You are on page 1of 8

Reconfiguration of radial distribution networks:

application of heuristic methods on large-scale


networks

G.Peponis
M. Papadopoulos

tndexitg terms: Distribution networks, Network reconfiguration. Energy loss reduction, Load balancing, Services restoration, Network model size reduction

- also enable full utilisation of system facilities. With the


Albstract: Heuristic methods for the introduction of remote control of the switches, online
reconfiguration of radial distribution networks configuration management becomes an important part
ha,ve been presented in recent years by several of distribution automation.
researchers. The objective of the studies involved As the operating conditions change, the network is
is either to minimise resistive line losses during reconfigured for two purposes: (i) to reduce the system
normal operation, or to balance load and relief energy losses; (ii) to relieve the overloads in the net-
overloads, e.g. during service restoration work. We will refer to the first problem as network
procedures. In the paper the two basic strategies reconfiguration for loss reduction and to the second as
employed and the adequate methods developed reconfiguration for load balancing. Service restoration
for both objectives are presented, improved and to as many customers as possible during the restorative
generalised. An efficient approach to the load state following a scheduled or forced outage, can be
balancing problem, using switch exchange partly treated as a special load balancing problem. Net-
operations, is presented. An overall algorithm for work reconfiguration can also be used in planning
the reduction of the size of the network model studies in order to determine the optimum configura-
without decreasing computations accuracy of all tion of the network during one step of the overall plan-
methods is also presented. The adequate ning procedure.
computer programs are applied on a real, large- Mathematical techniques from operations research
scale 20 kV Greek network, for the optimisation have been used mostly in planning models to minimise
of its operation under normal operating the costs associated with new constructions [l]. These
conditions and after the occurrence of an outage. methods have been also used for network reconfigura-
Gcneral conclusions are drawn regarding the tion and guarantee optimal solutions [2]. However,
comparison of the two strategies as modelled in they are either too time consuming or have other inher-
the paper and the opportunities network ent weaknesses which make them unsuitable for the
rec onfiguration offers for operation improvement. feeder reconfiguration problem [ 3 ] . The application of
- these methods, if properly structured, for the optimisa-
tion of the operation of real size networks with varying
1 Introduction loads is practically prohibited.
Most of the algorithms in the literature for network
Most electric distribution systems are normally oper- reconfiguration are heuristic search techniques based
ated radially; however, there are usually several inter- on analytical or knowledge-based engines. Civanlar et
connecting tie switches available, especially on the al. [4] presented a coinputationally attractive solution
underground medium voltage (6 to 35kV) networks. procedure for power loss reduction through network
Configuration alterations may be performed by chang- reconfiguration. Baran et ul. [5] were based on the
ing the state of network switches, in such a way that same strategy of load transfer steps, using different sets
radiality is always re-established after the end of the of power flow equations, to approach the solution of
manipulations. loss reduction and load balancing problems. Decision
An effective reconfiguration strategy takes advantage tree techniques were employed by T. Taylor et al. in [6]
of the large degree of load diversity that exists on some using principles founded in [4], and rules of thumb
distribution systems. Feeder reconfiguration would were created to decrease the search space. Liu et al. [7]
allow for the periodical transfer of load from heavily described an expert system operational aid for restora-
loaded portions of the distribution network to rela- tion and loss reduction of distribution systems. In [8] a
tively lightly loaded ones. This would not only improve knowledge guided heuristic search strategy was pre-
the operating conditions of the system, but it would sented by Morelato et al. These techniques are based
0 IEE, 1995 on a series of switch exchange operations, which is the
IEE Proceedings online. no. 19952155 first strategy for the approach of the network reconfig-
Paper first received 16th January 1995 and in revised form 12th June 1995 uration problem.
The au1:hors are with the National Technical University of Athens, A different approach to the problem of loss reduc-
Department of Electrical & Computer Engineering, Electric Power tion has been proposed by Merlin and Back [9], based
Divisiol:, Patission 42, 106 82 Athens, Greece on a special variation of the branch-and-bound tech-
IEE Pro<.-Gener. Transni. Distrib., Vol. 142, No. 6, November 1995 63 1
nique. The solution method starts with a meshed distri- 3.7 Switch exchange methods (SEM)
bution system obtained by considering all switches This method is based on the strategy of continuous
closed. Then, the switches are opened successively to reduction of network losses following sequential switch
eliminate the loops. This heuristic strategy was further exchange operations. A switch exchange operation is
improved and generalised by Shirmohammadi et al. in defined as the closing of an open switch and the open-
[lo] for loss reduction and in [l 11 for load balancing. ing of a closed one on the loop formed. The efficiency
This paper is aimed at generalising and improving of this method is based on the estimation by a simple
the two basic heuristic reconfiguration strategies in formula of the loss reduction AP obtained by a particu-
order to more efficiently apply them either for loss lar switch exchange option ([4] eqn. 1). Referring to
reduction or load balancing, using variable loads and Fig. 1, the loss reduction is given by:
different load models. An efficient approach to the
load balancing problem, using switch exchange opera-
tions, is presented. This is developed using the concepts
established in other methods.
An overall algorithm for network model size reduc-
tion, is also presented. Applying this algorithm some where:
network branch data are eliminated, while others are D = set of buses which are disconnected from Feeder-I1
replaced by equivalents. Accurate voltage values and and connected to Feeder-I with this switching option
changes of energy losses and load balancing index are
calculated, using the reduced size network model. This,
m, n = buses connected to branch m-n, where the
substantially improves the applicability of the two heu- switch to be closed is installed. Bus m is connected on
Feeder-I and bus n on Feeder-I1
ristic strategies for both objectives.
Applications on a real Greek overhead network of iz = complex load current at bus i
large size aim to make an exhaustive comparison of the Rloop;series resistance of the loop formed by closing
results of the two heuristic strategies as modelled in this the switch of branch m-n
paper. The opportunities these methods, combined with AVR, = voltage drop on the path 0 - m of Feeder-I
network model size reduction, offer for operation indi- when branch reactances are neglected
ces improvement are investigated.
AVR, = similar to AVRm but defined for bus n on
Feeder-I1
2 Load modelling
Re[.];*;l.l = real part, complex conjugate and magnitude
It is assumed that the total load at each node consists operators, respectively.
of five types (e.g. residential, industrial, etc.). For each After considering all possible switch exchange
type, load variation with time is introduced into the options, the one which provides the largest loss reduc-
network data base using typical load curves for the tion, without violating any facility loading limitations,
entire analysis time period. Each daily load profile (e.g. is carried out. This set of actions is called a ‘step’. Suc-
winter working day, summer weekend day, etc.) is cessive steps are followed until no further loss reduc-
characterized by a frequency of occurrence during the tion is possible.
overall analysis period. The total number of time
points (i.e. different network loading conditions) and 3.2 Improved switch exchange method
time subperiods (i.e. characteristic days) is practically (ISEM)
unlimited in our computer programs. Given the total SEM can be more efficiently applied by taking into
power installed and the load composition at each node, account the following remarks. f, is the load current
active and reactive load curves can be obtained. flow on branch i during one network loading condi-
Loads can be represented by different models as tion, while superscripts refer to the network configura-
constant current (voltage independent current injec- tions before and after the switching action.
tions), CC, constant power (inversely proportional to 1. Z,& = Ibefkl (in Fig. 1). Energy losses reduction can
voltage value current injections), CP, constant imped- be estimated by adding AP(t) for all different network
ance (directly proportional to voltage value), CI, and loading conditions.
mixed, MX, that is any combination of the previous
models. 2. A switch exchange option leading to energy losses
reduction is valid if no branch flow constraints are vio-
3 Network reconfiguration for loss reduction lated. Referring to Fig. l, the branch current flow
checks required, for all different network loading con-
The two main heuristic reconfiguration strategies and ditions, are defined by eqns. 2-6 [12].
the adequate methods developed for loss reduction are (a) On the path (0 - m - n):
briefly presented and discussed in this Section.

On the path (0 k - 1 - n):


-

-aft - xbef - “bef

-
I, - I a. Ik1 (3)
Check (3) is required only on the path I - n
Note: Generalising eqns. 2 and 3 it can be noticed that
feeder-I a switching action is equivalent to the flow of the
current -fbefkl(inverse current flow to this of branch
Fig.1 Switch exchange option: closing switch of branch m-n, opening k-l) on the loop formed by closing the switch of branch
switch of brunch k-1 m-n .
632 IEE Pvoc.-Gener. Transm. Distrib., Vol. 142, No. 6, November 1995
(b) [n practice, changes in the state of the two switches that provides the minimum losses on the next step is
are not simultaneous, and the loop formed may remain chosen to open. It is clear that as multiplier K takes
for several minutes. During this operating condition larger values the network with minimum increment of
constraint violations on the following branches should losses under OFP at each step is defined. This method
be examined: will be called the analytical SSOM (ASSOM) in this
paper.
(4) ASEM and ASSOM are introduced in order to check
where Zloo is the series impedance of the loop formed the potential of the corresponding methods to improve
by closing t t e switch of branch m-n. On the path (0 - their results. It is obvious that both analytical methods
m): require greater computational effort.
4"loop -
- 4"bef +Imn
"loop
(5) 4 Network reconfiguration for load balancing
On the path (0 - n):
"loop The methods presented in Section 3 can be applied for
I,, the determination of the network configuration that
It is expected that voltage quality and minimum volt- optimally or nearly optimally improves load balancing.
age values are improved by network reconfiguration The objective of this optimisation procedure can be
for loss reduction. Consequently, it is not necessary to expressed by the minimisation of the load balancing
check voltage drop limits violations at each step of index (LBI) [l 11:
SEM. This is validated in Section 6.

3.3 Sequential switch opening method


(SStOMI
LBI =
ZEB
Li [F)
/ I F I \ 2

in th.is method, developed in [9] and modified in [lo], a where:


low loss configuration is determined by applying an B = set of network branches forming loops
optirnal power flow analysis to the system with all
switches closed. This optimal power flow is referred as Li = length of branch i
'optimal flow pattern' (OFP). The system is led to a Ii= I[ + j I i = complex current flow in branch i
radial configuration by opening the switches of the IF = ampacity (current rating) of bus i
branches with the lowest current flow under OFP. If a subject to radiality and voltage drop constraints. The
switching action leads to constraint violations under multiplier Li is neglected by some authors [5], but it can
normal power flow solution, the switch carrying the be used in order to limit ampacity violations on the
next lowest current (under OFP) is opened. This set of shorter branches.
actions will be called 'step'. OFP at each meshed net- Wi can be defined for every network branch i, [I 11:
work is determined as the branch currents flowing in
the resistive network (with branch reactances (9)
neglected), the load nodal current injections considered Substituting W iin eqn. 8 reveals that the objective
constant. This method can be generalised with suffi- functions of loss minimisation and load balancing
cient accuracy for all load models. problems are mathematically similar, and W can be
Losadvariation during the entire optimisation period characterised as a modified branch resistance. Follow-
complicates the choice of the switch to be opened at ing this, many similarities can be expected between the
each step. The switch to be opened corresponds to the reconfiguration methods applied for these objectives.
branch k with minimum: Moreover, if one conductor type is used on the entire
F = xlfi(t)lz (7) network, reconfiguration for loss reduction and load
t balancing provide the same final configurations.
where i i ( t ) is the complex current flowing on branch i Service restoration, that is the minimisation of the
at time 1. The use of more complicated criteria, requir- load to be disconnected in the case of extended outages
ing additional computational effort, is not justified by a subject to ampacity and voltage drop constraints, can
corresponding improvement of the results. be partially treated as a special load balancing prob-
lem. Load balancing may not relieve all conductor
3.4 Analytical switch exchange method overloads in the case of an extended outage, especially
(ASEM); analytical sequential switch opening when the number of switch state alterations is practi-
method (ASSOM) cally restricted. A form of load shedding algorithm,
As both methods are based on heuristic algorithms, prioritising sections to minimise disruption to critical
they may converge to local minima. Storing the N best loads that provide essential services, must be applied in
configurations at each step of SEM and examining this case [7,14,15].
each of them as a starting configuration at the next The main differences expected between the algo-
step may decrease the chances of that event [13]. This rithms for service restoration and the respective for loss
extemion of the method will be called the analytical reduction, can be summarised in the following:
switch exchange method (ASEM). Similarly, at each (a) Switch state alterations for the isolation of the
step of SSOM several switches for which F (eqn. 7) has faulted area should be suggested prior to the applica-
value:; within a user-specified region above the mini- tion of the modified optimisation algorithms.
mum F are determined. That is, at each step all (b) There may be a strict limit to the number of the
switches that have P between switch state alterations suggested.
(minimum F ) 5 F 5 K x (minimum F ) (c) There may be no need to take into account several
( K 2 :I) are determined. Energy losses after the opening different network loading conditions, since an abnor-
of each of them under OFP are calculated. The switch mal operating condition shouldn't last so long.
IEE Prm-Gener. Transm. Distrib., Vol. 142, No. 6, Novembev 1995 633
(d) There is not a check for thermal limits violations at while another can be replaced by an equivalent, in a
each step, since this is the main objective of the optimi- way that the important electrical data are present, but
sation procedure. not the exact network synthesis.
In Section 4.1 an efficient approach to the load bal-
ancing problem is presented, based on a direct modifi-
5. I Branch data that can be neglected
It is obvious that it is not necessary to take into
cation of ISEM as this is applied for loss reduction.
account laterals that cannot take part in any loop
SSOM and ASSOM for load balancing are briefly pre-
formed by closing an initially open switch. Neglecting
sented in Section 4.2. these branches does not affect the optimisation proce-
4. I Improved switch exchange method dure. Adding the capacitance of the branches neglected
It is easy to prove (following the steps defined in [4], or and the load of the nodes fed by them to the load of
directly by applying eqns. 2, 3, 8 and 9), that LBI the node which presents the root of the lateral results
reduction obtained by a switch exchange operation can in an equivalent power flow solution on the remaining
be estimated, similarly to eqn. 1, by eqn. 10: part of the network.
I
1
5.2 Branch data that can be replaced by an
equivalent
On real networks there are several sections like A-B in
(10) Fig. 2 with the following characteristics:
where the quantities differing from those in eqn. 1 are: 1. Conductors on the path A-B are of the same type.
Wloop series modified resistance of the loop formed 2. There are no switches on the path A-B.
by closing the switch of branch m-n, where the resist- 3. The topology of the laterals departing from nodes on
ance of each branch has been replaced by W the path A-B can be neglected following the remarks of
AFmw = voltage drop on the path 0 - m of Feeder-I Section 5.1.
(Fig. 1) where branch impedances have been replaced On such sections, the load of all nodes on the path A-
by w B is transferred to the ‘destination nodes’ A and B
APnw = similar to AVmW but calculated on the path 0- using the equations:
n on Feeder-11.
If ISEM is applied for load balancing for one network LA-B
loading condition advantage can be taken by the heu- In this way the load of node k is divided and added to
ristic rule that LBI reduction can be expected only if the load of nodes A and B, and node k can be
lAFmwl < IAVnwI [4].
In some cases of ill designed networks load balancing
using ISEM cannot relieve all branch overloads that
may occur after a serious outage. A better approach is
to modify the objective function, eqn. 8, so that only LA-B ______i/
the overloaded branches are taken into account at each Fig.2 Load of nodes I , ...k,...N can be transferred to nodes A and B
step of ISEM. In this case ALBI‘ should be calculated
using eqns. 2 and 3. Other decision making criteria can neglected. At the end of these transfers, path A-B will
be also included in the objective function (on an eco- consist of one single branch, of the same conductor
nomical basis) at each step [16]. For example, under type and the total length of the initial path.
emergency reconfiguration during service restoration a After applying all possible transfers:
penalty related to the distance from the operations cen- the total load and the series impedance of all paths of
tre may be attached to each switch. reduced size remain the same;
4.2 Sequential switch opening method it is proven in the Appendix that network voltage cal-
SSOM as developed in [ll] faces load balancing and culations on the remaining nodes are not affected;
service restoration problems. Following the definition although the exact values of network losses and LBI
of the objective function, eqn. 8, the OFP of SSOM, is are affected, the changes evaluated by eqns. 1 and 10
replaced by the ‘secure flow pattern’, SFP. It is proven for switch exchange operations are not. Current flows
that this can be determined by solving the Kirchhoff on branches which have remained in their initial form
current law and Kirchhoff voltage law of a purely resis- (like those carrying switches), on radial or meshed con-
tive network, whose branch resistances are in this case figurations, remain the same as well. Thus, the deci-
equal to W. SSOM for service restoration provides suc- sions taken applying either ISEM or SSOM are not
cessive radial configurations (one at each step) in order affected.
to reduce the switch state alterations suggested to the Notes
limit specified by the operations engineer. At each step,
if an initially closed switch is decided to open, the ini- (a) In order to transfer the load of each node k to des-
tially open switch carrying the highest current under tination nodes A and B, only two remaining nodes
SFP is closed so that a radial configuration feeding the must surround node k . For example, in Fig. 3 if nodes
area not affected remains. A , B and C are maintained, node D must be also main-
tained.
5 Network model size reduction (b) Attention has to be given if there are long cables
having considerable capacitance, on network models
Different distribution network studies do not use a that are to be reduced (i.e. if the path A-B conductor
great part of detailed network data. For reconfigura- in Fig. 2 has considerable capacitance). If the presenta-
tion studies one part of branch data can be neglected, tion of the path A-B with several II-equivalents in
634 IEE Proc -Gener Transm Distrib , Vol 142, No 6, November 1555
series is more accurate, the capacitance of the single are indicative of the computation effort required by
branch A-B (after the load transfers) has to be each process.
adjusted. The estimation of network voltage quality on the
0 total network is obtained using Cw index [17]. This is
.-:, evaluated as the summation of node voltage variances
ok2.Each variance is calculated based on the nominal
,:=i voltage and the summation is weighted by the contri-
A
*+. ~. . 1-
D *...
0 bution of the node’s load to the total.

6.1 Applications network


a1’ ccq---. The applications network consists of sixteen 20kV lines
Fig.3 If nodes A, B and C are maintained, node D must also be departing from two 150120kV substations of the Ath-
maintained ens distribution network. 1104 branches defined by
1064 nodes and feeding 762 substations, describe the
5.3 Overall network size reduction algorithm network topology. There are 280 switches on it, 42 of
Using these ideas the following algorithm can be for- which are open, so that a radial configuration is
mulated for network model size reduction. ‘First class’ present under normal operation. Only small parts of
rejeccion of branches and nodes (steps 1 and 2) refers the network are underground. The total length of the
to the application of the ideas of section 5.1. ‘Second lines is 470.9km.
class’ rejection (steps 3 to 6) refers to the ideas of Sec- Five load types are used, i.e. urban, big industrial,
tion 5.2. small industrial, touristic, agricultural, or different
1. Find the branches that form loops when initially combinations of these types. Load curves are consid-
open switches close. Characterise them as first class ered to be different for each of two seasons of the year,
maintained. Characterise all other branches and the for working and not working days of each season.
node,s fed by them as first class rejected. Using hourly average values 96 different loading condi-
tions of the network are defined in total.
2. Add the load of the rejected nodes to the load of the The annual energy losses are 1721.9MWh (0.61% of
first node maintained on the path towards the root. the annual distributed energy). The maximum voltage
Add the capacitance of the rejected branches to the drop is 6.50%, and Cw voltage quality index is 13.6.
load of the same maintained nodes. These calculated values are similar to those reported by
3. Among the first class maintained nodes find the ones the operation engineers during 1993. It should be
where: remarked that the network is lightly loaded. Thus, no
Branches of different conductor types are connected. capacitors installation is economically justified.
Branches carrying a switch are connected. The study period is one year.
Characterise these nodes as second class maintained 6.2 Network model size reduction
(e.g. nodes A and B in Fig. 2). Application of the network model size reduction algo-
Characterise all first class maintained but not second rithm provides a network model consisting of 384
class maintained nodes as second class rejected (e.g. branches of total length 221.3 km and 344 nodes. 608
nodes 1,...,N in Fig. 2). branches are first class rejected (they do not take part
4. Among the second class rejected nodes find the ones in any possible loops, Section 5.1) and 112 nodes sec-
where at least three paths connected to second class ond class rejected (they belong to line sections with the
maini ained nodes are also connected. Characterise characteristics 1 - 3 of Section 5.2 and their load is
these nodes as second class maintained too (e.g. node transferred). Although second class rejected nodes are
D in Fig. 3). much less than first class rejected their removal sub-
stantially affects the computational effort required.
5. At this step each second class rejected node has only This is because second class rejected branches would
two :second class maintained nodes surrounding it. take part in many more computational procedures in
Transfer the load of all second class rejected nodes to both reconfiguration methods. 3 10 load nodes remain.
these maintained nodes using eqn. 11. Initial annual energy losses of the reduced network
6. Trmsfer and adjust the capacitance of the second model are 1633.4MWh. Computation time required by
class rejected branches to the two closest second class the size reduction process is 26.9s on our system.
maintained nodes (Section 5.2, note b).
7. Other user-defined nodes and branches may be also 6.3 Network reconfiguration for loss
characterised as maintained, e.g. in order to have accu- reduction
rate voltage drop values at remote nodes of the net- The main results of the steps followed applying ISEM
work. are illustrated in Fig. 4. At each step of this method the
state of two switches is altered. Successive radial con-
6 Applications figurations are provided. It is clear that energy losses
reduction is followed in general by voltage quality
All the above algorithms and methods were imple- improvement (Cw index). Application of ASEM (by
mented using C language and DOS graphics routines storing the 50 best configurations at each step) pro-
for interactive interface. The following applications vided the same final and intermediate results.
were implemented on a low cost 486 80MHz PC. The In Fig. 5 curve I illustrates the minimum losses under
computation times mentioned depend highly on the OFP at each step of SSOM for CC loads. At each step
management of the data files required to take into of this method the opening of one switch is proposed.
accouint load variation. However, as special attention If this switch is initially open, no switching action is
has been given by the authors to their reduction, they encountered. Otherwise, two switching actions are
IEE Pro<:.-Gener.Transm. Distrib., Vol. 142, No. 6, November 1995 635
encountered as an initially open switch should be Table 1: Network reconfiguration for loss reduction:
closed to maintain radiality on the final configuration. total energy loss reduction and computation times (CC
Only the final configuration is radial. The application load model)
of ASSOM for K = 2.0 and K = 13.0 provides the
Execution time, s
results illustrated by curves I1 and I11 in Figs. 5 and 6. Final Reduction
1750- ,1375% losses, from initial Network model:
c method
-135
72 MWh (%)
detailed reduced

ISEM 1582.8 8.09 2823 1077


SSOM 1607.3 6.62 5260 1971
ASSOM, K=2 1608.4 6.59
ASSOM, K=13 1632.7 5.18
0 6 12 18 24 30
ISEM: switch state alterations SSOM is next applied for other load models. The
Fig.4 ISEM reconfguration for loss reduction; annual energy losses and results indicate that although the load model affects the
voltage quality at each step
calculated losses, the final configuration suggested is
practically the same for all load models. Network
1650- model size reduction substantially improves the appli-
1600- cability of SSOM (execution times using the reduced
1550- network model are about 2.5 times smaller), without
affecting the suggested decisions for all load models.
1500-,
CC load model gives the results closer to these of MX
1450- model, which can be considered to be the most accu-
1400- rate.

0 4 8 12 16 20 24 28 32 36 40 44 6.4 Network reconfiguration for load


SSOM-ASSOM :switch state alterations balancing
Fig. 5 SSOM reconfguration for loss reduction ISEM and SSOM are applied in this section in order to
Annual energy losses under OFP: SSOM (curve I), ASSOM with K =2 (curve optimally balance the load after an outage in one of
11) and K = 13 (curve 111)
the two distribution centres. From the buses of the out-
detail raged centre six of the 16 lines feeding the area depart.
The initial radial configuration taken into account is
the one in which operations engineers would operate
the network by making 12 switch state alterations (six
to isolate the affected centre and six to connect the
lines served to the ones departing from the other cen-
tre). This operating condition is described by having
LBI = 13.38 and minimum voltage at the most remote
end 83.94%. There are no branch overloads.
LBI of the successive radial networks provided by
the two methods is illustrated in Fig. 7. The minimum
voltage of the network at each step of ISEM and
SSOM-ASSOM: switch state alterations SSOM is illustrated in Fig. 8. ASSOM is also applied
Fig.6 Detail from Fig. 5 (Figs. 7 and 8). ASEM provided again the same results
with SEM.
Final energy losses and execution times for these
methods, using the detailed and the reduced network
models are indicated in Table 1.
It is evident that the network model size reduction
substantially improves the applicability of ISEM and
SSOM, without affecting their results. It can also be
concluded that SSOM provides final results not as
close to the absolute optimum as ISEM, while it is
computationally more time consuming when applied on
large size networks. Furthermore, this strategy is
judged to produce unreliable results, since improve- 0 I 0 12 16 20 2 1 28 32 36 LO LL 18
ment of the intermediate steps does not improve the switch state alterations
final results. The conclusions drawn in [3] coincide with Fig. 7 Reconfiguration for load balancing, LBI for successive radial con-
the above. Application of the two methods on medium figurations provided by ISEM, SSOM and ASSOM
size networks [12,16] gives different results: SSOM is
much faster, while it gives practically the same results. It can be concluded that SSOM cannot be used to
If configuration alterations are accepted on a sea- provide successive radial configurations with improved
sonal basis (twice a year), a total annual energy losses operational indices. Only the final configuration pro-
reduction of 9.91 YOcan be achieved by 12 seasonal vided is close to the results provided by ISEM. Execu-
switch state alterations. The co-ordination of protec- tion times on our system are: 46.8s for ISEM and
tion should be examined in this case [16]. 229.9s for SSOM on the detailed network model, while
636 IEE Proc -Gene7 Transm Distrib , Vol 142, No 6, November 1995
those on the network model of reduced size (the results About 8% reduction of the annual energy losses is
are identical, respectively) are 6.6s for ISEM and 48.4s achieved if one network configuration is present during
for SSOM. one year of operation. If configuration alterations are
accepted on a seasonal basis an annual energy losses
,ISEM reduction of 10% can be achieved. Load balancing is
improved by 9.4% applying network reconfiguration,
after the occurrence of a serious outage.
Voltage quality is in general improved by network
reconfiguration for loss reduction. Maximum voltage
E14
drop is in general reduced by network reconfiguration
for load balancing.
a3 Constant current load model appears to be the most
o 4 a 12 16 20 24 2a 32 36 40 44 4a
accurate when there are no special data that justify the
switch state alterations
Fig.8 Reconfiguration for load balancing, minimum network voltage for
use of another model. Load model affects network
successive radial configurationsprovided by ZSEM, SSOM and ASSOM losses calculations but not the decisions suggested by
SSOM for loss reduction.
7 Conclusions SEM, when applied after the size of the network
model has been reduced by the proposed algorithm, is
The contribution of this paper can be outlined in the fast enough (especially if more powerful machines are
following: used) to be used online on emergency cases for service
1. The two basic heuristic reconfiguration methods, restoration.
switch exchange method (SEM) and sequential switch
opening method (SSOM), are generalised and improved 8 References
in order to be more efficiently applied either for loss
reduction or for load balancing. An efficient and flexi- 1 GONEN,T., and RAMIREZ-ROSAD0,I.J.: ‘Review of distribu-
ble approach to the load balancing problem, using tion system planning models: a model for optimal multistage
switch exchange operations is presented. planning’, IEE Proc. C, 1986, 133, (7), pp. 397408
2 CHEN,C.S., WU,J.S., and CHANG,Y.N.: ‘Criteria for inter-
2. An exhaustive comparison of the results of the two feeder switching in distribution systems’, ZEE Proc. C, 1988, 135,
(5), pp. 461467
heuristic methods when applied for both objectives on 3 WAGNER,T.P., CHIKHANI,A.Y., and HACKMAN,R.:
a real network of large size is made. The main conclu- ‘Feeder reconfiguration for loss reduction: an application of dis-
sions are the following: tribution automation’, ZEEE Trans., 1991, PWRD-6, (4), pp.
1922-1 933
While SEM requires substantially less computational 4 CIVANLAR,S., GRAINGER,J.J., YIN,H., and LEE,S.S.H.:
effort, it gives better results concerning the loss reduc- ‘Distribution feeder reconfiguration for loss reduction’, ZEEE
Trans., 1988, PWRD-3, (3), pp. P217-1223
tion and load balancing improvement achieved. 5 BARAN,M.E., and WU,F.F.: ‘Network reconfiguration in distri-
bution systems for loss reduction and load balancing’, IEEE
SSOM, on the other hand, can be applied for load Trans., 1989, PWRD-4, (2), pp. 1401-1407
models other than constant current, such as constant 6 TAYLOR,T., and LUBKEMAN,D.: ‘Implementation of heuris-
power, constant impedance or any combination of tic search strategies for distribution feeder reconfiguration’, ZEEE
Trans., 1990, PWRD-5, (I), pp. 239-246
these types. 7 LIU,C.C., and VENKATA,S.S.: ‘An expert system operational
SSOM cannot practically be used to derive successive aid for restoration and loss reduction of distribution systems’,
ZEEE Trans., 1988, PWRS-3, (2), pp. 619-626
radial configurations when applied for load balancing. 8 MORELATO,A.L., and MONTICELL1,A.: ‘Heuristic search
SEM provides radial configurations with small differ- approach to distribution system restoration’, ZEEE Trans., 1989,
ences in their operation indices in the last steps of the PWRD-4, (4), pp. 2235-2241
9 MERLIN,A., and BACK,H.: ‘Search for a minimal-loss operat-
method when applied for both objectives. This may ing spanning tree configuration for an urban power distribution
help the engineer to take decisions following other system’, Proceedings of PSCC, Cambridge, 1975, Paper 1.2/6
qualitative criteria and limit switch state alterations. 10 SHIRMOHAMMADI,D., and I-IONG,H.W.: ‘Reconfiguration
of electric distribution networks for resistive line losses reduction’,
The objective function of SEM is very flexible, since it ZEEE Trans., 1989, PWRD-4. (2), pp. 1492-1498
can include several different decision making criteria at 11 SHIRMOHAMMADI, D.: ‘Service restoration in distribution
networks via network reconfiguration’, IEEE Trans., 1992,
each step. That is, a combinatorial objective function PWRD-7,(2), pp. 952-958
can be established, based probably on an economical 12 PEPONIS,G.J., PAPADOPOULOS,M.P., and HATZIAR-
GYRIOU, N.D.: ‘Distribution network reconfiguration to mini-
basis. mize resistive line losses’, Proceedings of Athens Power Technol-
3. An overall algorithm for network model size reduc- ogy, Vol. 2, September 1993, pp. 601-605: republished in
Proceedings of IEEEiPES 1994 Summer Meeting, Paper APT
tion, is presented. One part of the network topology 425-06-21
data is neglected, while another is replaced by equiva- 13 STANKOVIC,A.M., and CALOVIC,M.S.: ‘Graph oriented algo-
lents in an efficient way, that provides a new network rithm for steady-state security enhancement in distribution net-
works’, IEEE Trans., 1989, P W R D 4 , (l), pp. 539-544
model of reduced size. On this, accurate voltage values, 14 CASTRO,C.H., BUNCH, J.B., and TOPKA,T.M.: ‘Generalized
and changes of losses and load balancing index are cal- algorithms for distribution feeder deployment and sectionalising’,
culated. Application of this algorithm substantially ZEEE Trans., 1980, PAS-99, (2), pp. 549-557
15 AOKI,K., NARA,K., ITOIH,M., SATOH,T., and
improves the applicability of the two heuristic methods KUWABARA,H.: ‘A new algorithm for service restoration in
for both objectives. distribution systems’, ZEEE Trans.., 1989, PWRD-4, (3)
16 PEPONIS,G.J., PAPADOPOUL:OS,M.P., and, HATZIAR-
4. Applications on a real overhead network of large GYRIOU,N.D.: ‘Optimal operatron of distribution networks’,
size were made to investigate operation indices Proceedings of IEEE/PES 1995 Winter Meeting, Paper WM 127-1
improvement that can be achieved by the use of recon- PWRS
17 BUNCH,J.B., MILLER,R.D., and WHEELER, J.E.: ‘Distribu-
figuration techniques. The main results on our applica- tion system integrated voltage and reactive power control’, IEEE
tions network are the following: Trans., 1982, PAS-101, (2), pp. 284-289

IEE Proc -Gener Transm Distrib , Vol 142, No 6, November 1995 631
9 Appendix

We will prove first that network voltage calculations on


the remaining part of the network are not affected by
the proposed load transfer (eqn. 11).
We assume that there are N nodes between destina-
tion nodes A and B (Fig. 2). All the branches on the
path A-B have the characteristics mentioned in Section
5.2.
Current symbols are defined in Fig. 2. Superscripts
refer to values on the detailed A-B section model
(superscript 'dtld') or on the one of reduced size ('rcd').
k=1
Assume that node A is closer to the root, i.e. branch
= p p l d - ~$dcI$ = v i t l d
current flows are directed as shown in Fig. 2. Load
current flow 7, will become: Consequently, after node B the network operation is
not affected.
The same are valid if branch flows are reverse, i.e. if 1
I
node B is closer to the root.
N N If the path A-B belongs to any part of the loop m-0-
p d - 'dtld 2cd - 'dtld + ;$tld L A - k n (Fig. 1) all the quantities in the second parts of eqns.
B -'B + k i B - zB
k=l k=l
1 and 10 remain the same if the proposed load transfer
is used. Rloopand Wloopare obviously not affected. The
5.,cd = 0 'dk E (1,.. . , N ) transfered load ZLEDi,(= Ikl in Fig. 1) is not affected as
branch k-Z remains on the reduced model (there is a
switch on it). AUmR and AUnR, AUmw and AUnW are
proven in the same way as above (voltage not affected)
not to be affected. Loss reduction or LBI reduction due
to a switch exchange step are thus proven not to be
affected by the proposed load transfer.
The resulting network model will have the same volt-
ages for the remaining nodes and the same losses and
LBI changes resulting from a switch exchange step.
Since network impedances and voltages remain the
same, nodal current injections representing the closing
of an open switch, eqn. 4, remain the same as well.
= ;Tld + 521d + 5Fld + y g l d = fdtld
A Therefore, there will be no changes on the power flow
k=l on meshed networks (using the original network
Consequently, before node A the way the netwqrk impedances, or under OFP, or under SFP). Thus,
'sees' section A-B is not affected. Furthermore, if Zk-l SSOM decisions will not be affected by the network
is the series impedance of the path between nodes k model size reduction. This is not valid when CP, CI or
and I: MX load models are used for SSOM, but size reduc-
i g d = 7,tld
tion can be applied with very satisfactory results in
these cases as well (Section 6).

638 IEE Proc -Gener Transm Distrib , Vol 142, No 6,November I995

You might also like