Rencana Desain Pembangunan RUMAH TINGGAL
Nama Pemilik : Teuku Harmany Boerhan Ali
Alamat : Jl. Dr. Rubini No. 4 RT. 05 RW. 01 Kel. Pasirkaliki Kec. Cicendo
Kota Bandung
Lokasi : Jl. Tirta Kencana II Kav. 74 Kec. Cimahi Utara Kel. Cibabat
Kota Cimahi
2
3
RENCANA PERHITUNGAN STRUKTUR DAN KONSTRUKSI
Pendimensian Pelat
5000
Asumsi :
Fc’ : 30 Mpa
3000
Fy’ : 240 Mpa
Ly = 5000
Lx = 3000
0.8 + Fy / 1500
h = Lny x
36 + 9β
0.8 + Fy / 1500
h = 94.117 mm
36 + 9β
Pendimensian Balok
Balok l = 5000 mm
h = 1/16 l
4
Diambil h = 350 mm (asumsi)
Utilitas = 25 kg / m2
Σ DI = 56340 N
Σ DI
A>
40 % x 0.85 x ƒc’
56340
A>
40 % x 0.85 x 30’
Asumsi b = h A = h2
h = √5523.529 = 74.32 mm
b = h > 74.32 mm
Beban kolom :
5
Berat kolom atas ( 0.15 x 0. 15 x 2400 x 3 ) = 162 kg / m2
DL = 5028 kg / m2
Σ DI = 5028 kg / m2 = 50280 N
Σ DI
A>
40 % x 0.85 x ƒc’
50280
A>
40 % x 0.85 x 30’
Asumsi b = h A = h2
h = √4929.41 = 70.20 mm
b = h > 70.20 mm
Beban kolom :
DL = 5244 kg / m2
Σ DI = 5244 kg / m2 = 52440 N
Σ DI
A>
40 % x 0.85 x ƒc’
52440
A>
40 % x 0.85 x 30’
6
A> 5141.176 mm2
Asumsi b = h A = h2
h = √5141.176 = 71.70 mm
b = h > 71.70 mm
DL = 242.4 kg / m2
qu = 1.2 DL + 1.6 LL
Lx = 3000 = 3 m ; Ly = 5000 = 5 m
Dimana nilai x :
Mlx = - Mtx 35
7
Mly = - Mty 35
= 167.2272 Kg.m
= 167.2272 Kg.m
5. Penulangan Pelat
Arah x :
Fy = 240 Mpa
Mn 1672272
As = = = 120.968 mm2
Φ x ƒy x jd 0.8 x 240 x 0.9 x 80
Pakai Φ 8 :
0.5
S= X 100 = 4.333 cm
1.20968
Ambil S = 40 cm
ρmin = 0.002 Amin = ρmin x b x h = 0.002 x 100 x 9 = 1.8 cm2 = 180 mm2
0.5
S= X 100 = 27.7777 cm
1.8
Arah y :
fy = 240 Mpa
8
Tulangan lapis (jd) II = d2 = 80 - 8 = 72 mm
Mn 1672272
As = = = 134.41 mm2
Φ x ƒy x jd 0.8 x 240 x 0.9 x 72
Pakai Φ 8 :
0.5
S= X 100 = 37.199 cm
1.3441
Ambil S = 35 cm
PENULANGAN PORTAL
Penulangan Balok
Diketahui :
Tumpuan
Mu 8144000
As = = = 149.67 mm2
Φ x γ x d x ƒy 0.8 x 0.9 x 315 x 240
Kontrol :
Ratio penulangan :
As 226.1946
ρ = = = 4.10 x 10-3
bxd 175 x 315
9
0.85 x ƒc’ x β1 600
0.75 ρ = 0.75 x
ƒy 600 + ƒy
0.75 ρ = 0.04821
1.4 1.4
ρmin = = = 0.00583
ƒy 240
As x ƒy 226.1946 x 240
a = = = 12.1650 mm
(0.85 x ƒc’ x b) (0.85 x 30 x 175)
1 1
Z = D- a = 315 - 12.1650 = 308.9175 mm
2 2
Lapangan
Mu 14073000
As = = = 258.542 mm2
Φ x γ x d x ƒy 0.8 x 0.9 x 315 x 240
Kontrol :
Ratio penulangan :
As 339.12
ρ = = = 6.15 x 10-3
bxd 175 x 315
0.75 ρ = 0.04821
1.4 1.4
ρmin = = = 0.00583
ƒy 240
As x ƒy 339.12 x 240
a = = = 18.2383 mm
(0.85 x ƒc’ x b) (0.85 x 30 x 175)
1 1
Z = D- a = 315 - 18.2383 = 305.8808 mm
2 2
Tumpuan
Vu = 2891.4 kg = 28914 N
11
Tulangan sengkang diperlukan
Vu 28914
Vs = - Vc = - 50318.1 = -2128.1
Φ 0.6
3 Av . ƒy 3 * 100 * 240
s max = = = 411.42 mm
b 175
Kontrol :
Lapangan
L = 5m = 5000 mm
Tumpuan
PENULANGAN KOLOM
Fc’ = 30 Mpa
B = 150 mm
H = 150 mm
Fy = 240 Mpa
Pu = 3412.19 kg = 341219 N
Pu 341219
Pn = = = 524952.3 N
Φ 0.65
Mu 8144000
Mn = = = 12529230 N
Φ 0.65
ƒy 240
m = = = 16
0.85 * ƒc’ 0.85 * 30
0.1307
ρtperlu = = 0.00816
16
Ast = ρtperlu . b . h
= 183.6 mm2
Gaya Geser
Data ETABS :
Vu = 40.24 kg = 402.4 N
0.3 * Pu √ƒc’
= (1+ Ag ) ( 6 ) bw . d
= ( 1 + 0.3 (150)
* 341219
2 ) ( √30
6 ) 150 . 130
= 98767.5 N
Selimut beton = 1 / 10 h = 20 mm
d = 150 – 20 = 130 mm
Vu = 40.24 kg = 402.4 N
0.3 * Pu √ƒc’
= (1+ Ag ) ( 6 ) bw . d
14
= ( 1 + 0.3 (150)
* 341219
2 ) ( √30
6 ) 150 . 130
= 98767.5 N
Selimut beton = 1 / 10 h = 20 mm
d = 150 – 20 = 130 mm
Vu = 40.24 kg = 402.4 N
0.3 * Pu √ƒc’
= (1+ Ag ) ( 6 ) bw . d
= ( 1 + 0.3 (150)
* 341219
2 ) ( √30
6 ) 150 . 130
= 98767.5 N
Selimut beton = 1 / 10 h = 20 mm
d = 150 – 20 = 130 mm
15
Maka dipakai tulangan Φ 10 - 65
PENULANGAN PONDASI
Penulangan Pondasi
Diketahui :
P = 218 N
H = 330 N
M = 99 Nmm
fc’ = 30 Mpa
fy = 240 Mpa
σt = 0.1 Mpa
γ tanah = 18 KN / m3 = 1800 N / m3
γ beton = 24 KN / m3 = 2400 N / m3
1. Pembebanan Pondasi :
P tot 55740
A perlu = = = 557400 mm2
σt 0.1
55740
σr = = 0.0387 Mpa < σ r = 0.1 Mpa OK
1200 x 1200
2. Syarat Geser
16
M+H.h 99 + 330 * 1750
e = = = 10.362 mm
R 55740
R 6.M
q max = +
B.L B . L2
55740 6 . 99
q max = + = 0.039 N / mm2
12002 12003
R 6.M
q min = -
B.L B . L2
55740 6 . 99
q max = - = 0.0387 N / mm2
12002 12003
d = 150 – 75 = 75 mm
C1 150
Bc = = =1
C2 150
1 2
Vc =
6 ( 1+
Bc ) √ƒc’ . bo . d = 92340 N
1
Vc = √ƒc’ . bo . d = 61560 N
3
Maka Vc = 92340 N
17
Φ Vc = 0.75 Vc = 69255 N
P = 218 N
5. Penulangan pondasi
q x (s + s) 2
Mu = +bx xs
2 3
Mu
As = = 26.667 mm2
Φ . γ d . ƒy
18
PERENCANAAN TANGGA
+ 4.70
+ 3.20 Lantai 2
+ 1.60
+ 0.00 Lantai 1
1.00 2.00
Syarat tangga :
19
- Sudut Kemiringan demi kenyamanan adalah 25° hingga 35°
Dengan begitu total jumlah tanjakan hingga lantai berikutnya adalah 18 buah (seperti pada
10 11 12 13 14 15 16 17 18 Lantai atas
8 7 6 5 4 3 2 1 Lantai
bawah
= 17.77 cm
= 16.66 cm
Syarat :
= 20 + 25 < 45 – 65 cm
= 45 < 45 – 65 cm OK
DL = 510.529 kg/ m2
20
2. Beban Super Dead (SDL)
B. S Sandaran = 20 kg/ m2
LL = 150 kg/ m2
Pembebanan Bordes
DL = 360 kg/ m2
B. S Sandaran = 20 kg/ m2
LL = 150 kg/ m2
Penulangan Tangga :
Penulangan Arah X :
Mu = 2577170 Nmm
Mu 2577170
A perlu = = = 114.775 mm2
ΣΦ. Jd . ƒy 0.8 (0.9 * 130) 240
Dengan jarak :
Penulangan Arah Y :
Mu = 6274430 Nmm
Mu 6274430
A perlu = = = 279.310 mm2
ΣΦ. Jd . ƒy 0.8 (0.9 * 130) 240
22
Diameter tulangan Φ 10 = 79 mm2
Dengan jarak :
Penulangan Bordes
Penulangan Arah X :
Mu = 5229040 Nmm
Mu 5229040
A perlu = = = 232.774 mm2
ΣΦ. Jd . ƒy 0.8 (0.9 * 130) 240
Dengan jarak :
Mu = 760040 Nmm
Mu 760040
A perlu = = = 340.101 mm2
ΣΦ. Jd . ƒy 0.8 (0.9 * 130) 240
23
Diameter tulangan Φ 10 = 79 mm2
Dengan jarak :
24
Gbr. Rencana Struktur dan Konstruksi Pelat Lantai dan Kolom
25