You are on page 1of 3

Maximum Loss Reduction by Optimal

Placement of Capacitors on a Distribution


System
B.V.Vibhute, Dr. H.P. Inamdar, and S.A. Deokar

Abstract -- This paper presents an implementation of a Novel and energy losses and to maintain the voltage profile within
Approach in radial distribution system for cost of loss reduction the acceptable limits. The amount of compensation provided
on an 11 KV distribution system consisting of 37 buses and 35 is very much linked to the placement of capacitors in the
transmission lines. The study is carried out incorporating an distribution system, which is essentially determination of the
appropriate load distribution model. This approach identifies location, size, number and type of capacitors to be placed in
an optimal location (node) of the capacitor by sequential the system.
comparison of line flows with previous ones followed by
The capacitor placement problem is a well research topic that
determination of size of the capacitor for maximum loss
reduction by taking the voltage magnitude and currents at that has been addressed by many authors in the past. All
particular node. The installation of capacitor indicated the approaches differ from each other by way of their problem
reduction in total system losses and there is overall formulation and problem solution methods employed.
improvement in voltage profile of the system. The paper proposes a method of minimizing the cost of loss
A study has been carried out on the 11 KV distribution system. associated with the reactive component of branch currents by
The objective of reducing the losses and improvement in voltage placing optimal capacitors at proper locations. The method
profile has been successfully achieved. After installation of first finds the location of the capacitors in a sequential
capacitor, the system can save a total energy of 682.8 KWH per manner. Once the location is determined, the capacitor size
day, which is very substantial.
at each location is determined through optimizing the
reduction in the cost of losses.
Index Terms – Capacitor, Energy, Reactive Power, System
loss, Voltage Profile.
II. PROBLEM FORMULATION
I. INTRODUCTION
In the proposed method a sequence of nodes to be
HE I2R loss reduction in distribution systems is very
T essential to improve the overall efficiency of power
system. The I2R losses can be separated into two parts based
compensated by the capacitors are identified. The sequence is
determined by repetitive application of minimization cost of
loss technique satisfying with single capacitor located at
on the active and reactive components of the branch current. proper node. Once the sequence of nodes to be compensated
Capacitors have been very commonly used to provide reactive are identified, the corresponding optimal capacitor size at the
power compensation in distribution system. The amount of compensated nodes can be determined simultaneously by
compensation provided is very much linked to the placement minimizing the cost of loss saving equation with respect to
of capacitors in distribution feeders as it reduces power and the capacitor currents. Following sections describes the
energy losses, increases the available capacity of the feeders, procedure for placement of capacitor.
and improves the feeder voltage profile. These capacitors
also reduces the lagging component current, increases the III. METHODOLOGY
power factor of generators, improves regulation and more
importantly increases the savings and hence reduces the cost With the help of line flows and bus voltages and powers
of power to consumers. obtained from the load flow result, the branch current is
Capacitors provide reactive power compensation in calculated from the formula.
distribution systems. They are provided to minimize power
Pik − jQik
B.V.Vibhute is with the Department of Electrical Engineering, Bharati I ik = --- ------------(I)
Vidyapeeth Deemed University College of Engineering, Pune, India Vi
(rajuvibhute@yahoo.com) where
Dr. H.P. Inandar is with the Department of Electrical Engineering,
Walchand College of Engineering , Sangli, India Iik = Current through branch (ik).
S.A. Deokar is with the Department of Electrical Engineering, All India Pik = Total real power flow in the branch (ik).
Shri Shivaji Memorial Societies College of Engineering, Pune, India Qik = Total reactive power flow in the branch (ik).
(s_seokar2@rediffmail.com)
Vi = Voltage at node (i).
0-7803-9525-5/06/$20.00 ©2006 IEEE.
Total power loss The loss saving S is the difference between equation (1) and
n (2) is given by
TPL = ¦ I ik2 Rik
ik =1 S = TPLr–TPLrcom
where
Rik = Resistance of branch (ik). n n
n = Total number of branches. = ¦ (I 2
r ( ik ) Rik − ¦ ( I r ( ik ) + D(ik ) I c ) 2 Rik
The branch current has two components: active (Ia) and ik =1 ik =1
reactive (If). The total loss associated with the active and n
reactive components of branch current can be written as, = ¦ (2 D ik I r (ik ) I c + Dik I c2 ) Rik
n n ik =1
TPLa = ¦ I a2(ik ) Rik TPLr = ¦ I r2(ik ) Rik
ik =1 ik =1 The capacitor current Ic that provides maximum loss saving
can be obtained from
The loss TPLa associated with the active component of branch δS/δIc=0 Ÿ
current cannot be minimized For a single – source radial ªn º
network because all active power must be supplied by the − 2 «¦ ( Dik I r (ik ) + Dik I c ) Rik » = 0
source at the root bus. However, supplying part of the ¬ik =1 ¼
reactive power demands locally, the loss TPLr associated with Thus the capacitor current form loss saving is given by
the reactive components of branch currents can minimized. − ¦ I r (ik ) Rik
ik∈α
. Ic = ----- (II)
¦α R
ik ∈
ik

The corresponding capacitor size is


Qc = Vm I c -----(III)

Where Qc = Capacitor size in KVAR


Vm = Voltage magnitude of bus ‘m’ in volts
Ic = Capacitor current in amps.
The corresponding Susceptance is
Fig. 1. Loss minimization using capacitor. S = Ic ---------------------------(IV)
Vm
Let a capacitor be placed at bus ‘q’ and ‘α’ be a set of The proposed technique can also be repeatedly employed to
branches connected between the source and capacitor is further optimising saving of cost of energy by identifying
placed and capacitor bus. A section of single line diagram is sequence of buses to be compensated for further loss
shown in Fig 1. If the capacitor is placed at ‘bus8’(q=8) the reduction by optimal placement of capacitor.
set α consists of branches a, b, c, f. Similarly when capacitor
is placed at ‘bus 6’ (q=6) the set α consists of branches a, b, IV. ALGORITHM
e.
The capacitor draws a reactive current IC and for a radial Step 1 : Variable declaration.
network it changes only the reactive component of current of Step 2 : Opening of input and output file.
branch set α. The current of other branches (∉α) is Step 3 : Conversion of polar form of bus voltage to
unaffected by the capacitor. Thus the new reactive current corresponding rectangular form.
I rnew th
( ik ) of the (ik) branch is given by,
Step 4 : The branch current is calculated using (I) with the
help of line flows.
( ik ) = I r ( ik ) + D( ik ) I c
I rnew Step 5 :The resistance of each line is read from the input file.
In order to find capacitor current.
where Dik = 1 ; if branch ik ∈ α
= 0 , otherwise. Step 6 :The destination is fixed as bus number ‘2’. The
Here Ir(ik) is the reactive current of the (ik)th branch in the source count is taken as ‘37’. From the line flows,
original system obtained from the load flow solution. The the From bus Of the 37th bus is compared with the
loss TPLrcom associated with the reactive component of branch bus of the previous branch line flow, if both are
current in the compensated system (when the capacitor is same, the branch is taken else it is left and is
connected) can be written as compared with the previous line.The process is
n repeated till the destination i.e bus ‘2’ is reached.
TPLcom
r = ¦ ( I r (ik ) + D(ik ) I c ) 2 Rik Step 7:After finding the path, the capacitor current is
ik =1 calculated using the formula (II).
Step 8 :The capacitor size is found by the formula (III).
Step 9 :The susceptance for the corresponding Q value is Total cost of capacitor = 345 * 220 * 4
calculated by formula (IV). = Rs. 3,03,600
Step10 : Now the source count is decremented till it reaches
bus number 2. Then the whole process is repeated VI. CONCLUSION
from step 6.
The objective of reducing the losses and improvement in
V. CASE STUDY & RESEARCH voltage profile has been successfully achieved studying 11
KV distribution system. After installation of capacitor, the
The technique proposed is tested on 11 KV distribution system can save a total energy of 862.8 KW per day, which is
system. There are about 37 buses, 35 transmission lines and very substantial. The repeated simulation results could be
28 load centres. The data regarding, line and transformers used to develop a Neural Network Model which can
are collected and are converted into per unit values to feed to accurately predict the location and size of capacitor for any
a load flow program. load conditions which gives a great promise for practical
Load flow study of the base case system is carried out using implementation of the proposed technique. The proposed
Mipower package. The result shows a system loss of method was tested on a 11 KV distribution system and
10.179% and voltage drop of 2.1 KV. This tells about the promising results were obtained.
scope for improvement in the distribution system.
With the help of the proposed technique loss reduction is VII. REFERENCES
maximum when a capacitor is placed at 22nd bus. After [1] S.I.Wamoto and Y.Tamura (1981), “A load flow calculation method for
installation, the load flow result indicate that the system loss ill-conditioned power system”, IEEE Trans. on Power Apparatus and
is reduced from 10.179 to 8.127 % and there is an overall Systems, Volume100, pp.1736-1740.
[2] D. Rajicic and Y.Tamura (1988), “A modification to fast decoupled power
improvement in the voltage profile of the system flow for networks with high R/X Ratio”, IEEE Trans. on Power Systems,
Volume 3, pp. 341- 348. [3] W.H.Kersting and D.L.Mendive (1796), “An
TABLE I application of ladder networks theory to the solution of three phase radial
POWER SAVING WITH CAPACIOR AND WITHOUT CAPACITOR load flow problem”, IEEE PES winter meeting, New York, paper A76
044-8.
[3] Aoki K, Kuwabara H, Satoh t, Kanezashi M (1988), “An efficient
Power Power With algorithm for load balancing of transformers and feeders”. IEEE Trans
Without the capacitor Difference in Power Deliv, Volume 3 (issue 4), pp.1865-1872.
Loading
placing placed at 33rd Active Power [4] Aoki k, Ichimori T, Kanezashi M. (1985), “Normal state optimal load
allocation in distribution systems”. IEEE Trans Power Deliv, Volume 3
capacitor bus (issue 1), pp. 147-155.
[5] S.Sivanagaraju, M.S.Giridhar, E.Jagadeesh Babu and Y. Srikath (2004),
Full load 0.2600 0.177 0.083 “A novel load flow technique for radial distribution system”,Proc. of
Half – National Power System Conference (NPSC-2004), IIT, Chennai, India, pp.
0.0559 0.0405 0.0154 140- 144.
Load [6] D.M. Tagare, Reactive Power Management, McGraw-Hill, 2000.
[7] Rani and Vijaya, “Distribution system loss reduction by capacitors”,Proc.
The load period per day is aassumed as of National Conference on Emerging Trends in Engineering(2000), Husur.

Full-load = 6 hrs
Half –load = 12 hrs VIII. BIOGRAPHIES
The cost of 1 KVAR of capacitor = Rs. 225
The cost of 1 KWH of energy = Rs. 2.5 B.V. Vibhute received the B.E. Degree in Electrical from Shivaji University in
Table I. presents computation results of active power with 1993, M.E. Degree in Electrical Power System from Pune University in 2002
and without capacitor placement. and perusing Ph.D. Degree under Bharati Vidyapeeth Deemed University, Pune.
Presently working as Assistant Professor at Bharati Vidyapeeth Deemed
Energy Saving per day: University College of Engineering, Pune.
F.L. = 0.083 * 6 * 103 = 498 KWH His research interests are electricity sector deregulation and ancillary service
pricing and management.
H.L = 0.0154 * 12 * 103 = 184.8 KWH
--------------------------- Dr. H.P. Inamdar received the B.Sc. Degree from Pune University in
Total savings per day = 682.8 KWH 1961,B.E. Degree in Electrical and Mechanical from Shivaji University in 1964
and 1965 respectively, M.E. Degree in Electrical from Shivaji University in
--------------------------- 1975 and Ph.D. Degree in H.V. Engineering from Indian Institute of Science,
Banglore in 1985. Presently working as Professor at Walchand College of
Total cost of energy saved per day Engineering, Sangli.
= 682.8 * 365 * 2.5
S.A. Deokar is perusing M.E. Degree in Electrical Power System from Pune
= Rs. 6,23,055. University and Presently working as Lecturer at All India Shri Shivaji Memorial
Societies College of Engineering, Pune.
A capacitor bank consisting of 4 capacitors each of 340 His research interests are modeling and design of hybrid renewable energy
system and energy conservation.
KVAR is installed at 22nd bus. The capacitor bank is
switched on / off according to the loading condition.

You might also like