodiversity Management..........................................................................9 Catchment Area Treatment Plan ............................................................13 Muck Disposal Management Plan..........................................................22 Fish Management Plan .............................................................................33 Greenbelt Development Plan ...................................................................37 Soil Erosion & Sediment Control............................................................40

4.10 Quarry & Borrow Area Management.....................................................41 4.11 Solid Waste Management ........................................................................43 4.12 Management Measures for Road Construction....................................45 4.13 Construction Camp & Construction Workers ......................................50 4.14 Public Health Delivery System ...............................................................52 4.15 Responsibility Matrix...............................................................................55 4.16 Environmental Monitoring Plan.............................................................76 4.17 Good Practices ...........................................................................................82 4.18 Capacity Building of THDC.....................................................................89 4.19 Budget for Implementation of EMP ....................................................135

Environment & Ecology Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:2 Date: Nov 2009 Revision: R4

4.1

OBJECTIVE OF THE EMP Environmental Management Plan (EMP) is the key to ensure a safe and clean environment. The desired results from the environmental mitigation measures proposed in the project may not be obtained without a management plan to assure its proper implementation & function. The EMP envisages the plans for the proper implementation of mitigation measures to reduce the adverse impacts arising out of the project activities during pre-construction, construction and operation stage. EMP has been prepared addressing the issues like: Institutional and Implementation Arrangement Biodiversity Management Catchment Area Treatment Plan Muck Disposal Management Plan Fishery Management Plan Greenbelt Development Plan Soil Erosion and Sediment Control Quarry and Borrow Area Management Solid Waste Management Management Measures for Road Construction Construction Camp & Construction Workers Public Health Delivery System Environmental Monitoring Plan Improving Environmental Management Capacity of THDC ISO 14001 Management System EMP Budget

4.2

ENVIRONMENTAL MANAGEMENT PROCESS For environmental management, the typical management principles of ISO 14000 can be used in setting objectives & targets and providing a framework for review and continual improvement. The environmental management process consists of:
Continual Improvement

Environmental Policy

Review & Improvement

Planning

Checking & Corrective Action

Implementation

Figure-4.1 Environmental Management Process

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:3 Date: Nov 2009 Revision: R4

Defining an environmental policy Developing plans for environmental management Implementation of the EMP Monitoring the EMP & incorporating corrective action Review of the policy, EMP and improvement 4.3 INSTITUTIONAL & IMPLEMENTATION ARRANGEMENT 4.3.1 Activities within Project Area THDC has a Social and Environmental Department at Corporate level to take care of environmental and social aspects. It is proposed to form an Environmental Management Cell (EMC) at project level for VPHEP. The EMC will handle all issues related to different environmental attributes, it will be responsible for overall environmental and social management in project being undertaken by THDC from investigation level to execution at project level. The activities within project area having major impact on environment will be land acquisition, felling of trees, clearing of land for construction work, establishing of construction camps, construction of project facilities and Operation of the project on completion of work Implementation of management measures for impacts related to forest and tree felling is the joint responsibility of THDC and State Forest Department. Compensatory Afforestation Plan (CAP) will be implemented by State Forest Department. Muck / Quarry Area Redevelopment Plan, Avenue Plantation and Landscaping will be implemented by THDC. Implementation of management measures for construction and operation phase of the project is responsibility of project Contractors and THDC respectively. Wherever contractors are involved, they will be responsible to implement mitigation measures and THDC will monitor the implementation program. THDC Environment Management Cell (EMC) The EMC of THDC will be responsible for the technical planning, implementation and monitoring of all environmental mitigation and compensation measures under THDCs responsibility outlined in EMP. The EMC will monitor mitigation measures that will be implemented by Contractor to ensure compliance with Constructors Contract (CC). The EMC will work closely with the State Pollution Control Board (SPCB) and MoEF, as appropriate. EMC will prepare regular reports for submission to SPCB and MoEF. The reports will address the following items:

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:4 Date: Nov 2009 Revision: R4

Progress made to implement the environmental mitigation measures in compliance with EMP and the CC. Schedule of implementation of environmental mitigation measures Difficulties with implementing the environmental mitigation measures and recommendation to solve the problems Any aspect that does not conform to the environmental mitigation measures and proposed remedial measures. Prior to the start of construction, the EMC will ensure the following: The relevant environmental mitigation measures are reflected in the project contract Discussion with the government authorities participating in the project to develop procedures for inter-agency coordination and reporting Construction phase activities include appropriate environmental monitoring During the construction and the operating phases, THDC, through the EMC, will be responsible for Implementing and monitoring environmental mitigation measures. The management of environment concern will include: Developing and implementing the monitoring programs; Managing the subcontracts for specialist studies to ensure their performance Liaising and cooperating with the government authorities Preparing work and cost schedules for the monitoring programs Conducting appropriate testing to ensure that the environmental mitigation measures are effective Arranging for reporting of the results of the monitoring programs Maintaining records for reporting to SPCB and MoEF Conducting internal and external audits to ensure compliance with the EMP and the procedures of THDC, The Construction Contractors The contractor will be responsible for implementation of measures to avoid or minimize environmental impacts during construction period. These will include protection measures relating to: Meeting effluent standards before discharging into surface water Managing waste at construction sites Location of construction camps at proper place - away from Forest Area and Settlements Arrange fuel for the construction camp no tree cutting for fuel and hut making for the camp Manage erosion and sedimentation in construction area Managing onsite traffic- provide diversion signs/flags/guard along approach road

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:5 Date: Nov 2009 Revision: R4

Control noise emissions Control dust and fugitive emission. Managing, preventing and developing emergency plans for chemical pollution incidents. Implementing a health program for all persons engaged in undertaking construction works. The contract between THDC and the Construction Contractor must include the Contractors obligations for undertaking measures to minimize and/or to mitigate impacts on the existing environment and social components. The constructions contractors contract must cover all the protection measures listed above and will be required to contain an over view of the project impacts that the contractors work will have on the physical, biological and social environment and including: Details of environment control to be implemented in accordance with the requirements of the Constructors Contract. Statutory requirements including approvals and licenses Location of environmental control works Timing of environmental control activities Assignment of responsibility to implement, maintain, asses and monitor each environmental control Procedures and instructions to implement, maintain, asses and monitor each environmental control Reporting procedures Emergency procedures Corrective action requirement and verification. State Forest Department State Forest Department has an important role in the sustainable development of the project. It will be responsible for Implementing Catchment Area Treatment (CAT) plan Implementing Compensatory Afforestation Plan Wildlife Conservation Program Develop Herbal Garden in consultation with State Medicinal Plant Board (SMPB) Facilitate and guide Van Panchayats. 4.3.2 Activities in the Project Influence Area The project influence area consists of the 7km from the project sites. The activities which are involved in the project influence area are: Biodiversity Management Catchment Area Treatment (CAT) Plan Compensatory Afforestation Wild Life Management

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:6 Date: Nov 2009 Revision: R4

Awareness program Income Generation Activities Managed River Flow Enhancement of cultural properties Control of communicable diseases Biodiversity Management will be joint responsibility of THDC and State Forest Department. Catchment Area Treatment (CAT) Plan, Compensatory Afforestation and Wild Life Management will be implemented by State Forest Department. THDC will be responsible to undertake environmental awareness program in the area involving Van Panchayats, Gram Panchayats, schools and Mahila Mangal Dals (womens group). Income Generation Activities, Managed River Flow responsibility and enhancement of cultural properties will be the responsibility of TDHC. THDC may also support research, documentation and monitoring program of Nanda Devi Biosphere Reserve. THDC will be responsible to organize health camp and periodic checkup in the project area in consultation with Public Health Centre (PHC) The large influx of labourers the project during construction & operational phases will be a major problem and requires monitoring District Administration will maintain record of the same as the area is sensitive with respective national security. Van Panchayats The Van Panchayat is an important institute in the area and may be involved to carry following activities: Protection of plantation sites in the project area Cultivation of Herbal species Develop nurseries for Plantation under the Project area 4.3.3 Activities in the Catchment All the prescribed works in the CAT plan will be executed on the basis of annual approval received from Conservator of Forests, Garhwal circle Pauri and Conservator of Forests/ Director Nanda Devi Biosphere Reserve, Gopeshwar on Annual Work Plan (AWP) prepared by the concerned Divisional Forest Officers. AWP will be submitted by the concerned DFOs to D.F.O, Badrinath Forest division, Gopeshwar who will work as Nodal Officer among all the divisions.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:7 Date: Nov 2009 Revision: R4

Revenue Department and Forest Department will work in tandem to follow the institutional process of Village Forest Panchayat (VFP). A clear understanding will also be reached with the line departments and other agencies through coordination with District Administration to prevent duplicity of works. Plantation will be carried by Forest Department. Forest department will ensure the participation of the local community. A large area of Civil Soyam and Van Panchayat falls with in catchment area. The plantation works will be done by Nanda Devi National Park, Kedarnath Wildlife Forest Division, Alaknanda Soil Conservation Division and Badrinath Forest Division. Maintenance of the plantation in Vanpanchayat area will be done by the respective village Panchayats. Van Panchayats will be also involved in protection of forests against fire. Plantation of medicinal plants will be also undertaken by Forest Department Soil conservation works will be carried by Forest Department and local communities and will maintain the same. Engineering works pertaining to landslide control will be executed by Forest Department with the help of expert agency who has the local engineering expertise for such treatments. This expert agency will be identified by the nodal officer, DFO Badrinath Forest Division under the guidance of Conservator of Forest (CF), Garhwal circle and Director/CF Nanda Devi Biosphere Reserve (NDBR). The Nanda Devi National Park, Kedarnath Wildlife Forest Division, Alaknanda Soil Conservation and Badrinath Forest Division will be involved in Wildlife Management works. Arms training and tranquilizer gun training will be given to the Forest staff through Uttarakhand Police and Wildlife Institute of India. Patrolling team will be formed involving local youths, Panchayat members, Exservicemen for wildlife management under the DFOs of the concerned Forest Divisions. Village Van Panchayat (VP) will work for Eco-development and conservation oriented livelihood improvement programmes. The local forester, in-charge of the village will be the member secretary in the executive committee of VFC The Institutes Identified for implementation, guidance and technical support for various activities in the catchment area are given below. Vivekananda Lab, IARI Almora and G.B Pant University will be collaborated for conducting participatory research on long-term basis on breed improvement of traditional crops with the farmers of this region. Uttarakhand Cattle Board and Animal Husbandry Department will be consulted for animal husbandry program. Technical/ Expertise / Collaboration from I.V.R.I Bareilly and Pant Nagar University, Pant Nagar will also be sought.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:8 Date: Nov 2009 Revision: R4

Horticulture Department will be consulted for giving technical trainings to the villagers for development of horticulture crops and rejuvenation of old orchards. Wildlife Institute of India, Dehradun will provide the technical guidance regarding the census, monitoring, and evaluation of the faunal diversity in the area. Wadia Institute of Himalayan Geology, Dehradun will provide / assist in monitoring the environmental aspects in the project area. Herbal Research & Development Institute, Gopeshwar will be associated for technical knowledge and information regarding plantation and marketing of medicinal plants. Uttarakhand Renewable Energy Development Agency (UREDA) will provide technical support related to street lights, solar lanterns in villages where electrification are not possible due to some unavoidable reasons. JAL Sansthan/ Jal Nigam will be sought for providing drinking water facility in the villages. Bamboo & Fibre Board, Uttarakhand, Dehradun will provide financial & technical support to villagers for planting of ringal. Forest Deptt. will arrange the tie up between Villages & Bamboo Board. Indian institute of Remote Sensing (IIRS) and FSI (Forest Survey of India) will provide necessary expertise in the digitization of the maps used for various purposes like reports, and documentation. Internal monitoring will be conducted regularly by Conservator of Forest, Garhwal Circle and Director, Nanda Devi Biosphere Reserve on the quality of project implementation process. For external monitoring, Project Implementation Monitoring Committee (PIMC) will be constituted at State level at Forest Headquarter Dehradun under the direction and guidance of PCCF, Uttarakhand for conducting external monitoring of the interventions made in this project.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:9 Date: Nov 2009 Revision: R4

4.4

BIODIVERSITY MANAGEMENT Government of India, under Ministry of Environment & Forests (MoEF) constituted National Biodiversity Strategy & Action Plan (NBSAP) a, firm step towards addressing the various issues related to the use, status and conservation needs of biodiversity in the country. Under this initiative, it has been envisaged to produce a series of planning documents dealing with various facts related to the conservation of National Biodiversity. Under this initiative, 5% of the countrys surface area has been successfully declared as legally protected areas. In order to conserve the rich biodiversity of the State the Government of Uttarakhand constituted State Biodiversity Board in 2006. Uttarakhand has also adopted the National Forest Policy (1980) that seeks to integrate biodiversity conservation and sustainable use by local people. A complete ban on hunting (1982) and green felling (1984) has been imposed in the state. A number of legislation having a bearing on biodiversity conservation in the state have been enacted in the state. The Biodiversity of the Project Area is described in Chapter 3- Section, 3.9. 4.4.1 Conservation plan of Project Influence Area Responsibility for implementation of biodiversity management plan in Project Influence Area (7km radius of the project site) will lie with State Forest Department. Local people will be involved by the Forest Department on its discretion, for encouraging community participation. Various mitigation measures are required to be implemented to protect the biodiversity from adverse environmental and social impacts likely to be caused by the Vishnugad Hydropower Project. Control Timber and Fuel wood Demand: Timber demand by villagers is seriously affecting forests of the project influence area. The climax species of natural forests are under pressure due to increased timber demand. The timber species of forests such as Cedrus deodara (Deodar); Pinus roxburghii (Chir), Pinus wallichiana (Kail); Quercus incana (Ban oak), Quercus himalayana (Moharu oak); Picea smithiana (Rai); Grewia oppositifolia (Biul) etc. are under pressure due to illegal felling of trees. To reduce dependency on fuel wood by the villages, arrange alternative fuel such as LPG, Solar Cookers, etc. Awareness program may be organized against illegal felling of trees Control of Agriculture & Horticulture Activities: Horticulture, a cash crop/profit gaining activity i.e. cultivation of fruits, vegetable, flowers is increasing at the cost of forestland leading to loss of forest area year by year. There is also tremendous demand of timber for packing cases for marketing of fruits due to horticulture bloom, leading to increase pressure on

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:10 Date: Nov 2009 Revision: R4

forest. Areas under dense forests cover will not be disturbed for agriculture/ horticulture activities Control of Grazing: Animal husbandry is an important vocation for agriculturist and almost every family rears livestock for rears livestock for their day to day requirement the livestock is mainly defendant upon natural resources mainly forests for sustenance. Extensive grazing of livestock and severe lopping of trees for fodder had adversity affected the forests of probed-influenced area. Overgrazing will be controlled by punitive as well as awareness building measures, as mentioned below: In the permitted grazing areas, the animals will be allowed to enter the forests well after the rains so that grasses would have grown sufficiently to withstand grazing and trampling. To reduce the dependency of grazing on forest, stall feeding, balanced animal nutrition, improved cattle varieties application of concentrates etc. will be encouraged Fencing or Vegataive Hedge will be planted along plantation area. Thorny species like Prinsepia utilis, Agave, Zizyphus, Euphorbia royleana, etc. will be planted so that it prevents animals from entering into the forest. Plantation of fodder species such Quercus incana, Quercus dilata, Quercus floribunda, Boehmeria regulosa, Grevia oppositifolia, Debregeasia longiflolia, Melia azedarach, and Grass species Arundinaria falcate, Napier etc in wasteland / Panchayat land to meet fodder requirement. Control Forest Fire: Forest fire is commonly recorded throughout the forest area. Most of the fires are due to local incendiaries with the belief that burning forest areas improve the resources by getting fresh grass & tender herbages. Effective fire protection measures like early detection systems, communications systems, equipment and public awareness will be implemented for forest fire control. Gram Panchayats and Van Panchayats will be involved to take care of the forest 4.4.2 Conservation plan of Project Affected Area The Biodiversity Management of Project Affected Area is the joint responsibility of THDC, State Forest Department and Local Community. Compensatory Afforestation Plan, Catchment Area treatment Plan and Wild Life Management Plan will be implemented by State Forest Department; Govt. of UA. Whereas, Muck/Quarry Area Redevelopment Plan, Avenue Plantation and Landscaping will be implemented by THDC. The local community will ensure protection of the plantation from human and livestock.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:11 Date: Nov 2009 Revision: R4

Plantation along the 4 approach roads and colony area will be carried to maintain slope stabilization, air quality and improvement of aesthetic view of the area. Development of Herbal Garden: THDC must undertake development of Herbal garden at suitable place in consultation with Forest Department. The vulnerable species Berginia ligulata (Silpara), Hedychium spicatum (Banhaldi) and Thalictrum foliolosum (Mamiri) found in the area and propagation of the species must be taken. Besides the three species other species of medicinal value like Aegle marmelos (Bel), Embelica officinalis (Awla), Cinnamomum tamala (Tejpat), Ocimum basilicum (Tulsi), Adhatoda vasica (Vashaka), Centella asiatica (Brahmi), Thymus serpyllum (Ban ajwain), Asparagus officinails (Satvar), Ocimum kilimandscharicum (Kapoor Tulsi) may also be grown. Plantation of ornamental plants such as Silver Oak, Bottle Brush, Gulmohar, Baken, Jacaranda etc can be also taken to increase aesthetic nature of the disposal area and catalyze growth of biodiversity on the land and in surrounding area Wildlife Protection: It may be ensured by the Contractor that no hunting is practiced at the site by any of the worker and that all site personnel are aware of the location, value and sensitivity of the wildlife resources Part of the project area is located in the transitional zone of Nanda Devi Biosphere reserve. Movement of wildlife is reported in the area therefore check post may be established in the project sites in consultation with Forest Department. Roadside Plantation: Tree felling for road construction/works should be kept bare minimum and strict control must be exercised in consultation with the Forest Department. Equivalent amount of new trees should be planted as integral part of the project within the available land and if necessary, separate additional land may be acquired for this purpose. Depending on the availability of land and other resources, afforestation of roadside land should be carried out to a sufficient distance on either side of the road. 4.4.3 Compensatory Afforestation Plan In order to compensate diversion of forestland i.e. 100.39 ha (includes 23.13 ha land for underground works) for establishment of various project units, compensatory afforestation plan is proposed to be on 201 ha as per the Forest

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:12 Date: Nov 2009 Revision: R4

(conservation) Act (1980). The compensatory afforestation will be carried out by the Forest Department. Local species must be preferred for plantation under compensatory afforestation. The species suggested for plantation is given in Table-4.4.1.
Table-4.4.1 Species Suggested for Plantation under Compensatory Afforestation Plan Scientific Name Common Name Pangar Aesculas indica Siris Albizzia lebbek Utis Alnus nepalensis Kachnar Bauhinia variegata Toon Cedrela toona Kharak Celtis australis Dalchini Cinnamomum tamala Leuri Cupressus torulosa Banj Quercus incana Moru Quercus dilata Amla Embelica officinalis Biul Grewia oppositifolia Denk Melia azadirach Chil Pinus roxburghii Semul Bombax ceiba Walnut Juglans regia Apple Pyrus malus Apricot Prunus armeniaca Plum Prunus communis Peach Prunus persica Malta Citrus sp.

Sl. No 1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Source: CES

4.4.4

Budget for Biodiversity Management A capital cost provision of Rs. 66.6 million has been kept towards the implementation of biodiversity management plan. Year wise budget is presented in Table-4.4.2.

Table-4.4.2 Year wise Budget for Biodiversity Management I Year II Year III Year IV Year V Year (Rs.) (Rs.) (Rs.) (Rs.) (Rs.) Herbal Garden 3,68,000 1,69,000 39,000 12000 12000 Wildlife 3,00,000 1,50,000 50,000 Protection Roadside 9,00,000 4,50,000 1,50,000 Plantation Compensatory 1,92,00,000 2,24,00,000 1,28,00,000 64,00,000 32,00,000 Afforestation Total (Rs.) 2,07,68,000 2,31,69,000 1,30,39,000 64,12,000 32,12,000 Percentage 31.18% 34.78% 19.60% 9.62% 4.82% Activity
Source: CES

Total (Rs.) 6,00,000 5,00,000 15,00,000 6,40,00,000 6,66,00,000 100%

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:13 Date: Nov 2009 Revision: R4

4.5

CATCHMENT AREA TREATMENT (CAT) PLAN 4.5.1 Need for Catchment Area Treatment Area draining into dam through different local streams situated with in the CATCHMENT area mainly responsible for soil erosion. It disturbs the eco-logical balance by destroying the vegetated cover, dislocating wild life, removing precious topsoil, modification of stream morphology. Consequently natural vegetation is removed on either side of riverbank. Soil gets disturbed and is easily removed during periods of heavy down pour, leading to accelerated erosion of soil cover. This causes silt/sediment flow into streams below. Siltation of stream beds reduces the capacity of stream channel and reservoir. The study of erosion and sediment yield from catchments is of utmost importance as the deposition of sediment in reservoir reduces its capacity, thus affecting the water availability for the designated use. The eroded sediment from catchments when deposited on streambeds and banks causes braiding of river beach. The removal of top fertile soil from catchments also adversely affects the agricultural production. Another important factor that adds to the sediment load, and which contributes to soil degradation is grazing pressure. A large number of cattle, sheeps, and goats graze the pastures during summer season continuously for about six months. Due to this pressure, the productivity of these pastures is also declining further. The lack of proper vegetal cover is a factor to cause degradation and thereby results in severe run off/soil erosion, and subsequently premature siltation of the reservoir. Thus, a well-designed Catchment Area Treatment (CAT) Plan is essential to ameliorate the above-mentioned adverse causes and process of soil erosion. The catchment area treatment involves understanding of the erosion characteristics of the terrain and suggesting remedial measures to reduce the erosion rate. For this reason the catchments of the directly draining rivers, streams, tributaries, etc. are treated and the treatment plan has been included in the project. 4.5.2 Project area in the CAT Plan The Catchment Area Treatment Plan for VPHEP has been prepared by the Badrinath Forest Division, Gopeshwar; Garhwal Circle, Pauri, Uttarakhand. The Plan includes 37 micro watersheds in 5 sub watersheds namely Saraswati, Dhauliganga, Rishigang, Budhiganga & Nagoigad. But as various CAT plans are already under implementation in this catchment particularly Tapovan Vishnugad CAT plan, only 18 micro watershed in 2 sub watersheds namely Budhiganga and Nagoigad has been selected for treatment. The total area of selected catchment is 84085.00 ha. Out of which, 12964.00 ha (15.42%) is rocky and snowbound. The remaining area of 71121.00 ha (84.58%) is treatable, of which, agriculture area is 6647.00 ha (7.90%), forest area is

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:14 Date: Nov 2009 Revision: R4

40678.00 ha (48.38%) and blank area is 23.796 ha (28.30%). Therefore, total workable area is 71.121 Sq. Km.
Table-4.5.1 Land Use Classification in Revised Catchment Area Treatment Plan (in Ha)
Name of the Catchment (SubWatershed) Name of the micro watershed Treatable area Agriculture Forest Blank Untreatable area Total Rocky River Snow Bed Bound

Budhiganga

Karmansa Senkora Garurganga Batula Gauna Pulgadhera Birahiganga Gadiyal gadhera Taraktal Lasi Total Budgiganga Nagoigad Jaisal Menagad Topon Bangina Kalpagad Barki Aroshigad Vishnugad Total Nagoigad:Grand Total :-

537 395 638 594 100 200 144 37 637 1988 5270 581 43 230 486 0 19 18 0 1377 6647

2293 288 338 3519 137 1562 2556 126 592 950 31 500 1150 0 1250 3538 175 1187 3337 1569 4000 2763 525 869 6463 250 0 1944 80 38 28513 3181 10336 875 800 0 6506 8288 0 305 1353 0 1857 188 0 731 3869 0 556 937 0 648 1109 0 687 4071 0 12165 20615 0 40678 23796 10336

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 938 0 0 0 938 0 520 0 0 896 0 0 274 1690 2628

3456 5613 3912 2075 2500 5100 9988 4194 7350 4050 48238 2256 15357 1888 2531 5496 1512 1775 5032 35847 84085

Source: CAT Plan prepared by Badrinath Forest Division, Gopeshwar

Total area Treatable area Un-treatable Area 4.5.3

: - 84085.00 ha. : - 71121.00 ha. : - 12964.00 ha.

Objective of the CAT Plan a) The Primary objective of this plan is to restore the ecosystem and biodiversity of Impact Area affected by the Vishnugad-Pipalkoti Hydroelectric Project. b) The actual project area is located in forest bound area which is on one hand geologically fragile zone and on the other hand it houses rich in floral and faunal wealth. The wild animals of this area are highly endangered and needs special care & treatment in full movement zone in and around the project area. As such the plan will provide management inputs in the Impact Area for the conservation and management of floral and faunal diversity.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:15 Date: Nov 2009 Revision: R4

c) Project will give maximum emphasis on catchment treatment through plantation, soil and water conservation works. Treatment of land slide areas, improvement of habitat of wild animals and conserving biodiversity treatment of agricultural field of stake holders, which are sensitive to soil and water erosion to improve the life standard of the local people through Eco development works and ensure people participation. A certain amount of fund has also been earmarked for annual maintenance and upkeep of soil conservation works. The project will be implemented with integrated watershed management approach. d) The project will be executed by three different agencies i.e. forest department, expert agencies and the local communities depending upon the expertise needed to conduct these works and the stake of the community to own and maintain the intervention. Heavy engineering works pertaining to landslide control in and around the project area will have to be executed with the help of expert agency who has the local expertise for such treatment works. The expert agency will be identified in the annual plan to be made every year by the forest department. e) The catchment area is strategically located between Nanda Devi National Park, Kedarnath Wildlife Forest Division, Alaknanda Soil Conservation Division and Badrinath forest Division. f) The CAT plan earmarks the provision for selected inputs in livelihood support activities for the local community, which would facilitate eco-restoration as well as eco-development of the catchment area. Education and awareness of the community for catchment development on watershed approach will be central to all these activities. Apart from this, special care is to be taken on decreasing dependence of the local people on forest areas. For this special effort will be done by raising forest on Civil Soyam and Van Panchayats and doing pastoral development activities.

g) Village communities have been put to the center in the case of all village related eco-development works. Institution and capacity building will be the major intervention areas for conducting any work in the village. Project will focus on the process development in participatory approach with the community in terms of owning the responsibility for maintenance of created assets. h) Women are the main natural resource managers in the project area and the poorest have the largest stake in the forests. To motivate the women in the project process, women social motivators will be appointed. Special support in the areas of rural technology, gender support, focus group and the public healthcare has been identified for this. i) The approach to supporting the animal husbandry, agriculture, horticulture and energy conservation sectors will be mostly through technical training inputs and facilitation for forward and backward linkage, long term

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:16 Date: Nov 2009 Revision: R4

participatory research programmes and demonstrations for trying out the adaptation and penetration of innovative technologies that lead to lesser dependence on natural resource use will be encouraged in this programme. Income generation activities to provide alternative livelihood opportunities have also been envisaged to reduce pressure on the forests and grazing lands. j) Dovetailing the awareness training and technical inputs of the project with the ongoing schemes of the line department will be done in order to sustain the initiatives taken up by the project and to prevent misuse of funds through duplicity.

k) A large area of agriculture field of stakeholders lies in the catchment area. This area is also fragile and due to soil erosion land holding is decreasing day by day. So special efforts will be made to check soil erosion and conserving the moisture of agricultural fields of stakeholders by soil and water harvesting measures. 4.5.4 Plantation in the Reserve Forests Areas Plantations will be carried out in the reserve forest areas in the project area with multi objective of soil conservation, water recharge and Eco restoration of degraded areas. These areas are in addition to the plantations which will be carried out by in nearby Civil and Forest Panchayat areas for meeting their fuel wood and fodder needs that would ultimately reduce the biotic pressure on forests. The participation of the grazer community will be very crucial to make the plantations successful in the reserve forest area in the higher hills. Forest department staff will ensure the participation of the local community in planning the plantation species and in protection of these plantations. Plantations that will be done in the soil conservation areas near the drainages for vegetative treatment will be in addition to the above plantation target. These plantations will be carried out by Nanda Devi National Park, Kedarnath Wildlife Forest Division and Badrinath Forest Division. 4.5.5 Plantation in the Civil Soyam and Van Panchayat Areas A large area of Civil Soyam and Van Panchayat falls with in catchment area. Mostly this area is blank and unable to work as buffer in between community and the reserve forest. Therefore, all the biotic pressure falls on the Reserve Forest. So there is special need to make plantations in these areas so that they could meet the requirement of the local people in and have and restoring the eco systems of the area. These plantations will also increase the livelihood of the people and also the income of the Van Panchayats. These plantation works will be done by Nanda Devi National Park, Kedarnath Wildlife Forest Division, Alaknanda Soil Conservation Division and Badrinath forest Division. A total of 1000 ha area will be treated for plantation activities. Out of this, 450 ha

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:17 Date: Nov 2009 Revision: R4

area will be taken under densification, 50 ha under pasture development and 300 ha under medicinal plants. Apart from this, around 1200 ha area has been selected for assisted natural regeneration. 4.5.6 Drainage Line Treatment and Soil Conservation Work The Impact Area is very fragile and there is a huge scope of soil and moisture conservation works. These works will be conducted as erosion control works in gullies and eroding stream and river training works. This component concentrates on protection works where lasting benefits will be assured in the lower catchment area. Works will concentrate on construction of site specific physical structures accompanied by tree planting to stabilize banks and planting for short vegetative cover in the landslide prone areas through brushwood and perennial grasses. Project will seek the technical assistance from the institutes identified for deciding the treatment measures and treatment norms. The plan has identified a number of streams which needs treatment from their primary source. The phasing of work in the selected stream has been done depending upon the urgency for treatment needs. The phasing of interventions and type of the structures will be decided based on the treatment needs of each stream on the ground right before the execution of work. Thus, the physical target kept in this plan has to be regarded as nearest possible indicative targets keeping in view the fragile geological condition of the catchment area. Effort will be made to synergies the treatment works with the soil conservation practices of the catchment community. For the works of drainage line treatment to be executed by Forest Department, the village community will be integrally involved in the execution of these works. 4.5.7 Wildlife/ Biodiversity Protection Works The Impact area of Vishnugad Pipalkoti Hydroelectric Project is strategically located between Kedarnath Wildlife Division, Badrinath Forest Division and Nanda Devi National Park. The area is endowed with variety of flora & fauna, many of which fall under endangered category, e.g. Leopard, Himalayan Black bear and Ghural, Jungal Cat, Barking deer, Sambhar, Wild boar. The area also houses high-risk pheasant like Monal, Koklas and Chir Pheasants. The civil soyam areas lying in the impact area are also rich in wild Life. The overall objective of wild life and bio-diversity management plan of is: Training and capacity building of the forest staff for protection and surveillance Protection of floral and faunal resource and conservation of threatened flora and fauna and protection of corridors Management of man animal conflict Wireless and mobile communication for protection support Infrastructure maintenance Habitat improvement works Biodiversity conservation support to the village communities

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:18 Date: Nov 2009 Revision: R4

Mobility support for field staff The usage of the earmarked fund for wild life protection activity will be governed by wild life management plan of each division. The earmarked fund will remain as corpus with the department under a separate account head. This will remain as a corpus fund in fixed deposit in a nationalized bank giving competitive interest rate. Out of this generated interest approximately 90% will be used annually for wild life protection purpose and balance amount will be used to develop the corpus fund further. 4.5.8 Responsibility of Forest Department The responsibility of implementing the project will lie with the concerned Divisional Forest Officer (DFO). The DFO, Badrinath Forest Division, Gopeshwar shall be the nodal implementing agency who will be the Nodal officer. For effective implementation of this project, the DFO, Badrinath Forest Division/ Nodal Officer will need a Project Management Cell (PMC). The project will be closely monitored in terms of physical, financial progress and quality by Conservator of Forests, Pauri Garhwal & Conservator of Forest, Nanda Devi Biosphere Reserve, Gopeshwar. The concerned Assistant Conservator of Forests (ACFs) will closely supervise the project in all respects. One ACF shall be posted at the Nodal Office who will act as the point of overall co-ordination of the staff from the all Implementation Units and specialists from different disciplines including Project Coordinator. The Project Coordinator shall be hired/engage or taken on deputation from the linked departments as per the needs. In PMC the Nodal Asst. Conservator of Forests (ACF) will work in close coordination with Project Coordinators (PC). The technical staff of PMC will comprise of one horticulture specialist, one livestock specialist and other specialists who shall be hired/consulted as per the site specific requirements. The concerned ACFs will be directly responsible for field level planning and monitoring of implementation of work under forestry and soil conservation to be executed by the Forest Department. Project coordinator (PC) will be directly responsible for overall planning and implementation of all the institution building and capacity building trainings, workshops, exposure visits for the project which includes project staff of all the ranks from different disciplines and the villagers. For Eco-Development Activities carried out by the V.P., Project Coordinator will make recommendations to the DFOs concerned for execution of all these activities through the ACF. PCs shall be primarily responsible for planning, coordinating and monitoring the execution of village based eco-development works and livelihood improvement works. PCs shall work in close coordination with horticulture specialist, livestock specialist, engineering specialist and the concerned line

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:19 Date: Nov 2009 Revision: R4

agencies for appropriate field level planning and recommending social and technical inputs. PCs will make the joint recommendation in proposals, estimates and vouchers along with ACF for village based livelihood improvement works. Specialist of different components will plan and execute work through PIU office. PCs will also monitor the institutional health of the VPs, assess the adaptive challenges being faced by these institutions and give feedback to the concerned DFOs. PMC will be handled by assistant accountant and assistant programmer & other staff (as per the based needs) along with the normal ministerial staff of Badrinath Forest Division, Gopeshwar. It will be the responsibility of DFO, Badrinath Forest Division/ Nodal Officer to coordinate with all the expert /line agencies to seek adequate support partnership for study, research, documentation and information dissemination for planning and execution of work with quality participation of the local communities into the project work. DFO will closely work with concerned ACF and PCs for seeking their assistance for this work. It will be the responsibility of Conservator of Forests, Garhwal Circle, Pauri and Conservator of forest/Director, Nanda Devi Biosphere Reserve, Gopeshwar ,closely monitor the quality of the project regularly through monitoring committee, coordinate with THDC and the Government for regular fund flow and give expert on hand guidance to PMC for effective implementation of the plan. 4.5.9 Responsibility of THDC THDC will responsible implementation. for overall supervision of the CAT Plan

The Environmental Management Cell (EMC) of THDC will supervise the implementation of each activity given in the CAT plan. EMC will also monitor physical & financial progress and prepare a quarterly progress report. Year wise fund will released by THDC for which a Memorandum of Understanding (MoU) may be signed between THDC & Forest Department. 4.5.10 Financial Provision for CAT Plan The project cost is estimated as Rs. 2491.58 Crores including IDC & FC of Rs 366.80 crores at March 2008 price level. As per the guidelines the provisions for CAT PLAN is being computed at the rate of 2 % of the project cost (excluding the IDC) which comes to Rs. 47.00Crore. This includes financial provision for the CAT plan 23.43 million rupees and for the Eco-restoration plan the provision is 446.66 million rupees. Breakup of the cost is given in Table-4.5.2 and year wise financial targets for Eco-restoration plan is given in Table-4.5.3.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:20 Date: Nov 2009 Revision: R4

For maintaining the assets created during the plan period, a corpus fund of Rs. 1.50 Crores is also being provided.
Table-4.5.2 Financial Provision for Eco-restoration Sl. No. Particulars 1. Forestry Work 2. Engineering Work 3. Wild Life Management Work 4. Residential and Non Residential Building New Construction and Renovation for Field Staff 5. Foot Path Renovation 6. Foot Bridge New Construction and Renovation 7. Other Developmental and Participatory Activities Total
Source: CAT Plan for VPHEP, prepared by Badrinath Forest Division, Gopeshwar

Rs. 37529900 191140000 24325000 25910000 12060000 3700000 152000000 4466664900

Table-4.5.3 Year wise Financial Target for Ecorestoration


Issues Forestry work Soil & Moisture conservation Wildlife Management Capacity Building/ Exposure visit Other Activities Total I Year (Rs) 4478610 II Year (Rs) 12373300 III Year (Rs) 11499210 IV Year (Rs) 4918560 V Year (Rs) 2224520 VI Year (Rs) 1986300 VII Year (Rs) 49400 Total 37529900

57185000

81605000

43290000

9060000

191140000

14875000 2000000

6250000 2000000

1800000 2000000

700000 2000000

700000 1000000

0 500000

0 500000

24325000 100000000

56310000

50700000

33660000

17000000

12000000

7000000

7000000

93670000

134848610 152928300 92249210 33678560 15924520 9486300 7549400 (30.19%) (34.24%) (20.65%) (7.54%) (3.57%) (2.12%) (1.69%) Source: CAT Plan for VPHEP prepared by Badrinath Forest Division, Gopeshwar

446664900

4.5.11 Agencies Involved in Implementation of the Plan Following institutions will provide technical support during implementation of the Catchment Area Treatment Plan: Wildlife Institute of India (WII), Dehradun will provide the technical guidance regarding the census, monitoring and evaluation of the faunal diversity in the area. Wadia Institute of Himalayan Geology, Dehradun will assist in monitoring the environmental aspects in the project area. Herbal Research & Development Institute, Gopeshwar

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:21 Date: Nov 2009 Revision: R4

UREDA is a premier agency, which is working in the field of nonconventional energy. JAL Sansthan/ Jal Nigam: There are various schemes executed by Jal Nigam and Jal Sansthan for providing drinking water facility in the different villages. This facility will be made available in the affected villages by the above agencies under rural development program. Bamboo & Fibre Board, Uttarakhand, Dehradun will provided financial & technical support to villagers Indian institute of Remote Sensing (IIRS) Forest Survey of India (FSI) will give necessary expertise in the Digitization of the maps used for various purposes like reports, and documentation.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:22 Date: Nov 2009 Revision: R4

4.6

MUCK DISPOSAL MANAGEMENT PLAN 4.6.1 Introduction The construction of Vishnugad Pipalkoti Hydroelectric Project (444 MW) would involve excavation of earth and rock generating muck in large quantum i.e. in the volume of 1.5 Mm3. The muck thus generated needs proper disposal. With the objective to protect the disposal areas from further soil erosion and develop the surrounding areas in harmony with the environment the Muck Disposal Plan is formulated. The Muck Disposal Plan detailed in the following sections gives the quantification of muck, identifies location and activities wherein muck is generated (excavation and blasting operation) and quantifies muck generated from each activities with relevance to disposal options. The identified locations/sites of muck disposal is in conjunction with various characteristics viz. landscape, cost effectiveness, nearness to source of generation, groundwater/blockage to surface water, relief and scope of afforestation and erosion control/sediment arrest. The plan identifies landscaping measures for disposal of muck, modes of transportation for muck disposal and species selection for use of biofertilizer method for vegetative growth on muck spread, delineates muck disposal options for each site implementation and development of landscape. 4.6.2 Excavation of Muck and its Disposal As per Detailed Project Report (DPR) due to the construction of the various components of the project the total quantity of muck to be generated is estimated to be about 1.5 Mm3. Of the total muck generated 0.45 Mm3 will be used for construction purposes. For dumping of the remaining muck of 1.05 Mm3. Four areas viz. (i) Haat, (ii) Jaisaal, (iii) Gulabkoti and (iv) Guniyala, have been identified by THDC adjacent to project components. In these 4 identified sites dumping will be done and further they will be restored and revegetated with proper landscaping. The capacity and location of disposal areas are given in Table-4.6.1.
Table-4.6.1 Capacity and Location of Disposal Area Sr. No. Name of location & Area (in ha.) Capacity of Muck Disposal Area (in m3) 1. Haat (4.03) 282,100 2. Jaisaal (2.47) 172,900 3. Gulabkoti (6.03) 422,100 4. Maina Nadi (Guniyala)(2.4162) 169,134 TOTAL 14.9462 1,046,234 Source: Survey carried out by CES

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:23 Date: Nov 2009 Revision: R4

4.6.3

Muck Disposal Sites The description and details of the 4 muck disposal sites viz. (i) Gulabkoti (ii) Guniyala, (iii) Jaisaal and (iv) Haat are given in the following sections. i) Gulabkoti Gulabkoti site has been identified for the disposal of muck to be generated due to the construction of the dam. The Gulabkoti area is more or less open with sparse vegetation cover in the form of scrubs with scattered trees. A survey was conducted to find out the total area of site. The map of muck disposal area at Gulabkoti with contour intervals is shown in Drawing No. 2008026/EC/EMP-01. The cross-section of the muck disposal site at Gulabkoti is shown in Drawing No. 2008026/EC/EMP-02. It is proposed to construct a 65 m Rock fill dam, sizeable quantity of the excavated material will be utilized as construction material for the rock fill dam. Muck for dam construction will be generated by open and underground excavation in the river bed and in the hard rock and will be dumped in a sloping gradient with a ratio of approx. 1:0.405 by constructing a retaining wall of 7 m on the down hill side along the river bank and a slope of 50 cm high with 50 cm thickness on the uphill side along the footpath line. The muck to be excavated comprising of mostly coarse aggregates will be utilized for different components from the construction of the foundation of the diversion dam, stone pitching on downstream of coffee dam, coffer dams works, and diversion tunnel. The clayey material excavated at dam site could be used for forming an impervious layer within the upstream coffer dam. The dumping site which is identified near Gulabkoti has a capacity of 4,22,100 m3. Typical Cross Section of filling area of muck disposal at Gulabkoti is shown in Drawing No. 2008026/EC/EMP-03.

Views of Muck Disposal Site at Gulabkoti near Dam Site

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:24 Date: Nov 2009 Revision: R4

ii) Guniyala Guniyala site near Mainagad River has been identified for the disposal of muck to be generated due to the construction of the Head Race Tunnel. The general landscape of the area has vegetation cover in the form of scrubs mixed with trees. Dense vegetation growth in the form of dense to moderate forest can be seen on the steep slopes of the Mainagad River. A survey was conducted to find out the total area of site. The map of muck disposal area at Guniyala with contour intervals is shown in Drawing No. 2008026/EC/EMP04(a) and (b). The cross-sections of the 2 muck disposal sites at Mainagad near Guniyala village are shown in Drawing No. 2008026/EC/EMP-05(a) and (b). Muck will be generated due to construction of 13.4 km long 8 m diameter Head Race Tunnel (HRT). Muck will be dumped in 2 different sites at Mainagad, near Guniyala village with steep sloping gradients with a ratio of approx. 1:1.009 and 1:1.5 respectively. Muck will be deposited along the slope by constructing a retaining wall of 7 m each on the down hill side along the river bank and a slope of 50 cm high with 50 cm thickness on the uphill side along the footpath line. The muck is proposed to be dumped at dumping sites at Mainagad and Guniyala, which are near to Guniyala (Mainagad) Adit No. 2. The dumping sites have a capacity of 1,69,134 m3. Typical Cross Sections of filling area of muck disposal at Mainagad near Guniyala village is shown in Drawing No. 2008026/EC/EMP-06(a) and (b).

Views of Muck Disposal Site at Guniyala near Head Race Tunnel

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:25 Date: Nov 2009 Revision: R4

iii) Jaisaal Jaisaal site near Siyasin has been identified for the disposal of muck to be generated due to the construction of the Tail Race Tunnel. The terrain of the muck disposal site at Jaisaal has a steep topography for approximately 19 m followed by a more or less gentle topography for approximately 15 m and a very steep topography near the river bank for approximately 11 m. The general landscape is more or less barren with scanty vegetation growth in the form of scrub, grasses and scattered trees which are more prominent in the lower reaches of the river bank and along the streamlets and channels of water. A survey was conducted to find out the total area of site. The map of muck disposal area at Jaisaal with contour intervals is shown in Drawing No. 2008026/EC/EMP-07. The cross-section of the muck disposal site at Jaisaal is shown in Drawing No. 2008026/EC/EMP-08. Muck will be generated due to the construction of 22m dia and 130 m high restricted orifice type upstream surge shaft and 80 m high, 8 m dia horse shoe shaped tunnel of 3.07 km long downstream surge shaft. Muck will be generated due to underground and surface excavation works. The muck is proposed to be dumped at dumping site at Haat, Adit No. 3 and Jaisaal which is near to Jaisaal village. The muck disposal site has a sloping gradient with a ratio of approx. 1:0.545. Muck will be deposited along the slope by constructing a retaining wall of 7 m each on the down hill side along the river bank and a slope of 50 cm high with 50 cm thickness on the uphill side along the footpath line. The dumping site has a capacity of 1,72,900 m3. Typical Cross Section of the filling area of muck disposal Site at Jaisaal is shown in Drawing No. 2008026/EC/EMP-09.

Views of Muck Disposal Site at Jaisaal near Tail Race Tunnel

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:26 Date: Nov 2009 Revision: R4

iv) Haat Haat site has been identified for the disposal of muck to be generated due to the construction of Surge Shaft and Power House. The terrain of the muck disposal site at Haat has a steep topography in the upper reaches (approximately for 41 m) and a gentle sloping topography in the lower reaches (approximately for 13 m) in the close proximity of the river bank. The general landscape of the area is more or less open with sparse vegetation cover in the form of scrubs with scattered trees concentrated along the arterial road. A survey was conducted to find out the total area of site. The map of muck disposal area at Haat village with contour intervals is shown in Drawing No. 2008026/EC/EMP-010. The cross-section of the muck disposal sites at Haat is shown in Drawing No. 2008026/EC/EMP-011. Excavation for the underground power complex comprising of two separate caverns viz. power house cavern which is 117m long, 18.5 m, and 41 m height and transformer cavern which is 92 m long, 13.5 m wide and 17.5 high will be carried out. The muck generated due to the underground excavation will be disposed on a sloping gradient with a ratio of approx. 1:0.578. Muck will be deposited along the slope by constructing a retaining wall of 7 m each on the down hill side along the river bank and a slope of 50 cm high with 50 cm thickness on the uphill side along the footpath line. The dumping sites has a capacity of 2,82,100 m3. Typical Cross Section of the filling area of Muck Disposal Sites at Haat is shown in Drawing No. 2008026/EC/EMP012.

Views of Muck Disposal Site at Haat near Power House and Surge Shafts

4.6.4

Conclusion From the discussions in the above sections it can be seen that the total volume of muck to be generated is approximately 1.5 Mm3 of which 0.45 Mm3 will be utilized in the projects construction and 1.05 M3 is required to be disposed off. The capacity of the muck disposal sites is estimated at 1.046 Mm3. In our

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:27 Date: Nov 2009 Revision: R4

opinion, the balance amount, which is less than 4000 m3, can be easily managed to be disposed off in the identified muck disposal sites and there is no need for developing another site. It may also be possible that utilizable muck may be much more than the estimated 0.45 Mm3, which will be known at the execution stage of the project. Apart from this by using Tunnel Borrowing Machine (TBM) the generation of muck will also be less as there will be no over breaks. As discussed above apart from the disposition of the muck through construction of masonary gravity walls the counterfort gravity masonry walls can also be constructed which will incur additional costs due to construction of additional counterfort structures. A typical cross section of simple masonry gravity and a counterfort gravity retaining wall are shown in Figure-4.6.1 & 4.6.2.

Figure-4.6.1 Typical Cross Section of a Counterfort Gravity Retaining Wall

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:28 Date: Nov 2009 Revision: R4

Figure-4.6.2 Typical Cross Section of a Simple Masonry Gravity Retaining Wall

With the start of excavation works in the initial phase the muck will be used for development of working and facility area, construction of the 4 approach roads, protecting, filling and soling works. Muck will be dumped with the help of the dumpers, taking into consideration the slope of the dumping areas.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:29 Date: Nov 2009 Revision: R4

4.6.5

Planning & Management of Muck Disposal a) Re-vegetation Plantation will be carried out at the muck disposal sites for the stabilization of the slopes, landscaping and improving the aesthetic value of the area. The waste material dumped at spoil tip would be mechanically compacted and properly leveled with suitable safe slopes. A retaining wall of about 7 m will be constructed at the muck disposal sites. On the uphill side of the slope a 50 cm high and 50 cm thick wall would be provided to protect the uphill side of the terraces from slipping. In order to restore the area, all these dumping sites need to be rejuvenated by means of turfing and vegetation growth. A Schematic Diagram of the turfing of slopes is given in Figure4.6.3. As the muck would be disposed on an unstable slope, for proper compaction and stabilization 1 m terracing along the contour at 5 m interval along the slope in staggered manner may be done for muck disposal. Muck disposal sites with gentler slopes viz. Gulabkoti, Jaisaal and Haat will be provided with stairway for accessibility and maintenance. For the muck disposal site like Guniyala which has a steeper gradient cant be provided with stairway as rise and tread cannot be designed on a slope of more than 1: 1 m gradient.

Figure-4.6.3 Schematic Diagram of Turfing on Slopes

All spoil tip areas will be developed as per specifications and its feasibility. Water treatment will be given for settlement of muck with suitable

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:30 Date: Nov 2009 Revision: R4

compaction. Once the dumping is completed these areas will be developed into terraces and restored by laying of the top soil on the top, digging of pits and planting of plant sapling. Once the dumping activities are completed, these dumping areas will be developed into terraces and restored by laying of soil on the top and digging of pits and planting of plant sapling. These areas may be developed into parks, gardens and view point sites for tourists. In between the spoil tips drains or channels, will also be provided for draining of sprinkled water. The brief work plan formulated for revegetation of these spoil tips is through Integrated Biotechnological Approach Development of the spoil tips taking into consideration their chemical properties to ensure supportive and nutritive capacity to sustain vegetation growth Delineation of appropriate blends of organic waste and soil to develop rhizosphere of good nutritive and supportive capacity Mass culture of plant specific bio-fertilizer and mycorrhizal fungi. Plantation of 4 spoil tips covering about 14.9462 ha. using identified blend and biofertilizer inoculums b) Plantation Plantation will be carried on spoil tips by digging of pits. These pits will be mixed with external soil, organic fertilizer and vermi-compost. Saplings will be planted in these pits. Refilling will be done by covering the entire root system. Turfing (sodding) and suitable shrubs will be grown at slopes. Thick layer of external soil will be spread on the slope area. Sod patches will be grown in form of patches. Before sowing the area should be properly amended with manure. Species for Plantation Afforestation with suitable plant species of high ecological and economic value and adaptable to local conditions will be undertaken in accordance to canopy requirement. The major plant species in the area are: Non Leguminous including fruit trees (i) (ii) (iii) (iv) (v) (vi) (vii) Poplar (Populu sp.) White willow (Salix alba) Deodar (Cedrus deodara) Kail (Pinus wallichiaia) Apricot (Prunu sp.) Mourning cypress (Cupressus torulosa) Pangar (Aesculas indica)

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:31 Date: Nov 2009 Revision: R4

(viii) (ix) (x) (xi) (xii) (xiii) (xiv) (xv) (xvi) (xvii) (xviii) (xix)

Utis (Alnus nepalensis) Kachnar (Bauhinia variegata) Toon (Cedrela toona) Shisham (Dalbergia sissoo) Semul (Bombax ceiba) Biul (Grewia oppositifolia) Denk (Melia azedarach) Apricot (Prunus armeniaca) Plum (Prunus communis) Peach (Prunus persica) Pomegranate (Punica granatum) Malta (Citrus spp.)

Leguminous (i) (ii) (iii) (iv) Locust tree (Robini psuedoacacia) Maharukh (Ailanthus excelsa) Indigiogofera pulchela Siris (Albizzia lebbeck)

Shrubs (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) (xi) (xii) (xiii) Rambans (Agave americana) Basinga (Eupatorium adenophorum) Shuru (Euphorbia royleana) Nagphani (Opuntia dilleni) Karonda (Carissa spinarium) Ber (Zizyphus mauritiana) Bhilmora (Rumex hastatus) Kath Neem (Murraya koengi) Bindu (Colebrookea oppositifolia) Rasaut (Berberis aristata) Barapilu (Salvodara sp). Basak (Adathoda vasica) Safed musli (Asparagus sp.)

Grasses (i) (ii) (iii) Gini ghas (Panicum maximum) Rhodes grass (Chloris gayana) Doob ghas (Cynodon dactylon)

The various species of leguminous and non-leguminous plant species will be grown on the spoil tips. A small portion (approx. 2%) of the vegetation cover will comprise of horticulture plants and one site will be kept for other plantations depending on its suitability.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:32 Date: Nov 2009 Revision: R4

c) Irrigation Facility The vegetation in the Vishnugad Pipalkoti area is mostly dependent on rainfall and to some extent on small streamlets. In general the afforestation programme in the vicinity is not supplemented by any irrigation system. However, in order to ascertain quick greenery and growth in the spoil tip areas, irrigation, especially during the drought period is to be provided. To cater to this need portable water pumps along with requisite PVC pipes need to be utilized to draw water from immediate down slope sources. For sites where no immediate source of water is available for this irrigation, the water will be provided by project tankers. d) Fencing All the 4 sites will be properly fenced to protect the area from human and animal interference. e) Watch and Ward Manpower in the form of watchmen and gardeners would be deployed for protection and maintenance of the sites for three years. The duties will include replacement of casualties, weeding, watering, repair of fence line etc. 4.6.6 Budget The above mentioned activities involve capital investments, annual recurring and maintenance costs. Some of the activities like nursery and cost of vehicles are capital costs. Some of the costs are recurring which include purchase of seed, manure, salary and wages and miscellaneous expenditure. Capital costs other than the nursery are taken in Lump Sum. Recurring costs are determined based on annual basis. Contingency of 15% of total cost (sr. no. 1-7 of Table-4.6.2) is considered for plan implementation. The details of the budget are presented in Table-4.6.2.
Table-4.6.2 Budget for Implementation of Muck Disposal Plan
Issues Development of Nursery (or Contract) Procure pumps & pump house Plantation on spoil slope Turfing of slopes bio-fencing of site Maintenance Watch & ward 150000 I year 600000 II year 600000 III Year 600000 1800000 600000 200000 2500000 200000 150000 800000 800000 2500000 523000 150000 800000 600000 2500000 120000 150000 1000000 IV year 200000 V year Total 2000000 1800000 2000000 7700000 843000 600000 2600000

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan Issues Contingencies /escalation Total Source: CES I year 448000 1048000 II year 448000 1398000 III Year 448000 7098000 IV year 448000 5421000 V year 448000

Page:33 Date: Nov 2009 Revision: R4 Total 2240000 19783000

4818000

4.6.7

Recommendations For smooth implementation of the Muck Disposal Plan following measures may be considered. a) b) c) Retaining wall for muck disposal sites shall be completed by EPC contractor prior to the start of dumping /disposal. Species of trees be selected which are fast growing and helpful in stabilizing the dump sites Project authorities may have frequent review and coordinate the activities of contractors for smooth and timely implementation of the Muck Disposal Management Plan

4.7

FISH MANAGEMENT PLAN An aquatic study was conducted details of which are provided in detail in Chapter 3Section 3.8. Snow trout (Schizothoraichthys progastus and Schizothorax richardsonii) is found in the project stretch. The fish management plan involves various options for management of Mahseer and Snow trout.

4.7.1

Characteristic of Endangered Fish Snow trout (Schizothoraichthys progastus and Schizothorax richardsonii) is a freshwater fish. It is mainly herbivorous basically feed on plant material. Breeds in the upper reaches of river and travels down locally after breeding. Maximum size is 50 cm The dam on river Alaknanda to be developed as a part of the project will act as a barrier to the local free movement of fish species. Due to its dorso-lateral compressed body, the snow trout is not an active swimmer.

4.7.2

Sustenance of Fisheries Most of the fish species found in Alaknanda are abundant in nature. However two species of Mahseer (Tor tor ; Tor putitora ) are endangered as per NBFGR categorization, which are absent at the sampling sites S0, S1 and S2. Other two species of Schizothoraichthys progastus and Pseudecheneis sulcatus are vulnerable in nature.

4.7.3

Management Measures Habitat Restoration: Mahseer is a migratory fish and comes in the Alaknanda and its tributaries in search of feeding and breeding grounds. The Birahi is the most

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:34 Date: Nov 2009 Revision: R4

appropriate habitat for Mahseer and able to provide suitable conditions for the survival of its young ones. The catchment of Birahi River can be improved by plantation along the bank. The anthropogenic activity like extraction of sand, pebbles, gravels, stones and fishing activity in the river should be completely banned. Efforts for diversion of route of Mahseer towards Birahi river may be done for effective management of Mahseer and other vulnerable fishes in the region. A capital cost provision of Rs. 10 lakhs has been kept towards habitat restoration of Mahseer through improvement of the catchment of Birahi River and conservation of fish stock in the study stretch of Alaknanda The Mahseer hatchery already constructed at the Tehri Dam on the Bhagirathi River is used for propagation of the Mahseer and will be utilized for VPHEP. Management of Snow trout For the management of the Snow trout (Schizothoraichthys progastus), Fish management program will be undertaken by THDC Ltd. in consultation with Dept of Fisheries, GoUK/ Directorate of Cold Water Fisheries (DCFR), ICAR, Bhimtal. THDC has already consulted the DCFR, ICAR, Bhimtal. The Senior Scientist from DCFR Bhimtal have already visited the project site for identification of suitable site for establishment of Snow Trout hatchery for fulfillment of fishery action plan towards restoration of aquatic ecosystem. The MoU for implementation of Fishery Action Plan is under process. Upgradation of Trout Hatchery In this direction THDC has already consulted the Dept of Fisheries, GoUK /DCFR, ICAR, Bhimtal. The Senior Scientist from DCFR Bhimtal have already visited the project site for identification of suitable site for establishment of Snow Trout hatchery for fulfillment of fishery action plan towards restoration of aquatic ecosystem. The Dept of Fisheries, GoUK / DCFR, ICAR, Bhimtal will also utilize the Fish Farm, Baranganga, district Chamoli to meet the demand of fish seeds. The water supply facilities of the farm should be strengthened as there will be increase in water required at farm to produce fish seed for stocking at the site. For capacity enhancement existing tanks can be renovated and if necessary new rearing/ brood tank should be constructed. Provision for other requirement like feed, medicines net, aerator, etc should be also considered. Production and rearing of Fish Seed Brood stock will be procured and maintained at the fish farm to produce the seed required for stocking. The hatchling will be reared at the farm upto the required stocking size. Health management and feeding of the reared stock should be taken care regularly. Stocking of fish seed in the Stream For stocking of fish seed at the site necessary facilities like packaging materials, oxygenation equipment, feeder/ graders etc will be purchased. A vehicle will also be

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:35 Date: Nov 2009 Revision: R4

required for transportation of fish seed reared at the farm to the stocking site. Apart from this, the vehicle will also be used to carry items required for survey and monitoring of water quality and stock assessment fortnight / monthly. For assessment of fish stock and water / soil quality at the site technical expertise would be required. Manpower will also be required to carry out various activities at the farm ranging from maintenance of brood, stock, rearing of fish seed, health management and transport of the stocking material to the site. For this scientific and manpower, if needed will be arranged on contractual basis.
Table 4.7.2: Proposed budget by Dept of Fisheries, Govt. of Uttarakhand S.No Component Cost (Rs) 1. 3. Upgradation of Trout hatchery Monitoring and assessment of water quality upstream and downstream of the project (including necessary equipments) Miscellaneous expenditure (including administration HR,POL Contingency etc) Total
Source: Director Fisheries, Uttarakhand Dehradun

8740000 1000000

4.

60000 9800000

Fish passes and ladder are not required as Mahseer is not available at S0, S1 and S2 so it makes no sense in investing in fish ladder and passes. Moreover seeing the performance of fish passes in other hydropower projects, the performance of these are very poor. THDC will also maintain the minimum flow required for the survival of aquatic life and maintain the water quality. For management of Snow trout, Gram Panchyats must be involved along with Dept. of Fisheries, GoUK / DCFR, ICAR, Bhimtal. Dept. of Fisheries, GoUK / DCFR, ICAR, Bhimtal will provide the technical assistance and the Gram Panchayats will be involved in intensive culture of fish. This will be an income generating activity for the local inhabitants and also provide nutrition to the malnourished population of the area. Thus, it will contribute in enhancing the living condition of the people in the area. 4.7.4 Proposed Budget for Fish Management Tentative budget proposed for Fish management is of Rs. 11.4 million given in the table below

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:36 Date: Nov 2009 Revision: R4

Table 4.7.3: Budget for Fish Management


Issues Up-gradation of Hatchery including O&M Vehicle for fish transportation Water Quality monitoring U/S and D/S Miscellaneous & Contingencies Plantation along Birahi Total Source: CES 200000 12000 200000 51,52,000 200000 12000 400000 16,12,000 I year 4740000 II Year 1000000 III Year 1000000 200000 200000 12000 400000 18,12,000 14,12,000 14,12,000 IV Year 1000000 200000 200000 12000 V Year 1000000 200000 200000 12000 Total 87,40,000 6,00,000 10,00,000 60,000 10,00,000 114,00,000

4.7.5

Recommendations THDC may undertake separate study during construction phase to assess the Impact of flow on aquatic life so that appropriate discharge could be released from dam to provide conducive environment for fish survival. A detail fishery study is recommended in the river stretch to understand the exact route that is followed by Mahseer and to understand the microclimatic requirement of the species in the area. For an in-depth study on fish potential and fishery biology in addition to aquatic biodiversity any institute which has a reputation of undertaking this kind of work can be consulted. For that purpose the Department of Environmental Sciences, HNB Garhwal University (A Central University), Srinagar Garhwal, Uttarakhand is recommended for further consultation. A MOU may be signed between THDC & Department of Fisheries GoUK/ DCFR, ICAR, Bhimtal or any other organization for Fish propagation in the area involving Gram Panchayats and local inhabitants.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 37 Date: Nov 2009 Revision: R4

4.8

GREENBELT DEVELOPMENT PLAN Although the forest loss due to various project appurtenances would be compensated as a part of compensatory afforestation, it is proposed to develop greenbelt around the perimeter of various project appurtenances, selected stretches along the periphery of water spread area, etc. The general consideration involved while developing the greenbelt are: Local/native trees growing up to 10 m or above in height with perennial foliage should be planted around various appurtenances of the proposed project. Planting of trees should be undertaken in appropriate encircling rows around the project site. Generally fast growing trees should be planted Since, the tree trunk area is normally devoid of foliage up to a height of 3 m, it may be useful to have shrubbery in front of the trees so as to give coverage to this portion. The plantation should be at a spacing of 2.5 * 2.5 m. About 1,000 trees per hectare should be planted. The plantation and maintenance of the plantation area should be done by the project proponents. 4.8.1 Species Suggested for Plantation Local species will be planted under the greenbelt development plan. The list of plant species suggested for plantation is presented below:
Table-4.8.1 Species Suggested for Plantation under Greenbelt Development Plan Sl. No Trees 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. Scientific Name Aesculas indica Albizzia lebbek Alnus nepalensis Bauhinia variegata Cedrela toona Celtis australis Cinnamomum tamala Cupressus torulosa Dalbergia sissoo Embelica officinalis Grewia oppositifolia Melia azedarach Pinus roxburghii Bombax ceiba Juglans regia Pyrus malus Prunus armeniaca Prunus communis Prunus persica Punica granatum Citrus spp. Common Name Pangar Siris Utis Kachnar Toon Kharak Dalchini Leuri Shisham Amla Biul Denk Chil Semul Walnut Apple Apricot Plum Peach Pomegranate Malta
Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 38 Date: Nov 2009 Revision: R4

Sl. No Scientific Name Shrubs 1. Agave americana 2. Euphorbia royleana 3. Opuntia dilleni 4. Jasminum humile 5. Rosa brunonii Herbs 1. Ageratum conzoides 2. Artemisia capillaris 3. Bergenia ligulata 4. Centella asiatica 5. Oxalis corniculata 6. Solanum nigrum 7. Tridex procumbens
Source: CES

Common Name Rambans Shuru Nagphani Shunjai JangliGulab Gunriya Pati Silphara Brahmi Amrit sak Makoi Ground weed

4.8.2

Precautionary Measures: Plantation activity to be carried out in monsoon months The height of the plants should not be less than 1 ft and should be in polythene bags and are not to be removed till the time of planting All plants supplied must be planted within three days of removal from the nursery The contractor will be required to water the area in case of insufficient rains after planting 2 kg of compost /manure are suggested for each pit before plantation. To ensure better growth and survival of plants, surface should have sufficient layer of good quality soil (up to 45 cm)

4.8.3

Budget for Greenbelt Development Plan 6,153 Trees are likely to be felled for development of various project sites. Double no. of trees i.e. 12,306 trees may be planted to compensate the loss of trees. A capital cost provision of Rs. 6.153 million has been kept for development of greenbelt as given in Table-4.8.2. The budget includes cost of digging of pits, fertilizers, saplings and maintenance for 3 years.
Table-4.8.2 Budget for Greenbelt Development Plan

Issue Plantation Fencing

I Year 1500000 250000 1750000


Source: CES

II Year 1500000 250000 1750000

III Year 2000000 250000 2250000

IV Year 153000 250000 403000

V Year -

Total Rs 5153000 1000000 6153000

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 39 Date: Nov 2009 Revision: R4

Bauhinia variegata

Melia azedarach

Prunus armeniaca

Juglans regia

Citrus spp.

Prunus persica

Pinus roxburghii

Bombax ceiba Embelica officinalis

Species Suggested for Plantation under Greenbelt Development Programme


Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 40 Date: Nov 2009 Revision: R4

4.9

SOIL EROSION & SEDIMENT CONTROL There is a possibility of site erosion and sedimentation in the downstream if the site activities are not carefully managed. Erosion and sedimentation will be controlled during the construction phase. Areas of the site not disturbed by the construction activities will be maintained in their existing condition. A principal effort at the construction areas will be the management of erosion of excavated surfaces especially during the wet/monsoon season when the volume of the runoff is expected to be high. Management plan for control of soil erosion and sedimentation is given below: Areas within the construction areas not disturbed by construction activities will be maintained in their existing conditions. Soil erosion and sediment control practices will be implemented prior to any major soil disturbance, or in their proper sequence, and maintained until permanent protection is established. Only approved areas due for construction activity according to the programme will be cleared and topsoil will be preserved; Prior to wet season, the contractor shall implement appropriate measures to ensure that erosion is minimized from works where the permanent drainage and erosion control measures, if any, are yet complete; Materials excavated by the Contractor from open and underground excavation, which are unsuitable for incorporation into the permanent works or are surplus to such requirements, will be disposed of as spoil dumps in spoil disposal areas. Materials suitable for roads, dams, slope protection, channel armoring or riprap and resettlement area fills will be stockpiled separately from spoil disposal areas, at agreed locations for later use by the Contractor or THDC; Soil excavated during construction will be stockpiled separately. The soil will be used for landscaping and restoration of work areas. All stockpiles and spoil dumps will be constructed and stabilized, including provision of drainage and erosion control measures in accordance with the Landscaping and Re-vegetation Plan. The height of stockpiles and spoil dumps in spoil disposal areas will be proposed in the Sub-Plan and will be limited to 3m for topsoil and material for future use. Topsoil stockpiles will be deep ripped to provide for moisture retention and re-growth. Drainage and erosion from the stockpiles will be controlled by locating them in areas away from drainage lines. The erosion of the base of the dump will be prevented by providing a silt fence to contain any sediment in any runoff resulting from stockpile or spoil dump; Stockpiles and spoil disposal areas shall not be located on drainage lines or in floodway zones or other areas important for the conveyance of floodwaters during major floods. Flooded area behind spoil disposal areas will be allowed to drain to the downstream channel;

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 41 Date: Nov 2009 Revision: R4

Plans for water management during construction will include development of drainage works, sediment traps, diversion, culverts and other structures designed to treat water before discharge into natural watercourses. All these structures will be constructed progressively prior to commencement of construction work and areas will be directed to the sediment settling areas. They will be inspected regularly for damage caused by scouring, sediment deposition, channel obstruction, and loss of vegetation cover. Sedimentation controls will be implemented in the form of silt trap fences and sedimentation ponds where appropriate depending upon the size of the catchment, and other physical and environmental constraints. The silt trap fences shall control flows along minor drainage lines, whereas the sedimentation ponds will be utilized for removing sediment-laden runoff from the construction areas. These will be built prior to the start of the activity and will be maintained until the completion of that activity. Contractor will be responsible for implementation of the above mentioned plan. Following activities will be undertaken by the Contractor for proper implementation: An assessment of the potential for water pollutants to be generated; Measures to be taken to collect, store and treat storm water prior to any discharges form the site, (considering options for water re-use on site); Management of material storage areas, including raw materials, chemicals, fuels, and oils; Measures to prevent litter entering water courses and details of permanent pollutant treatment measures or other water pollution control devices proposed for the operational stage; An inspection and maintenance program to maintain the effectiveness of erosion and sediment control measures Budget: Budget for implementation of the plan will be prepared by the Contractor. 4.10 QUARRY & BORROW AREA MANAGEMENT The contractor is required to take quarry material only from licensed quarries. In the case of existing quarries the contractor through the Engineers representative will have to ensure that all actions in these quarries are in accordance with the environmentally sound and acceptable manner. In case the contractor establishes additional quarries and dedicated crusher plants, the contractor has to ensure that all actions are in accordance with the environmental requirements. In the case of borrow areas, Contractor need to specify a detailed arrangement including the agreement with the owner of the land. The Contractor must comply with provisions of taxes, levies, royalties etc. of the State.

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 42 Date: Nov 2009 Revision: R4

Management Plan: The contractor is required to provide following details: Name, location and ownership of the borrow or quarry area; Existing land use of the area (including the access road to be developed) to be quarried; Approximate quantity of the material available; The number of trees and the species of the trees to be removed; Total area involved; Arrangement with the owner; Whether purchased or leased; A statement from the owner saying the actual arrangement (not in terms of exact monitory compensation) with him is agreeable for him; The exact restoration plan indicating the number of trees that will be planted; The action plan for leveling and landscaping in order to bring the area in conformity to the neighboring land uses; and The access roads rehabilitation. Compliance certificate of tax, levy, royalty etc. provisions. The objective of the rehabilitation programme is to reinstate the quarry /borrow pit sites to a safe and secure area, which the general public should be able to safely enter and enjoy. Securing borrow pits /quarry sites in a stable condition should be a fundamental requirement of the rehabilitation process. This could be achieved by filling the quarry/ borrow pit with suitable materials to approximately the access road level. Quarries and borrow pits may be backfilled with rejected construction wastes and will be given a vegetative cover. Plantation will be done extensively for slope stabilization. The species suggested for slope stabilization are given in the Table-4.10.1. If this is not possible, then excavation slopes will be smoothed and depression will be filled in such a way that it looks more or less like the original ground surface.
Table-4.10.1 Species Suggested for Slope Stabilization Scientific Name Common Name Rambans Agave americana Basinga Eupatorium adenophorum Shuru Euphorbia royleana Nagphani Opuntia dilleni Karonda Carissa spinarium Ber Zizyphus mauritiana Bhilmora Rumex hastatus Kath Neem Murraya koengi Bindu Colebrookea oppositifolia

Sl. No. 1 2 3 4 5 6 7 8. 9
Source: CES

During works execution, the contractor shall ensure preservation of trees during piling of materials; spreading of stripping material to facilitate water percolation and allow natural vegetation growth; re-establishment of previous natural drainage flows; improvement of
Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 43 Date: Nov 2009 Revision: R4

site appearance; digging of ditches to collect runoff; and maintenance of roadways where a pit or quarry is declared useable water source for livestock or people nearby. Once the works are completed, the contractor shall restore the environment his own expense around the work site to its original splits. A provision of Rs. 5.00 million shall be earmarked for quarry slope stabilization. The details of cost required for various measures are given in Table-4.10.2.
Table-4.10.2 Cost Estimate for Restoration of Quarry Sites I Year II Year III Year IV Year V Year 400000 400000 400000 300000 400000 250000 30000 15000 200000 50000 100000 192000 1237000 200000 30000 15000 150000 50000 100000 211200 1156200 50000 20000 10000 150000 50000 100000 232320 912320

Items Filling up of excavated sites Purchase green manure Digging pits Plantation of saplings Purchase Fertilizer Weeding & maintenance Fencing Watch & ward 4 persons TOTAL

Total 1500000 500000 80000 40000 500000 250000 300000 1830000 5000000

Source: EIA Report prepared by WAPCOS / CES

4.11

SOLID WASTE MANAGEMENT A sufficient number of garbage bins and containers will be made available at the worker camps, the areas of planned and spontaneous resettlement and at the main work sites. Garbage and other waste will be regularly collected and be transported to a designated waste disposal site. Suitable sanitary and solid waste collection and disposal facilities or systems will be provided at all camps, workshops, stores, offices, main work sites and personnel will be provided to operate and maintain the systems. During construction phase, labour, clerical staff and technical personnel are likely to congregate. The increase in population is expected to be of the order of 8,200. The average per capita solid waste generated would be of the order of 425 gm/day/person. The solid waste likely to be generated from labour camps will about 3.5 tonnes/day. For solid waste collection, 30 number of masonry storage vats, each of 2 m3 capacity will be constructed at appropriate locations in various labour camps. These vats will be emptied at regular intervals and the collected waste can then be transported to disposal site. Two covered trucks to collect the solid waste from common collection point and transfer it to the disposal site will be put to service. A suitable landfill site should be identified and designed for disposal of municipal waste generated from project township, labour colonies, etc. The waste disposal site will be located at least 2km from the nearest village. Generally,
Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 44 Date: Nov 2009 Revision: R4

from sanitary landfill sites, there is little risk from methane, generated due to the decay of organic or degradable component, as it slowly diffuses at low concentration through the covering material. To minimize groundwater pollution from leachates, bed of the disposal site(s) should be covered with an impervious material, so as to ensure that leachate does not lead to soil and water pollution. Paper and other material also flies off the landfill area due to wind action. This often creates a nuisance in the immediate vicinity of the landfill site. The landfill site, therefore, needs to be skirted with wire fence of about 3 m high wire fence with paper catchers to avoid fly of papers. Once landfill operation is complete, the entire landfill site will be covered by a depth of 1.5m of soil, and then re-vegetated according to relevant requirements included in the Landscaping & Re-vegetation Plan. A separate collection and storage procedure will be developed for hazardous or toxic waste, such as batteries, unused paint, thinners and hydrocarbons, disused electronic equipment, etc. These wastes will be stockpiled in accordance with the requirement of the applicable Laws and subsequently transported to special solid waste treatment plant capable of proper disposal of such hazardous or toxic waste as approved by UKPCB. EMC of THDC will ensure proper management of solid waste generated by project activities during construction period and will also assure that the solid waste is disposed as described in the solid waste management plan. A total provision of Rs.9.8 million needs to be earmarked for this purpose. The details are given in Table-4.11.1.
Table-4.11.1 Budget for Solid Waste Management I Year II Year III Year IV Year V Year 2500000 878000 100000 3478000 2500000 878000 100000 3478000 878000 100000 978000 878000 100000 978000 878000 9100 887100

Items Covered truck Employee Persons Miscellaneous

Total 50,00,000 43,90,000 409100 97,99,100

Source: EIA report prepared by WAPCOS / CES

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 45 Date: Nov 2009 Revision: R4

4.12

MANAGEMENT MEASURES FOR ROAD CONSTRUCTION The approach roads will have to be constructed as a part of the access to the construction site. In a hilly environment, construction of roads sometime disturbs the scenic beauty of the area. In addition, landslides are often triggered due to road construction because of the loosening of rocks by water trickling from various streams. A total length of 25.6 km of new roads needs to be constructed as a part of the proposed project. The detail of approach roads is provided in Chapter 1, Section 1.8.2, d and Chapter 3, Section 3.9.8. Steeply sloping banks are liable to landslides, which can largely be controlled by provision of suitable drainage. The basic principle is to intercept and divert as much water as possible, before it arrives at a point, where it becomes a nuisance. The other erosion hazard is that of surface erosion of the bank, which is best controlled by vegetation. However, in a steeply sloping terrain, difficulty lies in growing vegetation on steeply sloping banks. Engineering solutions such as surface drainage, sub-surface drainage, toe protection and rock bolting can be used. Landslides can be stabilized by several methods-engineering or bio-engineering measures alone or a combination of these. The cost required for implementation of various measures has already been incorporated in the overall budget earmarked for construction of roads. In hilly terrain, road construction often generates significant quantity of wastes (muck) due to the stripping of the rocks to make way for the roads. The stripped muck is generally cleared by dumping the material along the slopes. These dumped material finally flow down to the valleys and ultimately finds its way in to the river. However, it is recommended to adopt a more systematic approach. The stripped material should be collected and dumped in the designated muck disposal area which will have check dams to prevent the muck to flow down into the river. After disposal operation is complete at the dump site, dump yard should be contoured and vegetated. Due to the construction of the roads landslides results due to destabilization of the slopes. Muck will be generated due to cutting of the slopes and stripping. Various measures to be taken for cutting, stabilization of the slopes and proper disposal of muck, preventing it to go into the river are shown in Figure-4.12.1 to Figure-4.12.2

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 46 Date: Nov 2009 Revision: R4

Figure-4.12.1 Ground Conditions and Shape of Cut Slope

Figure-4.12.2 Treatment for Cut Slope Failure of Rock Mass

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 47 Date: Nov 2009 Revision: R4

Figure-4.12.3 Typical Cutting and Filling Works in Landslide Area (Large Sliding Type)

Figure-4.12.4 Typical Cutting and Filling Works in Landslide Area (Creeping Type)

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 48 Date: Nov 2009 Revision: R4

Figure-4.12.5 Typical Fill Slopes with Berms

Figure-4.12.6 Stabilization of Slopes

The various aspects to be considered while making the project roads are briefly described in the following paragraphs.
Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 49 Date: Nov 2009 Revision: R4

Construction Area for clearing and grubbing shall be kept minimum subject to the technical requirements of the road. The clearing area shall be properly demarcated to save desirable trees and shrubs and to keep tree cutting to the minimum. Where erosion is likely to be a problem, clearing and grubbing operations shall be so scheduled and performed that grading operations and permanent erosion control of features can follow immediately thereafter, if the project conditions permit; otherwise temporary erosion control measures shall be provided between successive construction stages. Under no circumstances, however, a very large surface area of erodible earth material be exposed at any one time by clearing and grubbing. The method of balanced cut and fill formation shall be adopted to avoid large difference in cut and fill quantities. The cut slopes shall be suitably protected by breast walls, provision of flat stable slopes, construction of catch water and intercepting drains, treatment of slopes and unstable areas above and underneath the road, etc. Where rock blasting is involved, controlled blasting techniques shall be adopted to avoid over-shattering of hill faces. Excavated material should not be thrown haphazardly but dumped duly dressed up in a suitable form at appropriate places where it cannot get easily washed away by rain, and such spoil deposits may be duly turfed or provided with some vegetative cover. Drainage Drainage of the water from hill slopes and road surface is very important. All artificial drains shall be linked with the existing natural drainage system. Surface drains shall have gentle slopes. Where falls in levels are to be negotiated, check dams with silting basins shall be constructed and that soil is not eroded and carried away by high velocity flows. Location and alignment of culverts should also be so chosen as to avoid severe erosion at outlets and siltation at inlets. An amount of Rs. 9.0 million (Table-4.12.1) is earmarked for the purpose of implementing these management measures described above. Contractor will be responsible for implementation of the plan.
Table-4.12.1 Budget for Implementation of EMP Measures for Road Construction I Year II Year III Year IV Year V Year Total 4000000 3000000 2000000 Total 9000000 0 0 0 0 4000000 3000000 2000000 9000000

Items

Clearing & grubbing Construction of breast walls Drainage

Source: EIA Report prepared by WAPCOS Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 50 Date: Nov 2009 Revision: R4

4.13

CONSTRUCTION CAMP & CONSTRUCTION WORKERS During construction there will be potential for construction work camps and spontaneous settlement areas to be developed without sufficient consideration of planning, health, and environmental requirements. The contractor shall plan, design and construct construction work camps for the construction workers and the officials of the contractors organization, which satisfy the following specific requirements. The EMC will be responsible for monitoring activities within the camps to ensure compliance with the plan. Normally, it has been observed in construction phase of many projects that labour camps are not well planned and are generally haphazard in their layouts, without adequate facilities. The spatial distribution of concentration of construction activities ensures that labour population is likely to be concentrated at two or three major construction sites, i.e. dam, power house and along tunnel alignment. It is recommended that project authorities can compulsorily ask the contractor to make semipermanent structures for their workers. These structures could be tin sheds. These sheds can have internal compartments allotted to each worker family. The labour camp site should have facilities like electricity, water supply and community latrines. The water for meeting domestic requirements may be collected from the rivers or streams flowing upstream of the labour camps. The water quality of Alaknanda River is good and can be used with/ without chlorination. 4.13.1 Sanitation Facilities One community latrine can be provided per 20 persons. The sewage from the community latrines can be treated in septic tanks. For each 500 persons, one septic tank should be provided. The effluent from these septic tanks can be disposed off through soak pits. Drinking water facilities and waste disposal sites will be located away from each other. The total construction time for the project is about 5 years. At peak construction phase, there will be an increase in population by 8,200. To ensure that the sewage from the labour camps do not pollute the river water, it has been estimated that about 410 community latrines and 17 septic tanks need to be constructed. The total cost required will be Rs. 12.5 million.
Items Table-4.13.1 Budget for Sanitary Facilities for Labour Camps I Year II Year III Year IV Year V Year 4000000 4000000 200000 Total 8200000

Construction of Community latrines with water supply Construction of Septic tanks Miscellaneous & Contingencies Total

1500000 10000 200000

1750000 10000 200000

1000000 10000 200000 10000 200000 10000 200000

4250000 50000 12500000

Source: EIA Report prepared by WAPCOS / CES Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 51 Date: Nov 2009 Revision: R4

4.13.2 Provision of Fuel The cost required for LPG and Kerosene distribution shall be Rs. 9.72 million and Rs. 30.60 million respectively. The total cost required for provisions of fuel works out to Rs.40.32 million. The cost has to be borne by the contractor; hence, the same has not been earmarked in the cost required for implementation of Environmental Management Plan. However, THDC can provide subsidized fuel for such labour population and their families. An amount of Rs 1.0 million needs to be earmarked for this purpose
Table-4.13.2 Cost Estimate for LPG Distribution No. of Annual requirement Total Cost @Rs. 300/cylinder Employees @1cylinder/family/month (Rs. million) (No. of cylinders) 400 4800 1.44 500 6000 1.80 600 7200 2.16 600 7200 2.16 600 7200 2.16 Total 9.72

Year

I II III IV V

Source: EIA Report prepared by WAPCOS

Year I II III IV V

Table-4.13.3 Cost Estimate for Kerosene Distribution No. of Quantity @15 litre/family/month Total Cost @ Rs. 20/litre labours (litres/year) (Rs. million) 1000 180,000 3.60 1500 270,000 5.40 2000 360,000 7.20 2000 360,000 7.20 2000 360,000 7.20 Total 30.60

Source: EIA Report prepared by WAPCOS

Item Kerosene/ LPG

I Year 200000

Table-4.13.4 Year wise Budget for Fuel II Year III Year IV Year V Year 200000 200000 200000 200000

Total Rs. 10,00,000

4.13.3 Other Facilities 1. 2. 3. 4. Paved internal roads, storm water drainage systems to prevent stagnant water, adequate day time, night time and security lighting will be provided Camp areas will be sited to allow effective natural drainage. Camps shall consist of living facilities with housing mess, recreational and sanitary facilities for all workers accommodated within the camps. Effective sediment control measures during construction and operation of the construction work camps in accordance with the Environmental Requirements, especially near rivers.
Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 52 Date: Nov 2009 Revision: R4

5. 6. 7. 8. 9.

Fire fighting equipment and services and portable fire extinguishers will be provided for all building Medical and first aid facilities will be provided at each camp area The camp areas shall have an adequate supply of potable water compliant with WHO criteria and Applicable Laws Ventilation of buildings within the camp areas will be in accordance with Applicable Laws and Standards Adequate provision for medical facility; signage for awareness on health and hygiene; and condom vending machines and other awareness materials to combat HIV/AIDS

4.14

PUBLIC HEALTH DELIVERY SYSTEM The increase in water fringe area provides suitable habitats for the growth of vectors of various diseases and they are likely to increase the incidence of water-related diseases. Malaria is one such disease. Malaria control measures which aim at destroying the habitat and interrupting the life cycle of mosquitoes by mechanical or biological or chemical means need to be implemented. The anti-malarial operations can be coordinated by Primary Health Centre (PHC) in the nearby villages and Hospital at District Headquarters in association with the project proponents. The suggested measures are given in following paragraphs: Site selected for habitation of workers should not be in the path of natural drainage. Adequate drainage system to dispose storm water drainage from the labour colonies should be provided. Adequate vaccination and immunization facilities should be provided for workers at the construction site. Labour camps and resettlement sites should be at least 2 km away from a main water body or quarry areas. 4.14.1 Development of Medical Facilities A population of about 8,200 is likely to congregate during the construction phase. The labour population will be concentrated at two or three sites. There is no medical facility in the immediate vicinity of the project area. It is recommended that necessary medical facilities be developed at the project site. It is also recommended that the dispensary should be developed during project construction phase itself, so that it can serve the labour population migrating in the area as well as the local population. 4.14.2 Proposed Health Facilities at Construction Sites and Labour Camp It is possible that during the construction period, technical staff operating different equipments is not only exposed to the physical strain of work but also to
Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 53 Date: Nov 2009 Revision: R4

the physical effects of the environment in which they are working. The workers and other technical staff may come up with common manifestations such as insect bites, fever, diarrhoea, work exhaustion and other diseases. In addition they may invariably come up with injuries caused by accidents at work site. Under all circumstances, workers need immediate medical care. A first-aid centre is to be provided at each of the major construction sites, so that workers are immediately attended to in case of an injury or accident. This first-aid centre will have at least the following facilities: First aid box with essential medicines including ORS packets First aid appliances-splints and dressing materials Stretcher, wheel chair, etc. 4.14.3 Health Extension Activities The health extension activities will have to be carried out in the villages situated in the nearby areas. It is important to inculcate hygienic habits of environmental sanitation especially with respect to water pollution by domestic wastes. There would be possibility of the transmission of communicable diseases due to migration of labour population from other areas at the construction site. The doctors from the dispensary should make regular visits to these villages and organize health promotional activities with the active participation of the local village Panchayat, NGOs and available local health functionaries. The health functionaries would undertake the following tasks as a part of health promotional activities: Collect water samples to ascertain the potability of water from different sources so as to monitor regular disinfection of drinking water sources. Maintain close surveillance on incidence of communicable diseases in these villages. Maintain close liaison with the community leaders and health functionaries of different departments, so that they can be mobilized in case of an emergency. 4.14.4 Budget for Public Health Delivery System The cost estimated for implementation of Public Health Delivery System is Rs. 37.30 million. The details are given in the following paragraphs.

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 54 Date: Nov 2009 Revision: R4

Table 4.14.1 Budget for Public Health Delivery System Items I Year II Year III Year IV Year V Year Amount ( Rs.) 16000000

Construction & establishment of Hospital / Dispensaries Doctors Nurses Health workers Attendants Drivers Health assistants Dressers Drugs & Medicine Ambulance Recurring Expenditure & Contingencies HIV / AIDS Protection TOTAL

16000000

840000 576000 480000 288000 300000 192000 120000 600000 1600000 204000

840000 576000 480000 288000 300000 192000 120000 600000 800000 204000

840000 576000 480000 288000 300000 192000 120000 600000

840000 576000 480000 288000 300000 192000 120000 600000

840000 576000 480000 288000 300000 192000 120000 600000

4200000 2880000 2400000 1440000 1500000 960000 600000 3000000 2400000

204000

204000

204000

1020000

200000 21,400,000

200000 4,600,000

200000 3,800,000

200000 3,800,000

200000 3,700,000

900000 37,300,000

Source: EIA Report WAPCOS / CES

Infrastructure Hospital / Dispensary: It is proposed that THDC may establish Hospital / Dispensary at two locations where the influx of labour is maximum. The two locations i.e dam site and colony/powerhouse site are identified for establishment of the Hospital / Dispensary. In addition to this Ambulances equipped with necessary medical aid shall be procured by the project. Assistance as and when required shall be taken from District Hospital functional at Gopeshwar. A total budget of Rs. 16 million and Rs. 2.4 million has been earmarked towards establishment of Hospital/ Dispensary and Ambulances respectively. .

Department

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 55 Date: Nov 2009 Revision: R4

4.15

RESPONSIBILITY MATRIX Environmental Management Plan (EMP) is the key to ensure a safe and clean environment. The desired results from the environmental mitigation measures proposed in the project may not be obtained without a management plan to assure its proper implementation & function. The EMP envisages the plans for the proper implementation of mitigation measures to reduce the adverse impacts arising out of the project activities during pre-construction, construction and operation stage.

Pre-construction Stage: During the pre-construction stage, management measures required will include land acquisition, the clearance of the site, borrow area & quarry area identification, arrangement of construction water, measures for relocation of sensitive receptors (if any) such as temple, mosque etc. and other utilities likely to be impacted etc. Construction Stage: Construction stage is the most crucial and active stage of the EMP. The construction activities shall increase pollution load in the atmosphere as well as there shall be some other impacts. Therefore, in addition to the monitoring of construction activity to ensure that the environment is not impacted beyond permissible limits, safety of the workers, labour camp management, disposal of construction waste and risks associated with construction activities such as accidental spillages and consequent damage to the surrounding environment in terms of loss of flora, fauna, agricultural crops or loss of fertile land shall be monitored simultaneously. Operation Stage: The operation stage shall essentially entail monitoring activity within the project area. The monitoring for pollutants specified in the monitoring plan will serve two purposes. In addition to checking the efficacy of the protection/mitigation/enhancement measures implemented, this will help to verify or refute the predictions made as a part of impact assessment. Thus, it will complete a very important feedback loop for THDC.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 56 Date: Nov 2009 Revision: R4

Table-4.15.1 Environmental Management Measures & Responsibilities - Pre-construction Stage Sl. Environmental No. Issues P1. Acquisition of Forest land Impacts (Direct/ Indirect) Management Measures Responsibility Planning and Supervision/ Execution Monitoring State Forest THDC Department, EMC of THDC

Diversion of 100.39 ha 100% compensation shall be provided towards the cost of (includes 23.13 ha land for forest land to be diverted and cost of compensatory underground works) forest land afforestation. Cost of compensatory afforestation shall be decided by the Forest Department at the time of Forest Clearance. Forest Clearance for 15.063 ha of Forest land already been obtained and possession has been taken by THDC For remaining forest land, THDC has submitted the documents to Nodal Office at Dehradun, which is under progress

P 2. Felling of Trees

The tree density in the project area ranges from 570-640/ha, which indicates the area have moderate tree cover

All efforts shall be made to preserve trees including evaluation of minor design adjustments (as applicable) to save trees. Specific attention shall be given for protecting trees of importance and of big sizes. Tree cutting is to be carried out only after all the legal requirements are completed and subsequently a written order is issued to the Project Proponent by the Forest Department. Stacking, transport and storage of the wood shall be done as per the relevant norms. Systematic corridor level documentation for the trees cut and those saved shall be maintained by the EMC.

State Forest Department, EMC of THDC

THDC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 57 Date: Nov 2009 Revision: R4

Sl. Environmental No. Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Planning and Supervision/ Execution Monitoring The Contractor EMC / THDC

P.3 Clearing & Grubbing

Loss of biodiversity Loss of habitat

Vegetation shall be removed from the construction zone before commencement of construction. All works shall be carried out such that the damage or disruption to flora other than those identified for cutting is minimum. Only ground cover/shrubs that impinge directly on the permanent works or necessary temporary works shall be removed with prior approval from the Environmental Expert of EMC. The Contractor, under any circumstances shall not cut or damage trees. Trees identified under the project shall be cut only after receiving clearance from the State Forest Department or after the receipt of written permission from THDC.

P.4 Construction vehicles, equipment and machinery

Deterioration of air quality, All vehicles, equipment and machinery to be procured and noise level and surface water brought to site for construction shall confirm to the relevant Bureau of India Standard (BIS) norms and the quality manufacturers specifications. The discharge standards promulgated under the Environment Protection Act, 1986 shall be strictly adhered to. Noise limits for construction equipment to be procured shall not exceed the value specified in the Environment (Protection) Rules, 1986. The equipment proposed to be used for construction and

The Contractor

EMC / THDC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 58 Date: Nov 2009 Revision: R4

Sl. Environmental No. Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Planning and Supervision/ Execution Monitoring

installed close to waterway/streams, must be checked and certified fit, especially with respect to the potential leakage of oil and grease. The inspection should verify that: Equipment is clean (free of mud, dirt and oil) Equipment is in good working order. A drip pan is available for equipment that shall be stored on site. Contractor has a spill kit Operator is trained on the refuelling, maintenance and emergency spill procedures. A log book shall be maintained documenting all fuelling and maintenance events (date, time, location, condition of site, weather conditions, amount of fuel on maintenance event, issues). Adequate inspections shall be conducted during the construction period. P.5 Labour requirements Employment opportunity The Contractor is encouraged to the extent practicable & reasonable to employ staff and labour with appropriate qualifications from sources within India and in particular from the local area. The contractor shall keep the Panchayat informed of opportunities for employment of local labour. The Contractor EMC / THDC

P.6 Construction

Likely sanitation & health Sitting of the construction camps shall be as per the hazards & other impacts on the

The Contractor

EMC / THDC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 59 Date: Nov 2009 Revision: R4

Sl. Environmental No. Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Planning and Supervision/ Execution Monitoring

camp location, surrounding environment due to guidelines below: design and lay- inflow of construction labourers. out Construction camps shall not be proposed within 500 m from the nearest settlements to avoid conflicts and stress over the infrastructure facilities with the local community. The waste disposal and sewage system for the camp shall be designed, built and operated such that no odour is generated. Unless otherwise arranged by the local sanitary authority, arrangements for night soils (human excreta) disposal approved by the local medical health or municipal authorities or as directed by Environmental Expert of EMC shall have to be provided by the contractor. P.7 Arrangements for Temporary acquisition of land temporary land The Contractor as per prevalent rules shall carry out negotiations with the landowners for obtaining their consent for temporary use of lands for workers camp, construction sites etc. The Environmental Expert of EMC shall ensure that the clearing up of the site prior to handling over to the owner (after construction or completion of the activity) is duly carried out by the Contractor. From P.1 (given in Annex-4.15.1) shall be used for reporting status of temporarily acquired land to Environmental Expert The Contractor EMC / THDC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 60 Date: Nov 2009 Revision: R4

Sl. Environmental No. Issues P.8 Orientation of Implementing Agency and the Contractors

Impacts (Direct/ Indirect)

Management Measures

The EMC of THDC shall organize orientation sessions and regular training sessions during all stages of the project. This shall include on-site training (general as well as in the specific context of a sub-project). The Contractor shall ensure that his environmental staff attends these sessions.

Responsibility Planning and Supervision/ Execution Monitoring EMC / THDC EMC / THDC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 61 Date: Nov 2009 Revision: R4

Sl. No. C.1

Environmental Issues Preservation of top soil

Table-4.15.2 Environmental Management Measures & Responsibilities - Construction Stage Impacts (Direct/ Indirect) Management Measures Responsibility Execution/ Civil Supervision/ Work Monitoring Loss of top soil The topsoil from all areas of cutting and all areas to be The Contractor Environmental permanently covered shall be stripped to a specified depth Expert of SC of 15 cm and stored in stockpiles. A portion of the and EMC temporarily acquired area shall be earmarked for storing topsoil. The locations for stock piling shall be pre-identified in consultation and with approval of Environmental Expert of Supervision Consultant (SC) & EMC. The following precautionary measures shall be taken to preserve them till they are used: (a) Stockpile shall be designed such that the slope does not exceed 1:2 (vertical to horizontal), and height of the pile is restricted to 2 m. To retain soil and to allow percolation of water, the edges of the pile shall be protected by silt fencing (b) Stockpiles shall not be surcharged or otherwise loaded and multiple handling shall be kept to a minimum to ensure that no compaction shall occur. Such stockpiled topsoil shall be utilized for covering all disturbed areas including borrow areas top dressing of the muck disposal areas in the agricultural fields of farmers, acquired temporarily. Residual topsoil, if there is any shall be utilized for the plantation.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 62 Date: Nov 2009 Revision: R4

Sl. No. C.2

Environmental Issues Earth from Borrow Areas for Construction

Impacts (Direct/ Indirect)

Management Measures

Disfiguration of topography due to indiscriminate digging of borrow pits Uncontrolled digging of borrow pits resulting in water accumulation & breeding of vector disease.

No borrow area shall be opened without permission of the Environmental Expert of EMC & SC. The Contractor shall rehabilitate the borrow areas as soon as borrowing is over from a particular borrow area in accordance with the Borrow Area Rehabilitation/ Redevelopment Guidelines or as instructed by the Environmental Expert. The Contractor shall develop a Comprehensive Quarry Redevelopment Plan as per the Mining Rules of Uttarakhand and submit a copy to EMC and SC prior to opening of the quarry site. The quarry operations shall be undertaken within the rules and regulations in force. Sediment traps will be installed Dust suppression measures will be implemented Landscaping will be carried out by the Contractor to rehabilitate the quarry areas as soon as quarrying is over from a particular area In borrow pits, the depth shall be so regulated that the sides of the excavation shall have a slope not steeper than 1 vertical to 2 horizontal, from the edge of the final section of the bank.

Responsibility Execution/ Civil Supervision/ Work Monitoring The Contractor Environmental Expert of SC and EMC

C.3

Quarry operation

Loss of vegetation Deterioration of surface water quality Dust generation Slope instability

The Contractor

Environmental Expert of SC and EMC

C.4

Construction water

Impact on the local water sources due to use of

The Contractor shall arrange adequate supply and storage of water for the whole construction period at his own costs.

The Contractor

Environmental Expert of SC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 63 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

construction water.

The Contractor shall submit a list of source/s from where water shall be used for the project to SC and EMC.

Responsibility Execution/ Civil Supervision/ Work Monitoring and EMC

The Contractor shall take all precaution to minimize the wastage of water in the construction process. Form C.1 (given in Annex-4.15.1) shall be used for reporting. C.5 Construction of approach roads Soil erosion Dust Generation Slope instability The Contractor shall provide necessary drainage measures to control soil erosion & fly of dust etc., and shall take necessary slope protection measures for making the slopes stable, as directed by Environmental Expert of SC & EMC. Top soil will be reused for landscaping activities Suitable retaining walls shall be constructed at muck disposal sites to develop terraces so as to support the muck on vertical slope and for optimum space utilization. Loose muck would be compacted layer wise. The muck disposal area will be developed in a series of terraces of boulder crate wall and masonry wall to protect the muck from flood water during monsoons. In-between the terraces, catch water drain will be provided. The terraces of the muck disposal area will be ultimately covered with fertile soil and suitable tree species will be planted. The Contractor Environmental Expert of SC and EMC

C.6

Muck disposal

Loss of vegetation Loss of top soil Heavy siltation of river specially during monsoon season due to muck falling in surface water/ river Loss of aesthetic value of the area

The Contractor

Environmental Expert of SC and EMC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 64 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring The Contractor Environmental Expert of SC and EMC

C.7

Water pollution from construction wastes and fuel & lubricants

Increase of sediment load in the run off from construction sites and increase in turbidity in receiving water bodies. Water pollution due to sewage from construction camps. Deterioration of surface water quality.

The Contractor shall take all precautionary measures to prevent the wastewater generated during construction from entering into Alaknanda River & its tributaries, All waste arising from the project is to be disposed off in the manner that is acceptable to the State Pollution Control Board or as directed by Environmental Expert. Construction activities shall be prohibited during the rainy season. The Contractor shall ensure that all construction vehicle parking location, fuel/lubricants storage sites, vehicle, machinery and equipment maintenance sites are located at least 100 m away from water body.

C.8

Air pollution

Deterioration of air quality due to fugitive dusts emission from construction activities like excavation,

The Contractor shall also ensure that spillage of fuels and lubricants do not contaminate the ground. All location and lay-out plans of such sites shall be submitted by the Contractor prior to their establishment and shall be approved by the Environmental Expert of SC and EMC. The Contractor shall arrange for collection, storing and disposal of oily wastes to the pre-identified disposal sites The Contractor shall take every precaution (water sprinkling etc.) to reduce the level of dust generating from construction site.

The Contractor

Environmental Expert of SC and EMC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 65 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

backfilling & concreting, and hauling & dumping of earth materials & construction spoils, and vehicular movement along unpaved roads. Deterioration of air quality due to gaseous emissions from construction equipment & vehicular traffic.

The Contractor shall provide necessary certificates to confirm that all crushers used in construction conform to relevant dust emission control legislation. The Contractor shall ensure that all vehicles, equipments and machineries used for construction are regularly maintained and confirm that pollution emission levels comply with the relevant requirements of State Pollution Control Board (SPCB). The Contractor shall submit PUC certificates for all vehicles/ equipment/ machinery used for the project and maintains a record of the same during the contract period. Monitoring results shall also be submitted to SC and EMC as per the monitoring plan. Appropriate Ventilation in Underground works.

C.9

Noise pollution

Increase in noise level due to The Contractor shall confirm the following: construction activities like operation of construction All plants and equipments used in construction shall equipment, blasting & vehicular strictly conform to the CPCB noise standards. All vehicles and equipment used in construction shall traffic. be fitted with exhaust silencers. Servicing of all construction vehicles and machinery shall be done regularly and during routine servicing operations, the effectiveness of exhaust silencers shall be checked and if found defective shall be replaced. At the Construction sites noise be restricted as per the

The Contractor

Environmental Expert of SC and EMC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 66 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

norms under Environment Protection Act 1986. A noise meter be installed for time to time measurements. Form C.2 (given in Annex-4.15.1) shall be used for pollution monitoring during construction. The Contractor shall provide: Protective footwear and protective goggles to all workers employed on mixing asphalt materials, cement, concrete etc. Protective goggles and clothing to workers engaged in stone breaking activities, welding activities etc. Earplugs to workers exposed to loud noise, and workers working in crushing, compaction, or concrete mixing operation. Adequate safety measures for workers during handling of materials at site. Helmets & Boots for workers working underground and in open excavation areas. Safety Belts etc. The Contractor shall comply with all the precautions as required for ensuring the safety of the workmen as per the International Labour Organization (ILO) Convention No. 62 as far as those are applicable to this contract. The Contractor shall make sure that during the

C.10

Safety

Personal safety measures for labour Risk from electrical equipments

The Contractor

Environmental Expert of SC and EMC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 67 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

construction work all relevant provisions of the Factories Act, 1948 and the Building and other Construction Workers (regulation of Employment and Conditions of Services) Act, 1996 are adhered to. The Contractor shall not employ any person below the age of 14 years for any work and no woman shall be employed on the work of painting with products containing lead in any form. The Contractor shall also ensure that no paint containing lead or lead products is used except in the form of paste or readymade paint. He shall provide facemasks for use to the workers when paint is applied in the form of spray or a surface having lead paint is rubbed and scraped. The Contractor shall mark no smoking in high risk areas and enforce non-compliance of use of PPE with zero tolerance. These shall be reflected in the Construction Safety Plan to be prepared by the Contractor during mobilization and shall be approved by SC and EMC. All machines to be used in the construction shall conform to the relevant Indian Standards (IS) codes, are free from patent defect, are kept in good working order, regularly inspected and properly maintained as per IS provision and to the satisfaction of the Environmental Expert.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 68 Date: Nov 2009 Revision: R4

Sl. No. C.11

Environmental Issues First aid

Responsibility Execution/ Civil Supervision/ Work Monitoring Health related problems to The Contractor shall arrange for The Contractor Environmental construction workers due to Expert of SC inadequate health & safety A readily available first aid unit including adequate and EMC measures. supply of sterilized dressing materials and appliances as per the Factories Rules in every work zone Availability of suitable transport at all times to take injured or sick person(s) to the nearest hospital Equipment and trained nursing staff at construction camp. Likely sanitation & health hazards & other impacts on the surrounding environment due to inflow of construction labourers. The Contractor Accommodation: The Contractor shall follow all relevant provisions of the Factories Act, 1948 and the Building and the other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 for construction and maintenance of labour camp. Potable water: The Contractor shall: a) Supply of sufficient quantity of potable water in every workplace/labour camp at suitable and easily accessible places and regular maintenance of such facilities. b) If any water storage tank is provided, the bottom of the tank shall be kept at least 1mt. above the surrounding ground level. c) Testing of water shall be done every month as per parameters prescribed in IS 10500:1991. Environmental Expert of SC and EMC

Impacts (Direct/ Indirect)

Management Measures

C.12

Labour Camp Management

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 69 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

Sanitation and sewage system: The Contractor shall ensure that: The sewage system for the camp shall be designed, built and operated in such a fashion that it should not pollute the ground water or nearby surface water. Separate toilets/bathrooms, shall be arranged for men and women Adequate water supply is to be provided in all toilets and urinals All toilets in workplaces are with dry-earth system (receptacles) which are to be cleaned and kept in a strict sanitary condition Night soil (human excreta) is to be disposed off by putting layer of it at the bottom of a permanent tank prepared for the purpose and covered with 15 cm. layer of waste or refuse and then covered with a layer of earth for a fortnight. Waste disposal: The Contractor shall provide segregated garbage bins (biodegradable and non- biodegradable) in the camps and ensure that these are regularly emptied and disposed off in a hygienic manner as per the Comprehensive Solid Waste Management Plan approved by the Environmental Expert of SC. Form C.3 (given in Annex-4.15.1) shall be used for hygiene reporting of construction/labour camps.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 70 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

Environmental Expert of SC shall be required to inspect the labour camp once in a week to ensure the compliance of the EMP. C.13 Clean-up operations, The Contractor shall prepare site restoration plans, which The Contractor restoration and rehabilitation shall be approved by the Environmental Expert of SC and EMC. The clean-up and restoration operations are to be implemented by the Contractor prior to demobilization. The Contractor shall clear all temporary structures; dispose all garbage, night soils, POL waste and all construction zones as per Comprehensive Waste Management Plan and as approved by SC. All disposal pits or trenches shall be filled in and effectively sealed off. Residual topsoil, if any shall be distributed on adjoining/ proximate barren land or areas identified by Environmental Expert Cultural Property Chance find during Whenever chance finds of cultural or historical artifacts Construction construction, if any. (moveable and immovable) are made the Department of Contractor / THDC Archaeology of the state Government, the Archaeological Survey of India will be informed. Should the continuation of work endanger the historical and cultural artifacts, the project work will be suspended until a solution is found for the preservation of these artifacts, or advice from the Archaeological Survey of India is obtained. Contractors, employees of the contractors and all project employees will be responsible for informing the Project Director immediately after discovery of the chance find, Contractors Demobilization Environmental Expert of SC and EMC

C.14

Archaeological Survey of India

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 71 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

without any judgment on their own on the value of the chance find. The Project head will be responsible to inform the Department of Archaeology of the State Government, and the Archaeological Survey of India, local Office, within 48 hours of such discovery. The Project Head will request for a representative of the State Department of Archaeology, Government of Uttarakhand, and/or the Archaeological Survey of India, local Office in Uttarakhand to make a site inspection. Project Head will order cessation of work in the vicinity of the chance find until the visit of a representative (usually required within 48-72 hours of notification); and follow the advice by the State Department of Archaeology, and / or the Archaeological Survey of India on possible salvage or excavation (usually required within 48-72 hours of notification). Failure to report a chance find within the 48 hours of discovery, is a punishable offence under the relevant Indian legislation. Similarly, (intentional) damage to a historical or cultural artifact is a punishable offence. Understanding existing conditions & trends related to demography and employment. Identifying potential impacts of camps and related construction activities, including the work force requirements and potential impacts on services and communities in the project areas, impact on natural

C.15

Social Management

The Social Impact of Work force of this size will be significant especially in small communities near the camp. Although the impact will be short term (Construction

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 72 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)

Management Measures

Responsibility Execution/ Civil Supervision/ Work Monitoring

period). There are also a number of specific impacts arising from the interaction between the social & physical environment which requires immediate mitigation such as the risk of exposure to Dust, the increase risk of traffic accidents etc.

resources such as forest produce and developing procedure to minimise the impacts. Identification of Mitigation measures. Direct work force local labour recruitment policy. Social management of potential risks associated with spontaneous camp followers. Management & Monitoring of health issues in the Contractors camp area / work areas which shall necessarily include test for HIV. Provision of free fuel wood, kerosene oil, or LPG to workers. Community outreach & communication programme including resolution mechanism to deal with issues and concerns that they may arise during the construction period. Code of Conduct Work Force behaviour. Detailed procedures for receiving and addressing complaints including a complaint register. Educating the work force on traditional village life. Communicating risks to villagers and river user etc.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 73 Date: Nov 2009 Revision: R4

Sl. No. O.1

Table-4.15.3 Environmental Management Measures & Responsibilities Operation Stage Environmental Impacts (Direct/ Indirect)/ Management Measures Responsibility Implications Issues Execution/ Civil Supervision/ Work Monitoring Monitoring Operation Enhancement of surrounding The EMC shall monitor the operational EMC THDC Performance environment of the project area performance of the various mitigation/ enhancement measures carried out as a part of the project. The indicators selected for monitoring include the survival rate of trees; utility of enhancement provision for relocated utilities and structures; status of rehabilitation of borrow areas; quarry areas; muck disposal sites etc. Pollution Monitoring To evaluate the performance of mitigation measures proposed in the EMP To suggest improvements in management plan, if required To enhance environmental quality To satisfy the legal and community obligations The periodic monitoring of the ambient air Pollution Monitoring Agency, EMC quality, noise level, water quality, soil pollution/contamination in the selected locations as suggested in Environmental Monitoring Plan shall be the responsibility of EMC. EMC shall appoint SPCB approved Pollution Monitoring Agency for this purpose. Form O.1 (given in Annex4.15.1) shall be used for pollution monitoring. Compensatory Afforestation plan towards State Forest Department/ EMC loss of forest Effective Catchment Treatment Plan THDC

O.2

O.3

Terrestrial Biodiversity

100.39 ha (includes 23.13 ha land for underground works)forest land

THDC

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 74 Date: Nov 2009 Revision: R4

Sl. No.

Environmental Issues

Impacts (Direct/ Indirect)/ Implications

Management Measures

Responsibility Execution/ Civil Work Supervision/ Monitoring

and associated vegetation will be affected by the project Improved accessibility of the area and increased human population in the area will increase pressure on natural resources and wildlife Increased land erosion in the catchment area

Control measures for grazing Control measures for forest fire

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 75 Date: Nov 2009 Revision: R4

4.16

ENVIRONMENTAL MONITORING PLAN 4.16.1 Introduction Environmental monitoring is an essential component for sustainability of any water resources project. It is an integral part of any environmental assessment process. Any water resources project introduces complex inter-relationships in the project area between people, various natural resources, biota and the many developing forces. Thus, a new environment is created. Monitoring will determine during the concession period (pre-construction, construction and operation) whether the mitigation measures undertaken by construction contractor, THDC and other agencies responsible for implementation of activities are achieving their objectives. A monitoring plan is framed to monitor the implementation of activities provided in EMP. EMC, VPHEP in association with Corporate office shall be monitoring the EMP. However, a third-party monitoring for the implementation of the EMP will be conducted by an agency or a committee of experts who will visit the Project site twice a year to oversee and evaluate the EMP implementation and suggest improvements. In addition, THDC has retained an International Panel of Experts on Environment and social to advise THDC during preparation phase and this will continue in the implementation phase as well. An Environmental Monitoring Programme has been designed with the following objectives: Assess the changes in environmental conditions, if any, during construction and operation of the project; Monitor the effective implementation of mitigation measures; Warning of any significant deterioration in environmental quality so that additional mitigation measures may be planned in advance From the monitoring point of view, the important parameters are water quality, ecology, land use, induced impacts etc. The suggested monitoring details are outlined in the following sections. 4.16.2 Water Quality Construction Phase: It is proposed to monitor the effluent before and after treatment from septic tanks. The frequency of monitoring could be once per month. Since, 17 septic tanks have been proposed for labour camps, a total of (17 septic tanks* 12 months* 2 samples, i.e. before and after treatment) 408 samples/year need to be analysed. The parameters to be monitored include pH, Bio-chemical Oxygen Demand, Total Suspended Solids and Total Dissolved Solids. The cost of treatment of one sample is expected to be Rs. 2,000/-. Thus, total cost for analysis of 408 samples is expected to be Rs. 0..96 million/year. The total cost over the entire construction phase works out to Rs.4.98 million.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 76 Date: Nov 2009 Revision: R4

The analysis work can be done by a laboratory recognized by the State Pollution Control Board or the same can be done in-house by THDC. Operation phase: The surface water quality of the impounded water and river Alaknanda needs to be monitored thrice a year. The proposed parameters to be monitored include pH, temperature, electrical conductivity, turbidity, total dissolved solids, calcium, magnesium, total hardness, chlorides, sulphates, nitrates, DO, COD, BOD, Iron, Zinc and Manganese. The sampling sites shall be: 1 km upstream of reservoir periphery 1 and 3 km downstream of the confluence of the tail race discharge Reservoir water The total cost of analysis will be Rs.0.09 million/year. This analysis shall be done throughout the entire life of the project. The analysis work can be conducted by a reputed external agency recognized by State Pollution Control Board or the same can be done in-house by THDC. During project operation phase, a Sewage Treatment Plant (STP) is proposed to be set up to treat the effluent from the project colony. Once every week, it is envisaged to analyse a sample each before and after treatment from the STP. The parameters to be analysed include pH, Biochemical Oxygen Demand, Chemical Oxygen Demand, Total Suspended Solids and Total Dissolved Solids. The cost of analysis of 104 samples @ Rs.2000 per sample works out to Rs.0.21 million/year. Thus, total cost for analysis in project operation works out to Rs.0.30 million/year. The analysis work can be conducted by a reputed external agency recognized by State Pollution Control Board or the same can be done in-house by THDC. 4.16.3 Ambient Air Quality and Meteorology Construction Phase: The ambient air quality monitoring during construction phase can be carried out by an external agency, approved by State Pollution Control Board (SPCB) at four locations. Monitoring location will be finalized in consultation with SPCB. Every year monitoring is to be done for three seasons namely, winter, summer and Post-monsoon. The frequency of monitoring could be twice a week for four consecutive weeks at each station for each season. The parameters to be monitored are Respirable Particulate Matter (RPM) and Suspended Particulate Matter (SPM), Sulphur dioxide (SO2) and Nitrogen Oxides (NOx). Every year, ambient air quality is to be monitored for (4 stations * 2 days/week * 4 weeks * 3 seasons) 96 days. A total cost of Rs. 0.56 million/year can be earmarked for this purpose. For a project construction phase of 5 years, the total cost required shall be Rs. 2.84 million. A meteorological station will be set up (by UKPCB with financing from the project) at one of the ambient air quality monitoring stations. Automatic recorders for temperature, wind speed and direction, humidity, rainfall needs to be

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 77 Date: Nov 2009 Revision: R4

commissioned at the site. An amount of Rs. 0.50 million has been be earmarked for this purpose. 4.16.4 Noise Construction Phase: Noise emissions from vehicular movement, operation of the construction equipment may be monitored during construction phase at major construction sites. The frequency of monitoring could be once in every three months. Monitoring location will be finalized in consultation with SPCB. An amount of Rs. 0.05 million has been earmarked for this purpose. 4.16.5 Ecology Construction Phase: A detailed ecological survey covering forestry, fisheries, wildlife is recommended during the entire construction phase. The survey can be conducted once every year for the entire construction period. The various aspects to be covered include qualitative and quantitative assessment of flora & fauna and monitoring of restoration of muck disposal area. Operation Phase: Monitoring of aquatic ecology will be essential to achieve sustainable yield of fish. Some of the parameters to be monitored are phytoplanktons, zooplanktons, benthic life and fish composition etc. The parameters can be monitored twice every year at the water sampling sites. The monitoring can be conducted by a reputed external agency for which an amount of Rs.0.3 million/year has been earmarked. Status of afforestation programmes, changes in migration patterns of the aquatic and terrestrial fauna species should be studied. The staff at the proposed unit of the Environmental Management Cell can undertake the work. A provision of Rs.0.2 million/year has been kept for this purpose. 4.16.6 Soil Erosion and Siltation Operation Phase: Soil erosion rates, slope stability of embankments of barrage, efficacy of soil conservation measures need to be closely monitored twice a year. The study can be done by the staff of the proposed Environmental Management Cell. The study should be undertaken throughout the life of the project so as to design the soil erosion prevention measures and also for the rehabilitation/decommissioning of the project. Following parameters like soil erosion rates, stability of bank embankment would be measured. In addition to above, soil quality at various locations in the catchment area needs to be monitored once every year. The parameters to be monitored are pH, organic matter and texture. A provision of Rs.0.16 million/ year has been made for this purpose.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 78 Date: Nov 2009 Revision: R4

4.16.7 Incidence of Water-Related Diseases Construction Phase: Identification of water-related diseases, adequacy of local vector control and curative measures, status of public health are some of the parameters which will be closely monitored three times a year with the help of data maintained in the government dispensaries/hospitals. The monitoring can be done by Public Health Department and other agencies e.g. hospitals and dispensaries constructed by the project proponents. The total cost required for monitoring over the entire project construction phase of 5 years shall be Rs. 2.44 million. Operation Phase: Increased prevalence of various vector borne diseases and adequacy of local vector control and curative measures need to be monitored. The monitoring can be done three times in a year. The monitoring can be done by Public Health Department and other agencies, e.g. hospitals and dispensaries constructed by the project proponents. 4.16.8 Land Use Operation Phase: During project operation phase, it is proposed to monitor land use pattern once every year using satellite data as procured by National Remote Sensing Agency, Hyderabad. Summary of environmental monitoring programme are given in Table-4.16.1 and Table-4.16.2.
Table-4.16.1 Summary of Environmental Monitoring Programme during Construction Phase S. N. Component Parameters Frequency Location 1. Effluent from septic pH, BOD, COD, Once every month Before and after tanks TSS, TDS treatment from each septic tank 2. Air quality SPM, RPM, SO2 Once every season At four locations and NOx 3. Meteorological Wind speed & Thorough out the At one of the ambient aspects direction, construction period air quality sampling temperature, relative sites humidity, rain fall 4. Noise Equivalent noise Once in three At major construction level (Leq) months sites. 5. Water-related Identification of Three times a year Labour camps and diseases water related colonies diseases, adequacy of local vector control and curative measure, etc.
Source: EIA Report prepared by WAPCOS

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 79 Date: Nov 2009 Revision: R4

Table-4.16.2 Summary of Environmental Monitoring Programme during Operation Phase S. N. Component 1. Water Quality Parameters Frequency Location pH, Temperature, EC, Turbidity, Thrice a year 1 km upstream of Total Dissolved Solids, Calcium, dam site Magnesium, Total Hardness, Submergence area Chlorides, Sulphates, Nitrates, 1 and 3 km DO. COD, BOD, Iron, Zinc, downstream of Tail Manganese Race discharge pH, BOD, COD, TSS, TDS Once every Before and after week treatment from Sewage Treatment Plant (STP) Twice a year Once in a year -

2.

3. 4.

5.

6.

Effluent from Sewage Treatment Plant (STP) Soil Erosion & Soil erosion rates, stability of Siltation bank embankment, etc. Ecology Status of afforestation programme; green belt development programme Water-related Identification of water-related diseases diseases, sites, adequacy of local vector control measures, etc. Aquatic Phytoplanktons, zooplanktons, ecology benthic life, fish composition

Three times a Villages adjacent to year project area

Once a year

7. 8.

Land use Soil

Land use pattern using satellite data pH, EC, texture, organic matter

Once in a year Once in a year

1 km upstream of dam site Submergence area 1 and 3 km d/s of Tail Race discharge Catchment area Catchment area

Source: EIA Report prepared by WAPCOS

4.16.9 Environmental Monitoring Budget A capital cost provision of Rs. 22.31 million has been kept for implementation of environmental monitoring programme as presented in Table-4.16.3.
Table-4.16.3 Budget for Environmental Monitoring Programme Items I Year Water Quality Air Quality& meteorology Noise Level Water related diseases 568000 100000 488000 568000 100000 488000 568000 100000 488000 568000 100000 488000 568000 100000 488000 Construction Phase II Year III Year IV Year Operation Phase 90000 Total 90000 2840000 500000 2440000

V Year

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 80 Date: Nov 2009 Revision: R4

Items Effluent/ Water Quality monitoring Aquatic ecologyPhytoplankton, Zooplankton, macrozoobenthos, fish Soil erosion & siltation Environmental Expert Panel (1+5) Total 2100000 I Year 996000

Construction Phase II Year III Year IV Year 996000 996000 996000

V Year 996000

Operation Phase 300000

Total 5280000

500000

500000

160000 2100000 2100000 2100000 2100000

160000 10500000

4252000

4252000

4252000

4252000

4252000

1050000

22310000

Source: EIA Report prepared by WAPCOS / CES

4.16.10 Adaptive Environmental Management Requirements The concept of adaptive management has become a foundation of effective environmental management for initiatives characterized by high levels of ecological uncertainty. Adaptive environmental management is based upon the premise that managed ecosystems are complex and inherently unpredictable. Adaptive management accepts the uncertainty that exists in the real world rather than ignoring it. Consequently adaptive management views management actions as experiments rather than solutions. Generally, adaptive management of environmental issues involve the monitoring and evaluation of the environmental performance of a particular program or activity and responding to that evaluation with appropriate changes to the program or activity. This is an iterative process, repeated for as long as it takes for an environmental system to stabilize after an impact. THDC recognizes that changes may need to be made to the methods used to address and implement the impact management and monitoring objectives determined for the Project. An Adaptive Management approach will therefore be adopted for environmental and social management components. Adaptive management will be applied to following project related impacts for at least five years irrespective of changes to these over five years period. If any impact does not show uncertainty within five years then that component will be assumed to be stabilized for environmental complexity point of view:
River Water Quality: THDC will continuously monitor river quality for three

seasons every year at 4 locations viz. at 1 km upstream of dam site; submergence area and 1 and 3 km downstream of Tail Race discharge. The monitored results will be utilized for adaptive management of environmental and ecological issues generated from managed flow.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 81 Date: Nov 2009 Revision: R4

Silt Load and Grain Size Distribution: Siltation is common phenomenon in

Alaknanda river. Upstream project activities and other natural disasters often dump large amount of silt in the river causing heavy load on power generating units downstream. For the Vishnugad Pipalkoti Hydroelectric Project, measurement of silt load & grain size distribution in the Alaknanda river within the project stretch will be undertaken every year to evaluate the effectiveness of CAT plan and further mitigation/improvement measures required if any. State of the art tools and latest models will be used for this study.
Indoor Air Quality at Power House Area: This is important parameter for

measuring occupational health of the operators in the powerhouse. Indoor air quality will be monitored twice a year for internationally established indoor air quality parameters. The results will be utilized for designing effective air quality management in the area and continuous improvement of the same.
Erosion and Landslide: Erosion and landslides will be monitored through

photographic analysis of pre selected areas of rock and land strata at 6 monthly intervals. THDC team will undertake survey of the potential areas, mark and photograph them on visible scale of clarity. Exercise will be repeated every six month and comparative analysis will be made of photograph to identify changes, if any in the rock, vegetation and strata locations. A record will be maintained of changes occurring in the character of the land strata and /or rock. Evaluation will be used for advance warning of possible erosion and landslide possibility.
Fish Management: Fish management as approved by State Fishery

Department will be implemented and evaluated for progress every year. Adaptive management principles will be implemented in case the progress is not found satisfactory. Budget for fish management will be prepared by the State Fishery Department.
Review of Adaptive Management Targets: In the first five years, adaptive

management targets and related monitoring requirements will be reviewed and amended. Thus, the adaptive management process will accommodate any changes based on new information.
Future Studies: In addition to studies already done, other studies are either

ongoing or will be conducted for the project to assist in preventing, mitigating potential project impacts. These studies will also, in some cases, facilitate each of the major areas identified for adaptive management, particularly: The effect of CAT Plan implementation on reduction on sediment and silt load; Effect on the landscape of the river banks due to reduced flow of the river; Effectiveness of the EMP implementation

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 82 Date: Nov 2009 Revision: R4

Budget: The monitoring and evaluation process will require additional and at

times, extensive surveys and primary data collection, either to establish a base line or to measure changes. In order to respond to evolving management needs, a contingency budget may be required-especially where response may require capital works. 4.17 GOOD PRACTICES 4.17.1 Landscaping & Re-vegetation For Landscaping and Re-Vegetation Plan, Contractor will follow the biodiversity management plan, muck disposal management plan, greenbelt development plan and borrow & quarry area management plan. All areas disturbed by construction activity, including temporary access roads, will be landscaped to reflect natural contours, restore suitable drainage paths and encourage the reestablishment of vegetation. Spoil heaps and excavated slopes will be re-profiled to stable batters and grassed to prevent erosion. Topsoil stripped from the areas occupied by the spoil heaps will be used for landscaping works. Re-establishment of vegetation will be commenced at the earliest possible opportunity. The EMC will be responsible for ensuring the compliance of the construction contractors. The EMC will also inspect the construction areas at the end of the construction phase to ensure that the areas have been re-graded to conform to the natural topography and that appropriate grasses and shrubs have been planted to start the re-vegetation process. The constructor contractor will be responsible for the stabilization of construction areas before they are allowed to vacate the construction areas. 4.17.2 Vegetation Clearing During construction there will be a potential for areas to be cleared in excess of real requirements and insufficient consideration given to retaining vegetation. THDC will minimize vegetation clearing for construction activities and control erosion and sedimentation from the disturbed areas. All such additional clearance will be subject to the approval of the State Forest Department, if the land is designated as forest land, or if the land supports forests. All land and forest/vegetation clearing activities will be carried out according to a site plan, which enforces the minimization of vegetation disturbance. Areas proposed for clearing will be submitted to and agreed by THDC, and only those proposed areas will be cleared. The design of roads, including temporary and permanent access roads, shall avoid crop areas where

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 83 Date: Nov 2009 Revision: R4

reasonable and practical. The application of chemicals for vegetation clearing will be minimized to the greatest extent reasonable and practical. Chemicals, if any, will be selected on the basis of being non-residual and with regard to human health. Herbicides used in the Project shall have negligible adverse human health effects; be shown to be effective against the target vegetation species; have minimal effect on the natural environment; and be demonstrated to be safe for inhabitants and domestic animals in the treated areas, as well as, for personnel applying them. Herbicides will be appropriately packaged, labelled, handled, stored, disposed of and applied according to international standards to be proposed by the Contractor. Persons applying herbicides will be provided with appropriate training, equipment, and facilities to handle, store, and apply these products properly. All herbicides shall have labels in both English and local Languages to allow those handling the herbicides to comprehend the labeling fully. Vegetation clearing will be carried out in accordance with the Logging and Removal of Waste Forestry Products discussed below.

4.17.3 Logging and Removal of Waste Forestry Products Prior to commencement of construction, THDC shall have the right, but not obligation, to remove or arrange for the removal of commercial and noncommercial timber as well as other forestry products from the designated construction areas. After commencement of construction the Contractor shall have the right to log and remove forestry products remaining as required to clear areas to carry out the construction works, as necessary. However, in either case, the ownership and any value accruing remains with the State Forest Department. The contractor shall submit plans for removal of the remaining timber and other forestry products in the areas permitted under this clause to THDC for approval at least three months in advance of any work being executed by the Contractor. The plan will be in accordance with the Contractors obligations of the contract Requirements, including in particular, the following items: erosion and sedimentation control and mitigation vegetation clearing air quality noise pollution The contractors plan shall provide detailed information regarding the proposed logging and clearing work, including the following: Clear identification and justification of the areas to be logged and cleared; Name of the company or organization to do the logging and clearing work; Schedule for logging and clearing to be undertaken;

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 84 Date: Nov 2009 Revision: R4

Clear identification of disposal sites for the timber and forestry products; All works involving the logging and removal of timber and other forestry products after commencement of construction works must be carried out in accordance with the Contractors non objected Vegetation Clearance Plan. Other than the contractors right to use timber obtained from the site for construction/ temporary works, the contractor must not sell, use or obtain any other benefit from the commercial timber/ forestry products. The contractor, with explicit permission from the State Forest Department, shall dispose of any timber or forestry products resulting from the clearing not used in the construction Works and which are not sold, in a manner selected by the contractor including leaving the timber and forestry products at the perimeter of the cleared construction areas or areas selected by the Contractor. For timber and forestry products discarded by the contractor, the THDC shall have the right to arrange for the removal of such discarded timber and forestry products. 4.17.4 Storage, Handling & Emergency Response for Hazardous Chemical During construction there will be a potential for the pollution of downstream waterways if site activities are not carefully managed. The contractor will be responsible for preparation of the management plan for storage & handling of hazardous chemical, which will be approved & monitored by the EMC. The plan will incorporate measures and process to handle situations resulting from accidental spills of hazardous materials, including chemicals and hydrocarbons or other similar incidents. General outline of the plan is given below: Refueling/Maintenance Procedure There will be no storage of fuel, oil or fluids within 100m of any surface water body. Prior to re-fueling or maintenance, drip pans and containment pans will be placed under the equipment. Absorbent blankets may also be required to be placed under the equipment and hoses where there is a possibility of spillage to occur. All used oils or fluids will be properly contained and transported to appropriately licensed (authorized) disposal sites. Spill Procedure (inside the stream, river or pond /open surface) In the case of an accidental spill, overflow or release of fluid occurs into the stream, open surface; the following steps will be followed: a) Stop the follow Shut down the equipment Close valves and pumps Plug hoses

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 85 Date: Nov 2009 Revision: R4

b) Remove Ignition Sources Shut down the vehicles and other engines Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire extinguisher on hand but keep it a safe distance away from the potential ignition source (if a fire starts, the extinguisher must be easily accessible) c) Contact the Concerned Officials and initiate emergency response Notify the site supervisor and the Contractors Environmental Officer as soon as possible The Environmental Officer will review the situation and decide if Emergency Services (like Fire Brigade) are required or not. Appropriate parties to be informed: - The Contractors Project Manager - The Site Engineer of SC through his designated Environmental Officer - Environmental Management Cell of THDC - Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable - Site Safety Officer d) Cleanup and Disposal Emergency Services will be engaged for the cleanup and disposal of contaminants released into the environment. e) Reporting The Contractors Environmental Officer will document the event and submit the reports to THDC and appropriate regulatory agencies like the State Pollution Control Board etc. The report should include reason for the spill, remediation action taken, consequences/ damages from the spill and proposed corrective actions. f) Procedure Review The Site Engineer of Supervision Consultant and THDC will review the report, determine if changes are required to the procedures and will recommend to implement all required changes. The plan will be subsequently updated and submitted to THDC for no objection, every time such an accidental spill happens.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 86 Date: Nov 2009 Revision: R4

4.17.5 Emission & Dust Control Fugitive dust from the site disturbances and emissions from the vehicles and plant have the potential to negatively affect air quality in the vicinity of the construction sites and access roads. THDC will minimize emissions from vehicles and equipment used for construction activities and minimizes fugitive dust from construction areas and from unpaved roads within the construction areas. Responsibility for incorporating specifications for regular maintenance of vehicles and equipment used will be with construction contractor. The EMC of THDC will review the contracts to ensure that these specifications are incorporated. The Contractor will aslo prepare an Emissions and Dust Control Plan. The EMC will develop a monitoring program to ensure that specifications within the construction contracts are respected. The Contractors Emissions and Dust Control Plan will include the following: Proposed methods and action to control dust resulting from construction related activities, including quarry sites, crushing and concrete batching plants, earthworks including road construction, embankments and channel construction, haulage of materials and construction work camps. Dust will be controlled by water spraying or any other similar measures. These are to be applied as necessary to reduce to a minimum spread of dust from unpaved roads when construction equipment is active, in areas of major earth excavation and any other areas which produces dust; The exhaust gases from the construction machinery and vehicles will be inspected and adjusted as required to minimize pollution levels; For all underground works/activities, the Contractor shall install mechanical/ forced ventilation systems which shall provide air pollution concentration that comply with the requirements of the National Ambient Air Quality Standard. When internal combustion engines are operated in the underground works, only diesel engines will be used. The burning of waste and/or garbage will be done in designated areas at a distance of at least 2km downwind from the nearby villages and in accordance with Applicable Law and the Contractors Environmental Monitoring and Management Plan. Burning of any material which produces toxic gases will not be allowed. 4.17.6 Environmental Training for Construction Workers During construction there will be a potential for workers to damage the forests and waterways adjacent to camps and work areas. The contractor shall prepare a training plan for all construction workers. The training will need to ensure that all employees of the contractor are aware about their duties, responsibilities, liabilities and consequences of non-compliance. All employees of the contractor will be required to comply with environmental protection procedures and they will be able to provide evidence that they have attended the training sessions detailed in the plan.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 87 Date: Nov 2009 Revision: R4

The goal of the Environmental Training for Construction Workers program will be to educate all construction workers on the following issue: traffic regulations, illegal logging and collection of non-timber forestry products (particularly in the resettlement areas), hunting and fishing restrictions, sanitation practices, waste management, erosion control, general health issues including the information and education, specific health issues related to HIV/AIDS, safety issues and general information on the environment in which they will be working and living. Training will also include awareness generation that (personal, not related to work) use of explosives and chemicals is not permitted; or hunting and fishing is not permitted. Contractors will establish rules and penalties for violation. These training sessions will be organized by the contractor, and would include formal training sessions, posters, signage in construction and camp areas, and tool box meeting. These would be in addition to the training program organized by EMC, THDC. However, both training program could be coordinated.

4.17.7 On-Site Traffic & Access Management During construction there will be a potential for use of large numbers of vehicles of variable size, leading to hazardous conditions on public roads, camps, project roads and work areas. To address the potential hazardous conditions, the contractor will prepare and implement an On Site Traffic and Access Management Plan. The plan shall address the following: Details regarding expected road quality, maximum permissible vehicular speed on each section of road, establishment of safe sight distance including within the construction areas and construction camp site; Detailed plans for signage around the construction area to facilitate traffic movement; Estimated maximum concentrations of traffic and effects on existing traffic patterns for different times of day, and at individual locations within the construction area; Provisions to be made by the contractor for adequate off-road parking of all construction related vehicles; Plan to be followed while moving special loads, such as hazardous material, or heavy loads. Plan for controlling site access, including both construction areas and construction camp areas; Monitoring and methods of enforcing the requirements of the traffic management plan. Construction traffic, including heavy loads, must not damage public roads. Personnel authorized to the construction areas will be briefed on traffic regulations applicable to the construction area. Parking will be provided for all classes of vehicles traveling to the site. At no time shall construction vehicles be parked in a manner which may restrict movement of traffic on public roads.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 88 Date: Nov 2009 Revision: R4

Signage should provide directions to various components of the works, provide safety advice and warning. All signs will be in both English and Local Language. 4.17.8 HIV/ AIDS Prevention Measures To effectively address the HIV/AIDS issues and the associated risks, the contractors will associate with the State AIDS Control Society (SACS) fully and without any failure or excuse. THDC will insist that the contractor implement all advice from the SACS. In addition, the contractors will be obliged to implement regular and periodical awareness campaign on HIV/AIDS, provide for all awareness materials and their dissemination, including erecting large signage in prominent areas; and to provide for and maintain condom vending machines in all work areas including construction camps, pubic toilet booths, and work sites annually are as under; Table 4.17.1: Responsibility for AIDS/HIV Protection
Contractor Responsibility Item Condom vending machine , (1 machine per 250 workers at any point of time) Signboards on AIDS/HIV Awareness. (At least one prominent at each work site) Workers awareness camps ( twice a year ) HIV/ AIDS testing of workers (At least one camp annually for one week ) Contractor may tie up with district / state hospital for regular referrals No./unit 8 No. THDC Responsibility (Project Hospital Authorities) No./unit Item In discussion with (SACS) finalize referral system. (State Hospital, Gopeshwar) SACS collaboration initial development of testing procedures at VPHEP Hospital Monitor Compliance Contractors -

10 No.

5 times per year

20 camps 1 camp

monthly

Support SACS , if needed by SACS to organize HIV / AIDS Camp at Pipalkoti.

2 camps per year

5 times a year

Budget for HIV/ AIDS control for contractor is provided in EPC contract. A budget of Rs 9,00,000 lakhs (Rupees Nine Lakhs) is earn marked for THDC under Public Health Delivery System.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 89 Date: Nov 2009 Revision: R4

4.18

CAPACITY BUILDING OF THDC THDC is committed to power development in a sustainable manner. The vision document of THDC states as: A major global player in power sector, providing quality affordable and sustainable power with commitment to environment, ecology and social value & Create work ethos of growth through professionalism and achievement of excellence Driven by its commitment for sustainable growth of power, THDC has evolved a well defined environment management policy for minimizing environmental impact arising out of setting up of power units and preserving the natural ecology. THDC has adopted an Environment, Policy which reiterates companys commitment to sustainable development which is within the carrying capacity of the ecosystem and promotes the improvement of quality of life. 4.18.1 Environmental Management measures taken by THDC The Tehri Hydro Power Project is now fully operational and THDC has successfully implemented environmental management measures and have ensured that their efforts towards improving the environment match with the developmental efforts in the power sector. THDC has prepared and followed a comprehensive Environment. Management plan and Rehabilitation & Resettlement Plan for its Environmental and R&R related activities in Tehri Hydro Power Project. The various environmental measures undertaken by THDC is given below: Implemented CAT Plan in 52,204 ha in the Catchment of the project. Command Area Development Plan (CADP) for 2.7 lac ha and stabilize existing irrigation area in 6.04 lac. ha area. Prepared Disaster Management Plan (DMP) Carried Water Quality modeling study Established River Valley Authority under Uttranchal River Valley Development & Management Act 2005 To meet the existing international standard in safety a Project Safety Manual is prepared and implemented Foundation of Engineering College and Hydro Power Institute at Village Dibnu in Tehri- unique Institute for meeting the requirement of skilled Manpower particularly in the Power Sector Adopted 2 ITI under public private partnership model located close to the project sites at Chamba,Tehri Garhwal and Gopeshwar, district Chamoli, Uttarakhand THDC is also engaged in the engineering consultancy work for stabilization of Varunavat Parvat in Uttarkashi entrusted by Government of Uttarakhand

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 90 Date: Nov 2009 Revision: R4

4.18.2 i

ISO 14001 ENVIRONMENT MANAGEMENT SYSTEM Introduction & Approach The ISO 9000 Quality Management System (QMS) and ISO 14401 Environmental Management System (EMS) standard take a management system approach to achieving specific objectives. In case of ISO 9000, the objective is enhanced product quality; for ISO 14001, it is enhanced environmental quality. It contrast to performance-based controls that establish specific requirements, the ISO approach focuses on the process by which organizational policies and objectives are established and achieved. The rationale behind the approach is based on three general assumptions: 1. effective policies will be developed and achieved within the context of effective management system; 2. by exploiting common characteristics, the same management can help any organization in any industry to achieve designated objectives and targets on a consistent basis; and, 3. an effective management system must be flexible enough to accommodate characteristics specific to any organization to which it is applied.

ii

The ISO 14001 Environmental Management System (EMS) Standard The ISO 14001 Standard establishes a framework of basic requirements for the design of an effective and responsible environmental management system. Although companies can self declare their compliance with the standard, it is also amenable to independent third-party certification. Its requirements include: the development of an environmental policy; the implementation of a management system based on the concept of plan-do-check-act (PDCA); and a commitment to continual improvement of the management system. It should be noted that this International Standard does not establish absolute requirements for environmental performance beyond commitment, in the policy, to compliance with applicable legislation and regulations and to continual improvement.

iii

The 14001 EMS Approach 1. A commitment by top management to define the organizations environmental policy and implement the EMS; 2. The establishment of a procedure by which all aspects of the organizations activities which have, or can be expected to have, environmental impact are identified and documented; 3. The establishment of an effective procedure by which all relevant legal and regulatory requirements are identified, and to comply with them; this also

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 91 Date: Nov 2009 Revision: R4

involves a commitment to comply with any non-regulatory guidelines to which organization voluntary subscribes (e.g. policies and objectives stated by an industry association. 4. The identification of environmental objectives and targets, quantified where practicable, which effectively address each of the following: the overall environmental policy, the organizations environmental impacts, and the organizations legal and regulatory requirements; 5. The development of a procedure to monitor performance against the objectives and targets, and to channel this information back into the EMS; 6. Creation of a workplan (subject to financial constraints) through which all objectives and targets are to be achieved; this workplan may consider changes in production processes, product design and services provided, employee training, communication of results, evaluation of performance indicators and documentation of the above; 7. A regular management review which addresses the possible need for changes to policy, objectives and other elements of the environmental management system, in the light of the EMS audits of the entire management system; 8. A commitment to continual improvement and the prevention of pollution. The ISO 14001 standard is a generic standard which is intended to be applicable to any sized organization in any sector. It does not refer to relevant international guidelines or agreements that may exist. ISO has established a new type of document to help meet the needs of different industrial sectors. These technical specifications must be reviewed every three years and, at the end of the second review, must either be withdrawn or revised to become a full ISO standard. As ISO is the process of harmonizing ISO 9000 with ISO 14001, any structural change in one will have to be mirrored by changes in the other. This ISO 14001-based-specific standard would have to be reviewed every three years; after six years (two cycles of review) it would qualify to become a full ISO standard. Even while it remains a technical specification document, auditors could refer to the guidelines it contains when assessing the quality of a dam operators management system against the ISO 14001 standard. iv Benefits of the ISO 14001 There are a number of benefits associated with the ISO-based approach. These involve the benefits of Working with a strong institutional partner;

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 92 Date: Nov 2009 Revision: R4

Access to funding for the development of the standard; Implementing the guidelines through a management framework that corporate/companies are familiar with; Assessing training needs and developing training programmes; and Ensuring that the guidelines are regularly reviewed. A Strong Institutional Partner: Developing an international certification system through ISO would give access to the strong institutional components that make up ISO. In particular, the vast network of national standard bodies and the well defined standard-drafting procedures will obviate the need to establish its own consultation and distribution networks. In many cases, national standard bodies have participation mechanics that enable national stakeholders to be involved in the international process. Financial Support: Second, the development of an international dam certification system through, ISO would reduce the fund-raising pressure on the project proponents. If ISO agrees to develop a standard, the drafting process is managed and funded by one or more national standard bodies. Although these bodies do not have particular abundance of funds, they do have close links with the access to industry associations and relevant government departments. These links give national standard bodies access to public and private sources of funds that may not be readily available to the project proponents. Private Sector Familiarity: Third, using the ISO-approach will help companies to guidelines, and may increase their credibility. Many companies are already familiar with ISO management system approach. Capacity Building: Clause 4.4.2 of the ISO 14001 standard requires organizations to identify training needs, to require all personnel to acquire relevant training, and to ensure that employees are aware of potential impact of their activities. In this way, the ISO 14001 standard can help dam operators to develop the institutional capacity needed to comply with the requirements of the World Commission of Dams (WCD) guidelines. Evolution of the Standard: Fifth, as per the WCD, ISO standard, certification system will be continually reviewed. Not only are national standard bodies responsible for the development of standard, so too must they review and update the standards at least every years. v Environmental Management System (EMS) THDC India Ltd. wants to incorporate an Environmental Management System for managing and implementation of the Environmental and Social Management Plan (including the Rehabilitation Plan) as part of the proposed dam construction project. The THDC India Ltd. has therefore planned to introduce a formal ISO 14401 compliant EMS into its construction and corporate operations and aims at achieving a certification. The main objective of THDC is to implement an operational level EMS system with a regional function with practical measures to protect the environment.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 93 Date: Nov 2009 Revision: R4

As part of implementation of EMS plan and process will be developed in the context of organizations environmental and aquatic policies, and the various environmental risks will be identified as part of corporate review processes. THDC will call for a open bid for consultancy services for attaining ISO 14001 2004 certification for the Vishnugad Pipalkoti Hydro Electric Project (4 X 111 MW), Chamoli District, Uttarakhand. The different activities to be carried out by the consultant as part of ISO 14001 2004 implementation and certification are given under the various phases starting from A to D. Phase A 1. Visit of the consultants to Vishnugad- Pipalkoti site to analyse the gap 2. Preparation and submission of gap analysis report and action plan for carrying out consultancy process within a limited time frame Phase B 1. To prepare awareness program for key personnels on ISO 14001:2004 2. Listing out all the activities involved at VPHEP 3. Conducting study for identifying the aspects, related to their construction and operation activities 4. Identifying significant aspects/activities of the project 5. Assistance/guidance in identifying all legal and other statutory requirements 6. Identifying objectives, targets related to significant aspects 7. Preparation of environmental monitoring programs for achieving as part of Environmental Management System (EMS) for achieving objectives and targets laid out by THDC for VPHEP project 8. Development of a Corporate Policy for THDC 9. Development of Environmental Management System (EMS) Manual & Procedure for THDC Phase C 1. Consultant will help in providing internal auditor training to key identified personals of THDC on ISO 14001:2004 2. Assist /guide THDC officials in identifying corrective actions 3. Assist / guide THDC officials in conducting management review meeting and finalising the issues to be taken up for discussion 4. Assist / guide THDC in identifying certification bodies to get themselves certified Phase D 1. Assist / guide THDC officials in complying with the non-conformances and closing the points raised by the certification body during Pre-Assessment audit 2. Assist / guide THDC officials in complying with the non-conformances and the points raised by the certification body during documentation/surveillance audit

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 94 Date: Nov 2009 Revision: R4

3. Assist / guide THDC officials in complying with the non-conformances and the points raised by the certification body during certification audit 4. The consultant should be responsible and should ensure that ISO 14401:2004 certification is awarded to THDC by the accreditation body within the time frame as set out in the contract with the ISO consultant vi Departmental Training of ISO 14001-2004 All departments of THDC will be covered under the Environmental Management System (EMS) under ISO 14001:2004 implementation. Training Programs a. Induction / Awareness Training Induction Training and awareness programs will be conducted by the ISO consultants for all the staffs of THDC at different levels. Different training programs will be conducted for different level of officials in different batches. At the executive levels awareness programs on ISO 14001:2004 series will be held for approximately 35 in 2 batches. b. Training on ISO 14001:2004 Documents (Manual, Procedure & Controls) Document

Training program will be conducted by the ISO consultants on ISO Manual and Procedure and control of documents for each of the functional head and his or her representatives for all the personnels in separate batches depending on the total staff strength of THDC involved in VPHEP. The different responsibilities of each of the functional heads will be clearly spelt out as part of the ISO procedure and their duties adequately explained by the ISO consultants. c. Internal Quality Auditors Training Training program will be conducted by the ISO consultants for Internal Auditors to carry out Internal Quality Audits prior and after the surveillance and recertification audits to be carried by the certification firm. Internal Auditors training is an important part of implementation and monitoring of EMS as part of ISO 14001:2004. The duration of the above programs shall be finalized by the ISO consultants in discussion and in mutual agreement of the THDC officials. d. Other Training Programs Any other training program if required and felt necessary will be carried out by the ISO consultants for implementing ISO 14001:2004 for the THDC office at Vishnugad-Pipalkoti office at Chamoli. The consultants will specify and fix the

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 95 Date: Nov 2009 Revision: R4

duration and details of such programs if any in consultation with the THDC officials, if any. e. Logistics, Equipment and Accessories All the training programs to be carried out by the ISO consultants will be framed and conducted in coordination and consultation with concerned THDC officials of Vishnugad Pipalkoti Project. All training programs will be carried in their THDC office either in Pipalkoti or in Rishikesh wherever feasible where adequate space and logistics in the form of presentation equipments in the form of Over Head Projectors (OHP), projectors, screen, Audio system and auditorium or hall is available to accommodate for at least 25 persons at one time. However any other equipments or accessories, stationeries required in connection for imparting such training program shall be the responsibility of the consultant. THDC will provide the local transportation facility to the ISO consultant for carrying out the training program. f. Study & Course Material All the study and course material required in connection with various training programs to be carried out by the consultants while imparting ISO 14401:2004 training program will be provided by the consultants to each of the participant(s) of THDC free of cost. g. Consultants Visits for follow up Two (2) representatives from the ISO consultants side will visit THDC office at Pipalkoti at least twice (2) a month or as required for the accomplishment of the job. These consultants will be provided with company vehicle/ taxi from Rishikesh to Vishnugad Pipalkoti Hydro Power Project and back. THDC will also arrange for their accommodation in one room of their THDC Guest House / Hotel whichever available at Pipalkoti with lodging facilities free of cost. vii Surveillance /Recertification Audit Once the ISO consultant ensures that an ISO 14001:2004 certification has been accredited to Vishnugad Pipalkoti Hydro Electric Project of THDC by a certification audit body, timely surveillance and recertification has to be carried out for operational level implementation of EMS by the third party audit to be carried by the certification agency. By this significant non compliances with procedures will be reported for maintaining the certification. For timely attending to and removal of the non conformances as per the ISO 14001:2004 procedures and to the comments raised by the certification company, internal audits has to be carried out by the group of Internal Auditors of THDC trained by the ISO consultants for this purpose. Timely recertification Audits will also be carried out by the certification audit body for upgradation of the EMS as per the latest certifications.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 96 Date: Nov 2009 Revision: R4

A summarized Concepts of ISO 14001:2004 is given in Annex-4.18.1. Applicability of EMS for various activities of VPHEP viii Monitoring Activities during Implementation of EMP Water quality, heavy metals, and the fishery. To monitor the development of the physio-chemical environment of the new storage, including changes associated with thermal stratification and decay of flooded vegetation; To assess the spatial and temporal distribution of metal contamination in the water and sediments. To assess the effect of any contamination on the productivity. To monitor the fish population and development of the trout fishery. To assess the effect of release from the lake on the water quality in the river Alaknanda and its Tributaries. The monitoring programme included water, soil and sediment sampling; lake productivity measurement; and investigation into aspects of the fishery such as heavy metals levels in trout, distribution of fish in the rivers, growth rates, physiological condition and reproductive success of the fish. Ongoing monitoring had established there were no major problems with either copper toxicity or the development of the river fishery. Dissolved organic matter binds with copper, rendering it biologically unavailable, and so protects organisms from any toxic effect of this heavy metal. Based on these results, the remediation works were found to be adequate for the protection of the fishery. The river supports snow trout fishes for which constant monitoring of copper and other heavy metals like nickel and cobalt residues from the proposed turbines has to be carried out on a routine basis. Oxygen depletion is likely to occur in trail race water soon after commissioning of the power project. Water containing very low levels of oxygen accompanied by hydrogen sulphide is likely to be noted in the tailrace, a common problem in the early life of rivers or water bodies. The low level of oxygen is likely to be caused by thermal stratification. This results in the release of cold, de-oxygenated bottom water into the river. So after investigation and considering mitigation option, water discharged downstream from the power station may be aerated by operation of a jet pump installed on the turbine. This may be utilized to increase dissolved oxygen concentrations at appropriate times. Ongoing and continuous monitoring of the quality the water leaving the tailrace ensures adequate notice of low dissolved oxygen levels, and timely utilization of the air injection facilities in the turbine. Once operational, with respects of auditing, VPHEP, THDC should undergo frequent internal audits as part of the organization EMS, and periodic external audits to maintain ISO 14001:2004 certification.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 97 Date: Nov 2009 Revision: R4

ix

Main Lessons Learned The example illustrates six aspects of relevant practice: Voluntary adoption of an EMP in the absence of any regulatory requirement. Attention to visual aspects of design and construction so as to minimize impacts on visual values, important both intrinsically and in relation to tourism and recreation. Detailed attention to water quality during design, construction and operation, with specific attention to recreational and commercial fisheries. Partnering with other stakeholders to develop the science-based knowledge needed for power station operations, in this case through the Environmental Study of Vishnugad Pipalkoti Hydro Power Project, Chamoli District for THDC India Ltd.

Compliance with national Guidelines and Policy EIA Notification of September 14, 2006 Air (Prevention & Control of Pollution) Act, 1981 Water (Prevention and Control of Pollution) Act, 1974 and Cess Act of 1977 Forest (conservation) Act, 1980 and its amendment in 1988 Forest (conservation) Rules and its amendment Act,2003 The Wildlife (Protection) Act, 1972 Wildlife (Protection) Amendment Act,2002 Ancient Monuments and Archaeological sites & Remains Act,1958 The Land Acquisition Act, 1894 & 1989

xi

Budget The above mentioned activities involve capital investments, annual recurring and implementation costs. Some of the activities are like initiating the process of Quality Management System for Vishnugad Pipalkoti Office; implementing Environment Management System (ISO 14001:2004); formulation of Quality Manual & Quality Procedure and Planning, Monitoring and Implementation of EMS. An approximate lump sum budget of Rs.0.8 million has been kept towards hiring of the ISO Consultant. Once EMS (ISO 14001:2004) implementation in Vishnugad Pipalkoti Project THDC office has been initiated and implementation has been completed by the consultant it will also ensure VPHEP, THDC of a proper certification from an accredited certifying agency. Periodic surveillance and recertification audit will be carried out by the certification agency during its total project life. The budget for the ISO 14001:2004 certification firm has not been considered as part of the above budgetary estimate as the budget can only be provided by the accreditation firm to be shortlisted by the VPHEP, THDC officials as per their requirement. Some of the costs are recurring which include periodic surveillance audit and recertification audits to be carried out by the certification agency as part of third party audit.

4.18.3 OHSAS 18001

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 98 Date: Nov 2009 Revision: R4

It is suggested that THDC may adopt Occupational Health & Safety (OHSAS) 18001. The Occupational Health & Safety (OHSAS) 18001 is an internationally recognized voluntary, management system to enable organizations to manage their occupational health and safety (OHS) risks, and thereby improve their overall performance. OHS pertains to the conditions and factors that affect the well being of all employees, temporary workers, contractor, visitors and any other person in the workplace. The OHSAS 18001 specification is compatible with ISO 9001 (Quality) and ISO 14001 (Environment) management systems. Objective The primary objective of this advanced course in OHS Auditing is to impart training on the principles and practices in auditing management systems for conformance with national and internationally accepted norms on OHS, in particular those of BSI-18001. The major elements of the course, providing both knowledge and practical skills essential to an OHS Auditor, are reproduced below. Occupational Health & Safety Basics Introduction to the OHSAS 18001 Implementing OHSAS 18001 Introduction to OHS Management System Auditing OHS Management System Planning Techniques Auditors Qualifications- ISO 19011: 2002 OHSAS 18001 Requirements: The Plan Elements of the PDCA Cycle OHSAS 18001 Requirements: The Do Elements of the PDCA Cycle OHSAS 18001 Requirements: The Check Elements of the PDCA Cycle OHSAS 18001 Requirements: The Act Elements of the PDCA Cycle OHS Legislation in India OHS Auditing Principles The Registration Cycle This course is designed to build understanding and develop skills essential to auditing an OHS management system. The course is therefore useful to Internal auditors in companies with an established OHS management system Professionals/ Practitioners who conduct OHS audits, in various organizations Companies planning to establish an OHS management system in the near future An approximate lump sum budget of Rs1.2 million has been kept towards OHSAS 18001 4.18.4 Safety Manual of THDC It is the policy of THDC to provide a safe place to work for its employees. THDC has their own Safety Manual for the Hydropower Projects. It is acknowledged that THDC has the ultimate responsibility for compliance with all the requirements of applicable safety rules and orders on the VPHE Project. THDC management will ensure that all employees including contractors and subcontractors, are aware of their personal responsibility in maintaining an accident-free and healthy work environment.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 99 Date: Nov 2009 Revision: R4

The purpose of the safety Manual is to present information & rules, the observance of which will be helpful in preventing occupational injuries. Every employee of THDC India Ltd. is required to comply with all the rules laid in the manual, that are applicable to his area of operation, the purpose of this manual is to aid employees to discharge fully their duties as regards to the safety of themselves, their colleagues, plants equipment, materials and all other valuable resources. Guiding Principles The occupational health & safety policy is guided by the following principles: It is essential to respect human life All accidents are preventable To ensure that injuries are prevented Working safely is a condition of employment All hazards can be safe guarded either physically or through safe working procedure Safety training is essential at all levels Whatever we do, we shall do it safely Safety Management Arrangement As per the manual, Safety Committee to be formed according to Section 38 of B&OC Act, 1996 & 41 G of the Factory Act, 1948, as follows: Representative of the Management: General Manager (Project); a Senior Officer nominated by the GM (Project); one representative from each site, operation, maintenance, purchase, contractor, safety and P&A. Representative of the Workers: one nominated member each from all department. At all project sites, a Health Center should be well equipped to detect and prevent occupational/work related diseases/ injuries and facility to treat them. A Medical Office will head the Center. Responsibility a) General Manager (Project) Is entrusted with the responsibility of ensuring effective health and safety management at Site/ in Plant. b) Engineer-in-Charge/ Departmental Heads Are responsible to maintain the safe working conditions and prevention of accidents in their own area/sites. c) Chief Safety Officer

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 100 Date: Nov 2009 Revision: R4

To advise on planning & organizing, measures necessary for effective control of personal injuries To advise on safety aspects in a building and other construction/ commissioning works and to carry out detailed safety studies of selected activities. To advise on purchase of personal protective equipment conforming to national standard and ensuring their quality. To investigate all fatal and other selective accidents and take remedial measures. To investigate the cases of occupational diseases contracted and report their occurrences and dangers involved therein. To organize, in association with concerned departments, campaigns, competitions, contests and other activities, which will help to develop & maintain the interest of workers in establishing and maintaining safe conditions of work and procedures. Supervise and guide safety precautions to be taken in construction/ commissioning works of the organization. d) Materials Management Department Consider the safety aspect while purchasing plant machinery, equipment, materials etc., where necessary consult Safety department. Obtain and provide to the user/ plant, material safety data sheet (MSDS) while purchasing any chemicals. e) Obligation of Workers To observe safety rules and practices to protect themselves and the fellow workers. To report all injuries, however minor and to avail first-aid. To report unsafe conditions, equipment and practices as soon as the same are observed. To take all precautions against hazardous foreseen. f) Obligation of Contractors Obtain permission from the concerned site-engineer/ departmental head before starting any work at sites Discuss all possible hazards with the Chief Safety Officer and workers, their remedial measures and implement those before starting the work. The contractor shall not employ any workers below the age of eighteen years. Ensure that every worker uses personal protective equipment provided to them. Fulfill all statutory obligations and appraise the Corporation as per requirement e.g. Building & Other Construction Workers Act & Central Rules; Indian Electricity Rules, Factories Act/ Rules, coverage of workmen under Insurance Policy act. In order to supervise the work from safety point of view, the contractor shall provide a full time safety engineer, who shall report to the Safety Officer/ Site Engineer of the THDC and shall be responsible for coordinating the safety programme. Contractor shall also provide necessary certificates and documents to the THDC as and when required by them.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 101 Date: Nov 2009 Revision: R4

The Contractor shall provide all necessary fencing and lights to protect the public from accidents and shall be bound to bear all expenses of defense of every suit, action and other proceedings at law that may be brought by any person for injury sustained owing to neglect of the precautions and to pay any damages and costs which may be awarded in any such suit, action and proceedings to any such persons or which may with the consent of the contractor be paid to compromise any claim by any person. g) Transporters Strictly follow all laws relating to safe transportation of material and men inside the work premises. Follow all safety rules while parking their vehicles. Safety Programme and Its Implementation a) Within 30 days from the date of issue of the notice to commence, the Contractor shall submit, in writing, his proposal for a comprehensive safety programme covering all aspects of the works. b) This safety programme shall have detail policies, procedures and plans which the Contractor intends to implement to ensure the safety and health of his employee. It shall comply with the standards and regulations in force in India applicable to construction safety. c) The Contractor shall designate a competent employee specially trained and experienced to act as Safety Officer, who will administer and be responsible for the implementation of the Safety Programme. He shall carry out frequent and regular safety inspections of the working areas, materials and equipment. The name and qualifications of the Safety Officer shall be submitted for approval of the Engineer-inCharge prior to his appointment. d) The Contractor shall be responsible for enforcement of the health & safety provisions for his subcontractors to be employed at the site. e) Prior to the start of any major construction activity or hazardous operation, the contractor shall submit to the Engineer-in-Charge for approval of a specific plan for safety precautions covering such operation. f) All accidental occurrences with serious accident potential such as major equipment failures, contact with high voltage lines, exposure to hazardous materials, slides, caveins etc., shall be immediately reported to the Engineer-in-Charge.

g) All serious and fatal injuries and diseases caused by the progress of work shall be immediately investigated by the Contractor and a comprehensive report shall be submitted to the Engineer-in-Charge.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 102 Date: Nov 2009 Revision: R4

h) In case of a fatal accident, only rescue and emergency teams and operations shall be permitted at the place of the occurrence until the Engineer-in-Charge gives permission to resume normal operations. Fire Prevention a) b) All construction areas and storage yards shall be kept clean and well arranged. A clear space of 15 m around the outer boundary of saw mill and lumber storage area may be provided. All lumber shall be stored in sections with firebreaks with a distance of 15 m between consecutive sections. All combustible waste material, wood scaling, solid rags etc. shall be removed daily and burned in suitable burning areas. Sawmill and lumberyard shall be kept free from accumulation of combustible debris. All buildings, rooms and compartments where flammable liquids are present shall be adequately ventilated. Smoking shall be prohibited in all flammable material storages viz. carpentry, paint shops, garages, service stations etc. No Smoking signs shall be posted on all such areas. Accumulation of flammable liquids on floors, walks etc. shall be prohibited. All spills of flammable liquids shall be cleaned up immediately. Smoke pipes from Diesel Engines passing through roof of combustible material e.g. in compressor stations at dam site and quarry shall be insulated by asbestos. All joints of smoke pipe shall be riveted, welded or otherwise securely fastened together and supported to prevent accidental displacement or separation. The joint shall not be leaky. Petrol or other flammable liquids with a flash point below 100 degree F shall not be used for cleaning purposes. All electrical installations shall be properly earthed. Repairs shall not be made on electrical circuits until the circuit has been de-energized.

c)

d)

e)

f)

g)

h)

i)

Fire Fighting Arrangements a) Fire extinguishers and fire buckets, painted red shall be provided at all fire hazardous locations viz. batching & mixing plant, winch house, workshops, store yard, saw-mill, switch gear room, compressor station, office establishment etc. The extinguishers shall be inspected, serviced and maintained in accordance with manufactures instruction. Extinguishers shall be located outside doorways or other places of relative safety and accessibility.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 103 Date: Nov 2009 Revision: R4

b)

Full reliance shall never be placed on portable hand extinguishers as all of these have a very limited capacity. Water, in ample amounts and under adequate pressure, shall always be available for fire fighting. Sprinkling systems, automatic carbon dioxide or foam systems or automatic fogtype systems shall be installed when the value of the buildings, equipment or supplies to be protected justifies the cost of installation. Where a group of buildings are located beyond the range of protection from a public water supply, the installation of a water system for private fire protection may be warranted. Excavation facilities and fire exit may be provided at all locations featuring fire hazards. Siren or other suitable fire alarm arrangement shall be made on all projection. Warning signs may be posted at all locations having fire hazards. All staff shall be conversant with the use of all types of fire extinguishing apparatuses. Demonstrations and training in fire fighting shall be conducted to ensure that sufficient personnel are familiar with and are capable of operating fire-fighting equipment.

c)

d)

e)

f)

g)

h)

First Aid and Medical Care At every work site adequate and suitable arrangement for rendering prompt and efficient first aid to injured persons shall be maintained under the guidance of the medical officerin-charge of the project. First aid appliances including an adequate supply of sterilized dressings and sterilized cotton shall be maintained in a readily accessible place. The appliances shall be kept in good order and they shall be placed under the charge of a responsible person who shall be readily available during working hours. The minimum requirements to the first aid kit shall be as under: 24 small sterilized dressing 12 medium size sterilized dressing 12 large size sterilized dressing 12 large size sterilized burn dressing 12 (15 cm) packets of sterilized cotton wool A sufficient number of eye wash bottles filled with distilled water or suitable liquid clearly indicating by a distinctive sign which shall be visible at all time. Four percent xylocaine eye drops, boric acid eye drops and soda bicarbonate eye drops One 200 ml bottle of certimide solution (1%) or suitable antiseptic solution

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 104 Date: Nov 2009 Revision: R4

One 200 ml bottle of mercurochrome solution (2%) in water One 120 ml bottle of salvolatile having the dozes and mode of administration indicated on the label One bottle (30 ml) containing potassium permanganate crystals One pair of scissors One roll of adhesive plaster (6 cm x 1 m) Two rolls of adhesive plaster (2 cm x 1 m) 12 pieces of sterilized eye pads in separate sealed packets 12 roller bandages of 10 cm wide and 5 cm wide each A bottle containing 100 tablets of asprin or any other analgesic One tourniquet A set of suitable splints Three packets of safety pins Kidney tray A snakebite lancet One copy of first-aid leaflet Six triangular bandages Two pairs of suitable, sterilized, latex hand gloves Adequate identification and directional markers shall be provided to readily denote location of all first aid centers. An ambulance shall be provided to transport seriously injured persons to the hospital. 4.18.5 Corporate Social Responsibility (CSR) THDC is committed for fulfillment of its social obligation under Corporate Social Responsibility. The scheme addresses the issue of Community Development (CD) in the neighbourhood area of operating stations where construction has been completed and rehabilitation and resettlement issues addressed stand as per the R&R policy of Corporation applicable for project under construction stage /planned for construction. i Aims & Objectives: To undertake community development in the neighbourhood area of operating stations with particular focus on women, children, disabled persons and senior citizens. To create appropriate partnership with concerned stakeholders for the effective delivery of community development programs through consultation and participation. To explore and work in various domains of community development such as Health, Education, Drinking Water, peripheral development etc. on individual basis or partnership basis with the help of Govt, NGOs, Private firms etc as per requirement to promote sustained livelihood, overall development and well being of the target communities. ii Program covered under unit level CSR-CD Since, THDCs operating stations are located under varying socio-economic conditions , the community development programs have to be identified and formulated based on the specific needs and requirement of the particular location. The suggestive list of the

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 105 Date: Nov 2009 Revision: R4

programs which could be considered by the operating stations while formulating the annual plan is: Education: To organize skill development /vocational training and other training program to improve the skill and employment. It will include sponsoring peple for vocational training, ITI training, Computer training etc Scholarship for the selected local children for studying in near by schools or in THDC township. Preference may be given to girl child/ poor child Supply of study material like School bags, books and stationery etc Health: To conduct health surveys, identification of health concern, awareness campaign, publicity printed material/ films etc. To organize regular immunization program for children and medical checkup in schools To organize regular health camps like family planning, medical checkup for eye and heart etc. Supporting health facility by way of providing health staff including ambulance facility. Others: Provide community infrastructure, upgradation of community health/potable water/ Sanitation/ education facilities. Promote community plantation and forestry programs. Organize veterinary camp for the cattle stock. Corporate Centre: The Corporate S& E Group will be responsible for policy matters, compilation of information and annual reports, organizing annual CSR CD meet and facilitating the processing of allocation of funds to stations. Operating Stations: The CSR-CD policy will be implemented through dedicated CSR Cell constituted at unit level under functional guidance of Corporate S&E Group. Voluntary Work by THDC Employees & Their Family members: The volunteering by THDC employees will be promoted through collective efforts by THDC employees at station, who will partner in planning and implementation of the identified CD programs. THDC employees and family members will also be encouraged to mentor the needy local population and participate in the relief work in cases of national calamities. Their work will be recognized as a special activity. iii Implementation mechanism a) Planning and Co-ordination The specific program will be identified based on the need of communities, which will change from time to time and location to location. The CD program will, therefore be formulated based on Need Assessment Survey (NAS) for identifying the specific areas of concern. Based on the survey, a detailed program report will be prepared detailing the need for a CD program, time frame of implementation and budget.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 106 Date: Nov 2009 Revision: R4

The S&E Department at project will prepare annual plan including budget estimate for each year and forwarded by January of each year to corporate S&E group who shall consolidate and up for the approval of CMD. b) Consultation and Participation of Stakeholders The targeted communities and the local authorities will be closely involved in the process of planning and implementation of the CD programs to the extent possible. Efforts will be made to evolve development al partnership with local administration The Annual plan will be prepared based on the findings of need assessment surveys. c) Monitoring & Evaluation The head of Project at operating stations will review the CD program on monthly basis and submit monthly Progress Report to Corporate S& E. The Incharge of S&E will review progress on quarterly basis. d) Reporting Each station will prepare an annual report of community development activities delineating the activities identified, benefits accrued to neighbouring communities and the number of people benefited. The Corporate S&E Dept will compile and prepare an annual report for the corporation. The summary of the report will be published in print and also posted on the THDC website under a separate dedicated section on CSR. e) Budget For implementation of CSR activities a budget of 1% of Net Profit is being provided. Upto 60% will be utilized in nearby villages, upto 25% in the valley area and the balance at other places. The scheme shall be affective from financial year 2008-09. Major steps taken for the sustainable development of the Society are as under Providing Medical facilities and Organizing Medical Camps Construction of Drinking water schemes Development of Educational Facilities : An engineering college (Hydro Power Institute) near Tehri HPP is being set up Adoption of Industrial Training Institutes (ITI) Improving road connectivity in the vicinity of the Project Area 4.18.6 Disaster Management Plan

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 107 Date: Nov 2009 Revision: R4

Dam Break Analysis for VPHEP was carried out by the DPR Consultant. The National Weather Services DAMBRK model developed by Dr. D. L. Fread has been used for the analysis. This model simulates the failure of a dam, computes the resultant outflow hydrographs and also simulates movement of the dam break flood wave through the downstream river valley. It can be inferred from the hydrographs below the dam that the attenuation of the outflow hydrograph from the breached dam is significant only in the initial reaches and rate of attenuation of the hydrographs decreases when the distance increases from the breached dam. The water depth and water spread at various distances downstream of the dam are outlined in Table-4.18.1.
Table-4.18.1 Water Depth and Spread Downstream of Dam in the event of Dam Break Distance from Max. elevation River bed Water depth (m) Water spread dam (km) above MSL (m) level (m) width (m) 3.7 10.2 11.5 15.8 18.4 20.0 1200.00 1080.00 1050.00 1030.00 1010.00 1000.00 1223.44 1104.39 1071.96 1060.57 1044.20 1038.33 23.44 24.39 21.96 30.57 34.20 38.33 86.1 114.8 72.0 110.7 172.2 229.6

Source: Dam Break Analysis Report

The water will flow with force eroding the banks and causing damage to life and property located at the elevation given in the Table-4.18.2. Most of the villages are located at higher elevations and there are no villages located close to the bank of the river Alaknanda. The villages which are located at lower elevation and may suffer some lose of property and life are identified and given below. The villages may not be impacted directly but may be impacted in terms of loss of access route and agricultural land.
Table-4.18.2 List of Villages which will be affected in case of Dam Failure Sl. Name of River Latitude (N) Longitude(E) Elevation Approx. Loss No Village Bank (m) Distance from the Dam 1. Tapon R 1280 3 Access route 30 29 43.2 79 28 25.4 2. 3. 4. 5. Langsi Tirosi Hyuna Guniyala L R R R 30 29 25.8 30 29 15.5 30 28 23.4 30 27 32.1 79 28 57.1 79 28 02.2 79 26 20.7 79 25 30.3 1345 1126 1117 1213 3 6 8 10 Access route Access route Access route Access route, Agricultural land, Structures Access route, Agricultural land Agricultural land Access route, Agricultural land Access route, Agricultural land

6. 7. 8. 9.

Tenduli Pipalkoti Haat Siyasain

R L R R

30 26 34.5 30 26 04.8 30 25 18.8 30 24 58.7

79 25 30.1 79 25 41.6 79 24 53.7 79 24 29.8

1220 1259 1075 1069

12 13 15 16

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 108 Date: Nov 2009 Revision: R4

Sl. Name of No Village

River Bank

Latitude (N)

Longitude(E)

Elevation (m)

10. Batula 11. Durgapur 12. Birahi 13. Bowala 14. Chhinka
Source: CES

L R L R R

30 24 47.5 30 24 38.6 30 24 31.8 30 24 45 30 24 54

79 25 00.5 79 23 14.2 79 25 46.3 79 22 38 79 22 0

1160 1063 1071 1083 1041

Approx. Distance from the Dam 16 20 20 22 23

Loss

Agricultural land Access route Agricultural land Access route, Access route, Agricultural land

THDC will prepare a map showing danger level. No construction work may be planned in the danger area by the govt. authorities / private owners. Signboard showing no construction zone may be placed in the area. Several dam safety surveillance systems have been suggested to ensure that the dam never fails even under most adverse conditions. However, in case of a dam break, the measures which can be implemented to minimize loss of lives and property are as follows: To establish an effective Dam Safety Surveillance and monitoring programme including rapid analysis and interpretation of instrumentation and observation data periodic inspection and safety reviews/evaluation by an independent panel of experts To formulate and implement an Emergency Action Plan to minimize, to the maximum extent possible, the probable loss of life and damage to property in the event of failure of dam. Surveillance Surveillance activities which are an important part of any Dam Safety Programme are generally limited to post fill monitoring of performance and aging process of most of the dams. For the VPHEP more rigorous and effective dam safety surveillance and monitoring programme, encompassing rapid analysis and interpretation of instrumentation and observation data along with periodic inspection and safety reviews and evaluation have been suggested. Such programmes will have to be implemented during the following five critical phases in the life cycle of a dam: 1. 2. 3. 4 5. Design and Investigation Phase Construction Phase First Reservoir Filling Early Operation Period Operation and Maintenance Phase

Emergency Action Plan (EAP)

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 109 Date: Nov 2009 Revision: R4

Dam safety programme as indicated above includes the formation of an Emergency Action Plan for the dam. An emergency is defined as a condition of serious nature which develops unexpectedly and endangers downstream property and human life and requires immediate attention. Emergency Action Plan should include all potential indicators of likely failure of the dam, since the primary concern is for timely and reliable identification and evaluation of existing or potential emergency. This EAP presents warning and notification procedures to follow during the monsoon season in case of failure or potential failure of the dam. The objective is to provide timely warning to nearby residents and alert key personnel responsible for taking action in case of emergency. Administration and Procedural Aspects The administrative and procedural aspects of the Emergency Action Plan consist of a flow chart depicting the names and addresses of the responsible officials. In order of hierarchy, the following system will usually be appropriate in the event that the failure is imminent or the failure has occurred or a potential emergency conditions is developing, the observer at the site is required to report it to the Junior Engineer/Assistant Engineer who will report to the Executive Engineer/ Superintending Engineer for their reporting to the Chief Engineer through a wireless system or by any available fastest communication system. The Engineer-in-charge is usually responsible for making cognizant with the developing situation to the Civil Administration viz. District Magistrate. Each personnel is to acknowledge his/her responsibilities under the EAP in an appropriate format at a priori. The technical aspects of the EAP consist of preventive action to be taken with regards to the structural safety of the dam. The EAP is drawn at a priori for the regular inspection of the dam. For this purpose, providing an adequate and easy access to the dam site is a necessity. The dam, its sluices, and non-overflow sections should be properly illuminated for effective operations during night time. Whenever sinkholes, boils, increased leakages, movement of rock, gate failure, rapid rise or fall of the level in the reservoir, rise in the level of reservoir beyond the maximum working level, or wave overrun of the dam crest are observed, the personnel on patrol is required to inform immediately to the Junior Engineer (JE)/Assistant Engineer (AE) for initiation of the execution of EAP. They are required to inform the Engineer-in-charge and the local administrative authorities. It is desirable if the downstream inhabitants are warned using siren, if available, so as to make them aware of the likely imminent danger. The other preventive measures may include availability of a sufficient number of sandbags at several selected downstream locations and logs (for holding and sandbags) and at the dam site, one tractor, one motor boat, lanterns and rope. Areas from where the labour can be mobilized should be chalked out at a priori. In addition to these, public participation in the process of execution of the EAP may further help in amelioration the adverse impacts of the likely disaster and for this, it is necessary that the public should be aware of its responsibilities.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 110 Date: Nov 2009 Revision: R4

Preventive Action Once the likelihood of an emergency situation is suspected, action has to be initiated to prevent a failure. The point at which each situation reaches an emergency status shall be specified and at that stage the vigilance and surveillance shall be upgraded both in respect of time and level. At this stage a thorough inspection of the dam should be carries out to locate any visible sign(s) of distress. Engineers responsible for preventive action should identify sources of equipment needed for repair, materials, labour and expertise for use during an emergency. The amount and type of material required for emergency repairs should be determined for each dam, depending upon its characteristics, design, construction history and past behaviour. It is desirable to stockpile suitable construction materials at an appropriate site. The anticipated need of equipment should be evaluated and if these are not available at the dam site, the exact location and availability of these equipments should be determined and specified. The sources/agencies must have necessary instructions for assistance during emergency. Due to the inherent uncertainties about their effectiveness preventive actions should usually be carried out simultaneously with appropriate notification on alert situation or a warning situation. Mock Drills It is imperative that periodic mock drills are conducted by the project authorities. The mock drills will be carried-out step by step as stated below:First Step: Test the effectiveness of communication system. Second Step: Test the speed of mobilization of the plant emergency teams. Third Step: Test emergency isolation of all the actions to be taken during an emergency Fourth Step: Conduct a full rehearsal of all the actions to be taken during an emergency. The Disaster Management plan need to be periodically revised based on experience gained from the mock drills. Communication System An efficient communication system and a downstream warning system are absolutely essential for the success of an emergency preparedness plan. The difference between a high flood and a dam-break situation must be made clear to the downstream population. Evacuation Plans Emergency Action Plan includes evacuation plans implementation based on local needs. These could be: and procedures for

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 111 Date: Nov 2009 Revision: R4

Demarcation/prioritization of areas to be evacuated Notification procedures and evacuation instructions Safe routes, transport and traffic control Safe areas/shelters Functions and responsibilities of members of evacuation team Any precarious situation during floods will be communicated either by an alert situation or by an alert situation followed by a warning situation. An alert situation would indicate that although failure or flooding is not imminent, a more serious situation could occur unless conditions improve. A warning situation would indicate that flooding is imminent as a result of an impending failure of the dam. It would normally include an order for evacuation of delineated inundation areas. Public Awareness for Disaster Mitigation Guidelines that have to be followed by the inhabitants of flood prone areas, in the event of a flood resulting from dam failure, which form part of public awareness for disaster mitigation may also include following: Listen to the radio for advance information and advice. Disconnect all electrical appliances and move all valuable personal and household goods beyond the reach of floodwater, if one is warned or if one suspects that flood waters may enter the house. Move vehicles, farm animals and movable goods to the higher place nearby Keep sources of water pollution i.e. Insecticides out of the reach of water Turn off electricity and gas one has to leave the house. Lock all outside doors and windows if one has to leave the house Do not enter floodwaters. Management after receding of Flood Water It is to be accepted that in the event of dam break, even with maximum efforts, the loss of human lives, livestock and property would be inevitable. Under such a scenario, a massive effort would be used by various government agencies to provide various relief measures to the evacuees. Some of the measures which need to be implemented are listed as below: Provision of various food items & shelter to the evacuees Provision of fuel for various evacuees Provision of adequate fodder supply Arrangements for potable water supply Commissioning of low cost sewage treatment & sanitation facilities, and disposal of treatment sewage Approximate disposal of dead bodies human & livestock Immunization programmes for prevention of outbreak of epidemics of various water related diseases Adequate stocks of medicines of various diseases. especially water-related

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 112 Date: Nov 2009 Revision: R4

diseases. 4.18.7 Adaptive Capacity Building Capacity building is concerned with human resources and the development of institutions, it emphasis on the overall environment within which organizations operate and interact. Unlike capacity building efforts, adaptive capacity is something organizations pursue in an ongoing manner through measures that embed the four attributes of adaptive capacity- external focus, network connectedness, inquisitiveness and innovation. A capacity development approach requires that, even if the focus of concern is a specific capacity of an organization to perform a particular function, there must nevertheless always be a consideration of the overall policy environment and the coherence of specific actions with macro-level conditions. Capacity development is therefore concerned with the micro and macro factors that determine how institutions translate their capacities into actual performance. Following suggestions are given for strengthening the environmental management of the projects. The components which must be taken care described below ii. Ecological Monitoring THDC can undertake comprehensive Ecological Monitoring through Satellite Imagery Studies over project area and vicinity. These studies would reveal significant environmental gains in the vicinity areas as a result of pursuing sound environment management practices. Some of these important noticed may be a change in forest area, agriculture area, waste land etc. Such studies conducted from time to time around and in vicinity of a project would establish the environment status at various post operational stages of the project. iii. Aquatic monitoring Aquatic ecology is critical issue in Hydropower projects. Monitoring of aquatic life in the river during construction and operation phase must be carried out. Changes observed in the aquatic life with the change in flow associated impacts must be documented to provide framework for future development policies. Memorandum of Understanding (MoU) must be formed with State Fisheries Department for management of fish. iv. Monitoring of Environmental Parameters A broad based Environment Monitoring Programme needs to be formulated Environmental parameters for water quality and sediment quality must be monitored at the stipulated frequency. v. Environmental Reviews To maintain constant vigil on environmental compliance, Environmental reviews must be carried out at all sites and remedial measures should be undertaken wherever necessary. Such periodic Environmental reviews and extensive monitoring of the facilities carried out at all locations help in compliance with the environmental norms and timely renewal of different environmental permissions. vi. On-Line Data Base Management

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 113 Date: Nov 2009 Revision: R4

It is imperative to have an on-line, reliable and efficient environment information system on the operational to achieve effective environment management. In consideration of this, a GIS based computerized programme, which could provide reliable storage, prompt, and accurate flow of information on environmental performance of project locations should be developed and installed in THDC. This software will help and facilitate direct transfer of environment reports and other environment related information from project locations to the Regional and Corporate Centre. This system will help in achieving continuous improvement in THDC's environment performance through improved monitoring and reporting system by using the trend analysis and advanced data management techniques. vii. GIS Facilities To facilitate, on-line data base management, environmental management and monitoring requirements related to different proposed and on going project developments advanced remote sensing and GIS facilities at corporate level should be set up. This cell will not only serve the in-house project requirements but also proposed to take up the charge of capacity building of other similar institutions viii. Photographic Monitoring Photograph monitoring is simple and reliable method to monitor the changes in environmental features. Plantation can be monitored through photographic analysis of pre selected areas at 6 monthly intervals. Similarly erosion and landslides can be monitored for pre selected areas of rock and land strata at fixed intervals. THDC team will undertake survey of the potential areas, mark and photograph them on visible scale of clarity. Exercise will be repeated every six month and comparative analysis will be made of photograph to identify changes, if any in the vegetation, rock, and strata locations. A record will be maintained of changes occurring in the character of the land strata and /or rock. Evaluation will be used for advance warning of possible erosion and landslide possibility. ix. Setting up Environmental lab An environment lab with the following facilities should be setup by THDC for: Water quality analysis Air quality analysis Meteorological Observations x. Staffing and Training Requirements THDC has a Social and Environmental Dept at Corporate level however adequate persons with relevant expertise to take care environmental issues linked with various ongoing and proposed projects are required. In view of existing organizational structure at THDC Corporate office, following is suggested: The Social and Environmental Dept should be able to handle all issues related to different environmental attributes. Deploy professionals from relevant environmental discipline such as EIA, Terrestrial Biodiversity, Aquatic Ecology, Chemist, GIS and Socio economics. Emphasis may be given on specialized areas to be filled up at THDC.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 114 Date: Nov 2009 Revision: R4

Establish an Environmental Management Cell (EMC) at project level. The EMC will handle all issues related to different environmental attributes, it will be responsible for overall environmental management in project being undertaken by THDC from investigation level to execution at project level Training on EIA procedure, Legal status, EMP, Monitoring, Disaster Management Plan, ISO-14001 EMS, Sound construction practices may be given to Corporate and Project Staff. Undertake to national /international exposure visit. In the first five years, adaptive management targets and related monitoring requirements will be reviewed and amended. Thus, the adaptive management process will accommodate any changes based on new information. A budget of Rs.64.08 million has been proposed for Adaptive Capacity Development Table 4.18.3 : Budget for Adaptive Capacity Development
Items Corporate Recruitment Manager Level and above Water & WQ Unit EIA & Compliance Unit Aquatic Ecology Unit Biodiversity & Forestry Unit Climate Change & Carbon Finance Unit Sub Total Manager and above Environment Engineer / Scientist Sub Total Water Quality Air Quality Meteorological Sub Total Special Studies, Compliance Reporting, regular quarterly report Photographic monitoring Web Dissemination Sub Total Grand Total I Year 840000 840000 840000 II Year 900000 1920000 1920000 III Year 960000 2160000 2160000 IV Year 1020000 2400000 2400000 V Year 1080000 2640000 2640000 Total Amount 4800000 9960000 9960000

420000 420000

1440000 1440000 480000

2160000 2160000 1620000

2400000 2400000 2400000

2640000 2640000 2640000

9060000 9060000 7140000

Project Recruitment

3360000 840000 840000

8100000 900000 960000

11220000 960000 1080000

13020000 1020000 1200000

14280000 1080000 1320000

49980000 4800000 5400000

Laboratory Equipments

Documentati on & Communicat ion

1680000 250000 200000 100000 550000 400000

1860000

2040000

2220000

2400000

400000

600000

600000

1000000

10200000 250000 200000 100000 550000 3000000

50000 20000 470000 6060000

50000 20000 470000 9410000

50000 20000 670000 12790000

50000 20000 670000 14650000

50000 20000 1070000 16370000

250000 100000 3350000 64080000

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 115 Date: Nov 2009 Revision: R4

Source : CES

4.18.8

Institutional Setup and Capacity Building The THDC India Ltd. is headed by Chairman & Managing Director. The Board of Directors constitutes of total 12 executive staff. There are 3 Directors - Personnel, Technical and Finance in the board. The organizational setup of the THDC is given in Flow Chart - Annex- 4.18.2. There are 22 internal departments under corporation and the strength of executive staff of THDC is 696. THDC has established a separate Social & Environment department at Corporate Office Rishikesh. The total strength of Social & Environment department at Corporate Office is 19 (Nineteen). i Staffing Requirement

THDC has moved from single project (Tehri Dam Project) organization to multiple projects. At present THDC have 13 projects at National level and 2 Overseas (Sankosh Multi Purpose Project (4060 MW) and Bunakha HEP (180 MW) in Bhutan). The Tehri Power Station is now fully operational. The list of projects with THDC under various phase of development is given below.
Table 4.18.4 Projects under THDC within India Location Uttarakhand Uttarakhand Uttarakhand Uttarakhand Uttarakhand Uttarakhand Maharashtra Maharashtra Uttarakhand Uttarakhand Uttarakhand Uttarakhand Uttarakhand

Name of Project

Phase Operation Construction Construction Construction

Tehri Hydro-Electric Power Project (THPP) Stage - 1 Koteshwar Hydro-Electric Power Project (KHPP) Tehri Pump Storage Plant (TPSP) Vishnugad Pipalkoto Hydro-Electric Project (VPHEP) Jhelam Tamak Hydro-Electric Project (JTHEP) Malari Jhelam Hydro-Electric Project (MJHEP) Malshej Ghat Pump Storage Scheme (MGPSS) Humbarli Pump Storage Scheme (HPSS) Kishau Multipurpose Project (KMP) Karmoli Hydro-Electric Power Project (KHEPP) Jad Ganga Hydro-Electric Project (JGHEP) Gohana Tal Hydro-Electric Project (GTHEP) Bokang Bailing Hydro-Electric Project (BBHEP
Source: THDC

Survey & Investigation Survey & Investigation Survey & Investigation Survey & Investigation Survey & Investigation Survey & Investigation Survey & Investigation Survey & Investigation Survey & Investigation

Name of the Project

Table 4.18.5 Overseas Projects under THDC Country Phase

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 116 Date: Nov 2009 Revision: R4

Sankosh Multi Purpose Project (SMPP) Bunakha Hydro-Electric Project (BHEP)


Source: THDC

Bhutan Bhutan

Survey & Investigation Survey & Investigation

With increase in projects of THDC the increasing role of the organization is also felt. The man power efficiency is a key issue along with the technical and non technical inputs. The work load stresses on to the capacity building and staffing requirement for proper management and successful implementation of the projects. Requirement of qualified man power for the various Hydro Projects and enforcement of environmental activities at various stages - Construction, Commissioning, Operation & Maintenance phase, is essential. Comparative Strength of THDC Table 4.18.6 Comparative Strength of THDC with National & International Hydropower Companies
Staffing International BC Hydro (2009) Total Staff Environmental Staff 3547 127 National NHPC (2009) 1000 25 2008 (Corporate executive ) 696 7 THDC Ideal case Corporate executive (2011) 1000 20

The strength of Environmental staff of BC Hydro is 3.5% of the total staff and that of NHPC is 2.5%. The No. of Environmental executives at corporate office is 1% . It is proposed that by 2014 the No. of Environmental executive staff should be at least 2.5 % of total staff. THDC is committed to the environmental management of the projects and a Social & Environment Department headed by General Manager assisted by Senior Managers and Senior Environmental Officers at Corporate Office is already established. However strengthening of the Department is imperative with the increasing projects and responsibilities to carry out specific environment related functions. The Social & Environment Department will be responsible for monitoring environmental and social issues related to all projects undertaken by THDC. Therefore the Department must deploy professionals from relevant environmental discipline such as EIA, Terrestrial Biodiversity, Aquatic Ecology, Environmental Science/ Env Engineering and Biology background, Chemist, GIS and Socio economics. The proposed structure of the Social and Environmental Department at Corporate office is given as Figure-4.18.1. A Corporate Division (CS) will be formed under the AGM/DGM Environment. The Corporate Division will consist of five sub- units which will be Water & Air Quality, EIA & Compliance, Aquatic Ecology, Biodiversity & Forestry and Climate Change and Carbon Finance. Each unit will have at least four staff.

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 117 Date: Nov 2009 Revision: R4

Water & Air Quality Unit will deal with monitoring and quality aspects of the projects and necessary inputs EIA & Compliance Unit will look after the EMP compliance and regulatory requirements. Aquatic Ecology Unit: Will be responsible to conduct aquatic study and related issues. Biodiversity & Forestry Unit will responsible look after the terrestrial components. Climate Change and Carbon Finance Unit will work for carbon credits and necessary requirements. The qualification and specification of the staff in the four units is given in Table 4.18.6

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 118 Date: Nov 2009 Revision: R4

Chairman & Managing Director

General Manager (S&E)

AGM / DGM (Social)

AGM / DGM (Environment)

Corporate Division
Sr. Mgr. / Mgr. Ongoing Projects Sr. Mgr. / Mgr. New Project

Water & Air Quality

Unit
Dy.Mgr / Sr. Engr Dy.Mgr / Sr. Engr Dy.Mgr / Sr. Engr Dy.Mgr / Sr. Engr 2 Env. Eng 2 Env Scientist

EIA & compliance Unit

Aquatic Ecology Unit

Biodiversity & Forestry Unit

Climatic Change & Carbon Finance Unit

2 Env. Eng 2 Env planners

4 Aquatic Specialist

4 Biodiv. Specialist

4
Specialist

Fig 4.8.1: Organizational Structure of Social & Environment Department at Corporate Office

118

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 119 Date: Nov 2009 Revision: R4

Table 4.18.7: Qualification of Environmental Staff in the five units in Corporate Division in S&E Department
Name of Env Unit Water & Air Quality Unit Professional required 2 Env Engineers Qualification Exposure / Experience Roles / Responsibilities Air, Water Soil, Noise quality parameters Air, Water Soil, Noise quality parameters EMP Compliance and monitoring Regulatory requirements and EMP monitoring Database preparation & on-line presentation, updating of website and dissemination of environmental inventory Fisheries, Macro Zoobenthos Aquatic ecology, etc Zooplanktons, Aquatic ecology, etc

Degree in Chemical Engg

2 Env Scientist

EIA & Compliance

1 Env Engineers

2 Env Scientist

M.Sc Env Science / Chemistry / Diploma in Env Mgmt, Degree in Environmental Engg M.Sc in Env Science / Diploma in Env Mgmt M.Sc / Diploma in Remote sensing & GIS

3 years of experience of working in CSIR / CPCB approved labs or 5 years monitoring experience 5 years of working experience

3 years of working experience 5 years of working experience

1 Env Planner

5 years of working experience

Aquatic Ecologist

1 Aquatic specialist

M.Sc Zoology with specialization in Fisheries M.Sc . Zoology with specialization in invertebrates/ microorganisms M.Sc / diploma in microbiology M.Sc Botany with specialization on phytoplanktons M.Sc Env Science

5 years of working experience

1 Aquatic specialist

5 years of working experience

1 Aquatic specialist 1 Aquatic specialist Biodiversity Unit 1 Biodiversity Specialist

5 years of working experience 5 years of working experience 5 years of working experience

1 Biodiversity Specialist 1 Biodiversity Specialist Biodiversity 1 Biodiversity

M.Sc Forestry M.Sc Botany specialization in Taxonomy M.Sc Zoology with

5 years of working experience 5 years of working experience 5 years of working

Phytoplanktons , Zooplanktons aquatic ecology Phytoplanktons , Zooplanktons aquatic ecology Terrestrial ecology, CAT plan Compensatory afforestation, Restoration of quarry sites, muck disposal areas etc Do Do

Do

119

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 120 Date: Nov 2009 Revision: R4

Name of Env Unit Unit Climate Change Carbon Finance

Professional required Specialist 1Climate Change Economist 2 Env Specialist

Qualification

Exposure / Experience

Roles / Responsibilities

&

specialization in Wildlife M.Sc Economics / Diploma in climatic change Env Engineering / MSc Env Science Specialization in Carbon Financing

experience 5 years of working experience in similar projects 5 years of working experience in similar projects 5 years of working experience in similar projects Carbon credits and necessary requirements Carbon credits and necessary requirements Carbon credits and necessary requirements

1Carbon Finance Specialist

The future requirement for carrying out Environmental activities in various projects of THDC is summarized below.
Table 4.18.8: Future Environmental Manpower required for various Projects Man Year/ Man Days Days 1 2 3 4 5 6 7 8 9 10 315 315 315 335 170 140 140 140 110 110 2090

Projects Tehri & Koteshwar HEP VPHEP & Gohana Tal HEP Malari Jhelam & Jhelam Tamak HEP Jadhganga & Karmoli HEP Bokang Bailing HEP Kishau HEP & Other New Projects Total No. Staff of

429

735

815

815

770

325

180

180

180

180

4609

20

300

890

965

980

905

905

905

320

245

6435

60

90

90

1130

975

925

895

895

895

300

6255

50

170

145

635

630

600

600

600

600

187

4217

1075

1205

1360

1190

1120

700

600

480

7730

874 4

1610 7

3330 15

5085 24

4885 23

4085 19

3840 18

3420 16

2705 13

1502 7

31336 150

120

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 121 Date: Nov 2009 Revision: R4

Recognizing the importance of protection of the environment with development of the power sector, it is proposed to form an Environmental Management Cell (EMC) at project level. The EMC will handle all issues related to different environmental attributes, it will be responsible for overall environmental management in project being undertaken by THDC from investigation level to execution at project level. EMC will be strengthened by posting at least one specialized Environment specialist and one Social specialist at each project site. However during execution stage of various environmental mitigation measures, the individual teams can be reinforced from the Corporate Head Quarter Environment team. The Institutional setup of EMC is given as Figure-4.18.2.
PROJECT HEAD

DGM (EMC)

Sr. Mgr./Mgr. (Social)

Sr. Mgr./ Mgr. (Environment)

Dy. Mgr. / Sr. Engr. / Sr. Officer (2)

Dy. Mgr. / Sr. Engr. / Sr. Officer (2)

Figure-4.18.2 Proposed Environmental Management Cell at Project level

The Head of EMC may be equivalent to DGM or above. The personnel deployed may be familiar with the National Environmental Legislation and R& R policy The EMC at Project sites will send the detail of EMP Implementation progress through their Project In-charge to Corporate Social & Environment Department. There are 32 (thirty two) staff at Vishnugad Pipalkoti Hydro -Electric Project site, of which two officials look after the Environmental affairs of the project.

121

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 122 Date: Nov 2009 Revision: R4

ii

Environment Activities at Corporate Level The roles of Corporate Environment Department will be: Obtaining statuary and Non-statuary clearances, viz. Site / Environment Clearances, Forest Clearance, Wild Life Clearance and No Objection Certificate from SPCB etc. Coordination and interaction with MOP, MOEF, SPCB etc. Coordination with the Project on environmental matters and providing required assistance/ inputs Compliance reporting to statuary/ monitoring agencies. Monitoring of all environmental studies / implementation of environmental conditions. Policy related issues, viz National Environment Policy, NPV for Forest Land transfer, apportionment of CAT etc. Material for Standing Committee of Parliament reply of Parliament/ Assembly Questions related to environment and other VIP references Preparing Terms of References of Environment Impact Assessment studies for the Projects Award of EIA Studies based on approved TOR by Ministry of Environment, GOI Finalization of EMP for inclusion in to the EIA Report based on Public Hearing of each Project. Co-ordination for finalization of CAT Plan proposal in consultation with project authorities or the Forest Department and other external agencies. Assistance for completion of EIA Studies by constantly interacting with agency for sampling and preparation and finalization of report thereof. Preparation of comments and guidelines for project environment for timely completion of these studies. Preparation of agendas for approval of these studies. Regular monitoring of approved Environment Management Plan for each project. For effective implementation the Corporate Environment will undertake periodic visits to site and will seek monthly / quarterly progress reports on Muck disposal, Environment Monitoring, Compensatory afforestation and CAT plan, etc. Prepare implementation guidelines and monitoring mechanism so as to address the EMP Implementation in letter and spirit at the project site in coordination with project head. Preparation of technical reports, technical papers, status reports and other inputs for Management from time to time. Environment related consultancy services to other outside agencies undertaken by THDCs consultancy wing. Collection and dissemination of relevant environmental information indicating amendments to environmental protection acts Proposals for Carbon Financing involving environmental aspects.

122

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 123 Date: Nov 2009 Revision: R4

iii

Environment Activities at Project Level The following activities have been identified for Project Environment Management Cell for implementation of Environment Management Plan: Carrying out EIA/EMP Studies, Public Hearing and preparation of details of submission of proposal for environmental appraisal Implementation of Environment Management Plan, viz CAT, CAD, Compensatory Afforestation, Water Quality Monitoring, Health Impact Assessment, Ambient Air Quality Monitoring, Green Belt Development, Biodiversity Management etc and other conditions of environment clearance. Coordination with State Implementing Agencies. Reporting of compliance of environmental conditions periodically as required by MoEF/ State authorities. Carrying out studies related to Aquatic Life, Catchment Area Treatment and other Environmental Issues. Prepare schedule of implementation of the approved Environment Management Plan (EMP); based on schedule implement the EMP the activities will be monitored and compliance report will be submitted to Corporate Environment Dept. Interact with Contractor throughout the course of study and seek guidance if required on matters of Environment aspects of the project from the Corporate Environment Department. Undertake compliance monitoring to provide periodic checks Submit monthly / Quaterly progress reports on environment aspects of the project to Corporate Environment Department. Establish Environmental Management System (EMS) as per ISO-14001 at project site. Establish an environment lab with some facilities for water quality, noise and air pollution facilities will be setup so as to keep a check from time to time. Undertake environmental training activities.

4.18.9 Training for Environmental Staff THDC have a Training and Learning Policy for its staff with an objective to: Identify Training Needs of the human resources keeping in view objective of the organization. Provide a minimum of seven days training in a training year to all employees. A separate budget provision equivalent to minimum of 1.5% of the salary expenditure (i.e. Basic Pay + D.A. of all employees) will be kept in the annual Revenue Budget of the Corporation as minimum investment for Training of Employees, which will be progressively enhanced to 5%. On the basis of duration/training programmes (in-house /external) are categorized as under:

123

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 124 Date: Nov 2009 Revision: R4

Short duration : up to three training days Medium duration : up to five training days Long duration : above five training days THDC has already taken initiative to augment the capacity on environmental management. The detail of training program attended by environmental staff of THDC is attached as Annex 4.18.3. It is suggested that along with the HR policy the training policy for Environmental staff may be developed and incorporated. An annual calendar may be prepared for attending training programs and the Environmental Staff may be nominated to attend workshops / seminars/ conferences on environmental issues. Training Need The objective of training program is to identify Training Needs of the employees and upgrade their skill in respective fields. In order to identify training, learning and developmental needs of the staff, a Training Need Analysis (TNA) may be carried out periodically. Successful operation of hydro electric project demands regular monitoring of various activities related to civil works, environmental issues and social issues. In addition, an overall development of the project area by association with local organizations in various development schemes is required. In view of existing organisational structure at THDC Corporate office and at project office (Vishnugad Pipalkoti Hydropower Project), following, is suggested: a) The existing staff working on environmental aspects in THDC will be kept abreast with the latest tools and methodologies in Environment field including Impact Assessment Studies. b) They should undergo short and mid duration trainings on environmental issues linked with hydro electric projects and their remediation practices being followed in other areas from prestigious institutions in India or abroad. In India, it could also be in the form of attachment with some organizations already involved in implementing environment mitigation requirements for hydro power development like NHPC or conceptual up gradation by attachment with TERI, NEERI etc. c) Short term overseas training could also be undertaken at University of Oklahoma or East West Centre, Hawaii with emphasis on modeling of various environmental parameters. These are the institutes which are pioneer in the field of Environment managements. d) Exposure visit may be undertaken to Hydro project site where EMP implementation has been undertaken in India / Abroad.

124

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 125 Date: Nov 2009 Revision: R4

Training Components Considering the requirements for environmental and social management of projects, training components have been identified. The various components identified for training on Environmental Management are given in the Table below. The relevant World Bank safeguard policies must be also considered for compliance of environmental and social aspects of the project along with the requirement of the Government of India.
Table-4.18.9 Trainings Identified for Environmental Management S. N. Target Trainee Trainings Trainer 1 Environmental EIA Case studies, Screening & National Experts Management Cell (EMC) / Scoping, Guidelines for EIA and EMP Environmental Dept. Indian Environmental Regulations, Acts CPCB/ MoEF Officials & Procedures World Bank Safeguard Policies World Bank / National Experts Procedure for baseline survey: physical National Experts ecological, cultural properties, health etc Procedure for Impact Assessment National Experts Monitoring Methodologies National & International Experts / Exposure visit Risk Assessment and Management International Expert / Exposure visit Public Consultation / Information World Bank / dissemination National Experts Implementation of THDC Corporate National Experts Policies EMS Quality System: ISO 14000 National OSHAS 18000 & International EMS Audit Expert Carbon Finance: Opportunities, World bank methodologies & monitoring for claims Exposure visit 2. Project Engineers Environmental Impacts of Hydropower National Expert projects, storage run off river Dam Safety Indian experience, National Preparedness & Response, Safety & International Issues, Emergency Warning System Expert / Exposure visit Indian Environmental Regulations, Acts CPCB/ MoEF & Procedures Project EMP : monitoring output, National outcome of EMP and Owners & International responsibility Expert Clean Construction Technology National Waste Minimization and Management & International Expert Exposure visit

125

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 126 Date: Nov 2009 Revision: R4

S. N. Target Trainee

Trainings Health & Safety Management System and Responsibilities Risk Assessment and Management

3.

4.

Public Consultation / Information dissemination Implementation of THDC Corporate Policies THDC - Corporate Unit THDC Corporate Policies (Social & Env Dept Environmental Impacts of Hydropower Technical, Planning, projects, storage run off river Finance, Procurement) & Dam Safety Indian experience, Senior Management Preparedness & Response, Safety Issues, Emergency Warning System Detail Safety manual and Safety Plans EIA / EMP Content and Phases National / State requirements for EIA and Other relevant Rules Responsibility for EMP and Resource need for Env Mgmt in THDC Construction Contractor & Indian / State Environmental Its Staff Regulations, Acts THDC Environmental Polices / Guidelines Implementation of THDC Corporate Policy Details of Project EMP Contractors responsibilities Monitoring outputs, results and outcome of EMP Contactors reporting on : Environment, Health and Safety Detail Safety Manual & Practices Safe Construction Practice and Clean Construction Technology
Source: CES

Trainer National & International Expert National & International Expert National Expert National Expert Env Dept THDC Env Dept THDC / Exposure visit Env Dept THDC Exposure visit National Expert National Expert SPCB/ other Experts National Expert SPCB EMC THDC EMC THDC EMC THDC EMC THDC Contractors EnvIncharge Outside Expert Contractors EnvIncharge / Project Engineer THDC

Any new staff joining in Social & Environment Dept should undergo short duration trainings on EIA, EMP and THDCs Corporate Policy, the Dept. will provide in house training. Subsequently other identified trainings may be imparted to the staff. Any person suggested for external training program in India or abroad, the Corporate Social & Environment Dept will process nominations for the same to the institute.

126

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 127 Date: Nov 2009 Revision: R4

List of Training Institutes Given below is a list of training institutes which can be contacted for providing training in various issues related to environmental management and capacity building. These institutes are certified by Central Electricity Authority (CEA) for providing training.
Table-4.18.10 List of the Power Sector Training Institutes Recognized by CEA Sl. No. Name of Institutes Corporation 1. HINDALCO Renu power Technical Training & Thermal Management Development Centre, HINDALCO, Hindalco Industries Ltd, (Renusagar Power Division) P.O. Renusagar, Sonebhadra - 231218 (UP) 2. Lineman Training Centre, T&D Dholighat, HPSEB, Solan (H.P.) HPSEB: Himachal Pradesh State Electricity Board

3.

Training Centre, NHPC: National Hydro Chamera Power Hydro Station-I, Khairi, Post- Khairi, Power Corporation Dist.- Chamba (H.P.) Hydro Power Training Institute, Uri- Hydro I Hydro Power Station, Gingle, Dist. Baramulla (J&K) - 193 122 O&M Training Centre, Salal HEP, Hydro Jyotipuram - 182 312 6 Hydro Training Centre, Tanakpur, Hydro P.O. NHPC Campus, Banbassa, Champawat 262 310, Uttarakhand National Power Training Institute, Thermal, Hydro, NPTI Complex, Sector-33, T&D, Power Faridabad -121 003 , Haryana Power Management Institute (PMI), Thermal, Hydro & NTPC Ltd, Plot No. 5-14, Sector- Power 16A, NOIDA-201301 (U.P.) Employee Development Centre, T&D 400 kV Ballabgarh Sub-Station, PGCIL, Near Village Samaipur, Ballabgarh, Dist. Faridabad (Haryana) Employee Development Centre, T&D 400 KV Kishenpur Sub-station, Manwal, ViaDansal, Dist. Jammu (J&K) - 181 224 Officers Training Institute, RVPN NPTI: National Power Training Institute

4.

5.

6.

7.

8.

NTPC: National Thermal Power Corporation PGCIL

9.

10.

11.

127

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 128 Date: Nov 2009 Revision: R4

Sl. No. Name of Institutes RVPN, T&D JMC Building, Kabir Marg, Bani Park Jaipur 12. Electricity Training Institute, U.P. T&D Power Corporation Ltd, Sarojini Nagar, Lucknow - 226 008 (U.P.) 13. Centre for Research and Industrial Hydro Staff Performance, GPO, Box 92, Shyamala Hills, Manas Bhavan, Bhopal - 462 002 (M.P.) Centre for Power Sector T&D Development, Pune, Mahatransco, (Maharashtra) NPTI

Corporation

UPPCL

Autonomous Society (in MP)

14.

Mahatransco (YASHADA)

15.

National Power Training Institute, NPTI: Thermal, Hydro & South Ambazani Road, Opp. T&D National Power V.N.I.T., Gopal Nagar, Nagpur - 440 022 (Mahrashtra) Training Institute Employees Development Centre, T&D 400 kV Itarsi Sub-Station, PGCIL, Betul Road, Pathrota, Itarsi-461 111, Dist. Hoshangabad (M.P.) Reliance Energy Management Power Institute, Reliance Infrastructure Management Ltd, 19 Aarey Colony, J-V Link Road, Goregaon (E), Mumbai- 400 065 (Mahrashtra) National Power Training Institute (Ministry of Power, Govt. of India) PO Box No. 8201, Subramanyapura Road, Banashankari II Stage Bangalore- 560 070 (Karnataka) PGCIL: Power Grid Corporation of India Ltd. REL

16.

17.

18.

NPTI; National Power Training Institute

Source: CES

Besides the above mentioned institutes educational institutes, universities and Indian Institute of Technology (IIT) also provide training programs. Some institutes providing training in Environmental Aspects are given below.
Table-4.18.11 Training Institutions that can be contacted for Capacity Building Sl. No. Name of the Training Institutes Address 1. Govind Ballabh Pant Institute of Kosi-Katarmal, Almora- 263643, Himalayan Environment & Uttarakhand, Gram:HIMVIKAS Development (GBPIHED) - Kosi Phone: (05962) 241041, 241014, Katarmal, - Almora (Uttarakhand) 241015 Fax: 05962-241150, 231507 http://gbpihed.gov.in/ 2. Environment Protection Training and 91/4, Gachibowli, Hyderabad - 500 Research Institute (EPTRI) Hyderabad 032 Andhra Pradesh INDIA

128

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 129 Date: Nov 2009 Revision: R4

Sl. No.

Name of the Training Institutes

Address Phone : +91-40-23000489, 23001241, 23001242, Fax : +91-40-23000361 Email : info@eptri.com URL : www.eptri.com

3.

4.

Administrative Staff College of India Administrative Staff College of India (ASCI) - Hyderabad (Andhra Pradesh) Bella Vista, Raj Bhavan Road, Khairatabad,Hyderabad-500082 Phone:+91-40-66533000 Fax : +91-40-23312954 Irrigation Management & Training Irrigation Management & Training Institute(IMTI), Kota Institute(IMTI) Dadabari Road, Kota, Rajasthan- 324 009 Tel.: 2500642, 2500682, 2500970 Fax: 0744- 2500682 E.mail: dirimt12@sancharnet.in Pollution Control Research Institute BHEL House, Siri Fort, New Delhi (PCRI) 110049, Fax:+91 11 26493021; +91 11 264, 92534 phone : +91 11 26001010 Email: query@bhel.com Forest Research Institute(FRI) Dehradun Forest Research Institute (FRI) (Indian Council of Forestry Research & Education) P.O. New Forests DEHRADUN - 248006 E-Mail : icfre@envfor.delhi.nic.in Indian Institute of Public Administration IIPA New Delhi (IIPA) - New Delhi Phone:23702434(D) 355504 / 8321 (Fax) 23702440 email: bsbaswan@yahoo.com National Institute of Management (NIFM) (Haryana) Finance NIFM, Faridabad Sector-48,Pali Road, Faridabad 121001.Haryana phone: 2418857,2418875,2418893, Fax:91-0129-2418867 91-0129-2423593 & NITIE Campus, - Near Vihar Lake, Mumbai 400087 Phone : 022 28575590 Fax : 022 28575670 Website: http://www.nitie.edu

5.

6.

7.

8.

9.

National Institute of Training Industrial Engineering (NITIE) Mumbai

10.

National Environmental Engineering NEERI Research Institute (NEERI) Nehru Marg, Nagpur, 440020,

129

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 130 Date: Nov 2009 Revision: R4

Sl. No.

Name of the Training Institutes Nagpur (Maharastra)

Address Tel: 0712-2249885-88 & 2249970-72. Fax: 0712-2249900. e-mail: ra_sohony@neeri.res.in, URL: http://www.neeri.res.in National Water Academy Central Water Commission Pune-Sinhagad Road, Khadakwasla, Pune - 411024, Maharashtra (India) Telephone No. : 091-020- 24380678; NWA EPBX (DID) : 091-02024380392, 24381517 Fax Nos.: 091-02024380110/24380224; E-mail: nwa.mah@nic.in

11.

National Water Academy Maharashtra (India)

Source: CES

Some of the reputed International Institutes which can be contacted for providing training are given below. Gailillee College, International agricultural Training Centre, Ruth Fishmann, Nahalal, Israel. Charted Institute of Water & Environment Management, UK. (www.ciwem.org) UNEP-Environmental Impact assessment Training institute , Production & Consumption branch (www.uneptie.org) Asian Institute of Technology Bangkok Centre for International Postgraduate Studies of Environmental Management CIPSEM, Dresden, Germany. University of California ,Barkeley College of Natural Resources, Centre for Sustainable Resource Development, Environment Leadership Programme (http;//enr.berkeley.edu/BeahrsELP) British Columbia Hydro, Canada, World Bank Institute, Washington, USA Yangtze River Three Gorgers Study tour through Yangtze Cruise, Inc. (www.YangtzeCruises.com) University of Oklahoma East West Centre Hawaii Japan AOTS -Japan Sponsored Program 4.18.10 Budget for Capacity Building The Corporate HRD group will prepare the detailed training calendar in consultation with EMC and allocate an annual budget for it. The sum invested on Training shall be monitored quarterly. Tentative budget proposed for capacity building of VPHEP is Rs. 21.38 million. The break up for 5 years is given below.

130

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 131 Date: Nov 2009 Revision: R4

Items Environment Engineer / Scientist-EMC & Env Dept. Project Staff Corporate staff Contractor staffTrainings Grand Total

Table-4.18.12 Year wise Estimate for Environmental Training I Year II Year III Year IV Year V Year 1600000 1985000 1550000 1640000 1000000

Total 7775000

1000000 340000 500000 3440000

1700000 1575000 500000 5760000

1550000 1150000 50000 4300000

1300000 1500000

1500000 940000

7050000 5505000 1050000

4440000

3440000

21380000

Table-4.18.13 Proposed Tentative Capacity Building Budget for VPHEP S.No. Target Trainee Trainings Schedule for Training 1 Environmental EIA Case studies, Screening & 30 person days in India Management Cell Scoping, Guidelines for EIA and EMP / Environmental 20 person days abroad Dept. Officials Indian Environmental Regulations, 12 person days in Acts & Procedures India World Bank Safeguard Policies 12 person days in India Procedure for baseline survey: 30 person days in physical ecological, cultural properties, India health etc Procedure for Impact Assessment 30 person days in India Monitoring Methodologies 30 person days in India 20 person days abroad Risk Assessment and Management 30 person days in India 20 person days abroad Public Consultation / Information 5 person days in dissemination India Implementation of THDC Corporate 10 person days in Policies India EMS Quality System: ISO 14000 5 person days in OSHAS 18000 India EMS Audit Carbon Finance: Opportunities, 30 person days in methodologies & monitoring for claims India 16 person days abroad Environmental Impacts of Hydropower 24 person days in 2. Project

Training Budget 4.5 lakh 5.0 lakh

1.5 lakh 2.5 lakh 4.5 lakh

4.5 lakh 4.5 lakh 5.0 lakh

4.5 lakh 5.0 lakh

2.0 lakh 2.0 lakh 2.0 lakh

4.5 lakh 5.0 lakh

3.0 lakh

131

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 132 Date: Nov 2009 Revision: R4

S.No.

Target Trainee Engineers

Trainings projects, storage run off river Dam Safety Indian experience, Preparedness & Response, Safety Issues, Emergency Warning System Indian Environmental Regulations, Acts & Procedures Project EMP : monitoring output, outcome of EMP and Owners responsibility Clean Construction Technology Waste Minimization and Management Health & Safety Management System and Responsibilities Risk Assessment and Management Public Consultation / Information dissemination Implementation of THDC Corporate Policies - THDC Corporate Policies Environmental Impacts of Hydropower projects, storage run off river

Schedule for Training India 24 person days in India 16 person days abroad 24 person days in India 24 person days in India 24 person days in India 24 person days in India 24 person days in India 24 person days in India 10 person days in India 6 person days in India 5 person days in India 16 person days abroad 5 person days in India 16 person days abroad 5 person days in India 5 person days in India 5 person days in India 5 person days in India 5 person days in India 5 person days in India 5 person days in India 5 person days in India 5 person days in India 5 person days in

Training Budget 3.0 lakh 5.0 lakh

2.0 lakh 2.0 lakh

2.0 lakh 5.0 lakh 3.0 lakh 3.0 lakh 2.0 lakh 2.0 lakh 2.0 lakh 2.0 lakh 5.0 lakh

3.

THDC Corporate Unit (Social & Env Dept Technical, Planning, Finance, Procurement) & Senior Management

Dam Safety Indian experience, Preparedness & Response, Safety Issues, Emergency Warning System Detail Safety manual and Safety Plans EIA / EMP Content and Phases

2.0 lakh 5.0 lakh

2.0 lakh 2.0 lakh 2.0 lakh 2.0 lakh 1.0 lakh 1.0 lakh 1.0 lakh 1.5 lakh 1.0 lakh 1.0 lakh

4.

National / State requirements for EIA and Other relevant Rules Responsibility for EMP and Resource need for Env Mgmt in THDC Indian / State Environmental Construction Contractor & Its Regulations, Acts Staff THDC Environmental Polices / Guidelines Implementation of THDC Corporate Policy Details of Project EMP -Contractors responsibilities Monitoring outputs, results and outcome of EMP Contactors reporting on : Environment,

132

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 133 Date: Nov 2009 Revision: R4

S.No.

Target Trainee

Trainings Health and Safety Detail Safety Manual & Practices Safe Construction Practice and Clean Construction Technology

Schedule for Training India 5 person days in India 5 person days in India

Training Budget 1.5 lakh 1.5 lakh

Source: CES

Scheduled Year of Training

2009-2010 2010-2011 2011-2012 2013-2014 2014-2015


Source: CES

Table-4.18.14 Tentative Estimate for Environmental Training Person days of training Person days training planned source Budget (INR planned by Category of Lakh) of training officers Middle level Senior In India Abroad Visit In House Management 72 24 72 24 48 34.4 100 45 100 45 48 57.6 60 30 60 30 48 43.0 72 30 72 30 48 44.4 42 24 72 24 48 34.4 Total Budget for Training on Environmental Management 213.8

The training requirements have been suggested keeping in view the strengthening and capacity building requirements of THDC, particularly the officials and staff involved in VPHEP, to enhance their capability in the management of environmental and social issues related to the project and to ensure compliance of applicable safeguard policies of the World Bank and the Government of India. Environmental Training should be prioritised for Environmental Staff. The order of training program should be as Environmental Staff - Project Staff - Corporate Staff Senior Management. A. 30 % Environmental staff should be trained then only training to Project Unit staff should be provided B. 50% Environmental staff should be trained then training to Corporate staff (Technical,
Planning, Finance, Procurement) should be provided

C. After completing training of 70% Environmental staff Senior Management should be provided
training.

4.18.11 Lesson Learnt By TDHC Tehri Dam Project was approved by the Planning Commission in 1972 and was accorded the administrative clearance in 1976 by Uttar Pradesh Government. Various Project activities related to R&R and Catchment Area Treatment (CAT) works started during 1976 to 1978. Forest (Conservation) Act came into existence in 1980; Environmental (Protection) Act came into existence in 1986 while National Forest Policy was framed in 1988, National Environment Policy in 2006 and National Water Policy in 2002, thus there were no guidelines and hence there was no clarity about environmental safeguards. The National R&R Policy was adopted in 2007 The EIA notification of

133

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page: 134 Date: Nov 2009 Revision: R4

19994 has been revised in September 2006. In view of the above, there were no guidelines at that time on R&R as well as environmental aspects. Following experience were gained from implementation of Tehri Hydro power Project: The CAT programme should be developed by the Project in consultation with the State Forest Department keeping in mind (i) the results of fauna study, (ii) botanical species required for the desired fauna considering the fauna study, and (iii) soil conservation works in direct draining areas. CAT plan should include plantation of all types of the area including fruit bearing plants, medicinal plants, herbs and shrubs etc. The CAT plan should be implemented by Forest Department of the State Government, adopting their Joint Forest Management (JFM) Scheme Compensatory afforestation should fulfill the requirement of an ideal forestry, that is: Supply of forest goods and services to the people with a well thought out plan of production; and long term ecological security through conservation of forest cover and its restoration. A massive social forestry programme is needed to meet the demands of local people for fuel, fodder, timber etc. Compensatory afforestation in the same eco-system is more effective and compensate the damages due to deforestation in that eco system . Measures should be taken for propagations of Fisheries Stabilization of Hill Slopes and Reservoir Rim A plan for re-vegetation of muck disposal sites should be adopted. Treatment of borrow areas, abandoned quarries should be undertaken by the project. People displaced from the affected areas may not be moved up-stream of the watershed as, use of forest and cultivation by them can change land use pattern and increase soil erosion, leading to increased sedimentation thereby reducing storage capacity and affecting water quality. Therefore, it is always advisable to resettle the displaced families in the plains or command area of the Project. Employment provision to local inhabitants for unskilled work. Promotion of improved ecotourism EIA and SIA study should be conducted and a detailed Environmental and Social Management and Monitoring plan should be framed With the hind sight of the lessons learnt during implementation of the Tehri Hydro Project, the management of VPHEP have taken a conscious decision to initiate actions on all the above aspects, as applicable to the project. Thus, the VPHEP have already taken up or going to take up shortly, at appropriate time, the work relating to catchment area treatment, compensatory afforestation, hatcheries for fish propagation, resurfacing/ re-vegetation of muck disposal sites, quarry and borrow area relocation and rehabilitation of project affected people and so on.

134

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:135 Date: Nov 2009 Revision: R- 4

4.19

BUDGET FOR IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN A capital cost provision of about Rs. 760.9 million has been kept towards the environmental protection measures in the EMP. The details are given in the following tables and the summary is presented in Table-4.19.1.
Budget for Biodiversity Management Activity Cost (Rs. million) Herbal Garden 0.6 Wildlife Protection 0.5 Roadside Plantation 1.5 Compensatory Afforestation 64.0 Total (Rs.) 66.6
Source: CES

Budget for CAT Plan Particulars Rs. in Crores CAT Plan 2.37 Forestry Work 3.75 Engineering Work 19.11 Wild Life Management Work 2.43 Residential and Non Residential Building New Construction 2.59 and Renovation for Field Staff Foot Path Renovation 1.20 Foot Bridge New Construction and Renovation 0.37 Other Developmental and Participatory Activities 15.21 Total 47.00
Source: CAT Plan prepared by Badrinath Forest Division, Gopeshwar

Budget for Implementation of Muck Disposal Plan Cost Plantation on spoil slope (plain area) Turfing of Slopes Fencing cost for 2092 Rm(biofencing) Cost of 4 portable pumps (flow 20 cm/hr,20 m head, along with 200m pipe) and pump house Cost of nursery Maintenance of Nursery (for 4 years) Watch & Ward Contingencies) Grand Total
Source: CES

Cost (Rs. million) 2.00 0.490 0.843 1.800 2.000 0.600 2.600 2.240 19.783

Budget for Fish Management S.No Component Up-gradation of Hatchery including O&M 1. 2.
Vehicle for fish transportation Water Quality monitoring U/S and D/S

Cost (in Rs. million)


8.740 0.600 1.000

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:136 Date: Nov 2009 Revision: R- 4

S.No

Component
Miscellaneous & Contingencies Plantation along Birahi Total

Cost (in Rs. million)


.0600 1.000 11.400

Source: CES

Budget for Greenbelt Development Plan Description Unit Quantity Plantation of 12,306 trees
Source: CES

No.

12,306

Cost (Rs.) 500

Total Cost (INR) 6153000 Rs. 6.15 million

Budget for Restoration of Quarry Sites Activities/purpose Cost (Rs. million) Filling up the land with soil 1.50 Cost of green manure 0.50 Cost of sapling (10,000 saplings/ha) @ Rs. 4.00 per sapling 0.04 Cost of fertilizers and pesticides 0.50 Fencing with RCC pillars and barbed wire 0.30 Maintenance activities including cleaning of weeds @ Rs.50,000 0.25 for 5 years Digging of pits 0.08 Watch and ward (4 persons for 7 years @ Rs. 4000/month 1.83 including escalation of 10% every year) Total Rs 5.00 million
Source: EIA Report prepared by WAPCOS /CES

Budget for Solid Waste Management Item Covered truck Employee Persons Miscellaneous Total
Source: EIA report prepared by WAPCOS / CES

Cost (Rs. Million) 5.000 4.390 0.409 9.799

Budget for Implementation of EMP Measures for Road Construction Item Cost (Rs. million) Clearing and grubbing 4.0 Provision of breast walls, construction of catch water and 3.0 interceptor drains Provision of drainage system along roads 2.0 Total 9.0
Source: EIA Report prepared by WAPCOS /CES

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:137 Date: Nov 2009 Revision: R- 4

Budget for Sanitary Facilities for Labour Camps Unit Rate (Rs./unit) Construction of Community latrines with water supply Construction of Septic tanks Miscellaneous & Contingencies Total
Source: EIA Report prepared by WAPCOS/CES

Number

Total cost (Rs. million) 8.200 4.250 0.050 12.500

20,000 250,000

410 17

Budget for Provision of Fuel The total cost required for provisions of fuel works out to Rs.40.32 million. The cost has to be borne by the contractor; hence, the same has not been earmarked in the cost required for implementation of Environmental Management Plan. However, THDC can provide subsidized fuel for labour population and their families. An amount of Rs. 1.0 million needs to be earmarked for this purpose. Budget for Public Health Delivery System: Items Rs. 37.30 million Total cost (Rs. Million) 16.000 4.200 2.880 2.400 1.440 1.500 0.960 0.600 3.000 2.400 1.020 0.700 TOTAL 37.300

Construction & establishment of Hospital / Dispensaries Doctors Nurses Health workers Attendants Drivers Health assistants Dressers Drugs & Medicine Ambulance Recurring Expenditure & Contingencies HIV / AIDS protection

Budget for Environmental Monitoring Programme Component Construction Stage (Rs. million) Water Quality 0 Air Quality& meteorology 2.840 Noise Level 0.500 Water related diseases 2.440 Effluent/ Water Quality monitoring 4.980

Operation Stage (Rs. million) 0.090

Total (Rs. million) 0.090 2.840 0.500 2.440

0.300

5.280

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:138 Date: Nov 2009 Revision: R- 4

Aquatic ecologyPhytoplankton, Zooplankton, macrozoobenthos, fish Soil erosion & siltation Environmental Expert Panel (1+5) Grand Total
Source: EIA Report prepared by WAPCOS

0.500

0.500

0 0 10.500 21.260 1.050 22.310 0.160 0.160 10.500

A budget of Rs.64.08 million is proposed for Adaptive Capacity Building


Item Corporate Recruitment Project Recruitment Laboratory Equipments Documentation and Communication Total Cost (Rs. Million) 49.980 10.200 0.550 3.350 64.080

Budget for Capacity Building Scheduled Person days of training Year of planned by Category of Training officers Middle Senior level Management 2009-2010 72 24 2010-2011 100 45 2011-2012 60 30 2013-2014 72 30 2014-2015 42 24
Source: CES

Person days training planned source of training In India 72 100 60 72 72 Abroad In Visit House 24 48 45 48 30 48 30 48 24 48 Grand Total

Cost (Rs. million)

3.44 5.76 4.30 4.44 3.44 21.38

Budget for ISO 14001 Environment Management System & OHSAS 18000 :Rs. 2.0 million Item Cost (Rs. Million) ISO 14001 OHSAS 18001 Total Archaeological Budget is: 2.5 million Item Opening museum Conservation of Heritage Structure Enhancement of Village TemplesTotal Total 0.8 1.2 2.0

Cost (Rs. Million) 1.5 0.5 0.5 2.5

Project Document Chapter-4

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Environmental Management Plan

Page:139 Date: Nov 2009 Revision: R- 4

Table-4.19.1 Summary of EMP Budget S. No. Item

Cost (Rs. million)

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16.

Biodiversity Management Implementation of CAT Plan Muck Disposal Management Plan Fish Management Greenbelt Development Plan Restoration of Quarry Sites Solid Waste Management EMP Measures for Road Construction Sanitary Facilities for Labour Camps Provision of Fuel Public Health Delivery System Environmental Monitoring Programme Adaptive capacity Capacity Building ISO 14001 Environment Management System Archaeological Management Grand Total

66.600 470.095 19.783 11.400 6.153 5.000 9.799 9.000 12.500 1.000 37.300 22.310 64.080 21.380 2.000 2.500 760.900

An EMP Evaluation Format is developed to monitor the activities provided in EMP. The Corporate S&E Dept will be responsible for Monitoring Statutory stipulation provided by MoEF, State Pollution Control Board and Forest Department. (Format attached as Annex 4.19.1).

Project Document Annex-4.15.1

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Forms for Environmental Management Plan

Page:1 Date: Nov 2009 Revision: R4

Annex-4.15.1 FORMS FOR ENVIRONMENTAL MANAGEMENT PLAN


FORM P.1 SITE IDENTIFICATION AND SETTING UP OF WORKERS CAMP AND CONSTRUCTION EQUIPMENT (Reporting by Contractor to EMC after certification by Environmental Expert) Construction Stage Report: Date Month.Year.. (Site layout of Construction camp and working drawings of dwelling units with allied facilities to be attached with format) Format to be submitted before target date (decided by PD) of establishing camps as Camp no. WC Location of Camp (_________) S. Item N. Detail of item camp 1. Size of Camp 2. Area of Camp 3. Distance from Nearest settlement Unit mxm Sq.m Type/Size/ Capacity/Present use/Ownership Details Remarks by SC, if any

4. 5. 6. 7.

Distance from nearest water source Date of camp becoming operational dd/mm/yy Present land use No other trees with girth>0.3m Details of top soil stacking Quantity of top soil removed Detail of storage of topsoil Details of workforce Total no. of labourers Total no. of Male Workers No. of male workers below 18 years of age Total no. of female workers No of female workers below 18 years of age No. of children Details of dwelling units No of dwellings Minimum size of dwelling No of opening per dwelling Minimum size of opening Walls Roofing Flooring Drinking water tank Capacity of Drinking water tank Size of drinking water tank

1. 2.

Sq.m Describe stackling

1. 2. 3. 4. 5. 6.

Nos. Nos. Nos. Nos. Nos. Nos.

1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

Nos. mxm Nos. Nos. Specifications Specifications Specifications Specifications Cum mxmxm

Project Document Annex-4.15.1

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Forms for Environmental Management Plan

Page:2 Date: Nov 2009 Revision: R4

S. N. 11. 12. 13. 14. 15. 16.

Item

Unit Nos. Nos. mxm Nos. mxmxm

Details

Remarks by SC, if any

Total No. of WC No. of WCs for female workers Maximum size of WC Total no. of bathrooms for female workers Size of septic tank for WCs Capacity of Water Tank for WCs/Bathrooms and general purpose 17. Fencing around camp Details of facilities Availability of security guard 24 hrs a day Details of First Aid Facility Availability of Day Care Centre

Y/N

1. 2. 3.

Y/N Y/N Y/N

Certified that the furnished information is correct the quality of work is as per god practice and all relevant information as required is attached

Environmental Expert (Environmental Management Cell)

Contractor

Project Document Annex-4.15.1

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Forms for Environmental Management Plan

Page:3 Date: Nov 2009 Revision: R4

FORM C.1 - WATER REQUIRED FOR CONSTRUCTION (Reporting by contractor to Environmental Expert) Construction Stage: Monthly Report Date. Month..Year

Sl. Source (Name) No. 1. Rivers

Location

Distance from Railway Track

Water Drawn (m3/day)

Remarks

2.

Streams/Canal

3.

Ponds

4.

Tube well

5.

Other source / tankers

Total Water Used

Certified that the above information is correct

Environmental Expert (Supervision Consultant)

Contractor

Environmental Expert (Environmental Management Cell)

Project Document Annex-4.15.1

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Forms for Environmental Management Plan

Page:4 Date: Nov 2009 Revision: R4

FORM C.2 - POLLUTION MONITORING (Reporting by Contractor to Environmental Expert of SC) Construction Stage: Report -Date________ Month__________ Year_________ (Locations at which monitoring to be conducted as per EMP) S. N. 1 2. 3. 4. 5. Water Monitoring 1 2 3 4 5 Soil Monitoring 1 2 3 4 5 Noise Monitoring 1 2 3 4 5 Location Details of location Duration of monitoring Instruments used Air Monitoring Target Date Date of completion Reason for Delay if any

Certified that the Pollution Monitoring has been conducted at all the locations specified in the EMP and as per the directions of the Environmental Expert SC

Environmental Expert (Supervision Consultant)

Contractor

Environmental Expert (Environmental Management Cell)

Project Document Annex-4.15.1

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Forms for Environmental Management Plan

Page:5 Date: Nov 2009 Revision: R4

FORM C.3 - HYGIENE REPORTING AT CONSTRUCTION SITE AND WORKER CAMPS

(Reporting by Contractor to Environmental Expert of SC) Construction Stage: Monthly Report Date Month.Year.. S. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Item Total No. of WCs No. of WCs Functioning No. of bathrooms functioning Water Tank cleaned First Aid facilities available Emergency Vehicle available & functioning Camp visit by Doctor/month Accident occurred, if any Measures taken Security available 24 hrs daily Water logging if any in Camp If yes, measures taken Unit Quantity Remarks

No. of times Details to be given Details to be given Yes/No Yes/No

Certified that the furnished information is correct and all relevant information as required is attached.

Environmental Expert (Supervision Consultant)

Contractor

Environmental Expert (Environmental Management Cell)

Project Document Annex-4.15.1

: Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project : 2008026/EC/Final Report : Forms for Environmental Management Plan

Page:6 Date: Nov 2009 Revision: R4

FORM O.1 - POLLUTION MONITORING Operation Stage: Report -Date________ Month__________ Year_________ (Locations at which monitoring to be conducted as per EMP) S. N. Location Details of location Duration of monitoring Instruments used Completion Date of Reason for completion Delay if any

Target Date

Air Monitoring 1 2. 3. 4. 5. Water Monitoring 1 2 3 4 5 Soil Monitoring 1 2 3 4 5 Noise Monitoring 1 2 3 4 5 Certified that the Pollution Monitoring has been conducted at all the locations specified In the EMP and as per the directions of the SC

Nodal Officer (THDC)

Field Officer (EMC)

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Annex-4.18.1 : ISO 14001:2004 Requirements

Page:1 Date: Nov 2009 Revision: R4

Annex-4.18.1 ISO 14001:2004 REQUIREMENTS GENERAL REQUIREMENTS Establish, document, implement, maintain and continually improve an environmental management system. ENVIRONMENTAL POLICY Define the environmental policy. a) Appropriate; b) Commitments: i) Continual improvement, ii) Prevention of pollution, iii) Comply with requirements, d) Framework for environmental objectives; e) Documented, implemented, maintained, f) Communicated; g) Available to the public PLANNING Environmental Aspects: Identify environmental aspects to determine those that have or can have significant impacts on the environment. Legal and other requirements: Identify and have access to legal and other requirements. Determine how these requirements apply. Objectives, targets and programme(s): Establish, implement, and maintain environmental objectives and targets (measurable where practicable), considering. a) b) c) d) e) Legal and other requirements, Significant environmental aspects, Technological options Financial, operational and business requirements, Views of interested parties.

Establish, implement and maintain programs for achieving objectives and targets, Include: a) Designation of responsibility; b) Means and timeframe.

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Annex-4.18.1 : ISO 14001:2004 Requirements

Page:2 Date: Nov 2009 Revision: R4

IMPLEMENTATION AND OPERATION Resources, Roles, Responsibility and Authority a) Ensure the availability of essential resources. b) Define and communicate roles, responsibility, and authorities. c) Appoint a specific management representative for establishing, implementing, and maintaining the system and for reporting. Competence, Training and Awareness a) Persons performing tasks are competent based on education, training, and/or experience. b) Identify training needs and provide training or other actions. Communication: Internal and external communications. Documentation: Information to describe the management system Control of Documents a) b) c) d) e) f) Approve documents for adequacy; Review and update as necessary; Ensure changes are identified; Relevant versions are available; Identify and control distribution of external documents Prevent unintended use of obsolete documents.

Operational Control: Identify and plan operations, and carry them out under specified conditions. This includes informing suppliers of any requirements Emergency Preparedness and Response: Identify potential for and respond to accidents and emergency situations. Review, revise, and test procedures. CHECKING Monitoring and Measurement a) Monitor and measure the key characteristics of operations. b) Calibrate or verify and maintain monitoring equipment. Evaluation of Compliance Periodically evaluate compliance with applicable legal requirements. Evaluate compliance with other requirements.

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Annex-4.18.1 : ISO 14001:2004 Requirements

Page:3 Date: Nov 2009 Revision: R4

Nonconformity corrective action and preventive action Deal with actual and potential nonconformities. a) Identify and correct nonconformities. b) Investigate nonconformities, determine causes, take actions to avoid recurrence. c) Evaluate need to prevent nonconformities and implement appropriate actions. d) Record results. e) Review effectiveness of actions taken. Actions taken are appropriate to the magnitude of the problems and the environmental impacts encountered. Control of Records: Establish and maintain legible, identifiable and traceable records to demonstrate conformity and results achieved. Internal Audit: Environmental management system internal audits at planned intervals. a) Determine if the system 1) Conforms to planned arrangements; 2) Has been implemented and maintained; b) Provide information to management. Base the program on activity importance and the results of previous audits. Selection of auditors and conduct of audits to ensure objectivity and the impartiality of the audit process. MANAGEMENT REVIEW Review the environmental management system at planned intervals for continuing suitability, adequacy, and effectiveness. Assess opportunities for improvement and the need for changes to the system. Input to management reviews include a) Results of internal audits and evaluations of compliance, b) Communication(s) from external interested parties, c) Environmental performance, d) Extent objectives and targets have been met, e) Estatus of corrective and preventive actions, f) Follow-up actions from previous reviews, g) Changing circumstances, and h) Recommendations for improvement. Outputs include decisions and actions related to possible changes to the system.

Annex 4.18.2

BOARD OF DIRECTORS

CHAIRMAN & MANAGING DIRECTOR (CMD)


COMPANY SECRETARY (CS) CHIEF VIGILANCE OFFICER (CVO)

Director (Technical)

Director (Finance)
G. M. (Finance & Accounts) AGM (Commercial) AGM (Internal Audit)

Director (Personnel)
AGM (Law & Arbitration) G.M. (Services) E.D. (HRD) G. M. (P & A) DGM (Corporate Communication) DGM (IT)

E. D. (Contracts) Rishikesh G. M. (Liaison) Noida


(Corp planning)

G.M. (Tehri Power Plant & Tehri PSP) G. M. (Koteshwar HEP) G.M. (Social & Environment, CSR) G.M. (Design-Civil/HM) G.M. (Design EM) GM (VPHEP) AGM (QA&I, OMS Safety) AGM (New Projects)

G. M.

Rishikesh

AGM (MPS) Rishikesh

Flow Chart: Organizational Setup of THDC India Ltd.

Project : Environmental Studies for Vishnugad Pipalkoti Hydro-Electric Project Document : 2008026/EC/Final Report Annex-4.18.3 : Details of Training Programs attended by VPHEP Staff

Page:1 Date: Nov 2009 Revision: R4

Annex-4.18.3
Details of Training Programs attended by VPHEP Staff Designation Type of Training Institution Training General Manager Senior Manager Senior Officer Environment ST MT MT MT 4 Mr. V. Thapliyal Senior Officer Environment Senior Officer Environment MT ST MT MT 6 7 8 9 10 Mr. S. Ghildiyal Mr. R. S. Negi Mr. N. C. Bahuguna Mr. Sanjeet Singh Mr. M. S. Rana Senior Officer Senior Engineer Senior Engineer Supervisor (GRI) Supervisor (GRI) MT MT MT MT ST MT
Source: CES Note: ST- Short Term, MT Mid Term

S No. 1 2 3

Name Mr. R. Khare Dr. D. L. Bhatt Mr. R. P. Bhatt

Training Component CDM Exposure visit EIA Exposure visit Exposure visit EIA EIA Exposure visit Exposure visit Exposure visit Exposure visit EIA EIA Exposure visit

Marcos Env. Mumbai SJVNL Centre for Science & Environment SJVNL SJVNL ESCI, Hyderabad Centre for Science & Environment SJVNL SJVNL SJVNL SJVNL Centre for Science & Environment ESCI - Hyderabad SJVNL

Mr. Manoj Rangar

Annex 4.19.1

Vishnugad Pipalkoti Hydro Electric Project (VPHEP)


Environmental Management Plan Budget
Item Activity Sub-Activity Unit TOTAL 201011 Physical Targets 2011- 2012- 2013- 201412 13 14 15 TOTAL 2010-11 2011-12 Financial Targets 2012-13 2013-14 2014-15 Operation Phase budget Implementation Responsibility Special Monitoring Requirement

Bio Diversity Management Plan

Develop Herbal Garden

Selection of Site year

300,000

300,000

Forest Dept GoUK

THDC/CS

Selection of species Nursury Development Plantation work

year

percent

63

37

65,000

36,000

23,000

6,000

Percent

10

75

15

167,000

20,000

126,000

21,000

Maintenance

68,000

12,000

20,000

12,000

12,000

12,000

Road Side Plantation

Slection of species Plantation & Fencing

year

CC

percent

80

20

1,500,000

900,000

450,000

150,000

Wildlife Protection

Setup Monitoring No. units Awareness Programs No.

200,000

200,000

Forest Dept GoUK 150,000 50,000

300,000

100,000

Compensatory Afforestation

Selection of Site ha

201

120

80

Selection of species Selection/ development of nurseries Plantation & fencing

year

year

year

year

ha

201

85

64

60

64,000,000

19,200,000

22,400,000

12,800,000

6,400,000

3,200,000

Sub Total

66,600,000

20,768,000

23,169,000

13,039,000

6,412,000

3,212,000

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

Catchment Area Catchment Area Treatment Plan Activities Gap plantation

ha

364

124

120

120

9,100,000

3,100,000

3,000,000

3,000,000

Forest Dept GoUK

THDC/ Joint Body

ha Pasture Development ha Social Forestry ha Fuel wood and fodder no Nursery development no Nursery maintenance km Barbed wire fencing Watch & ward 10 persons

280

100

100

80

2,800,000

1,000,000

1,000,000

800,000

60

20

20

20

1,500,000

500,000

500,000

500,000

60

20

20

20

600,000

200,000

200,000

200,000

1,000,000

600,000

400,000

500,000

250,000

250,000

500,000

300,000

200,000

manmon 360 th ha 15

12

12

12

1,800,000

600,000

600,000

600,000

15

380,000

380,000

Contour bunding m Step drain no Check dams ha Ecorestoration Plantation ha Densification ha Pasture development ha Medicinal Plantation ha ANR No. Vegetative check Engineering WorkDams 3750 1200 1400 1150 24,750,000 7,920,000 9,240,000 7,590,000 1200 200 200 200 300 300 10,971,600 1,828,600 1,828,600 1,828,600 1,828,600 1,828,600 1,828,600 300 80 140 80 8,723,700 1,376,240 3,228,420 2,910,920 1,009,640 141,480 57,000 50 50 1,085,150 666,500 376,950 22,700 9,500 9,500 450 90 230 130 10,933,650 1,273,770 4,069,330 3,985,090 1,358,220 154,140 93,100 200 150 50 5,815,800 2,580,450 2,397,650 699,400 90,800 47,500 20 10 10 4,000,000 2,000,000 2,000,000 500 200 200 100 1,250,000 500,000 500,000 250,000

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

No. Gully plugging No. Stone checkdams No. Cratewire checkdams No. Spur No. Percolation tank Wildlife Management Work No. Anti Poaching hut No. Forest guard residence No. Wildlife Chetana centre Fire Extinguishing centre No.

6000

2000

2000 2000

9,900,000

3,300,000

3,300,000

3,300,000

6000

1200

2400 1200 1200

45,300,000

9,060,000

18,120,000

9,060,000

9,060,000

4000

1250

1750 1000

66,000,000

20,625,000

28,875,000

16,500,000

2200

700

1050 450

33,440,000

10,640,000

15,960,000

6,840,000

2500

1200

1300

11,750,000

5,640,000

6,110,000

10

2,500,000

1,500,000

1,000,000

10

5,500,000

3,300,000

1,100,000

1,100,000

3,000,000

3,000,000

10

4,500,000

2,700,000

1,800,000

No. Wireless Room No. Watch Tower Conservation of No. Water Resources No. Water Chery Man Animal Conflict Evaluation

700,000

700,000

3,000,000

2,000,000

1,000,000

25

15

10

1,250,000

750,000

500,000

25

15

10

375,000

225,000

150,000

3,000,000

600,000

600,000

600,000

600,000

600,000

500,000

100,000

100,000

100,000

100,000

100,000

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

No. New ConstructionWages Hut No. Forester Residence No. Deputy Ranger Residence No. Forest Rest house No. Store room No. ACF Residence No. T.O Quarter No. Renovation Forest Guard Residence No. Forester Residence No. Resin Chowkidar Quarter No. Check gate No. ACF Residence No. TO Quarter No. Range Ordalee residence No. Foot Path new construction Foot Path renovation No.

14

4,200,000

2,700,000

1,500,000

3,000,000

2,250,000

750,000

850,000

850,000

5,000,000

5,000,000

1,400,000

1,400,000

2,500,000

2,500,000

6,000,000

6,000,000

600,000

600,000

1,000,000

750,000

250,000

350,000

350,000

150,000

150,000

400,000

400,000

400,000

400,000

60,000

60,000

178

50

80

48

8,900,000

2,500,000

4,000,000

2,400,000

158

40

80

38

3,160,000

800,000

1,600,000

760,000

No. Foot Bridge new construction Foot Bridge renovation Other Development activities No.

2,200,000

1,100,000

1,100,000

1,500,000

500,000

500,000

500,000

percent

100

25

25

25

12

13

152,000,000

37,500,000

35,500,000

32,000,000

19,000,000

13,000,000

15,000,000

Sub Total

470,094,900

144,028,610

161,578,300

97,849,210

33,678,560

15,924,520

17,035,700

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

Muck Management Plan

Construction of Selection of retaining walls on dump sites disposal sites Handover sites to Contractor Construction of retaining wall Rehabilitation

No.

CC

THDC/ CS

No.

No.

EPC Contract

Identify rediness year for rehabilitation (part of site) Prepare plan year

CC

Development of year Nursery (or Contract) Procure pumps & pump house Plantation on spoil slope Turfing of slopes No. 4

2,000,000

600,000

600,000

600,000

200,000

1,800,000

1,800,000

sites

2,000,000

600,000

800,000

600,000

7,700,000

200,000

2,500,000

2,500,000

2,500,000

bio-fencing of site Maintenance

843,000

200,000

523,000

120,000

600,000

150,000

150,000

150,000

150,000

Watch & ward

2,600,000

800,000

800,000

1,000,000

Contingencies/es calation Sub Total D Fish Management Plan upgradation of Hatchery including O&M Vehicle for fish transportation Water Quality monitoring U/S and D/S Year

2,240,000

448,000

448,000

448,000

448,000

448,000

19,783,000 8,740,000

1,048,000 4,740,000

1,398,000 1,000,000

7,098,000 1,000,000

5,421,000 1,000,000

4,818,000 1,000,000

0 Dept of Fisheries,GoUK / DCFR ICAR Bhimtal THDC / CS

No

600,000

200,000

200,000

200,000

2 per season

30

1,000,000

200,000

200,000

200,000

200,000

200,000

Miscellaneous & year Contingencies Plantation along year Birahi

60,000

12,000

12,000

12,000

12,000

12,000

1,000,000

200,000

400,000

400,000

Sub Total

11,400,000

5,152,000

1,612,000

1,812,000

1,412,000

1,412,000

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

Green Belt Development Plan

Selection of site year

THDC

THDC /CS

Selection of species Plantation

year

No

12306

4000

4000 4000 306

5,153,000

1,500,000

1,500,000

2,000,000

153,000

Fencing

No

4000

4000 4000 306

1,000,000

250,000

250,000

250,000

250,000

Sub Total F Restoration of Quarry Site Filling up of excavated sites year 4

6,153,000 1,500,000

1,750,000

1,750,000 400,000

2,250,000 400,000

403,000 400,000

0 300,000

0 CC THDC /CS

Purchase green year manure Digging pit year

500,000

250,000

200,000

50,000

80,000

30,000

30,000

20,000

Plantation of saplings Purchase Fertilizer Weeding & maintenance Fencing

year

40,000

15,000

15,000

10,000

year

500,000

200,000

150,000

150,000

years

250,000

50,000

50,000

50,000

100,000

year

300,000

100,000

100,000

100,000

Watch & ward 4 years persons

1,830,000

192,000

211,200

232,320

1,194,480

Sub Total G Solid Waste Management Plan Selection of Disposal Area Covered truck year

5,000,000

400,000

1,237,000

1,156,200

912,320

1,294,480 THDC THDC / CS

No

5,000,000

2,500,000

2,500,000

Employee Persons Miscellaneous

No

10

10

4,390,000

878,000

878,000

878,000

878,000

878,000

409,100

100,000

100,000

100,000

100,000

9,100

Sub Total

9,799,100

3,478,000

3,478,000

978,000

978,000

887,100

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

Road Construction

Clearing & grubbing Construction of breast walls Drainage

Year

4,000,000

4,000,000

CC

THDC /CS

Year

3,000,000

3,000,000

Year

2,000,000

2,000,000

Sub Total I Sanitary Facility Labour Camp Construction of Community latrines with t l Construction of Septic tanks Miscellaneous & year Contingencies 5 No 410 200 200 10

9,000,000 8,200,000

9,000,000 4,000,000

0 4,000,000

0 200,000

0 CC THDC/ CS

No

17

4,250,000

1,500,000

1,750,000

1,000,000

50,000

10,000

10,000

10,000

10,000

10,000

Sub Total J Fuel Kerosene / LPG Year Construction & establishment of No Hospital /Dispensaries No Doctors No Nurses No Health workers No Attendants No Drivers No Health assistants No Dressers years Drugs & Medicine No Ambulance Recurring Expenditure & Contingencies * HIV / AIDS Protection 3 2 1 5 2 2 2 2 5 5 4 4 4 4 4 4

12,500,000 1,000,000

5,510,000 200,000

5,760,000 200,000

1,210,000 200,000

10,000 200,000

10,000 200,000

0 0 CC / THDC THDC /CS

Public Health Delivery Plan

16,000,000

16,000,000

THDC

THDC /CS

4,200,000

840,000

840,000

840,000

840,000

840,000

2,880,000

576,000

576,000

576,000

576,000

576,000

2,400,000

480,000

480,000

480,000

480,000

480,000

1,440,000

288,000

288,000

288,000

288,000

288,000

1,500,000

300,000

300,000

300,000

300,000

300,000

960,000

192,000

192,000

192,000

192,000

192,000

600,000

120,000

120,000

120,000

120,000

120,000

3,000,000

600,000

600,000

600,000

600,000

600,000

2,400,000

1,600,000

800,000

years

1,020,000

204,000

204,000

204,000

204,000

204,000

years

900,000

200,000

200,000

200,000

200,000

100,000

THDC

THDC/CS

Sub Total

37,300,000

21,400,000

4,600,000

3,800,000

3,800,000

3,700,000

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

Environmental Monitoring Plan Water Quality

No

15

90,000

90,000

THDC

THDC /CS

days Air Quality& meteorology

480

96

96

96

96

96

2,840,000

568,000

568,000

568,000

568,000

568,000

CC

quaterly 20 Noise Level No Water related diseases samples Effluent/ Water Quality monitoring Aquatic ecology- No Phytoplankton, Zooplankton, macrozoobentho No Soil erosion & siltation No of Environmental visits Expert Panel (1+5) Sub Total M Adaptive Capacity Corporate Recruitment Manager Level and above Water & WQ Unit No 2 2040 15

500,000

100,000

100,000

100,000

100,000

100,000

2,440,000

488,000

488,000

488,000

488,000

488,000

408

408

408

408

408

5,280,000

996,000

996,000

996,000

996,000

996,000

300,000

CC / THDC

10

500,000

500,000

THDC

10 10 2 2 2 2 2

160,000 10,500,000 2,100,000 2,100,000 2,100,000 2,100,000 2,100,000

160,000 THDC 2 visits per year each expert

22,310,000 1 1 4,800,000

4,252,000 840,000

4,252,000 900,000

4,252,000 960,000

4,252,000 1,020,000

4,252,000 1,080,000

1,050,000 THDC THDC/ CS

No

9,960,000

840,000

1,920,000

2,160,000

2,400,000

2,640,000

EIA & No Compliance Unit Aquatic Ecology No Unit Biodiversity & Forestry Unit No

9,960,000

840,000

1,920,000

2,160,000

2,400,000

2,640,000

9,060,000

420,000

1,440,000

2,160,000

2,400,000

2,640,000

9,060,000

420,000

1,440,000

2,160,000

2,400,000

2,640,000

Climate Change No & Carbon Finance Unit

7,140,000

480,000

1,620,000

2,400,000

2,640,000

Sub Total Project Recruitment Manager and above Environment Engineer / Scientist No 1 1

49,980,000 4,800,000

3,360,000 840,000

8,100,000 900,000

11,220,000 960,000

13,020,000 1,020,000

14,280,000 1,080,000

No

5,400,000

840,000

960,000

1,080,000

1,200,000

1,320,000

10,200,000

1,680,000

1,860,000

2,040,000

2,220,000

2,400,000

THDC

THDC / CS

Laboratory & Equipment

Water Quality

No

250,000

250,000

Air Quality

No

200,000

200,000

Meteorological

No

100,000

100,000

Sub Total

550,000

550,000

Annex 4.19.1

Item

Activity

Sub-Activity

Unit

TOTAL 201011

Physical Targets 2011- 2012- 2013- 201412 13 14 15

TOTAL 2010-11 2011-12

Financial Targets 2012-13 2013-14 2014-15

Operation Phase budget

Implementation Responsibility

Special Monitoring Requirement

Documentation & Special Studies, No 1 Communication Compliance Reporting, l t Photographic l monthly 60 monitoring Web Dissemination Year

3,000,000

400,000

400,000

600,000

600,000

1,000,000

12

12

12

12

12

250,000

50,000

50,000

50,000

50,000

50,000

100,000

20,000

20,000

20,000

20,000

20,000

Sub Total

3,350,000

470,000

470,000

670,000

670,000

1,070,000

Sub Total Adaptive

64,080,000

6,060,000

10,430,000

13,930,000

15,910,000

17,750,000

Capacity Building Plan

Training

Environment percent Engineer / Scientist-EMC & E D t Project Staff percent

100

30

30

20

15

7,775,000

1,600,000

1,985,000

1,550,000

1,640,000

1,000,000

THDC

THDC /CS

60

15

15

10

10

10

7,050,000

1,000,000

1,700,000

1,550,000

1,300,000

1,500,000

Corporate staff

percent

30

15

5,505,000

340,000

1,575,000

1,150,000

1,500,000

940,000

Contractor staff- Trainings 10 Trainings Sub Total

1,050,000

500,000

500,000

50,000

21,380,000

3,440,000

5,760,000

4,300,000

4,440,000

3,440,000

ISO /OHSAS

Systems

ISO 14000

Year

800,000

800,000

THDC

THDC /CS

OHSAS 18001

Year

1,200,000

1,200,000

Sub Total P Archaeological Management Plan Opening Museum Year

2,000,000 1,500,000

800,000

1,200,000 1,500,000

0 THDC THDC /CS

Conservation of Year Heritage site Enhancement of Year Village teples Sub Total GRAND TOTAL

500,000

500,000

500,000

500,000

2,500,000 760,900,000

0 226,086,610

0 225,187,300

2,500,000 155,655,210

0 78,072,760

0 56,517,940

0 19,380,180

76.09 Crores

Note

CC: Construction Contractor CS: Construction Supervisor/Third Party Monitoring

* The budget towards HIV / AIDS protection for Construction Contractor(CC) has been incorporated in EPC .

You might also like