You are on page 1of 9

554 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO.

1, FEBRUARY 2004

A Zonal Congestion Management Approach Using


Real and Reactive Power Rescheduling
Ashwani Kumar, S. C. Srivastava, Senior Member, and S. N. Singh, Senior Member

Abstract—In a deregulated electricity market, it may always and are adjusted continuously to reflect the changing system
not be possible to dispatch all of the contracted power transac- conditions.
tions due to congestion of the transmission corridors. System op- Several optimal power flow (OPF)-based congestion manage-
erators try to manage congestion, which otherwise increases the
cost of the electricity and also threatens the system security and ment schemes have been proposed. An approach for relieving
stability. In this paper, a new zonal/cluster-based congestion man- congestion using the minimum total shift in the transactions
agement approach has been proposed. The zones have been deter- is presented in [5]. A willingness-to-pay premium [6] has also
mined based on lines real and reactive power flow sensitivity in- been suggested to avoid curtailment of the transactions. Mar-
dexes also called as real and reactive transmission congestion dis- ginal cost signals are used in [7] for generators to manage con-
tribution factors. The generators in the most sensitive zones, with
strongest and nonuniform distribution of sensitivity indexes, are gestion. A similar approach is proposed in [8], where the con-
identified for rescheduling their real power output for congestion gestion cost is bundled with the marginal cost at each bus in a
management. In addition, the impact of optimal rescheduling of pool model and a congestion cost minimization is adopted in bi-
reactive power output by generators and capacitors in the most lateral model. With the help of flexible ac transmission systems
sensitive zones has also been studied. The proposed new zonal con- (FACTS), transmission network capability is utilized in a better
cept has been tested on 39-bus New England system and a 75-bus
Indian system. way and congestion can be managed in an efficient manner [9],
[10].
Index Terms—Congestion zones, transmission congestion distri- A congestion clusters-based method, which identifies the
bution factors, transmission congestion management.
group of system users according to their impact on transmis-
sion constraints of interest, has been proposed in [11]. These
I. INTRODUCTION clusters based on congestion distribution factors are termed as
clusters of type 1, 2 and higher, where type 1 cluster represents
I N a competitive electricity market, congestion occurs when
the transmission network is unable to accommodate all of
the desired transactions due to a violation of system operating
users with strongest and nonuniform effects on transmission
constraints of interest. The proposed clustering-based method
limits. Congestion does occur in both vertically bundled and has been used to create an efficient congestion management
unbundled systems but the management in the bundled system market, where the readjustment of transactions in the most
is relatively simple as generation, transmission, and, in some sensitive cluster can help in eliminating congestion. However,
cases, distribution systems are managed by one utility. The man- this method is based on dc load flow involving the assumptions
agement of congestion is somewhat more complex in competi- of lossless system and unity voltage magnitudes at all of the
tive power markets and leads to several disputes. In the present buses.
day competitive power market, each utility manages the conges- The optimal reactive power support in the system plays a very
tion in the system using its own rules and guidelines utilizing important role in maintaining an acceptable system voltage pro-
a certain physical or financial mechanism. Various congestion file and helping in managing the congestion more effectively.
management schemes suitable for different electricity market However, reactive power cannot always be delivered from a
structure have been reported in literature. But there is still a need source to an electrically remote sink. The local nature of the
for an efficient and more reliable method to solve this problem reactive power also implies that the generator may provide the
[1]. reactive power support for a number of transactions even if that
Hogan proposed the contract path and nodal pricing approach particular generator is not involved in the real power dispatch.
[2] using spot pricing theory [3] for the pool-type market. Chao The allocated contributions of the individual generator’s reac-
and Peck [4] proposed an alternative approach, which is based tive power output to a particular transaction can be negative or
on parallel markets for link-based transmission capacity rights positive [15]. Thus, the Var support requirement from genera-
and energy trading under a set of rules defined and administered tors and capacitors to manage congestion along with real power
by the system operator (SO). These rules specify the transmis- rescheduling poses a great challenge to SO in an open-access
sion capacity rights required to support bilateral transactions electricity market.
In this paper, a new zonal/cluster-based congestion manage-
ment approach has been proposed. The proposed method uti-
Manuscript received March 20, 2003. lizes two sets of sensitivity indexes termed as real transmission
The authors are with the Department of Electrical Engineering, Indian Insti- congestion distribution factors (PTCDFs) and reactive transmis-
tute of Technology Kanpur, Kanpur 208016, India (e-mail: ashwa@iitk.ac.in;
scs@iitk.ac.in; snsingh@iitk.ac.in). sion congestion distribution factors (QTCDFs) for congestion
Digital Object Identifier 10.1109/TPWRS.2003.821448 management in competitive power markets where selection and
0885-8950/04$20.00 © 2004 IEEE
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING 555

participation of generators/sources, not only depend on their rel- The coefficients appearing in (7) and (8) can be obtained
ative sensitivity, but also on their bid price for up/down regula- using the partial derivatives of real and reactive power flow (1)
tion to alleviate congestion. The most sensitive zones have been and (2) with respect to variables and as
identified as the union of most sensitive zones obtained on the
basis of real and reactive line flow sensitivity indexes separately. (9)
The impact of optimal rescheduling of generators and capacitors (10)
has been demonstrated in congestion management. The effec- (11)
tiveness of the proposed method has been tested on 39-bus New (12)
England system and a 75-bus Indian system.
(13)
(14)
II. MATHEMATICAL FORMULATION
The real power flow and reactive power flow in
a line- connected between bus- and bus- can be written as (15)
(16)
(1) For determination of TCDFs, the following Jacobian relation-
ship has been used:

(2) (17)

where and are the voltage magnitude and angle at bus- . Neglecting and coupling, (17) can be simplified
and are magnitude and angle of th element of as:
matrix. is the shunt charging admittance of line- .
(18)
A. Transmission Congestion Distribution Factors (TCDFs) (19)
Real and reactive transmission congestion distribution factors From (18) and (19), we get
(TCDFs) denote how much active and reactive power flow over
a transmission line would change due to change in real and re- (20)
active power injections, respectively. The real PTCDF’s are de- (21)
fined as the change in the real power flow in a trans-
mission line- connected between bus- and bus- due to unit Equations (20) and (21) can be rewritten in the following
change in the power injection at any bus- . Mathemati- form:
cally, the PTCDFs for line- can be written as
(22)
(3)
(23)
Similarly, the QTCDFs are defined as the change in the reac-
tive power flow in a transmission line- connected be- where is the number of buses in the system and is the slack
tween bus- and bus- due to unit change in the reactive power bus.
injection at bus- and can be written as It is assumed that the impact of change in the bus voltage on
real power flow and bus angle on reactive power flow is negli-
gible and, therefore, (7) and (8) can be rewritten as
(4)
(24)
Using, Taylor series approximation, (1) and (2) can be written (25)
(ignoring second and higher order terms) as
Substituting (22) into (24) and (23) into (25), we get

(5) (26)

(6)
(27)
Equations (5) and (6) can be rewritten as
or
(7)
(8) (28)
556 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 1, FEBRUARY 2004

sensitive zone 1 will contribute very little to the line flow.


(29) Thus, the identification of congestion zones will reduce the
computational burden, considerably, in both redispatching and
Equations (28) and (29) can be rewritten as physical curtailments necessary for the transmission loading
relief (TLR) in case of emergency and the adjustment of system
users themselves under normal conditions.
(30) The congestion zonal-based method is also applicable if more
than one transmission line congestion conditions are present in
the system. The congestion clusters/zones for a multicongestion
(31) case can be obtained by superimposing the clusters/zones cor-
responding to the individual line congestion.
where
The paper assumes that only one system operator is managing
the complete system. However, in case of several system opera-
tors, the clusters/zones will be defined separately to manage the
congestion in their operating area.
are the real and reactive transmission congestion distribution C. Selection of Generators and Optimal Location of
factors corresponding to a bus- and a line- connected between Capacitors for Reactive Power Support
bus- and bus- .
The Jacobian utilized for computing the TCDFs, in the The proper management of reactive power support in the net-
present work will change for any change in the system oper- work improves the system voltage profile and also helps in man-
ating condition. However, the suggested method is quite fast aging congestion up to some extent. It is important to identify
and can be utilized for updating the TCDFs and, hence, the the generators and capacitors required to provide reactive power
cluster of buses (zones) for congestion management. support in congestion management. In the present paper, the re-
active support of generators and capacitors, in addition to the
B. Zonal-Based Transmission Congestion Management rescheduling of real power generation, has been considered to
manage the congestion.
There are two broad methods for congestion management in Based on the QTCDFs, the SO identifies the most sensitive
a deregulated market. The first one is based on “price signal,” zones and optimally selects the generators for their reactive
which may be in the form of change in locational marginal price power rescheduling. However, the optimal placement of a
due to congestion or in the form of zonal price as practiced in the capacitor has been considered at a bus having the most negative
California market. The second approach is based on readjust- reactive power flow sensitivity indexes with respect to the
ment of transactions, which have been considered in the present congested line.
work. The concept of congestion zone in this work is different
from that used in the “California market.” In the present work, D. Transaction Redispatch for the Congestion Management
congestion zones are nothing but a cluster of buses, selected
The redispatch of transactions for congestion management in
based on sensitivity of flow in the congested line.
a pool model is formulated as a nonlinear programming problem
The TCDFs have been utilized for identifying congestion
and has been solved using the GAMS/CONOPT solver [13].
clusters (zones) for a given system. The congestion zone/cluster
The optimization problem is formulated as: [See equations (32)
of type 1 has been defined as zone having large and nonuniform
and (33) at bottom of page]
TCDFs, and the congestion zones of type 2 and higher have
been defined as those having small or similar TCDFs. There- (34)
fore, the transactions in the congestion zone1 have critical
(35)
and unequal impact on the line flow. The congestion zones
of type 2, 3 and higher are farther from the congested line (36)
of interest [11]. Therefore, any transaction outside the most (37)

Minimize (32)

subject to

(33)
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING 557

and The number of participants in the transmission congestion


market will be generally much smaller than the number
of active participants in the electricity market. The congestion
cost can be determined for the hybrid type of market structure
in which bilateral and multilateral transactions are also taking
(38) place along with pool demands. Pool model formulation can
be modified to incorporate the additional equality constraints
representing the bilateral and multilateral contracts.

E. Modeling Bilateral/Multilateral Contracts


The conceptual model of bilateral dispatch is that sellers and
(39) buyers enter into transactions where the quantities traded and
the associated prices are at the discretion of these parties and
not a matter of SO. These transactions are then brought to the
where is the number of generators participating in con-
SO with a request that transmission facilities for the relevant
gestion management, is the MVA flow limit of a line
amount of power transferred to be provided. If there is no static
connected between bus- and bus- , and are the total
and dynamic security violation, the SO simply dispatches all
real and reactive power loss, which have been expressed using
of the requested transactions and charges for the transmission
exact loss formula [14]. is the set of capacitors and are
service.
the number of buses in the system. and are the orig-
In a practical system, not all of the sellers have bilateral con-
inal real and reactive power flow in line- (between bus- and
tract with buyers and vice-versa. Mathematically, each bilateral
bus- ) caused by all of the transactions requesting the transmis-
transaction between a seller at bus- and power purchaser at
sion service. is the real power adjustment of generator at
bus- satisfies the following power balance relationship:
bus- . is the change in the voltage due to
change in the reactive power injection. is the incremental or (42)
decremental price bids submitted by generator- . These are the
prices at which generators are willing to adjust their real power The bilateral concept can be generalized to be multilateral
outputs. The second term in the objective function is the oppor- case where the seller (for example, a generation company) may
tunity cost of the generator defined as [15] inject power at several nodes and the buyers also draw load at
several nodes. Unlike pool dispatch, there will be a transaction
power balance in that the aggregate injection equals the aggre-
(40) gate draw off for each transaction. The contracted demands of
where is the cost of active power generation and is modeled load buses to be provided by generator- have to be shared in
by a quadratic function as a proportion decided optimally by SO. Mathematically, a mul-
tilateral contract- involving more than one supplier and/or one
consumer can be expressed as

where , , and are predetermined costs coefficients of (43)


generator and is the nominal apparent power of gen-
erator and is the profit rate of active power generation taken where and stand for the power injections into the
between 5 and 10% [15]. seller bus- and the power taken out at the buyer bus- . is
The third term in the objective function is the equivalent cost the total number of contracts.
for return on the capital investment of the capacitors, which is
expressed as their depreciation rates (the life span of capacitors III. SYSTEM STUDIES
is assumed as 15 years)
The proposed concept of congestion zone-based congestion
management system utilizing the real and reactive TCDFs has
been illustrated on a 39-bus New England system [16] and
(41) 75-bus Indian system [17]. The 39-bus system is a simplified
representation of the 345-kV transmission system in the New
where is the average usage rate of capacitors taken as England region having ten generators and 29 load buses.
(in per unit at 100-MVA base). Equation (39) is a The 75-bus Indian system represents a reduced network of
linear cost function with a slope of Uttar Pradesh State Electricity Board’s network comprising of
400-kV and 220-kV buses with 15 generators, 24 transformers,
and 97 lines.

The second and third terms in (38) and (39) incorporate the A. Thirty-Nine-Bus System (Single Congestion Case)
change in the losses in the system occurring due to redispatch For this system, the congestion zones based on the real power
of the generators and capacitors. flow sensitivity for a line 34-14, which is considered as con-
558 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 1, FEBRUARY 2004

Fig. 1. Congestion zones based on PTCDF for 39-bus New England system.
Fig. 2. Congestion zones based on QTCDF for the 39-bus New England
system.
TABLE I
ZONES (BUS NO., PTCDF) FOR 39-BUS NEW ENGLAND SYSTEM
TABLE II
ZONES (BUS NO., QTCDF) FOR THE 39-BUS NEW ENGLAND SYSTEM

gested line, are shown in Fig. 1. The congestion zones are de-
cided on the basis of PTCDFs and accordingly the SO selects
most sensitive congestion zones for managing congestion. The
PTCDFs for the congested line 34-14 corresponding to each bus
are given in Table I for the four different zones.
The zone 1 is the most sensitive zone with larger magnitude
and strongest nonuniform distribution of PTCDFs. The magni-
tudes of PTCDFs in zone 4 are higher than zone 2 and zone 3
but due to uniform distribution of PTCDFs, the zone 4 is consid-
ered as the least sensitive zone. Fig. 2 shows the zones based on
the QTCDFs for the congested line 34-14. The reactive power
flow indexes are given in Table II. The combined zones based on
both real and reactive power flow sensitivity indexes are shown
in Fig. 3. The most sensitive combined zone (zone-1) has been
taken as the union of the most sensitive zones obtained from the
real and reactive power flow sensitivity indexes, separately.
The next sensitive zones (zones 2, 3, and higher) have been Fig. 3. New combined congestion zones for the 39-bus New England system.
formed, in sequence, by taking union of the remaining buses in
the respective zones obtained from the real and reactive power C4: pool model with one bilateral contract between bus
flow sensitivity indexes. Since the sensitivity of both real and re- 8–21 and multilateral contract between 3–35, 36;
active power sources is with respect to the flow in the congested C5: pool model with two bilateral contracts between buses
line, the zones (clusters of buses) formed are almost overlap- 8–21, 10–23 and multilateral contract between buses
ping. 3–35, 36.
Different combinations of market structures comprising pool In the present study, the full capacities of generations at a
model and mix of pool plus bilateral and multilateral contracts bus have been assumed to participate either in pool or in a bi-
taken for study are lateral/multilateral contract. For example, in a market structure
P: pool model without bilateral and multilateral contracts; type-P, it is assumed that the full capacity of all the generators
C1: pool model with one bilateral contract between buses bid only in the pool, whereas in type C1, the full capacity of
3–35; all the generators bid in the pool except the generator at bus 3
C2: pool model with two bilateral contracts between buses whose full capacity is assumed to participate only in the bilateral
3–35 and 8–21; contract. However, the problem formulation is quite general and
C3: pool model with one multilateral contract between can consider the participation of any of the generators simulta-
buses 3–35, 36; neously in pool as well as in bilateral/multilateral contracts.
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING 559

TABLE III
CONGESTION COSTS (DOLLARS PER HOUR) FOR 39-BUS NEW ENGLAND
SYSTEM FOR DIFFERENT CASES

Fig. 6. Change in P-generation for the 39-bus system (case 2).

Fig. 4. Congestion costs for the 39-bus New England system.

Fig. 7. Change in P-generation for the 39-bus system (case 3).

Fig. 5. Change in P-generation for the 39-bus system (case 1).

The congestion cost has been determined for a pool-based Fig. 8. Change in P-generation for the 39-bus system (case 4).
market model and a mix of pool, bilateral, and multilateral con-
tracts as given above considering the reactive support provided comparison. It is observed that the cost with proposed method is
by the generators and the optimally placed capacitors apart from much smaller compared with the method proposed in [11]. It can
real power scheduling of generation in each case. The different also be seen that capacitors reactive support is more effective
cases taken for the study are: in reducing congestion cost as compared to generator reactive
Case 1) without reactive power support from generators and support. This may be due to the fact that the optimal placement
capacitor; of capacitors meets the reactive power requirement of the zone
Case 2) with generators reactive support; directly without involving the flow of reactive power through
Case 3) with capacitor reactive support; lines. The congestion cost is found to be minimum with both
Case 4) with generators and capacitor reactive support. generator and capacitors giving reactive support in the system.
It has been assumed that the SO selects generators G3, G8, Figs. 5—8 show the optimal change in real power (P) output
and G10 from the most sensitive zones to participate in the con- of generators G3, G8, and G10 in per unit for different market
gestion management based on the qualifying bids. The capacitor models considering four different cases. Comparing Figs. 5—8,
has been located optimally on bus 14 based on its most nega- it is found that the generators are subjected to a lower magnitude
tive reactive power flow sensitivity index value as highlighted of rescheduling in the presence of reactive support provided by
in Table II. the generators and capacitors.
The congestion costs for all of the cases are presented in The reactive power support from capacitor at bus-14 (C14)
Table III and Fig. 4. The congestion cost for case 1 has also and the change in reactive power output of generators for all
been determined with dc method [11] and shown in Table III for transactions (in per unit) are given in Table IV. The reactive
560 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 1, FEBRUARY 2004

TABLE IV
REACTIVE POWER RESCHEDULING (IN PER UNIT) FOR CASES 2 AND 3

TABLE V
REACTIVE POWER RESCHEDULING (IN PER UNIT) FOR CASE 4

Fig. 10. Congestion cost for 75-bus Indian system.

Fig. 11. Change in P-generation for the 75-bus Indian system (case 1).

Fig. 9. Combined congestion zones for the 75-bus system.

power support from capacitor and change in reactive power out-


puts of generators for the case 4 are given in Table V.
From Tables IV and V, it is observed that capacitors are re-
quired to generate less MVAR when generators are also pro-
viding additional reactive support in the system. The generators
are subjected to lower reschedule of reactive power generation Fig. 12. Change in P-generation for the 75-bus Indian system (case 2).
when the capacitor is supporting the reactive power requirement
in the system. C3: pool model with one multilateral contract between
buses 12–27, 73;
B. Seventy-Five-Bus Indian System C4: pool model with one bilateral contract between bus
For this system, the combined congestion zones based on the 13–55 and multilateral contract between 12–27, 73;
real and reactive power flow sensitivity indexes for a line of in- C5: pool model with two bilateral contracts between buses
terest 26–41 are shown in Fig. 9. The system has been divided 3–24, 13–55, and multilateral contract between buses
into three zones with zone 1 as the most sensitive zone. It has 12–27, 73.
been assumed that SO selects generators G3, G12, and G13 from The changes in real power output of generators have been
the most sensitive zone 1 to participate in the congestion man- determined for the two cases:
agement based on their qualifying bids in an open market. Case 1) without reactive support from generators;
Different combinations taken for the study are: Case 2) with reactive support from generators.
P: pool model without bilateral and multilateral contracts; The congestion costs for the general market model structure
C1: pool model with one bilateral contract between buses having pool, bilateral, and multilateral transactions are shown in
3–27; Fig. 10 along with the congestion costs for case 1 with dc model
C2: pool model with three bilateral contracts between [11]. Figs. 11 and 12 show the change in real power output of
buses 3–27, 12–24, and 13–55; generators for the above two cases.
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING 561

TABLE VI
CHANGE IN REACTIVE GENERATION (IN PER UNIT) (CASE 2)

Fig. 14. Congestion cost for multicongestion case for the 39-bus system.

Fig. 13. Multicongestion case of 39-bus system.

From Fig. 10, it is found that the congestion cost is less for
case 2 compared with case 1 and the congestion costs are quite
less as compared to those obtained from dc model [11]. From Fig. 15. Change in P-generation for multicongestion case for the 39-bus
system.
Figs. 11 and 12, it is observed that the generators are subjected
to lower real power rescheduling in the presence of reactive sup-
TABLE VII
port from the generators. The change in reactive power output CPU TIMES IN SECONDS
of generators for all of the transactions for case 2 is given in
Table VI.

C. Multicongestion Case
In a power system network, there may be more than one
line getting congested simultaneously. The studies for the mul-
whereas both real and reactive power TCDFs in the proposed
ticongestion cases were carried out for both 39-bus and 75-bus
method) and the OPF utilized for congestion management are
system. However, the results for only 39-bus system are being
presented in Table VII.
presented. For the simulation of a multicongestion case (case
It is observed that the CPU time required by the proposed
mc), it is assumed that two lines 34–14 and 36–21 are congested
method is quite close to that with the dc-based method [11].
simultaneously. The combined zones based on real and reactive
TCDFs are shown in Fig. 13. The zone 1 and the zone 2 are
the most sensitive zones. For managing the congestion, genera- IV. CONCLUSION
tors 3, 8, 10 were selected from zone 1 and generators 4 and 6 In this paper, a new zonal-based congestion management ap-
were selected from zone 2, based on their qualifying bids in the proach has been presented. The zones have been formed based
market. The congestion costs for the multicongestion case along on the combined effect of real and reactive line power flow sen-
with those for case 1 are shown in Fig. 14 for the transactions P, sitivity indexes. An optimal power flow model minimizing the
C1 to C5. It is observed that the congestion cost is significantly congestion cost for redispatch of generators and capacitors con-
high for the multicongestion case. The change in optimal real sidering a general market structure with pool, bilateral, and mul-
power generation of the generators participating in the conges- tilateral contracts has been studied. The test results on a 39-bus
tion management is shown in Fig. 15. New England system and 75-bus Indian system reveal the fol-
lowing.
D. Computational Time • The congestion costs in all of the cases based on the pro-
In order to compare the computational time taken by the pro- posed method are found to be quite less compared with
posed ac distribution factors-based method with the dc distri- those obtained from a dc model [11].
bution factors based method, CPU times were computed on a • The congestion costs for cases employing reactive power
Pentium IV, 1.9-GHz, 512-RAM computer. The CPU time for support from generators and capacitors are considerably
calculation of TCDFs (only real power TCDF in the dc method less than the cases without any reactive support.
562 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 1, FEBRUARY 2004

• The reactive power support utilized from an optimally lo- [16] K. R. Padiyar, Power System Dynamics: Stability and Control. New
cated capacitor in the system is more effective in reducing York: Wiley, 1996, p. 601.
[17] S. N. Singh and S. C. Srivastava, “Corrective action planning to achieve
congestion cost as compared to additional reactive power optimal power flow solution,” Proc. Inst. Elect. Eng. C, vol. 142, pp.
support taken from the generators. 576–582, Nov. 1995.
• The amount of rescheduling of real power transactions is
reduced in the presence of reactive support considered in
the system for congestion management.
The proposed approach is computationally efficient and
simple as it utilizes the sensitivity factors, which can be easily Ashwani Kumar received the B.Tech degree in electrical engineering from
G.B. Pant University, Pant Nagar, India, in 1988, and the M.Tech. degree in
updated. power systems from Punjab University, Chandigarh, India, in 1994. He is cur-
rently pursuing the Ph.D degree under Quality Improvement Program (QIP)
REFERENCES in the electrical engineering department at the Indian Institute of Technology,
Kanpur, India.
[1] Federal Energy Regulatory Commission (FERC), Regional Transmis- Currently, he is a Lecturer in the Department of Electrical Engineering at Na-
sion Organizations, Washington, DC, Dec. 20, 1999. tional Institute of Technology (NIT)-Kurukshetra, Haryana, India. His research
[2] W. W. Hogan, “Contract networks for electric power transmission,” J. interests include power system deregulation optimization and power system dy-
Regul. Econ., vol. 4, pp. 211–242, Sept. 1992. namics.
[3] F. C. Schweppe, M. C. Caramanis, R. D. Tabors, and R. E. Bohn, Spot
Pricing of Electricity. Norwell, MA: Kluwer, 1988.
[4] H. Chao and S. Peck, “A market mechanism for electric power transmis-
sion,” J. Regu. Econ., vol. 10, pp. 25–29, July 1996.
[5] F. D. Galiana and M. Ilic, “A mathematical framework for the analysis
and management of power transactions under open access,” IEEE Trans.
Power Syst., vol. 13, pp. 681–687, May 1998. S. C. Srivastava (SM’91) received the Ph.D. degree in electrical engineering
from the Indian Institute of Technology, New Delhi, India.
[6] R. S. Fang and A. K. David, “Transmission congestion management in
an electricity market,” IEEE Trans. Power Syst., vol. 4, pp. 877–883, Currently, he is a Professor in the Department of Electrical Engineering at the
Aug. 1999. Indian Institute of Technology, Kanpur, India. His research interest includes en-
ergy management system, power system optimization, security analysis, voltage
[7] H. Glavisch and F. Alvarado, “Management of multiple congested con-
ditions in unbundled operation of power systems,” IEEE Trans. Power stability, and power system deregulation.
Dr. Srivastava is a Fellow of the Indian National Academy of Engineering
Syst., vol. 13, pp. 1013–1019, Aug. 1998.
[8] H. Singh, S. Hao, and A. Papalexopoulos, “Transmission congestion (INAE), Institution of Engineers (India), and Institution of Electronics and
Telecommunication Engineers (IETE) [India].
management in competitive electricity markets,” IEEE Trans. Power
Syst., vol. 13, pp. 672–680, May 1998.
[9] S. C. Srivastava and P.Perveen Kumar, “Optimal power dispatch in
deregulated market considering congestion management,” in Proc.
Int. Conf. Electric Utility Deregulation and Restructuring and Power
Technologies, vol. 4–7. London, U.K., Apr. 2000, pp. 53–59.
[10] S. N. Singh and A. K. David, “Optimal location of FACTS devices for S. N. Singh (SM’02) received the Ph.D. degree in electrical engineering from
congestion management,” Int. J. Elect. Power Syst. Res., vol. 58, pp. the Indian Institute of Technology Kanpur, India, in 1995.
71–79, 2001. Currently, he is an Associate Professor in the Department of Electrical En-
[11] C.-N.Chien-Ning Yu and M. Ilic, “Congestion clusters-based markets gineering at the Indian Institute of Technology Kanpur. He was with the De-
for transmission management,” in Proc. 1999 IEEE Power Eng. Soc. partment of Electrical Engineering at the Hong Kong Polytechnic University,
Winter Meeting , New York, Jan. 1999, pp. 1–11. Hong Kong, China, and was Assistant Professor with the Energy Program at
[12] N. G. Hingorani and L. Gyugi, Understanding FACTS: Concepts and Asian Institute of Technology (AIT) Bangkok, Bangkok, Thailand. His research
Technology of Flexible AC Transmission Systems. Piscataway, NJ: interests include power system restructuring, flexible ac transmission systems
IEEE Press, 2000. (FACTS), power system optimization and control, security analysis, and power
[13] A User’s Guide, GAMS Development Corp., 1999. system planning.
[14] A. J. Wood and B. F. Wollenberg, Power Generation, Operation and Dr. Singh is a Fellow of the Institution of Engineers (India). He has received
Control. New York: Wiley, 1996. several awards including Young Engineer Award 2000 of Indian National
[15] Y. Dai and Y. X. Ni et al., “A study of reactive power marginal price in Academy of Engineering, Khosala Research Award, and Young Engineer
electricity market,” Elect. Power Syst. Res., vol. 57, pp. 41–48, 2001. Award of CBIP New Delhi (India).

You might also like