You are on page 1of 22

1.040/1.

401
Project Management
Spring 2007

Planning

Dr. SangHyun Lee

Department of Civil and Environmental Engineering


Massachusetts Institute of Technology
Project Management Phase

FEASIBILITY DESIGN DEVELOPMENT CLOSEOUT OPERATIONS


PLANNING

Fin.&Eval. Organization
Risk
Estimating

Planning
Planning
Outline

¾ Planning – Hierarchical Project Structures


ƒ Work Breakdown Structure
ƒ Organization Breakdown Structure
ƒ Cost Breakdown Structure
Planning Components

„ What: Work Breakdown Structure


„ How: Plans and Specifications
„ Who: Organization Breakdown Structure
„ How much: Cost Breakdown Structure (via estimate)
„ When: Schedule
Outline

ƒ Planning – Hierarchical Project Structures


¾Work Breakdown Structure
ƒ Organization Breakdown Structure
ƒ Cost Breakdown Structure
Work Breakdown Structure

„ A WBS is a deliverable-oriented grouping of project components


that organizes and defines the total scope of the project
„ Work not in the WBS is outside the scope of the project
„ WBS is usually an operative tool used by contractors

„ First step towards constructing a schedule

„ Central role in project monitoring and control


WBS: Example different
summary level

Project

Level I
Site-Work On-Site Utilities Buildings Major Facilities

Grading and Paving Water Underground Office Maintenance Warehouse Level II


Drainage Surfaces System Electrical Building Building Building Sub-Facilities

Level III
Drives Parking Architectural Structural Mechanical Electrical Work Item

Foundation Shell Level IV


Tasks

Work Work Work Level V


Package Package Package Work Packages
Denotes continued
breakdown

Illustrative Work Breakdown Structure (WBS)

Figure by MIT OCW.


Source: Shtub et al., 1994
Work Package

„ Lowest level

„ Distinguish from Others

„ Single Responsible Organization

„ Assigned Start and Finish

„ Assigned Budget

„ Limited Duration
Types of WBS

„ Project WBS
„ Operative tool for monitoring and control contractor work

„ Contractual WBS
„ Defines the level of reporting that the seller will provide the buyer
„ May include less detail than Project WBS
„ Agreed between owner and contractor
Functional Approach

GAS-STEAM COMBINED
POWER PLANT
level 0

MAIN FUNCTIONS OF PLANT


level 1 GAS STEAM INTERFACES

level 2 ITEMS
TURBINE GENERATOR COMPRESSION STATION

level 3
COMPRESSORS GAS TREATMENT ENCLOSURE UNITS

level 4
COMPRESSOR 1 COMPRESSOR 2 FOUNDATIONS SUB-UNITS

level 5
DESIGN PROCUREMENT INSTALLATION WORK PACKAGES
Physical Space Approach
„ Project
„ Main building
„ 1st floor
„ Structures
„ Plumbings
„ Electrical
„ HVAC
„ 2nd floor
„ Service building
„ Structures
„ Plumbings
„ Electrical
„ HVAC
Procedure Approach
„ Project
„ Feasibility
„ Design
„ Basic
„ Detail
„ Bid documents
„ Shop drawings
„ Bid
„ Construction
„ Foundations subcontract
„ Main building
„ Piles
„ Concrete foundations
„ Service building
„ Piles
„ Concrete foundations
„ Steel erection
„ Finishings
„ Commissioning
WBS: CSI Master Format - Example
NORTHWEST CONSTRUCTION COMPANY
1242 First Avenue, Cascade, Washington 98202
(206) 239-1422

Work Breakdown Structure


Huna Office Building
7/15/2000

CSI CSI
Description Description
Division Division
1 Job Site General conditions 9 Finishes:
2 Site work: Drywall
Earthwork & Utilities Painting
Paving Acoustical Ceilings
Walks & Miscellaneous Sitework Floor Covering: Carpet
3 Concrete: Floor Covering: Ceramic, Vinyl, Base
Purchase Reinforcement Steel 10 Specialties
Foundations 11, 12, 13 Equipment, Furnishings, & Special
Walls & Slabs Construction
4 Masonry 14 Conveying Systems (Elevator)
5 Structural and Miscellaneous Metals 15 Mechnical Systems:
6 Wood & Plastic Plumbing
Rough Carpentry Fire Protection
Finish Carpentry / Wood Floors HVAC
7 Thermal & Moisture Protection Controls
Insulation 16 Electrical Systems
Roof & Accessories
Gutters & Downspouts
8 Doors, Windows, Glass
Doors
Windows & Storefront Sample
Door Hardware
Source: Schaufelberger et al., 2002
Outline

ƒ Planning – Hierarchical Project Structures


9Work Breakdown Structure
¾Organization Breakdown Structure
ƒ Cost Breakdown Structure
Organization Breakdown Structure

„ Decomposition of necessary resources to perform job


„ Identification & organization of the resources responsible with
carrying out activities associated with the project
„ Used to keep track of specific work assignments & resource
allocations
Organization Breakdown Structure
„ Project resources
„ Project management team
„ Project manager
„ Construction superintendent
„ Field superintendent
„ Office manager
„ Scheduler
„ Accounter/controller
„ Field engineer

„ Construction force
„ Worker
„ Subcontractor
„ Electrical
„ Plumbing
„ Insulation
„ Tankage
„ Roads
OBS/WBS
Linkages Project
Linking the WBS and OBS.

People

WBS OBS

Major Major
Facility Group

Sub Facility Sub Group


or Department

Work Item Discipline

Task 1 Task 2 Task 3 Engineer A Engineer B Engineer C

Work
Package 1
Work
Package 2
Work Denotes continued
Package 3 breakdown

Figure by MIT OCW.


Source: Shtub et al., 1994
Outline

ƒ Planning – Hierarchical Project Structures


9Work Breakdown Structure
9Organization Breakdown Structure
¾Cost Breakdown Structure
Cost Breakdown Structure (CBS)

„ Breakdown of the costs of the various components of the


structure including all work done by the subcontractors
„ Serves as a basis for subsequent monthly pay requests by the
contractor
„ Used to continuously compare costs as they actually occur
with the budget
Cost Breakdown Structure (CBS)
MASTER LIST OF PROJECT COST ACCOUNTS
Subaccounts of General Ledger Account 80.000
PROJECT EXPENSE
Project Work Accounts .100 - .699
100 Clearing & Grubbing 245 Precast Concrete
101 Demolition 260 Concrete forms
102 Underpinning .01 footings
103 Earth Excavation .05 grade beams
104 Rock Excavation .07 slab on grade
105 Backfill .08 beams
115 Wood structural piles .10 slab
116 Steel structural piles .11 columns
117 Concrete structural piles .12 walls
121 Steel sheet piling 280 Structural Steel
240 Concrete poured 350 Masonry
.01 footings .01 8 in. block
.05 grade beams .02 12 in. block
.07 slab on grade .06 common brick
.08 bcarns .20 face brick
.10 slab on forms .60 glazed tile
.11 columns 400 Carpentry
.12 walls 440 Millwork
.16 stairs 500 Miscellaneous Metals
.20 expansion joints .01 metal door frames
.40 screeds .20 window sash
.50 float finish .50 toilet partitions
.51 trowel finish 560 Finish Hardware
.60 rubbing 620 Paving
.90 curing 680 Allowance
685 Fencing
Source: Shtub et al., 1994
Two Main Approaches

„ CBS = WBS
„ CBS is the project cost control structure

„ CBS ≠ WBS
„ CBS is the corporate multi-project cost control structure
„ Usually the case of a firm that has an integrated cost control system
Diverse Combinations

„ WBS + OBS: Task assignments


„ CBS + OBS: Budget monitoring of crews, etc.
„ OBS + Schedule: Time-specific crew assignments
„ CBS + Schedule: Cost monitoring

You might also like