CALCULATION FOR THE COMPONETS OF THE SEWERAGE SYSTEM

Project Title : NICHIA (MALAYSIA) SDN. BHD. Sheet No : 1/1

Date : 12TH MAY 1997


Job No : SM/NM/SW/001
Designed By : H. P. LOW

Manhole Unit Density Population Cummu Cummu Design Cummu Diameter Gradients Velocity Capacity Length Fall G.L. I.L. Depth Manhole
to (Persons/ on line -lative -lative Flow at -lative (mm) (m/s) (l/s) (m) (m) (m) Type
Manhole Unit Population Population DWF Design
(Person) Equivalant (m³/min) Flow
P.E (0.3) (m³/min)
MH-II-7 29.1 27.60 1.5 HEAVY

2 3 6 6 1.8 0 0 225 1 : 150 1.2 50 24 0.16

MH-II-8 29.1 27.44 1.66 HEAVY

- - - 6 1.8 0 0 225 1 : 150 1.2 50 15 0.10

MH-II-9 29.1 27.22 1.88 HEAVY

17 3 51 57 17.1 0 0.01 225 1 : 150 1.2 50 22 0.15

MH-II-10 29.1 27.03 2.07 HEAVY

TO 4 3 12 69 20.7 0 0.01 225 1 : 150 1.2 50 28 0.19

MH-II-6 29.57 26.88 2.69 HEAVY

MH-II-1 29.1 27.60 1.50 HEAVY

6 3 18 18 5.4 0 0 225 1 : 150 1.2 50 22 0.15

MH-II-2 29.1 27.45 1.65 HEAVY

- - - 18 5.4 0 0 225 1 : 150 1.2 50 11 0.07

MH-II-3 29.1 27.38 1.72 HEAVY

26 3 78 96 28.8 0 0.02 225 1 : 150 1.2 50 8 0.05

MH-II-4 29.57 27.33 2.24 HEAVY

- - - 96 28.8 0 0.02 225 1 : 150 1.2 50 17 0.11

MH-II-5 29.57 27.22 2.35 HEAVY

- - - 96 28.8 0 0.02 225 1 : 150 1.2 50 17 0.11

MH-II-6 29.57 26.88 2.69 HEAVY

TO 23 3 69 165 49.5 0 0.03 225 1 : 150 1.2 50 17 0.11

PUMP SUMP 29.71 26.77 2.94 HEAVY

TO

50 PE AERATION TANK
: 12TH MAY 1997

Remarks

FR. CHANGING

RM.

FR. EXT'G MH 5

FR. M/T 1

FR. M/T 2,3 &

F/T 1,2

FR. MH-II-10