You are on page 1of 314

Hybrid

Propulsion

Technology

Program

Final Report

i:!Ti! ......
::d'-" :i::: :-:... ...... :':'.'x.;:.:.:.-,;,:.:.

7:,.I

,.^>...

Presente,

i.

Atlantic

Research

Corporation

Virginia Propulsion Division 31 January,,; 990


N'O - 2 _i_._, 7 'J

un c I :%

Table

of Contents

Section

Title INTRODUCTION .................................................. TECHNICAL 2.1 2.2 DISCUSSION ..........................................

Page

1.0 2.0

2.3 2.4

Oxidizer Evaluation ................................ _..... Fuels Evaluation ......................................... 2.2.1 Gas Generator Fuels ............................... 2.2.2 Classical Hybrid Fuels ............................ Propulsion Conceptual Studies ............................ Point Design ............................................. 2.4.1 Gas Generator ..................................... 2.4.2 Thrust Chamber .................................... 2.4.2.1 Regeneratively Cooled Design ............ 2.4.2.2 Ablative Design ......................... Injector Design ................................... Combustion Stability .............................. Oxidizer Delivery System .......................... 2.4.5.1 Pressure-Fed System ..................... 2.4.5.2 Turbopump Feed System ................... LOX Tank ........................................ 2.4.6.1 Pressure-Fed Option ..................... 2.4.6.2 Turbopump Option ........................ Thrust Vector Control ............................. Ancillary Components .............................. 2.4.8.1 Launch Pad Support Truss ................ 2.4.8.2 Aft Skirt and Thrust Transfer Ring ...... 2.4.8.3 Recovery System ......................... Performance Predictions ........................... Size Point Design ................................ Gas Generator ..................................... Thrust Chamber .................................... Thrust Vector Control ............................. Oxidizer Tank .....................................

2.4.3 2.4.4 2.4.5

2.4.6

2.4.7 2.4.8

2.4.9 2.5 Quarter 2.5.1 2.5.2 2.5.3 2.5.4

2.6

2.5.5 LOX Delivery System ............................... Life Cycle Cost Trade Studies ............................ 2.6.1 Introduction and Summary .......................... 2.6.2 Conceptual Studies ................................ 2.6.2.1 Pump-Fed Versus Pressure-Fed ............ 2.6.2.2 Classical-Versus-Gas Generator Hybrid... 2.6.2.3 Reusable-Versus-Expendable Hybrid Boosters ......................... 2.6.3 Reference Design Trade Studies .................... 2.6.3.1 Large Booster, Pump-Fed Trades .......... 2.6.3.2 Large Booster, Pressure-Fed ............. 2.6.3.3 Quarter-Size Booster .................... 2.6.4 Additional Booster Design Studies ................. 2.6.4.1 Thrust Vector Control ................... 2.6.4.2 Propellant Reserve ......................

2 5 6 6 8 10 21 22 32 34 37 39 41 42 42 43 50 52 53 55 63 63 63 64 67 73 73 78 78 78 78 79 79 83 86 86 87 88 89 91 96 96 96 100

ii PRECEDING PAGE BLANK NOT FILMED

Table

of Contents

(Cont'd)

Section

Title

Page 102 102 102 102 106 106 107 107 110 120 123 123 124 124 124 125 125 126 126 130 130 132 138 139 139 142 142 145 149 151 153 156 156 156 157 157 157 158 160 161 162 165

2.7

2.8

2.9

Design Margins .......................... Volumetric Loading of Gas Generator Propellant .................... 2.6.4.5 Oxidizer Pump-Out Capability ............ 2.6.5 Hybrid Model Optimizer Results .................... Rellabl lity Analyses ..................................... 2.7.1 Introduction ...................................... 2.7.2 Reliability Block Diagram ......................... 2.7.3 Reliability Estimation Procedures ................. 2.7.4 Failure Modes and Effects Analysis ................ Technol ogy Identification ................................ 2.8.1 Gas Generator Fuel Development .................... 2.8.2 Injector Design ................................... 2.8.3 Combustion Interaction ............................ 2.8.4 Combustor/Nozzle (Regenerative or Ablative) ....... 2.8.5 Turbopump Development ............................. 2.8.6 Tridyne Expulsion System Development .............. 2.8.7 Thrust Vector Control ............................. Acquisition Plan .........0.........0...0........0....... 2.9.1 Introduction ...................................... 2.9.2 Program Tasks ..................................... Point Design Updates (Task I) ........... Fuel Development and Characterization (Task 2) ............... 2.9.2.3 Oxidizer Studies (Task 3) ............... 2.9.2.4 Material Screening (Task 4) ............. 2.9.2 .5 Combustor/Nozzle Studies (Task 5) ....... 2.9.2 .6 Thrust Vector Control Design (Task 6)... 2.9.2 .7 Injector Studies (Task 7) ............... 2.9.2 .8 Combustion Studies (Task 8) ............. 2.9.2 .9 Subscale Demonstration (Task 9) ......... 2.9.2 .10 Oxidizer Delivery System Development (Task 10) ............................... 2.9.2 .11 Component Integration (Task 11) ......... 2.9.2 .12 Risk Assessment (Task 12) ............... 2.9.2 .13 Phase 3 Planning (Task 13) .............. 2.9.2 .14 Propulsion System Integration (Task 14) ............................... 2.9.2 .15 Facility Requirements (Task 15) ......... 2.10 Mi Ilion-Pound Thrust Demonstration Plan ........... 2. 10.1 Introduction ............................ 2. 10.2 Motor Design (Task 1) ................... 2. 10.3 Component Procurement and Verification (Task 2) ................... 2.10.4 Motor Assembly and Shipment (Task 3) .... 2.10.5 Testing (Task 4) ........................ 2.10.6 Data Analysis and Documentation (Task 5) ................................

2.6.4.3 2.6.4.4

iii

List

of Tables

Table 1 2 3 4 5 6 7 B 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

Title

Page 3 3 7 9 20 24 24 25 47 47 51 52 56 58 59 61 62 65 67 75 82 82 84 89 106 111 113 121 130 133 134 141 144 148 150 152 155 164 166

Concept Summary Overview ...................................... Design Selection Summary ...................................... Gas Generator Hybrid Fuels Evaluated .......................... Classical Hybrid Fuels Evaluated .............................. Concept Summary ............................................... Full-Size Vehicle Weight Breakdown (Pressure Fed) ............. Full-Size Vehicle Weight Breakdown (Turbopump) ................ Gas Generator Fuel ............................................ System Pressure Schedule ...................................... LOX Turbopump Operating Requirements .......................... Maximum Flow and Pump-Out Performance ......................... LOX Turbopump Transient Performance ........................... Hybrid Booster TVC Design Requirements ........................ FITVC Injectant Trade Study Summary ........................... Conceptual Design Implementation Decision Summary ............. FITVC System Sizing/Performance Summary ....................... FITVC Weight Estimate Summary ................................. Recovery Options .............................................. Recovery Systems Weights ...................................... Quarter-Size Vehicle Weight Breakdown (Pressure-Fed) .......... Hybrid Booster LCC Breakdown Summary .......................... Vehicle LCC Breakdown Summary ................................. DDT&E Breakdown Summary ....................................... Configuration and Material Parametrics ........................ Hybrid Booster LCC Trade Studies Optimized Booster Design ..... Hybrid Component Predicted Failure Rates ...................... Preliminary Failure Modes and Effects Analysis ................ Key Technology Issues ......................................... Phase II Task Summary ......................................... Gas Generator Fuels ........................................... Compositions to be Screened ................................... MBA Material Characterization Preliminary Test Matrix ......... Injector Variables ............................................ 7.6- and 22.g-Centimeter Diameter Test Matrix ................. Subscale Demonstration Test Matrix ............................ Subscale Demonstration Test Summary, Task 9 ................... Component Integration Test Summary, Task 11 ................... Large Subscale Motor Test Series .............................. Phase 3 Motor Instrumentation .................................

iv

List of Fiqures

Figure

Title

Page

6 7 8 g 10 11a 11b 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

Gas Generator Hybrid with Hydrogen Peroxide (Pressure Fed Version) ........................................ Gas Generator Hybrid with Hydrogen Peroxide (Turbopump Version) ........................................... Gas Generator Hybrid with LOX (Pressure Fed Version) .......... Gas Generator Hybrid with LOX (Turbopump Version) ............. Classical Hybrid Hydrocarbon/Hydrogen Peroxide (Pressure Fed Version) ........................................ Classical Hybrid Hydrocarbon/LOX (Pressure Fed Version) ....... Classical Hybrid Hydrocarbon/LOX (Turbopump Fed) .............. Hybrid Configurations Life Cycle Costs ........................ Full Size Booster Designs ..................................... Vacuum I_. Versus.................................... and Mixture Rati?: Expansion Rati?: Chamber v_essure Full Size Grain Design ........................................ Results of Grain Structural Analysis .......................... Igniter Pressure Traces for Full-Size Booster ................. Igniter Grain Design (Full-Size Booster) ...................... Igniter Pressure Traces (Full-Size Booster) ................... Thrust Chamber Design ......................................... Throat Wall Temperature as a Function of Passage Height ....... Coolant Passage Pressure Drop as a Function of Passage Height ........................................................ Relationship Between Coola?t Temperature a?d Chamber Pressure ................................................. Single Pass Regeneratively Cooled Thrust Chamber .............. Ablative Thrust Chamber Design ................................ Injector Manifold Design ...................................... Catalytic Warm Gas Pressurization System Schematic for GG/LOX .... Preliminary'Oxidizer'Pump_Fed'System'SchematicZ_Z_ ..... IZ_Z_ Reserve Pitot ................................................. LOX Turbopump ................................................. Selected Turbopump Operating Points ........................... Aluminum-Lithium LOX Tank Design .............................. Comparison of Injectants with Three Maximum Nozzle Deflections ................................................... Hybrid Engine FITVC Performance (Liquid Oxygen Injectant) ..... Hybrid Booster Program FITVC Schematic ........................ Recovery Scenario ............................................. Predicted Thrust Trace Full-Size Booster ...................... The Predicted Chamber Pressure for the Full-Size Booster Grain Design .................................................. The Predicted Mixture Ratio for the Full-Size Booster Grain Design .................................................. The Predicted Vacuum Specific Impulse for the Full-Size Booster Grain Design ................................

13 14 15 16 17 18 19 2O 23 26 28 28 29 3O 3O 33 33 35 35 36 36 40 44 45 48 48 51 54 57 57 62 66 66 68 68 6g

List of Figures

(Cont'd)

Figure 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 7O 71 72 73

Title Turbopump Start-up Characteristics ............................ Predicted Start-up Transient Full-Size Booster ................ Predicted Start-up Pressure Transient Full-Size Booster ....... Gas Generator Pressure ........................................ Burning Rate Versus Pressure .................................. Emergency Shutdown Thrust ..................................... Emergency Shutdown Pressure ................................... Quarter Size Booster Designs .................................. Quarter Size Booster Thrust Trace ............................. Quarter Size Booster Mixture Ratio ............................ Quarter Size Grain Design ..................................... Operations LCC Breakdown ...................................... Hybrid Concept LCC Comparison ................................. Hybrid Concept Comparison, LCC/payload ........................ Life Cycle Cost vs Number of Missions ......................... Mixture Ratio vs LCC for the Pump Fed Large Booster ........... Mixture Ratio vs LCC/payload for the Pump Fed Large Booster... LCC vs Expansion Ratio for the Pump Fed Large Booster ......... LCC/payload vs Expansion Ratio for the Pump Fed Large Booster ................................................. LCC vs Chamber Pressure for the Pump Fed Large Booster ........ LCC/payload vs Chamber Pressure for the Pump Fed Large Booster ................................................. LCC vs Body Diameter for the Pump Fed Large Booster ........... LCC/payload vs Body Diameter for the Pump Fed Large Booster ................................................. Mixture Ratio vs LCC for the Pressure Fed Large Booster ....... Mixture Ratio vs LCC/payload for the Pressure Fed Large Booster ................................................. LCC vs Expansion Ratio for the Pressure Fed Large Booster ..... LCC/payload vs Expansion Ratio for the Pressure Fed Large Booster .... ....................................... LCC vs Chamber Pressure'for'the'Pressure'Fed'Large'Booster.. LCC/payload vs Chamber Pressure for the Pressure Fed Large Booster ................................................. LCC vs Body Diameter for the Pressure Fed Large Booster ....... LCC/payload vs Body Diameter for the Pressure Fed Large Booster ................................................. Life Cycle Cost vs Thrust Deflection for the Large Booster ......... Cost Per Pound'of'Payioad'vs'Thrust'Defiection'for'the Large Booster ................................................. Life Cycle Cost vs Thrust Deflection for the Quarter Scale Booster ................................................. Life Cycle Cost vs Reserve Propellant ......................... Cost Per Pound of Payload vs Reserve Propellant ............... Life Cycle Cost vs Safety Factor .............................. Cost Per Pound of Payload vs Safety Factor ....................

Page 69 71 71 71 72 72 72 74 77 77 76 84 85 85 88 90 9O 92 92 93 93 94 94 95 95 97 97 98 98 99 99 101 I01 IO0 103 103 104 104

vi

List of Figures

(Cont'd)

Figure 74 75 76 77 78 79 80 81 82 83

Title

Page 105 105 108 108 127 129 143 147 149 159

Life Cycle Cost vs Grain Radius ............................... Cost Per Pound of Payload vs Safety Factor .................... Hybrid Booster Reliability Block Diagram ...................... Hybrid Propulsion System ...................................... Program Schedule .............................................. Program Logic Flow ............................................ Full-Scale Nozzle Design Activity Interacts With Material Characterization, Design, Technology Efforts .................. Test Motor Hardware ........................................... 50 in Heavywall Subscale Demonstrator Motor ................... Program Schedule ..............................................

vii

1.0

INTRODUCTION

This Technology identify

report

describes contract

work

accomplished NAS8-37776. application The Hybrid

during

the

Hybrid

Propulsion was to

Program, the

number

The program of hybrid

objective

technology space to

to enable vehicles. the

propulsion Technology 1,

to manned Program that

and unmanned Is designed

launch

Propulsion In

identify

necessary

technology it In a large the tasks

Phase

acquire

technology 3.

in Phase 2, and demonstrate is to cover

subscale

system

in Phase I. in a

The scope of this report Atlantic Research the request system

completed two

In Phase

Corporation for proposal

(ARC) (RFP)

proposed MSFC

design The

concepts first was

response hybrid

to

8-I-8-EP. method across of

propulsion

utilizing

the classical

regression

(classurface.

sical hybrid) The second to

resulting

from the flow of oxidizer a self-sustalnlng exhaust offered that

a fuel grain (gas

system produce

utilized a

gas was

generator mixed with

generator in a

hybrid) separate over

fuel-rich Both

oxidizer

combustor.

systems

cost

and reliability

improvements

the existing The

solid rocket ARC program

boosters was

and proposed

liquid boosters. the selection for each cost and of one propulreliaof

contracted

designed

to address point llfe

of

the hybrid system. Our

concepts The

by developing were

a booster using

design cycle

sion

designs

evaluated of: (1)

bility. candidate concepts; and

program

consisted fuels;

identification evaluation

and of

evaluation booster

oxidizers

and

(2) preliminary point

design cost tech-

(3) preparation analyses;

of a detailed

design of

including hybrid

life cycle specific

reliability needing

(4) identification and

those

nologies

development;

(5) preparation plan. provided by

of a technology

acquisition

plan and large-scale In Group tract addition to

demonstration the expertise

ARC,

the

Preliminary under

Design subcon-

of the Boeing to provide

Aerospace

and Electronics and System to

Company

was placed cost

system

integration

life cycle Division provide vector

analysis;

AiResearch Aerospace design and

Los Angeles Company were

Division placed data,

and the Fluid under

of Allied-Signal turbomachinery control

subcontract injection provided of

performance tively; trades; ARC and

and liquid

thrust the the

designs, system

respecdesign

Liquid the

Propulsion

oxidizer Acurex

delivery Corporation

Aerotherm

Division

(Huntsville

Operations), under subcontract turbopumps and controls.

to ARC, provided additional

information

on

During the program, ARCevaluated eight classical hybrid and gas generator hybrid conceptual designs. ARC selected the gas generator hybrid with liquid oxygen oxidizer (LOX) because: (1) it provided a lower life cycle cost for 150 missions over 10 years of operation ($11.4 to $15.3 billion) than the classical hybrid ($12.9 to $19.2 billion); (2) had the same calculated reliability (R = 0.998); associated advantages (3) offered with an approach to solve and the historical (4) offered scaling uncertainty operational the classical hybrid; with all of the

historically

associated

liquid propulsion.

2.0

TECHNICAL DISCUSSION

To encompass rocket motors (3.0

a range

of possible

vehicle a

system

requirements, motor motor, should which four meet

two hybrid produces in

were

conceptualized: of thrust; thrust.

full-size

13.3 106 N combination,

x 106 Ibf) the

and a single Each motor

of which,

produce

same

the following

requirements: Concepts Concepts Concepts imbalance, Concepts Concepts Solid shall use thrust vector control (TVC). materials. for performance, thrust

shall not use asbestos-containing shall utilize propellant active control

system

utilization,

and all transients. degrading exhaust products.

shall minimize shall maximize grain

environmentally shelf shall life. extinguish

propellant

when

the

fluid

propellant

flow is stopped; Safety

no restart

capability. shall be identical for manned and

and reliability systems.

requirements

unmanned

Recoverable evaluated.

and reusable

concepts

versus

expendable

concepts

shall

be

During tor hybrid

the program, designs

ARC evaluated 1).

eight

classical were were

hybrid

and gas generafrom the compocost the

(Table

The concepts weights our

configured estimated studies,

nents and

listed

in Table As

2, and booster a result of

to calculate we selected

reliability.

conceptual

Table

I.

Concept Case Epoxy Epoxy Epoxy Epoxy Epoxy Epoxy Epoxy Epoxy

Summary

Overview. Oxidizer Feed System Pressure Fed

ID Number i IT IA IAT 2 2T 2A 2AT

Cycle GG GG GG GG Classical Classical Classical Classical

Oxidizer H202 H202 LOX LOX H202 H202 LOX LOX

Motor Carbon Carbon Carbon Carbon Carbon Carbon Carbon Carbon

Oxidizer Carbon

Tank Epoxy

TVC Flexseal Flexseal LITVC LITVC Flexseal Flexseal LITVC LITVC

Recovery Expendable Recoverable Expendable Recoverable Expendable Expendable Expendable Expendable

AI-Li Carbon Epoxy

Pump Fed Pressure Fed

AI-Li Carbon Carbon Carbon Carbon Epoxy Epoxy Epoxy Epoxy

Pump Fed Pressure Pump Pressure Pump Fed

Fed Fed Fed

Table

2.

Design

Selection

Summary. Selection Rationale Lower Life Cycle Cost (LCC) Lower Development

Component Concept

Selection Gas Generator

Also Considered Classical

Risk

Oxidizer

LOX

Hydrogen

Peroxide

Currently Used Lower LCC Lower LCC Offers Pump Out Higher Specific Impulse High Ejection Efficiency

Oxidizer System

Feed

Turbopump

Pressure

Fed

Gas Generator

Fuel

ARCADENE

399C

ARCADENE 246B and Others (see pgs 6-8) D6AC Steel

Gas Generator

Case

Carbon/Epoxy Composite Ablative

Lower LCC Improved Manufacturing

Thrust

Chamber

Regenerative Cooled Flexseal

Improved Reliability Lower LCC Higher Reliability Lower LCC Recommended by ALS Contractors Simplest System Lowest LCC

Thrust Vector Control Oxidizer Tank

LITVC

AI-Li

Carbon/Epoxy

Oxidizer Pressurization System Recovery System

Tridyne

Cold Gas and Others, (see pgs 40-46) Recover Nested High Cost Items

Expendable

Simplest System Lowest LCC

pump-fed offers

gas

generator

hybrid

for

our

baseline

point

design.

This

hybrid

the following Calculated Reduced

advantages: reliability of 0.998. parts; only one cryogen (LOX) compared to

number

of critical

liquid boosters. $11.4 billion life cycle cost for 150 missions over 10 years of

operation. Engine Mission On-pad 13,608 shutdown and throttling even with capability. the loss of one turbopump.

accomplished abort. kilograms

(46 percent)

shuttle

payload

improvement

(over ASRM

boosters). In approach associated the oxidizer addition also to the features shown above, the the gas generator hybrid

offers the

an approach classical

to solve

historical complex

scaling

uncertainty between

with

hybrid;

i.e.,

the

interaction

flow and the changing in the classical ports and reacts are

(regressing) hybrid with flows

fuel grain. down the free stream portion

The oxidizer of the fuel layer while in grain fuel this Thus, are the

the fuel from the the

at the edge grain rate of

of the boundary The heat and

materials oxidizer

ejected

surface. fuel

released

reaction

controls ratio layer

ablation

regression. tion mixing Beddini, firmed rate and a ARC's

the oxidizer/fuel to of the boundary

and total because Discussions of rocket deal of

mass

and energy the

generarate of

tied rate

it controls with motor

heat

feedback. analysis is

Professor port

Robert con-

leading

expert that

in the there

flows,

analysis

a great

uncertainty

associated phenomout down

with the scaling

of such a boundary scale with port dependency

layer process size. I of fuel

since

the combustion

ena do not directly that there

Professor regression

Beddini

also pointed distance

is a strong port.

rate with

the grain

As the flow moves fuel

down the port, combustion

the boundary products

layer thickens, heat

and the ejected

and accumulated

lead to reduced

1.

Personal Communication, Beddini, R. Astronautical Engineering, University 1989.

A., Dept. of Aeronautical and of Illinois, Urbana, IL, April

feedback, yet higher mass flux, resulting in uncertain localized regression rates. In addition, the low regression rate historically associated with classical hybrids [0.003 - 0.01 cm/sec (0.001 - 0.004 in/sec)] require complex
grain designs and energy of sliver metric 2.1 to produce rates. from sufficient surface area to generate designs the required mass release ejected The complex grain increase the probability the volu-

the nozzle resulting

during

grain

burnback

and reduce

packing

efficiency Evaluation

in large booster

designs.

Oxidizer

ARC performed tual life studies, cycle

oxidizer

evaluations, designs

fuel

evaluations,

propulsion

concep-

developed cost

point and

for two sizes analyses.

of booster, The

and performed of these

studies

reliability

results

studies ered

are discussed

in the following

sections.

Two oxidizers liquid were

were

considand the

to be viable

candidates peroxide

for the hybrid (H202). Both

booster, oxidizers

oxygen

(LOX), on

95-percent

hydrogen

evaluated oxidizers out

basis of safety, nitrogen system

cost, and performance were also

impacts. but

Alternative quickly for

such as of gas

tetraoxide safety. hybrid ARC

considered, LOX as

ruled the

because and

selected

the oxidizer

classical

generator

point designs is well

as a result of our evaluation. known for the performance understood it provides with any

LOX as an oxidizer fuel.

Its use and handling

are well

and are currently with a hybrid

practiced. booster use

Most of the core vehicle LOX; therefore, ality

designs

to be incorporated for the hybrid, requirements.

if LOX was used in facility

there

would

be system

common-

and reduction

LOX is relatively for a cryogenic

inexpensive; fluid cannot

however,

the complexity

of handling

and designing

be minimized. Hydrogen pulsion would peroxide has been proposed by ARC for use in other in the last hybrid 20 years proand it conThe

systems.

It has not been to enable

extensively

used

require

training

its use.

Since

H202

is a monopropellant, for thrust expulsion results vector tank.

has applications trol, density booster ture and of at an

to drive

turbopumps, to

as an

injectant the LOX, helium which

energy is

source 24

pressurize higher than

H202

percent

in a smaller mix-

the same mixture is g78K (1,760R)

ratio; lower

the flame than

temperature system,

at the optimum reducing the

ratio

a LOX

thermal as the

protection the

requirements. Hydrogen

The disadvantages peroxide of the

of using purity

H202

are as numerous for use in

advantages.

required

booster is not currently manufactured in the United States and has a higher ingredient cost. Peroxide can also decomposespontaneously due to contamination; the specific impulse (Isp) of a hybrid system using H202 is 9 percent lower than LOX for the classical hybrid, and 6 percent lower for the gas generator hybrid;
to the training 2.2 Fuels

and the operations costs for H202 are greater than LOXdue
and lack of personnel experience.

requirements

Evaluation of fuels were evaluated using thermochemical calculations and

A number trajectory concepts. vacuum fuel Isp and

analysis Hybrid and the

for both the classical fuels evaluation

hybrid

and the gas generator of the

hybrid

included

definition exhaust of

theoretical (C*) of the of

theoretical combination

characteristic as a function vacuum total

velocity ratio,

oxidizer

mixture

quantity

propellant relative 2.2.1

to provide

the required

impulse,

and estimation

of the

payload

capability. Fuels for the gas generator hybrid (Table fuels, 3) are derived by

Gas Generator The fuels

evaluated

from the

propellant program

formulations. of work

Requirements (SOW) and

for these

established

statement

by ARC,

include: rates

(1) total

extin-

guishment

below

2.06 MPa

(300 psia); in/sec)

(2) burning at 6.8B

of 0.76

to 1.27 centiand (3) proin the

meters-per-second duction exhaust. ARC selected terminated percent it has: of less

(0.3 to 0.5 than 1

MPa

(1,000

psia);

percent

hydrogen

chloride

(HCI)

emissions

ARCADENE

399 [34 percent (CTPB), 37

polystyrene, ammonium

25 percent perchlorate

carboxylCAP), 4

polybutadiene (Fe203)]

percent

iron oxide (I) high of

as the initial specific cm/sec

formulation

to be evaluated

because rate high

theoretical 0.51 to This Ducted

impulse; (0.2 to

(2) demonstrated 0.8 in/sec); demonstrated program and

burning (3) a

tailorability ejection in the

2.03

efficiency. Fixed Flow

fuel-rich Rocket

formulation

good performance Contract No.

Development was tested

(DRPTV),

F33615-77-C-2057. (7 inch) heavywall tunnel

The formulation hardware

in 7.62 cm

(3 inch) and 17.8 cm hardware in wind

and 17.8 cm (7-inch) Development

flightweight Center (AEDC).

tests at Arnold the original AP with sodium

Engineering formulation nitrate on

For the hybrid some HCI

program, of the

was subsequently an equal molar

modified basis to

by replacing scavenge the

formed

in the exhaust

products.

Table 3.

Gas Generator

Hybrid

Fuels

Evaluated.

Maximum Isp
NO.

Mixture Ratio 1.5 3.5 1.5 4.0

Fuel ARCADENE 399

Oxidizer LOX H202 95%

N-SIKg 3112.1 2947.3 3128.7 2945.3

ARCADENE

399C

LOX H202 95%

(w NaNOR) (wo Fe203) 3 AGN

LOX H202 95%

2873.7 2785.5 2084.2 3040.5 3148.4 3040.5 2812.9 2880.6

0.5 1.0 0.5 1.0 1.5 2.0 0.33 0.67

ARCADENE ARCADENE ARCADENE ARCADENE 12% HTPB 48% AP 40% Al

246B 246* 246* 246*

LOX LOX LOX LOX LOX H202 95%

NOTES:
i.

2. 3. 4. 5. 6.

ARCADENE 399C: scavenged version of ARCADENE HTPB; hydroxyl terminated polybutadiene. AP: ammonium perchlorate. Al: aluminum. AGN: aminoguanidine nitrate. ARCADENE 246*: scavenged version oxidizer. of ARCADENE

399.

246B with

35% solid

A conventional ated. percent iron wide

gas generator

propellant

(ARCADENE

246B)

was

also

evalu69.5

The formulation ammonium

[25.6 percent

polybutadiene

acrylonitrile (DER-331)

(PBAN),

perchlorate was

(AP), 4.5 percent because it:

curative (I) was propellant

0.4 percent over a

oxide

(Fe203)]

selected

characterized

range of burning

rates;

(2) had excellent and physical the HARDROCK

reproducibility;

and

(3) had excellent tion was used tract

processing

property Silo

performance.

The formulaActuator (Con-

to pressurize

Lid Door Opening Generator System

FO4704-A3-C-O048),

the

UPSTAGE

Jet

Gas Weapon

program (Contract

(Contract F04704-85some of the

F04704-87-C-0054), C-0039).

and the MX Buried formulation

Trench

The original

was modified

by:

(1) replacing

AP with sodium nitrate on an equal molar basis to meet the HCI emissions requirement; and (2) reducing the weight-percent of the solid oxidizer from 69.5 to 35 percent, and subsequently increasing the binder content to make the
exhaust products more fuel-rich. fuels 40 were also evaluated. and 48 The best-performing AP. The metallized Isp 399, for and this the

Metallized formulation formulation system had was

percent

aluminum lower

percent scavenged One

9.6 percent at a lower

than

the

ARCADENE design

optimized from

mixture was

ratio. higher were

of the

issues these many

which higher

resulted

this for

evaluation metallized

flame

temperatures; with

temperatures advanced

systems

incompatible

of

the

material

concepts

considered

for this design. 399 variant variant binder percent formulation consisted including ammonium 3 was completed of 25 percent plas15.5 graph-

A limited under corporate

evaluation IR&D.

of an ARCADENE This

formulation (HTPB) 21.5

hydroxyl-terminated ticizer, percent 34 sodium percent

polybutadiene polystyrene, 2 percent were made

percent

perchlorate, fluorinated Samples

nitrate, mixes

iron oxide, and cast

and 2 percent

ite (CFx). were cut from 1.38 to

Pint

into cartons. burner

of the fuel {from strands of 6.88 and

the cartons (200

and tested

in a strand

at six pressures pressure. The

13.8 MPa

to 2,000

psi)]

and atmospheric in/sec) good

had a burning MPa (1,000

rate of 0.38 Further,

cm/sec they

(0.15

at a chamber ejection

pressure

psi).

exhibited

characteristics

would

not burn

below

3.44 MPa (500 psi). was also completed of 65 percent

A limited under

evaluation

of an ARCADENE This

246 variant formulation (PBAN), The

formulation consisted percent had

corporate

IR&D funding.

polybutadiene-acrylic and 14.7

acld-acrylonitrile sodium nitrate. at a

20.3

ammonium

perchlorate, of less

percent cm/sec

strands

a burning

rate

than

0.25

(0.1 in/sec)

chamber The

pressure

of 6.88 MPa (1,000 psi). version of ARCADENE 399 was eventually selected for the

scavenged

point design.

The formulation

was selected

because

it exhibited

better

ejec-

tion characteristics of mixture 2.2.2 The

than ARCADENE

246, and the theoretical provided a wider

Isp as a function operability range.

ratio was flat above Hybrid Fuels

1.5, which

Classical fuels

utilized

in the classical

hybrid Based

(Table

4) were

selected

from

our solid fuel ramjet

(SFRJ) database.

on our airbreathing

experience,

we assumedthat
concerns tion. the The H202

the oxidizers

would

be gasified mixing

prior

to injection

to minimize combusand tem-

of flameholding,

injection,

efficiency,

and hypergolic to

was decomposed using

using

a catalyst to obtain

bed prior

injection, (GOX)

LOX was

preburned

propane

a gasified

oxidizer

perature

of 667K

(I,200R).

Table 4.

Classical

Hybrid

Fuels

Evaluated.

Maximum Isp No. I HTPB Fuel Oxidizer GOX*667K H202 95% 2 75_ HTPB 25% PS GOX*IOOOK GOX*667K H202 95_ H_O 2 88_ 3 HC + 10% AP GOX*667K H202 95% 4 HC + 20% AP GOX*667K H202 95% 5 HC + 18% Al GOX*667K H202 95% 6 7 HC + 18% Mg/Al HC + 18% Al + 10_ AP 8 50_ HTPB 50_ Mg/Al 9 50_ HTPB 50% Al H202 95% GOX*667K H202 95% 3061.1 3174.8 3074.8 2.5 1.5 3.0 0 4890 0 H202 95% GOX*667K H202 95% N-S/Kg 3291.6 2996.3 3276.8 3277.8 2990.4 2898.3 3245.5 2988.5 3241.5 2981.6 3271.0 3020.0 3015.0 3252.3 3018.9 Mixture Ratio 2.5 6.5 2.75 2.5 6.5 7.5 2.0 6.0 2.0 5.0 2.0 5.5 5.5 1.75 4.75 Propane Kgs 5615 0 8601 5638 0 0 5315 0 5321 0 5273 0 0 5063 0

NOTES: 1. 2. 3. 4. 5. HC: hydrocarbon fuel 75_ hydroxyl polystyrene (PS) Propane is used to gasify LOX. AP: ammonium perchlorate. Al: aluminum. Mg/Al: magnesium aluminum alloy. terminated polybutadiene (HTPB); 25%

The baseline fuel for the classical hybrid approach is a hydrocarbon (HC) SFRJ fuel which contains no solid oxidizer and is 75 percent HTPB and 25
percent baseline polystyrene fuel was {PS). evaluated The addition at the of solid oxidizer and metals of 6.88 MPa to the {I,000 fillers reference Alternate conditions binders

psla) and an expansion were also evaluated

ratio of 15. to

and nonmetallic

and found

provide

minimal

differences

in performance

and density. We concluded tives provide from the evaluation results with of fuels and oxidizers oxygen (GOX) that than fuel addiH202 as

different

gasified

with

the oxidizers. the Isp and

The addition

of aluminum mixture

to the baseline ratio with GOX;

solid using

fuel decreases peroxide, only the

lowers

the optimum The addition

the Isp is reduced. optimum formance increased trations mixture penalty solid above

of solid oxidizer the burning optimum shown

decreases

Isp, reduces

ratio, and

and improves the shift levels in the in is

rate

tailorability. ratio 4.

The perwith

mixture

associated AP

oxidizer 10 percent

in Table will

Further,

concento meet

solid

fuel

require

scavenging

the HCI emissions Preliminary indicate for the

goal of less than analysis of

1 percent. performance of these fuels did not Isp

the payload

a formulation classical system

with a superior was offset

capability. by the

The higher in system The

theoretical weight

hybrid

increase

due to of

the propane

required

to gasify

the oxidizer.

increased

density

H202 was offset

by the lower Isp and the requirement the fuel evaluation, for ARC selected point

to carry

a catalyst

bed. 399

To summarize as the fuel fuels fuel of

the scavenged design point

ARCADENE

choice

the gas generator

and the hydrocarbon design. (Section These 2.3) two and

containing were used

HTPB and PS for the classical for all of the engineering

hybrid trade

studies 2.6.

cost parametrics E.3 Propulsion Concurrent studies dizers were with

developed Conceptual with the

and presented Studies oxidizer The and

in Section

fuel

studies,

booster

system

trade oxi-

initiated. either

hybrids

were

evaluated

using

LOX and H202 Eight

a pressure-fed

or turbopump

delivery

system.

configfeed

urations systems).

were evaluated In were order

(two hybrid concepts, to compare the eight

two oxidizers, configurations,

two oxidizer certain

vehicle

parameters

held constant.

I0

The overall vehicle diameter was set at 3.7 m (12 feet), close to the shuttle solid rocket booster (SRB) diameter [3.7 m (12.2 feet)]. The thrust
profile MSFC established these for the Advanced The Solid Rocket Motor operating (ASRM) was provided pressure occurs by for calculations. maximum about The was

10 seconds nozzle

Into operation

and was calculated Using

to be 7.57 MPa these values,

(1,100 psia). a mixture ratio

expansion

ratio was set at 15. highest vacuum

selected to produce the for the entire burn. Fuel profile sidered sets of and oxidizer

Isp, and this

ratio

was held constant

requirements in the

were

calculated of work.

to meet These

the vacuum values

thrust con-

specified

(ASRM)

statement

were

to be independent values were

of oxidizer

feed system;

therefore, weights out

only four unique (fuel and oxlof the to be

calculated. conceptual

With

the propellant designs were

dizer)

identified,

booster

laid

for each assumed

eight options. 95 and 98

Packing for

efficiencies the classical

and fuel hybrid

utilizations

were

percent Grain

and gas generator time, lead

grains,

respecwas

tively. given to

geometry high

was not optimized port velocities were

at this

but consideration to erosive components materials

avoid

which selected

could

burning (motor were

phenomena. cases,

Structural tanks,

materials gas

for the major

oxidizer

pressurization

tanks).

Composite

used extensively, ous trade boosters studies

especially clearly

for the pressure-fed that based

designs; on weight,

results large booster relative

from previpressure-fed designs. merits were of not

indicated

with metal

tanks could goal of

not compete this effort which

with turbopump was to evaluate common thrust

Since the eight evaluated tronics, for these A booster carried hybrid

the major

configurations, in great detail.

components These

were

to all eight vector

items

include

control,

elec-

instrumentation,

nose cone,

and recovery systems, F-1

system. notably

Weight

allocations SRB. Saturn V

items were derived turbopump used to

from similar from

the shuttle for the

single was

derived

the

pump

design gas

generate gas

weight

breakdown. to power

The the

generator The

designs classic

separate designs

solid

generators burned with

turbines. to power

used propane, the oxidizer. design These

some oxidizer,

the turbines

and to gasify

Pressure-fed the oxidizer the purpose tank. of

options options

considered

a number

of methods

to pressurize A. For

are discussed trade studies,

in detail the

in Appendix LOX

the

engineering

pressure-fed

options

11

used Tridyne to
Aerojet gen and 0.03 moles to produce

pressurize

the

oxidizer of

tank.

Tridyne gases

was

developed

by

and consists

of a small fraction combined mixture controlled used with that by

reactive

(0.06 moles (0.91 moles

hydrohelium) The

oxygen)

an inert can

diluent

a nondetonable is

be stored the

at high mixture was

pressure.

hot-gas

temperature H202

varying helium,

concentration. heated in a heat tank. Tank stored

Pressure-fed exchanger

options

subcooled

which

by the decomposition in the turbopump

of f1202 to pressurize options was

the oxidizer using

pressurization at ambient

accomplished head. for

helium

temperature layout

to provide and component

positive weight

suction

Booster designs pump other

breakdown

seven

of

the

eight

are provided was

in Figures completed it was

1 through because

7; the classical by that combining this the

hybrid-H202-turboresults would not from be the cost

design design

never

efforts, with

determined

option

competitive Table were 0.5

LOX (Figure

8). of the than study: (I) the classical gas than generator systems hybrids hybrids; H202,

5 summarizes to 2.5

the results lighter 7 to

percent LOX were

equivalent lighter

(2) systems

using

10 percent longer

using

but they were also 5 to 17 percent (3) turbopump fed from options, this systems and 33 were to 68

due to the lower density 2 percent cost. lighter than

of LOX; and

approximately percent lower

the pressuredrawn

Additional in large

conclusions

study

were:

(1) use of composites improvement; and

structural

components benefit

provides the most

substantial from

performance

(2) pressure-fed

systems

the use of composites; systems into warrant each

(3) the benefits consideration a reliability major

of using

composites

for expendable

continued was

and development. goal of 0.9995 using for the

Incorporated booster. data was This

design

goal

was apportioned Aerospace. impact

to each

component trade The

historical reliability system

supplied evaluated

by Boeing as

For the initial on the system. turbopump

studies,

a weight

liquid pump

oxidizer

incorporated

redundancy

(additional goals;

to provide systems were

out capability) at a higher

to meet the reliability margin of safety life flight (1.6).

the remaining

designed trace.

Each design (LCC) for

met the MSFC thrust each configuration

The constant provided ($11.4

cycle

cost

was estimated The lowest with 2,

using

rate of one flight

per month

for 10 years. hybrid Concept

LCC was

by Concept billion),

1AT, the pump-fed the highest was

gas generator provided by

LOX oxidizer the classical

and

12

FOLDOUT

_" '_' _"

/
Concept No. 1 ARCADENE-399C/Hydrogen Peroxide Pressure Fed Version

Cgm_oonent

Weight

Breakdown

Com_nent Gas Generator Propellant Case Liner/Insul. Igniter Oxidizer Tank Liner Piping Manifolds Valves Gas Tank Liner Ext. Insul. Chiller Feed Lines Valving Heat Exchangers Gas Generator Injector Case Insulation Nozzle Ext. Insulation lnterstage ARCADENE-399 IM-7/826 Kevlar/EPDM 107, 2,';'
Z

Oxidizer Delivery System

95% H2 02 IM-7/826 Aluminum S.S.

435,f 9,, (

Pressurizing System

Helium IM-7/826 Aluminum Blown Foam S.S.

6,_ 14,"

Catalyst

Bed
1

Thrust Chamber

S.S. HPg-4 Steel Silica/EPDM Ablative

1, 10,

Ancillary Components Propellant Weigh t Inert Weight Total Propulsive System

AI-Li 543 53 597

* For a metal

(aluminum-lithium)

gas generator

case add 12,796 kg

FOLDOUT

FRAME

1
553.7

o 325.1

+
H e Tank Wall 12.4 Thick IM-7 0.08 Thick AI Liner Gas Generators Heat Exchanger H 2 0 2 Tank Case, Wall 2.1 Thick IM-7

39.4

1
1
J_
,54 '80 77 :17 365.8

2.705.1

25.4 4,998.7

Manifold Igniter Gas Generator Wall 1.7 Thick IM-7 Insulation 0.04 Thick H2 02 Feed Line 20.3 ID 4--Places Injection Plate

1
1

5O '58 69 993.1

20.3

1
'21 _35 _25 186 1 1.8

yalves

1
Flex Seal o 119.4

1
5080

_29 47 )76

1
Lo 462.3J Note: All dimensions are in centimeters

Nozzle

Figure

1.

Gas

_enerator

hybrid

with

hydrogen

peroxide

(pressure fed version).


01gO.HYBRIOFIPT

13

FOLDOUT

FRAME

Concept No. 1T ARCADENE-399C/Hydrogen Peroxide Turbopump Version

Component

Weight

Breakdown

.CJQI]3DgJ1P,_ Gas Generator Propellant Case Liner/Insul. Igniter Oxidizer Tank Liner Piping Manifolds Valves Gas Tank Liner Hardware Catalyst Bed Injector Case Insulation Nozzle Ext. Insulation Interstage

Material ARCADE NE-399 IM-7/826 Kevlar/EPDM 107, 2,,


Z

2 95% H 2 0 2 AI-Li Teflon Aluminum


444,2 5,1

Oxidizer Delivery System

Pressurizing System

Helium IM-7/826 Aluminum

Turbopump System Thrust Chamber

Silver/Nickel S.S. HP9-4 Steel SilicaAEPDM Ablative 3,1 6 1,," I0,_

Ancillary Components
Propellant Inert Total Weight Propulsive System Weight

AI-Li 552, I 28,1 580,_

* For a metal (aluminum-lithium)

gas 9enerato[ case add 12_,796kg

FOLDouT

FRAME

e 182.9

.t
119.4

Valve H e Tank Wall 6.1 Thick IM-7 0.08 Thick AL Liner H 2 0 2 Tank Case, Wall 0.47 Thick Aluminum-Lithium _lq-" 1/ Gas Generator Turbopump Igniter
f/ /

1
o 365.8

J_
_54 '80 W7 17 34 70 tO3 498.3

2,786.4

99.1

Gas Generator Wall 1.7 Thick IM-7 Insulation 0.04 Thick -- 0 78.7 H 202 Feed Line 20.3 ID 4-Places Injection Plate

"-" 993.1 ',25 ;26 19 ,88 79 _21 "35 '25 _86

Valves

111.8 1
Flex Seal 508.0 e 119.4 Nozzle L o 462.3 J

1
88 11 '.99 Note: All dimensions are in centimeters

Figure

2.

Gas

generator

hybrid

with version

hydrogen ),

peroxide

(turbopump

O I Oa44YBRO-RI_t

14

I_OLDOUT

FRAME

/.

Concept ARCADENEPressure

No. 1A 399C/L OX Fed Version

Component

Weight

Breakdown

Gas Generator

Propellant Ca se Liner/Insul. Igniter Oxidizer Tank Liner Piping Manifolds Valves Insulation Gas Tank Liner Ext. Insul. Catalyst Bed Feed Lines Valving Injector Case Insulation Nozzre Ext, Insulation Interstage

ARCADENE-399 IM-7/826 Kevlar/EPDM

20"

Oxidizer Delivery System

LOX IM-7f826 Aluminum S.S. S.S. S.S. Blown Foam He/H2/02 IM-7/826 Aluminum Blown Foam S.S.

30'

Pressurizing System

Thrust Chamber

S.S. HP9-4 Steel Silica/EPDM, Ablative

Ancillary Components Propellant Weight Inert Weight Total Propulsive System

AI-Li
51

5_

For a metal aluminum-lithium

gas generator

case add 12,796

kg

FOLDOUT

FRAME

._:_

t
432.6

e 337.8_

365.8 17 _2 7 /6 17 )6 _0 5:491.5 I 2,550.2

H e Tank Wall 12.4 Thick

Case, Wall 2.1 Thick IM-7 Manifold Igniter

16 20 78 1 1,813.6

78.7

Gas Generator Wall 1.7 Thick Insulation 0.04 Thick H2 02 Feed Line 20.3 ID 4-Places Injection Plate

21 35 25 g6

20.3

Valves 1 1.8

Flex Seal 27 09 36 {} 119.4 Nozzle

Note:

All dimensions are in centimeters

Figure

3.

Gas generator (oressure

hybrid

with LOX

fed version),
01GO4"._Ia_N_IqPT

15

FoLDOUT

FRAME

Concept

No.

1AT

ARCADENE-399C/LOX Turbopump Version

Comoonent

Weight

Breakdown

Subsystem Gas Generator

Comoonent Propellant Ca se Liner/Insul. Igniter Oxidizer Tank Piping Manifolds Valves Insulation Gas Tank Liner Valving Piping Hardware Propane Tank Propane Deliveq/ System Injector Case Insulation Nozzle Ext. Insulation Interstage S.S. HPg-4 Steel Silica/EPDM Ablative ARCADENE-399 IM- 7/826 Kevlar/EPDM

Weight

(kg)

203,251 4,918 842 217 310,166 3,701 350

Oxidizer Delivery System

Lax AI-Li Aluminum S.S. S.S.

Pressurizing System

Helium IM-7/826 Aluminum SS. S.S.

361 556 17

Turbopump System

1,463 174

Thrust Chamber

3,221 635 1,225 10,886 222 340 513,416 30,156 543,568

Ancillary Components Propellant Weight Inert Weight Total Propulsive System

For a metal

(aluminumqithium)

gas generator

case add 12,796 kg

FOLDOUTFRAME '__'_

182.9

1
119.4

Valve HeTank Wall 6.1 Thick IM-7 0.08 Thick AI Liner H20 2 Tank

t
365.8 2,786.4

Case, Wall 0.4 Thick Aluminum-Lithium


/

4-I

Propane Igniter

Tank

99.1

Turbopump Gas Generator Wall 1.7 Thick IM-7 Insulation .015 Thick -e 78.7 H202 Feed Line 20.3 ID 4-Places

2,094
1,813.6

Injection t 111.8 20.3


r

Plate

Valves

t _ ,_ Flex Seal g119.4

[
508.0

L
Note: All dimensions are in centimeters

"--- Nozzle

Figure

4.

Gas

generator

hybrid version),

with

LOX

(turbopumo

019t_pCBR_- I_CrT

16

FOLDOUT

FRAME

////_

Concept No. 2 Hydrocarbon/H2 02 Pressure Fed Version

Component com nen[


Solid Motor

Weiaht Breakdown

Fuel Case Insulation Cat. Bed Injector Plate Oxidizer Tank Liner Piping Valves Manifold Gas Tank Liner Hr. Exchanger Cat. Bed Plumbing

Hydrocarbon IM-7/826 Kevlar/EPDM Ag Plated Ni Carbon-Carbon H 2 02 IM-7/826 Aluminum

68,497 2,474 1,964 4,540 791E, 473,18; 10,351 79#'

Oxidizer

Tank

Pressurizing System

Helium IM-7/826 Aluminum Steel Ag Plated Ni

7,414 12,629 258 31( 5O

Nozzle Ancillary Components Propellant Weight Inert Weight Total Propulsive System Ext. Insulation Interstage

Ablative

10,886

AI-Li 541,68, 52,08,: 593,7611

For a metal

(aluminum-lithium)

gas generator

case add 12,796 kg

FOLDOUT.:,,-_,,,,,-

580.4

e 340.4 H e Tank Wall 10.8 Thick

e 365 H202 Tank Wall 1.7 Thick

5t570.2

l
231.1

Oxidizer Plate

Injection

Multi-Port Hydrocarbon Solid Fuel Grain

7
A Case Wall 1.2 Kevlar/EPDM Insulation 0.8 Thick Nozzle

I 508.0 I I 1 Lo 462.3 J Section A-A

Note:

All dimensions

are in centimeters

Figure

5.

Classical peroxide

hybrid (pressure

hvdrocarbonlhvdroeen fed version I.


O I QOI_BAI[_ Alert

17

J_

FO!.._OUTF_._,.? _

Concept

No.

2A

Hydrocarbon/LOX Pressure Fed Version

Com00nent

Weiaht

Breakdown

Subsystem Motor

Com_nent Fuel Case Liner/Insul. Injector Plate Oxidizer Tank Liner Piping Manifolds Valves Fuel Tank Precombustor Piping Valves Manifolds Press. Gas Press. Tank HTPB/Poly IM-7/826 Kevlar/EPDM Carbon-Carbon LOX IM-7/826 Aluminum SS.

Weiaht

(k

126,37' 3,83! 2,58(

Oxidizer Delivery System

362,167 8,67_c 72_

LOX Pre-heater

Propane IM-7/826

5,994 38c_

Helium IM-7/826 H e/H2/02 rM-7/826 Aluminum S.S.

23_ 58_ 4,219 11,399 142

Pressurizing System

Gas Tank Liner Feed Lines Valving Nozzle Ext. Insulation Interstate

Thrust

Chamber

Ablative

10,886 222 408 494,532 45,100 539,632

Ancillary Components Propellant Weight Inert Weight Total Propulsive System

AI-Li

For a metal aluminum-lithium

gas generator

case add 12,796

kg

FOLDOUT

FRAME

HeTank Wall 10.8 Thick Catalyst Bed

IM-7

LOX Tank Wall 1.7 Thick

IM-7

3p45.5

5_62.3

1
t
116.8

Toroidal Tank Oxidizer Plate

Propane

Injection

231.1

LOX Feed Line 20.3 ID 2-Places Multi-Port Hydrocarbon Solid Fuel Grain Case Wall 1.4 Kevlar/EPDM Insulation 0.8 Thick Toroidal Injection Manifold

1_386.8
A

92.7

I
508.0 Lo

Aft Insulation Kevlar/EPDM Nozzle

7.6 Thick

Section

A-A

Note:

All dimensions

are in centimeters

Figure

6.

Classical (pressure

hybrid

hydrocarbon/LOX ),
0 IgO44Y BRIO.-RIPT

fed version

18

FOLDOUT

FRAME

Concept No. 2AT Hydrocarbon/LOX Turbopump Version

Comoonent

Weight

Breakdown

Subsystem Motor

Comoonent Fuel Case Liner/Insul. Injector Plate Oxidizer Tank Piping Manifolds Valves Propane Tank Liner Piping Valves Manifolds Gas Tank Liner Feed Lines Valving Nozzle F-1 Combustor Ext. Insulation Interstate

HTPB/Poly IM-7/826 Kevlar/EPDM Carbon-Carbon LOX IM-7/826 S.S. 126,3 3,8. 2,5

Oxidizer Delivery System

370,9 3,_ 5,

Propane System

IM-7/826 Aluminum

Pressurizing System

Helium IM-7/82 6 Aluminum S.S.

Thrust

Chamber

Ablative

10,_,

Turbopumps Ancillary Components Propellant Weight Inert Weight Total Propulsive System

1,4_

AI-Li

2: ,3 503,5 26,8 530,3

For a metal aluminum-lithium

gas generator

case add 12.796 kg

F.....

C?--" , :,:3.ME

Valve H e Tank Wall 6.1 Thick IM-7 .08 Thick AI Liner H 202 Tank Wall 1.7 Thick C3 H 6 Tank 71 39 80 e 365.E 3'2i0"7 Turbopump Oxidizer Injection Plate

266.7

5;494.0

[
1.386.8 115.6

Multi-Port Hydrocarbon Solid Fuel Grain

45 05 34

Case Wall 1.2 Kevlar/EPDM Insulation 0.8 Thick Nozzle

52 91 31

]
508.0

o 118.6

e 462.3 J Section A-A

86 05 91

Note: All measurements

are in centimeters

Figure

7.

Classical

hyOrid hydrocarbon/ fed),


0100-HYBRIDRPT

LOX (turbopump

19

25 [LR_Classical Hybrid I II GG Hybrid 20

0 Concept Oxidizer

1AT LOX

1A LOX

1T H202

1 H202

2AT LOX

2A LOX

2T H202

2 H202

Figure

8.

Hybrid

configurations

life cycle

costs.
01gO-HYBRIDRPT

Table

5.

Concept

Summary.

ID No. 1 1T 1A 1AT 2 2T 2A 2AT

Hybrid GG** GG GG GG Classical ++ Classical Classical Classical

Oxidizer H202 H202 LOX LOX H202 H202 LOX kOX

Feed System Pressure Turbopump Pressure Turbopump Pressure Turbopump Pressure Turbopump

Weight* 597 580 553 543 594 ...... 540 530

Length + 4978 4539 5532 5819 5560

LCC (%)*** 166.5 117.3 133.6 I00.0 189.0 120.9

5837 5494

168.0 111.4

+ * ** ++ ***

In centimeters. In thousands Gas generator Classical Compared of kilograms. fuel was ARCADENE 399C. HTPB, 25 percent PS.

hybrid

fuel was 75 percent hybrid 20

to the gas generator

with pump-feO

LCX.

hybrid shown

with

pressure-fed

H202

($22

billion).

summary

of

the

results

is

in Table 5 and Figure 8. certain assumptions

To calculate had to be

the costs made.

of the eight

conceptual are as

designs, follows:

These

assumptions

Classical

hybrid utilized

gaseous

oxidizer bed.

injection.

H202 was decomposed Fuel utilization

by a catalyst

for the gas generator

was 98

percent,

and the clas-

sical hybrid was 95 percent. Turbopump system had pump-out trade capability studies, design to meet the mission. the gas generator all consideration life due to the

As a result hybrid of to develop

of our initial a more-detailed hybrid. The

ARC selected and dropped

point

the classical cost,

gas generator hybrid

hybrid

had lower

calculated risk

cycle

and the classical uncertainties

presented

higher

development interactions

the scaling oxidizer 2.4 Point To requested two of

associated

with the complex

between

and the solid fuel grain. Design a for range two of hybrid meet eight possible rocket the vehicle motors: specified system a large ASRM requirements, (full-size) profile; MSFC motor, and a

encompass designs

which

in combination motor,

thrust meet

small

(quarter-size)

of which design The

in combination will

the same thrust first, followed

profile.

The full-size

motor

point

be described design

by the quarter-size gas generator which

motor

design.

full-size solid

features to be

a fuel-rich

contains

sufficient pressure 2.06 MPa

oxidizer

self-sustaining yet completely

above

a predetermined

operating below

(2.06 MPa, (300 psia) from

300 psia), without

extinguishes eous

at pressures The

a liquid or gasare injected

oxidizer.

fuel-rich chamber, eliminates motor

products mixed many

the gas

generator

into a separate tion. This

thrust

with of

an oxidizer, the complex

and burned processes

to compleinvolved in

approach rocket

classical thrust

hybrid

design.

Flow between in chamber

the gas generator pressure rate

and the

chamber

is subsonic;

thus,

changes

are communicated

to the gas generator. tor can be modulated ber which oxidizer bustion affects flow limit.

By this means, by changing

the fuel burning

in the gas generachamoff

the oxidizer Thrust

flow rate

into the thrust

chamber causes

pressure.

can be terminated pressure to fall

by shutting below

which

the gas generator

the com-

21

Design pressure-fed pump design the required

of

the

oxidizer and four point

delivery designs

system were

considered generated of for

both both.

turbopump

and

options, features oxidizer

The turboof

oversized even a Tridyne psia). less than

pumps, with

capable

supplying of operation.

100 percent

flow,

one pump out system (helium,

The presoxygen) at a

sure-fed pressure

design of 68.9

features MPa (10,000 have

hydrogen,

Both designs 1 percent maximizing

utilize

LOX as the

oxidizer.

The exhaust The

emissions effort of the

HC1 by weight. the safety safety factor was of and 1.6 reliability was chosen where

design

focused vehicle.

upon

characteristics to provide

A structural Design

a conservative safety, were

margin.

simplicity

emphasized safety, the SRB and

possible ity, and

to improve cost

reliability, given gains Layout

and cost. over

Although

reliabilresulting or other

factors

priority over the

performance, shuttle turbopump

design advanced

provides booster

performance designs.

current both 9.

drawings

for

pressure-

fed, full-size

booster

designs

are given

in Figure

Point designs assuming a peak

for both pressure-fed pressure of 8.62

and turbopump MPa (1253

options

were

generated expan-

chamber

psia)

and a nozzle might

sion ratio of mal the for either subsequent the

15. of

It was recognized the systems, effort, designs. but as

that these this as

conditions

not be optiin comand is

assumption

permitted

commonality basis for

design system

well Weight

a straight-forward for

paring

two

breakdowns 6 and 7. 3.4

the pressure-fed version

turbopump lighter porate

options than the

are presented pressure-fed thrust

in Tables version vector by

The turbopump Both for

percent. designed

designs

incor-

liquid

injection

control

3 to 5 of thrust

deflection. 2.4.1 The terized Gas Generator fuel-rich formulation gas generator propellant was derived from a well-characis given in

previously

developed

by ARC.

The formulation ARCADENE

Table 8 and lation sodium was

is identified modified by

as ARCADENE removing

399C.

The original of the AP and

399 formuit with of the to form

a portion basis.

replacing

nitrate

on an equal-molar thereby

The sodium acts as a scavenger it from combining with hydrogen

chlorine HCI.

molecule, has in

preventing

ARC

successfully 907 kg

demonstrated Ib)

a different hardware

sodium-nitrate-scavenged (726 kg, 1,600 Ibs of

propellant propellant);

(2,000

heavywall

363 kg (800 Ib) Super

BATES; and 32 kg (70 Ib) BATES motors

under

22

2,288.5 cmA

Pressure Fed Gas Generator

. !1,981.2

cm

Pump Fed Tridyne Wall IM-7 Tank _ Tank Valve r t _ / Tridyne

/(_1 _)-_ -_ _'" i _ !i _ F

LOX Tank 434.3 cm

LOX Tank _ 419.1 cm

Aluminum _ Lithium C_se J

Composite Case

4,681.2 cm

Gas Generator Wall IM-7

I_ 386.1 cm Igniter

Valves

119.4

O 119.4 cm Pad Support Structure Nozzle

L
Figure 9. Full size booster designs.

462.3 cm

O190-HYBRID-RPT

23

Table 6. Subsystem Gas Generator

Full-Size

Vehicle

Weight Element

Breakdown

(Pressure

Fed). (kg)

Weight 209,911 7,418 635 45 299,700 13,164 522 3,601 9,740 103 298 105 1,134 8,174 892 2,428 1,592 497 2,631 680 563,269

Fuel Case Liner/Insulation Igniter System LOX Tank (Composite) Feed Lines

Oxidizer

Delivery

Pressurizing

System

Tridyne Tank Liner Catalyst Plumbing

Bed and Valving

Thrust

Chamber

Injector Manifold Chamber/Nozzle TVC External Insulation

Ancillary

Components

Interstage Nose Cone Skirt Thrust Transfer Total Weight

Ring

(1,241,796

Ibm)

Table 7. Subsystem Gas Generator

Full-Size

Vehicle

Weight

Breakdown

(Turbopump). Weight 214,900 7,541 644 45 299,700 4,213 170 1,124 816 (kg)

Element Fuel Case Liner/Insulation Igniter System LOX Tank Feed (AI-Li) Lines

Oxidizer

Delivery

Pressurizing Turbopumps Thrust

System

Tridyne/Inert

Chamber

Injector Chamber TVC External

Manifold

1,134 6,350 892 2,428 594 497 2,631 68O 544,360 (1,200,109 Ibm)

Ancillary

Components

Insulation

Interstage Nose Cone Skirt Thrust Transfer Total Weight

Ring

24

Table B.

Gas Generator

Fuel.

ARCADENE

399C Formulation 34.0K 29.0% 21.5% 15.5% Total 100.0_

Polystyrene HTPB Ammonium Perchlorate Sodium Nitrate

Oxidizer Liquid Oxygen (LOX) at 77.6K

Combustion Flame Temperature Flame Temperature Density Without With

Properties LOX (K) 392 1,134 (g/cm 3) 1.2 982 1,686 (moles/t00 grams)

LOX (K) Fuel

of Gas Generator Fuel

C* of Gas Generator C* of Gas Generator Major Exhaust Products

(m/sec)

Fuel and LOX (m/sec) Fuel:

from Gas Generator

H20 CO CH 4 C (Solid) NaCl (Liquid) Major Exhaust Products from Gas Generator H20 CO N2 CO 2 NaCl Vacuum Vacuum Specific Specific Impulse Gas Generator Impulse Gas Generator

0.376 0.718 0.600 3.262 0.182 Fuel and LOX: 11.372 0.691 0.076 1.185 0.044 Fuel (N-sec/kg) Fuel and LOX (N-s/kg) 1,208 3,128 (moles/t00 grams)

25

contract used

to

the Astronautics will

Laboratory

(F04611-89-C-0028). using subscale

The motor

formulation hardware in

in the point design

be demonstrated

Phase 2. It guishment to provide The total mixture strated Figure is the nature of fuel-rich point propellants takes of this type to have extin-

limits.

ARC's

design

advantage

of this

characteristic

thrust-termination design of the

capabilities

for the booster. was driven by fuel flow A rate and

gas generator for the

grain

fuel

requirements

specified

booster

duty

cycle. this

desired

ratio by 10.

(MR) of 1.4 was selected the plot of vacuum Isp

for optimum

performance;

is demonratio in

(theoretical)-versus-mixture of mixture ratio

This curve shows that mixture ratios of

Isp as a function

is fairly and perbased

flat between total cent

1.25 and 1.5. we assumed an

To determine impulse

grain

geometry of 92.5

propellant and fuel

requirements, (excess

efficiency

sliver

propellant

left at

burnout)

of 2 percent,

on our airbreathing

database.

3,139.2 _ 3,041.1 Pc= 1,000, E = 15 l

2,943.0

_, '_

2,644.9 2,746.8

2,648.7 I Pc Chamber Pressure E = Expansion Ratio 2,550.6 0.50


I I i I I I I I I

] 3.00

0.75

1.00

1.25

1.50

1.75

2.00

2.25

2.50

2.75

Mixture Ratio (weight OX/fuel) Figure 10. Vacuum h,_ versus


-AO190-HYBR|D..RPT

mixture

ratio,

expansion

ratio,

and chamber

presst_r,

26

An outer the fuel

diameter this

(OD) of 386 centimeters is considered to

(152 inches) the current

was

selected

for

grain;

be within base.

industry grain

manu-

facturing resulting pounds) required

and transportation from of the ballistic An

experience analysis, additional

The gas generator 209,gli kilograms shown

design, (462,774 is

requires 3,402

kilograms (7,500

propellant.

pounds)

to drive the turbopumps. configuration option is

The grain eight

design,

in Figure

11a, is a

center-perforated for the

with

aft slots.

The length inches), for

of the grain with the a port

pressure-fed of 79

1,600

centimeters the grain

(630

diameter option

centimeters centimeters The slot

(31 inches); (640 design inches) for both

length the

turbopump fuel for

is 1,625

to provide options

additional

the turbopumps. eight slots extend

is the same.

Four

of the while are 10

343 centimeters

(135 inches)

axially

into the grain, The slots

the remaining centimeters

four extend (4 inches)

only 292 centimeters spaced.

(115 inches).

wide and equally

A structural Texas Grain

analysis

of the gas generator (TEXGAP) the grain 278K

grain

was completed This at

using

the

Analysis analysis

Computer assumed of

program. 2 was cured (worst

three-dimensional, (590R) and then are

finite-element cooled given the to

328K

a bulk

temperature

(500R)

case). occurs

The results

in Figure of

11b. the

The maximum grain. This

strain of 18.2 percent value is within the

in the bore at allowable changes for to

aft end

maximum

propellants provide

when factors relief

due to grain

aging

are considered. bulk grain

Design operating

stress

would be required

if lower

tempera-

tures are specified. To aid length of in ignition, the long slots of the fuel grain with a 2.54 are overcast (1 inch) for a thick

368 centimeters igniter

(145 inches) propellant This

centimeter

web of HTPB-based second

with

a burning propellant

rate of 2.54 centimeters/ provides the initial the or gas

(1 inch/second). pressurization. reach The the

overcast time for

generator rates to

Its burn levels pressure

is sufficient either be is

to allow

LOX flow turbopump limits

required

the pressure-fed above

systems. of the

gas generator when

will grain

the extinguishment due to the

propellant

the starter

exhausted

secondary

TEXGAP 84, Anatech International Corporation, Force Contract No. F04611-84-C-0017.

Report

No. ANA-85-O029,

Air

27

_ 203o2 :_,,1_

203.2

406._l.. j A

_9rai6L.n_12iScm

'

1.0;6__J

1.219.2

1.42:._J

1.625.6

Section A-A

Section B-B

Section C-C

Figure

11a.

Full size _rai_

design,

194.6 cm

_c

! 39.1 cm

Propellant Modulus = 4.82 MPa -5 Thermal Coefficient of Expansion = 6 x 10 Stress Free Temperature = 327.6 K

Cold Temperature = 277.6K Maximum Stress = 0.66 MPa

Maximum

Stress = 0.42 MPa

Bore Strain Equals -3.4% Bore Strain = 18.2% Bore Strain = 16.1%

Figure

I l b.

Results

of _rain

structural

analysis.
01B)-HYBRIDRPT

28

combustion products tained

occurring and LOX. the

in Stable

the gas

thrust

chamber

between

the

fuel

rich will

exhaust be mainThe in

generator or to

propellant until the LOX

combustion flow is

until

grain

is exhausted trace due

terminated. is given

predicted Figure 12.

chamber

pressure

start-up

propellant

The spooling propellant small pad. igniter trade

use

of

an

overcast

grain

is

one

of

several

possible

schemes

for

up the turbopumps combustion

and establishing

required

pressures

and subsequent the use of a on the

in the gas generator. which

This approach installed

allows

aft-mounted An

igniter

can be easily be of to the

and activated

alternative located in

design the head

would end

use a cartrldge-type, gas generator. approach to

grain-mounted design and

Further

studies The

should

be performed

before

the final which

can be selected. the only fuel injector pres-

baseline is

aft-mounted in Figure

igniter, 13. The

is bolted provides

manifold, surization to build

shown

igniter

limited

of the gas generator, pressure that and must ignite be

Figure

14, relying of the

on the start-up fuel. This plate

propellant the the

the

balance through

minimizes to which

thrust igniter

loads

reacted

the

injector

is mounted. 640 560 "Start- Up" Propellant

480

400 320

240 160

80

0.4

0.8 Time, s

1.2

1.6

2.0

Figure

12.

leniter

Pressure 29

traces

for full-size

booster. 01gO-HYBRID,. RPT

Cross-section

Specir_:ations

Diameter ........................... 29.1 cm Length ............................. 83.7 cm No. of Spokes ............................ 30 Web ............................... -14.0 mm Spoke Length ...................... 5.64 cm Propellant Weight .................. 27.2 kg

Figure

13.

Igniter

grain

design

(full-size

booster).

30

20-

0.2 T/me, s

0.4

Figure

14.

l_niter

t_ressure

traces

(full-size

booster).
01EO-HYBRID-RPT

3O

The

baseline

gas

generator weight

case

design

incorporates steel case

carbon/epoxy construction.

comThe

posite materials gas generator and aft ends. lated psia) for

to provide

savings with

over

case

is monolithic, thickness

steel

polar

bosses (0.90 (MEOP)

at both the forward inches)], of 8.62 with was calcuMPa (1,253 for our than

The case

[2.3 centimeters pressure

a maximum

expected

operating

and to meet ASRM

bending axial

stiffness

requirements

commensurate not

those

the ASRM. booster

stiffness

requirements

were

addressed

because

design

transmits as the

loads to the core vehicle for the shuttle. boss and

at the aft end rather The fuel injector

the forward interfaces section

end, with

is the case aft polar

manifold design

is discussed weight

in the

injector

of this

report.

The case for

structural

was calculated and

to be 7,416 kilograms

kilograms

(16,350

pounds)

the

pressure-fed

option,

7,530

(16,600 pounds) A steel tion assumed stress

for the turbopump generator

option. also 1,514 sized MPa for comparison. (220,000 case psi) The calcula-

gas

case was of

a tensile

strength factor.

and a 7 percent for the same in a

biaxial

improvement factors

The resulting (0.66

thickness

loads and safety case weight or 23,133 The HTPB with

is 1.7 centimeters (67,500

inches).

This results

of 30,617

kilograms

pounds)

for the pressure-fed

option,

kilograms baseline glass

(51,000 gas

pounds)

heavier

than the composite is a an ablative of

case design. material gm/cm 3 made of

generator

insulation and has

microballoons

density

1.05

(0.038

Ibs/in3); The

it is designated insulation as the

the "ARC thioxotropic

insulation

process"

(ARCTIP). in exposed

required such

thickness and

is 1.3 centimeters aft domes and the

(0.5 inches) tip regions will by

regions fins, flame

forward

of the

long

and 0.13 exposure. web.

centimeters These

(0.05 inches) regions include

in the areas wall are areas minimal

which covered due

have minimal the maximum flame

propellant temperature A high

Insulation

thicknesses propellant safety was

to

the

low

of the gas generator thermal margin of

11,278K imposed

(2,300R)]. on the gas generator is defined and as:

components

in the hybrid

booster.

The thermal

margin

of safety

(original insulation thickness) TMS = (erosion + pyrolysis + char thickness)

- 1

(i)

The minimum

acceptable

TMS in the hybrid

booster

is 1.0.

31

Thermal analyses were performed at two locations in the gas generator using the charring and material ablation (CMA) computer code. 3 CMA models
surface response thermochemical erosion, in-depth decomposition, model. Boundary and temperature in the for a one-dimensional gas generator for predicted axisymmetric conditions

solid-fuel corrected file.

were calculated exposure times

using derived

pipe-flow from

theory

(Sieder-Tate), burnback pro-

the grain

Results thermal composite 2.4.2

of the thermal of safety of

analysis 2.75,

predict with

that the insulation

has a minimum in the

margin case.

no temperature

rise predicted

Thrust

Chamber requirements for the combustor The throat and nozzle diameter were established by

The design modeling

the combustion pressure of

process.

for the 8.62 MPa (1,253 (47 inches) nozzle with has

psia) chamber

was calculated

to be 119.4 centimeters (182 inches).

an exit diameter a throat-to-exit ber diameter throat throat area area,

462 centimeters

The bell-shaped

length

of 470 centimeters (66.5 of

(185 inches), giving

and the thrust

cham-

is 169 centimeters ratio. L*, was The ratio

inches),

a two-to-one free

chamber-toto the

the

combustor

chamber (120

volume

assumed This

to L*

be 305 centimeters value yielded a

inches)

to minimize (cylinder

combustion

instability.

chamber

length

only) of 147 centimeters Figure 15 shows a sketch types of

(58 inches)

and a residence chamber designs

time of 4.3 milliseconds.

of the thrust chamber

design. were examined, could to regeneratively be incorporated recoverability Thus, into the

Two cooled into and

combustion

and ablative. of the

While either booster in the design grouping thrust

thrust

chamber

design

either reuse

options, of

issues

related

resulted

high-cost

components

together.

the regeneratively turbopump design was system

cooled design

chamber

design was only

incorporated

for cost into

and performance

evaluation,

and the ablative designs. design As

incorporated

both the turbopump trades, we selected

and pressure-fed the ablative

a result hybrid

of our

engineering

for our

concept.

Aerotherm Charring Version 3, Aerotherm

Material Thermal Response and Report No. UM-70-14, April 1970.

Ablation

Program,

32

Igniter

Aft Skirt

TVC Injector (8) Proportional Flow (

Turbo Pump (4) Generator

Gas J
LOX Manifold

Injector Manifold

Isolation Valve

Launch Pad Support Truss desien.

Figure

15.

Thrust

chamber

9220

t
810.9

s@s

#,

S d r

I_

477.6
f

"
s @

I
w6'@ o

*-

i=,

366.5 255.4 0

f ,, ,'* 2.54

jo,_ .----- .... 5.08 7.62 Gas Side Coolant Side 10.2 12.7

Passage Height (mm) Figure 16. Throat wail temperature as a function of passage height_

011K)-HYBRID- RPT

33

2.4.2.1 chamber porates is

Regenerativel_ a single wall

Cooled

Design from ARC The

The D6AC

regeneratively (low alloy)

cooled that

thrust incor-

piece

machined

steel

channel

architecture. with LOX.

investigated cooling

the feasibility is complicated

of coolby the

ing the thrust

chamber

problem

fact the oxidizer coolant. sectional wall

is throttled

during

the mission would

resulting

in less available and the crossFigure 16 shows height

It was assumed area would vary

the chamber axially

have 150 channels, chamber.

along

the thrust passage

temperature

as a function (0.4

of throat

height.

If a passage

of 1.02

centimeters would be

inches)

is selected, 700K

the corresponding Figure

gas sidewall coolant height pas-

temperature passage of 1.02

slightly

under

(1,260R).

17 shows

pressure

drop

as a function (0.4 inches), under

of passage

height. drop

For a passage

centimeters

the pressure

(AP) in the coolant

sage would Figure different atures). LOX will 8.95 MPa

be slightly 18 shows

1.38 MPa (200 psi). temperature-versus-chamber (100 and 75 percent (1,000 pressure for two

coolant

exhaust This

gas temperatures shows that of

of the uncooled chamber

temperthe of As

plot

at 6.88 MPa 136K

psia)

pressure, pressure

be at a temperature (1,300 psia). chamber

(245R) still

at a coolant

passage

The LOX would

be a liquid pressure

at this condition. of 3.79 MPa

the thrust the coolant MPa

is throttled is 139K

to a chamber (250R)

(550 psia), of 4.65 at

temperature

at a coolant

passage

pressure

(675 psia). lower

At these pressures,

conditions, film boiling

the LOX is still starts and the

a liquid; heat

however,

slightly cients

transfer

coeffi-

would

have to be determined

experimentally

to determine

if it is still

possible

to cool the chamber. on the previous thermal and hydrodynamic designed ratio, out to analyses, (Figure LOX a single-pass The back of inlet to the an

Based

regeneratively manifold injector uncooled is

cooled located at

thrust the

chamber 9:1

was

19). flow

expansion point

with an

manifold. braided wall a

From

the

g:l

area

ratio

15:1,

carbon-carbon construction

nozzle

extension

is used. thrust provide chamthe

Channel ber using

was selected plated A number (SSME) with a on of

for the regenerative the D6AC steel to

copper-based

alloy

required the of Space

thermal Shuttle

conductivity. main is and to engine start

large

thrust

chambers

including method to the The

use this ring

approach. spin

One possible the forging

construction shape,

forging, to the

general

then

finish-machine

required

dimensions.

34

688.2

68.8

6.88

0.69 0

2.54

5.08

7.62

10.2

12.7

15.2

Passage Height, mm Figure 17. Coolant passage oressure drop as a function of passage height.

166.7 155.6 144.4 133.3 4" I_ 122.2 111.1 100.0 88.9 77.8 66.7 55.6 0
I I I I

TO% u ,S,,rO0

/
I 1.38 2.75 4.13 5.51

......
Tg = 2849 OKJ Temperature 6.88

Chamber Pressure, MPa Figure 18. l_elationship between coolant temoerature and chamber pressure.
01go-HYBRIDRPT

35

-=
_-147m3.-_

469.9cm

19.4 cm

Manifldl

462.3 cm

/
617.2 cm Figure 19. Single pass regenerative!v cooled thrust chamber, 469.9 cm 147.3
cm

__

Aft

Skirt

Attachment

Point

119.4 cm

462.3 cm

Braided Glass Phenolic

Filament Wound Glass Epoxy_l 617.2 cm Figure 20. Ablative thrust chamber design. vj

36

channels

are machined

onto the outer nickel closure over

surface

of the thrust surface.

chamber

and closed to the

by electro-depositing fabricate assembly. The channel the height of at wall the a one-piece

the entire

It is also possible to complete

and slide

it over

the channels

height

at the throat end is 1.14

is 1.02

centimeters (0.45

(0.4 inches), and the

injector

centimeters (1.1

inches), The thrust

height

the manifold for buckling computer

is 2.8 centimeters modes. program

inches).

chamber

was analyzed

The BOSOR5 tion of

for analysis shells of

of stress, used. 4 centimeters

stability, To meet (0.50

and vibrabuckling was

segmented, a channel

ring-stlffened wall thickness

was 1.3

the

pressure, calculated. Based follows:

inches)

upon

the

design,

the weight

of the thrust

chamber

assembly

is as

Regeneratively Cooled Portion Carbon-Carbon Nozzle Extension Injector Weight 2.4.2.2 Ablative Desiqn The ablative thrust

5,352 kg 998 1,134 7,484 chamber kg (16,500 design, Ib) Figure 20,

incorporates braided insert. designs

a three-directionally (MBA) thrust

(3D)-reinforced, with

glass-phenolic

monolithic throat

ablative The typical via MBA

chamber/nozzle over

a 3D carbon-carbon laminated

offers

advantages SRM nozzles

conventional

multi-ring is

of shuttle a 3D

in that

(1) ply-lifting/delamination (2) leak and paths (3) due

eliminated component simplified near-net for

reinforced and

architecture, are

to multiis to

interfaces via

bondlines low raw

reduced, costs

manufacturing scrap with due

automation,

material injector

and reduced along with

molding.

Attachment cone

to the are

manifold achieved

provision wound

the nozzle

extension

integrally

a filament

overwrap At

of glass/epoxy. an expansion benign ratio to of 5.7 aft of the throat, the glass/epoxy the flow to environment as is both

sufficiently

allow

overwrap

perform

Buckling of Elastic-Plastic Complex Shells of Revolution Including Large Deflections and Creep, Lockheed Missiles and Space Company, Report No. LMSC-D407166, December 1974. 37

flame-surface expansion chamber

and structure; of 15. The

therefore, total

the glass/epoxy of the

is continued

aft to an thrust

ratio

weight

composite

ablative

is 8,165

kilograms carbon

(18,000 pounds). phenolic, silica and phenolic, of a continuation and glass of the

Carbon/carbon, glass/phenolic were evaluated show that tlmeters

ablative

structure,

a hybrid

silica region.

fibers

for performance

in the nozzle erosion

throat

The calculations [1.3 cen-

carbon/carbon (0.5 inches or

has better

resistance

at the throat MBA

erosion)]

than

the glass

phenolic

[10.2 centimeters The glass due to the envi-

(4.0 inches)] phenolic

carbon

phenolic

[8.9 centimeters rates were

(3.5 inches)]. high

and silica

phenolic Carbon

erosion

unacceptably

high temperature. ronment resulting

phenolic

was unacceptable

due to the chemical also

from

an excess

of free oxygen. throat, effect

The environment

impacts in

the performance flame

of the carbon/carbon which has

but is offset on the

by the reduction reactions dioxide

temperature

a direct reactions modeled

kinetic

being (C02), pro-

modeled.

The kinetic

carbon

with water using

(H20), carbon

and hydrogen gram. 5 ses

(H2) are directly

the GASKET

thermochemistry

The reaction

rates are extremely

sensitive in

to temperature. erosion will

Our analyresult at

show

a two-order-of-magnitude film cooling conditions in

reduction

total

the throat when Boundary results viscous gral

is assumed. the thrust fluid chamber dynamics were calculated using coupled energy the with inte-

of the FLUENT flow boundary

computational

(CFD) analysis by the momentum

layer solutions

calculated

technique

(MEIT). 6,7

The CFD analysis

was used to predict fuel

the reduction injection at

in the gas temperatures the manifold. gas temperatures thrust chamber

at the boundary

layer due to annular show a significant a 2,478K (4,460R)

The results

of the analysis ranging from

reduction reduction throat. performed

in the at the

at the wall to a 1,144K material

(2,0600R) ablation

reduction (CMA) mixing

at the nozzle analyses chamber. were

Charring, locations

and

at

five in

in the nozzle

and combustion

The oxygen

content

Aerotherm Graphite Surface 1978, AFRPL-TR-78-77. Creare Incorporated,

Kinetics

Computer

Program,

Version

B, December

"Fluent

Manual,"

Version

2.9, TN-369,

Rev. 3, 1987.

7.

Momentum/Energy

Integral

Technique,

July

1978, AFRPL-TR-78-53.

38

the

combustion

gasses flame

is three

times

what in

is present of

in conventional (6,460R).

solid In the

propellants absence cally the with of

with film

temperatures wall

excess

3,58gK are

cooling, environment The

component

materials

subjected glass

to a chemiused in

reactive liner.

resulting

in erosion

of the

fibers

MBA

analysis fuel

performed injection,

in the combustion there will

chamber

shows of

that the gas

film

cooling

and

be minimal using

erosion

glass MBA. generator The ratio ratio wrap of

Our point design effluent.

is dependent

on film cooling

unreacted

effects 1.7;

of

film the

cooling static

are

no

longer

significant

beyond

an

area

however,

temperature

drops

sufficiently MBA.

at an area over-

of 2.9 forms

to allow transition exit cone at an

back to the glass area occurs ratio of

The composite minimum between

the

5.7.

The

predicted the carbon/

thermal carbon 2.4.3 The central ters by

margin insert

of safety

of 3.15

at the transition

and the quartz/phenolic Desiqn (Figure of 21)

MBA.

Injector injector dome an

consists

of

the

thrust along

chamber their

dome common

and

the

segment oxidizer

the gas generator, plenum.

Joined

perimefrom

supply

Fuel-rich chamber

combustion

products tubes.

pass

the gas generator is 3.9 centimeters and lower dome

into

the thrust

via 500 injector and passes

Each tube

(1.55 inches)

in diameter ports

through

both the upper pressure (doublets)

elements.

The fuel

are designed chamber dome,

for a maximum eight pairs

drop of 0.38 MPa (55 psi). of oxidizer port is injectors

In the thrust about

are spaced (0.131 of

each

of the fuel ports. and

Each oxidizer for a

0.33

centimeters

inches) 1.72 MPa

in diameter (250 psi). streams is angled port

is designed of

maximum ports

differential is angled

pressure

Each pair for ligament

oxidizer and

for self-impingement the doublet the fuel

of the pair

breakup

atomization. of gases

In addition, out of

inward toward the

the stream oxygen is the A

flowing

injector the fuel

so that Since selected

atomized

stream

will

impinge warm

and mix with 1,278K

stream. at the with

the fuel mixture

stream ratio,

relatively finely

{about LOX will

(2,300R)]

atomized

vaporize thermal

and react loads

the fuel-rich injector

gas stream. that

preliminary specified A more

evaluation mixture ratio

of

on the

indicate will

at the

and LOX pressure, will

the oxidizer

remain

a liquid. design

detailed

evaluation

have to be completed

once

the injector

has been finalized.

39

Refer to Schematics A and B.

Schematic A Gas Generator Side

Schematic

I I

Oxidizer

.....

kl
3,3 mm

_--1--,___,_er-_i_'
38.1 mm Thrust Chamber Side

_--NI.NN

Figure

21.

Injector

manifold

desien.

40

The be

fuel

ports by

at the outer ports.

periphery This

of will

the injector provide a

manifold zone of

will

not

surrounded

oxidizer

combustion of gas cooling in the

products

along the wall of the thrust chamber. and for cooled oxygen concentration near

The resulting the wall and will

reduction reduce rates

temperature requirements ablatively

the regeneratively chamber. Previous

cooled

chamber with

erosion

experience

film cooling

of this type

has demonstrated

only minimal

penalties

in combustion the injector pressure

performance. B ports is designed to be

The flow of the gaseous subsonic. This unchoked

fuel through allows

injector

changes

in the thrust chamburning

ber to be communicated rate is a function pressure,

to the gas generator. the fuel

Since

the gas generator is controlled

of pressure, which in turn

flow rate

by adjusting speed

chamber

is accomplished

by varying

the turbopump

and, thus, the LOX flow rate. The attachment eratively on the injector area, cooled is fabricated the stainless thrust chamber from stainless steel. At the thrust alloy. coating the chamber

is reinforced attachment The injector to a flange

with

a nickel

The regendeposited

area has a nickel is welded to

copper-based thrust As chamber

alloy.

regeneratively cooled to weigh thrust 1,134

cooled

and bolted the

on the ablatively is estimated

chamber. kilograms The rocket

configured,

injector

manifold

(2,500 pounds) proposed

for both designs. design offers two advantages: (I) and the liquid

injector

fuel

injection can

development using

experience subscale

is applicable; test motors,

(2) injector up.

development Injector program. 2.4.4 A

be performed will

and then scaled Phase

designs

be evaluated

in the acquisition

phase,

2 of this

Combustion preliminary

Stability evaluation of combustion During stability was made to identify

issues that need to be addressed. of the design

the evaluation, benefits:

four characteristics

were noted that will provide

Liquid Rocket April 1972.

Engine

Fluid-Cooled

Combustion

Chambers,

NASA

SP-8087,

41

I.

High-solids-loading damping agent of for the

in the thrust chamber high-frequency fuel-rich gas solid

is known

to be an effective The products are of

instabilities. generator particulates

combustion mately

propellant

approxisize

50 percent-by-weight ranging of

with the particle

distribution 2. The free

from 1 to 400 microns. the gas generator is larger than that for the

volume

thrust

chamber.

This minimizes

the effects

of pressure

oscillations

originating 3. The injector sions low of

in the thrust fuel port thrust

chamber. than the characteristic flow area will dimenthe and

area is smaller This

the

chamber.

lower

dampen

frequency chamber.

pressure

oscillations

between

the

gas

generator

thrust 4. The

oxidizer drop

injection across the

system

has

been

designed

for

25

percent

pressure chamber 2.4.5 An eight The Oxidizer

injector

face to minimize flow rate.

effects

of thrust

pressure Delivery trade

oscillations System study was

on oxidizer

engineering

performed

by

ARC/Liquid

Propulsion

on

systems study was

for the of

storage

and control detail to

of oxidizer make major

for hybrid feed system A.

combustion. selections. Components

sufficient

Results

of the trade

study are discussed

in detail

in Appendix

incorporated 2.4.5.1 zation

into the point design System tank.

are presented

below. was selected for pressuriand a

Pressure-Fed of the oxidizer

- A Tridyne Tridyne

system

is a mixture

of 91 percent

helium

stoichiometric temperature flowed mixture upstream tank. each of

ratio of hydrogen at a pressure

and oxygen. of 68.9 the at MPa

The Tridyne (10,000

is stored When react, Parallel on

at ambient Tridyne producing regulators, is a

and

psia).

through of of

a catalytic and water

bed,

hydrogen 667K

and oxygen

helium the

vapor

(1,200R). head

catalytic flow

bed, rate

establish is modulated (8 inch)

the

pressure

the

oxidizer one in

The oxidizer the four

by four throttling diameter valve supply located valves ignition by

valves, The

20.3 centimeter

lines.

lines

are prefilled and near the

to the normally injector lines Booster

closed

isolation The just

in each feedline in the gas presthe open

manifold. are opened

isolation before

surization oxidizer

outlet tank.

to

pressurize a normally

shutdown

is accomplished

closing

42

isolation tank. The

valve feed

located system

in

the

common sized

oxidizer to provide

plenum

at

the

base

of

the

has been

100 percent

of the required Figure 22 shows a

LOX flow, even with a failure schematic of the delivery of 3,601

of one of the four feedlines.

system. (7,938 pounds) of Tridyne an epoxy is required. resin. a 0.08 The

A total Tridyne wall tank

kilograms

is fabricated centimeters

of IM-7 carbon (7.68 inches) The total and the

fiber with thick and

The tank centimeter (21,701

is 19.5

includes is 9,843 system

(0.03 inch) aluminum pounds) (330 2.4.5.2 given in (tank and

liner.

tank weight feed

kilograms

liner),

Tridyne

weighs

150 kilograms

pounds). Turbopump Figure capacity delivery Fuel-rich 23. Feed System Four equal of to the A schematic were of of the with normal even if LOX delivery each having system is

turbopumps 133 percent required

used, the

a maximum

operating This

operating one of the

requirement. four turboparallel in

permits

LOX flow

pumps fails. throttle the event upstream down. ambient

gases from the gas generator These

are sent through valves

valves of of an the

to power the turbines. emergency catalytic exhaust shutdown. gas

throttle

can be closed valve

The normally

open

isolation

just shutto

generator

is also used a separate

for

an emergency

The turbine pressure

is passed

through

nozzle

and expanded

conditions. system was used for the turbopump to the suction valves (Figure feed system to

A Tridyne provide dyne

pressurization

a constant

head pressure

side of the pumps. 23). Each valve fails

The Triis capable A pres-

is controlled

by two isolation in case

of handling

full gas flow is provided flows

one isolation

valve

to open.

sure transducer The regulator Tridyne

so pressure a normally

in the tank can be monitored. open where isolation the oxygen LOX tank valve through a gas

to

to a catalytic

gas generator

and hydrogen are heated the

react to and is

heat up the helium. steam. connected A second to

The products regulator is

entering provided

the in

helium and

parallel

with

first

a normally this

closed

isolation

valve.

In case

the first

regulator the

malfunctions, malfunctioning ate.

isolation

valve

can be opened,

the isolation will will

valve with

regulator with

can be closed,

and the system systems

continue be used,

to operand the

Regulators

built-in

health monitoring

switchover

will occur

automatically

with no outside

signals

required.

43

Pressurant Bottle

Pressure Sensor

r_

FilWent Valve

Isolation Valves

I
Pressure Regulator

Catalytic Reactor Relief Valve r--i Pressure Sensor

Fill/Vent Valve

r_

Fill/Drain Valve

F-]

Isolation Valves N.O.

]
_] To Injector

Isolation Valves N.C, Throttle Valves

Figure

22.

Catalytic

warm

gas pressurization

system

schematic

for GGILOX.
01gO-HYBRID RPT

44

Pressure Transducer Isolation Valves (NC)

r-_

Fill/Vent Valve

I
Isolation Valve (NC) Isolation Valve (NO) Regulators (with Health Monitoring Equipment)

NO Isolation Valve

Catalytic Gas Generator

Fill/Drain Valve

Throttle Valves

c 1
Solid Gas

I
I

for Ablative T.C. T= Turbine P= Pump Turbine Exhaust

/
I

[_

To Injector

Figure

23.

Prelimina_

oxidizer

pump-fed

_stem

schematic.
0190-HYBRID RP'r

45

Since the fluid to be pressurized liquify oxidizer more and eventually freeze. This We have

is a cryogen, will not create

the steam any

generated until

will the

problems volume

tank is almost empty. to prevent

increased

our ullage

and loaded

oxidizer Oxidizer

entrainment

of the water. inlet and from the pump outlet or to the cooling jacket to

is routed directly (ablative

to the pump

either

the

injector

thrust

chamber)

inlet

(regeneratively A system ablative-

cooled thrust pressure

chamber). is shown in Table chamber 9. This schedule covers the

schedule

and regeneratively design,

cooled provided were

thrust

cases. is driven from the fuelrange

Our turbopump rich gas generator.

by Allied-Signal, required

The pumps

to have a wide

throttling

to supply

the LOX flow rate throughout operating condition. pump and

the burn and to accommodate

a potential is given psia) for

one-pump-out in Table 10.

A list of operating outlet pressure (1,675 is 9.46 psia) the

requirements MPa (1,375

The maximum thrust chamber

the ablative cooled thrust

11.5 MPa

for the regeneratively regeneratively the coolant cooled

chamber. chamber

The

higher

delivery

pressure drop taken contains gas

for

is due to the pressure exhaust from the

through

channels. of the

Since the gas generator separating turbopump pitot, the particulates reliability. filter,

solid

particulates, required this by to using

a method improve

stream

was

Allied-Signal developed

accomplished

a reverse

inertial

and proven

in cooling

turbine

applications.

The reverse the probe

pitot, directed

Figure

24, extends Flow

into the gas flow with entering prevents the probe

the open end of to turn and

downstream.

is forced being

1BO . they

The momentum are separated 99 percent each of

of the particles from the flow.

them from probe

entrained,

A well-designed

will remove would be made

approxione

mately feeding

of

the solid

particulates. The

Four probes probes would

be used, an

the four

turbopumps. manifold

integral be

part of the fuel injector fabricated temperature. The Allied-Signal stage, mixed-flow

to simplify steel

case construction, to survive

and would

from an austenitic

stainless

the moderate

effluent

turbopump

is shown

in Figure

25.

The pump impeller

is a singletip diameter uses tip

design with (9.3 inches impulse

a 22.9 centimeter

(9 inch)

[23.6 centimeters a single-stage,

for the regenerative with a 48.3

option)I. centimeter

The turbine (19 inch)

impeller

46

Table 9.

System

Pressure

Schedule. Pressure 68.8 1.8 1.8 O.B 0.9 (min) (max) MPa

Tridyne

Storage Outlet

Pressure Pressure

at 289K

Regulator Catalytic

Gas Generator

Pressure

Tank Pressure*

Inlet Pressure Pump Outlet Pump Outlet

to Pump (Ablative) (Regen)

0.4 9.5 11.5

Pressure Pressure

*Includes static 0.4 MPa.

head.

Minimum

tank pressure

is

Table 10.

LOX Turbopump

Operating

Requirements.

Maximum

Flow Rate

(kg/sec) (MPa) (MPa)

3,144 0.8 9.5 11.51

Pump Inlet Pressure Pump Outlet Pressure

Turbine Turbine Turbine Turbine Turbine Minimum Minimum

Drive-Gas Drive-Gas

Flow Molecular

Weight 2 Heats 2 Chamber Pressure) (K) (MPa)

13.75 1.12 7.5 392 0.2 1,895 3.5

Ratio of Specific

Inlet Pressure

(Main GG Maximum (GG Chamber (MPa)

Inlet Temperature Discharge Pressure

Temperature)

Flow Rate (kg/sec) Chamber Pressure with (MPa) Pump Out Capability

Four Turbopumps

Single

I. Regenerative cooling version. 2. Assuming solids are filtered out using

reverse

pitot.

47

Gas Generator Exhaust Flow

To Turbine Inlet

Figure24.

Reverse

pitot,

Pump Volute Turbine Inlet Volute

Irope lie r

_ _'_'. -_,)1

_--_--_

Inducer Inlet

66.1 cm

_._--_

Y_____,. __

57.00 cm

__..
.........

_"

,-_ .

r"

..
",

.H.e/ium 7-_ _i==_-

't

--

T_

70.4 cm

_._l

Figure

25.

LOX

turbopump,
0111_III_#D. p-r R

48

diameter. Inconel 3 percent percent Its good

The pump, 718 (77

turbine N,

housing, 15

and turbine Cr, 0.2

impellers percent K-500

are fabricated CO, 7 percent

of Fe,

percent

percent

Al).

The inducer

is fabricated

from Monel percent turbopump

(63 percent

N, 30 for

Cu,

2 percent

F3, 4 percent

s, 2.75

Al, O.g percent weight

Mn)

erosion

resistance.

The estimated

is 204 kilograms

(450 pounds). The design uses foil bearings several rather than conventional ball bearings.

Ball bearings offer stable,

have caused high-speed

failures at

in LOX turbopumps. 9 temperatures In addition,

Foil bearings where ordinary do

operation

extreme

lubrication not have

systems

cease to function and them rotor unique

properly.

foil

bearings with

the

clearance giving

stability

problems

associated

hydro-

static tion.

bearings, Excellent

advantages

in the LOX turbopump for foil bearing for foil bearings

applicaused coolof is

reliability

has been achieved

machines bearing

in other

applications.

The mean-time-between-failures over 60,000 hours.

ing turbines

is typically a Teflon

The foil

are made rubbing

Inconel 750 with likely to occur, ary lip areas. There to ensure

coating.

Silver

plating

is used wherever

such as the labyrinth

seal and at the balance

piston

station-

are several efficient

seals around and safe the

the rotating A from

assembly

of the LOX turbopump seal is used outlet on the

operation. leakage

labyrinth the

impeller pump main

shroud stage effects

to control inlet. of The

high-pressure

to the the

seal clearance hydraulic

is determined load growth. of good

by considering

combined runout, edges seal

static

unbalance

deflection, The number The

vibration of knife

and differential of the labyrinth

thermal seal

and centrifugal the amount offers

control

leakage. ignition occurs

stationary and

land

is plated

with

silver,

which

resistance

reduces

the danger

of burnishing

if localized

contact

between

the knife

edges and the seal land. A carbon wheel, prevents During is face seal near the right as a spring-loaded from journal seal the bearing, during turbine inboard of the turbine This seal

used liquid

static into

chill-down. cavity a finite

oxygen

leaking

during

starts. that

operation,

this face seal lifts off and creates

clearance

g.

Personal AiResearch

Communications, Dr. Los Angeles Division,

Alston L. Torrence,

Gu, Turbomachinery California, August

Systems, 1989.

_9

controls

the bearing

cooling

flow.

Radial grooves

may be utilized

in the face

seal to promote The bearing a drain between

lift-off. cooling the flow is prevented and a from entering the turbine carbon, cavity by

face

seal seal to

helium-purged,

floating-ring inlet of

seal.

Another

floating-ring flow

is utilized

to the right

of the helium

to control the

the helium

the turbine by

cavity.

The finite leakage

clearances rates

floating-ring

seals

are determined thermal

the desired growth normal

and the

effects

of differential

and centrifugal at the 11.

of the components. maximum flow, and during

The performance pump-out conditions

of the turbopump is presented higher

in Table

The flow

rate for the pump-out flow point. chamber pressure of flow

conditions At 7.5 MPa point, tively version. high

is 33.3 percent

than that of the maximum the total gas generator while

the pump-out (1,085 this psia)

condition, is used level and

to drive

the turbine; to 4.3 MPa for

at the maximum for

pressure version

is throttled 5.2 MPa (760

(618 psia) the

the ablacooled

cooled

psia)

regeneratively tip speed. (17,440

Turbine

efficiency the maximum

is limited turbine

by the turbine top speed

To achieve rpm) is 457

reliability,

allowed

meters/second Turbopump booster that duty

(1,500 feet/second). performance cycle, Figure design was 26. evaluated The purpose at of four selected points in the

the evaluation margin.

was to ensure Table inlet 12 prefrom the LOX flow to reduce at

the turbopump

had an adequate The available that will

performance

sents the study results. gas generator A bleed

pressure

to the turbine

is above valve

necessary be located from the

to deliver in the gas

the required inlet is

rate.

throttling The

turbine

pressure.

required

gas

bleed

generator This

estimated

617 kilograms mately 4,990

(1,360

pounds)

for each turbopump. pounds) of extra

translates

to approxithe four

kilograms

(11,000

propellant

to power

turbopumps. 2.4.6 LOX Tank LOX tank booster designs were developed for both the pressure-fed kilograms and turbopump pounds).

options. is:

The total

LOX carried

is 299,700

(660,725

A summary

Mission Requirement FITVC Requirement 2-Percent Reserve Total

281,681 kg 12,143 5_876 299,700 kg

50

Table Ii.

Maximum

Flow and Pump-out

Performance.

Pump LOX Flow, kg/sec Efficiency Required Power, W (x105)

Maximum 786 0.84 70.8

Flow

Pump-Out

Condition

I,048 0.76 104.4 (128.9) I

(87.6) I

Turbine Turbine Turbine Inlet Pressure, Flow, kg/sec MPa

4.3 2 (5.2) 1 7.3 (9.0) 1


0.42 16,000 10.4

7.5 (12.8) I 0.48 17,440

Efficiency Speed, rpm

I. Regenerative cooling version. 2. Throttled down from GG chamber

pressure

of 7.5 MPa (1,085 psia).

8.26 7.57 6.88 Chamber Pressure 2 482 3 A 4 tiP" 2 3


zk

12 11 10 9 8 7 -. E

413 344
2.75

5
2.06 1.38 0.69 0 0
|

Low Mass Flow Rate

4 3 2 1

0 160

20

40

60

80 Time, s

1O0

120

140

Figure

26.

Selected

turboDump

operating

points.
0190-HYBRID-RPT

51

Table

12.

LOX Turbopump

Transient

Performance. 1

Location

on Duty Cycle kg/sec Per Pump, kg/sec MPa MPa 2

PT1 3,144 786 7.5 9.5 0.84 16,000

PT2 2,177 544 5.2 6.5 0.75 12,640 36.0 2.8 0.37 4.8

PT3 2,359 590 5.6 7.1 0.76 13,280 42.0 3.1 0.39 5.3

PT4 1,905 476 4.4 5.6 0.74 11,520 27.3 2.3 0.35 3.9

Flow Rate, Flow Rate Chamber

Pressure,

Pump Outlet

Pressure,

Pump Efficiency Speed, rpm Power, W x 105 MPa 3

Required Turbine Turbine Turbine

70.8 4.3 0.43 7.3

Inlet Pressure, Efficiency Flow, kg/sec 4

I. 2. 3. 4.

Using solid propellant gas generator fluid to drive turbine. Ablative cooling version. Assuming 26.7 percent higher than chamber pressure. Throttled down from chamber pressure. Total turbine flow for whole duty cycle is estimated to be 617 kilograms (I,360 pounds).

The LOX tank is calculated

storage from

requirement the density

is 255 cubic meters of LOX at its

(9,003 cubic

feet). of

This 78K

storage

temperature

(140R), manifold 2.4.6.1

a 3 percent is prefilled Pressure-Fed

allowance

for ullage,

and the assumption (2.0 cubic

the the LOX feed

to the isolation Option

valves

meters). tank was selected

- A filament-wound to minimize with

composite

for the pressure-fed keep the life cycle

LOX system cost

the system the

weight

and, therefore, For the

competitive IM-7 carbon strain 826,

pump-fed

systems. 5,402 MPa

preliminary modulus resin

design, MPa

Hercules

fiber

[strength was

(785 ksi), with two

275,283 systems: will

(40 msi), EPON

1.85 and

percent)]

evaluated

epoxy-based require

polyimide. analysis

Final and

selection testing.

of the A 419

materials centimeter

additional

engineering was selected

(165 inch) tank diameter

to reduce

the length to 1,981

52

centimeters (7BO inches).


(1,793 psia) MEOP based on analysis "twang" included

The tank pressure the pressure of bending shuttle and drop

was calculated through

to have a 12.3 MPa Structural

the system. caused by

the effects by the

loads at the

launch

by the launch the 12.3 MPa

experienced

loads

imposed

(1,793 psia) MEOP. because thrust

Shuttle-type

axial

stiffness

requirements

were not applied at the aft end of designed which

reaction

to the core vehicle than the forward loads is 3.4

is accomplished end.

the hybrid to

booster the

rather

The case thickness (1.36

accommodate a case 27

structural of 9,740 than

centimeters

inches),

yields mately

weight

kilograms a case not

(21,474

pounds). for

This

is approxibending

percent

higher

designed

shuttle-type

stiffness

requirements. LOX tank but it liner materials the were considered. tank fabrication Aluminum process was a primary contributes materials a polyimide

Several candidate, significant such

complicates

and

weight

for a nonstructural and Kapton

member. also

Several evaluated.

elastomeric Upilex,

as Upilex,

Teflon,

were

film, was selected range Upilex mandrel The (140R) of thermal

because

it has good elongation A thickness

properties

and can meet the centimeters of

requirements.

of 0.008

to 0.01

is estimated before

to be adequate.

The liner will tank. cryogenic the flight, The tank

be layed up on the winding

manufacturing tank will

the oxidizer experience During

composite

temperatures pressurization wall

down

to

78K

due to the LOX storage. will using replace ARC's on the

gas at 667K rise was

(1,200R) calculated maximum

oxidizer.

temperature The

trapped-gas the inner

thermal wall

response

model. 10 which

predicted within

temperature

is 439K

(790R),

is well

the capabilities

of the composite. LOX tank branch will be monolithic exhaust boss. with port steel polar bosses. The Preswill be

The composite LOX feedlines will

off

a single the

in the

aft boss. baffles

surization integrally 2.4.6.2 porates

lines wound

will

enter

forward

Anti-slosh

into the case. Option - The point LOX tank. design for the turbopump option incorand

Turbopump an

aluminum-lithium

Aluminum-lithium

offers

weight

10.

Spear, G. B., Developed by ARC in variable heat loss due to mass flow.

1982

for

gas

generator

modeling

of

53

strength also more loads the wall 0.73 as

advantages expensive. the was

over

conventional

aluminum

fabrication;

however,

it

is and

The tank was sized using tank, with the

the same general that

dimensions

pressure-fed assumed at the

exception

the pressure analysis (0.11

within a and

tank

to be 0.5 MPa

(75 psia). of 0.29 bottom.

Structural centimeters A 434

yielded

thickness centimeters

top of the tank at the

inches) (171

(0.286 inches)

centimeter

inch)

tank diameter and reduce

was selected

to improve The

the overall estimated

packaging

of the components is 4,213 kilograms

the booster

length.

tank weight

(9,287 pounds).

A liner is not required

for this

application. of the tank, three monoThe second spot-

For the manufacture coque options first option welded, option were

of the cylindrical as applicable

section based

identified

on Boeing's

experience. The uses

incorporates

a spot-welded, internal

internal

"Z" stringer. The final option

has a laser-welded external

"L" stringer. stringers,

trapezoidal

hat-section

Figure 27.

Four 56' x 11' Machined or Rolled Panels/'


#/ /

Single Piece Spun End Domes


I

;;I T

14.6 m 19.8m

Spot Welded Internal Stiffners

Laser Welded rnal Stiffners

_ / y

Spot Welded ( External Stiffners

Figure

27.

Aluminum-lithium 54

LOX tank desien.

2.4.7

Thrust

Vector

Control thrust vector control were evaluated for the

Three methods hybrid booster

of performing

design: injection.

(1) thrust Large for

chamber

gimballing; angles

(2) nozzle

vectoring; are often rocket by

and (3) fluid required boosters. to

vectoring

(8 to 10 degrees) a pair could of

compensate

thrust between the

mismatch hybrid

between

solid

"Thrust

mismatch of

booster In

pairs

be corrected The as to

differential deflection geometry range.

throttling requirement,

oxidizer by

either of

booster. such two

remaining vehicle degree

driven

a number shift,

factors in the

core three

and

center-of-gravity

(C.G.)

is

Gimballing boosters, flow cannot

of

the

thrust

chamber,

commonly in the

utilized hybrid

In

large design.

liquid The

be readily

incorporated

booster

of large volumes the design

of hot gas from the gas generator of a gimballed approach is thrust chamber.

to the thrust

chamber

complicates

Due to the complexity consideration. such angle as the

of the design, Vectoring shuttle bility.

the gimballed of the nozzle

was excluded practice

From further in large

common large

SRBs

SRB, because While this

it provides approach

(9 to 10 degree) to the

deflection booster based

capait

is applicable

hybrid

design,

adds weight data. Fluid of

and cost

to the design

and reduces

reliability

on historical

injection angle nozzle

thrust and

vector

control

(FITVC)

can provide

2 to 3 degrees reliability TVC

deflection vectored

potentially This

provides concept

higher was

calculated

than

designs.

pursued

as our baseline

approach. Since undefined, purposes reviewing the overall vehicle could configuration, not be absolutely including defined core vehicle, is For by

TVC requirements of sizing an FITVC shuttle

at this time. was established

system,

a set of requirements and compensating

typical

SRB duty cycles

for the elimination are summarized conceptual

of thrust mismatch. in Table design. 13. These

The assumed requirements

TVC system design were used

requirements basis

as the

for the

55

Table 13.

Hybrid Booster Performance

TVC Design Requirements

Requirements.

Maximum

Thrust

Deflection

(deg)

3-5

Dynamic Response - Frequency Response (-3db) (Hz) - Slew Rate (deg/sec) Resolution Duty Cycle (deg) (deg/sec) Program I. 2. 3. Design Priorities

4 5 0.05 150

Safety/Reliability Cost Performance

Early used

emphasis

in the

study

centered

on

the

choice were

of

injectant

to

be

for the

system. 11

Three

injectant

candidates outlet;

evaluated fuel

for feasibled from

bility: off

(1) LOX

bled off and

the turbopump

(2) solid

exhaust LOX bled

the gas

generator; and solid

(3) a hybrid approach exhaust bled from

that combines the gas

the turbopump mixture ratio.

fuel

generator

at a fixed three kg/sec

Figure

28 shows

the injectant booster

usage

estimates rate of

for the 3,969

candidates

assuming

a total

hybrid

mass

flow

(8,750 Ibm/sec), (3,500 Ibm/sec) Although the most

corresponding

to 80 seconds kg/sec

into the duty

cycle

[1,588 kg/sec 1.5:1 MR)]. approach LOX-only is and

fuel flow, 2,381

(5,250 Ibm/sec)

LOX flow, FITVC by

all three injectants in terms of

are effective, propellant

the hybrid followed

efficient

usage,

fuel-only, cal data

respectively. for secondary

The propellant injection

usage

estimates Figure

are based 29 shows

on empiriof

systems. 12'13

the ratio

11.

W. G. Koch, "Design Concepts for Liquid Injection Thrust Vector Control, Part 1 - System Considerations," Hydraulics and Pneumatics, September 1965. Personal Communication, Burgunder, A. T., Fluid Systems Signal Aerospace Company, Tempe, AZ, August 1989. Nogues, P., and Mazond, M., "Values Asservies Par Injection Secondaire Liquide". Pour Division, Allied-

12.

13.

le Pilotage

d'un

Engin

56

800 Main Flow 3968.9 kg/s 603.3 m600 523.9 682.7

i_ 400

293.9 258.1 269.9

[]

Deg 3Deg 5 Deg


1

I_-

200 75.3 83.5

Hybrid

LOX only UTVC SiSera

Fuel only

Figure

28.

Comparison

Of iniectants

with three maximum

nozzle

deflections.

0.09

0.08 0,07 0.06 _. 0.05

=-

0.04
"6 '_ 0.03 0.02 1 0.01 0
I I I I I I I

0 0.16

0.02

0.04

0.06

0.08

0.10

0.12

0.14

Ratio of lnjectant Mass Flow Rate to Main Flow Rate

Figure 29.

Hybrid engine FITVC performance

(liquid oxy_ gen iniectant).


0190-HYBRIDRPT

57

side-force-to-main LOX force larger system become when injectant. ratio thrust design

thrust versus This

injector

mass flow rate-to-total the thrust of deflection an

flow for the angle system and at

relationship the

between

illustrates deflection

increasing This

inefficiency characteristic

FITVC the

angles. (I) at

impacts

injectant

in two ways:

large deflection port at each the main

angles, injector

the flow rate may location; and (2) 16 is LOX

too large to have only a single the deflection of the LOX angle is

5 degrees, for Thus, the

inJectant propulsion

flow

approaches which using

percent

requirement

system, angle

impractical

for TVC application.

a practical

deflection

for the hybrid application The injectant approaches cost, control require

is 3 degrees. is shown in Table 14. The fuel-only in additional would fuel/LOX and hybrid complexity, a second ratio,

trade study hot-gas

control

valves

resulting

and design valve

risk.

In addition, a means

the hybrid of monitoring

system the

require mixture

for

LOX and

both of which

impact reliability. to be the best and choice for an injectant because it offers usage) a

LOX appears system that

is simple

low cost,

with

performance

(injectant

close

to the hybrid FITVC approach. The major point design design implementation study are decisions necessary 15. in defining Each better an FITVC deci-

for this

summarized

in Table

of these defined.

sions must

be reviewed Table

as the system 14. FITVC

requirements

become

Injectant

Trade Study Hybrid

Summary. LOX Fuel 1.14 to 1.30 Medium Medium Medium

System Injectant Dry Weight Reliability Cost Usage (Relative to Hybrid)

1.0 High Low High

1.05 to 1.15 Low High Low

Conclusions 1. Fuel-only system can't win. 2. Lower flow rate of hybrid probably doesn't offset system advantages for reliability and cost. 3. Focus on LOX-only system design.

LOX-only

58

eE E x O I._J .E rE >_ eE _ O I.O E I e.O U cO I::: O 11,-"O u_ C: o U eO 1.3 O r,.e{J 0


p...

QJ I.l.0

O
"9""

I:::

c O

4_ O

o u_
_ 0 U

O O I-.

o
u r=_ o
.f=-

O QJ "o O 4_ u E QJ

C
1i-

.=.1

V_

C-,'-,-_0

O _

u O

e-

"

_J

eO e-

e-

I_ c E E_ E >_'o _.j v1 QJ c_

I..

u O _J

4_

4,_-e- O

_-

"_ O vt _--N
_

r.N
o_'=-

i,_ _

_" {.j

0 vI .._
_ o_=-

_
4.a ._E

o
r-

_E

_E

QJ > QJ

rul.l_

_J

,,3.-o

_ e._ eo
0

O 0
o_ O

c x e'_ N _ N _ _YC_ O o 0 o. G/ e'-

G)

0 4_ U vl le- rl-- o

_"I',-N

_ S,_ O _

O {J 4_ U ,,_ o I._ o = e0 ,.'"o

O E xu_E E _

_J _" _J ,-*r-

_ I_ ,-_J

I-I.O_ U*,_O

_ ,=*_

O _ IJ _

I.O _J

IO

__I _"

1.0 0 I.-

QJ_J

59

Figure consists feedlines with of

30 is a schematic eight

representation controlled manifold.

of the FITVC injectors Each of the

system.

The system through four

independently injection

supplied injectors

by the fuel source

is supplied (primary) of

a constant

of LOX at a controlled that the primary

pressure

by the four

turbopumps. supplying

It was assumed the required

turbopumps

have the capability

LOX to each of the injectors design sizing

at design

flow conditions. is shown the nozzle in is

The FITVC Table given 16. A

conceptual sketch 15. of

and performance FITVC integrated include: fluid.

summary with

the conceptual

in Figure

Key features as the servo

of the design actuator

LOX is used

working piston

Simple one-piece Stepper

pintle/actuator

design. produces 150:1 force

motor-controlled

servo-actuator

amplification. Integrated Head pintle/slide with valve design toroid reduces package size/weight.

loss minimized injector

feed manifold

and collimators. with nozzle. 17. The weight (aluminum assumes a

Self-housed

assembly

easily system of The

integrated is shown

A weight estimates bronze)

estimate

for the FITVC density

in Table (0.10

assume for the

an average injector

2.8 gms/cm 3 feed

Ibm/in 3) estimate

assembly.

line weight power

7.8 gms/cm 3 mated

(0.28 Ibm/in 3) density.

Electrical

requirements

are esti-

to be 40 watts per injector, The LOX feedlines for the (26,770 designed approach.

and the accuracy will be taken duty

of the system off the of

is estimated manifold.

at 0.1 degrees. The total

injector

LOX requirement kilograms were

baseline pounds). using The

cycle

150 degrees-seconds

is about 12,143 The valve

injectors

a pintle large

valve

controlled flow forces

by a slide typically to actuate used in

"follower

servo"

pintle

experienced the injector

in an FITVC system dictate pintles. Traditionally, of their

the use of a servo mechanism hydraulic inherent actuators have

been

these

applications

because

high-force/low-electrical LOX can be used This approach actuator for

power

capability. tor working injector

In this fluid

application, of

high-pressure

as the actuasimplifies power the

because

its availability.

design

and eliminates design

the need for a separate were examined

source. using "open

Several LOX. An

servo

approaches design

feasibility (the

"open center"

valve

was considered

for simplicity

60

Table 16.
_r

FITVC System Sizing/Performance

Summary.

Injectant Maximum Mass Thrust Deflection (deg)

Liquid Oxygen 3 at maximum thrust

Flow Capability

(kg/sec)

(at 3) Pintle/Seat * Design

355 (per injector) 391 (system)

Seat Diameter (cm) Maximum Stroke (cm) Piston Diameter (cm) Pintle Loads (N) Design

9.7 2.8 13.7 22,686

(maximum)

Nozzle

- Seat Angle (deg) - Nozzle Diameter (cm) * Collimator Design

60 (includes 7.9

angle)

- Number of Holes - Hole Diameter (cm) * Slide Valve Design - Diameter (cm) - Stroke (cm) - Valve Load (N) * Stepper * *
_r

12 2.0

2.54 _+ 0.06 44.5

Motor Design 15 0.5 216 0.11 40 12.7 Nozzle Area Ratio = 0.33

Step Size (deg) Acme Screw Lead (cm/rev) Stepping Speed (steps/sec) Stepping Torque (Nm) Electrical Power (w/injector) Diameter (ID) (cm)

Feedline Injector System -

Axial Location

Performance 38,78B @ 5.5 MPa supply 4 5 0.1

Actuator Force Output (N) Frequency Response (Hz) Slew Rate (deg/sec) Accuracy (deg)

Fill Port Turbopumps

Injectors (8) Slid L02 Inlet

Vent Port

Figure

30.

Hybrid

booster

Droeram

FITVC

schematic.

Table

17.

FITVC Weight

Estimate

Summary.

Item Feedlines/Mounting Injectors Misc. Mounting System Total Hardware Flanges

Weight (kg) 130 41 43

Quantity 4 8 -

Total (kg) 519 330 43 892

65

center" valve

approach leakage

requires

no seals

in the valve the pintle using

porting during

area). closed

The quiescent conditions. A

could

be used

to cool servo"

stepper-motor-driven selected usage. feedback 2.4.8 2.4.8.1

"follower

a linear

slide

valve

was finally power

for the conceptual This approach

point

design

because without

of the

low electrical

can be implemented further simplifying

the use of a pintle

position

transducer, Ancillary Launch

the design.

Components Truss - A truss-type and the ability the launch pad support to retract system from can was chosen the rocket

Pad Support

to provide motor exit

structural cone during

efficiency launch.

Because

support

be retracted

and remain The meters

on the pad, truss

launch weight was sized

is reduced. with a top at inner diameter of 386 centi-

structure and

(152

inches),

an outer

diameter

the bottom

of 635 centimeters (see Figure length, 15,

(250 inches). Page 33).

This provides Each strut is

ample clearance 254 centimeters centerline was

for the exit cone (100 axis, inches) in

angled to

45 degrees adjacent of thrust strut

relative

to the motor

and 60 degrees

relative

struts. with in

The strut support a safety factor of The

sized

to withstand kilograms each

13.3 x 106 Newtons (60,000 pounds) strut steel was made on of

1.6 or 27,216 analysis

each

the

structure. D6AC steel

assumed

1,514-MPa The

(220-Ksi)

or an equivalent-strength

or composite. area to withfor the strut strut that

truss required

3.8 centimeters 2 of material load. buckling The Euler buckling did not occur.

cross-sectional was solved in

stand the required radius radius a to ensure

equation This

resulted on mode

a minimum showed

of 7.8 centimeters (6

(3.08 inches).

A check with

buckling

15.2 centimeter

inch) diameter

strut

a O.2-centimeter

(O.08-inch)

wall was acceptable. 2.4.8.2 fer Aft Skirt and Thrust Transfer Rinq - The aft skirt the launch and thrust transand also

ring must this

withstand

the truss

load from

pad support

truss

transfer withstand to the

load into the composite loads

wall of the booster.

The ring must of each must

the out-of-plane vehicle. The

introduced

by the attachment vehicle attachment

booster transmit

core radial, ring

booster-to-core loads. fitting

axial,

and circumferential is designed as a

The bulky

fabricated

from

D6AC with

steel,

and

is

to accommodate

the stress

concentrations

associated

the attachment

63

of struts and pins.


force in (l-inch)

and due to the geometry needed to make this attachment with sockets Each individual
the pin vertical is required strut applies in thls 27,216 kilograms strut. It (60,000 A pounds) of direction for line with the 2.54-centimeter a calculated

application.

provides

safety margin

of 3.14 with

a 1,101MPa

(160 Ksl) pln strength. to withstand the boosterradial

The I-beam-shaped to-core at attachment

portion

of the rlng is sized are based load, and

loads. of

These axial

on ASRM and are 98.7 Newtons Z6.7 x 104 Newtons I beam load using on was the

8.8 x

106 Newtons to the

circumferential sized using the ring. is

load 98.7 The

relative Newtons

booster which

centerline. is for the this

The

radial

load

dominant load,

interface

calculated

bending

moment

Roark's

formulation,

451,600

Newton-meters. I beam for the the ring with a 20.3-centimeter is will 184 (8-inch) depth, (72.6 the required The moment I beam

For an of inertia of

section fitting

centimeters a flange

inches). of

portion

have

thickness

1.1 centimeters The weight The weight must be

(0.45 inches) of this

and a web thickness will portion be 46.2

of 0.8 centimeters

(0.3 inches). meter.

portion

kilograms

per circumferential

of the fitting

of this ring

(struts from pad and core

vehicle)

added to this weight. 2.4.8.3 Recovery is System - The option to reduce of recovering LCC by reusing some or all of the booster high-cost, refurbishable booster chamber,

components components. worth

motivated

Based on examining include

component

costs,

the items

on a hybrid thrust

recovering

turbopumps,

the regeneratively

cooled

and heavywall

metal tanks. recovery of options, 12.2 a saltwater landing (40 was selected with a

To investigate terminal loads, impact

velocity

meters/second

feet/second). were

Impact in

floatation

system(s), reliability

and saltwater was

contamination After

all included

trade decisions; tial options was assembled, Recovery laminate involved was with

not evaluated. and pressure-fed

analysis

of all poten-

for recovery Table 18.

of pump

concepts,

a set of options

of a composite strengthened

tank was

Judged

to be unacceptable. the impact loads,

Even the

if the effort water

sufficiently

to take the tank

inspecting/refurbishing exceed

for delamination

and/or

absorption

would probably

the cost of a new tank.

64

Table 18.
Pressure-Fed Composite Full Partial Metallic

Recovery

Options.

Pump-Fed Composite Metallic

X (Recover Engine Component Only) X X X

X (Recover Engine Component and Gas Generator) X

None

The only the thickwalled cost advantages

item of value metal

in the pressure-fed tank,

system worth

recovery

would

be The

oxidizer

if it was to be used using

in the design.

of this approach systems use

can be modeled

the shuttle tanks.

SRB cases. of of

The pump-fed large pressure

low-pressure tanks tend

oxidizer

In the absence and not capable

loads, impact thrust

these loads. chamber)

to be

lightweight

the sustaining tively cooled

The high-value would be worth

components recovering. together

(turbopumps, Our design

regenera philoso-

phy was to physically the rest. Several recovery

group these

components

for recovery

and discard

concepts

were

explored.

A recovery in Figure

technique

for reuse a method bladders, of are to

of the grouped of keeping the

high-value reusable with

items, components

illustrated dry,

31, provides valves,

and avoids The booster hybrid

complex

and seals associated parachutes structurally impact housed tied

some concepts. nose aft cone end after of

is slowed by a series Risers, the which booster

in the to the

burnout.

the

booster,

reorient

in a nose-down

attitude.

Solid

retrorockets

in the aft skirt are fired (40 feet/second). flood yield the a The end dif-

to slow the impact Ports are opened tank. stable The

velocity

to less than tank;

12.2 meters/second are designed

in the oxidizer

these

to rapidly locations the water or lift

resultant

center-of-gravity/center-of-buoyancy with the aft end well-above tow the entire Recovery vehicle system

floating ship tank

configuration would then

line. aft

recovery while ferent the

either

the

is separated

and sunk. 19.

weights

for the

options

are shown in Table

65

_ -,._, _

Deploy pilot and 48,768 m

_.''_1_'.,/,._'._____,

Deploy main chutes

drogue chutes at

,'
Recovery aids deployed Engine system remains dry

J
Retro rocket fires at 61m retarding decent to < 12.2 m/s LOX tank floods further retarding impact and stabilizing vehicle

" Y'e?ee "'2os:,o,


water impact Forward LOX tank dome opened Vents at aft LOX tank opened

Figure

31.

Recovery

scenario.

17793

q
I =IcJ1 Minimum 0 J1 Maximum

1334.5
o
v-X

A Thrust

z 2

889.6

444.8

O.OOe+ 0 0 100 Time (s)

200

Figure

32.

Predicted

thrusttrace

full-size

booster.

66

Table

19.

Recovery

Systems

Weights.

Item Pilot chute Drogue (kg) (kg)

Metallic Tank Pressure-Fed 13.6 997.9 3991.6 861.8

Composite Tank Pump-Fed 13.6 263.1 1043.3 226.8

Metallic Tank Pump-Fed 13.6 385.6 1814.4 385.6

Chutes

Main Chutes Retrorockets

(kg) (kg)

2.4.9 Each thrust was

Performance full-size the

Predictions booster was burn TRANSV was to designed time. to provide of 15.1 x 106 Newtons of

over

120-second the

Performance model for

the propulsion by ARC to for

system solid

predicted

using The

computer modified chamber

developed the

propellants. 14 (I) burning surface rate

model

hybrid

simulate: burning the

sensitivity

pressure;

(2) instantaneous

area;

(3) LOX flow rate calculated and maximum for

interaction;

and (4) pressure is given by in Figure the SOW (3

drop across

injector. with tion). shown MEOP, in was the

Thrust minimum Model

by the model values chamber The a

32 and compared percent and variaIsp are

provided

predictions 33

pressure, maximum

mixture expected

ratio,

Figures

through by

35.

operating

pressure, to the

determined calculated with

adding

3 percent

manufacturing

variation

prediction rate

at 306K (551R). fuel batch-to-batch

This variation processing; throat

is dominated it is also and fuel

by burning of

associated

comprised

variations The mixture

associated ratio the

with grain

dimension,

area, at

properties. values and

and theoretical using a

Isp are maintained of grain

near-optimal

throughout throttling The

flight

combination

geometry

tailoring

of LOX flow rate. gas generator bore the grain is a center-perforated configuration slots with a

78.7-centimeter spaced around

(31 inches)

and eight

lO.2-centimeter-wide slots are

equally with a

circumference.

The

overcast

14.

TRANSV: Transient Internal Ballistic Prediction program; ARC developed; provides pressure, mass flow rate, thrust predictions in three calculation phases, ignition, steady state combustion, tailoff.

67

8.26

6.88

5.51

4.13 2.75

g
1.38

25

50

75 Time, s

100

125

150

Figure

33.

The predicted

chamber

pressure

for the full-size

booster

erain

design.

1.6 1.4 1.2

0.8 _ 0.6 0.4 0.2 0 0 25 50 75 T/me, s


100

125

150

Figure

34.

The predicted

mixture

ratio for the full-size

booster

grain design.
O190.HYBRIDRPT

68

3432.8 2942,4 _ 2452.0

"_'_

1961.6

1471.2 980,8 490.4

25

50

75 Time, $ impulse

100

125

150

Figure

35.

The predicted

vacuum

spec(fic

for the full-size

booster

grain

design,

16 Speed

14

12
907.2 725.7 544.3 362,9 181.4
! !

10 " 8-

O"

0.2

0.4

0.6 Time, =

0.8

1.0

1.2

Figure

36.

Turbopump

start-up

characteristics,
0190-HYBRID-RPT

69

2.5-centimeter-thick 2.5 centimeters/second. to stabilize to

web

of

igniter that

propellant

with

burning

rate

of

To ensure of the

LOX flow could fuel,

be established used LOX the

quickly

combustion the

gas and

generator start-up curve

ARC

combustion rate at

model

examine is shown

ignition 36.

transients. was calculated

flow

start-up

in Figure

The

using

the turbine

inlet pressure,

pump speed,

and head pressure

at the injector.

This predicted thrust and are the than

LOX flow rate was input to the TRANSV model pressure given in in Figures 37 and 38.

to predict

the start-up thrust

Steady-state The of

and pressure exceeds less

established 2.1MPa (300

approximately psia)

I second. limit

chamber the gas

pressure generator

extinguishment

0.3 seconds During sonic,

after ignition. normal operation, gaseous fuel flow through to the injector is sub-

allowing

pressure

changes

in the

thrust

be transmitted is only

to the gas higher in

generator. than the

Further,

the gas generator pressure. and thrust without flow

pressure

level

slightly

thrust-chamber

When chamber LOX flow

LOX flow decreases.

is terminated, The predicted the gas

pressure

both the gas generator ator still sure) port pressure with

gas generwould pres-

and

(assuming below of

generator

burn without is shown flow area in

oxidizer Figure

at pressures sizing

the extinguishment fuel is

39. in

Proper a gas

the cumulative pressure fuel that to

injector below the

will limit Fuel 40

result of the

generator the

extinguishment oxidizer funding. tested flow.

fuel.

Thus, was

ceases under

burn

without IR&D

extinguishment shows the burning

demonstrated of the

corporate 399

Figure

rate

ARCADENE

formulation to meet

as a function

of pressure.

This

formulation below

was not tailored (500 psi). at a number of

the hybrid

requirements shutdown the

but extinguished of the booster computer be not

3.4 MPa

Emergency the flight assumed

was simulated model.

of points LOX flow was In

in was not

using

hybrid to

The termination (turbopump for our

for this because

analysis it

instantaneous be quantified

spool-down design).

considered instance, thrust

could

every of

this termination

resulted combustion. in Figures

in the immediate The results 41 and 42.

and total

termination

and gas generator are provided combustion the pad-abort

from one of these the termination

shutdown of gas

simulations generator to meet

While

is not a requirement requirements: levels

under

this program, will

it was addressed shut down

the booster

automatically

on the pad if LOX flow rate up grain is exhausted.

are not established

by the time the start-

70

FOLDOUT

FRAME

/-

1423.4

1245.5

1067.6

889.6

711.7

533.8

355.9

177.9

0 0

0.4

0.8 Tim_s

1.2

1.6

Figure

37.

Predicted

start-up

transients_full-size

booster.

FO v _r ..... 6.88

5.51

4.13

2.75

1.72

0.4

0.8 Time, s

1.2

.6

Figure

38.

Predicted

start-up

pressure

transient

full-size

booster.

10.32

8.60 6.88 5.16

3.44

Combustion Limit

1.72 Without LOX Flow


I I I I

25

50 Time, $ Figure 39. Gas generator

75

1O0

125

oressure.
01gO44YBRIDRPT

71

/
/-

0.6 0 0.5 "_


<.l

0.4

Q:

0.3

0.2

0.1

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0 10.0 11.0 12.0

13.0

14.0

Pressure, MPa Figure 40. Burning rate vs pressure.

FOLDOUT

FRP_ME
1601.4

1423.4

1245.5-

1067.6-

889.6 -

711.7-

533.8 -

355.9

177.9

0.4

0.8 Time. Emergency_

1.2 s shutdown

1.6

2.0

Figure

41.

thrust.

8.26

6.88

5.51 q 4.13

2.75

1.38

40

80 Time,

120 $

160

200

Figure

42.

Emergency

shutdown

pressure.
0 lgo-t'-P/BRIDRPT

72

To conclude generator hybrid.

the full-size The hybrid

evaluation, booster

Boeing

"flew" the turbopump-fed 414 centimeters lift-off weight

gas

was nominally with a gross

in diameof 564,859 case, nozzle was were

ter and 4,681 kilograms.

centimeters

in length,

The booster

had a carbon/epoxy silica phenolic, vector point control and

(IM-7/EPON

B26) gas generator ablative

aluminum-lithium with fluid to

LOX tank, thrust

monolithic-braided (LOX injectant). shuttle and

injection their

The booster tank

"flown" "flown" 2.5

separation

the miles

external

to low earth orbit

(150 nautical

at 28E).

Quarter Besides

Size Point Design the full-size design point a design developed having eight between mixture above, ARC was the required of to the a

develop full-size core

point booster.

for

booster

one-fourth boosters the

thrust

In this configuration, provide a comparison design

are mounted and

around

vehicle. designs,

To

quarter-

full-size expansion the

booster

chamber

pressure, between of the

ratio, This

and nozzle

ratio were design while

held constant since scaled many

the two sizes. major Many design

approach

simplified

effort others

parameters of the

remained

unchanged were

directly.

features

full-size between

booster

retained are: hybrid

for the quarter-size

design.

The differences

the two designs of the eight

(1) the core vehicle boosters on the pad;

supports

its own weight

and the weight truss are

(2) the launch pad support for the booster

is not required; relieved since

(3) bending there

stiffness

requirements

case

is no launch (5) only

"twang"; one

(4) a single diameter is used per

was selected (no

for the entire and

booster;

turbopump rate

booster

redundancy);

(6) the propellant

burning

and pressure

exponent booster.

were

reduced

to compen-

sate for the reduced Layout drawings in Figure 43.

grain web of the smaller for both the pressure-fed weights

and turbopump

options

are given and turbo-

A list of the component is provided in Table 20.

for the pressure-fed

pump options 2.5.1 The full-size (0.32 (0.50

Gas Generator gas generator fuel formulation was identical to that used in the

booster,

but the burning at 6.88 MPa

rate was reduced (1,000 psia)

to 0.81 1.27

centimeters/second centimeters/second formulation or

inches/second) inches/second).

from

This

is accomplished size,

by tailoring

the fuel

such as changing

oxidizer

particle

decreasing

burning

rate catalysts,

_3

Pump

Fed Tridyne Tank Wall IM-7 Valve LOX Tank

Pressure

Fed

Gas Generator Lnk LOX Tank

1341 O 252.5 Aluminum-Lithium Case

1369 Composite 0252.5 Case

3088.6

t Gas Generator Wall IM-7 O 257.6 LOX Feed Line (2 pl) Igniter Igniter Gas Generator Wall IM-7

e 59.7

Injection

Plate Valves

Valves Turbopump Nozzle

L.j

o 231.1

Nozzle

Note:

All dimensions

are in centimeters

Figure

43.

Ouarter

size booster

desiens.

74

Table 20.

Quarter-Size Vehicle (Pressure-Fed).

Weight

Breakdown

Pressure-Fed Subsystem Gas Generator Element Propellant Case Liner/Insulation Igniter Weight (kg)

Pump-Fed Weight (kg) 53,725 1,247 252 11

52,478 1,227 249 11

Oxidizer System

Delivery

LOX Tank Feedlines

74,925. 2,946 i 73

74,925_ 943 z 24

Pressurizing System

Tridyne Tank Liner Catalyst Plumbing

Bed and Valving

891 2,136 41 75 34

278

980

Thrust

Chamber

Injector Chamber

Manifold

204 1,877

204 1,458

Ancillary Components

TVC External Insulation Interstage Nose Cone Skirt

249 1,004 304 298 726

249 1,004 113 298 726

Total Weight

139,748 (308,0911bs)

36,437 (300,792 Ibs)

Io

IM-7/EPON

826 carbon-epoxy tank.

tank

2.

Aluminum-lithium

75

using burning rate suppressants. A 25g centimeter (102 inch) diameter grain was selected to maintain similar length-to-diameter ratio between the two vehicle sizes. An impulse efficiency of 92.5 percent and a sliver fraction of
2 percent listic were assumed to In the design. the required ratio. The grain thrust design was tailored the by balwhile ratio is analysis achieve throughout thrust flight

maintaining are given similar meters Figure

an optimum in Figures

mixture

The predicted

and mixture grain

44 and 45, respectively. grain design; grain

The resulting

geometry

to the full-size (26.9 inches),

the center length

port diameter centimeters

is 68.3 centi(350 inches). The total kilois

and the

is 88g

46 shows the geometry propellant pounds).

of each of the two sets of aft slots. for the pressure-fed 1,225 option

gas generator grams (115,694

weight An

is 52,478

additional

kilograms option.

(2,700 pounds) Starter

required grain

to drive the turbopumps may be overcast, weighs 11.3

for the pump-fed or a separate

propellant The gas down from

segments

cartridge and

may be used. is scaled

generator

igniter

kilograms

(25 pounds)

the full-size

igniter. case was designed The resin for an MEOP of 8.6 MPa composite (1,253 psia) used

The gas generator and a safety IM-7 carbon of 1,227 factor fiber

of 1.6.

filament-wound was

case thickness inches) with were

and epoxy (2,704

1.1 centimeters The case

(0.45

{(weight (HTPB as

kilograms glass

pounds)].

is insulated requirements

ARCTIP the

filled

with

microballoons).

Insulation

same

the full-size 50

booster

since the environment

and burn time are the same.

0
0 Figure 46.

150

250

300

350

Quarter

size _rain

design.

76

, 8221
3_8577-1v'__
_i" 1779288-

_
I'_

889644
0

! I

t_
I

100 Time, s

200

Figure

44.

Ouarter-size

booster

thrust

trace.

2.5

2.0

0.5

20

40

60 Time,

80

100

120

140

Figure

45.

Ouarter-size

booster

mixture

ratio.
O1 IIO-HYBRIDRPT

77

2.5.2 The design, eral

Thrust

Chamber booster was considered thrust an expendable system; for this

quarter-size therefore,

only of

an ablative the thrust

chamber are

was considered. similar down; to the

The genfull-size and exit in a

characteristics Many of

chamber

booster. areas throat of

its major of

dimensions in the

are scaled full-size

the throat This

are one-fourth diameter of

those

booster.

results exit

59.7

centimeters

(23.5 inches)

and a nozzle

diameter porL* 4.3

231 centimeters of the of chamber

(91 inches). is

The physical

length

of the cylindrical to maintain

tion value

150 centimeters (120 inches)

(59 inches) and a

a design of

305 centimeters

residence

time

milliseconds. The booster fuel size fuel with injector manifold is a direct scale-down from the full-size Each

125 fuel ports (one-quarter port This of has eight is one pairs of the

that of the fu11-size ports,

booster).

injection booster. many

of oxidizer major

the same as the fullof the gas generator scaleable

advantages booster

approach:

the basic

features

of the

are directly

from one vehicle 2.5.3

size to another. Control booster. design LOX flow rates to perform the

Thrust Vector Fluid injection

TVC is used for the quarter-size scale directly

and total same duty

LOX consumed cycle.

from the full-size are estimated

Total

LOX requirements a 2 percent

to be 3,093 inert

kilograms of the

(6,820 pounds) TVC system 2.5.4

including

reserve.

The total

weight

is 249 kilograms Tank

(550 pounds).

Oxidizer The oxidizer

tank for the pressure-fed Two resin systems were

design

is filament-wound EPON point 826 epoxy

with and

IM-7 poly-

carbon imide.

fiber.

evaluated,

EPON 826 was selected

for the quarter-size from was of the absence calculated 2,946

design.

Sizing bending

of the stiff(0.65 The

tank for structural ness requirement. which

loads benefits Tank thickness

of a major

to be

1.7 centimeters (6,495 pounds).

inches) tank 2.5.5 The size

yields

a tank

weight

kilograms

is lined with

Upilex elastomeric System LOX delivery is used

material.

LOX Delivery pressure-fed Tridyne

system

resembles

the design and

of

the

fullin a

system.

to pressurize

the oxidizer

is stored

78

filament-wound composite tank fabricated resin systems evaluated were EPON 826
selected and for the point design. a 0.008 centimeter includes (0.003

from IM-7 carbon fiber.


epoxy and polyimide. kilograms liner. EPON 2,177

The two
826 was

The tank weighs inch)

(4,800 pounds) The feedlines LOX is

aluminum

for the pressurizing fed through 2.6 2.6.1 In reliability and Boeing trade fed (3) (5) thrust generator optimized An under Llfe

gas are 2.5 centimeter (4.65

diameter

stainless lines.

steel.

two 11.8 centimeter Cost Trade

inch) diameter

Cycle

Studies

Introduction order to and

and Summary assess the impact for the of component full-size selection and design on cost, ARC

performance

and quarter-size design the

boosters, model to (1) gas

Aerospace Cost versus versus expansion (9)

Company (mAC) used parametrics pressure-fed; expendable ratio; reserve (12) were (2) boosters; (6)

an integrated for

conduct pump-

studies. oxidizer reusable nozzle

developed classical (4)

following: versus

hybrid

generator; ratio; (8) gas cost-

oxidizer-to-fuel (7) body

mixture diameter;

chamber

pressure; (10) pump design

deflection; grain design

propellant; redundant

safety

factor; and (13)

(11)

radius; variables. model

capability;

integrated

was

used

to

conduct

the

conceptual

trades,

mAC, vehicle

corporate design

IR&D, developed (HAVCD)

the model, which

a hypervelocity array upper

aerospace

conceptual from

program,

uses a wide

of cost experience stages, design tactical/ subroutines a booster, and system

launch

vehicle

programs,

spacecraft/probes, aircraft

strategic to perform calculates

missiles,

and commercial analysis. cost, booster

and specialized model

optimization the life The

The integrated and predicts is

synthesizes performance input

cycle hybrid

payload from

reliability. component rithms hardware

synthesized

specifications, using cost to algo-

weights

and volume of: (1) design

algorithms. cost costs estimating

LCC is calculated relationships costs; test

comprised

(CERs)

predict costs and

engineering

and manufacturing

(2) support and tooling);

not related

to hardware

(system

engineering, The

software system

(3) facilities, based solid gas on

operations

and support.

reliability rates. was the

is predicted The low-cost source of the and

the specified study CERs.

components life The cycle CERs

and component cost for model, liquid

failure STACEM,

propulsion generator

booster

components,

vehicle

79

launch operations nonrecurring were provided by BAC.

costs,

and launch operations recurring

costs,

Hybrid life cycle costs were calculated for two mission models. Both mission models assumeda 4-year period of linear flight growth rate, followed by a 10-year operational period at a constant flight rate. Two constant flight rate calculations were provided: one flight per month totaling 150 missions (Mission I), and one flight per week totaling 650 missions (Mission
II). sion. and Two This 1,200 full-size resulted and Life 5,200 cycle or eight quarter-size boosters were required per misin total production quarter-size costs were quantities for of 300 or 1,300 full-size I and II, respecnot

boosters calculated

Missions

tively. discounted.

in constant

dollars

and were

New launch booster design,

and production

facilities costs.

were

assumed

to be required costs were

for the in

and operations development,

nonrecurring

Facilities

included

test and evaluation of 90 percent assumed was

(DDT&E). assumed for all component processing. costs. costs. A

A learning 95 percent cent

curve

learning curve

curve was was

for

propellant

A 100 perThe cost of

learning

assumed

for operations

recurring

unreliability Since rently, lar, the

was not included point design

in the cost calculations. trades and LCC analysis were performed concursimiwas

the

hybrid

booster

LCC were to the

calculated design.

for a reference The reference

vehicle booster

but

not

identical,

point

synthesized

by the integrated vacuum thrust.

hybrid booster

model

and was designed

to provide

the specified

The point of reference ratio of 1.5; of initial

for the full-size pressure feet); gas of

synthesized 6.88 MPa

design

is:

mixture LOX tank

chamber (14

(1,000 diameter

psia); of

diameter (13 feet);

4.27 meters

generator

3.96

meters for the chamber of

and a nozzle expansion synthesized 6.88 MPa design

ratio is:

of 15. mixture

The point ratio and ratio of

of reference 1.5; initial

quarter-size pressure of

(1,000

psia);

LOX tank

gas

generator

diameter

2.56 meters

(B.4 feet);

and a nozzle expansion includes a flexseal liner,

of 15. carbon-epoxy (IM-7/ and

The full-size EPON 826) an

booster

nozzle/TVC,

LOX tank with cooled

aluminum

carbon-epoxy thrust

gas generator The

case,

ablatively

PAN

fiber/phenolic

chamber.

quarter-size

80

booster includes the


flexseal system, trade rent pumps nozzle. aft skirt,

same

components,

but

fluid safety for

injection system,

TVC

replaced

the

The weights and igniter

of the range and those were

booster

separation

the expendable-versus-reusable to be consistent boosters with the curredundant

study shuttle

and recovery boosters.

system, The

assumed

reference

full-size sizes

utilized

for the pump-fed

designs,

and both

utilized

cold-gas

helium-pres-

surization

of the LOX tank. of the in LCC estimates Table 21. for both mission LCC is broken models down and both booster four general nonThe

A summary sizes is

shown

into costs, costs booster

categories: recurring

recurring costs

vehicle and

costs,

recurring

operations

vehicle

(DDT&E),

operations LCC than

non-recurring

(DDT&E).

large booster sion models. Vehicle vehicle

provides

lower

the quarter-size

for both mis-

recurring

cost

is

the

primary

LCC

element. with

The

weighting number

of of 22.

recurring A

and non-recurring of the

LCC increases LCC

the increased is shown

missions.

breakdown

vehicle

elements

in Table

These categories Oxidizer valves. Thrust

are further supply

broken

down as shown below. pressurization, piping, and

includes

LOX tank, pumps,

chamber

includes

injector,

combustion

chamber,

insulation

and

the nozzle. Integration subsystem Structures Solid fuel assembly and checkout includes subsystem integration,

assembly, includes includes

and final

assembly

and checkout.

nose cap, aft skirt, and attachments. the gas generator and liner. (E&I) includes avionics, batteries, propellant, gas generator case,

gas generator Electronics

insulation and

instrumentation and wiring.

instrumentation Miscellaneous items. The relative models; The structures weighting

includes

range

safety

system

and miscellaneous

booster

of

the

cost

elements

is constant effects. booster of sizes

for the two mission

differences major and

are a result

of learning the two

difference E&I.

between

is

in

the

cost

of the

The difference

in the cost

structures

is due to

81

Table

21.

Hybrid

booster

LCC breakdown

sumner,

l_aLilaa.rt_

Missions

150

650

150

650

Vehicle (%) Operations (%) Vehicle DDT&E (%) Operation DDT&E (%) LCC (Billions) LCC/Mission (M)

53.0 26.7 8.8 11.5 $11.43 $76.2

68.8 16.6 10.2 4.4 $30.21 $46.5

59.1 22.8 8.2 9.9 $13.24 $88.3

72.5 13.5 10.5 3.6 $37.07 $57.0

Table 22.

Vehicle

LCC

breakdown

summary,

Missions

150

650

150

650

Oxidizer Supply (%) Thrust Chamber (%) Integration Assembly Checkout (%) Structure s (%) Solid Fuel (%) Separation Sys (%) TVC (%) Electronics & Instrumentation Misc. (%)

22.8 18.7 17.5

22.8 18.8 17.4

21.6 19.2 17.3

21.6 19.2 17.2

12.1 8.6 6.2 5.1 4.8 (%) 4.3

12.1 8.6 6.2 5.1 4.8

8.3 7.8 4.5 6.0 12.0

8.4 7.8 4.5 6.0 12.0

4.3

3.3

3.3

0190-HYBRID

RIT

82
/ I

aft the

skirt. shuttle

The full-size SRBs. The

booster

was

assumed booster

to does

have not

the same include

aft skirt an aft

as

quarter-size

skirt

weight

allocation.

The difference for the two sizes. of DDT&E tooling, costs and

in E&I is due to the assumption

of constant

E&I requirements The vehicle increased

breakdown facilities, production

is

shown

in test

Table

23.

The is

increase due to

in the

special for

equipment

requirements and support

the one-flight-per-week decrease with

mission

model.

The costs of design and are functions facilities the booster

engineering

increasing

missions,

of the design support

cost of the vehicle. (GSE) the

The costs

of operations of

and ground stage

equipment Therefore,

are assumed of

to be a function the operations

weight.

weighting number

non-

recurring tion may

costs decreases not more be than valid one

with the increased the

of missions. mission.

This assumpThis if model the may one-

for

one-launch-per-week site, and should be

require

launch

reevaluated

launch-per-week

mission

is retained. recurring in Figure costs 47. is consistent for both sizes

The breakdown and mission 2.6.2 models

of operations and is shown Studies studies and

Conceptual Early

conceptual concepts

were

conducted

to address

the selection point using

of one designs LOX and LCC and a as the

of

the

hybrid

one and

of the oxidizers. pressure-fed

Preliminary systems

were

developed

for pump-fed

oxidizer used

95-percent LCC/pound single the

H202 to estimate of payload

components/weights were The calculated pump-fed the

in the LCC model.

estimates

(Figures 48 and 49) to select gas generator cost ($11.4 hybrid with LOX and

concept

and oxidizer. is shown to

oxidizer

provide with

lowest

billion), cost

pressure-fed lion). Life

classical cycle

hybrid and

H202 provided of

the highest for the

($22.5 bilis

cost

LCC/pound

payload

configurations

shown below. LCC Configuration Gas Generator Hybrid, Pump-Fed, LOX Classical Hybrid, Pump-Fed, LOX Gas Generator Hybrid, Pump-Fed , Peroxide Classic Hybrid, Pump-Fed, Peroxide Gas Generator Hybrid, Pressure-Fed, LOX Gas Generator Hybrid, Pressure-Fed, Peroxide Classic Hybrid, Pressure-Fed, LOX Classic Hybrid, Pressure-Fed, Peroxide LCC/Payload

(x__Z)
100.0 111.4 117.3 120.9 133.6 166.5 168.0 189.0

(%)
I00.0 120.8 132.0 139.9 152.2 253 280 313

B3

Table 23.

DDT&E

breakdown

stlrnrnarv,

Missions

15.0
28.9 62.4

1so
37,5

6so
70,0

Vehicle Facility Special Test Equipment (%) Operation Facilities and Ground Support Equipment Design (%) Support (%)

56.7

30.2

54.6

25.2

9.1 5.3

2.7 4.7

3.0 4.9

1.3 3.5

Technical System Management 19%

Prelaunch Operations and Checkout 52.9% Mission and Launch Control 21.2%

Spares 5.6% Consumables 1.3%

Figure

47.

OPerations

LCC

breakdown,
0190-HYBRID RPT

84

25 l 20
i [] GG Hybrid Classical Hybrid I

15

LOX Pump

LOX Press

H202 Pump

H202 Press

LOX Pump

LOX H202 Press Pump

H202 Press

Figure

48.

Hybrid

concept

LCC

comparison.

25 " [] 20 GG HybridHybrid I Classical

,o
,,,,4

0 LOX Pump LOX Press H202 H202 Pump Press LOX LOX H202 H202 Pump Press PUmp Press

Figure

49.

Hybrid

concern

comparison.

LCCIDavload.
0100-PIYBRIDRPT

85

Because cost, costs

the

gas

generator

hybrid

and point

LOX oxidizer design

provided

the

lowest the to

they were

selected

for the final designs, complexity

trades.

To calculate had to be made cost

of the eight system

conceptual and

certain factors

assumptions used in the

estimate

weights used are: hybrid

algorithms.

The assumptions

Classical

utilized

gaseous

oxidizer

injection.

LOX was preburned Turbopumps

to 667K using propane

propane

or methane.

utilized

or methane. bed. was 98 percent, and the clas-

H202 was decomposed Fuel utilization

by a catalyst

for the gas generator

sical hybrid was 95 percent. 2.6.2.1 evaluation pressure-fed than the and with design more Turbopump Pump-Fed system Versus had pump-out Pressure-Fed of capability. - The cost drivers tank for the pressure-fed system. The

are the cost oxidizer

the oxidizer operates

and pressurization 5.44 MPa

tank

at a pressure

(800 psi) greater that is heavier be larger

thrust-chamber complex.

pressure

and results the

in a tank design system LOX

In addition,

pressurization to empty the

has to The

sufficient provides

expulsion

capability

tank. operated

pump-fed

head pressure

to the pumps.

This

system

at 6.37 MPa expul-

(925 psi)

less than

the thrust-chamber this pressure. system mixture than on exceeded ratio

pressure

and required

a smaller

sion system

to generate

As a result,

the cost of the pressure-

fed tank and expulsion Oxidizer-to-fuel pressure-fed mixture sical 6.5. ratio systems

the cost of the turbopumps. impact on the evaluation LOX/gas generator of

has a greater

pump-fed.

The optimum generator

hybrid

is 1.5; for the peroxide/gas it is 2.75; ratios and the

it is 4.0; for the clasmixture ratio is

hybrid/LOX Higher

classical

hybrid/H202 gas

mixture

increase of this

the pressurizing Low mixture competitive

requirements

and,

therefore, for

cost

and weight systems

system. the cost

ratios with

are preferred the turbopump

pressure-fed

to

keep

designs. 2.6.2.2 the cost Classical-Versus-Gas classical methane LOX. hybrid Generator and the Hybrid - The difference gas to generator drive in the LCC of hybrid is the and

pump-fed of the the

pump-fed required preburner

or propane The weight of

system the

the turbopumps of

preburn

system

and weight

sliver

86

reduces the payload performance of the classical generator hybrid.

hybrid compared to the gas

Hydrogen peroxide offers a higher system density, but reduced Isp compared to LOX. This results in a smaller, heavier hybrid booster which costs more than the LOXsystem. 2.6.2.3
booster adding a Reusable-Versus-Expendable was synthesized recovery by H_brid Boosters A reusable hybrid by were

from the reference The weights for

expendable of the the

booster reusable safety

configuration components margins

system.

increased design

20 percent factor

to compensate for reusable were

higher

and the

complexity following skirt,

components

was increased

40 percent. flexseal nozzle, and

The TVC, aft

components attachments,

assumed

to be reusable: recovery system,

interstage, injector, solid cost first

electronics housing. from to

instrumentation, The STACEM

pumps, piping, cost of

valves

and the igniter was

refurbishment The

rocket of unit

components

obtained was

the be

code. of was

refurbishment

liquid cost. an

components The design attrition

assumed

25 percent components

the theoretical baselined materials at

life of reusable of 10 percent. of boosters required) *

10 reuses

with

rate

All composite required

were assumed to:

to be expendable. (total quantity rate).

The number of boosters

was assumed

to be equal

(units per booster)/(design ment month, and facilities 150 was

life)/(attrition to

A cost of recovery for Mission II

equip-

assumed and $200

be $100 million million for

I (1 flight/

missions)

Mission

(1 flight/week,

650 missions). The els. the LCC of the reusable booster was calculated rate assumptions for the two mission were varied mod-

The design

life and attrition In addition,

to determine was varied

LCC sensitivity. when

the number

of flights lower

per year

to determine hybrid drivers

the expendable The results

booster

provided

LCC than

the reusable 50. The cost

booster.

of this

study

are shown model,

in Figure

of this trade study are the mission the recovery cost attrition rate,

the design

life of reusable DDT&E. between missions the to

components,

and the recovery model. from 0

system

The major expendable 12.3 percent and

driver

is the mission designs ranges

The difference percent at 50

reuseable

at 650 missions.

87

35 30 Largebooster; 14 ft- 13 ft, flexsealTVC IM7 I oxidizertank, IM7 gas generatorcase

25 20
,'=

Expendable 8.6% Difference Reusable

12.3% Difference

,,,1

10

' I

50

100

150

200 250

300

350

400 450

500

550

600

650

700

Missions Figure 50. Life cycle cost vs number of missions.


01BO-HYBRID-RPT

If the design of the reusable in half results doubling 1 percent. For dicted to the the

life of the components would decrease

was

increased

100 percent,

the LCC rate and than

system

2.5 percent;

cutting

the attrition

in a decrease DDT&E

in the reusable increases the

booster reusable

LCC of 1.7 percent; booster LCC less

recovery

specified

mission

models,

the

reusable

hybrid these

booster

is

prevehi-

have

lower cost.

It must

be recognized

that

reference

cles are not optimized, may be decreased

and that apparent

LCC advantage

of the reusable

system

by the following: in the number payload reduces of flights per year. design (approximately

Reduction

The reduced 3 percent) Advanced Increased 2.6.3 The determine Reference reference the

capability the LCC/pound

of the reusable of payload

advantage.

nozzle and thrust recovery

chamber

technology.

system DDT&E.

Design Trade Studies design was used with the Boeing model to parametrically chamber presa

impact

of mixture

ratio,

nozzle

expansion

ratio,

sure and body diameter

on LCC with Mission

I (150 missions).

In this study,

88

single

operating

condition

was varied were

over

a range for

of values a composite

and the effects (carbon-epoxy) material

on weight,

payload, case

and costs

calculated

gas generator combinations,

and LOX tank, in Table

and repeated 24.

for a number

of other

summarized Table 24.

Configuration

and Material

Parametrics.

Full-Scale Pump-Fed LOX Tank Carbon-Epoxy (IM-7/EPON 826) Aluminum Aluminum-Lithium X X X X X X X X X Pressure-Fed

Quarter-Scale Pump-Fed Pressure-Fed

X X X

Gas Generator Carbon-Epoxy (IM-7/EPON 826) D6AC Steel X X X X X X X X

NOTES:

Operating Mixture Chamber Nozzle

conditions Ratio: Pressure: Expansion

varied: 1.3 - 2.9 4.13 - 15.14 MPa (600 - 2,200 Ratio: 6 - 22 3.05 - 5.49 meters (10 - 18 feet) psia)

Body Diameter:

2.6.3.1

Large Booster I Pump-Fed Ratio The LCC

Trades and LCC/pound 51 and 52. tank of payload-versus-mixture is a large for ratio in

Mixture calculations the gas

are shown case

in Figures and LOX

There

difference the

generator

operating mixture case

pressures ratio

pump-fed

designs. weight changes. The materials

The selection and cost of

for the optimum gas generator

becomes tank

a trade between and performance

the

and

LOX

sensitivity cost and

of

LCC

to

mixture

ratio

depends

on

the

component

raw

manufactured

component

weight.

Composite

components,

89

16

15
I and gas generator case Materials of construction for LOX tank ]

14
,Q

,..,i AI and IM7

12

IM7 and Steel


i

IM7 and IM7

11
I I I I I I I I I

.2

1.3

1.4

1.5

1.6

1.7

1.8

1.9

2.0

2.1

2.2

Mixture Ratio

Figure

51.

Mixture

ratio vs LCCfor

the pump

fed large

booster,

1,400

1,300
I and gas generator Materials of construction case for LOX tank J

1,200
AI-Li.. nd Steel a

1,100 AI and Steel

1,000 ,4 900

8OO

700 1.2

1.3

1.4

1.5

1.6

1.7

1.8

1.9

2.0

2.1

2.2

Mixture Ratio

Figure

52.

Mixture

ratio

vs LCCIpayload

for the pump_fed

large

booster,
O190-HYBRID-RPT

90

manufactured high cost of

from the for

carbon fiber. the

fiber On D6AC

(IM-7), the basis gas

are the least of LCC/pound

sensitive of

because

of the

payload, is 1.7.

the optimum The optimum

mixture mixture

ratio

steel

generator

case

ratio for the composite Ratio

gas generator

case is 1.5. ratio are

Expansion shown on Figures due to the

- LCC and LCC/payload

results-versus-expansion with increasing impulse

53 and 54. criteria

The LCC decreased of constant vacuum

expansion and

ratio in

design

total

increase

vacuum for

Isp with

expansion

ratio.

LCC/pound

of payload

calculations

account The

increased

inert weight

of the nozzle-versus-performance is due to overexpansion of payload and

improvement.

decreased expansion

sea level thrust ratio

of the nozzle.

The optimum

for LCC/pound - LCC

is in the range of 10 to 14. of payload results versus chamber

Chamber pressure generator

Pressure

LCC/pound

(Pc) are shown in Figures case material. decrease For with

55 and 56.

This trade generator

is driven case,

by the gas and LCC/

a composite increasing

gas

LCC case,

pound of payload LCC/pound

pressure. 6.88

For a steel psi)

LCC and

of payload

are a minimum

between

MPa (1,000

and 9.63 MPa

(1,398 psi) and increase with Body Diameter are shown between the

increasing

pressure. results of a body drag versus body diameter is a trade area and with the and

- LCC and LCC/pound 57 and 58.

of payload

in Figures

The selection

diameter

inert weight in booster

and performance length. such as Other

due to increased potential

reference associated

change

problems with

booster

body

diameter,

interface were

problems

the core

vehicle

launch equipment,

and transportation system,

not considered uniformly not follow from

in this trade. with increasing diameEach

For each material ter; however,

LCC decreases does

the cost/pound has an to

of payload diameter

the same trend. 3.66 meters

material (all

system

optimum 4.88

ranging

(12 feet) tank

carbon-epoxy)

meters

(16 feet)

(aluminum-lithium

oxidizer

and carbon-epoxy 2.6.3.2

gas generator). Pressure-Fed LCC and LCC/pound 59 and of payload-versus-mixture The results indicate ratio that a of

Large Booster_ Ratio are

Mixture calculations composite payload. materials

- The in

shown

Figures

60.

gas generator Costs

case

and LOX tank have the lowest LCC and LCC/pound by the cost, LOX tank materials and aluminum-lithium of construction. has the highest

are driven

Other cost.

will have a higher

91

15
AI-Li and Steel

AI-Li and IM7

14

I Materialsofgasgeneratorcase for and construction LOXtank


AI and Steel

AI and IM7 ,,J IM7 and Steel

12
IM7 and IM7

11 6

10

12

14

16

18

20

22

Nozzle Expansion Ratio

Figure 53.

LCC vs exoansion

ratio for the pump_fed

large

booster.

1,400

1,300 Materials ofgas generatorcase tank I and construction LOX for


AI-Li and Steel

1,200

1,100
AI and Steel AI-Li and IM7 IM7 and Steel AI and IM7

1,000 900

800

IM7 and IM7

700 6

10

12

14

16

18

20

22

Nozzle Expansion Ratio

Figure

54.

LCC/payload

vs exp_ansion

ratio for the pump_fed

large

booster.
0IgO-HYBRID.RPT

92

AI-Li and Steel

14

Materials ofgasgeneratorcase tank [ and constructionfor LOX


AI and Steel

12

11 4,13

5,51

6.88

8.26

9,63

11.01

12.39

13.76

15.14

Chamber Pressure, MPa

Figure

55.

LCC

vs chamber

pressure

for the pump fed large

booster.

1,400

1,300

;rials of construction for LOX tank and gas generator case


AI-Li and Steel

1,200

1,100
AI and Steel

1,000
AI-Li end IM7 IM7 and Steel

900
AI and IM7

800

IM7 and IM7

700 4.13

5.51

6.88

8.26

9.63

11.01

12.39

13.76

15.14

Chamber Pressure, MPa

Figure

56.

LCCIpayload

vs chamber

pressure

for the Dump_fed

large

booster.
01gO-HYBRID-RPT

93

16

15

Materialsofgas generatorcase tankI for and construction LOX J

14

12

IM7 and Steel IM7 and IM7

11 3.05

3.66

4.27 Body Diameter, m

4.88

5.49

Figure

57.

LCC vs body diameter_for

the pump_ fed large

booster.

1,200

1,100 Materialsof construction LOXtank J for and gas generatorcase 1,000

900
,,,.,I AI and IM7

800
IM7 end IM7

700 3.05

= 3.66

I 4.27 Body Diameter, m

I 4.88 5.49

Figure

58.

LCC/payload

vs body diameter

for the Dumo fed lare -

booster.
0190-HYBRID- RPT

94

40
AI-Li and Steel

35

AI-Li and IM7

30

I Materials and gas

of construction generator case

for

LOX

tank

AI and Steel

AI and IM7

2O
IM7 and Steel

15

IM7 and IM7

10 1.3

1.4

1.5 Mixture Ratio

1.6

.7

Figure

59.

Mixture

ratio vs LCC for the pressure

fed

large

booster,

6,000 l Materials of gas generator for LOX tank 1 and construction case 5,000
AI-Li and Steel

4,000
AI-Li and IM7

3,000
,,,4

2,000
IM7 and Steel IM7 and IM7 1,000
I I I

.3

1.4

1.5 Mixture Ratio

1.6

1.7

Figure

60.

Mixture

ratio vs LCCIpavload

for the vressure

fed

large

booster,
0190-HYBRID.RPT

95

Expansion shown to the impulse. performance zle.

Ratio

- LCC and LCC/payload LCC decreases Isp, and design for level an

results with

versus

expansion expansion

ratio ratio

are due

in Figures increase

61 and 62. in vacuum

increased

criteria

of constant

vacuum

total versus

LCC/payload and

accounts sea

increased due

weight

of the nozzle

decreased expansion

thrust

to overexpanslon of payload

of the nozof

The optimum

ratio

for LCC/pound

is In the range

10 to 14. Chamber pressure with (Pc) Pressure are - LCC and LCC/pound 63 and of of payload LCC results increases is optimum versus chamber

shown pressure.

in Figures

64.

significantly at 6.88 MPa for a

increasing

LCC/pound

payload case,

(1,000 psi)

for a composite case.

gas generator

and 4.13 MPa

(600 psi)

steel gas generator Body are shown fed case, obtained case Diameter

- LCC and LCC/pound 65 and 66. with increased

of payload

results design

versus cost,

body diameter like the pumpof payload is

in Figures decreases at diameters

The pressure-fed diameter.

Minimum

LCC/pound

greater

than 3.66 meters

for the composite

gas generator

and approximately quarter-Size

3.66 meters Booster

for the steel gas generator

case. were consisvehicle results was are

2.6.3.3 tent not with

- LCC results performance of the

for the quarter-size of the quarter-size booster

the full-size. Summary B. Booster the LCC

Payload tables

determined.

quarter-size

included 2.6.4 To

in Appendix Additional complete

Design Studies evaluations, additional design booster complexities cost. were

investigated evaluated lant

to determine

the impact on the reference model were: (4) (I) thrust volumetric

The items (2) propelgenerator

using the Boeing (3) design

vector

control; of

reserve;

margins; pump-out

loading

gas

propellant; 2.6.4.1 offers compared shuttle

and (5) oxidizer Vector

capability. injection thrust and vector control life (FITVC) cost the

Thrust the to

Control for

- Fluid

potential the

improved nozzle

reliability actuation

reduced

cycle used on

flexseal

and

system

presently

booster. the cost We assumed benefit of FITVC, a series of reference of duty boosters was to of

To define synthesized. calculate

a deflection required.

requirement We assumed

1, 3, and 5 degrees cycles for the TVC

the mass

of fluid

96

4O

AI-Liand IM7

35

-"

30

I Materials ofgas generatorcase tankI and construction LOX for


AJ and Steel

25
AI and IM7

2O
IM7 and Steel

15

IM7 and IM7

10 6

10

12

14

16

18

20

22

Nozzle Expansion Ratio

Figure

61.

L,CC vs expansion

ratio for the pressure_fed

large

booster.

6,000 _._ 5,000 [ Materials of construction for LOX tank] [ and gasgeneratorcas_ _ J

4,000
AI and Steel

3,000

AJ and IM7

2,000
IM7 and Steel

1,000 6 8

IM7 end IM7 I

10

12

14

16

18

20

22

Nozzle Expansion Ratio Figure 62. LCC/oayload vs expansion ratio for the pressure fed large booster.

Ol 90-HYBRID-RPT

97

4O
AI-Li and Steel

35

AI-Li and IM7

AJ and Steel

AJend IM7

Materials of construction and gas generator case

for LOX tank]

15
IM7 and IM7

10 4.13

5.51

6.88

8.26

9.63

11.01

12.39

13.76

15.14

Chamber Pressure, MPa

Figure

63.

LCC

vs chamber

pressure

for the pressure

fed large

booster.

6,000
of construction and gas generator case for LOX

tank1
_J/

5,000
AI-Liand_ / AI-LI and IM7

4,000

3,000
...I

2.000

1,000

IM7 and IM7 1 !

"r

4.13

5.51

6.88

8.26

9.63

11.01 MPa

12.39

13.76

15.14

Chamber Pr_sure, Figure 64. LCC/oavload vs chamber pressure

for the pressure

fed large

booster,

oi gO.HYBRIDRPT

98

40
AFLi and Steel

35
I Materials

AFLi and IM7

of construction and gas generator

for LOX tank I case I

3O

AI and Steel AI and IM7

20
IM7 and Steel

15

Ill

IM7 and IM7

10 3.05

3.66

4.27 Body Diameter, m

4.88

5.49

Figure

65.

LCC

vs body

diameter_for

the pressure

fed

large

booster.

5,000

4,000

AI-Li and IM7

AI and Steel

3,000 -

AI and IM7

,,,,,,,I

2,000 -

I Materials ofgasgeneratorcase tank I for and construction LOX

IM7 and Steel IM7 and IM7


! I I

3.66

4.27 Body Diameter, m

4.88

5.49

Figure

66.

LCC/pavload

vs body_ diameter

for the pressure

fed large

booster.
019OJ-rYBRIDRPT

99

20,

40,

and 60 percent

of the total

burn time

(135

seconds)

at each boosters.

deflec-

tion.

This was done for both the full-size The large booster LCC and LCC/pound quarter-scale FITVC $13.2 offers

and quarter-size

of payload FITVC

FITVC results are shown the

are shown on Figure

in 69.

Figures Over

67

and range

68.

The

results

the

evaluated, full-size;

a lower

LCC than

reference

case of

($11.4 billion LCC/pound duty

billion

quarter-size).

However,

on a basis

of payload,

the break-even of payload

point

is at 3 deflection point would

and 60 percent be increased by

cycle.

The LCC/pound

break-even

the use of an advanced 2.6.4.2 through designed bility variable Propellant

nozzle

technology - The

such as the MBA nozzle. to extinguish allows the hybrid booster to be reliawith

Reserve

ability flow

the termination into through burning the the

of the oxidizer Reserve of

propellant the

reserve booster associated

booster.

propellant propellant

improves failure

elimination

modes

rates

and combustion were synthesized

efficiency. with propellant reserve increased to

Hybrid 5 percent.

boosters

The impact of reserve

propellant

on LCC and LCC/pound

of payload

Material

IM7

Solid

Case

Body

Diameter

= 2.56

1
f J A-60% Dub/Cycle

11.95 -

OxidizerFlowSize-

IM70X Tank LOX Pumps Quarter

Chamber Pressure = 6.88 MPaI Mixture Ratio = 1.5:1 I Expansion Ratio = 15:1 I Injection Fluid- Oxidizer I

Cycle

11.75 Cycle 11.65 -

11.55 -

11.45

1.0

3.0 Thrust Deflection Angle Ideg)

5.0

Figure

69.

life

cycle

cost vs thrust deflection_for

the quarter

scale

booster.
OtgO-HYBRID- PT R

I00

11.8 Material OxidizerFlowSizeIM7 Solid Case IM70XTank LOX Pumps Full Body Diameter = 4.27 m Chamber Pressure = 6.88 MPa Mixture Ratio = 1.5:1 Expansion Ratio = 15:1 Injection Fluid - Oxidizer

11.6 -

....

11.4 -

11.2 Duty Cycle

,,,J

11.0 -

40%

Duty Cycle

20% 10.8
i

Duty Cycle

10.6

I 1.0 Thrust

1 3.0 Deflection Angle (deg)

I 5.0

Figure 67.
920 Material880 OxidizerFlowSize-

Life cycle cost vs thrust deflection for the large booster.

IM7 Solid Case IM70X Tank LOX Pumps Full

Body Diameter = 4.27 m Chamber Pressure = 6.88 MPa Mixture Ratio = 1.5:1 Expansion Ratio = 15:1 Injection Fluid - Oxidizer

840-

800

ty Cycle

760 Cycle 720

680

I 1.0 Thrust

I 3.0 Defl_'tion Angle (dog/

I 5.0

Figure 68.

Cost per round

of payload vs thrust deflection for thelarce booster.


0190-HYBRID-RPT

I01

is

shown

in

Figures

70

and

71.

The

increased of 4,400 million)

inert

weight

to

store

the of

reserve payload.

propellant LCC

resulted

in a decrease ($140

kilograms and

(9,700 pounds) of

increased

1.2 percent ($gl/pound). Increased were case

LCC/pound

payload

increased 2.6.4.3

$200/kilogram Design Margins

design

margins with tank

may the

be

used

to

improve safety 1.6 to

reliability. margins 1.9. 73. of The the

Hybrid gas on

boosters generator

synthesized and oxidizer

structural from

increased

impact

LCC and LCC/pound

of payload

are shown

in Figures

72 and as of

Inert weight of the

is increased increase

approximately margin was

1,225 kilograms resulting

(2,700 pounds) decrease 1

a result 363

in design LCC of

in a payload by less than

kilograms

(800 and

pounds). LCC/pound

increased increased

percent

($100 million), ($12/pound)]. 2.6.4.4 packing may be

payload

1.5 percent

[$26/kilogram

Volumetric of the

Loadin 9

of

Gas

Generator provide

Propellant processing of

- Lower cost

volumetric or

gas generator due to

case

may

reductions clean

required To

burning

rate

limitations with

scavenged in gas

propelcase port in

lants.

document loading,

the cost a hybrid

associated

changes

generator grain results

volumetric radii to

booster

was synthesized of 75 to

with different The

reflect

volumetric

loadings

95 percent.

terms of LCC LCC/pound 2.6.4.5 pump-fed pump-fed four Oxidizer system system each

of payload

are shown

in Figures

74 and 75. of a single-string system. The use with The of

Pump-Out

Capability

- The

reliability

is lower

than

the reliability be improved

of a pressure-fed through redundancy. flow rate,

reliability sized for

can

pumps,

133 percent

of the design assures

common feed

manifold rate

and independent

block valves, if one pump of the of

that the required capability by

oxidizer

can be maintained on LCC. and LCC

fails.

Pump-out design

has a minimal 0.35 percent

impact

reference payload

increases 0.66

($40 million) ($5/pound)].

LCC/pound

increases

percent

[$11/kilogram equivalent

Pump-out

capability

provides

a predicted

reliability

to a pressure-fed 2.6.5 To (HAVCD) Mission Hybrid

system,

but at a lower Results trade

LCC.

Model Optimizer the

complete was used I.

parametric

studies, conditions

the

hybrid

booster

model for

to predict

the optimum

for the hybrid valuable

booster

The optimizer

is a tool that can provide

insight

into the

102

11.64

Material OxidizerFlowSizeIM7 Solid Case IM7 OX Tank LOX Pumps Full Body Diameter = 4.27 m Chamber Pressure = 6.88 MPa Mixture Ratio = 1.5:1 Expansion Ratio = 15:1

11.60 -

11.56 -

11.52 11.48

11.44

11.40

- "'"T 2.0

1" 3.0 Reserve Figure 70. Life cycle Propellant cost

l 4.0 (%1 t_rot_ellant.

1" 5.0

vs reserve

860 Material Oxidizer FlowSize820 IM7 Solid Case IM70X Tank LOX Pumps Full Body Diameter = 4.27 m ] Chamber Pressure = 6.88 MPa / Mixture Ratio = 1.5:1 _ Expansion Ratio = 15:1 [ _ _IP ._" ._"

840-

800 -

,,,,d

780 -

760 -

1"
3.0 Ruerve Propellant

1"
4.0 l%1

t
5.0

Figure

71.

Cost per pound

of payload

vs reserve

orooellant.
0190-HYBRIDRPT

103

11.54

11.52 -

11.50 -

11.48 -

11.46 / 11.44 -OxidizerFlowSizeI 1.6 I 1.7 Safety Figure 72. Life Factor cost vs safety_factor. -IM70X Tank LOX Pumps Full I 1.8 Chamber Pressure = 6.88 MPa Mixture Ratio = 1.5:1 Expansion Ratio = .27 m 15:1 ]

11.42

I 1.9

cycle

780 -MaterialOxidizer Flow SizeIM7 Solid Case IM70X Tank LOX Pumps Full

776 -

i Body Diameter = 4.27 m I Chamber Pressure = 6.88 MPa Mixture Ratio = 1.5:1 Expansion Ratio = 15:1

772 -

768

.4

764

760

756

I 1.6

I 1.7 Safety Figure 73. Cost Der pound Factor

I 1.8

I 1.9

of payload

vs s_e_

factor. O190-HYBRID-RPT

104

11.95

11.85 -

11.75 Material11.65 ,,,,I 11.55 OxidizerFlowSizeIM7 Solid Case tM70X Tank LOX Pumps Full Body Diameter = 4.27 m Chamber Pressure = 6.88 MPa Mixture Ratio = 1.5:1 Expansion Ratio = 15:1

11.45 -

11 35

I 45.72

I 60.96 Radious Figure 74. of Solid Life Grain

I 76.20 (cml radius.

I 91.44

cycle cost vs erain

960

920 -

880 I

840-

Material OxidizerFlowSize-

IM7 Solid Case IM70X Tank LOX Pumps Full

Body Diameter = 4.27 m I Chamber Pressure = 6.88 MPa I Mixture Ratio = 1.5:1 I Expansion Ratio = 15:1 I

I
IM7 Case

,,,,I

800 -

760 -

720

i 45.72

I 60.96 Radius Figure 75. Cost of Solid per pound Grain

I 76.20 (cm) vs

I 91.44

of pa),Ioad

s_e_

factor,
01gO-HYBRIDRPT

105

design

of

a booster choices

system

with

a significant

number

of

operating

variables

and materials for different

such as the hybrid. minimum LCC/pound empty

Operating of

conditions

were optimized of payload, lift-off

results: minimum Optimizer

payload,

LCC/pound

maximum weight

payload, (GLOW). optimum payload,

LCC, minimum results and

weight, in Table

and minimum 25. based

gross

are shown results

The pound for of

conditions or payload. weight

were

consistent

on

LCC,

LCC/

LCC/pound minimum the

of payload GLOW, were

results, not

when

optimizing with and the the

minimum The

empty

or

consistent conditions pressure; psi) to

others. reference chamber

difference

between

optimum of

operating

conditions pressure

is in the the

selection 6.88

the chamber MPa (1,000

increasing

from

reference

approximately

12.4 MPa (1,800 psi) results The LCC/pound optimum. 2.7 2.7.1 ARC hybrid. designs ties Reliability Analyses LCC of the

in lower LCC and improved booster varied booster

performance. from the optimum. than the

reference

2.2 percent

of payload

for the reference

was 5.4 percent

higher

Introduction performed The a preliminary reliability analysis for the gas generator point

predicted

reliabilities to be 0.9985

for the pressure-fed and 0.9987, respectively. were

and pump-fed

are estimated

Only reliabiliitems such

related

to the actual

flight of the components

included;

Table

25.

Hybrid

Booster

LCC Trade

Studies

Optimized

Booster

Design.

Optimized On

Mixture Ratio

Chamber Pressure (MPa)

Body Diameter (m)

Expansion Ratio

LCC ($nx 107 )

$ Per Payload (kg) kg Payload

S/Payload Payload LCC Empty Wt GLOW *Reference Conditions

1.496 1.487 1.600 1.429 1.600 1.50

12.8 12.4 12.8 4.8 7.3 6.88

3.g 3.0 4.8 4.3 3.7 4.3

18.8 17.5 22.5 7.0 25.0 15.0

11.207 11.480 11.180 11.970 11.390 11.430

47,491 48,126 46,992 43,822 43,577 45,858

1,581 1,588 1,584 1,819 1,740 1,652

106

as prelaunch reliability and their effects on the probability of booster operation were not considered for this evaluation because of the limited data available at Boeing. 2.7.2
Reliability Figure system. component Block Diaqram the reliability system, block Figure diagram 77, for the hybrid as booster a seven-

76 presents hybrid

The

propulsion of:

is presented

system

consisting system;

(1) a solid

fuel gas generator;

(2) nozzle; drive

(3) oxidizer system;

feed

(4) preburner; system.

(5) turbopumps;

(6) turbine

and (7) pressurization

The block diagram system requiring

is intended

to imply operation of each

of an independent in the order math

series

successful booster

operation

subsystem

depicted model is

to obtain therefore

successful

functioning.

A series

reliability

used to arrive

at the overall

booster

reliability
r

and has the form:

RT = R1 x R2 x R3 x ... x Rr =

n s=1

Rs

(2)

Where:

R1 RT

= =

predicted system

component

reliability

reliability

2.7.3 One

Reliability of the

Estimation used

Procedures distributions to describe "time to fail" for

widely

electrical

and mechanical

components

and systems

is the Weibull

distribution:

R (t)

:
y 6 B t

exp [-

l (t---_--_6)B
parameter

(3)

where:

= = = =

location scale shape

parameter parameter time reduces to an exponential

mission above

When

assuming

distribution

6 = 0 and B = 1, the 1. with _ = _.

equation

R (t) = exp I- xt] where: x = failure rate

(4)

I07

Hytmd Booster R = 0.9995

I
Electrical System and Instrumentation R - 0.99991 Structures and Mechanisms R - 0.gG9913

I
Pro_L_K>n System R = 0.9996

Figure

76.

Hybrid

booster

reliabili_

block

diagram.

Propulsion

I
Turbine Pressurization System I System Drive Turbopumps Pmburner Oxidizer System Feed Solid Gas Fuel I Nozzle Generator -- Tr,clyne - Service - Isolation Pressure Pressure Valve Valve Tank Value Value Regulatc Relief -- Control --Tank -- Service - Isolation - Throttle Value Valve Valve Box -- Tur'bopump Assembly -- Pre-cool -- Case Valve -- Se_ice -- Relief Valve Valve --Case -- Convergent Section Case Convergent Section Inaul Throat Structure -- Igniter -- Tank -- Insulation

'[VC Actuator Nozzle Structure Control Box

-- Isolatio41 Valve
m

Pressure Regulator

Posrtion

-Valve Position Indicator

-- Inlector -- Manifold -- Combustion Chamber Case

Indicator Control Lines Box

-- Combustion Chamber -- Propellant -- Igniter Insulation

Figure77.

tIybrid

propulsion

sy_ stem.
01gO-HYBRID RPT

108

The bility stress.

reliability the

of

the of

structural the

components

is

based

upon

the the

probaapplied

that

strength

structural as:

material

exceeds

Mathematically,

this is expressed

R = P (R > S)

(5)
(6)

= _ fs (S) [ ) fr (R) dR] dS

= 7 fr

(R)

7 fs

(S)

dS]

dR

(7)

where:

fr (R) = PDF of strength fs (S) = PDF of stress PDF = probability density function

For normal

distributions

of strength using

and stress, the equation:

the reliability

of the struc-

tural components

is calculated

R = _ [

_ - )

(8)

where:

R S oR

= = =

mean mean

value value

of the material of the material deviation deviation of of

strength stress the the material material

standard strength standard stress strength

oS

For

non-normal

distributions

of

and

stress,

the reliability

of

the structural other

components

is calculated there is are

by evaluating only to two random

the integrals variables integrals

for these a

distributions. program 15

When

involved, for

computer

called

POFAIL

used

evaluate

the

other

distributions. mation method

When there are more than three Mean Value First Order

random variables, Moment (MVFOSM)

an approximethod has

called

Second

15.

Ang, A. H. S., Wilson, Tang H., "Decision Risks and Reliability," Probability Concepts in Engineering Planning and Design, Vol. V, 1984.

109

been used. 16 A computer program for MVFOSM been written has the Hybrid Propulsion Technology Program.

and utilized

for

Prior to beginning the reliability analysis, an estimate of failure rates was obtained from a variety of data sources, reliability handbooks, engine analysis reports, and engineering estimates by reliability Table 26 is a compilation of componentfailure rates and sources
item. Once the component Boeing for input reliabilities RELIB were predicted, subroutine the values were given This to

engineers.
for each line

into their

computer

data files.

suband

routine, finally,

part

of the HAVCD program, reliability. were 0.9985 of 0.9995

calculated Predicted

the subsystem reliabilities

reliability,

the booster

for the pressureThis was lower but was the

fed and pump-fed than

designs

and 0.99B7, established

respectively.

the reliability

goal

for the booster, components: These

result case;

of low historical (2) combustor for

data for the following (3) nozzle; improvement

(1) gas generator specific the items Phase are II

case;

and (4) TVC. and validation

emphasized activities. 2.7.4 To minary pump-fed failure

design

during

Failure

Modes and Effects

Analysis on mission has been success, performed a prelifor the

identify potential failure design. analysis; mode and

impact of each failure effects analysis (FMEA)

The major ground i.e., each when

rule observed

in the analysis to

is the single in

failure

is considered failure modes

be the only failure

the system. of a

However,

critical mode

are identified, the

the effects are also

simultaneous

failure

which

might

worsen

situation

investigated. Another The parts of ground rule observed to be in the analysis of is at the assembly components dispositioned level. as a as

are

considered undergone

assemblies

failure-free and being

result

having

receiving

inspection 27.

acceptable.

The FMEA is presented

in Table

16.

Ang, A. H. S., Cornell, C. A., "Reliability Bases of Structural and Design," Journal of Structural Division, ASCE, Vol. 100, Sept.

Safety 1974.

110

Table 26.

Hybrid ComponentPredicted Failure Rates. Item Failure Rate* Source

ELECTRICAL SYSTEM ANDINSTRUMENTATION Avionics Wiring Batteries/Power Supply Instrumentation STRUCTURES ANDMECHANISMS NoseShell and TPS Interstage Aft Skirt Attachment Struts Separation System PROPULSION Pressurization System Tridyne Tank Service Valve Isolation Valve Pressure Regulator Pressure Relief Valve Valve Position Indicator Control Box Lines Turbine Drive System Control Box Tank Service Valve Isolation Valve Throttle Valve Valve Position Indicator Turbopumps TurbopumpAssembly Preburner Igniter Precool Valve Case Oxidizer Feed System Tank Service Valve Relief Valve Isolation Valve Pressure Regulator Manifold *Per 1.0 x 106 hours.
111

20.0 1.5 169.0 155.0

9 9 9 9

45.0 1.0 1.0 1.0 0.0

6 6 6 6 7

37.5 1.6 11.0 55.3 9.8 155.0 20.0 5.0

1 2 5 5 5 4 9 6

20.0 37.5 1.6 11.0 10.2 155.0

9 1 2 5 5 9

164.0

10

74.0 35.0 1.0

2 8 6

37.5 1.6 9.8 11.0 55.3 1.1

1 2 5 5 5 6

Table 26.

Hybrid ComponentPredicted Failure Rates (Cont'd). Item Failure Rate*


Source

Solid Fuel Gas Insulation Case Convergent Convergent Injector Combustion Combustion Fuel Igniter

Generator 6.3 134.0 134.0 6.3 45.0 6.3 6.3 56.0 85.0 11 11 11 11 11 11 11 11 11

Section Section Chamber Chamber

Case Insulation Case Insulation

Nozzle TVC Actuators Throat Structure Nozzle Structure Control box

321.0 248.5 248.5 20.0

7 11 11 9

The following I. 2.

are the sources

or assumptions

used to assign

failure 1985,

rates: unpublished Center,

Spacecraft Reliability Prediction, Boeing Aerospace, report based on analysis of a variety of systems. NPRD-3, Non-Electric Parts Reliability RADC, Griffiss AFB, New York 21985. Data, Reliability

Analysis

3.

Boeing Document D290-10404-1, Reliability & Maintainability Allocations, Assessments and Analysis Report IUS System, CDRL #050A2, Boeing Company/Aerospace Division, Seattle WA 1979. YVAE-80-O05, Space System Effectiveness Requirements Document Transportation System: Inertial Upper Stage (IUS), USAF/Space 1981. Engineering Assumed judgement for environment adjustment for Space Division,

4.

5. 6. 7. 8. g.

of data from item 2.

as based on high design margins for data in item 3. for environmental of undefined

of safety.

Calculated Engineeering Assumed

Judgement

adjustment

of data from

item 4.

for components

complexity.

10. Engineering judgement for environmental adjustment of data from Boeing Document D232-10627-1 AGM-86, Reliability and Maintainability Allocation Assessment and Analysis Report, 1980. 11. Based on a combination of data from CSD Titan SRMs and Thiokol SRM data.

*Per

1.0 x 106 hours

112

U C 0 e0 U 0 _ _ U 0 _

U I.U (%; C

|*-,_
_.r-

c"
4_'_-

o,-"
"1_ 0

o "_
0 ,--

,
0'--

.o
0

c_
0 _

O,--

_o>
X

%
c-

U_ eI-

e-

C(30 O_

(.J

L_

tO

cO

L_ '_-_ 0 _" 0

r 0 0 S._

_3_ _" "_

E
0 0

_ I.0

!-

_.

I_.r0 :E: G)

r"

_.

a_

1-

I,..

_.

0".--

_-

! U e"_ >_ S,rE .r-C _0 0 0 e" _.J_ ",0 _I,-. L 0 _.I_ _J _ 0 I,.- r :_0"_ _" ._.._ -_" E I_ I_ I,0

LJ-

V_

_.

"-

_-

_'_

"_

Q_

_-

_-

"_

E _-_-I_-_

Q. t-r Ie-

0 e_

C 0 I-

,'"

I...

ICU 0 e-

--_ 3C

CUE w

113

u u

U U I0

u U U

(IJ ao (..) G)

is"-

,2

0 _11 "_ IO_

o o.

I0 ,_ f_ _J cO v _ _.._ 0 4-_ I.,_ -_ fb r" I._ "_ _,- _._,,I, o _I_ _,,'1 q.. e,O0 O_J 0

1:1 (J

u _"g
I_ .'0_ O: 0 _ 0 _L IM

%
c'0 (I) 0

d E E
0 0 0 0 I,0 0 0

(3J

L._

"c
0

'-c

usc o LL 0'_

"_

(_.,_

"_

"_

5.. I.=_=_

ta, _E .rE

r'_ S. o

_8-___

r_

4-) t.-

i_
_

I.--

(_)

)
i-

0 tU

> -_
IU

_ >
0

_v _E 0

0 ,,e-r_

114

.._ m U U

>_ 0

"_

_,q..

%- U

_"

$.,

u_

sit 0

U',"

_O V,.. U

,,_- _

:_

",-" (1_

"0 4.a U v.. L_ _,_._ L _ _,._ 0 e" _ _ 1,@a _.U_ 0 0 0 e.. r._

0 v

E_
>_ _:m :ira _.34.,a tl., t,n 4,_ "_ v'_ 4,_, _ 0

%
c'u') .) 0 T OJ I-eft3 SOJ 0 "_r_ (1) Sr-CO t0 > I,O0 0 _ m4O r.O C _.leOJ I,,=m _ E _ _ _'=_ I _,_ QJ q_ e". Om ,,_'m 4--_ 0 _ e" (,.) _" I._. 0 _ _J _. "" U IO" _ _ --3 _ "--" L tJ O" V_ .._ "E _. . e(j e--

o
0")

o_,
e" (j c-

_0 0"_

_'-" "_

_ 0

L J_ "I0 0 _.. 0 .,c-

La_

rO cE o_

e" L.

S.3-

C_ O3 r-.:3 r_ t-e"

X 0 aJ

0 e0 e"e0 e--

tL_

0E _0 m 0 N C.._ l-

_.l.a -_ >_

115

GJ I-

,2
q U oq"_ 0 _-_. ._ _ COU

I-

4..)

_1_1-__.-_ _ _,_ _ 0

I.0

ICI_ _ _-_"

_J _.:)

!.- _ "_ I.. _'-- _

q.4-D r" L _" I=r-=1 I; :301C :_ _ _ 0 I,.. _ _ 0 4-_

_l_ _.

'_ S-

0 0

r-o c_)

-,,_ "_" _,-

,4_' _,,..

_"'_ 0

_,. _'-

I"-" _.

"l"a' I_- _

_'-"

",_," e',,_._

_,,_

%
O 0 _ IO I-

IL.U C ,-j-,,-._-_ O "O Q 0 0 f_ to o N I._ _ w_.," ,_ 4_' "_-" ",'0 I::: O

IO

R5

_ O G_*,I. 4_ r-

_tl:

>

_
0 IUO e"

V)

.,- .,- ..
O0 0

0 r_ o,J c _

_-

o 4,z -_-. 0 0",tn

GJu_ _n e_. O S,E ,-eE 0 I%. I.

116

0 .,l,.a _ U O _ a-_ e.- e-

i_,.@
.=I i--

J_

'0%-

',,_" eO .4=a,

rI.. ,-aJ _1 ",=" 0 I.. _

_b.- I..

v) 0 cO 0 v _._ x (M

E
.p.. _,'I I_ ,u'1 0--_ 0 0 r- L b.._ e-_ o: Qo 1=,-

%
t-"

t_)

O_ S"0 0 X

m r

(U 0 _ ,L

l..a.l r.= c'O

.,-

>.

e_,.O

o 3 e.- e,- o

iso

"t. O_ 0 '-

:3 SS.-

S-_,0 0 GJ 4-)._ "0

.-_

C_

-J L

k-

N U C 0 *eX 0

f,. _E

o e. SN P" N _ I_I4.J . _"" G_ _L

L.I_

S.. t-.r.E e==. _J S..

-g

"o

_._ N

I_-,X 0 e-EU_

_o

IIU

t_ n_

E
U fGP g,..

eo m.4=;

e.o

3 3 _
m eZ

%
ac

IUN,,_ "0 0 .,_,. _.=.) x___ . 0 E OJ U,'l

.0

r.,-_ 0

I17

4")

0 _ C e-

k_ Q _J

_
_---q_0 $-4-) R_ _ . I.,. S.- e" f..) _ "_ l=m

x.,-

0 Q.

(J

_"

U"

l,J _'

E._O

0 (I) W f,. O0 X _) 01 .,V_ O_ f,. _j.,(J_,-

(u

4_ 0 v q_J

_'_

,,
I_ I_

o
f,,,.

g_o
0",0

r, ," 0

S.:3 "_ 0

%
C _0 U Z L_

cL_

C)

L r-OJ Ut" 0 f_ _ _J

U. E r--

0-

C 0 4_ C r--

L-

S
J= e0 r0

_a*--"

118

I0 .e_- 0

U 0

_
tlv 0_"

"_l_

,-o_
_-'_ :_ t_ 0 U J ,_-

o D.

=,-

4,a

"-_

U U U e-

tO v

E
u

_._
0

_-

,I,._ .I.-_

l"

_J

e..,_ u,.z _ _Z I,0'-0 I, "0 0 $,.. _ U I.-I:= 0 I:: c r, Oj:: _ la_ t 0 0 e" _0 _"_ 0 !_ _ 0,-UO C"P" 0"_ I:: -_'0"_ _0

Oa_a_ !,- e-

e-

0 0 I,-

co i,_ x u eE .e.U C._.we0 i,.. o 0,-" l,/,_ ,l_ ,4=l0 _,lx l,,_ 0 _---

e4_ I.-o U 0 x 0

U V_ N 0 ,y I0

cO v E 0 _ _'- "_ _ LL 0 _0_ I:: N N 0 Z

119

2.8

Technology ARC

Identification the pump-fed in safety, gas generator reliability, (STS) solid hybrid cost, as our baseline and performance booster. The concept. over the 1

selected

It offers existing

advantages shuttle

transport

system

rocket

Phase

point design

offers

the following: reliability of 0.998. parts; only one cryogen (LOX).

Calculated Reduced $11.4 Engine Mission On-pad 13,608

number

of critical

billion

life cycle cost. and throttling even with capability. loss of one pump.

shutdown

accomplished abort. kilograms

(30,000

pounds)

(46

percent)

shuttle

payload

improvement The that have nologies The major Growth

over ASRM boosters.

capability. hybrid proposed by ARC has several major technologies minor tech-

gas generator

to be developed that offer

to demonstrate (cost, below

the concept, reliability) and discussed are listed

and several to existing

improvements are listed

technology. sec-

technologies major

in the following in Table 28 and

tions.

The

and minor

technologies

include

the rationale

for selection.

Major Gas Generator Injector

Technoloqy

Priority I 1 2 or Ablative) 2 Priority

Fuel Development

Design Interaction (Regenerative Technology

Combustion

Combustor/Nozzle

Minor Turbopump Tridyne Thrust Systems

Development Expulsion System Development LOX

Vector

Control

Using

Integration

120

t. 0 E 0 G; U I,,--4-)

_u tI u1 _ _I el

"_4.a e-

3aS r_ Sr_

_"_

O"I_

tn

i-

ul

aJ ,-C 0

i- in i_,--,o _ o _ul,-_j,o (..) _'.,- _j._ ('-.I.-u_,--,-- > .,-

0 c tu QJ

O--O .._ O.._ I-I--

-,_J _ O n,,

_J

GJ

(1; u aJ r-4-J _GJ _


ir,--, ,f=-

u _4-) L)
_ -r--

S>_ r_-ae--

_,J "_3

L._ "_ u _l.iJ o 4._ i/I :0


r'-

e_n

4._

,--,-0 0 S -u. 0 --4 _ ,v 0 _tn 0 e3 I__ "_

t) t__.

,-oo'--

1:7" QJ rv

e- w 0 ._of--

_ ._. c" 0 O O'_-_,1"{..)

O "-_ :3

_" O O
f.J

_) I-I

I(U ,N

N
r'-

..i0
(.,_

"I',-,v __n --I-

tn (U I.. "'

4._ In 0 ]I 0 ._j

0",I- 3_ _. ul _'_ t- .8-.)-,-> S- 0 -_- _ _/) _- C1 "_C)

_"

",")

I_

S O (.3

,-_ U..

.iX C)

U(D

> )_

O_ 0 0 0 L)

l_J t.._o _,.I.- aJ e-.jm

E
o,--,-

u_ _J O O-,0 O,-*I,==

Io") N O oJ 0 N .l,.a _-. (.,e) .x .._ _-

0
.f-)

.9 _n (1; c__u_

f.) cu ,-.j

E._ O (.3,---.,

E_ O

121

- l,_u,..

>_ 0
r--

E E

o _. r- O O ",l.-so
_i.= 3

t_

_2.0J h-

3[

122

2.8.1 The burning

Gas Generator fuel-rich rates

Fuel Development used in the hybrid booster should: (1) have

propellants to 1.27

of 0.76 than

centimeters/second hydrogen and chloride (4)

(0.3 to 0.5 emissions

Inches/second); in the below exhaust; 2.06 MPa

(2) produce (3) have

less high

l-percent

ejection

efficiency;

extinguish from

(300 psia). propellants (ducted

These

fuel-rich

formulations

are derived

both

conventional

and fuel-rich

formulations ramjet) to meet

previously

developed

for air-breathing need to be tairequirements. under able to IR&D fundbe extinpoint the to do

rocket

and solid fuel further

applications, specific

but will booster

lored and/or Two ing

developed

hybrid

promising

gas generator in Section actual these 2.2.

formulations Both rates

were evaluated were

as discussed but

formulations were too

guished, designs. required ensure not

their of

burning

low for our tailoring

baseline to

Both burning that

formulations This tailoring one

will

require be

achieve

rate. to

must

performed

experimentally for example)

changes another

improve

parameter

(burning

rate,

degrade

parameter the

(physical

properties, must be

for fully

example).

Further, with

following regard

tailoring,

propellant/fuel including,

characterized

to all of its properties

but not limited

to, reproducibility

and reliability. 2.8.2 The Injector injector gas Design in the gas generator generator effluent, hybrid provide is used to control to the flow of the oxi-

the fuel-rich dizer, and

a location

inject

and to minimize

uncontrolled Because

feedback the gas

(instability) generator

between

the primary when

secondary

combustor.

operates

unchoked

oxidizer rate of

is flowing, the

the pressure and,

in the thrust

chamber flow

controls rate.

the burning In addition, wall

gas generator has to provide of

therefore, mixing,

its mass

the injector and damping development ulates

uniform

film cooling There

of the combustor of

high-frequency

oscillations.

are a number

critical particinterface

issues for the injector: impingement, (3) erosion);

(1) interaction

of gas generator injector feedback

(mixing,

(2) gas generator/

temperature thrust bility. efficiency cycle cost

effects;

subsonic

velocities/combustion nucleate boiling; and

to

produce insta-

requirements; The

(4) oxidizer of the

(5) combustion

development high

injector An

is critical

to achieve will

high packing increase life

and by

performance. combustion

inefficient

design

lowering

efficiency,

and reduce

reliability

because

123

of

increased

combustor

erosion. with

This

has

high

priority

because

of

the

historical 2.8.3 The processes

problems

associated Interaction

injector

development.

Combustion gas

generator

effluent chamber.

is

important

to

the

mixing

and

combustion release,

in the thrust

Incomplete

mixing,

nonuniform

heat cost

and short residence bility. tion

times

have a direct volume

impact

on performance

and reliainsulaor to

The gas generator combustor zones, flow

may have to be increased, reconfigured delivery to incorporate

excessive

added,

geometry and

flameholding in size it the

recirculation provide impacts generator 2.8.4 higher

oxidizer

components

increased

rates. and

Development pad abort

is a high due to the

priority feedback

because between

also gas

extinguishment and combustor. Combustor/Nozzle

(Regenerative

or Ablative) using both a regener(monolithic chamber life

The gas generator atively braided offers cooled thrust

hybrid point chamber

design was evaluated

(combustor/nozzle)

and an ablative cooled weight,

ablative) performance

thrust

chamber. by

The regeneratively reducing component improving chamber

thrust

advantages

reducing

cycle cost for a reusable ing exhaust bility and due temperatures. to single-piece cycle cost

system,

and possibly thrust

reliability offers and and

by reducreliadesign) pro-

The ablative construction to

improved simple

(no delaminations raw materials

low life

due

inexpensive

automated

cessing. at the

An ablative size for and

thrust

chamber conditions booster.

needs to be developed for the hybrid

and/or it be

demonstrated is more cost

operating

since will

effective under program Solid the

an expendable technology

The MBA at MSFC

approach for ALS

investigated This for ALS Large

focused

programs

boosters. and Nozzles hybrid

(Low-Cost, Rocket

High-Reliability NRA-89-MSFC-1) the exhaust will

Cases, will

Insulation, complement for the

Motors;

the

technology

efforts,

but because

environment be different

hybrid

is oxygen-rich, fibers,

the development variable 2.8.5 ARC Ball

requirements geometries, Development

from ALS.

Alternative

component Turbopump has

and case attachments

will have to be developed.

selected

foil-bearing have

turbopumps demonstrated

for poor

the

hybrid

point and

design. operating was

bearing

LOX turbopumps

durability

life was short

and unpredictable

in some programs.

The poor reliability

124

17,18,19,20,21 primarily due to the premature failure of the ball bearings. The life cycle cost and reliability objectives for the hybrid depend on the use of foil bearings. Foil bearings have accumulated approximately 510,000 hours of operation in small pump applications. This pump offers cost and reliability improvements comparedto current ball bearing pumps, but a system sized for the hybrid requirements has not been developed or demonstrated. 2.8.6
The Trid_ne Tridyne in Expulsion system subscale Tridyne System proposed hardware consists to form Development for by oxidizer AeroJet expulsion but was was developed and in an

demonstrated operating and 0.03

never

installed

system. moles

of 0.91 moles

helium, mixture

0.06 moles

hydrogen, at

of oxygen The energy bed. Gas

a nondetonable by passing are cost

that can be stored through the

high pressure. num catalyst

is released

the mixture by

a platireactant over

temperatures system offers

controlled and

varying

mixture. cold

This

Tridyne

reliability

improvements volume

gas or solid

gas generator

systems

because

of the lower number

require-

ments for the high-pressure 2.8.7 Thrust Vectoring This Fluid method of Vector of the

helium

and the reduced

of components.

Control nozzle vector is common control practice adds for solid cost because An FITVC rocket to boosters. design. the

thrust TVC was

weight

and

the

injection

baselined

in the point from 0.987

design

it raised system

calculated

predicted

reliability

to 0.995.

using

17.

Gass, F. D., Alcock, J. F., and Flickinger, S. A., "Space Shuttle Main Engine - Alternate Turbopump Development Health Monitoring Program," AIAA-S8-3411, 24th Joint Propulsion Conference, July 1988. Hale, J. R., and Wood, B. Y., "Operational Life Improvement Pressure Turbopumps," paper presented at 36th International Federation, Stockholm, Sweden, October 1985. Childs, D. W., and Moyer, D. S., "Vibration Characteristics of the SSME," paper presented at the 2gth International Conference, June 1984. Merrimar, Cryogenic T. L., and Kannel, J. W., "Evaluation Fluids," ASLE Preprint 85-AM-1F-1. of SSME HighAstronautical

18.

19.

of the HPOTP Gas Turbine

20.

of EHD Film Thickness

for

21.

Duframe, D. D., and Kannel, J. W., "Evaluation Bearings," NASA Contract Report CR-15096, November

of Shuttle 1978.

Turbopump

125

LOXoffers
will 2.9 2.9.1

simple during

design

with

low life

cycle

cost.

If the system degrees

require-

ments defined

Phase 2 permit,

a system

with three the booster

of deflection and cost.

be investigated Acquisition Plan

as a means of improving

reliability

Introduction The Phase 2 Hybrid Propulsion Technology Program study efforts are planned as a

two-part, ment, and

33-month

experimental

and analytical components with

for the design, key technology delivery

developissues system.

investigation

of critical hybrid

for the

affecting

the gas generator

a pump-fed

oxidizer

This propulsion and lowest

system was selected in Phase

because 1 trade will

it offered studies. consist

the highest

reliability

life cycle cost

Part A, which will fabrication, ual cost critical

last 23 months,

of component

development, individand (see

and demonstration; hybrid components determined

the goal of Part A will consistent in Phase with 1 the

be to develop

safety,

reliability,

considerations

Technology last

Identification

Section

2.0 of this report). interactions,

Part B, which

will

10 months,

will consist This reliaan of

of component part will

performance

assessment, to

and system the

scale-up. safety,

demonstrate cost

interactions for the

critical booster that

achieving

bility,

and of

goals

system. remain

It will

also

provide

assessment

the development

risks

but are beyond

the scope

Phase 2.

A program schedule is presented in Figure 78.

It shows major The four

tasks

to be performed in each phase and includes milestones. program elements are:


Point Design Updates Development, Fabrication,

principal

Part A Component Propulsion

and Development

System

Development and Characterization

Fuel Development Oxidizer Material Studies

Screening Studies

Combustor/Nozzle TVC Design Design Studies

Injector -

Injector

126

FOLDOUT

FRAME

Task

Phase
,, ,. ,

2A

Month
Point Design

,12 ]_14151oI_I_ I Iiol,, [,21,31 ,o1,71 ,_1,51 _81191


4
A
I

_A , i ,,,..
and A
I

Fuel Development Characterization Oxidizer Material Studies Screening

9
I

m Work
i

Combustor/Nozzle TVC Design

m I

3
Injector Studies Studies Integration Combustion

7 8

11
'I r
,, I

Phase A Subscale

,It----

Phase

B Component

Integration

Risk Assessment 1 Propulsion System Integration


I

Phase 3 Planning
I

Facility '";-_r

Requirements Delivery

10
I

12

,J
o__j L_//

j14_'_

---w

j_

FOLDOUT

FRAME

Phase

U Milestones contractor;

1. Hardware integration with system detail point design. - LOX tank and auxiliaries Injector design Igniter design Gas generator TVC

Recovery system Combustion chamber/nozzle

design and

2 Update design to incorporate fuel, combustion, injector studies 3. Fabricate subscale injectors 4. Complete preliminary fuel development studies measure efficiencies. 5. Fabricate subscale combustor nozzles.

to

16
14
I

19

20

21
t

18

6. Complete review with NASA of test plans. 7. Complete subscale injector tests. 8. Integrate subscale injector with gas generator and combustor/nozzle. 9. Finalize gas generator design. 10. Finalize oxidizer system design. 11. Complete injector design. 12. Interim review with MSFC to present results and future plans. 13. Complete changes as a result of MSFC review. 14. Complete fabrication of 100-k thrust motor hardware. 15. Integrate SE&I input into the point design. 16. Complete component testing. 17. Complete development of full-size oxidizer

22

24

w
v

turbopump. 18. Complete assembly of 100-k motor, oxidizer delivery system and stand. 19. Demonstrate thrust termination. 20. Demonstrate gas generator extinguishment. 21. Demonstrate performance. 22. Complete hybrid system manufacturing plan. 23. Complete hybrid design. 24. Formal review with MSFC to present Phase II results, documentation, and Phase III program plan.

Figure

78.

Program

schedule.
(_90-HYBRID RPT

127

Gas Generator/Combustion Combustion Subscale Studies

Chamber

Interaction

Demonstration System System Development Performance Assessment and System

Oxidizer Part B

Delivery

Oxidizer

Delivery

Component

Interactions,

Scale-up Component Integration

Risk Assessment Phase 3 Planning

Programmatics These interaction between soon as Propulsion Facility elements between System Integration

Requirements will be investigated in parallel will efforts. The technical Interaction be tested an as

the experimental injector, testing of

efforts

be emphasized. chamber will

the gas generator, practical. The

and combustion functional

interaction occur 79.

between

active

oxidizer

system and the propulsion

system will

in Part B. Direct and frequent MSFC deci-

A program involvement sion points. Initially, Second, fuel

logic flow is presented and informal

in Figure

via formal

reviews

is planned

at all critical

the and

point

design

developed

in

Phase

will be

be

updated.

oxidizer

experimental

investigations areas

will

undertaken. defiand LOX.

Exploratory nition. definition Components generator

tests will tasks the be

be performed will

to identify by more

requiring

further

These of

be followed plate

detailed

characterization of injecting with

injector

and method separately at

and

location

will to

investigated

and a

then

integrated

the gas [B8,g64N

demonstrate of thrust, integrate (100,000

capability 127 centimeters the key

subscale

level,

(20,000 pounds) Part nominal hardware. assess ducted B

(50 inches) into 190.5

hardware). an overall system (75 at a

will

components thrust,

444,822N

pounds) testing of

of

centimeters will be

inches) to con-

Verification performance. test.

integrated

motors

conducted will be

system for each

Ballistic Research to

and reliability Corporation the

analyses

Atlantic approach

will

incorporate of

a probatests

bilistic

reliability

verify

number

integrated

128

FOLDOUT

FRAME

4 0 Task 1 Point Design

Program Review

1 Task 2 Fuel Develop Characterize

12 Task 8 Combustion Studies

d
/ 2 18 12 Program Start I Combustor/ Nozzle Studies Task 5 Task 5 Combustor/ Nozzle Studies Task 3 Oxidizer Studies 12 Task 7 Injector Studies Task 12 Oxidizer Delivery System 20 Task 4 Material Screening 2

Propulsion Start Subcontracts

System I

Turbo

Pump

Development!/ Task 13 Facility Requirements _ I/

:"'t

"

34

Fuel Develop and Task 2 Characterize

End Phase

II

1, _ ,
j I 16 Design
/

3, t
Review 31 Pro .gilm

V Point / Program Review

Task 5 Combustor/ Nozzle Studies __ [ 4

Design

Point 10 Task 10 Phase B Component Integration

18 Task 9 Phase A Subscale Integration

I
23

21

2 Point Design r

24

Fuel Develop and Characterize 24 Task 12 Oxidizer Delivery System

Program Review

Figure 79.

program

logic flow.
01 gO-HYBRID RPT

129

required verify will

to demonstrate

reliability.

The test

results

will

also

be used

to

life cycle cost equations as an

and results. part of

Life cycle

cost and reliability activities. The

be calculated

integral to MSFC

the point

design

results

will be presented on the work

at each formal

review. in the following in Phase II. sec-

Details tions. 2.9.2 2.9.2.1 A

to be performed

are discussed

Table 29 summarizes Program Tasks

each task that will be completed

Point Design POINT DESIGN

Updates WILL BE

(Task I) DEVELOPED FROM THE PHASE I RESULTS AND

UPDATED

AS COMPONENT

DESIGN

AND DEVELOPMENT

MATURES

AND AN OPERAT-

ING SYSTEM A point point design

IS SELECTED. will be developed for the selected configuration. and materials The

design will

include

system

geometry,

components, cost,

of con-

struction;

weight

breakdown;

performance,

and reliability

estimates;

Table 29. Task I 2 3 4 5 6 7 8 g 10 11 12 13 14 15

Phase

II Task Summary. Title

Point Design

Updates and Characterization

Fuel Development Oxidizer Material Studies

Screening Studies

Combustor/Nozzle TVC Design Injector Studies Combustion Subscale Oxidizer Component

Studies

Demonstration Delivery System Development

Integration

Risk Assessment Phase 3 Planning Propulsion Facility System Integration

Requirements

130

structural and thermal analysis; and specifications. The following design parameters will be evaluated relative to their impact on system parameters. Operating pressure Length-to-diameter ratio Oxidizer-to-fuel mixture ratio Structural requirements TVCrequirements Start-up; shut-down; extinguishment requirements Expendable; reusable requirements

Operating pressure will be optimized by analyses to determine the weight/ pressure/reliability/life cycle cost sensitivity of each system component. The individual sensitivities will be subjected to variational computation to maximize reliability and safety at its lowest attendant cost and weight. Length-to-diameter trades will be madeusing the Boeing trajectory model, NTOP, to evaluate aerodynamic loading on the system to minimize cost and achieve the performance goals. Oxidizer-to-fuel mixture ratio will be analytically evaluated to determine performance sensitivity during transients, impacts on turbopump design and operation, and booster size.
Booster stiffness, thrust structural stability grain, bond will be analyzed system, nozzle to verify design internal loading, and

propellant

and attachments,

transfer design

to the case. will be finalized based on MSFC requirements, trajectory will define

TVC analyses,

and projected

booster

thrust mismatch.

The requirements

FITVC can be utilized. Combustion design, igniter, modeling will be analytically rate exponent extinguishment thrust optimized to determine the grain

and burning

to meet will

the start-up

and shut-down the on-pad

requirements.

Gas generator and flight will be

be modeled

to meet

abort requirement The tivity of design a

termination. by an analyses updated to determine mission against model. the cost This sensiwill system. be

optimized with

reusable

system

evaluated

using the updated

design

parameters

the expendable

131

The point design effort

will

be initiated

immediately following

contract

award. This design will be updated three different times during the program and presented to MSFC. Life cycle cost and reliability calculations and updates will be an integral portion of the point design activities. 2.9.2.2
Fuel Development and Characterization (Task 2) ARE ESSENTIAL TO

FUEL DEVELOPMENT AND PROPERTIES CHARACTERIZATION FINAL CONFIGURATION DESIGN In the gas generator mary combustor (gas hybrid, a fuel-rich The

propellant exhaust with

is burned is

in a priinto a

generator). (thrust

fuel-rlch

directed

secondary expands

combustor

chamber)

where thrust.

it reacts

liquid

oxidizer

and

through

a nozzle gas

to produce generator with equal

ARC's

baseline

incorporates molar amounts

a fuel-rich

propellant

grain to

that has been formulated produce less than

of AP and sodium

nitrate

l-percent

HCI in the exhaust. (300 psia), to 1.27 have

The gas generator high ejection

is required and a

to extinguish burning second). rate

below 2.06 MPa between 0.76

efficiency, to

centimeters/second

(0.3

0.5 inches/

The fuel grains and evaluated the ingredients Our primary performance problems. tion. gated impact To as on in this

to be used task.

in the gas generator initial I. grains will

hybrid will be developed be formulated utilizing

The

specified approach

in Phase

is to develop

a non-metallized injector develop

fuel

that meets

the

requirements, This

but does not create will be used potential, because they to

erosion the

and deposition configurabe investiTheir

formulation future

injector will

provide

growth

metallized offer will

fuels

a secondary life cycle

approach cost and

higher

performance.

reliability

determine

if the development

should continue. The gas that have generator formulations and for this program for are derived from fuels

been The

formulated two variants

characterized are

different 399 and

applications, ARCADENE for the This 246. Fixed

Table 30. ARCADENE Flow tion 399

selected

ARCADENE

is a fuel-rich Rocket Program

gas generator (Contract Number

propellant

developed

Ducted gave

F33615-77-C-2057). rocket

formulahardware gas

good in

performance tunnel

in full-scale tests at AEDC.

ducted

flightweight

(DRPTV)

wind

ARCADENE

246 is a conventional

132

Table 30.

Gas Generator

Fuels.

Fuel Rich Binder HTPB CTPB PBAN Solid Oxidizer Fuel % Polystyrene Poly Poly Op %/oC rlO00 cm/sec (,-Methylstyrene) (Methyl Methacrylate) 30-45 34-40 34-40 0.16 - 0.34 0.47 0.32 - 2.62 - 0.58 _ 27-37 % 22-26 22-26

Conventional

21-30

21-30 60-70

0.16 - 0.22 0.1 - 4.54 0.22 - 0.39 0 - 3

_k %/C Motors Catalyst %

0 - 3

generator

propellant of

based

on

PBAN Silo This rates

binder. Lid

ARCADENE Door Opening

246 was

developed and the

for MX

pressurization Buried history Trench

the

HARDROCK

Actuator

Weapon

System. burning

gas

generator

propellant

provided

a good

of reproducible with

and ejection

efficiencies. will be modified of each

Beginning stepwise,

the existing one component

database, at a time

the formulations to evaluate

changing

the effects for

change/substitution application, formulations tive binders properties, propellant Each binder

required 31.

to achieve The planned These f_rst

a suitable changes eight

propellant

the hybrid eight

see Table

are listed

as the first

in the table. for evaluation and

changes

consist

of (i) alterna-

of their

impact

on ballistic required to

and ejection/residue achieve a "clean"

(2) oxidizer

modifications an exhaust to be

(one which yields grain formulation serves

free of all HCl). consists of one or more for primary fuels; a

screened

which

also

as a fuel;

an oxidizer ejection

necessary

combus-

tion of the solid grain and subsequent species modify into the secondary combustion combustion

and expulsion and

of the fuel-rich necessary to

chamber; such

catalysts rate.

the primary

ballistics

as burning

The preferred

133

Table

31.

Compositions

to be Screened.

Fixed Level Formulations Binder CTPB HTPB HTPB PBAN PBAN HTPB HTPB (R-45M) (R-45M) (HC-434) (R-45M) (R-45 HT) Fuel PS PS PS PS PS PS PS

for Reference Additive Fe203, Fe203,

to Database Oxidizer AP AP AP AP AP + NaNO 3 AP + NaNO 3 AN Baseline Ref to 399 Database Ref to 399 Database Ref to 246 Database Clean Clean Clean Variant Variant Variant

CFx/AI CFx/AI

Fe203, CFx/AI Fe203, CFx/AI

Fe203, CFx/AI Fe203, CFx/AI Fe203, CFx/AI

Formulation

Variations

For Screening (1) Additives (Catalysts) (2) Oxidizer (3)

Binder

Fuel

Fe203

HTPB HTPB PBAN

(R-45M) (R-45HT)

PS PS PS PS + Mg PS PS + Al Mg Mg Al

X X X X X X X

AP + NaNO 3 AP + NaNO 3 AP + NaNO 3 AP AP + NaNO 3 AP + NaNO 3 AP AN

HTPB (4) HTPB (4) HTPB (4) HTPB (4) HTPB (4) HTPB (4)

AP + NaNO 3

1.

CFx/AI

will

be

evaluated

at

O,

2,

and

5 percent

in

selected

candidate

formulations 2. 3. 4. Additive Oxidizer

for effect on secondary (not in combination):

combustion. Fe203 = O, 0.5, 1.0, 2.0 percent.

levels levels:

25, 30, 35, 40 percent. based on previous results.

R-45M or R-45HT

134

binder

is HTPB

(R-45HT

or R-45M).

Fuels

include

polystyrene as a chlorine to achieve

(PS), Al powder, scavenger. adequate The

and Mg powder burning rate rate

- the last of which catalyst is Fe203,

also functions it is required

burning little com-

and ejection effect

properties.

CFx/AI

is also Since

a catalyst, it functions

but has very as a secondary

if any bustion

on primary it will

combustion. be evaluated secondary of

catalyst,

at low levels combustion. 399

in selected

formulations

to determine

if it enhances evaluation during

A limited corporate binder AP; IR&D

an ARCADENE This

formulation consisted

was completed of 25 percent 21.5 CFx/AI.

under HTPB

1989.

formulation 34

including percent

3 percent NaNO 3,

plasticizer; iron

percent and

polystyrene; 2 percent

percent Pint

15.5

2 percent

oxide,

mixes were 1.38

of the formulation cut from the cartons to 13.76 MPa

were made and cast and tested 2,000

into cartons.

Samples

of the fuel [from of

in a strand burner The strands

at six pressures had a burning

(200 to

psia)].

rate

0.38 centimeters/second (1,000 psia). A limited Further,

(0.15 inches/second) they would of not burn

at a chamber

pressure

of 6.88 MPa

below 3.44 MPa (500 psia). 246 formulation formulation The was also completed of 20.3

evaluation

an ARCADENE Curing 1989.

under corporate percent rate AP, 14.7 than

IR&D funding percent 0.25

This

consisted

NaNO 3, 65 percent

PBAN.

strands

had a burning at a chamber

less

centimeters/second Further, will the strands require

(0.10 inches/second) would not burn below rate tailoring

pressure Both

of 6.88 MPa. formulations however,

3.44 MPa. to meet the

burning

requirements;

both fuels can meet the extinguishment of Fuel Properties consists type - The initial a small strand step

requirements. in characterizing proa wide which charsensi-

Characterization each fuel formulation ejection, range,

of the making and amount,

mix and evaluating rates over

cessing, pressure

residue

burning

and rapid

pressure

(Pd_) extinguishment. test results

Formulations will be further temperature

show promise acterized tivity of

and have

acceptable

screening

for ballistic burning and from rate,

and combustion motor

properties

including

performance properties, will also

and ejection/expulsion and be mechanical characterized

efficiency, The

ignition effluent and

extinguishment the fuel

properties. for

generator

temperature and tensile the most

composition. will be

Combustion conducted

characterization, to quickly

extinguishment, assess

testing promising

in parallel candidates.

and select

fuel formulation

135

Initial in the

Screening Baker

- For the Perkins

initial

screening,

a small

mix will

be made

one-pint

mixer.

If end-of-mix be cast

viscosity

and processing After (at cure,

characteristics ambient under ejection

are acceptable, properties (in

the mix will air),

and cured.

residue

characteristics and strand MPa

pressure rates psi)] from

nitrogen),

Pd_ extinguishment pressures

characteristics, 1.38 to 13.76

burning

in duplicate wlll

at seven

[from

(200 to 2,000 characterized

be determined. (1-gallon) (ESD), or

Promising mixes.

formulations tests

wlll be further [impact, on

larger

Sensitivity will be of

friction,

electrostatic containing new

discharge ingredients level.

and

DSC]

conducted ingredients

formulations

new combinations

to establish

potential

hazard

Combustion acceptable burning testing

and

Ballistic

Characterization and for

which will

Formulations ejection, be subjected (10-pound)

which residue, to

have and

processing

characteristics, are deemed

rate

properties

adequate, Nominal

further in

for combustion

properties.

4.5-kilogram

grains

15.2 centimeter to determine

(6 inch) diameter performance

6C4-11.2 including

Rohm and Haas hardware C* efficiency,

will

be used and

motor

burning

rate,

motor

expulsion

or ejection and these burning

efficiency. data will

An eroding be used

nozzle throat

will

be used rourange

in these tines

firings,

in our ballistic over

computer

to determine

rate and pressure

exponent

the pressure

of the firing. Selected timeter 3 to grain rates 11 candidate formulations will also be cast to produce testing in into 7.6 and 22.9 cengrains The

(3 and 9 inch) diameter kilograms in weight tested verify of 52

cartridges for later

center-perforated heavywall the hardware. higher

configurations required to

will

be designed the

to produce from

mass-flow motor grains

and

scale

results grains

the

4.5 kilogram

firings.

A total

7.6-centimeter

and 21 22.9-centimeter

will be cast for Task 4 testing. Extinguishment terization boundaries a studies, will In parallel with the combustion and ballistic charac-

the effects

of compositional The 4.5 kilogram be be used to

variations

on extinguishment with test

be established. design will

Rohm and Haas hardware the Pd_ screening an initial

regressive The

grain nozzle

verify

results.

throats

will well,

sized

to generate

pressure with The

level at which time due to

the fuel burns

with area,

subsequent until

decrease

in pressure

the regressive

surface

the grain

extinguishes.

136

pressure decay rate will

not be sufficient

to determine dp/dt extinguishment,

but the results shall be correlated to Pd_ measurements. Confirmation tests will be repeated later in 22.9-centimeter hardware on selected candidates.
Ignition combustion deficiency. relatively As teristics will Fuel-rich, gas generator propellants propellants and exhibit more marginal

characteristics The fuels

than conventional to be more

due to their oxidizer slower to ignite. A

tend pyrogen

difficult

long-acting of the

will probably testing, duration, ARC

be required will define

for this system. the igniter The of gas characresults

part

subscale rate,

required as

(flow

product

composition). version larger

be used

inputs to of

for calibration predict the the

of a modified for

the Cavenygenerators. be made in

Kuo 20 ignition Confirmation

model tests

requirements motor

15.2-centimeter

results

will

22.g-centimeter Physical specimens, one

hardware Property strain Based

to fine-tune Testing -

the model Class

for the full-scale C tensile will will tests

definition. (triplicate on selected to improve extensively

JANNAF

rate, three on these

temperatures) tailoring

be conducted be performed be more seven

formulations. and optimize

results,

tensile

properties.

Final four

candidates strain

will

characterized Additional for dynamic rheological expansion, candidates. Bondline liner and double-lap

(triplicate

specimens, of final

rates,

temperatures).

characterization mechanical properties. and DSC

candidates

will

include

use of the RMS-4 viscometer for

properties Glass

and gel time,

and the

Haake

transition

temperature, will

coefficient

of thermal on final

and TGA

thermal

profiles

also be determined

properties

between

promising also

fuel

formulations using

and

candidate

insulation

materials

will

be evaluated

bond-in-tension,

shear, and peel boat specimens. Characterization to provide - The effluent on from the gas generator will be

Effluent characterized and (3) nature

information

(1) temperature;

(2) gas composition;

and size of condensed

species.

20.

A. Pertz, L. H. Caveny, K. K. Kuo, M. Summerfield, "The Starting Transient of Solid Propellant Rocket Motors with High Internal Gas Velocities," NASA Grant NGL 31-001-109, Aerospace and Mechanical Sciences Report No. 1100, Princeton, April 13, 1989.

137

For characterization

of the effluent,

we will

use isokinetic

sampling of

an unchoked stream (produced by firing into a pressurized tank with controlled venting) at several gas generator pressures. Gaseous products will be analyzed by standard laboratory techniques. Gas temperatures will be measured using embedded thermocouples and radiometer measurements. Collected particulates will be sized, and the fractions will be chemically analyzed to determine composition. The results will be used to define the injector requirements. 2.9.2.3
Oxidizer Studies (Task 3) THE HEAT TRANSFER COEFFICIENTS FOR THE

OXIDIZER

STUDIES

DEFINE

DESIGN OF A REGENERATIVELY COOLED COMBUSTORAND NOZZLE. The point design cooled The meet developed thruster is in Phase I includes the option to of using a

regeneratively cycle cost. to

(combustor/nozzle) because thrust

with of the

LOX

improve

life

design

complicated regressive

oxidizer At the

throttling lower oxi-

required

the prescribed film boiling

trace.

dizer flow rates, Oxidizer be used as

of the LOX may occur. the necessary the if data to determine cooled if LOX can and is

studies the

will generate fluid for

cooling will be

regeneratively the

combustor nozzle

nozzle. selected

This

performed

regeneratively

cooled

for development. Measurements - Benefits for the system may be achieved nozzle. The Phase with

Heat Transfer

the use of LOX as the coolant design 4.65 is based (675 on chamber to meet

for a regenerative variations

1 point to

pressure the

from

8.95 MPa trace.

(1,300 psia) At these

MPa

psia)

required

thrust-time

presthe

sures,

the LOX would begin to

still be liquid; boil. Heat

however, transfer

at slightly coefficients

lower pressure, must

LOX will

film

be determined and

experimentally nozzle. A flow

to determine

if it is still

possible

to cool

the combustor

reactor

will

be

designed,

fabricated, LOX will

and

instrumented at various

with rates

thermocouples through

and pressure

transducers.

be flowed

a heated furnace

to simulate

the combustor

temperatures.

The temperato deter-

ture of the LOX will be measured mine the thermal coefficients

at several

flow rates

and pressures

during

boiling.

138

2.9.2.4

Material

Screening FOR

(Task 4) COMPONENT TECHNOLOGY DEMONSTRATION WILL BE

CRITICAL SCREENED. Before combustor combustor

MATERIALS

integration and nozzle,

tests and

are performed, to

the

ability in

of the

the gas

insulation, generator/ within the

composites

function

environment

must be verified. range from

The critical strongly

environments to

gas generator ing. result The

and combustor tank

oxidizing

strongly

reduccan

oxidizer

materials

experience

cryogenic resin

temperatures system. will consist

that

in embrittlement of nozzle

of the epoxy and oxidizer

or polyimide tank

Screening ing test factured AS4 FMI

composites Nozzle mold.

of prepar-

specimens

of the systems

considered.

specimens

will be manu(Hercules and

in an 20.3 centimeter and

(8 inch) square fibers

Two PAN fibers

and Amoco T650-35) High Purity Quartz) Five

two quartz be

(J. P. Stevens using each three

Astroquartz

will

investigated specimens of

different system shear.

phenolic will be

resin tested erosion

systems. for thermal

duplicate

material and

erosion,

tensile,

compression, the samples be

impact

Thermal exhaust.

will

be tested tank

by subjecting will

to the hybrid motor into fibers using 30.5

Oxidizer (12 inch) Apollo resins. duplicate pression,

specimens

manufactured

centimeter T650/42,

square

sheets.

Three

intermediate-modulus be investigated 15.2-centimeter system will

(Amoco

43-750, The

Hercules sheets will

IM-7) will be cut

epoxy

and polyimide squares. Five com-

into

(6-inch)

specimens impact,

of each

material

be tested

for tensile,

shear and chemical that will

stability be tested EPDM.

at ambient include Test

(298K) and 78K. (HTPB with glass

Insulation microballoon mer

materials

ARCTIP specimens of the

fillers), will be

and Kevlar-filled installed at the

of the elasto15.2 centimeter and after the

candidates

exhaust

end

insulation test.

screening

motor.

Dimensions

will

be measured

before

Thermal ical made, results.

properties Heat

of the materials and

must

be established diffusivity

to verify

analytwill be

capacity will

thermal

measurements design.

and the results

be incorporated Studies ABLATIVE (Task 5)

into the point

2.9.2.5

Combustor/Nozzle BRAIDED

A MONOLITHIC DEMONSTRATED.

THRUST

CHAMBER

WILL

BE DEVELOPED

AND

139

ARC's hybrid
(MBA) thrust extension in resin cone. matrix.

fuel

booster incorporates
The MBA is an of integral

a monolithic
combustion

braided ablative
nozzle, and architecture structures, The MBA due to

chamber.

chamber,

It consists This

a three-dimensional design requires

(3D) braided no secondary

one-piece

insulators, thrust Joints ciated

or complex achieves paths,

assembly

of flame-surface

ablative

components. failure modes

chamber and with

high reliability secondary bonds,

by eliminating and

leak

delamination/ply-liftlng laminated ablative

asso-

conventional,

two-dimensionally

components. fiber in

The design a phenolic

of the combustor/nozzle resin selected to

for the hybrid minimize the

incorporates effects of

quartz the

oxidizing

environment. Development through of the MBA thrust quartz-phenolic chamber material will proceed in a stepwise testing, manner

3D-braided and Thrust

properties

reliability test bed procon-

development firings. cesses, currently

design/process chamber design

validation and

via seven

subscale

engine

analysis will

methodology, be developed The will

manufacturing and matured MBA

and product during

evaluation course

techniques of this

the

program. techniques

full-scale be refined

design,

manufacturing points and

process,

and evaluation to reflect

at specific chamber cham-

in the program

increased

understanding

of the thrust

booster

requirements.

Verification/demonstration subscale firing

of the MBA thrust II.

ber will occur Material

in an integrated Properties

at the end of Task

Analysis

and Testing and testing activities to establish an

ARC will conduct initial rials to database

design,

analysis,

for the quartz-phenolic mechanical, thrust thermal chamber

MBA material

properties. will of

MBA mate-

physical,

and erosion design and

properties refinement

be determined the full-scale

support

subscale

point design.

The following

tasks will

be performed:

Micromechanics

modelling

Test plan definition Physical, Subscale mechanical erosion and thermal properties testing and evaluation

testing be developed Using quartz to describe the various braided

A micromechanics fiber architectures for the

model will available. selected

this model fiber

in conjunction resin,

with published MBA mechanical

properties

and phenolic

140

properties will be predicted. These properties the most appropriate braided architecture. Physical,
creation of a micromechanics variables

will

guide the selection

of

thermal, and mechanical testing


preliminary model material and properties prediction, properties. (9 inch)

of the MBA material database, of the

will

allow of the

validation effects of

assessment

process 32. used to

on material centimeter

A test matrix diameter hybrid series

is presented test motor

in Table will be

A 22.9 conduct

laboratory

screening

of an axial study. for

of cylindrical erosion with

specimens

from

the process the

parameter

variation

Measured correlation

data will predictions

be input to based on

aerothermal thermal

analysis

models

measured

properties. Testinq in and an Evaluation iterative Four subscale MBA thrust

Subscale chambers sequence subscale will

Component be

fabricated of

design-fabrication-evaluation test based series. on the Each successive motor

as part thrust

a reliability design

development be refined

chamber

will

preceding

test firing Six part will of

evaluations. subscale MBA thrust test chambers series. thrust will The chamber then be fabricated as

additional

a design/process according

validation

fabrication process

procedures

be frozen

to the subscale

specification

so that overall Table 32.

repeatability MBA Material Tests

of the process Characterization 294K 3 3 3 3 3 3

and performance Preliminary 2200K 3 3 3 3 3 3 3 3 3 3 3 3

can be evaluated. Test Matrix. 3033K 3 3 3 3 3 3 3 3 3 3 3 3

Hoop Compression Meridional Compression

Hoop Tension Meridional Axial Shear Radial Shear Expansion Expansion Expansion Tension

Hoop Thermal Axial Radial Thermal

3 3 3 3 3 3

Thermal

Meridional Radial

Conductivity Conductivity

Thermal Heat

Specific

141

All strain
each

ten

thrust
data, Pre-

chambers will firing.


along with and

be instrumented with Thrust,


hardware,

thermocouples and
strain gage, and following will

gages during the test


test.

pressure,
will (CT) for aid or occur

thermocouple

post-test

be analyzed

post-test and as

computed depth

tomography profiles will

inspection test

exhibit

surface of

recession article, signs

char

each

article. of CT if

Dissection evaluations any exist. development 2.9.2.6 A

each

appropriate,

in verification incipient during

and yield Updating

of anomalous

performance design 80. will

failure

of the full-scale

the subscale

phase as illustrated Vector Control BE

in Figure

Thrust TVC

Desiqn

(Task 6) LOX AS THE INJECTANT AND

DESIGN

WILL

DEVELOPED USING

INCORPORATED INTO THE POINT DESIGN. Several (FITVC) cation. fairly were They simple, designs for a by that fluid Allied injection Signal in thrust Phase vector control system

investigated determined reliable

I, Technology because duty

Identifia

LOX was the most Definition of

feasible the

it provided requirements, decision.

design.

total

and thus propellant In design optimum Changes will be this studies task,

usage, Allied

is crucial Signal,

to making under

a final

feasibility to ARC,

subcontract

will

perform the

of an FITVC system. of weight,

The final design development number on of risk,

selected

will provide and

combination in the system and

complexity, thrusters, cost,

cost.

pressure, evaluated

control basis of

and redundancy and

studied

the

reliability,

complexity. Allied develop Signal will assemble the hardware, fabricate A prototype thrusters, and

the electronic

controller

for the system. in Task

will be tested

on the 100,000 2.9.2.7

pound thrust Studies

test motor

II to verify

the design.

Injector

(Task 7) DROP AND SPRAY PATTERN MUST BE OPTIMIZED TO

INJECTOR PROVIDE

PRESSURE FILM COOLING

AND REQUIRED

MIXING. includes a multi-port combustion injector that

The gas generator separates chamber). ports. the gas

hybrid

point design from the

generator combustion the

secondary pass

chamber via

(thrust injector pressures

Fuel-rich Flow through

products is

into the combustor at normal

ports

subsonic

operating

142

Material Design

Characterization, and Analysis

Full.scale

Thrust

Chamber Design

and Nozzle

Analytical Prediction of Material Properties

I _..

I-"

Design Full-scale

Material Properties Testing

I _.

I-"

liD'[

Design Update Full-scale

Design and Analyze Subscale Thrust Chamber and Nozzle

Evaluate Subscale Test Results

_i

Design Update Full-scale

Design and Analyze Midscale Thrust Chamber and Nozzle

Evaluate Midscale Test Results

L
F" I

Update Design

Full-scale

Establish Final Design Properties

Full-scale Thrust Chamber Design and Analyze and Nozzle

Document Database

Detailed Full-scale Thrust Chamber and Nozzle Design

Figure

80.

Full-scale nozzle characterization,

design activi_ interacts with material desien, technoloev efforts.

0190-HYBRID

RPT

143

resulting

in an unchoked

injector;

pressure

changes

occurring flow rate

in the combustor is controlled and

are communicated modulated

to the gas

generator.

The fuel

by adjusting

the chamber

pressure.

This is accomplished

by changing

the LOX flow rate. This The tests for task will involves the evaluation of candidate a separate simulated oxidizer so plate injector will designs. be set up using

be conducted flow

at ARC, where to conduct This facility

facility cold flow will

storage

and

control

studies

liquid with

nitrogen our

and liquid static

oxygen. test

facility

be integrated gases with

standard

simulated

exhaust

entrained

particulates

can be used tests in to

in flow studies. are planned. 33 We will initially in evaluate the with the

A total of 75 injector injection water and variables liquid effluent shown nitrogen

Table

individually test cost.

and In

combination since

minimize

addition,

combustion carbon

from the gas generator we will also evaluate

will

contain

from

30- to 40-percent a hot, simu-

particulates,

the variables with

using

lated gas (compressed injection verify system.

air) that has been entrained final tests will

carbon using

using liquid

a metered oxygen to

The

be conducted

the results. oxidizer delivery system will be used to minimize system

A pressure-fed fluctuations. oxidizer to flow

Data from the tests will rate, high-speed mixing to Table Variable movies, As in

include still part

tank pressure

and temperature, traverses utilize study

photography, of this

and pitot ARC

measure

stagnant

zones. assist 33.

task,

will

combustion

consultants

the development

of our injector

Injector Variables. Number of Tests Per Series

Design Oxidizer/Fuel Flow Area Ratio Swirl (Inlet Angle) Impingement (Impact Angle) Shape Circular Pattern Diamond Pattern

(Orifice

Pattern)

6 6

Size Diameter (Orifice Diameter) Length (Orifice Slot Length) Angle of Injection 144

6 4

matrix. baffles,

The consultants will provide expertise injector posts, and 3-dimensional flowfield

with acoustic modeling.

cavities,

Injector plate modules (zone of 1-fuel and 1-oxidizer injector) will be tested and verified in the 22.g centimeter (g inch) diameter hardware tests. Wewill run cold-flow studies and then verify the results in the 22.9-centimeter hardware (approximately 27 tests). This iteration will produce an injector for the 127 centimeter (50 inch) diameter subscale and lgO.5-centimeter (75-inch) component integration tests. 2.g.2.8
Combustion Studies (Task B) INTERAC-

CHARACTERIZATION TION

OF THE GAS GENERATOR PRODUCTS AND THEIR IN THE COMBUSTOR IS ESSENTIAL

WITH THE OXIDIZER

TO THE DESIGN

OF THE INJECTOR AND OPTIMIZATION The combustion nature of the gas generator in the secondary

OF CONBUSTION EFFICIENCY. effluent is important Jets of to the mixing effluent and

processes

combustor.

and oxi-

dizer must mix completely zation expected require of the

(down to a molecular potential the heavily of

scale) the fuel

and burn for full utiliand oxidizer. fuel species It is

thermodynamic combustion of

that

laden

particulate

will

good mixing (limited

and sufficient by

residence of

time for relatively oxidizing species that to

slow particle the particle be

combustion surface). exposed to

microdiffusion in some for The cases longer flow

In addition, hot

it is

important for

the particles which to

environments

periods

ignition be such as

requires non-

controlled uniform

recirculation.

patterns

will

avoid

heat release

patterns. - ARC will use existing of three-dimensional the TEACH code) to computadevelop will be

Combustor tional fluid

Modeling dynamic

(CFD) to

codes

(offshoots

combustor

geometries

be tested. 21,22,23

As we

test,

the results

21.

S. P. Vanka, J. L. Krazinski, A. S. Nejad, "Efficient for Ramjet Combustor Research," AIAA 26th Aerospace Reno, Nevada, January 1988.

Computational Tool Sciences Meeting,

22.

S. P. Vanka, "Computations of Turbulent Recirculating Flows with Fully Coupled Solution of Momentum and Continuity Equations," Report, Wright Patterson Air Force Base, ANL-83-74. D. G. Lilley, D. L. Rhode, "Computer Code for Swirling Axisymmetric Recirculating Flows in Practical Isothermal Geometries," NASA Contract Report 3442. Turbulent Combustor

23.

145

fed back will

into the code to scaling

improve

the modeling for our results. larger

capability.

The updated

codes

provide

information

test configurations,

and will

be used to predict Experimental centimeter

our full-scale Test Section

- ARC

will with

modify

our existing

7.6

and

22.9 81. into

test motors

to be compatible heavywall The hardware will be

the gas generator, that

see Figure

The test motors different

are flanged

construction

can be assembled

configurations. A gas igniter generator mounted

will function Into

as follows: piece with the

assembled

a long spool

in the head flange. be directed orifice. into the hot combustion through gases. a nozzle insert. into an insulated test section and

The exhaust through

gases will

a flow control

Test teristics Table

Oxidizer

will be injected products will

Combustion

will exit the cavity be monitored. be monitored testing We will have and

Cavity pressure Oxidizer Matrix of with the the

flow rate will Exploratory candidate

using be

a mass flow meter. used to assess seven test the test characseries, with the

fuels.

outlined five

34,

7.6-centimeter to verify

hardware performance

series

22.9-centimeter ator development lel in Task 2. The first

hardware

and extinguishment. will be performed

Gas generin paral-

and propellant

grain

manufacture

series tests

of and

tests prior and

will IR&D

establish tests.

relationship also

between the

the test

7.6-centimeter hardware, provide data data

It will procedures. the

validate

acquisition, alternative

operating

Series effects

2 and of

3 will

on

fuels

and demonstrate behavior.

additives,

and different Series rate

fuels on combustion 4 will evaluate This

combustion will

extinguishment

as

the

oxidizer

flow

is shut off.

series

incorporate evaluate

the optimum

fuel formulations with the fuels developed in

developed used Task

in Task 2. 4.

Series Series

5 will 6 will

combustor the

geometry designs

in Series 5. Series

evaluate

injector

7 will

complete

the fuel

7.6-centimeter formulation 5 and 6. from

hardware Series

tests.

The

series the

will

integrate

the optimum

I, 2, and 3 with

injector

and combustor

from Series

146

Cartridge Loaded as Generator Grain Combustor

(4)

(2) Injector Heat Loss Thermocouples

Typical 7.6 cm (3 in) Test Set-up

Cartridge Loaded Gas Generator Grain , LOX Injection

/
__ _

/-0
--11_

,,,
N_
Thrust (2)

(_

121

_Thermocouples Injector

Typical 22.9 cm (9 in) Test Set-up

Figure

81.

Test motor

hardware.

147

Table 34. Series

7.6- and 22.9-Centimeter Objective

Diameter

Test

Matrix. Tests 6

Relate IR&D activities. Validate hardware, instrumentation. Measure combustion efficiency. Relate Relate 3 Relate Relate combustion combustion combustion combustion to fuel type. to additive content. to solid oxidizer content. to oxidizer particle size. to extinguishment. efficiency. versus injector versus oxidizer thrust at fixed pressure drop. spray pattern. O/F ratio.

10

10

4 5 6

Relate fuel formulation Relate Measure Measure Measure

6 4 6

stay time to combustion combustion combustion combustion efficiency efficiency efficiency,

6 3

Duplicate Series 7 with Validate 7.6-centimeter Measure combustion

22.g-centimeter hardware. hardware results. thrust versus gas generator

efficiency,

grain design. 10 11 Verify Measure gas generator efficiency extinguishment. at three different O/F ratios; 6 6

and thrust

run duplicate 12

tests. at programmed O/F ratio to 6

Measure efficiency and thrust verify repeatability.

An will

additional

five-test

series

with

22.g-centimeter

diameter diameter

hardware The

be performed

at the conclusion verify

of the 7.6-centimeter

tests.

first series meter tests. data

(No. 8) will The remainder for the

scalability

of the results diameter

of the 7.6-centitests will provide of the gas

of the 22.g-centimeter modeling, verify

scaleup generator fuel

combustion

extinguishment

with termination

of oxidizers

flow, motor

and verification thrust.

of oxidizer-tobe used to

ratio by measuring the point design. final testing of

the resultant

The data will

update

The

in the 22.g-centimeter combustion to process. identify

hardware We will

will use

involve

repeata-

bility/stability response pressure

the

high-frequencybetween

instrumentation

combustion

instability

148

the

gas

generator

and

combustor. Since

Pulser natural tests

testing

will

be

investigated are dependent ensure that

to on the

define scale, system 2.9.2.9

stability

margins.

frequency may be

concerns to

short-duration has an adequate Subscale

full-scale

required

safety margin. (Task g) 8B,964N-THRUST SUBSCALE

Demonstration

ARC WILL UTILIZE

A 127 CENTIMETER DIAMETER,

TEST MOTOR TO EVALUATE THE GAS GENERATOR/COMBUSTOR PERFORMANCE. The objectives Establish Evaluate of the 127 centimeter baseline performance. (50 inch) subscale tests are to:

the injector. combustion stability.

Demonstrate Demonstrate

extinguishment. will to be be written run and at the start their of the task. facilities, procedures. the 88,964N (20,000 flow a The plan proce-

A detailed will dures, A identify updated 50-inch

test plan the tests

objectives, and analysis

schedule diameter subscale to

and data gas

acquisition, is tests

generator

required to

for

pound)-thrust rates

demonstration scaling. steel motor

provide

sufficient design will

mass

and thrust

verify

The demonstration case flanged

utilize

cartridge-loaded bility,

heavywall

to provide

geometry

flexi-

Figure 82.

ARC engineers

will perform

detailed

structural

and thermal

-L I/////zJ i__A

Oxidizer Injector Plate

MBA Combustor

70 in Diameter

--I-t'1- '
-Figure 82. 75 in Full Length 50 in heavvwall subscale 149 demonstrator =-

olBin _L_,_'_I Throat Diameter >,.,,_-_.,_N_,_',,,_ MBA Nozzle

motor.

analyses, document

and use computer the hardware will

aided

design

and manufacturing fabrication.

(CADAM)

software

to for

drawings be cast sleeve

for component and cured

The fuel grains (40 inch)

the gas generator sleeves. Each

in 102 centimeter using x-ray

phenolic NDE

loaded

will

be inspected

and ultrasonic

prior to being A

insulated

and loaded MBA at ARC.

into the hardware

for testing. will be braided, will be

cartridge-loaded and densified in Task motor 7. be

combustor/nozzle The fiber

insert

inspected, specified The supplied include pressure

selected

for the preforms

will

mounted

horizontally

for

testing. system. flow

Oxidizer

will

be

to the motor axial thrust

using

a pad-mounted pressures,

delivery oxidizer case

Measurements inlet

will

chamber

rate,

oxidizer

and temperature, of planned 35. and

and gas generator tests The with

strain measurements. integration test motors of the is gas comgas be

The matrix summarized generator, ponents generator replaced for

the subscale will

in Table injector, Part be B,

tests

demonstrate all of

the scaleup which are

combustor/nozzle, Integration verify

critical only the

Component to

tests.

Initially, The

will with

tested

its performance. The fuel mass flow

injector

will

a regressive

nozzle. rates.

rate will of subscale

be measured demonstraevaluate

and compared

to the required evaluate

The first assembly.

series These

tion tests will the two most Series thrust) strate

the injector

six tests will

promising 2 evaluates

injectors

from Task 5. in performance oxidizer flow (pressure, rate. regression 3 will rate, demon-

the change of variable

as a function gas generator will the be

Series on-pad

extinguishment. simulated L* with

In this oxidizer time)

series, flow to

abort

and thrust 4 will fuel mixing

termination demonstrate utilization.

control. provide the

Series

required

(residence

required

If necessary,

additional

tests will

be added

if secondary

Table 35. Series 0 1 2 3 4

Subscale

Demonstration Variable

Test Matrix. Tests

Gas Generator Injector Oxidizer

Only

Flow Rate

Extinguishment Combustor Geometry 150

is required for particulate

combustion.

A summaryof the oxidizer

and fuel

flow rates for the 127 centimeter (50 inch) diameter test motor are summarized in Table 36. 2.9.2.10
Oxidizer Delivery System AND Development (Task WILL 10) PROVIDE TO AN OXIDIZER THE

ARC/LIQUID TANK,

PROPULSION

ALLIED-SIGNAL AND FEED

OXIDIZER

TURBOPUMP,

SYSTEM

DESIGN

SUPPORT

COMPONENT

INTEGRATION oxidizer are powered

AND POINT system was

DESIGN TASKS. selected for the Phase 1 point design.

A turbopump The over turbopumps a wide

by the

gas generator

and are required exhaust

to operate solid is by is to

throttling

range.

Since

the gas generator

contains

particulates, used to

an inertial clean

filter

arrangement The efficiency

incorporating of the

a reverse

pitot

provide

fluid.

pumps This oxygen,

is maximized head pressure and hydrogen

supplying developed produce

a constant by reacting

head pressure Tridyne,

to the pump of

inlets.

a mixture

helium,

a 667K

(1,200R)

expulsion studies

gas to pressurize for the

the LOX tank. and specification point will of

We will the oxidizer and component

perform delivery

design system

integration

and controls

to support

the overall design

design

development results evaluate

studies.

The delivery 2 and 4. helium

system

incorpo-

rate the combustion We will sion of LOX. ratio of also

from Tasks the Tridyne will and

delivery

system

for the expuloptimum

The evaluation oxygen,

include to

the selection provide tank. will

of catalysts;

hydrogen,

helium

the required

temperatures;

and the fabrication Allied-Signal, the turbopump to

of the helium under support and

storage

subcontract the overall within

to ARC, design the

perform The months.

design

studies will

of be

effort. 23

turbopump The

developed, 10 months

built

tested

first

remaining and final-

in Phase 2 will required

be used

to procure 3.

the long-lead

hardware

ize the design

for Phase

A turbopump duty cycle. and rotor

design will

be developed

based on the final bearing

definition critical will the

of the speed per-

Stress, dynamic

aero and thermal response analyses design

analyses, and be

design, study verify

calculations will will also be

a material to

be

formed.

Transient The

performed using

component design

performance. techniques.

documented

computer

aided

151

Table

36.

Subscale

Demonstration

Test Summary.

Task 9.

Test Series

Test Objective

Test Conditions

Full Duration GG Test (2 Tests)


1 -

Test GG Parameters Verify Performance Full Duration Test

Monitor

Flow Rate

50 sec

GG Chamber Pressure GG Mass Flow Rate

Full Up Motor Test (6 Tests)


2 -

Injector Evaluation

Programmed Oxidizer and Fuel Flows 88,964 N Thrust

30 sec

GG Pressure and Flow Rate LOX Total Flow Rate

Full Up Motor Test With Cutoff (4 Tests)


3-

Evaluate Change in Performance with Oxidizer Flow Change

Programmed Oxidizer and Fuel Flows 88,964 N Thrust

40 sec

LOX Flow Rate to Combustion Chamber Total Thrust Pressure Drop Across Chamber Injector

Full Up Motor Test (3 Tests)

Demonstrate GG Extinguishment with Oxidizer Flow Control

Programmed Oxidizer and Fuel Flows 88,964 N Thrust

50 sec

Chamber

Pressure

4-

Up Motor Test Full Duration (4 Tests)


Full

Combustor Geometry Variation to Determine Characteristic Length

Programmed Oxidizer and Fuel Flows 88,964 N Thrust

50 sec

Note: After each test disassemble

hardware to check for discrepancies.

01 gO-HYBRID

RPT

152

Allied-Signal will perform development testing of the inducer (a specially designed axial flow impeller) in water. Since the inducer is highly
loaded, tion, careful foil load development bearing will is crucial be tested to for the pump's reliability. evaluation. stability In addiBearing will be the performance damping

stiffness, recorded.

capacity,

running

torque,

and

Initially, sure will test speed

air will

be used

as the test fluid. number

The bearing in the the

cavity

presThe of the

be raised will

to match be

the Reynolds to

LOX turbopump. higher to viscosity simulate

also to

increased Liquid

account will

for then

oxygen

relative

air.

nitrogen

be used

incompressibility Once will Once load will

of the LOX. tests have been An completed and evaluated, cycle the design

the component

be updated the pump test. be used

for manufacture. and

11-month

fabrication

is planned. a fullnitrogen leakage,

is assembled air will

inspected, to drive

Allied-Signal the turbine,

will and

conduct liquid rise,

Hot

be used

in the pump. and bearing the

The test will measure operation. test.

pump pressure test will be tested

balance as

piston, of

A full-speed The unit will

be accomplished at 26-percent vibration

a subset

full-load mechanical

overspeed

to verify

integrity

and demonstrate

acceptable

levels and shaft motion. The final fully assembled testing pump will will be performed be shipped jointly by ARC and Allied-Signal. to evaluate A

to ARC

and tested

turbine,

inducer, 2.9.2.11 ARC

and pump performance Component WILL Inteqration THE

in the design (Task 11)

fluids.

INTEGRATE

MBA

COHBUSTOR/NOZZLE,

FITVC,

AND

OXIDIZER (75 INCH)

TURBOPUMP THRUST The

IN A 444,822N

(100,000 POUND),

190.5 CENTIMETER

NOTOR. of this integration motor that testing is to verify the predicted and TVC hybrid.

objective of the

performance components Specific

hybrid

includes

all of for the

the propulsion gas generator thrust

(including performance to TVC

turbopumps) parameters duty

developed

include

specific thrust

impulse,

termination, and

conformance

cycle

and

profile,

stability,

extinguishment.

153

A detailed place. duty The test the

test plan plan data

will

be written

before of

component tests to test

integration be performed, procedures,

takes the data

will

update

the matrix and

cycle,

acquisition

instrumentation, The plan will

reduction for review

methods,

and reporting

format.

be submitted

to MSFC

and approval. designs plan. and test This support will systems will be established with concurrent drawing

Detailed with the test

effort

be documented

a complete

package. Motor hardware gas will be of heavywall fuel The flanged construction have which been utilizes

cartridge-loaded to minimize

generator risks.

grains.

The motors case

configured insulation, have been

hardware and

motor plate

hardware material

thickness, factors

combustor/nozzle increased tion with tional to 1.8.

injector

safety

The gas generator openings.

case will

be a steel heavywall will

construchave addifrom

two flanged for test

The forward

and aft closures

ports

instrumentation. The hardware thrust

The gas generator

will

be cast used

four 300-pound 88,964N

mixes.

will be scaled from the design motor. A

in the

(20,000

pound)

demonstration is required

190.5 centimeter (100,000

(75 inch) diameter pounds) The of thrust injector

gas generator planned used

to produce

the 444,822N

for this task. demonstration design versus will will be scaled for the by bench will be

in the subscale

190.5-centimeter tests with liquid

gas generator. nitrogen.

The injector drop

be verified flow rate

Pressure

oxidizer

measured The follows:

and compared test matrix

to the predicted for this

results. shown in Table 37, is outlined as

effort,

Series

Gas

generator duration).

operation

only

with

no

oxidizer

flow

(2 tests, Series

75-second

1 - Gas generator

operation

with programmed duration).

oxidizer

flow

rate

scheduled, Series reduced Series normal

no TVC (2 tests,

35-second

2 - Gas generator TVC duty cycle 3 Gas duty

operation (2 tests, with but

at maximum 50-second programmed

operating

pressure

with

duration). oxidizer flow 75 rate and

generator cycle,

TVC

terminate

oxidizer

after

seconds

(2 tests).

154

Table

37.

Comt_onent

integration

test summary.

Task

11.

Test Objective

Test Duration

Variables Measured

Full Duration GG Test (2 Tests)


1 -

Test GG Parameters for Full Duration Test Firing

Monitor

Flow Rate

75 sec

GG Chamber Pressure GG Mass Flow Rate

Full Up Motor Test With Cutoff (2 Tests)


_

Maintain GG PMBT No TVC Duty Cycle

Programmed Flow Rates for Oxidizer and Fuel 444.822 N Thrust

35 sec

GG Pressure and Flow Rate LOX Total Flow Rate LOX Flow Rate to Combustion Chamber

Full Up Motor Test With Cutoff (2 Tests)


_

Gas Generator at Maximum Pressure Reduced TVC Cycle

Constant Maximum Oxidizer and Fuel Flow Rates 444,822 N Thrust

50 sec LOX Flow Rate to FVC Injectors Chamber Pressure

Full Up Motor Test Full Duration (2 Tests)

Maintain GG PMBT Normal TVC Duty Cycle Terminate Oxidizer at 75 Seconds

Programmed Flow Rates for Oxidizer and Fuel 444,822 N Thrust

75 sec

Total Thrust Pressure Drop Across Chamber Injector and TVC Injector

Note: After each test disassemble

hardware to check for discrepancies.

0190-HYBRID

RPT

155

Thrust ments mented gained results thrust margins 2.9.2.12 ARC'S will with from from

and

characteristic The

exhaust

velocity

(C-star)

efficiency will be

measureinstru-

be made.

gas generator to define heat

and combustor/nozzle release will

thermocouples the Task

distributions. be used with

Information the modeling pound)

lO0,O00-pound 4 to permit

thrust the

tests of

design will

a 4,448,221N to

(1,000,000 identify

motor.

In addition, resonant

the

tests

be defined

stability

in various

frequency 12)

regimes.

Risk Assessment PLAN ALLOWS

(Task

FOR

IDENTIFICATION

OF

ITEMS

REQUIRING

ADDITIONAL

DEVELOPMENT

AND ASSESSMENT. of the component effort integration tests, an overall review of

After completion

the status of the development development assessed. new will be

will be made. the

Items requiring of success

additional will be or

identified, possible,

and

probability

To the extent with

recommendations or cost

for further data will

development be made

initiatives the course

improved

reliability

to MSFC

during

of program

and in the final

summary

report.

2.9.2.13 ARC'S

Phase 3 Planning PROGRAM ALLOWS

(Task 13) FOR IDENTIFICATION RESULTS will AND FROM UPDATE PHASE 2. our plans for the Phase 3 OF THE PHASE 3

ACTIVITIES During 4,448,221N include the

TO INCLUDE THE TEST Phase 2 efforts, thrust

ARC

update

(1,000,O00-pound) of facility

demonstration.

Our technical data

reports

will

an update

requirements,

instrumentation,

acquisition

requirements, 2.9.2.14

and documentation. System Inteqration THE (Task 14) INTO A SYSTEM TO

Propulsion WILL

BOEING

INTEGRATE

TECHNOLOGY RESULTS

DETERMINE IF ALL DESIGN CRITERIA Since particular some of the point design developed

ARE BEING DEVELOPED. in Phase 1 was launch This work not referenced to any

system,

ARC selected requirements and

the STS and ALS for the trades.

platforms assumption required

to calculate permitted to a

the design

preliminary reliability In this provide

evaluation and cost.

identified

additional

estimate

task, ARC will assessments

subcontract of the

with

the Boeing of each

Aerospace on

Company

to

detailed

impact

technology

the hybrid

156

development. with work. the

Boeing

will

determine and

overall

cost

and schedule areas

risk

associated additional

integrated early

booster

identify will

critical

requiring

Boeing's

integration

result

in development

and verification

cost savings. 2.9.2.15 Facillt_ Requirements (Task 15) 3 FACILITY hybrid REQUIREMENTS. design and establish a

ARC WILL Early facillty the size

IDENTIFY AND PLAN FOR THE PHASE program, we will review

in the

the

plan

and manufacturing Phase

plan for the demonstration our initial plan

components. will focus

Due to on manushipcompo-

of the

3 gas generator, grains they

facturing ment nents by

the gas generator rail to MSFC where

at our Camden, will be

Arkansas with

facility

with

assembled

the remaining

for testing. The Facility and manufacturing contract list, plan will identify the components to be of

fabricated, construction, critical tions

a vendors the

training

requirements,

the materials

specifications

required,

capital plans,

requirements, assembly

schedules, loca-

paths,

milestones,

transportation

procedures,

and requirements, We will include that will

permits, in our

and government the quality

agencies

to be contacted. and nondestructive (gas generator, injector,

plans

assurance

evaluations

be required and

for the critical helium storage

components

combustor/nozzle, combustion ARC program,

oxidizer

tanks,

turbopump,

controller, will submit

and igniter). our plans will to MSFC for review to and approval. the results During the

the requirements

be updated

include

of the pro-

gram tasks. 2.10 Milllon-Pound Thrust Demonstration Plan

2.10.1

Introduction Propulsion in Phase Technology 2 Program will demonstrate scaleup

The Phase 3 Hybrid of components developed thrust

(Technology motor.

Acquisition)

in a 4,448,221N an assess-

(1,000,000 ment

pound)

demonstration

It will also provide and need is planned

of the technology

development

risks

that remain This phase

to be addressed as a 36-month

in full-scale effort,

engineering

development.

comprising

five tasks.

157

The motor at MSFC. tasks are:

demonstrations schedule and

will

be

conducted

in the F-1 engine It shows

test

stand

The program performed

is presented

in Figure 83.

the major tasks

to be

includes

milestones.

The principal

program

Task 1 2 3 4 5 ARC's direct tion million-pound MSFC data Motor Design

Title

Component

Procurement

and Verification

Motor Assembly Testing Data Analysis thrust

and Shipment

and Documentation plan is structured planning stages. and to request implementawill be

demonstration from and

and frequent through in to the the

involvement analysis making

the early

documentation at all

MSFC

involved Details 2.10.2 THE AND

decision

process

critical

decision

points.

on the work

to be performed (Task 1) AND

are discussed

in the following

sections.

Motor Design PHASE

2 RESULTS

PROGRAM

RECOMMENDATIONS PLAN. (100,000

WILL

BE

REVIEWED

INTEGRATED

INTO THE PHASE of the six

3 PROGRAM 444,822N

After integration component Boeing a

completion tests

pound)

thrust

component

in Phase 2, ARC will make In this motor will review design the of

recommendations task,

to MSFC concerning

development.

ARC and its subcontractors, and perform selection and

and Allied-Signal, analytical prepare to MSFC

list of recommendations design plan and material

detailed

evaluation a detailed

the

impacts. present

We will this plan

program and

to implement Included

the changes in the

for review

approval.

program

plan will be the following: A schedule and request to proceed with the procurement of Iong-

leadtime

hardware. plan major efforts. test plan for the F-1 stand which The stand shall be ready will include all of the after listing facilities and to be used, quality schedule, critiand

A manufacturing cal personnel,

milestones,

assurance

plan

documentation Preliminary milestones.

for occupancy

24 months

158

FOLDOUT

FRAME

/'

Task

Month

4
t i i i i i

10

11

12

13

14

15 16

17

18

Task 1 Motor Finalize

Design
I

1 5
! I

, t
I i i i i

Phase III Hybrid Phase II Mods

Implement

SE&I Contractor and MSFC Verification and Test Facilities Definition and Design
I

6
I

10 v
I

12
W I

Test Facility

Requirements

Task 2 Component Procurement and Verification Long Lead Items

i i t i i

7' 4

t i n n i

11
i i L--. i

Documentation Task 3 Motor and Test Gas Generator Oxidizer Helium Tank Tank Assembly

15
I i L

16
V i

i
i
i

V I i J

13; Turbopumps TVC Combustor/Nozzle Injector Igniter l nterstage/Structures Instrumentation Controllers Task 4 Testing Inert Grain 6 HW Tests Task 5 Data Analysis Documentation Programmatics and
I I J I i i i | 0

17 w w 19 18 ,, ,, , i
i

w
I

,,

',
i 1_____

20 !21

i t T

FOLDC!

;T

r_: ,/, !::7

:-_

0 21

22

231 24

4 311321331 13 36
Phase III Milestones

i i i i i ' I

1. Contractor/MSFC meeting to review hybrid design. 2. Obtain MSFC approval/funding authorization for long lead hardware. 3. Let contracts for long lead hardware. 4. Initiate transportation permits and specifications. 5. Complete design recommendations from Phase II. 6. Formal review with MSFC on production and schedule. 7. Review with MSFC the test schedule and manufacturing plan. 8. Complete process specifications, drawings, procedures for signoff. 9. Establish quality assurance procedures, specifications, and product recovery. 10. Establish a test team of ARC, Boeing and MSFC personnel. 11. Establish material review board; set procedures and schedule. 12. Investigate MSFC test sites; develop Level I plan. 13. 'Green run" pumps at Allied Signal. 14. Complete fabrication of first three MBA nozzles. 15. Complete fabrication and inspection of heavywall hardware. 16. Receipt of oxidizer and helium tanks. 17. Receipt of turbopumps. 18. Trial fit all components. 19. Ship all components to MSFC. 20. Conduct simulated test with inert gas generator. 21. Finalize all test procedures, complete all safety reviews. 22. Finalize stand checkout. 23. Run gas generator tests. 24. Run hybrid motor tests. 25. Complete final design; prepare drawing package. 26. Submit final report.

23

24
i

26
w

Figure

83.

Program

schedule,
_HYBRIDRPT

159

authority handling

to

proceed.

The

plan

will

define

transportation

and

effects, and

preliminary installation

test

procedures, stand

instrumentation and data

requirements collection

procedures,

checkout,

and analysis. of any interface for the control drawing effects pound) on the Level and II

An appraisal documentation (3,500,000

4,448,821N

(1,000,000

15,568,776N

pound)

thrust motors. of the tests to be run, their objectives,

detailed

definition

expected This program

results,

and criteria be reviewed

for success and updated

or failure. during the Phase 3 tasks

plan will

and submitted 2.10.3

to MSFC for review. Procurement WILL BE and Verification FOR EACH THE (Task 2) HYBRID COMPONENT WILL REQUIRED

Component

SPECIFICATIONS IN THE

WRITTEN

DEMONSTRATION

MOTORS.

SPECIFICATIONS

BE DISTRIB-

UTED TO VENDORS ARC, performance with

FOR QUOTATION from

AND CAPABILITY will develop

VERIFICATION. mechanical, hybrid electrical, and

support

Boeing,

specifications

for the gas generator

components.

Included The speciwill that be

in the specifications fications distributed performed Department cations will to well will be

will be packaging to MSFC from and

and shipment

requirements.

submitted

for review. a

The

specifications of companies The the ARC

vendors on

selected ARC

compilation contracts. to

have

previous the

Boeing

Procurement specifiprior

verify

companies'

ability

meet

design

and schedule award. Boeing

for the major

components

by completing

a site visit

to contract ARC scheduled tation. and

will

implement

the

quality

assurance

plan

and

establish

visits ARC

at each major implement

vendor

for inspection for

of hardware

and documenrecovery repre-

will

a system Review

off-specification

product

and compliance. sentatives will

A Material

Board

of experienced deviations

ARC and Boeing

be established inspectors

to review

and discrepancies

reported

in the quality be requested.

site reports;

MSFC representation

on the board will

Each major manufactured prior point. to shipment.

component

will

be inspected will

at the vendor's

plant

All of the components

be reinspected

at the delivery

160

2.10.4

Motor ARC WILL DIZER

Assembly FABRICATE

and Shipment

(Task

3) FABRICATE SIGNAL THE OXIFABRI-

HYBRID MOTORS, BOEING WILL

TANK AND COMBUSTION CONTROLS, AND ALLIED TURBOPUMPS.

WILL

CATE THE OXIDIZER FIT This inspection cation

ALL OF THE COMPONENTS WILL

BE TRIAL

AND THEN SHIPPED TO NSFC FOR TESTING. task's of technical effort will result in the casting, curing, and

eight

86,183-kilogram

(IgO,OOO-pound) braided

gas

generators;

fabri-

and inspection

of eight, monolithic

ablative

combustor/nozzles,

and the assembly ARC's system

and checkout

of the oxidizer

delivery

system. an integrated tank, helium

approach of

for the demonstration gas generator,

tests

is to fabricate oxidizer

comprised system,

combustor/nozzle, lines, valves, installed in the will

expulsion vector

turbopumps, The system

oxidizer will be

controllers, F-1 stand

and thrust and reused. each

control. (gas

Consumables test.

generator

and

combustor/nozzle)

be replaced

after

ARC will meter with

design

a heavyweight, carbon

monolithic

cartridge-loaded, composite

317.5

centicase

(125 inch) diameter integral domes.

fiber/polyimide will

gas generator

A total

of ten cases the cases loading.

be manufactured

by an outside they will be loaded

vendor be

and shipped

to ARC.

After for fuel

have passed

inspection, will

insulated an inert gas

and prepared simulated

One of the cases be loaded hybrid

with (two

fuel, and eight tests, six

will

with fuels tests);

for testing case x-ray

generator-only

integrated be cured will

the tenth using

will be a spare. and ultrasonics.

Each fuel grain The inert

will

and then be

inspected

gas generator The first The

shipped

to MSFC will

for trial

installation scaleup of two proof

and checkout. of concept. a review

two live gas generators gas generators test would will

be used for in lots For this

remaining each

be cast

following we have

of

preceding facility

or test

series.

plan,

assumed

a new casting

be set up in the Highland facility. directed by ARC/Liquid Divi-

Industrial Design Propulsion. sion

Park adjacent of the

to our existing delivery

Camden Arkansas will be

oxidizer send

system

They will

representatives

to our Virginia

Propulsion

facilities Signal,

to direct under

the receipt,

checkout, will

and assembly primary

of components. and Signal redundant at their

Allied oxidizer

subcontract The pumps

to ARC, will

provide

turbopumps.

be green

run by Allied

161

facilities prior to shipment. The remaining componentswill subsystems, passivated, and then sealed for shipment.
fabrication tank final tured prior and to delivery will be directed the by Boeing. shipment, point passivate interior,

be assembled into
The oxidizer inspect tank the wil]

They

and then transport system wlll

it to the be manufacGroup

assembly by ARC.

at MSFC.

The helium tank will

expulsion

The composite

be fabricated

by the Composites will

of Virginia

Propulsion

Division,

and the remaining

components

be assem-

bled and integrated The MBA The nozzle drical

by Liquid

Propulsion. will be fabricated with quartz at our Virginia fibers facilities. cylininternal phenolic

combustor/nozzle will

preforms

be braided

in an automated to the nozzle

braider

using The

a rubber wlll

mandrel be

corresponding by ARC

dimensions. resin. date

preform will

densified at 350F

using

solvated

The preform

be cured

and then

consolidated

to accommo-

shrinkage. The hybrid motor components Allied will be shipped and MSFC to ARC's Arkansas will Propulsion inspect and

Division. trial tion

ARC,

Boeing,

Signal,

personnel

fit the will

components that:

to finalize (1) MSFC

the assembly personnel

procedures. are aware

This

integra-

ensure

stand

of the procedures of required devia-

and they are being implemented; tions or discrepancies they can be resolved Once MSFC. 2.10.5 ARC needed

(2) MSFC can make ARC aware for the tests;

and (3) if there

are any problems

prior to arrival have been

at MSFC. they will be crated and shipped to

the components arrival,

tested,

Upon

they will be reinspected

and then stored for testing.

Testinq WILL

(Task 4) TWO GAS-GENERATOR-ONLY PROOF OF CONCEPT. MSFC to conduct two gas generator will tests in the F-1 TESTS AND SIX HYBRID MOTOR

CONDUCT

TESTS TO VALIDATE ARC stand. for will assist

The gas generator strain,

case and combustor/nozzle temperature. For these

be fully

instrumented nozzle the fuel acqui-

pressure, will

and

tests,

a smaller

throat hybrid

be used to produce The two

the gas generator tests will

pressures validate

expected

during

tests.

gas generator tests

the predicted out data

delivery sition.

rate for the full-up The tests will

and will

be used to check duration.

be run for a full

135-second

162

The data from the two gas generator tests will be analyzed, and the results will be used to check the grain design for the hybrid tests. If a different mass flow rate is required, the grain design will be modified and new casting tooling fabricated.

ARCwill mix and cast the next two gas generators required for the first two test series, shown in Table 38. The gas generators will be inspected,
packaged, oxidizer analyzed. We analysis porated will of prior manufacture Series 1 and the 2. next If two gas generators required, following they will review be and and tank shipped for to MSFC. The The first gas generators tests will be be run bolted and to the data testing. two will the

changes

are The

incor-

to the next

series After

of tests. each

last two tests will test,

be run to

demonstrate will be

repeatability. and

hybrid

motor

all of the hardware tests of will be

disassembled to assure

inspected. of any

If necessary, problems. A

specific summary

repeated follows:

resolution

the

tests

Test Series

O:

Two full-duration injection. design Run

tests with

of the gas generator, nozzle throat

no oxidizer to produce

reduced

operating

pressure. design. Maintain pre-

Test

Series

1:

Full-duration dicted limits. Terminate

test of the complete trace within TVC

thrust-time Run

the operating angle and

temperature duty cycle.

reduced

slew

oxidizer test

flow rate after scheduled.

35 seconds. TVC duty vehicle after

Test

Series

2:

Full-duration cycle.

Run a prescribed

Measure

structural

loads at the simulated oxidizer flow

attachment 70 seconds. Test Test Series Series 3: 4:

points.

Terminate

rate

Repeat Test Series Full-duration cycle. thrust test

2 with with

cutoff

at 105 seconds. prescribed TVC duty

the maximum

Program

cutoff

at 135 seconds position.

with TVC deflecting

in maximum

degree

Test Series

5:

Repeat Test Series

4 for statistical

data

(2 tests).

163

Table

38.

Large

subscale

motor

test series.

Test Obj_'tive

Test Condiffons

Variables Measured

Full Duration GG Test (2 Tests)


1 -

Test GG Parameters for Full Duration Test Firing Maintain GG PMBT Full Duration Attempt Shutdown Motor Record Vehicle Loads Run TVC Duty Cycle Maintain GG PMBT Full Duration Attempt Shutdown Motor Record Vehicle Loads Run TVC Duty Cycle Maintain GG PMBT Full Duration Attempt Shutdown Motor Record Vehicle Loads Run TVC Duty Cycle Maintain GG PMBT Full Duration Test Run Maximum TVC Duty Cycle

Programmed Fuel Flow No Oxidizer Full Duration Programmed Fuel and Oxidizer Flow 4,448,221 N Thrust

135 sec

GG Chamber Pressure GG Mass Flow Rate

Full Up Motor Test With Cutoff (1 Test)


2-

35 sec

GG Pressure and Flow Rate LOX Total Flow Rate

Full Up Motor Test With Cutoff (1 Test)


a-

Programmed Fuel and Oxidizer Flow 4,448,221 N Thrust

LOX Flow Rate to Combustion Chamber 70 sec LOX Flow Rate to TVC Injectors Chamber Pressure

Full Up Motor Test With Cutoff (1 Test)


4-

Programmed Fuel and Oxidizer Flow 4,448,221 N Thrust

105 sec

Total Thrust Pressure Drop Across Chamber Injector and TVC Injector If Cutoff then Measure Loads from Strain Gauges

Up Motor Test Full Duration (1 Test)


Full .

Programmed Fuel and Oxidizer Flow 4,448,221 N Thrust

135 sec

Full Up Motor Test Full Duration (2 Tests)

Maintain GG PMBT Full Duration Test Run Maximum TVC Duty Cycle

Programmed Oxidizer and Fuel Flow 4,448,221 N Thrust

135 sec

Note: After each test disassemble

hardware to check for discrepancies.

0190-HYBRID

RPT

164

For each test, the following tor pressure, main injector, combustor total pressure, oxidizer

will

be measured: flow rate injector loads 39. (Task 5) THRUST NOTOR

motor

thrust,

gas generaand case

oxidizer

to the TVC

injectors motor

consumed,

pressure

drop, vehicle.

strain,

combustor

strain,

and structural in Table

to the core

A summary

of the instrumentation 2.10.6 THE Data Analysis 4,448,221N AND A

is shown

and Documentation POUND)

(I,000,000 STATISTICAL

DATA TO

WILL VERIFY

BE

ANA-

LYZED,

EVALUATION

COMPLETED

OVERALL

PERFORNANCE. ARC will measure used to cast the the mechanical to and ballistic mechanical properties property will of each fuel mix and be performance established,

motors

determine

repeatability.

The

variation

in mix-to-mix

properties

and the impact on cost and reliability The standard data. We test data will be data MSFC recorded analysis with

will be calculated. on FM tape software data for will for playback be used at ARC. to analyze ARC's the of a

static will

firing supply

the test will

independent to MSFC

evaluation include

the tests. description test data

Complete of the

test reports test, A test

be submitted and

and will

facility

equipment, will (2) be

instrumentation, completed motor

and

analysis. gas

statistical generator

evaluation operation; limits;

to verify: ignition; and duty or failIncluded has

(1) reproducible (3) extinguishment cycle; and

hybrid

within

the specified operation.

(4) TVC requirements of a test analysis to assure anomaly report. MSFC

(5) turbopump

In the event failure report

ure, ARC will deliver in the report will be

an oral and a written a corrective action

that ARC

taken the appropriate A history structive records To logbook and for

action to minimize all motors The tested logs

recurrence. at MSFC will be prepared of to the and provide nondeevent

traceability. test,

will

include and

the results

evaluation

manufacturing

inspection

records,

or discrepancy complete

reports. 3 activities, ARC will submit Included the a final report that

the Phase

summarizes be an

all technical booster drawing

activities point design

accomplished. scaled

in the report will requiredevel-

updated

to meet

performance engineering

ments, opment

a booster plan.

package,

and a detailed

full-scale

165

Table

39.

Phase

3 Motor

Instrumentation.

Channel

Description Gas Generator Gas Generator Combustor Combustor Oxidizer Helium Helium AP TVC AP Main Tank

Value

Channel

Description Case Forward Dome 0 Fiber Tan 0 Fiber

Value 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%

P1 P2 P3 P4 P5 P6 P7 P8 Pg

2K 2K 2K 2K IK 20K 20K .SK .SK

SI S2 S3 S4 S5 S6 S7 S8 S9 $10

Case Forward

Case Mid Hoop 0 Case Mid Axial Case Mid Axial 0 180

Tank Tank Injector Injector

Case Mid Hoop 180 Case Aft Tan 0 Fiber Case Aft Dome 0 Fiber Combustor Combustor Nozzle Nozzle Axial 0

Hoop 0 0

F1 F2 F 3 A&B F4 A&B

Forward Forward

Thrust Thrust

IO00K IO00K 50K 50K

$11

Axial

Hoop 0 Sklrt Skirt Axial 0

TVC Test Side Forward TVC Test Side Aft

$12 A&B $13 A&B $14 A&B

Interstage Interstage Oxidizer Oxidizer Oxidizer Oxidizer

2% 2% 2% 2% 2% 2%

Hoop 0 0

Tank Axial

T 1A&B T 2 A&B T 3 A&B T4 A&B T 5 A&B T6 A&B T7 A&B T8 A&B

Case Forward Case Forward Case Aft 0 Case Aft 180 Nozzle Nozzle Nozzle Flange Cone Cone

Dome 0 Dome 180

500F 500F 500F 500F

$15 A&B $16 A&B $17 A&B

Tank Hoop 0 Tank Axial Tank Hoop 180 180

45

500F 1500F 1500F 1500F

(1/2) (3/4) (Aft)

Nozzle Cone

166

OKIDI2_R

TRADE

S'YODIES

PRESSURE

FED

l_t_ FED

FRES_mE Inaction

F_)

The systems Oxidizers peroxide sufficient include A and

objective for to both be

of the

this

task

was

to

investigate (HC) and

pressure-fed gas generator

oxidizer hybrid

feed (GG).

classical for

hybrid each

evaluated and make liquid major ccml:onent

hybrid (LOX).

approach The depth

were of and

95-peroent this was study not

hydrogen was to be to

(H202) to

oxygen feed

system

selections

intended

any

detail

designs. oxidizer the feed system tank. consists studies of an were oxidizer conducted based tank to upon

typical

pressure-fed

a means the

of pressurizing selection criteria. of the

oxidizer

Trade

enable the

appropriate

pressurization

subsystem

following Safety Cost Weight

Reliability designed mission, storage have a so the that only

and a

safety single

are

of

equal failure the

importance. would not storage in

Each cause tank

feed

system of

was the

point being _nents jf

failure and the they

exceptions Since these

oxidizer are

helium should are

vessel. 100-percent

benign and

operation,

reliability

the are

design not

fabrication

processes

satisfactory; The (throttled) varied thrust upon to

therefore profile a

redundancies of the wide range

required. that Thus, rates of the tank required system thrust pressure to be varied must be the

thrust over

mission range

requires (1.6:1). flow

fairly the

aco:modate

of

oxidizer a

support

profile. which The the

Table oxidizer feed

A-I

provides trade for

summary

booster based.

requirements

system system,

studies all

were

oxidizer (8-inch) Normally

these the

designs, oxidizer

consists tank to

of the

four

20.3

centimeter valves. each

liquid closed A can

manifolds

from isolation

injector in the

explosive normally be

valves is

(isolvalve) located shut down. at

are the The

located exit to

oxidizer tank

line. which

open for

isova]ve emergency

oxidizer

actuated

classical

Table A-I.

System Requirements HC/H202

GG/H202

HC_

GG/LCK(

Oxidi zer Max Max Min

Load,

KG Rate, KG/sec

467,382 4,814 7.48 3.45

431,810 4,454 7.48 3.45

362,167 3,805 7.48 3.45

304,876 3,144 7.48 3.45

Oxidizer Chamber Chamber

F]ow

Pressure, Pressure,

MPa MPa

hybrid has the additional requirement of gasifying injection into the solid motor combustion chamber.
Pressurization Systems Using System Hydrogen percent is _s Peroxide has many favorable and It has is a

the oxidizer

prior

to

Ninety-five has with which a high the

H202

features relatively an

as

an

oxidizer. mixture

It ratio

density, solid fuel

noncryogenic,

high

constituents. of potential which

also

energetic is also problems,

monopropellant de_ses and is not at in

offers

a number low

advantages. can lead to

However, safety

relatively wide use

temperatures as an oxidizer. syst_n A-2,

today

Pressurization sun_rized approach. warm liquid warm gas in Some (N2H4), which Table

options along

that

were

evaluated and

for

this

system for out, gas

are each as the The to a

with options

advantages were of

disadvantages screened pressurant

pressurization due to the

immediately reaction of

such with

possibility to a

H202 gas

could approach

lead

catastrophic that the

uncontrolled H202

reaction. be oooled H202

(H202) that and

requires

decomposed of the

temperature complexity A in

precludes to the of is

self-decomposition system. a cold fed gas a (heli_n) high to present the

liquid

adding

cost

schematic A-I.

diagram Helium

pressurization pressure storage

system bottle valves the

is shown through and the to to

Figure

from valves is of

explosively-actuated oxidizer preclude tank. the A

isolation relief valve

pressure

regulating of

downstream A

regulators is used

overpressurization the is tank to and normal has a and

tanks.

fill/vent shortly

port

prepressurize This heavy, weights are system large as a

operating high heavy storage

pressure

before but

launch. in

simple

historical helium pressure

reliability, loads. for

results

pressure function in Table of in is

bottles of A-3. a warmed same to

Pressurization both HC and GG

system systems

helium

presented The

schenatic operates charge for the

helium manner heat as the

system the gas

is cold

shown gas in

in system the

Figure except bottle reduces and

A-2. a at the may

The solid

system

the

propellant in the and large

fired

remaining This less

a point weight produce Also,

mission of

more

efficient but

expulsion. cnmnplex, gas

approach reliable, to the

size

system,

is more

solid

particles

complicating

filtration

regulators.

Table A-2.

Pressurization

SystemOptions (H202)

PRESSURIZATION
SUBSYSTEM Cold Gas ADVANTAGES Simple Low Cost High Warmed He] ium Reliability More C_]ex Solid Particle Less Re]iab]e DISADVANTAGES Heavy Large

Bottle

Volume

_rWeight

Filtration

Heated

He] i_n

Low Weight Smaller Volume Pressurant as Liquid Stored

More Cc_]ex (Heat Exchanger, GG) Complex Warm Gas WarmGas Camp]ex

Warm

Gas

(H202 )

must may

be

Cooled with Ox

Warm

Gas(N2H

4)

LowWe_ght

react

]:_'e ss Lz2'_ t

Bottle

Ftll/Vent

Vtlve

Isolation

Vglves_Y_

!
Pressure Regulator

Fill/Vent

Valve

Relief

Valve

Ox

Fill/I_in

Valve Isolation Valve N.O.

Throttle

Valve

To Injector

Figure

A-].

Co_d

Gas

pressurization

System

_bema_$c.

_Solid

Gas Genentor

Bo_e_

----C_

Fill/Vent

Valve

"_

Isolation

Valves_

I
Pressure Regulator

FilL_/enI Va.]ve[--7

_K

ReliefVa.lvc

Ox

FilL/Drais: \'_ IsolationValve N.O.

lation

Valve

N.C.

l
_] Throttle Va.lve

To Injector

Figure

A-2.

Warm

Gas

Pressurization

System

Schematic.

Table

A-3.

Cold

Gas a.

(He) Gas

Regy]ated

Pressurization

Generator

PBO MPa 34.5 5] .7 68.9 86. ]

WHe

Loaded KG

WHe

Used KG

WHe

Bott]e KG

Bottle Length CM 2,328 1,4 34 ] ,091 909

i0,737 8,804 8,037 7,6] 6

5,762 5,760 5,757 5,756

33,151 28,822 27,662 27,328

b.

Classical/H202

34.5 5] .7 68.9 86.]

]] ,]05 9,]72 8,397 7,970

6,073 6,070 6,068 6,065

34,320 30,014 28,893 28,6]0

2,406 ],49] ] ,137 923

the accidental pressurization


countered A Js with

firing of a so]id charge at the wrong time cou]d cause overof the helium storage bottle. This possibility oou]d be
a re]Jef helium high flows valve, but would result in the loss of pressurant. Oo]d he]Jt_ bottle a shella heat

heated at

system pressure through

is shown and low

schematica]]y t_rature

Jn Figure (167K) isolation the helium of the to

A-3.

stored

minimize to of to

size. and-tube

Helit_ heat and to

explosively-actuated where to it travels The The tank to fed of the

va]ves tube is side fed

exchanger, is heated

through heated

exchanger regulators decGmposed Catalytic products side more of

333K. tank.

pressure uses

pressurize frcm the

the

shell to

side

heat to the

exchanger oo]d

H202 gas at the

oxidizer are I,IIIK The used

provide

heat the

helium.

generators

deeampose in

H202 . flow

Deecm_xgsition to the she]] and more

approximately heat exchanger. as

are use to

countercurrent he]itm_ results The this

heated cold

in a

lighter of

compact

system slightly

ccml:ared the

gas

system. of of

addition system. storage A-4

ccm_onents

]cwers system

predicted as a

reliability function are of

Pressurization and Heat Table temperature exchanger A-6. for

weights HC a

helium in

pressure and A-5. in are

GG

and as tank and

systems function

presented storage

Tables are various

dimensions Oxidizer

pressure for

presented cases

weight A-8.

and

dimensions

presented

in Tab]es Usin@ oxygen main

A-7 LOX (LOX)

Systems Liquid today. upon The

is

cryogenic

oxidizer

widely the

used

in

the

industry is cc_]ed

problem the LOX,

in pressurizing thus increasing

I/3X is that the amount of

pressurant

contacting Table A-9

pressurant which are

required. were also evaluated presented

stmlnarizes using LCM.

pressurization Advantages

system and

options

for for

the these Same

designs systems.

disadvantages

approaches

were

quickly gases, the out

screened solid

out.

Solids

were

not high

eonsidered temperature shutdown. of of its its

due of Warm

to reactive the gas pressurant (N2H 4)

combustion gas was and

particles, associated the the

re]ative]y with high and the

prob]ems due to of

emergency temperature reactivity

ruled the

relatively system,

deecm_position pressurant

gases,

e_mp]exity

gases.

Pr_ssur'_t

Bottle

Fill/Vent

Valve

"_

Isolation

Valves'Y_

ie l"dtots

Exchanger Heat

PI' $sure

ulator

FilVVent

Valve

l"']

_Relief

Valve

H202

Fill/Drain Isolation

Valve Valve N.O.

Isolation

Valve

Throttle To Injector

Valve

Figure

A-3.

Cold

Gas With Gas Pressurization

Generator/Heat System.

Exchanqer

Table A-4.

Cold

Gas (He) Regulated with GG/Heat Pressurization (GG/H202) Bottle Length CM 776 567 490 452 1,002 677 554 490 l ,259 l ,259 647 558

Exchanger

PBO MPa 34.5 51.7 68.9 86. l 34.5 51.7 68.9 86. l 34.5 51.7 68.9 86.1

THe 0 K 55.6 55.6 55.6 55.6 111 111 111 111 167 167 167 167

WHe Loaded KG II,095 9,226 8,501 8,114 9,479 7,832 7,183 6,830 8,945 7,373 6,750 6,409

WHe Used KG 4,648 4,646 4,644 4,643 4,633 4,631 4,629 4,628 4,618 4,616 4,614 4,613

WHe Bottle KG 9,790 9,982 10,878 II,956 12,895 12,137 12,485 13,105 16,406 14,885 14,827 15,169

WH202 Decomposed KG 6,992 7,001 6,996 6,551 5,571 5,571 5,576 5,576 4,160 4,164 4,164 4,169

WHX KG 378 374 373 371 319 317 310 315 273 272 266 272

WGG KG 62 62 62 62 50 50 50 50 38 38 38 38

Table A-5.

Cold Gas (He) Regulated with HC/Heat Pressurization (HC/H202) Bottle Length CM 789 580 503 464 1,021 695 570 505 1,285 839 568 575

Exchanger

PBO MPa 34.5 51.7 68.9 86. l 34.5 51.7 68.9 86. l 34.5 51.7 68.9 86. l

THe 0 K 55.6 55.6 55.6 55.6 111 111 111 111 167 167 167 1 67

WHe Loaded KG 11,274 9,456 8,743 8,278 9,667 8,057 7,414 7,063 9,136 7,596 6,979 6,638

WHe Used KG 4,863 4,860 4,858 4,856 4,847 4,844 4,843 4,841 4,832 4,829 4,827 4,826

WHe Bottle KG 9,955 10,233 11,640 12,316 13,136 12,491 12,887 13,548 16,771 15,346 15,333 15,712

WH202 Decomposea KG 7,281 7,281 7,285 7,289 5,796 5,796 5,805 5,801 4,325 4,330 4,330 4,334

WHX KG 378 374 373 371 319 317 310 315 273 272 266 272

WGG KG 62 62 62 62 5O 5O 5O 5O 38 38 38 38

Tab]e

A-6.

Dimensions

of Heat for H202

Exchanger System

and

Gas

Generator

PBo
MPa 34.5 34.5 34.5 51.7 5].7 51.7 68.9 68.9 68.9 86.1 86.1 86.1

THeO
K 55.6 Iii.i 166.7 55.6 iii.i ]66.7 55.6 lll.l 166.7 55.6 iii.I 166.7 CM 229 192 162 226 189 16] 224 184 156 221 186 158

DHX
CM 39 39 39 39 39 39 39 39 39 39 39 39 (]4 ii ii ii Ii ii II ii ii ii ii ii Ii

DOG
CM 52 46 40 52 46.5 40 52 46 40 52 46 40

Table

A-7.

Oxidizer System Parameters Regulated Pressurization

with

Cold

Gas

WTank
System GG/H202 HC/H202 KG 14,46] 15,153 CM 3,085 3,33]

ank
MPa 10.9 10.6

Table

A-8. Oxidizer Tanks GG/Heat Exchanger

with Cold Gas Pressurization

Regulated

a. THe K 55.6 111.1 166.7 O WTank KG 14,412 14,365 14,319

GG/H202

Hybrid ITank (_ PTank MPa 10.9 10.9 10.9 Max

3,145 3,135 3,125

b. 55.6 I]].] 166.7 ]5,083 15,036 14,989

HC/H202

Hybrid ]0.6 ]0.6 ]0.6

3,392 3,382 3,37]

Table A-9. PRESSURI ZATION SUBSYST_ Cold Gas Regulated

Pressurization

SystemOptions

ADVANTAGES Simple Low Cost High Reliabi]ity

DIS_AGES Heavy Large

Bott]e

Volume

WarmGas (He/O2/H 2) WarmGas (N2H 4)


Solid

Simple Low Weight Low Weight

More _]ex Reactor) Warm Gas Camplex Hot gases Cannot be may

(Catalytic

react

with

ox

Simp]e

react with shut off. be

ox.

Hot gas must overboard.

released

Cold and A-5

gas for

pressurization the GG to and the HC

systems designs, gas A The

are

shown

schematically The The GG/LOX HC/LC_ propane by prevent r_]ief but as a

in

Figures

A-4

respectively. for tank tank H202 .

pressurization system (C3H8) requires is also

system a

is similar before by in

oold

system fuel fuel to the lines simp]e

preburner

injection. he]i_n. line the gas

containing is sealed tank the

pressurized Check gaseous closes. and heavy valves

the the into

isolation the valve

va]ves. of and large helium

leading pressurant is

oxidizer in and case

backwash opens in of a

oxygen The

cold

system

reliable, weights

results function A-10.

system. for and

Pressurization HC and GG show the of systems

system are

storage

pressure A-6

presented of a warm

in Table gas

Figures pressurization utilizes ocmrposed a warm

A-7 for heating

schematics GG a and HC

(tridyne,

He/O2/H2) This system

system

designs,

respectively. gas mixture single promotes consists

catalytic of both

nondetonab]e ccmix)nents catalytic The 02 and

ca]led bottle, the of

tridyne, to provide

inert

and gas.

reactive The

in

pressurization predominate]y and

reactor mixture H2

reaction he]it_n

to

heat oxygen ca]ly. tion

the

inert

mixture. with

(He),

(02) This system;

hydrogen

(H2) , in as

proportioned and more

stoichi(m_etripressurizaL(3M oxidizer hybrid as

approach it was

results selected

a much the studies

lighter

ccmpact the

baseline selected

system the

for gas

system. the

Further, hybrid

separate system. system systems of

trade

generator

baseline

Pressurization for the GG and and HC

weights are the

as

function in Table and fuel and system.

of

he]lure Table (HC)

storage A-12 using of the

pressure shews cold the gas

presented oxidizer the

A-II. tanks

weight

dimensions Table (HC) S_,stem zat ion for

pressurization. and fue] tanks

A-13 a warm

shows gas

weight

dimensions

oxidizer

regulated

Baseline Pressuri of Tridyne

Description Subsystem gas, - The a base] ine pressuri zat ion resin subsystem wrapped consi sts bottle, valves, manifo]ds. a four A

pressurant valve, regulators, of these

carbon

fiber/epoxy actuated and

fill/vent pressure schematic

redundant a

pyrotechnically reactor

iso]ation gas

cata]ytic

associated A-8.

osmponents

is shown

in Figure

Fdl/Vent

V_ve

_rcssure

Regulato.-

FillA'ent

Valve

[_

Relief

Valve

Ox

Fill/Dram

Valve

Isolation

Valve

N.O.

lation

Valve

3
_ Throttle Va.lve

To Injector

Figure

A-4.

Cold

Gas

Pressurization

System

Schematic

for

GG/LOX.

l:_'_ SSU.T_t

Bo_e

Fill/Vent

Valve

Isola_on VaJves_

[_

[_Pressure

Regulator

Rclicf Valvc_

Figure

A-5.

Cold

Gas

Pr@ssuri_tion

System

Schematic

for

HC/LOX.

Tab]e

A-10.

Co]d

Regulated

Pressurization

(Tridyne)

a.

GG/Lf_

Hybrid Bottle

MPa 34.5 5] 7 68.9 86 ] 9,901 8,063 7,340 6,945 5,22] 5,2] 8 5,2] 6 5,2] 5 25,550 22,596 22,026 22,098

Lec_th 3607 998 766 644

b. 34.5 5] .7 58.9 86.] ]2,587 ]0,203 9,272 8,765

HC/LC_ 6,56] 6,558 6,555 6,554

Hybrid 32,]9] 28,229 27,4]0 27,395 20]8 ]239 945 789

Tab]e

A-II.

Warm

Gas

Regulated

Pressurization

(Tridyne)

a. GG/I/SX

Hybrid Bottle

MPa 34.5 5] .7 68.9 86. ] 5,056 4,002 3,60] 3,385 2,527 2,519 2,5]3 2,508 i0,546 9,224 9,00] 9,058

Lec_th 728 457 358 306

b. 34.5 51.7 68.9 86.] 6,477 5,084 4,560 4,280

HC/L(_ 3 ,]76 3,165 3 ,]57 3,]50

Hybrid ]3,285 ]] ,446 1] ,084 ]],]08 907 556 429 363

]_'e ssunJ_t

Bottle

Fill/VentValve

Isolation

V_ves_

Pressure

Regulator

Gas

Gene_tor

Ox

Fill:Drain

Valve Isolation Valve N.O.

3
_ Throttle Valves
To I/lie.clot

Figure

A-6.

Catalytic

Warm

Gas

Pressurization

System

Schematic

zgx_9_9/laz_

Fill/Vent

Valve

Pressure

Regulator

r-i

Th_ttle

Valves

Figure

A-7.

C_talytic

Warm

Gas

Pressurization

System

Schematic

LQL/LqL_QZ_

Tab]e

A-12.

Oxidizer Regu]ated

and Fuel Tanks with Pressurizat ion

Co]d

Gas

WTank Ox
System GG/LOK HC/LOX KG i0,026 12,128

_nk Ox
CM 1,958 2,309

WTank F
KG 0 679

Tab]e

A-13. Oxidizer and Fuel Regulated Pressurization

Tanks with Warm (He/H2/02)

Gas

System GG/LOX HC/LOX29,223

WTank KG 10,885 4]3

Ox

ITank CM ],962 4,]07

Ox

WTank KG 0 52

Pressure Regulator

CatalyticRe.actor Relief Fill/Veto Valve D Pressure Sensor

Ox

Fill/Drain Valve Isolation Valve N.O.

To Injector

Figure

A-8.

Catalytic

Warm

Gas

Pressurization

Svstem

Schematic

The (H 2 and

Tridyne 02) ,

pressurant are that

consists with

of

a an

small inert at

fraction diluent high

of

reactive to in a

gases, form a

which m_xture is

ec,nbined can

(helium) pressure

nondetonab]e Energy which release

safely by

be

stored the

a bottle. bed Gas

accomplished reactants

passing creates the

mixture a hot

through gaseous

catalyst

ocmbines

the

and

mixture.

temperature The

Js oontro]]ed weight the in MPa of

by varying

reactant is

concentration. upon the volume the to be gas A

Tridyne

pressurant the

dependent b]owdown reaction as

pressurized, temperature nc_ninal weight, savings pressure 68.9

storage the tank

pressure, and psia) the was

final

pressure,

final r_se.

catalytic selected concerns.

temperature compromise shows, The

(i0,000 s_ze, above MPa and

a reasonable Figure A-9

between weight bottle design

bottle of of of going

safety MPa

As are

the

68.9

(10,000 psia) tanks. is

psia) we]]

minima]. the

ncfnina]

68.9

(10,000 te-wrapped molar

within

demonstrated

capabi ] ity The sponds to

ccmposi

selected a

Tridyne

composition temperature The

of

0.91 of

He/0.06

H2/0.03 at

02 an

correinlet is

theoretical of 554K

reaction (997R).

983K

(I,770R) mass

temperature

respective

_sition

0.7711/0.2033/0.0256. Tridyne the oxygen of is and supp]_ed hydrogen and at are water consists contained stainless through the regulated ccmbined vapor. of in steel the pressure to The convert to the the catalytic cold Trjdyne reactor to a DEOXO the where heated MFSA by of end from

mixture Enge]hard aluminum plates.

he]it_n

catalyst,

designated metals housing prevents plates. on

Industries, oxide A 300 or to spheres series migrating

platintm_group a cylindrical wire holes flow screen of the

surface drilled

with the

catalyst

obstructing are used

Injection channeling made iS of

orifices within 300 the

evenly The

distribute outer A maxJm_n

gas of

and

prevent is of also

catalyst stainless

bed. steel.

she_] wail

the

reactor

series for the

temperature

900QF

expected

mission.
The (424R) to 2,084 coldest which psia) temperature to at the inlet fr_ of to the MPa catalytic to This Using 14.4 reactor MPa is 235K psia of

corresponds with

expansion

68.9

(i0,000

a po]ytropic of

exponent 61K

1.15.

results the

in a drop

reaction

temperature

approximately

(II0R).

empirica]

16329

15422

14515

4J (-E_ *r--

13608
E

DES_JNBO_CT

U_ {#I L

12700

11793 27.6 41'.3 55'. I Bottle Pressure

68.9 MPa

82.7

96.5

Figure

9.

GG/LOX Hybrid

System

Weight

vs

Bottle

Pressure.

Epstein (I,200R) A also the the

equation, in the

an oxidizer valve the

equilibritm_ tank is was

gas

temperature 1 outlet.

of

approximately

667K

determined. at the

fill/vent at

located to the

bottle to

pressure

sensor

Js of of

located storage pressurant upon

outlet Two

bottle

provide valves

oontinuous provide of the

monitoring eontairm_nt pressurization

pressure. gas signal.

redundant storage valves and

isolation ensure

during

activation closed,

system units.

These

are

normally

explosively-actuated

Tank regulator the

pressure is sized event can of be the

control to provide a

is

provided one-third should flow

by of

four the fail

pressure

regulators. flow three valve fail of rate.

Each In

maximum closed, A

expected the

unlikely

regulator the maximt_n so A and

remaining is located the tank

regulators downstream will not

handle the

demand.

relief

regulators

that

if a regulator sensor

should downstream launch

open, the

overpressurized. tank A pressure regulator total flow flow built valve seat The with inside ullage of 12.4

pressure

regulators has the below filter prevent

monitors failed mission one-third and slam

will

indicate (open) from

before

if a regulator not affect

open. because of

failure demand rate _nto

during the

flight

should not

engine The The

does

decrease have a

maximum

until the

tailoff. inlet. system tank resin. The

regulators slam

suppressor of the

suppressors

overheating

during

enable. is eonstructed A liner of a filament of Teflon is 254m 3 sized no-flow to _ound and

Prc_e]lant IM-7 fiber

Tank

oxidizer EPON the 826

impregnated is a located 3 percent pressure factor System The

oonsisting volume been a

insulation ft3), maximum The burst Liquid in Figure plus

tank.

total case

tank has

(8,962 a

allowance. MPa (1,793

The

handle

tank

psia)

during

condition.

safety Feed A-8.

is 1.6. The liquid will be feed fed system to the has liquid lines. of been shown schematically via four 20.3 will to

oxidizer diameter

injector Each the

centimeter have a

(8-inch) liquid

stainless valve

steel

feed

manifold injector

throttling

immediately

upstream

Epstein, Propellant En_in@ering,

M.,

Georg_us, H. K., Tank-Pressurization Vol_ne 10B, Plen_n

and Anderson, Analys_ s," Press, New York

R. E., Advances (1965),

"A Generalized in Cryogenic Page 290.

control

the flow

rate of the LOX. actuators, isolation tank

Throttling are used. is

pintle-type Upstream to

valves, of this

operated valve

by an

hydraulic-mechanical explosively ment. isolation When actuated the

valve is

located LOX

provide be

double down

containto the

oxidizer

filled,

will

bled

valve. activation sequence is:

The liquid feed system I.


.

Fill/vent

and fill/drain

valves on the LOX tank are closed. the the

LOX feedline isolation valves are opened. This will fill feedline to the throttle valve and will minimize the water hammer throttle valve will see. Gas feedline isolation valves are opened. The regulator pressure will

3.

The gas feed full open until

lines will such time

fill to the regulators. as the downstream will

flow

regulated warm up.

is reached. will be has

The catalyst monitored failed opening. Pressure The presented The present in

bed of the catalytic

reactor

Tank pressure

to ensure an open

that after regulated condition resulting

pressure in a

is reached, rise

no regulator and relief

pressure

valve

Schedule schedule at the maximum chamber pressure condition is

pressure

in Table A-14. acceleration at the head (due to valve A-tO long feed lines and large oxidizer the tank) preswith

throttling Figure levels drop

has not been shows how the

considered

in sizing head

surization vehicle feed head MPa

system.

acceleration Figure A-IO

varies

acceleration

and oxidizer with

use.

also shows

how the

line pressure available (35 psi) will

varies

oxidizer is shown

flow rate. in Figure

The net acceleration a minimum of 0.2

during is not

the mission for supply.

A-11;

available have to

pressurization, This results

that

the

pressurization of subsystem

subsystem weight

in a decrease

of approximately

472kg Weights

(1,040 Ibs).

S_stem/Component The presented

pressurization in Table A-15.

and oxidizer

delivery

subsystem

weight

breakdown

is

Table

14.

Pressure

Schedule

Pressure Chamber Pressure Drop (Max.) 7.5 2.2 0.3 0.03 0.4 ]0.4 - No flow ]2.4 0.04 0.99 ]].4 ]4.2 0.] 0.03 Max. Min. Max. 14.4 68.9 73.9 +

(MPa)

Injector Valve

Drop Drop

Isova] ve

Mani fo] d Drop Tank Max. L_qu_d Tank Pressure Pressure Drop Reactor Nc_. M_n.

Man_ fold Catalytic Regulator Regulator

Outlet, In]et,

8%

Man_ fold Iso] va]ve B]c_down Initial Initial

Drop Drop

Pressure, Pressure, Pressure,

@ 289K @ 311K

0.62

o.62ii

0.48

_'/J
LTOTAL ACCELERATIONHEAD

111
Q_ u_

\
0.21

\
0.07 0 50 100

Figure A-IO.

GG/LOX

Hybrid Acceleration

Head and LOX Line Pressure

Drop.

,.3.48

0.41

r,,

3.34

/
/
0 20 40 Time 60 (Seconds) 80

,. r'-,

O. 30

0.21 100 120

Figure A-11.

GG/LOX Hybrid

Net Pressure

Head.

Table

A-15.

System

Weight

Breakdown

Pressurizing Bottle FJ ] ]/Vent Isolation Gas

System

Weight 9,001

(KG)

Valve Va]ve (2)

0.9 9.] 7.3 83.5 4.5 298.5 3,600.6 13,005.4

Mani fold (4)

Regulator

Re] ief Valve Cata]yt Tridyne ic Reactor Gas

Oxidizer Tank

Delivery

System

Weight i0,885.3

(KG)

Fi ] I/Vent Fi] l/Drain Isolation Liquid

Valve Valve Valve (N.O.) (4) (N.C.) (4)

0.9 0.9 90.7 ] ,]38.5

Manifold Valve Valve

Iso]at ion Throttling

(4)

90.7 110.7 12,317.8

In--ion The main thrusts of the _


Investigation relatively Acccmplish be the designed most low of tank

fed system study involved the fo]]cwirg:


pressurization reliably, studies the throttle to safely systems and to provide cost. could a

candidate pressure, pump

at mini_L_n that a and pump

sufficient to

determine

accommodate way to

required the f]_.

thrott]irg

determine

efficient Syst_ system

Pressurization The pressure considered fed system pump to fed the

requires tank. the stmmary in

a The

pressurant basic those types

to of

provide

small

"head" systems pressure and both is

oxidizer essentially A

pressurization during their is the

were

same of Table

as

investigated and table

studies. are Some true as the

these A-16.

systems This for

advantages to This

disadvantages oxidizers. particularly elindnated

stm_narized approaches for

applicable concerns; was

were

eliminated H202.

safety

95-percent the _rk

Although

H202

eventually

oxidizer, Systems

acc(m_]ished

is reported.

Pressurization The the not

for H202 shown designed All and and of in Table so the A-17 a were single investigated. point system The failure schemes A/I of

pressurization were loss to was meet made

systems

systems cause

conceptually of mission.

that

_u]d were

pressurization requirements.

assessed prooess The o:m_lexity. Costs gas the was

reliability on a cost system the

safety

actual

selection

weight was

basis. rejected oo]d the because gas of cost and

autogenous Although same and is

eventually

solid-grain-augmented lower weight of its than

system gas

basical]y
stored and are be to

slightly

stored

system, data

fina]ly higher ocm_tib]e The problem auto

selected reliability. as cold arises therma]

because In gas. from

]arger the

historical

base gases

slightly not safe. about and make an as

addition, In the reality, fact

higher

temperature would

these when

systems

probab]y H202 gets

that can

95-percent unless The

250F,

decomposition of the tank though

result occur. of

c]ose]y

oontrolled tends to is

overpressurization this concept safe,

cou]d

feature hydrogen

that

even

some

the

peroxide

,-- e-a.; C ,... 0 e" _ e,J

f_

a.)

l,..

0.,,.-

e-

0. Q.J s.; e0 E

a_ o

aJ w.J (/1 u9 tO _ e0 N _. 0 .._ e._ _ 0 0 L.) "_'0 _-- tO e-_ _:: 0 %.. e",0. _ _ ee-" e_ _j _" _-

F_
u_

e- 0 _,J--J

'g
I_1 _ _

-_
0 l-

I c[ _J

_,. I,_

t_ (1,/

l.-0 "_" I. e-

o "_ "g

(_ Qj

_.ee-

.,"_ _-

.,.-_.0 r._

_ ,.,-. _ $_

,="0 .r_ _--

x _ tO QJ

_ _'_ etO I"--

0 U Q; "_

0 e-

o o

"T_

de--sing, oxidizer rate of

is usage. gas being Gas

that The

the rate

tank of by A

ullage ullage the

volume increase

is

oonstant]y be much

increasing greater

due than

to the

should of the

produced (Helium) in not

deccm_positJon diagram It uses of

hydrogen the _nts One one to

peroxide. helium so gas

Stored concept point of

schematic A-12. a

showing redundant

stored

is presented failure would

Figure cause

a single the wi]] use be

failure

a mission. only be out used the

examp]e regulator detect a

is

two

regulators. A whereby an health an

During monitoring isolation valve

normal

operation, wi]] lock

utilized. failure and open The oxidizer largest he]it_n of is the a

system wi]] the

regulator regulator on line. volume, The of

valve to a]]cw

malfunctioning to cane

isolation of

redundant is a

regulator of

amount tank portion

pressurant oxidizer

required

function and

oxidizer

tank

pressure, of the

temperature, system The

pressurant is from

temperature. the quantity

pressurization bottle and weight. the storage number f]ight in system which the source drive

weight

and

the

he]it_n of of gas

he]ium

bottle and

weight

is a

function

quantity function

pressure of

temperature. and

Reliability of the

redundancy, (ground and

(x:mlx)nents , is a

database of

components. or processes Autogenous In this

Safety that can

operation) case

function

components

malfunction This

a worst is drive

scenario. schematically in Figure to A-13. an is used

Syste_ the to a in is of

shown the

concept, pressure since

turbines accc_m_date

pumps tank

are

designed The

have

output

required is the not

pressure. The as of a solid its the

system is

simplified

separate this used case to

gas to

required. and

oxidizer own

catalytically, A The the taken maximum. acoDmmodate requi reme nt. Stored Figure addition provide system A-14. of a Gas relief static valve head

turbine,

pressurant. tank. spin must up be

prevent in the

overpressurization tank, to as we]] the as

oxidizer to

oxidizer be the

charge

turbines, to

should

sufficient turbine of

start

system. to

A precaution the

minimize A/so, a the

outlet the system

temperature must be

predetermined flexible throttling to

design of

sufficiently to the pump

range

turbine

outlet

conditions

due

(Solid It is

Grain

Added) to

A of be

schematic the used cold part

of gas way

the

concept

is

shown for

in the to

identical charge

that wi]] the is

concept through The stored

except the

solid

which up

m_ssion of

additional is the gas

gas

to heat

remaining smaller

helium. than the

advantage cold gas

this

storage

vessel

because

Table A-17.

Comparison

of Selected

H202

Pressurization

Concepts

SYSTEM CONCEPT Stored Gas (Helium) Autogenous Stored (Turbine Discharge)

WEIGHT* 2616 1860 2559

COST

INDEX

REMARKS Ist - Simple & low cost. (cost). than

100 It5 105

High Complexity

Gas (Solid Grain Augmented)

A little more complex plain stored gas.

* Weight

in kilograms.

I--]Fill/Vent

Valve

Isovalves

NC

lsovalve

_ NO

Isovalve

Regulators

[--'_ Fill/Vent

Valve

Figure A-12.

Stored

Helium Gas Pressurization

System.

N.C.

Isovalv(

Valves Relief N.O. Isovalve I--]Fill/Vent Valve

_]

Fill/Drain

Valve

To either Main GG or, Thrust Chamber

0-1C System); ,-(GG System)..J_. Gas Generators

! Throttle Valves

Turbine

Exhaust

Figure

A-13.

Autogeneous

Pressurization

System.

hd Propellant

Grain

[_]

Fill/Vent

Valve

Isovalves

) NC Isovalve

NO

lsovalve

Regulators

F"]

Fill/Vent

Valve

Figure A-14.

Stored Gas (Solid Grain Augmented).

there solid dental of gas which the

is

less

gas

to

store. and of

However, ignitor solid

additional and associated could

ccmp]exity wiring result in

is added is

because Acci-

propellant early he]itml the

grain

required.

ignition bottle. regulators

the

charge a filter debris can be

overpressurization to entry of the to of

In addition, because is of

is required the solid.

prior The

into the

from

temperature by the type

remaining grain

gas

heated

easily

oontro]]ed

propellant

utilized. Systems for LOX LCM is not a monc_rope]]ant, with hydrogen into a given therefore, peroxide. the tank more LOX, wi]] be

Pressurization Unlike pressurization however, ooo]ed; Systems is thus a hydrogen

peroxide, are

concepts cryogen, more

applicable any

than pressurant to below. same

therefore, is are This

cx_ming

pressurant for study -

required

maintain

tank

pressure.

selected Gas that

discussed is tank the

Stored A-12 of except

(He]it_n) the are

pressurization LOX instead of

as

shown

in Figure results

oxidizer

eontains A-18. -

H202.

The

the

analysis Gas

sum_narized Grain

in Table Aucjmented) A-14. system to

Stored d_scussed

(Solid

This

system are is

is

identical

to

that A-18. A-15. taps

previously

in Figure This

The

results

presented

in Table in The Figure first

Autogenous There are two gases second separate the

System possible (shown

concept power from the the

presented turbine. solid

sources in

combustion and uses to the a

schematic) gas

fuel-rich the

gas

generator, The the latter gases cost. and

uses fuel

separate (i.e.,

generators to

to drive react with the generator the

turbines.

methane) This

[/3X to generate and

drive

turbines. gases

complicates solid to gas

system

increases the turbines

Tapping then that

fuel-rich the

from outlet

the gas

to drive tank

using the

turbine

pressurize turbine of

is viable, and the

providing LCM can be

reaction eontro]led.

between Again,

the the

fuel-rich problem to

exhaust turbine results

readily oou]d A-18.

changing The

outlet are

conditions in Table

make

this

concept

difficu]t

achieve.

shcwn

Stored Figure appendix A-16. of

Reactive This this

Gas

(Tridyne) was

This

eoncept

is

shown in

schematically the A-18. pressure-fed

in

system The

previously are

described

report.

results

presented

in Table

N.C.l_v_ve Relief Valves Fill/Vent Valve

_-] Fill/Drain Valve

To either

Main

GG

0-1C System);

or, Thrust

Chamber

(GG

System),

I
Throttle Valves Main GG

Turbine

Exhaust

Figure A-15.

Autogeneous

Pressurization

System.

Fill/Vent Valve

IsovaJvcs

!
NC Isovalvc (_ NO IsovaJve Regulators

E]

Fill/Vent

Valve

Figure A-16.

Stored Reactive

Gas (Tridxne)

Pressurization

System.

.f.,- ,._

(_

",-_ u_ 0 U',_ 9..rI_"

_)

S.-

(2)

fi.

2. U cO

!
f_ tO ._ u_ ,mr--E 0 _- _-_ "'_._c" Z 0 uO LO ,--k_ (_

C 0 .peO N

'Z
L_

X ...I

(._

)-0 C 0 OxJ t"xg (',3 ,,--

"Z
C: E o O. CZ tO SO *r-_0 I-," ","0 "0 (1) C= *r--e" _. -Jr._ eI--0 t4J

,,

r_ 0 0 0 _ 0

The

basic 1.

objectives Determine operating the over the the the

of

this feasibility the most

subtask of

were: deve]oping range. to drive the turbine and where a tur_ capable of

required effective exhaust. and cost

throttle way

2.

Determine to pipe

turbine weight

3.

Estimate the overall an

of

turbopt_np

capab]e

of

meeting

requirements. overview viewpoint, It since was also in second the program it was schedule determined that of to two speed pumps capable condition, for turbopump that these more p_nps development. than one turbohave would fai]ed, a 1.6:1 a wider have to to be

4. From _)u]d operate insufficient particularly range In during a

Provide reliabi]ity be required.

determined case up the be

would there

simultaneously, time just normal to get

turbopumps, if must of the first

the lift-off.

pump Since

pump over over wou]d

after

thrott]e thrott]ing each pump

operation, under

they

must

a 3-pump over

configuration,

a pump-out

operate

a 2.4:1 throttle operating thrott]e

range. range

In a 4-pt_p is 2.13:1.

configuration, The 4-pump life cyc]e way

with one out, is

the design easier

configuration cost. to drive

to ac_ate, issue

but wou]d was to wi]]

resu]t

in a higher the most

Another turbine.

determine have an

effective

the

This

decision

impact

on turbopump

deve]opment

costs,

unit production No design the attempt studies of

cost, as we]] as overa]] was were made at this point

oxidizer

feed system weight. a turbopump. overview of Sufficient assessment a of

to design

acccmplished, in

however,

to get an the

degree

difficulty system

acccmplishing

development

turbop_mlp

capab]e

of satisfying

requirements. - The general requirements for the LOX turboprops

Turboptmlp Requirements are presented A Acurex in Table A-19. design provided

preliminary Corporation

study

was

conducted

by

two

lxm_p manufacturers. to a pump

pre]iminary gas generators their selected

information to drive approach,

pertaining the turbines. but was

oonfiguration not

using separate represent to drive

This does provided to

necessarily one way

evaluate provided

the turbine.

A_Research

Division using

of Allied tapped

Signal off the

information

pertaining

to a configuration

gases

Table

A-19.

LOX

Turbop_mlp

Operating

Requirements

Maximum Pump Pump

Flow

Rate

3144 0.8 9.5 (11.5 Molecular of Weight 2

KG/sec MPa MPa MPa I)

Inlet Outlet

Pressure Pressure

Turbine Turbine Turbine Chamber

Drive-Gas Drive-Gas

Flow Ratio

13.75 1.12

Specific GG

Heats 2

Inlet Pressure Pressure) Temperature

(Main

Maximum 7.5 MPa

Turbine Inlet Temperature ) Turbine Minimum Minimum Four

(GG Chamber 392K

Discharge Flow Rate

Pressure

0.2 1895 3.5 Pump Out Capability

MPa KG/sec MPa

Chamber

Pressure with S_ng]e

Turbopumps

i. 2.

Regenerative cooling Assuming solids are

version. filtered

out

using

reverse

pitot.

main solid gas generator to drive the turbines. was selected for further evaluation.
Acurex sufficient show the Turbopump preliminary feasibility turbopump booster ptm_ are systen Each that greatly design of Configuration design the work approach, to The primary a

The Allied

Signal turbopump

objective design

was concept

to accallplish that would a

establish to predict

weight,

cost of

and the

establish Acurex

preliminary pump and

development are shown

plan. in Table

Characteristics A-20. and Turbine A-22,

main

and

gas

generator

characteristics The thrust were This feed

presented will

in Tables utilize 4

A-21

respectively. to feed The design feed a single

parallel by could a

turbopumps gas generator. the

chamber. sized such

turbopump three

is driven

turbopumps flow rate.

turboptmlps the

provide of the

capability The basic

improves of the

reliability is

overall and

system. the stateAn the

turboprop fuel-rich not a the

conventional gas generators a positive

within

of-the-art. oxidizer-rich turbine safety, rich gas Both size. times is much means surant rich a The that and

Oxidizer-rich turbine the pump. and is drive

and does is of

were shaft and

evaluated. seal between

require great

This cost

simplification For this

impacts the

inherent oxidizer-

reliability generator the total of the for

turbopump. the

reason,

favored

to drive and

turbopump. gas generators gas generator the small and flow are similar in three

oxidizer-rich flow rate for

fuel-rich

the

oxidizer-rich

is about rate

fuel-rich the

gas

generator. gas is

However, A weight

of methane of methane less an pres-

less small than

oxidizer-rich tank gas which

generator. lower In in

quantity requires case, the

methane fuel-rich was the

generator. primarily while

this

particular

oxidizer and

gas

generator of

selected turboptmlp cost.

because

it simplified the inherent

design

construction bility, It generator generator, using using the gases and

increasing

safety,

relia-

decreasing also of for gas off be

should

noted

that are

the

characteristics to those the

of from

the the

fuel-rich main of solid

gas gas

products except fuel-rich tapped

combustion solids

similar

content. would solid gas

Therefore, be

design the same

the for a

turbine turbine

generator the main

essentially

generator. This ooncept the uses gases The tapped off

AiResearch the solid

Turbopumlo gas

Configuration generator to

fuel-rich

drive

turbines.

turbopump

Table A-20.

Acurex PumpCharacteristics

(4 PumpConfiguration) 3144 3 (i pumpout) 1048 65 1113 0.4 0.1 0.3 30 20,000 8,000 8,000 5,000 1.7 150 9.9 879 ] ]. 5 5748 2449 2075 0.66 3]45 12,116 0.85 14,255
131 0.5 86 33 38

Total Flow Rate to Thrust Chamber,KG/sec....... Ntm_er of Pt_,ps................................. Flaw Rate per Pump, KG/sec...................... GGOx Flow, KG/sec.............................. Total PumpOx Flow, KG/sec...................... Suction Pressure, MPa ........................... Vapor Pressure, MPa............................ . NPSH,MPa ....................................... NPSH,M......................................... Suction Specific Speed, Boost Pump .............. Suction Specific Speed, Main Pump ............... Main Stage Shaft Speed, rpm..................... Boost PumpSpeed, _ ........................... Boost PumpPressure, MPa....................... . M.......................... Main PumpPressure Rise, MPa .................... M...................... Discharge Pressure, MPa........................ . Specific Speed Boost Pump ....................... Specific Speed Main Pump ........................ Fluid Power Boost Pump, hp...................... Efficiency Boost Pump ........................... Shaft Horsepower Boost Pump, hp................. Fluid Power Main Pump, hp....................... Efficiency Main Ptmlp ............................ Shaft Horselx:wer Main Pump, hp.................. Tip Speed, Main Pump, raps.......................
Head Coefficient, Diameter, Diameter, D_ameter, Main Main Boost Boost Pump ..................... Pump, Pimp, Ptmlp, raps............... am ............... (_n................ Impeller Impeller Suction

Table A-21.

Acurex Turbine Characteristics

HIGHSPEED Type........................... Axial Flow, 2 Stage Axial Flow, 3 Stage Speed, rpm..................... 8,000 8,000 Power, hp...................... ]4,255 34,255 6.89 Inlet Pressure, MPa........... . 6.89 Flow Rate, KG/sec.............. 66 66 867 Temperature, K................. 556 46 Tip Diameter, CM ............... 46 ] .5* Blade Height, ist Stage, CM .... ].5 ]92 Tip Speed, MPS ................. ]92 0.22 Stage V/Co ..................... 0.35 0.4 Efficiency ..................... 0.7

LOW SPEED Type........................... Speed, rpm..................... Power, hp...................... F] c_ Rate, KG/sec.............. Exit Pressure, MPa ............. Exit Gas Temperature, K........ Exit Gas Density, KG/M 3........ Tip Speed, MPS ................. Blade Height, CM ............... Axial F]c_, 1 Stage Axial Flow, 2 Stage 5,000 5,000 3,]45 3,]45 21 66 0.4 0.4 494 389 4.0 ].9 ]20 ]20 ]0.2
7.6

* Partial

Admission

Table A-22.

Acurex Gas GeneratorCharacteristics

CK-RI(]_

FJEL-RICH

Propellants Mixture

...................... O/F ............... K ................... MPa .................... KG/sec ................ KG/sec .......

LOM/Methane 47 556 6.89 66 65 ].4 57.4 8.6 ]52 8758 ]6.5 48

LOX/Methane 0.6 867 7.] 21 7.7 ]] .8 36.] 6.9 ]52 55]0 ]2.7 43

Ratio,

Temperature, Pressure, F]ow Rate,

Oxidizer Fuel Throat Throat F]cw

F]ow

Rate,

Rate,

KG/sec

...........

Area,

CM 2 ................. (34.............. Length, CM ........

D_ameter,

Characteristic Chamber Diameter, Length, Volume,

CM 3 ..............

CM ..................... (34.......................

characteristics are sum_arized in Table A-23. The gas generator must be modified to aco(mmx)date the added requirement dictated by the turbine flow.
This for autogenous driving the turbine turbine are not drive since should theoretica]]y f]uids, an be gas the ]owest cost approach confound additional However, gas stream. using and the so]id of from gas the the generator gas for driving change and in generators, method storage must be

tainers, to

etc., the

required. out of the

efficient

separate Another

solids

problem is the that

associated the

with

the

turbines

pressure Four

flow _re

rate taken

generator

throughout the Tab]e

flight. turbopump

points

flight

profile, are shown

resulting A-24. Turbine

characteristics

for

these

conditions

Discharge the gases the

- There coming gases out to

are of

basically the

four

choices

available

as

to what

to do

with I.

turbine. through a separate nozz]e or thrust

Exhaust chamber.

ambient

2. 3. 4.

Use Use Use

a]] part a]]

or of or

part the part

of

the

exhaust for

to

pressure vector

the

LOX

tank.

exhaust of the

thrust

control. to heat pressurization gases

turbine

exhaust

(cold A/I wou]d require be of to

gas

system). above have via a some degree of merit. however, A pre]iminary final selection will

the

exhaust detai]ed

separate

nozzle;

se]ection

more

analysis. Feed System to Selection acccmplish was a program it stored cost is analysis, presented This Each fails a in gas leg to

Preliminary For pre]im/ Figure m_xture planning

Oxidizer purposes

and

nary A-17.

oxidizer The

feed

system system

selected; of two

pressurization in the fu]]

consists by in so

Tridyne. va]ves. valve tank

is contained of handling

pressure gas flow

bottle just

iso]ation one

is capable open. at all

case that

isolation in the

A pressure times. gas and up f]cw to

transducer

is provided

pressure

is known

The regulator to and heat

then

goes

to gas

normally

open where

isolation the the _ oxygen

va]ve and are the

through hydrogen heated first

a gas react helium and is

a catalytic helium,. The

generator

the A

products

entering in

tank with

steam.

second

regulator

is provided

para]]e]

Table A-23. PUMP


Type
LQX Flow HP Rate, KG/sec

Airesearch TurbopumpPerformance Characteristics


NOMINAL OPERATION Stage Mixed PUMP Flow 1048 (11,750") ]4,000 0.76 (23.6) 22.9 (23.6) (17,300") OUT OONDITIOM

S_ng]e 786 9500 0.84 Diameter, CM 22.9

Power,

Efficiency Mean Tip

q'JRBINE Type Turbine Turbine Efficiency Speed, Tip rpm CM Inlet Flow, Pressure, KG/sec MPa One 5.2 (1) 7.3 0.42 ] 6,000 a8.3 (9.0*) Stage Impulse 7.5 10.4 0.48 ]7,000 48.3 (]2.8*)

Diameter,

* (i)

Regen cooling condition Thrott]ed frcmmainGG

pressure

of

1085

psia

Tab]e A-24. Time on Duty Cycle


Flow F](_ Gas Pump Pump Speed, Required Turbine Turbine Turbine Rate, Rate KG/sec per P_np, Chamber Pressure KG/sec (Seconds)

LCKTurboprop Transient Performance


i0 3]44 786 MPa 7.5 9.5 0.84 ]6,000 60 2]77 544 5.2 6.5 0.75 ]2,640 4825 2.8 0.37 4.8 80 2359 590 5.6 7.] 0.76 ]3,280 5628 3.] 0.39 5.3 110 ]905 476 4.4 5.6 0.74 ]],520 3657 2.3 0.35 3.9

Generator Out]et

Pressure, (2), MPa

Efficiency rpm Power, Inlet HP Pressure (3) , MPa

9500 4.3 0.43 7.3

Efficiency F]cw (4) , KG/sec

(i) Using so]id propellant gas generator fluid to drive Ablative cco]Jng version. (2) Assuming 26.7% h_gher than chamber pressure. (3) Throttled down frcm chamber pressure. (4) Total turbine flow for whole duty cyc]e _s estimated

turbine.

to be

6]7

KG.

Pressure

Transducer'

'

[--]

F_/Vent

Valve

lsolationfNc)Valves

I
Isolation Valve Regulators Isolation Valve (NO) (W/Health Monitoring Equipment) Valve _

(_Q NO Isolation

I 1 Ca_ytic

Gas

Generator

Fill/Drain

Valve

.Throttle Fuel-Rich Solid


Gas

Valves

Generator T = Turbine P -- Pump

Turbine Exhaust [ _For To Injector Ablative T.C.

Figure

A-17.

Preliminary

Oxidizer

Pump Fed System

Schematic.

connected

to

normally this

closed

isolation valve can be can be

valve. opened. and

In

case The

the

first

regulator valve with to in no

malfunctions, the

isolation regulator with In

isolation will should

malfunctioning Regulators

closed,

the

system systems

continue be used with

operate. this

built-in this

health switchover

monitoring should

application. signals the

fact,

occur

automatically

outside

required. fluid to be pressurized is cryogenic, this forced than shou]d out of the steam generated any This the off The will

Since liquify until and the

eventually bit of

freeze. oxidizer more the

However, is being oxidizer gas power

not the

cause tank. for

problem can be

last by

prevented

adding gases

slightly from

is required are

mission. and sent

Fue]-rich through exhaust parallel will

solid to a

generator parallel and

tapped

throttle passed

valves through

turbines. to the

turbine pressure emergency upstream

be

nozzle can be

expanded in

ambient an just

conditions. shutdown of the

These is required.

throttle The

valves single

closed open for to

event valve

normally used

isolation an emergency the pump

catalytic

gas

generator tank is

is also sent and used

shutdown. The oxidizer when when an a

Oxidizer pressure ablative regenerative A both system

from

the

directly sent or to the to

inlet.

is greatly thrust

increased, chamber thrust is

thrust inlet

chamber cooling

injector jacket

the

cooled

chamber is

is used. shown Jn Table thrust A-25. chamber This schedule covers

pressure and

schedu]e

the

ablative

regeneratively

cooled

cases.

Tab]e A-25.

System Pressure Schedu]e

Tridyne Storage Pressure at 289 (MPa) Regulator Outlet Pressure (MPa) Catalytic Gas Generator Pressure (MPa) Tank Pressure* (MPa) Inlet Pressure to Pump(MPa) PumpOutlet Pressure (Ablative) (MPa) PumpOutlet Pressure (Regen) (MPa)

68.9 1.8 ].8 0.8 (min) 0.9 (max) 0.4 9.5 ]] .5

*Inc]udes static

head. Minimumtank pressure is 65 psia.

APPI_DIX

HYBRID LIFE

CYCJF. COST

Ilybrid

I/_

Rx]e

(bstilg

_tl*xblo

The from

hybrid

LCC

model

was

developed

using

a wide

array upper

of

cost

experience tactical/ cost ability is ]ess that more in and

launch

vehicle

programs, and

spacecraft/probes, aircraft. into the the As costing "pieces") the more hybrid the usually

stages,

strategic models, of the

missiles, weight is level the as the

(xmmmercia] input

in

most

parametric The cost

primary

algorithms. to predict

]cwer than

relationships mode] in a in total.

(i.e.,

accurate is

Typically, of the

detail

design program,

data the

available, the

later

phase

booster total very

accurate preliminary comparab]e. The elements. hardware costs, the and

component studies such

costs. as this

However, one are

costs

produced

representative

cost

algorithms estimating design

for

the

hybrid

booster (CERS) hardware items

are are

comprised used to

of

several the Other to

Cost engineering called

relationships costs and the for figures

predict costs.

manufacturing not directly to

support itself.

costs, Finally, are

account cost

attributable

hardware support The

related

facilities,

ol:eratJons,

equipment

calculated. design engineering include the shop, tasks testing, of basic

component and and

hardware design, and of

component support, CERS

subsystem supervision the

drafting, clerical. basic The

developmental The component labor, set of

finance

hardware quality cost

manufacturing control, and are and

include and

tasks

factory support

subcontract systems everything engineering

material

costs. software other.

relationships tooling,

engineering, else called

engineering, Some of the

system other and costs

test,

include

]ogistics,

liaison,

facilities

engineering,

data.

Cost

Element

Definitions

Design knowledge configure

Engineering: of and

The

function natural of

concerned phenomena, and

with and

applying the which to

understanding industrial satisfies prepare arts known

and to or

materials, design of systems

hardware It

software the

anticipated systems design

needs

customers.

includes and

effort

hardware/ and

drawings, confirmation

data, by

specifications, mockups,

required

design prototypes,

reviews, etc.

utilizing

breadboards,

Develq_entad Shop Labor: The shop support to engineering during the design, development, test and production activities. It includes the planning, building,
articles, development tools, tests, and maintenance to of models, in to the breadboards, conduct of mockups, laboratory test and assistance and engineers liaison

inplant

remote

activities.

Subsystem cc_ponents and verify

Integration into

&

Test:

Includes it

the

effort the and

to effort

integrate to test

subsystems. and

Specifically, structural

includes

electrical

interfaces

specification

ccmpl iance.

The

following

manufacturing

CERS

include

the

following

task

direct

funct ions:

Manufacturing production shipping. manufacturing the manufacture

Engineering: planning, Some of the special tasks

It

includes

the

activities

of

too]

and and into for ng

charges, include

manufacturing

development, designs required manufacturi the

converting equipment

engineering and tools

plans, of

identifying the

factory

hardware,

reviewing plans

supp]ier and

capabilities, of items

providing in

numerical

control and

programs, on the and

charge

damaged

transit, shipping

refining

reporting and

manufacturing crating parts

process, for

fabricating and

containers,

packaging

in-house

customer

delivery.

Quality on

Assurance: to see

The if and

effort

required engineering that

to

perform

non-destructive

tests

hardware

it meets ensure

requirements, products and

specifications, procedures meet

T.O.

requirements, requirements.

vendor

qua] ity

Subsystem assembly.

Assembly: Included _uld

The be

effort any

of

joining

ccmponents

into

st_-

subsystem

testing.

Basic

Factor and

Labor

(BFL):

The test and

shop an major end

activity item

required of hardware

to

fabricate, to include

assemble, fabrication,

functional assembly,

minor

assembly.

Final Assembly and (l_eckout:


final item. assembly. Inc]uded _u]d

The effort
be the

of joining
final

subassemblies into
test of the

functional

end

The

following booster

definitions cost model.

relate

to

the

support

oosts

categories

of

the

hybrid

System integrated system, integrate design; identify, elements, provide tion;

F.ngineering: engineering GSE,

A]]

activities It

directed includes

at the

assuring effort to

tota]]y

effort. and test

establish and and to

subsystem, technical to a]/ocate define, to monitor and to maintain

requirements to optimize parameters interface equipment to

and total to

criteria; system

to define definition ]eve];

interfaces performance and control and

the

subsystem

requirements determine CEI

between

system to

design inertia] and

compliance; and

properties system processes

analyses, specification

support to and

documentaparts, integrate is the from

develop and

maintain and

provide to

standards product

materials

surveillance to this

assurance of

activities. system ]eve]

Fundamental design and effort

element and derived

documentation customer analysis. definition, optimization, and intrasystem

requirements guidelines includes, and

established System overa]] cost and

requiren_nts engineering system

through

functional system system analysis includes requireof

for

examp]e, analysis, balance It also program

design,

design

integrity weight and

effectiveness intersystem

analysis, compatibi]ity safety, and

analysis. survivability program

reliabi]ity, ments, equipment ments, tion human

maintainability, engineering component support and

manpower

factors,

preparation

and logistics

performance integration,

specifications, and design of

security test and

requiredemonstra-

plans.

Software maintain software

Engineering: (for the

All

effort phase

to being

design,

develop,

test,

deliver, software; rules

and with and

program all

estimated) data,

computer

including

associated for system

programs, operation.

procedures, may be

docuraentation

required

Software

subdivided

into

the

three

categories

of

test,

ground

operational,

and

flight

operational.

System equipment

Test: as a

All

manpower in and

required order qualify to

to acquire the space

plan

for

and

test data, in

prototype confirm This wind

system

engineering design (space

engineering element tunnel, subsystem

hypotheses

system chamber

total.

is limited ground

to envirorm_nta], based tests, and

programs),

includes and

static,

dynamic, tests.

fatigue,

performance,

qualification,

reliability

Tooling design, and aids mission and/or the

&

Special

Test

_:jtdpment:

Tooling

includes test, and for

all

effort

to

plan,

fabricate, jigs, are

assemble, dies, fixtures, special

inspect, molds, nature

install, patterns, necessary

modify, other the

maintain,

rework that

manufacturing manufacture of

of

hardware. manufacture or

Special that

test

equipment

includes which

all

effort for

to

design during

unique

equipment of mission

is used

testing

development

production

hardware.

Other: logistics, engineering,

The

other and

category other

is

ec_prised

of effort

liaison such as

engineering, facilities

data, safety,

miscellaneous etc.

training,

The thermal of the

hardware protection, same box CERS CER

design tanks, will can be be

and

manufacturing box, a the

CERS actuation of gas

are

defined

to

the

]eve]

of

control used in in

system, subsystems.

valves, For

etc. example,

Many the the

variety cold

control liquid

used the the

pressurization

subsystem,

tank The

subsystem, of The

and using

nozzle cost routine

subsystem. mode] must begins supply with a careful (in accounting for of each

process

all line

CCmlzonents. item. Design

weights

weight

pounds)

engineering

costs

follow

the

form:

Engineering

Dollars

= A(wt)**B

The answer is subsequently modified by linear multipliers of this equation that account for hardware ccmplexity, technological maturity, and the degree of "off-the-shelf" hardware designs. The off-the-shelf (OTS) factor is a correction factor that acoounts for previous design efforts that could be applied to a new _nent, thus reducing the eost of engineering design. At the lowest and finest level of ccmponent definitions (nuts, bolts, chips, etc) virtually everything wou]d be off-the-shelf. The other extreme, the macroscopic end item ]eve], virtually nothing is off-the-shelf. To determine where the OTS factor would fall in this spectr_, we try to estimate what percentage of the total engineering drawings/specifications are available for a given component. Figure B-I
simply a valve converts required this percentage to an OTS factor. and By way of from example, a similar suppose valve or 15 engineering and valid. OTS The factor for drawings, percentage (from Figure 3 drawings of available of 0.8. Figure B-2, relates an for

were 20%,

applicable corresponds Similarly,

drawings,

3/15,

to an the

B-l)

curve of

design

ccmp]exity ccmp]exity to

factor, an

experienced the design The maturity status maturity of

judgement cost third for the

component

appropriate

multiplier

equation. design cost multiplier technology. technology use as reflects A the impact is made of the ]eve] of the a

the

selected

judgement

concerning B-3 provides equation.

hardware's factor to

development. to the

Figure design

design

a multiplier

cost

_R

0 c_

0
0
l.L IU

l,.0

L_ F-Z

i, e'_,..

Z
D

LU
U. .J LU

er. UJ

e!

_-r"
!

t_ ! LU

llJ
!

"T

LI. U..

C_

I"

C_ C_ 0 0

_--

_r-

C_

I=IO.LOV4 NZ)IS_BC]

n-r" ILl
,-J

0
0

>. iX DcO

E 0

I-"
D

0 (.9
Z

t_

X I.LI O.

e._

I-0

0 0

e"

e-

e_

Z r_ t.O ILl
m

OJ

O_

0,1

T-

_317dl7171Al

"

1._

t,...;

c)
LJ

,:

==

,,, =

LJ... _

>.,

I r-",, 0J .t....

_.

'_ == = ._.F. _-: _

-'
.__ Ilmlllm

oRIGINAL OF pOOR

pAGE

IS

QUALITY

The

following

CERS

are for the engineering factor)* (OTS

design have

of hybrid factor)

booster

components.

Note that all the equations

the form

(A (wt) * B) (complexity N0_e Cone: Structural

facto r)* (Maturity

shell

- includes

all structure

and fasteners tank.

for nose

cone

section

and attachment provisions A = 8609.5 B = 0.7647 Thermal - includes thermal structure of nose. A = 5,470.6 B = 0.6200 Cold gas oressudzation Tank - includes System: all structure,

to oxidizer

protection

and

insulation

and attachments

to

liners,

insulation,

and attachment

fittings

for

high pressure tanks fcr pressurant storage. Small tank: A = 57,700 (less Large (more Valves - includes than tank: than 200 Ib) valves, 200 Ib) B = 0.7643 A = 158,059 B = 0.479 service (less (more relief than than valves, and and pressure

iscla:ion

regulators. A = 72,220 B = 0.7034 A = 87,_20 B = 0.5163 Contrc! bcxcontroller includes structure, fcr pressurization A = 173,300 B = 0.7031 35 Ib) 35 Ib)

electronics, system.

wiring,

and a_achment

of

Oxidizer

tar_k: shell - includes all structure, cone stringers, and interstage. attachments, and --

Structural

interlace

flanges to nose A = 9188. ,4 B = 0.7638

Valves

- includes associated

isolation valves, pyro with oxidizer tank. A =72,220 B = 0.7034 A = 87,420 B = 0.5163 (less

valves, than than

and service 35 Ib) 35 Ib)

valves

(more

Control box - includes structure, electronics, wiring, and attachment of controller for oxidizer system. A = 173,300 B = 0.7031 Thermal - includes external thermal protection, insulation, liners, and attachments to tank structure. A = 5,470.6 B = 0.6200 Nozzle"
Structure - includes Based solid Actuation assembly nozzle structure and gimbal design and attachment activation. gimballed is vs. fixed 1.28 times hydraulic TVC nozzle higher) control, concepts. difference (Note: provisions to combustion chamber motor

on total

- includes

actuators,

sensors,

accumulators, and attachments A = 68,740 B = 0.8764

for gimballed

nozzle

Fluid

injection associated

system

- includes

all plumbing, TVC

sensors,

and injectors

with a fluid A = 130,000 B = 0.4100 all valves

injection

concept.

Valves

- includes

associated (less

with than

fluid

injection

"FVC concepts.

A = 72,220 B = 0.7034 A = 87,420 B = 0.5163 Thrust Control Valves valve: variable

35 Ib) 35 Ib)

(more

than

- includes control.

(throttleable) (less (more

valves than than

associated 35 Ib) 35 Ib)

with thrust

A = 72,220 B = 0.7034 A = 87,420 B = 0.5163

Control box - includes structure, controller for thrust control A = 173,300 B = 0.7031

electronics, valve.

wiring,

and attachment

of

Lines Lines - includes oxidizer lines, bypass lines, pressurant system lines, and turbopump fuel feed lines. A = 17,640 B = 0.4951
Other structures: Aft skirt with - includes nozzle, all structure actuators and fasteners, pad. interfaces case, and attachments and gas generator and load paths/hold

downs

for interfacing with a launch A = 218,000 B = 0.3305 allstructure

Interstage-includes

andinterfaceflanges

and a_achmentsto

the oxidizertank and gas generatorcase. A = 75,125 B = 0.4569

Attach

struts

- includes

all fore and aft attachment loads between the hybrid

struts booster

and fittings and parallel

required to handle core vehicle.

A = 795,000 B = 0.273 Seosration Rocket motor_' (cluster) motors -includes all rocket motors, ignitors, system. a_achments, safe and arm, anc secuencers A = 1,610,784 B = 0.553 for separation

Eiectrical Systems: Eiectronics and software, sequencing,

Instrumentation software range safety, A = 221,800 B = 0.5276

-inc!udes and control

all electronics algorithms.

hardware

and

development,

monitoring

instrumentation,

Electrical

power

supply hardware

- includes

all power power

storage, of time

conditioning, valves, from ground

and and umbilical

distribution

for electrical

to electronics,

any electrical actuators for the period disconnect to vehicle recovery. A = 242,500 B = 0.7009

Cabling - includes all wires and interface connectors assoc!ated with electrical power and signal distribution. A = 87,389
B = 0.63 Tvrbo0umos: Oxidizer (and hydrocarbon) turbopumps - includes turbopump assembly, exhaust system, and mounting A = 35,000 B = 1.000 provisions.

.Gas Generator: Solid motor arm, - includes and injector all structure, hardware. (General rocket equation motor) for total solid insulation, propellant, ignitor, safe and

A = 261,000 B = 0.4100 Injector -includes all structure A = 279,796 B = 0.4900

and interfaces.

q;atatyst

Bed: Bed - includes case, catalyst, interfaces, and mounting provisions. A = 195,857 B = 0.490

Catalyst

After

calculating

the engineering integration dollars equation. effort.

costs,

a 20%

addition

is made

to account

for

the subsystem The

manufacturing dollars

are calculated The equation

using

the same

general

form

of the of a

engineering

is then

modified

by a series complexity,

linear multipliers material factor,

that account for the hardware manufacturing and the learning curve cum factor. CERS, curve factor the first of these as for engineering for a selected linear design. multipliers, Refer level.

For the manufacturing factor, select uses the same the appropriate

the complexity to Figure B-2 to

complexity

The manufacturing costs are also modified by a material factor which accounts for the relative cost of manufacturing and raw materials for typical booster hardware. The material factors used are as follows: Aluminum Aluminum Lithium Titanium Stainless Steel Carbon Composite Steel = 1.0 = 2.64 = 1.45 = 2.0 = 1.14 = 1.0

The third multiplier accounts for the learning curve effect. The learning curve (LC) cum factor includes both the "slope" of the learning curve, as well as the quantity of units produced.

The value of the Nth unit, call it Y, can be expressed as

Y -

log10 AN

(slope) lOgl0 (2) unit slope

Where: Slope

A - theoretical learning

first curve

(TFU) values

value

The

cumulative

curve,

which

results

in a LC oum

factor,

is calculated

from:

LC cure factor

" Z + 1 Where:

(N + _) Y Z - m AN using

By way of example, building factor value of approximately

300 valves 171.3.

a 92% curve

results

in a LC cum

The following CERS are for the manufacturing of hybrid booster components. Note that all the equations have the form: (C" (wt) " " D) * (complexity factor) * (material factor) * (LC cum factor). The component descriptionsl as far as what each item entails, is the same as the descriptions previously given for the design CERS.
No_e Cone: Structural

shell

C = 12,140 D = 0.6727

Thermal

C = 2,156 D = 0.7505 system: 200 Ib) 200 C = 22,390 D = 0.5713 C = 14,863 D = 0.654 C = 4,254.7 D = 0.8617 C = 3,520.9 D = 0.5228 (less (more than than 35 Ib) 35 Ib)

C,.,01dgas oressurization Tank Small (less Large (more


Valves -

tank than tank than

Ib)

Control

Box-

C = 52,540 D = 0.5669

Oxidizer

tank: shellC = 3183.84 D = 0.8076

Structural

Valves

C = 4,254.7 D = 0.861 7 C-= 3,520.9 D = 0.5228

(less (more

than than

35 Ib) 35 Ib)

Control

box

C = 52,54O D = 0.5669

Thermal-

C = 2,156 D = 0.7505

Nozzle:

Moveable:

0.5X

(325250 (273250

+ 108 x nozzle + 0.97 x avg.

wt.) thrust)

O.5x

Fixed:

0.5

X (85005

+ 131 x nozzle wt.) +

0'5

(57701

+ 1.03 x avg. thrust)

Actuation

assembly-

C= 10,821.8 D = 0.5454 C = 52,540 D = 0.5669

Control

box-

Fluid

injection

system

C = 5,4OO D = 0.5454

Valves

C = Z,254.7 D = 0.8617 C = 3,520.9 D = 0.5228

(less (more

than than

35 Ib) 35 Ib)

Thrust

Control Valves -

Valve: C = 4,254.7 D = 0.8617 C = 3,520.9 D = 0.5228 (more than 35 Ib) (less than 35 Ib)

Control

box -

C = 52,540 D = 0.5669

Lines:

Lines Other

C = 11,550 D = 0.3143

Structures: Aft skirtC = 25,360 D = 0.4961 C = 11,905 D = 0.571 C = 4120.3 D = 0.6593

Interstage

Attach

struts

Seoaration Rocket Electrical

Motor_: (cluster) motorsC = 17,894 D = 0.544

Systems: and instrumentation C = 34,130 D = 0.7524 C = 22,720 D = 0.4477 C = 3445.2 D = 0.927

Electronics

Electrical

power

supply

Cabling Turbooumos: Oxidizer

(and

hydrocarbon)

turbopumps

C = 1,000 D = 0.800

Gas

Generator: Solid motor case ('(-291,291 + 382,584" + 330.86" Reuse)" volume

(-539,179 + + 737,152" Reuse = 1 Reuse = 2 InjectorC = 33,932 D = 0.613

50.57" weight Reus.-) ); = Fx'm_ndable Reusable

CataFvst

Bed: Bed C = 16,66 D =0.613

Catalyst

After

calculating

the manufacturing assembly assembly effort.

dollars,

a 5% addition

is made

to account

_ for the.subsystem To account manufacturing sum is multiplied for final

and checkout

to arrive

at a complete assembly

system, factor

the

dollars

are added

to the 5% subsystem

and the

by 15%. costs are calculated based on the resultant design and Refer to the previous definitions of what activities are area.

The support manufacturing included

function costs.

in each

suppo_

Systems

engineering

dollars 0.323

are computed

as:

- (Design

$) -- 0.9802 as:

Software

enoineerino

dollars 1.370

are computed

(Design

$) -" 0.8944 as: $) "" 1.3226

_dollars

are computed 0.0006

,, (Design

Tooling

costs

are manufacturing 0.0045

dependant: -o 1.1526

(Manufacturing$) as:

Miscellaneous

costs (0.1138-

are computed (Design

S) "" 1.0185)

+ (0.03-

(Manufacturing

$))

The remaining costs that need to be accounted for are for the ground complex and launch operations (GCLQ). The basis for the algorithms and estimating relationships related ground is a collection equipment of historical (GSE), booster system cos;s data. This data and the GCLO cost is to ncnrecurring support, investment operations. and recurring booster Figure launch B-4 for launch facilities,

operations, describes

recovery/refurbishment breakdown s;ructure. Cost data were tables. escalated Costs

to Fiscal in millions

Year

1988

levels

using

NASA

JSC and regressed

escalation

of FY 86 $ were

tabularized

against significant launch system technical or programmatic characteristics. All algorithms iP,c!uded herein provide solutions in FY88 millions of dollars. The algorithms are loosely structured into a preliminary which defines nonrecurring investment as the sum ground support equipment costs, recurring costs cost model architecture of launch facilities costs are defined as the sum of factors are to a particular used for and

launch operations costs and refurbishment costs. Complexity available within the detailed algorithms to tailor cost solutions booster and its launch GCLO data. All cost estimates requirements. Appendix

A lists the sources

are at price/outlay

level

in constant

FY88

dollars

(millions).

All facilities algori!h.ms cover construction of new installations. If existing facilities at ETR or PMR are to be modified/converted for advanced launch systems, modification algorithms system maximum and other complexity must related launch launch adjustments be applied. to the rates pad area and provide reflecting Facilities represent backup the relative percentage Support of Typically, to support explosions a and Ground Equipment pads

unit pad expense. individual event in the

complex

may contain

two or more

on on-pad

contingencies.

o._ ._. o=

_
f_

(D
,I

,,_0
...t

000000
.-1 ,,.I --,I ..I ,..I ,_1

uJ
rr
tO _,,-

Z m rt-

"g_;z

e'- _

I,u

i!
1,

Facilities (RPIE). (RPIE) Ground

include brick and mortar and real property installed equipment Any support item which is mobile or transportable is classified herein Support Equipment emplaced (GSE). during Real Property Installed Equipment complex. to launch, is permanently Support construction of the launch items

as Ground

Equipment maintain,

is that population and provide training

of support which

used or

service, checkout, transportable.

are mobile

Launch Operations includes costs operations and checkout, propellant and launch requirements

of technical system charges for liquid operations,

management, prelaunch fueled systems, mission spares

control operations, recovery of GSE and Facilities.

and sustaining

The following Launch

noru'ecu.mng Ceres',":

cost aJgohfl'_z_ are for facd.des costs (FC). (See FiD.u'e B- 5 )" " ((TOGW)-Where 0.474) (K1) = Takeoff Gross Weight K1 = Complexity Factor

& Control

FCI = 0.010

TOGW

Pad & Sire.._rz_'sa_don: FC2 = No" 0.037

(See Fi=m.Lre B-6) " ((TOGW)-Where 0.545) -(K2) of pacs Gross Weight Factor

Np = Number TOGW = Takeoff K2 = Complexity

Vehic!e

A,_se.-,,,blv BuLid.L_.__:

(See Figure

B-7)

FC3=

0.004

((TOGW)

-- 0.733)

- (K3) = Takeoff Gross Weight K3 = Complexity Factor .

Where

TOGW

l:h'O_.,'n

.a,0.,mJ.ni_-atiqn FC4=

& Facgi_' 0.094

Mo4ificadqn_: + FC2 + FC3)) FC1 = Launch

(See Fimare "- 1.224) Control Assy Facility Bldg Factor

B-8) (K4) Facility Cost

- ((FC1

Where

Center Facility

Cost

FC2 = Pad and Site FC3 = Vehicle K4 = Complexity

Cost

Y(in
.

millions)

= 0.011322-x

0.458713

-Launch & Con=ol C:nm: Cos_ _ons of $ ClrYSS)

- ....

................

(D San:_,'n V

G Tkan Ar.l_ (DAd_ I/ C_n=_

Tr[c

Afla.s Agenz

I00,000 CPlef:%,'#.t OF POOR Center Facilities Cost (FCI) vs.

10,000,000 PAGE iS

QUALITY

Figure

B-5.

Launch

& Control

TSGW.

Y(in

millions)

= 0.034174-x

0"54261

i & Site Prpa._tion JEw Cos: per Pad /_tions of S (FY88)

Sa.mm IB

_ _ At!a.s Atlas

Tl_mn IZIC

Agena

A_as

Centa "_

100,000

1,000,000 BoosmrTOOWOb=) ORIGINAL OF POOR FiQure B-6. Pad & Site Preparation Facility Cost (FC2) vs. TOGW.

10,000,000

PAGE. IS QUALITY

Y(in

millions)

= (7.300246-10-8).x

1"437259

idesCos_Vehicle
nbly Building llions of $ (FY88)

)0,000 Boos:::

1,000,000 TOGW Ohm)

10,000,000

.Figure

B-7.

Vehicle

Assembly

Building

Facilities

Cost

(FC3)

vs.

TOGW. iS

OL_iG;iG_L PAGE OF FOOR

QUALI_,;

Y(in

millions)

-- 0.094094

x(in

millions)

1.224191

a Admin & Mods.

I0 ORIGINAL OF POOR PAGE

1,000 IS

QUALITY

:iQdre

B-8.

Program

Administration

& Modifications

Facilities

Cost

(FC4)

vs.

Facilities

Costs.

Fscilit,ies

Initial

Spares: 0.02 (FC1) Where + 0.07 FCI= (FC2) Launch + 0.02 Control Assy (FC3) Center Bldg Facility Cost Facility Cost Cost

FC5=

FC2 = Pad and Site Facility FC3 = Vehicle The following nonrecurring GSE' = 0.355 ((ALR) K5 *cost algorithms are for GSE: (See 1.264)* Maximum Figure (K5) Annual B-9)

_.svn,h Control

GSE1

Where

ALR =

Launch

Rate

= Complexity

Adjustment

The

following

nonrecurring G_E_ = 0.355

cost

algorithms

are for GSE: (See Figure (KS) Annual Launch Rate Adjustment B-10) (Np) Weight B-9)

Launch

Control

GSE1

((ALR) ALR K5

--

1.264).

Where

= Maximum = Complexity (See

P,,aC G S E: GSE2 = 0.011, Where ((TOGW)-TOGW K6 Np IACO GSET GSE3 = 0.003 ((TOGW)" TOGW K7 Mobile Eauioment: GSE4 = 16.23 ((TOGW)-" TOGW K8

Figure

0.612) (K6)* = Takeoff = Number (See 0.743) = Takeoff Gross = Complexity

Adjustment of Pads B-11)

Figure

" (K7) Gross Weight Adjustment B-12) .... Weight --

Where

= Complexity (See Figure

0.228) = Takeoff

(K8i Gross

Where

= Complexity

Adjustment

onzrol GSE Cost ons of $ (F'Y88)

Y(in

millions)

= 0.354683-x

1.264195

/_rl )Ad_ Atlas Ag_na

as Centaur

lO Annual Launch Rate

IO0 C_:':i_-'i_!_'-"!- '_'"_ '>:" _ ' oF V_'O_: QUALITY )p,

Figure

B-9.

Launch

Control

GSE Cost

(GSEI)

vs.

Annual

Launch

Rate.

Y(in

millions)

= 0.012122,x

0.594603

GSE, cos: pc: pad _1_ons of S (i=_'88)

Saru_,, V

G Ti_.n ]EIC A'das _2_Afl_ Ag_nz

"

C'.nLZ_-

_.....

__

S arm"n IB

00,000

1,000,000 Boost::TOOW (Ibm)

I0,000,000

Fiqure

B-IO.

Pad GSE, cost

per

pad

(GSE2)

vs.

TOGW.

ORIGINAL OF POOR

P#,QE IS QUALITY

Y(in millions) = 0.000814,X0.827124


_m_c_ration Assembly

_ec-kout Cos{GSE ti.ltions of$ CFY88)

o Sa ",_-n/V

S a.m:z I

Atlas _.

,
Atlas Centauz

00,000

1,000,000 BoosterTOGW Obm)

10,000,000

Figure

B-II.

IACO GSE Cost

(GSE3)

vs.

TOGW.

OF PUOR

0UALITY

Y(in millions) = 0.533519" X0"44645

10,000,000

0,000

1,000,000 Boost::TOGW Obm)

Figure

B-12.

Mobile

Equipment

Cost

(GSE4) vs. TOGW. OR:G!NAL OF POOR PAGE IS QUALITY

Initial

$oares: GSE5 = 0.05 (GSE1) GSE1 GSE2 GSE3 GSE4 + 0.15 = (GSE2) +0.07 " (GSE3) Cost + 0.5 " (GSE4)

Where

= Launch = IACO = Mobile

Control Cost Cost GSE

GSE

Pad GSE

Equip

GSE

Cost

Ground GSE6

Sector = 0.036

Software: ((KSLOCTsT) K9 KSLOCTs "* 1.12) T lines of code, (Kg) + 0.043 ((KSLOC INST ) " 1.20)

Where

= Complexity

Adjustment

Thousands of source test & checkout KSLOCINST Thousands real time The following recurring cost = of source instrumentation

lines

of code,

algorithms

are for annual

launch

operations

costs

(LOC):

Tech

System

Manaaement: LOC1 = 0.009 " ((TOGW) TOGW L " 0.516) = Takeoff = Annual " ((L)" 0.360)

Where

Gross Weight Launch Rate

Pretaunch

Ooeraticns LOC2

Checkout: = 0.025" ((TOGW)

(see

above) ((L) "" 0.360)

"" 0.516)"

propellant

Cost: LOC3 = L" (WF" Where CF" BF)+(Wo F_--Fuel O = Oxidize CO" r per flight (Ibs) BO)) "10-6

W = Propellant weight C = Cost per Ib B = Boiloff factor L = Annual Note: Solid propellants are included in assembly Launch costs.

Rate

Mission

& Launch LOC4

Control" = 0.010((TOGW)

(see -- 0.516)

above) ((L) -0.360)

Recovery

Cost: LOC5= 1.77Where ((L) -- 0.534) L = Annual booster Launch Rate

Note:

Sea recovery

of 1st stage - FC/GSE; (FC5)

assumed.

Replenishment

Soares LOC6

= 0.10" Where

+ 0.20" FC5 GSE5 Initial L

(GSE5) = Facilities =Ground

" (L "" 0.05) Initial Support Spares Cost

Equipment

Spares

Cost Launch Rate

= Annual

GLCO

Data

Sources

SP-22.'-

- Launch

Comolexes

for

Soace

Missions: and Yates,

Eqonomic General

and Electric, Santa

Ooerational Considerations, Barbara, California, 1963 ELV date.base (_p_t Model and - So_ce for Soace Cost

Frederic

Advisory

Grouo _y_tems

c'SCAG).

NASA,

JSC,

1986

Tran._o0rt_.tiQn

Develooment. MBB, Atlas 1980 Centaur,

Fabrication.

Ooerations.

(TRANSCOST_. Pooulation. 1B, Saturn V

D. E. Koelle, Atlas Agena,

Facilities Saturn Ground Centaur, _.unch

- Prcgram 1, Saturn

Titan

IIIC,

SuDoort Ecuioment Titan IIIC, Saturn Ooerations, Scout,

- Progr_.m Pooulation. 1, Saturn 1B, Saturn V Atlas, Atlas Centaur,

Atlas,

Atlas

Agena,

Atlas

Delta,

Titan

34D,

Ariane

I_C

Ommp_er

Model

The computer design

Boeing program

Hyperve]ocity was utilized on hybrid

Aerospace to assess

Vehicle the cost, impacts

Conceptual of hybrid and

Design

(HAVCD) and

components performance.

considerations Boeing, under 1986 and

booster IR&D,

reliability, this

independent 1987. of HAVCD a

developed launch developed only a

specialized design

analysis subprograms

program with a

in

combines

vehic]e

modified the

version

previously with

optimization fraction comparison an a]] of

technique a number 1

to of In

perform design 1988,

optimization required further under

analysis by

small

evaluations HAVCD was study uses

traditional under 2

parametric IR&D to

methods. liquid

developed NASA

support

booster

propellant HAVCD hybrid programs. 13. The

contract.

specialized

conceptual/preliminary and additions

design to is

subprograms. the shown previous in Figure

The subB-

study A

required flow

modifications of were the used hybrid

diagram that

booster study

mode] are:

subprograms

in this

AIREZ WITNEW

- aerodynamics consolidating weights routine and configuration

determinator. SOLID hybrid required. structure, tank, solid avionics, case, recovery interstage system. sizing, both structure and performance plus required oxidizer and solid

propellant NOSE TANK - nose ox

dimensions. PRESS sizes the pressurant tanks for a]] of the configurations.

lo

G. T. Force April
o

Eckard and M. J. Hea]y, "Airplane Responsive Aero Propulsion Laboratory, Wright Patterson 1978, AFAPL-TR-78-13. Phi]lips, Study,"

Engine Se]ection," Air Air Force Base, Ohio,

V. We]don, M. Dunn, L. Fink, D. Booster Propulsion/Vehic]e Impact Washington, June 1988, NAS8-36944.

E. Wetze], =Final Report Boeing Aerospace, Seatt]e,

t_

O t._.'

,4

o_ t,

COSTIT RELIB _IDP

- design, - single

manufacturing booster subsystem

through and

life system

cycle

cost.

reliability.

- trajectory

performance.

AIREZ relationships data. The

relies

on

blend

of in

simplified acceptable a table number ef

aerodynamic agreement axial (Mach and 0.3 to

theory with normal 20) wind

and

empirical test force

which subprogram as 60 ) of

result

tunnel

generates

aerodynamic and angle

coefficients (-I0 to

a function based the on

of Mach airframe hybrid vehicle The

of attach The for the to

geometry booster matched was

determined evaluated thrust

from as ]eve]

WITNEW.

performance the shuttle and for the

fuji-size The core

a replacement and were drag of

SRBs. external the wave

the

shuttle account or from

tank. drag

aerodynamic from the the

drag

routines tank

modified

impact to

external

to the This

hybrid

boosters the drag

hybrid with is the

boosters

external

tank.

lowered

coefficients WITNEW sets up the

booster

length. routine to be size, ]iftoff through to and a for the output and from ca]Is the on subprograms. the appropriate locations, shutdown system up that It

co]]ection

configuration to get a physical

evaluated oclnponent weight a]]

subprograms center weight, and would of

weights, (GLOW), of the

eaaponent empty weight,

gravity The

travel, program

gross cycles

etc.

subprograms Files are

until set

subsystem be SOLID used

weights by COSTIT,

converge RELIB, flight the

constant

number.

NTOP. and solid propellant tables expansion as turbine and/or from ratio load and from the the

determines thrust (such as

the trace, mixture

oxidizer specific

given

ASRM

impulse

(Isp)

input etc.) gas

variables SOLID (from contro] This used

ratio, fluids from

operating lost

pressure, such

ratio, exhaust thrust the file

adjusts the gas (TVC)

the

Isp

for or (from

overboard

generator fluid sets up

a methane/LOX the gas Isp, during tank

preburner) generator and or

vector

either

oxidizer). that NTOP

program

the

time,

thrust,

expansion

to determine PRESS

booster the

performance pressurant in the The and

ascent. vo]tmle, tank use tank to the size and shape, in the or and ox

determines weight

pressurate tank at

initially

pressurant can as

pressurant helium TANK

thrust of

termination. hydrogen,

program oxygen)

either

pure

tridyne to

(a mix

helium,

the

pressurant.

is ca]led

determine the wall weight.

thickness,

el]ipsoida]

ratio

of the dome and the vessel

OOSTIT is a program that uses cost algorithms for each component generated from WITNEW calculate the design cost, first unit manufacturing to
cost, and the Total total manufacturing and DDT&E cost costs cost to be of the based on the delivered based total on ocmix)nent the design weight quantity. and of acquisition costs. and total the is calculated is based on the

manufacturing the boosters

Operational missions reliability on the

system

flown. each number each subsystem of and the reliability and of the

RELIB the overall of

computes system. ocmponents and

Depending used in

required

ccmlx)nents ecmponent subsystem

number

system,

de]ivered into the

re]iabi]ity re]iabi]ity

is calculated and the overall

is avai]ab]e

to be

integrated

system the tank

reliability. boosters low Earth to their (150 was and be a separation nm circular point, at and a shuttle The pounds of 452.4 ascent was a the was the and The to be

NTOP and an

flies

hybrid to tank of a

external and

orbit

28 East). 1,840,600 Isp

shuttle with

external

]iftoff

weight

determined de]ivered from the used

to be vacuum

1,578,600 No

pounds fluids

propellant assumed The where of a 50 to

seconds. except vertical shuttle used for

were

lost

shuttle in turn thrust this would

during study

thrusting ascent to an

propellant. to a point altitude is fly shown

flight

profile

continued nm. The B-14. ASRM

gravity booster As

deliver that

apogee mission up to

profile of

each was they velocity (see

in Figure

a point with the was

reference, shuttle, orbit.

program together staging 680

set

representative 73,500-pounds Peak a peak vehicle

boosters to

the above

delivered was Figure not

about

payload

4,800

ft/sec. with core

dynamic

pressure of

determined g's the (see

ib/ft 2

B-15), permit not

acceleration constructions

2.67 for

Figure

B-16). boosters;

Time

did

quarter-size

these

were

flown. can of be be this run generated optimization on the HAVCD The "n" using the method is of that a steepest minima] allowing is used

Optimization descent. number optimized for of The main

equations feature have to and is 8 be to

technique program, squares the

designs designs

thereby method of

derived

quickly. (n+a)2 is not where a

latin is

optimization and "a"

requires 1 when "n"

nit,bet and is are

independent "n" is to a be

variable prime

prime

number

2 when

number.

For

independent

variables

(8+1)2=21

cases

required

E
op-

L r"

C_

I I

.p-

i
I

i , ;....... : ..,i .... ; .

...... . ........... !.........!...... ,..... i. , ....... .

(iql ) ISn_Hi

q.)

o,r--

t-',

,.4
I

0...)

(;sd)

_RSS3_d

91RVNXO

........................ = :-""" ..... _..... "'_ ,'" ...... _ ..... ,_ ......... . _..... r.............. -................. -_.-.

'

"

_ _ !

,_

..... _---_---_ "i I" i.....i ..... .... : I ................ ...... ...... = ;.--- ................................... ...... _............... '.i-i-_ ', _ _ ' :.J I _ " ' " ' I i w i ] :
, t i

....... ,............ ........................ ii _...... ........ 1 ................. :""i..-, ............._ I.........I.......... I-! _ ......
_ . " ' ' , : : . I [

- -- --............... " ..............

'

: _

i_I

_ I : *

i.............. '.................... :............... i I....... i .....t...... --./_ ....... ;

* , I

'

I .

L.._,

,__

. .....
E
. _,,,.

.............. i '_ .
. ' '

:.:
.

:,
'

:_..!
i ' _

.....: I
'I i !

I'
,

I,--,-

..- ......--',i..." i......................... : .... _... -i............. ............ _....... :........ ....... . . : i.. . _.. _ -............... ............ _ 2 ...... i-:...... "i-"_ : i, i I' , ; f ..1: I i,._ !... , _
op,,.

-.,,.

....

'

'

__..

,__
,. : _ "

i- --...._ ....
i I ' _

I
.

,
_ , : . i

:
I

. .......... _........ ! :.........

...._,...... ! _ . _ :............ ]: ........... .... ............ _ .....

.............. ........ i ..... ,.............


I

f,,,_
_,.,.

,_', _ ................................... :..................... _,,,\1_. i. i...... .............. _ i i............... "


................ i _1 .... _. " ............... ;_ "I: I +--._.--,I , ',................ . I

run. plot levels minutes

The

time

savings would

is evident 65,536 4 to on

when

one

considers to power be

that

a traditional for cases). the time

carpet (4 30 is be be

approach per to

require requires a design the ten

designs the a 8th

evaluated of

8 variables At about

variable derive Once in or under used

number ocmputer, an

VAC are Any

8300

savings can can

substantial. performed optimized

equations seconds.

obtained, of the

optimization variables

dependent

as a constraint.

(3c_er

Model

Assumptions

Oxidizer

Tanks

Upper pressure developed thickness in

and from due was

]ower the to a

dome

thicknesses required

were

determined to the

based

on

liquid head

]eve]

m/nim_n

pressure ascent upper

hydrostatic The

pressure wall

3g maximum on the

allowed of

acee]eration. and lower would dome be wall added or wall gust

cylinder

based

average the

pressure,

assuming on a

practical

application pressure local

cylinder

walls The

tapered

based

representative evaluated in wall for

gradient. and if

cylinder were to

thicknesses a slight buckling. loads were

were increase Side not

buckling, would occur to

stiffeners required vehicle

thickness due to

prevent and

loads

booster wall was

core

moments

considered Tank volume. oxidizer IM7 by ARC.

in tank ullage Reserved load tank No

sizing. to be 2 percent of at the 2 total percent loading of the oxidizer flight

assumed propellant

was

ca]cu]ated

weight. dome el]ipsoida] were made ratio and tank for weight local equations wall were provided

provisions

available

buckling.

Turbopump turbines calculated each and pump added for

equations each on would

assumed be

that

boost

pump

and

main by

ptm_ each

plus was

required. oxidizer

Horsepower flow rate and

required the total Isp a

based was

the maximum to

head of

pressure system of the

required

deliver. or

Turbine

flow was

reduced added

the as

the

solid

propellant

methane/I/3X

function

turbine

in]et

temperature and delivered to the overall


Weights

horsepower. system thrust.

Turbine

exhaust

was

assumedto not contribute


Structural

The shutt]e would hcw of used

aft solid

skirt rocket

on

the

full-size It such

booster was as

used

the a

weight vehicle but An

of

the of

current type c]ear weight was

boosters. structure for

assumed the body aft

that

this not

require this would

support be

skirt,

it was aft No

modeled was

different for all

diameters. boosters.

skirt aft

13,722 on The the

pounds

assumed

full-size

skirt

quarter-size

boosters. between weight each the of and core each along vehicle booster with and (full the the or boosters, quarter thrust weights size) ]eve] and of

connecting based

truss, on

were the the

calculated maximum shuttle. Interstage

the of

thrust

]eve/

maximum

wall at

thickness No

was

based

on

localized were

buckling

and

the

load

it

was

supporting

3g's.

bending

moments

considered.

Quarter-Size

Boosters

The the

quarter-size

boosters

used

the levels case

same

weight

and

sizing by

algorithms one-fourth, remained was

as but the also

full-sized

booster. in the

Thrust motor

were

reduced

insulation same as

thickness the to full-sized remain in

and

combustion batteries,

chambers and

booster. of the

Avionics, full-sized booster,

wiring string

assumed were valve,

that the

booster. such as

Single one

cc_nponents throttle

assumed one

quarter-size valve, etc.

pump,

one

isolation

Sample

OcmputerNodel

Variable

Ir_uts

Figure from

B-17

shows The

the

list

of

variables were

that

were

available for

to the

be

changed

run-to-run. vehicle.

values

shown

those

used

full-sized

reference

T_rpica]

Caqmxter

M_]e]

O_

Figure reference and are

B-18

is

brief

list Cost and

of

the

ocmponent

size

and

weights are also

for

the

expendable shown

booster. B-19

and

re]iabi]ity respectively.

resu]ts

included

in Figures

B-20,

Beuseab]e

Booster

L(X:

Calculation definition the sheet cost is of of the

of

the

LCC

of

recoverab]e/reuseab]e design section ]ife. of a

boosters The

requires rate,

the and

reuseab]e

components' An examp]e

attrition

refurbishment. on Figure costs for B-21.

reuseab]e

booster

input

shown

Refurbi Refurbishment percent

shment costs

for ]iquid

SRM

ocmponenfs

were

obtai ned were

from to

STACEM. be 25

oxidizer

ccmponents

assumed

of TFU.

Referenoe

Trade

Data

Attached trades that

are were margins,

sun_ary completed. reserve

tables Also

of

the

referenee are

conditions the results

and of

materials the LITVC, loading

attached and

structural trade

prope]lant,

prope]]ant

volumetric

studies.

DISBTY-2. P, TINS= P .0!27 SPVFT.3. TFSOF1-0.


T(IS,)I:I,O. ELRTI':I<= 1.4 EL_,PTN= ]. &

:tJ,_t_HLlr.y,

Ut

UA

I_NI,

I'1

E):PR.,_ .5. RSuLID=6.5 RZERO,.2. 333333


CONANG= 18. ALTHK,. 03(I SL;NSU-. 15 SLINSI.-5.0 THKINJ =8. THk!NL=. 5 CMBF',AT=5. HLFANG=20. GYMBOL-5. DTYCY L,,.5 (;AS'I'VC= l GAPNOZ=. 5

!DISTANCE BET_:EEN TANi:. ASSE._IBLIES - FT !EXTERNAL TANK INSULATION DENSITY LB/IN3 !CUNE:ENTI(IC TANK SEPARATION DISTANCE - IN :FUEL TANF !NSULATI01." THICKNESS - IN !0 v TM_I" INSULATION THICKNESS - IN !ELLIPSOIDAL RATIO FOP, TANKS IF NOT CALCULATED !EELIPS01DAL RATIO FOR PRESS TANItS IF NOT CALCULATED !BOOSTER NOZZLE EXPANSION RATIO IOUTSIDE RADIUS OF SOLID CASE - FT !STARTING GRAIN RADIU. _ - FT !NO.C;E SECTION CONE ANGLE - DEGREES !%'ALL THICI[NESS OF AL LINER - IN !INSUL. THK FOR SOLID tIPPER SECT. IN !INSUL. THK FOR SOLID LOVER SECT. IN !THICILNESS OF INJECTO!_ - II4. ]RATIO OF THROAT AREA TO THROAT INLET FOR GG !COMBUSTION CHAMBER LENGTH - FT !NOZZLE HALF ANGLE - DEGREES !NOZZLE GYMBOL AWGLE - DEGREES !TVC DUT Y CYCLE !I-GG P0;!ERED; 2-OX POWERED TVC FLUID INJ !GAP NOZZLE UiLL MISS SIilF,'F %;HEN GYMBOLED - FT

TRBP}:S- IO. R SAB)'(5-1 I RSABPB= ] 15 FDOLIN.2] PDFLIN= .5. PMAX=] OODO. GPRATO- 1. FTI't(ES_ 15. OTNPS}'=25. I'C=I(100. DPIN,I.259. PPOXV=32. DPFiI SC= 1_., DPGLIE=IO. DPI<EG_22. REC,UII','=. 0! REGF, nT= 1.15

!TUI.:BINE PRESSURE RATIO INLET/OUTLET !PRESSURE INLET RATIO TO COHBUSTION C_AMBER 'PRESSURE INLET RATIO TO PRE-BURNER !DP OF 0._[ LINE - PSZ ]DP OF FUEL LINE - PSI !HE TAN]' INITIAL PRESSURE IPIiESSURE P_.TIO ABOVE TAIqI" PRESSUP, E !MINIMUM FUEL T_J_IC PRESSU.BE - PS!A !OX PUMP SUPPLY PRESSURE - PSIA !STAP,TII_G PC !DP OF II_JECTOR !D}' OF MAIE OX IS(l VALV5 !DP OF MISC ITEHS !DP OF GAS LINE !D. OF REGULATOE v !PRESSURE REGULATOR UNCERTAINTY !!,.INIMU._ REGULATOF, OPERATING PRESSURE RATIO

PTYPF, 1 i. |'MJ',[I=!. 5 AZNAX= 3 , YS:l .6 TAUT)- ] 00. CONH2U-95. EI.,'qq AH=I O. GG-I TFJHPIN. 6[_. TEMP--15. I'rEP,T. 3o(} A TEHTRB-1800 EFFIS}'_ 925 ]LI"I"CST-.92b

!CONF!GU?.ATIOK TYPI" !STARTING MI):TURZ RATI[' !HAY!HUH ALLOVED ACCELEI[ATiOF. - G'S !STRUCTUF, A[. SAFETY FACTOP, !AUTOGEIq0US GAS TEHPEKATURE - F !PEROXIDE CONCENTRATION IN PERCENI' !COHBUSTION CHAMBER 'i STAR !GAB GENEL'_TOP,-I, NORMAL HYBF,ID=O !HE TAME[ INITIAL GAS TEH}' ]TEMF OF HE GAS 1N OZ TANK DEG Y !STEPS IN TNRUS_ _hor;l,F. IIrI'EGKATION !TURBINE GAS TEHP FRO._:GG !!HPUSE EFFICENCY !CSTAR EFFICENCY

Figure B-17.

Computer

Input Variables.

ORIGIt_AL PAGE

IS

OF POOR QUALITY

UXP,SRV-. (_2 FLRSRV-. 02 OULLG=. 02 FULLG-. 02 FACNOZ-I. 3 DENSLI -. Ok DENIM J=. 1


"I

!OX RESERVE !FUEL RESERVE !OX GAS ULLAGE !FUEL GAS ULLAGE !NOZZLE WEIGHT FACTOR FOR TVC !SOLID INSUL. DENSITY #/IN3 !DENSITY OF INJECTOR _IIN3

RCBOOS=31. CPOXG-. 17 C}'OXL-. 4 TRB FAC- 3. CYIELD-_ CULT- I.

!2X RECOV.; 3X NOT RECOV.:XO NO TVC; X1GYMBOLED, _SP HT OX !SP HT LO): !TURBINE POWER I-TOPPING, 2-METHANE, !YIELD STRENGTH FACTOR * 3-GG REVERSED OX DOME !ULTIMATE STRENGTH FACTOR * 4-GG NORMAL OX DOME

X2

INJ.

PTMAT-5 OTHAT-5 FTMAT-5 STRMAT- I LN.h;AT-& !NSMAT-I SLMAT-5 SKTMAT-- 1 CMBFIAT-5

!PRESS TANK MATERIAL !OX TANK MATERIAL !FUEL TANK MATERIAL !STRUCTURE MATERIAL !LINE MATERIAL [INNEk STAG_ MATERIAL !SOLID CA$_ MATERIAL !SKIRT MAIEKIAL !COMBUSTION CHAMBER MATERIAL

I-ALUMINUM 2-AL-LI 3-TITANIUM 4-STAINLESS STEEL 5.1M7 CARBON FIBER 6-A6AC CARBON STEEL

FAX=O. FSID[5-O. DSiDEI=0. FVEI<T-O. DVEF,TI-O. DH_GH! =0.

!HOle AXIAL

FORCES

QNTY=I CASE_.I PUMPS=& PUMPER=3 HEVLV=3 HEVLVR=3 HEPYR=2 HE?YR_-I HEREG=I MEREGR-I HERLF-I HERLF[<.I HESRV=I HESRVR=] OZVLV-_ OXVLVR-& OXPYR-& OXP!_R=_ THVLV-d THVLVR._ OXSRV-I OXSRVI<-_

!_ _ !_ !_ !_ !_ !# !_ !_ !_ !_ !_ !_ !_ !_ !_ !_ !_ I# I_ !$ ?_

OF U[ OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF

HALF THE TOTAL BOOSTERS PER VEHICLE EYBEID MOTORS PER BOOSTER TURBO PUMPS TURBO PUMPS REQUIRED HELIUM VALVE REO'D HELIUM VALVE HELIUM PYRO ISO VALVES REO'D HELIUI_ PYRO ISO VALVES HELIUM REGULATORS REO'D HELIUM R_GULATORS HELIUM RELIEF VALVES REQ'D HELIUM RELIEF VALVES HELIU_ SEEV!CE VALVES REO'D HELIUH SERVICE VALVES OX VALVES IN SYSTEM REO'D OZ VALVES IN SYSTEM OE PYRO ISO VALVES REO'D OX PYRO ISO VALVE_ TIIROTTLE VALVES REO'D THROTTLE VALVES OX SERVICE VALVES _EO'D OX SERVICE VALVES B-17. Computer Input Variables (Cont'd).

Figure

i l , 'i : i

PRVLV-I FRVLVR-

PRPYR.2 PRPYRR- 1 PRRLF-1 PRRLFR-1 PRSRV-I PRSRVR-I OXREGII. 1 OXKLF-I OXRLFR- 1 AVION=I AVIONE=I WIRES-I VIRESR=I BA'IKY-! BATRYR- 1 1N_'fF,=I INSTER-I PAP,AC-- 1 PARACR-- 1 NOSES-! NOSESR=I OXTNK-I OXTNKR-! OXLIN-4 OXLINR,,4 GOXLN. 1 GOXLNR--I HELIN= 1 IIELINR=I SLDIG,I SLDIGR.! HETN[<= 1 M_TN_u',,1 F}'I'NK-I PPTNKR- 1 TVCVS,4 TVCVSR.4

-.

!_ !_ !# !# !# !# !# !_ !f !_ l# !_ !# !# !# !_ I_ I_ I# I# !_ !# }# !# !# [# !# !# !_ !# !_ !# !# }# !g !_ !_ I# _ !_

OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF OF

METHANE VALVES IN SYSTEM REO'D METHANE VALVES IN SYSTEM METHANE P_<0 ISn VALVES REO'D METHANE PYRO ISO VALVES METHANE RELIEF VALVES REO'D METHANE RELIEF VALVES METHANE SERVICE VALVES REO'D METH.&NE SERVICE VALVES OX REGULATORS REO'D OX REGULATORS OX RELIEF VALVES REO'D OX RELIEF VALVES AVIONICS REQ'D AVIONICS WIRES REQ'D VIRE_ BATTERIES REO'D BATTERIES INSTRUMEr_ATION REO D INSTRUMENTATION PARACHUTES REO D PARACHUTES NOSE SHELLS REO D NOSE SHELLS OX T_-_<S REQ D OX TANKS OX LIO LINES REO D OX LIQ LINES GAS OX LINES REO D GAS OX LINE5 HE LINES REO D HE LINES SOLID MOTOR IGNITERS RE0 D SOLID MOTOR IGNITERS HELIUM TANKS REO D HE TANKS METHANE TANKS REQ D TANKS FLUID INJECTION TVC VALVES RE0 D FLUID INJECTION TVC VALVES

Figure

B-17.

Computer

Input

Variables

(Cont'd).

TOTAL INITIAL VEIC,HT.I21313g.14L5 EF,PTh' WEIGHTB323B.23Lb EXPENDED ()X %,q'IGIIT.6601aO.69Lb TVC OX PROP.O.OOLb TURBINE FUDL= 5976.30Lb INITAL C.G.= 79.71Ft EMPTY C.G.= 12&.57Ft STARTING _.R.. SAFETY FACTOr1.50 1.60

OVERALL LENGTH= 166.6&Ft CUT OFF %'T= 1068&2.77L.h EXPENDED FUEL WEIGHT&_610_.69Lb TVC FUEL PROP.O.OOib TOTAL EXPENDED CUT OFF C.G.P_OPELL_. IOI.72FL II06295.38LB

STARTING PC-IO00.O0 PSIA NUMBER OF HYBRED UNITSzl

.-- NOSE SECTION SIZE --BASE DIA. - l_.OOFt NOSE TIP RAD. 1.27FT C.U. FROM NOSE TIP= lO.21Ft LOCATION F_OM NOSE TIP. O.OOFt --- HELIUM TANK SIZE --MATEI<IAL: IM? CARBON FIBER OUTSID DIAMETERz 8._3rt DOME HT. 2.92Fl DOME TIIICK.- 2.8691n VESSEL WEIGHT= 3354.23Lb INIT VEIGIIT, 4697.94Lb HE WEIGHT. l176.OOLb XNIT P_ESS=IOOOO.P$1A LOCATION FR(,E NOSE TIP. 13.OSFt --- HELIU._: TAI,:Ii VALVIN$ SYSTEK Hg }'YRO VAVLE VT. iz,91Lb P_,ESSUP,E P, EGULAI()F, WI= 17.81Lb HE SERVICE VALVi WI= 29.81Lb TO'IAL VALVE VT- 77.L3Lb ---

OVERALL LENGTH-18.91Ft CYL LEN- O.OOFT WEIGHT. 1523.65Lb TO BOTTOM 18.91Ft

LENGTH. .5.B3Ft CYL LENO.OOF CYL THICK.. O.O001n ALUMINUM LINER. 4&,2OLb SHUTD0:JN WEIGHT,, B544.O_,Lb C.G. FROM CYL TOP.. 2.91Ft FINAL PP, ESS= IAA.PSIA TO BOTTOM. !B,91Ft

OUANTITY, QUANTITY, OUAI:T!TY,

2 1 I

--- II,_]'ERSTAGE (NOSE TO ON TANK) IJ, ATEI(I AL: 22!9-T87 ALUH!NUY, DIA TO}',; IJ'.0OF[ LENGTh,. 5,OOFt WALL Tl!!Cl,'.- O.O&Oin CG FROH TOP= 2.5OFt LOCATION FRe_M NOSE TIP. ig.9!Ft --- OXTDTZER TANK --MATEkI,,I.: ill? CARBO'] FI_E[ i D:AMETE[<]a.OOFt DOMF HT= _.5_F_ UPPER DOME TH_C:[.- 0.0361u CYL THICK.O.lllln 0): TANK VOI.-9539.G_FT5 TOT OXIDIZgI< %rE1GET: 673Dt._:_.63Lb RESIDUAL OXiDiZERI%_._.3I.b 1 IHSULATIONO. OOLh INI'I WEIGIIT. 677312.63Lb INIT. C.(;. FRcH-' CYL TOI'. 29.27Ft UPPEP, DOLCE PRES<,,= 93.PSIA LOCATION FROM NUSL TIP. 19.4UFt

--DIA BOT= I&.OOFT %fRIGHT= 137.03Lb STIFFINERS REOUIRED= TO BOTTO_I= 23.91FL

TAVI( LENGTH= 70.31F_ CYL LEN. 6].29Ft LOPER DOME THICK.0.072In STIFFINEI_S REQUIRED. O. VESSEL wEIGHT= 24_2.97Lb RESEEVE OXID_ZER.132OS.81Lb PRE_ GAS W_IGIIT. l153.91Lb OX LINEI<. 1276.0&Lb EMPTY WEIGHT, 3719.01Lb FINAL C:._.. 2!.}6Ft LOVE_ DO_IE PRESS. I8?.PSIA 10 BOTTOM. 85.2OFt

Figure

B-18.

LOX With

Turbopumps,

Gas

Generator

System.

:.,;_ ,:_;F_R Q:._A[.I'FY F

--- L{_XVALVTI_CYETE_. S -.. OXIDIZERVALVE VT O):IDIZERrYE', VT METHANE THROTTLEALVE V VT. OX SZ_VICEVALVe, VT OZ RELIEF VALVE VT TOTALVALVEWT -

241.17Lb 120.59Lb 39.54Lb 120.59Lb &.4_Lb 3730.23Lh

OUANTITY&
0UANTITY. 0UANTITY, OUANTITYOUANTITY4 1 2

--- BOOST PUMP SIZE --DIAMETER1.38Ft WEIGHT/PUMP. 292,1655 PUMPS. 4 DELTA P- 54.47PSIA HORSE POWER, 417 NS. 8825 VAPOR PRES14.34PSIA LOCATION FROM NOSE TIP- 152.69Ft --- MAIN PUMP --DIAMETER_ 1.56Ft WEIGHT/PULP623.94Lb PUMPS4 DELTA P- ]034.88PSIA HORSE POWER= 7455 NS= 1995 VAPOR PRES, :_.3&PSIA LOCATION FRO_.: NOSE TIF=

LENGTH1.5_Ft TOTAL VTI168.66Lb FLOWKATE/PUMP. 1628.89Lb/Sec SPEED296ORPM PUMP EFFICIENCY. 77.97% INLET PRESS.25.00PSIA PUMP CG FROM TOP0.77Ft TO _OTTOM, 15&.23Ft

154.23Ft

LENGTH, 2.27Ft TOTAL %rT- 2_95.77Lb FLOWKATE/PUMP. 1628,89Lb/Sec SPEED6092RPM PUMP EFFICIENCY_ 83.06% INLET PRESS.79.47P$IA PUMP CG FROM TOP1.14Ft TO BOTTOMl_6.50Ft

_-. TURB.TI_F .... TURBIRE FLO'_qlATE = 752.0!Lb/Sec ISP P, EDUCED _Y O. 54",o TOTAL PUHP ASSEM. LEN_ 3.81F[ COMBUSTION

TURBINE TEMPEP, ATURE= 1800F FUEL REOUIRED, 5976.30Lb TOTAL PUMP ASSEM. L_IGHT3664.43Lb

--- OXIDIZER PROPELLANT LI!:Z TO MATERIAL: A_$i 301 STAINLESS OX LINE DIA.7.00in NUMBER OF LII:ES= a TOTAL LZNE L_i395.89Lb --- SOL!D FUEL CASE --HATERIAL: !M7 CARBON FILER DIAMETER13.0OF: DOME HT. 4.!gFt _ATIO PO_T TO THROAT AREA, l.&6 SOLID CA$_S= 1 UPPER DOME THICK., (l.3?Oln STIFFE!_ERS REOUIREDO. CA_E WEIGHTll!i2.80Lb RESERVE FUEL8912.09Lb INIT VEIGHT_ 469679.25Lb IGNITER500.0 Lb INIT. C.G. FROM CYt TOP- 25.6iFt STARTING ?_tSSIO00.PSIA LOCAT7ON FRO_ NOS_ TIPBI.OOF%

CHAMBER

---

LENGTH, 68.89Ft WEIGHT/LINE.

3&8.97Lb

LENGTHeS._Irt CYL LEN. 51.22Yt INIT PORT RAD.2.33Ft GRAIN LENGTH. 51.22Ft CYL THICK.. 0.627In AVG DEL ISP-293.66SEC -TOTAL FUEL WEIGHT. 455026.78Lb INSULATION. 3039.68Lb EMPTY WEIGHT. 14652.47Lb EMPTY C.G.- 25.61Ft MAXIMUM PRESSIO89.PSIA TO BOTTOM. 136.41F%

Figure

B-18.

LOX With

Turbopumps,

Gas

Generator

System

(Cont'd).

OFC,!GINAL OF POOR

PAGE QUALITY

IS

--- CONV_I_CENT _ECTTON MATERIAL: IM7 CARBON CASE VEIGHT3_9.51Lb TOTAL VT3579.41Lb LENGTH3.80Ft LOCATION --- GG INJECTOR VKIGHTLOCATION FROM NOSE TIP.

--FIBE_ INSULATION= 3229.90Lb CG FROM TOP1.52Ft OUTLET DIA.. 5.47Ft TO BOTTOM. 140.22Ft

136._11"t

INJECTOR --DIA.. 5.4PFt 2704.18Lb FROM NOSE TIP.

LENGTH. 140.22rt TO BOTTOH_

8.00In 140.89Ft

--- COMBUSTION CHAMBER --MATERIAL: IH7 CARBON FIBER VEIGIIT CHAMBER138.16Lb TOTAL WT. 2&21.62Lb WALL TIIICK.. 0.201n LENGTH, 5.0OFt LOCATION FROM NOSE TIP= I&O,89F[ --- THROAT SIZE --THROAT ID DIAMETER3.87Ft VEIGHT-]6656.26Lb LOCATION FROM NOSE TIP. !_5.89Ft --- NOZZLE SIZE --DIA. I_OZZLE EXIT= l&.97Ft WEIGH]87!!.62Lb CG F_UH _DP= 8.!GF[ LOCATION FRO_ NOSE TIP- 150.28Ft --- TVC ACTUATOR WEIGHT2328.03Lb ---

_EIGHT INS- 2283.a6Lb CG FROM TOP2.5OFt INSULATION THICK.5.O01n OUTSIDE DIA.* 5.47Ft TO BOTTOH_ 145.89Ft

LENGTH. &,40Ft CG FROM TOP- 26.39Ft TO BOTTOM. 150.28Ft

LENGTH= 16.36F: EX? RATIO. 15.0 TO BOTTOM= ]66.64Ft

--- BA_E SKI}IT SIZE --MATERIAL: 2219-T87 ALU_It_UM DIA TOP_ 13,OOFt LENGTH= 20,95Ft CG FROM qOFlO.47Ft LOCATION FROM NOSE TII'- 136.giFt --- BOOSTER TRUSS WEIGHTTO CORE TRUSS i165.56Lb ---

DIA BASE_3.68FT VEIGHT-13722.00Lb TO BOTTOm4. !57.36Ft

--- BOOSTER SEPARATION SYSTEM --SEPARATION SYSTEM WEIGHT. 1487.00Lb --- RANGE SAFETY --RANGE SAFETY VEIGHT.144.00Lb

Figure

B-18.

LOX

With

Turbooumps,

Gas

Generator

System

(Cont'd).

OF

POOR

QUALITY

REOUIRED

ASSEMBLIES=

300

INCLUDING

0 SPA_ES QUANTITY COST --HANUF :TOTAL-KS OTY 133,987 3O0 &0,462 3O0 18,378 3O0 88,633 3OO 199,350 300 507,3&3 300 3OO 22,975 11,486 600 7,410 3OO 11 709 30O 16,896 3OO 292,726 3O0 220,841 3OO 29,351 1,200 20 690 1,200 II 548 1,200 6 373 300 7 410 300 2 223 3O0 25 502 1,200 25 502 1,200 _7 155 1,200 47,155 1,200 189 864 3O0 _0,418 1,200 1_ 821 3OO 65,066 3OO 230 920 3O0 26 086 3OO 1778 300 638959 3O0 27.568 3OO 2964 3OO 242 185 3OO 198 313 3OO 297 766 3O0 423 897 3OO 64 029 3O0 362 536 30O 4,875 593

--- COMPONENT WEIGHT, DESIC.N COIIPONENT VEIGHT-LB AVIONICS 77 WIRING 260 BATTERIES _5 INSTRUMENTATION 45 NOSE SHELL ],O95 HE TANK 3,354 HE LINER HE rl_o VALVE lIE REGULATOR 17 HE SERVICE VLV 29 INTER STAGE 137 OXIDIZER TANK 2,442 OX LINER 1,276 OX ISO VALVE 2_I OX PYRO VALVE 120 OX THROT. VALVE 39 OX SERVICE VLV 120 OX REGULATOR 17 OX RELIEF VLV 4 BOOST TURBZNE 146 BOOST PUEP 146 311 MAIN TURBINE MAIN PUHP 31! SOLID FROFEL. 455,026 OX LINE 348 SOLID IGNITER 50O SOLID INSUL. 3,039 SOLID CASE !1,1!2 CON'VR_ CASE 349 COhWRG INSL 3,229 INJECTOR 2,70& COMB. CASE 138 COEB. INSL 2,283 THROAT 16 65c3 NOZZLE 8 71! TVC ACT 2 328 AFT SKIRT 13 722 TRUSS 1 165 SEP SYS 1 487 COLUM_ TOTALS SUBSYSTEM INTEGRATION SUBSYSTEM ASSEMBLY FINAL ASSEHBLY AND C_ECKOUT MANUF. COST PER UNIT SYSTEMS ENGINEERING SOFTWARE ENGINEERING SYSTEMS TEST TOOLING MISC. TOTAL SUPI'OId FUNCTION COST TOTAL ACOUISTION CO_T DDT&E C(!SI = . =

COST, FIRST DESIGN-KS 951 3,582 213 101 474 5,785 70 1 1 I 92 2,665 918 3 2 1 2 ! 0 2,299 2,299 &,910 4,910 32,908 41 2,01_ _,22! 7,182 1,739 _9_ 13,435 1,188 3,75_ 8,479 6,5UU 793 2,28_ 2,_57 3.525 120,31&

UNIT COST, AND MANUF(! )-KS 90_ 273 124 59B 1,345 3,423 155 _3 5O 79 11_ 1,975 I,_90 61 _3 2& _3 50 15 53 53 98 98 1,281 84 i00 439 1,558 176 12 4,311 186 20 1,634 1,338 2,009 2,860 _32 2,446 31,706

24,062KS 2&3,?79KS 767,905K$ 19,624K5 32,1&YKS 27,200]<$ 37,145KS 820,382K$ 199,877K$ I,!16,753K5 7,_8,_IOK$ 1,084,512KS

Figure

B-19.

L0X With

Turbopumps,

Gas

Generator

System.

..........

: "'"<:Z' i.5

--Cr_I.I_nN;.NT AVIONICS WIRING BATTERIES INSTRUMENTA'rlO[_ NOSE SHELL HE TANK HE LINER HE PYRO VALVE HE I_EGULATOR HE SERVICE VLV INTER STAGE OXIDIZ_I( TANK OX LINER OX ISO VALVE OX PYRO VALVE OX THROT. VALVE OX SERVICE VLV OX REC, ULATOP, OX RELIEF VLV BOOST TUI_BINE BOOST PUHP MAIN TUI<B!NE MAIN PUMI' SOLID PROPEL. OX LINE SOLID IGN!TE[_ SOLID INSUL. SOL_D CASE CONVRG CASE CONVRG INSL INJECTOR COHB. CASE COH5. INSL THROAT NUZZLE TVC ACT AFf SKIRT TlIUSS SEF SYS lllSC:

COST

ASSU._H_T_ON

FACTORS

FO._ DESIGN DESIGN MATURITY 1 1 i ] 2 4 2 2 2 2 2 & 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 8 2 2 2 2 _ 2 2 2 8

AND

MANUFACTURE

--LEARNING CURVE SLOPE% 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90 90

DESIGN COHP_E .... 'f 7 5 5 5 _ 5 5 5 5 5 2 5 5 5 5 5 5 5 5 5 5 5 5 5 2 5 5 5 5 5 5 .5 5 5 5 2 5 5 5 .u

OFF-THESHELF% 0 0 80 80 30 0 0 100 IO0 i00 50. 0 0 I00 I00 I00 100 IO0 I00 0 0 0 0 0 50 0 0 0 0 0 [) 0 0 O 0 80 0 0 0 lot

MANUFACTURE COMPLEXITY 5 5 5 5_ 5 5 5 5 5 5 2 5 5 5 5 5 5 5 5 5 5 5 5 7 2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 9

MATERIAL TYPE I I i 1 1 5 I I 1 I 1 5 1 1 1 1 1 I 1 I I 1 1 1 4 I I 5 5 i I 5 I I I 1 1 I I i

--- FACTOR DEFINITION FOR ABOVE TABLE --DESIGN COM._LE,XITY: i-9; "i" FOR LOV, "9" FOR HIGH COMPLEXITY OFF-THE-SEEL',%: PERCENTAGE OF DESIGN THAT IS 0FF-THE-SHELF. DESIGN MATURITY: i-8; "I" QUALIFIED, "8" CONCEPTUAL ONLY ...... MANUFACTURE COMPLEXITY: !-9; "I" FOR LO'4, "9" FOR HIGH COMPLEXITY MATERIAL TYPE: "i" FOR ALUMINUM OP, REFERENCE MATERIAL "2" FOR ALUMINUM LITHIUM "3" FOR TITANIUM "&" FOR STAINLESS STEEL "5" FOR GRAPHITE ?IBER "6" FOR D6AC STEEL LEARNING CLrRVE SLOPE IN PERCENT

Figure

B-19.

LOX With

Turbopumps,

Gas

Generator

System

(Cont'd).

---

NON-RECD_RING

OPERATIONS

COST

---

LAUNCH PAD

g CONTROL

CENTER

I0

62BKS

& SITE

PREPARATION BUILDING & FACIL. SPARES MODS ,

III,684K$ I09,265K$ 3&6,352KS I0,215K$ 8 209K$

VEHICLE PROGRAM

ASSY

ADHIN$.

FACILITIES LAUNCH FAD IACO MOBILE IVITIAL GROUND TOTAL GSE GSE

INITIAL GSE

CONTROL

BS,915K$ 166,391KS 377,440KS 4_ SOFT'ARE OPTS COST = 267K$

EOUIPZENT SPARES SECTOR

17 057K$ 1,290 427K$

NON-RECUrRING

--FOR YEARS LAUf4CHES P_N TECII SYSTEM

RECURKIN$

O._EEA.'IO._S COST O1 3

---

1 - 2
6 33,BO6KS 93,90BK$ 420KS lllKS 37,563KS IO,?04KS 176,514KS

2 - 3
9 39,120KS I08,666K$ 630KS 167K$ 43,&66KS I0,903KS 202,954K$

- 14
12

YEAS " " _"" = . = CONTROL - FC/CS_ =

26,341F.S 73, !691:3 2 !0KS 55K$ 29,267K$ 10.374KS 139,4!9|'.$

43,3BBK$ 120,524KS 840K$ 222KS 48,209K$ I],046K$ 224,232KS -

PRELAUNCH PROPELLAVT HELIUM MISSION

OPERATIONS/CHECKOUT COST - LIQUID ONLY

COST & LAUNfH

REFLENISH_E_:T YEARLY

SPARE

OPERATIONS

COST

TOTAL

OPERATZONS

COST

2,985,aaaK$

TOTAL

LIFE

CYCLE

COST

- l!,42a,283KS

Figure

B-19.

LOX With

Turbopumps,

Gas Generator

System

(Cont'd).

O};;GiNAL OF POOR

FAGE

IS

QUALITY

COHPONEI,'T

UNITS REO'D

UNITS OPER.

PRELAUNCH FAILS/ MILLIOK

PRELAUNCH OPER. HRS-CY8

BOOST FAILS/ MILLION

BOOST OPER, HRS-CYC

POSTBOOST FAILS/ MILLION

POSTBOOST OPER. HRS-CYC

AVIOI_ICS BATTERIES INSTRUMENTATION NOSE SHELL lie lie HE HE BE TANK LINER PYRO VALVE REGULATOR SERVICE VLV

1 1 I 1 1 1 1 1 I I I I i 4 4 1 1 1 4 1 1 3 3 3 3 1 I 1 I 1 1 I 1 I ._

I I I 1 1 i 1 2 1 1 1 1 I a _ _ ! 1 1 & 1 ! _ 4 _ a ! ! i i ! 1 _ _ ] 1 1 1 1

2.00 0,13 33.80 6.80 1.00 3.80 3.80 1.10 2.60 1.60 0._0 0._0 0.IO 11.00 8.00 9.60 _.60 2.60 _.60 0.00 3.80 3.80 0.00 0.00 0.00 0.00 0,00 U.70 0.?0 0.00 0.00 0.70 0.00 0.00 _.0.70 O.OU U. OU l). O0 0.00

0,000 0,000 O.000 0.000 0.000 0.000 0.OOu 0.000 0.000 0.000 0.000 0.000 0.000 0.000 _.O00 O.UOO 0,000 0.000 0.000 O.OOU O.OOO O.UO0 0.000 0.000 0,000 0.000 0.000 O.O0O 0.000 O.O00 O,OOL) 0.000 O.OU0 0.000 0.000 O. [)[)0 O. 000 O. 000 0,000

20,00 1.50 _69.00 155.00 4_.00 37.50 37.50 0.00 55.30 0.00 1.00 I.O0 1.O0 0.00 0.00 165.70 0.00 55.30 9.80 I.i0 37.50 37._0 267.73 267.75 267.75 267.75 6.30 13&.O0 134.00 6.30 _S.UO 13_.00 6.30 56.00 83.00 321.00 2z_8.50 248.50 0.00

0.038 0,038 0.O38 0,038 0.038 0.038 0.038 0.000 0.O3B 0.000 0.038 0.038 0.038 0.000 0.000 0.038 0.000 0.038 0.038 0.038 0.038 0.038 1.000 1.O00 1.000 1.000 1.000 1.000 1.000 1,000 1,000 1.000 1.000 1,000 1,000 1,000 I. 000 I. 000 0,000

0.00 0.00 0.00 0.O0 0.O0 0.OO 0.00 0.00 0.00 0.00 0.00 O.00 O.00 II.O0 0.O0 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.O0 0.00 0.00 0.00 O.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0,00 0.00 O. O0 O. O0 0.00

0.000 0.000 0.000 0.000 0.000


0.OO0 O.000 0.000 0.O00 0.O00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.O00 0.000 0.000 0.000 O.O00 0.000 0.000 0.000 0.000 0,000 0.000 0.000 0.000 0.000 0,000 0.000

INTER STAGE AFT SI'IR7 TRUSS OX ISO VALVE OX PYRO VALVE OX THROT. VALVE OX SERVICE VLV OX REGULATOR OZ RELIEF VLV OZ LINE OXIDIZER TANK OX LINE_ MAIN PUHP BOOST TURBINE BOOST PUMP MAIN TURBINE SOLID INSUL. SOLID CASE CONVRG CASE CONVRG I;_$L INJECTOR COHB, CASE COMB. INSL SOLID PROPEL. SOLID IGNITER TVC ACT THROAT NOZZL_ SEP SY_

o.oo0
O.000 O.000
O.OO0

l I I

Figure

B-20.

LOX

With

Turbopumps,

Gas

Generator

System.

ORIGINAL PAGE IS OF POOR QUALITY

(.'O.)(!'L)I_ENT AVI ONI CS WIRIt,_G BATTERIES IN,_TRUHENTATION NOSE SHELL NOSE HE HE HE lie HE SECTION

UI_ITS REO' D 1 I I 1 1 SUBSYSTEM 1 1 I l 2 SUBSYSTEE 1 1 i SUSYS'LEE & ,_ /. ! 1 1 & 1

UNITS O_ER. 1 1 i

"rl V RE,I AS, ,,.,IT. THRU PKB-LAUNCH

RELIABILITY THRU BOOST 0.999999250 O.99999994& 0.999993663 0.999994188 0.999998313 0.999985356 0.999998594 0.999998594 i.000000000 0.999997926 l.UOO000000 0.999995114 0.999999963 0.999999963 0.999999963 0.999999888 1.000000000 1.000000000 0.999975145 1.000000000 0.999997926 0.999999633 0.999999835 0.999998594 0.99999859_ 0 .999969727 0 0 0 0 .999999570 .999999570 .999999570 .999999570

RELIASILITY THRU POST-BOOST 0.999999250 0.999999944 0.999993663 0.999994188 0.999998313 0,999985356 0.999998594 0.999998594 1.000000000 0.999997926 1.000000000 0.999995114 0.999999963 0.999999963 0.999999963 0.999999888 I 000000000 1 000000000 0 999975145 I 000000000 0 999997926 0 999999633 0 999999835 0.99999859& 0.999998594 0.999969727 0.999999570 0.999999570 0.999999570 0.999999570 0.999998281 0.999993700 0 999866009 0 999866009 0 999993700 0 999955001 0 999866009 0 999993700 0.9999&&002 0.999915004 0.999393284

I. 000000C)00 i. 000000000 I. 000000000 i. 0000C)0000 i. 00C)000000 1.000000000

TANK LINER PYRO VALVE REGULATOR SERVICE VLV PRESS.

I 1 2 ] 1

I .000000000 1 .000000000 1 .000000000 1 .000000000 1 .000000000 1.000000000

HELIUM

:INTER STAGE AFT SKIRT TRUe. S STRUCTURE

! 1 )

1.000000000 l.O00CK)O000 l.O000OO000 1.000C'00000

0:.'. IS0 VALVE 07, PYI_O VALVF.. (IX THROT. VAI,VE I T OX SE.:V_C-'g' VLV 0): REGULATOR O)',RELIEF VLV 03: LI_:E O,.a.DI ZER Tr.,_I.

d & /, 1 1 !

1. 000000000 I. 000000000 !. 000000000 1. O00C)O00C)O !. O0000000O i. 000000OOC) !. 000000000 I. 000000000 i. OC)O000OOt_ !.000000000

OZIDIZEP,

_J:,S,ST_.. 3 3 3 3

HAYN P:!_::' BOOST TUREINE BOOST PUMP HAIN T[IRBINE TURB_-PU_I'

& &

1.000000090 1.000000000 !.000090000 1.000009009 1.000000000

SUB.SYS: gg 1 1 l I _ I I 1 l I I : I 1 1 ] :1 ]

0 .999998281 0 .999993700 0 .999866009 0.999866009 6.999993700 0.999955001 0.999866009 0.999993700 0.9999_4002 0.99991500& 0.99939328&

SOLID INSUL. SOLID CASE CONVRC, CASE CONVRC INSL INJECTOR COHB. CASE COHB. :INSL SOLID PROP!_L. SOLID IC,,N!TE_

:.000000000 1.000000900 1.000000000 l.O00000000 1.000000000 I.O000000UU 1.000000000 1.000000000 1.0000UOUU[} 1.000000000

SOI,ID MOTO. _ SU},SYS'[E, w

Figure

B-20.

LOX

With

Turbopumps,

Gas

Generator

System

(Cont'd).

"'" ....

"" F_'_'C'ES J

COHPON_ TVC ACT THROAT N_ZZL_ NOZZLE SZ? SYS SUZSYZTZ_I

UNITS ZE0'D 1 _ !

UNITS 0PEE. 1 I I

RELIABILITY THRU PR_-LAUNCH 1.000000000 i.O00000000 I.OO000D_O0 1.000000000

RELIABILITY THRU BOOST 0.999679052 0.999751531 0.999751531 0.999182334 I. 000000000

RELIABILITY THRU POST-BOOST 0.999679052 0.999751531 0.999?51531 0.999182334 I. 000000000

I.O00000000

O:<- BOOSTER

SYSTZH

RELIABILITY

!.O0OO0000O

0.998524554

0. 99852455&

Figure

B-20.

LOX With

Turbopumps,

Gas

Generator

System.(Cont'd).

0_' POOR

QUALITY

REUSABLEBOOSTER I::PUTS DEFAULTCOMPONENTDESIGNLIFE DEFAULTRECOVERYATTRITION RATE I0 fOX RECOVERY REFURBCOST REFURB COST IOTAL COST (K $) ATTRITION (l TFU) (K $)
_========= _======_== _==_==_== D .........

REUSELIFE
==========

E&I
........................

$445)113 I0 ] I ]0 IOZ 25Z $266,927 $0 SO $178, IS6 $70,iB9 )0 I0: 39i $70,:39 $I04,2B4 li:; i0 tO I IO IO_ IOX lot fOX I0_ 16t 16% 16_ 16X I_t $_I. 417 SO

$887,973 $402,226 $152,961 $268,504


e_c O_)i ._..,o,,

AVIONICS WIRING BATTERIES INSTRUMENTATION RECOVERY5YSTE_


........................ ........................

IOZ

25Z

PAPACHUIES STRUCTURES
........................ ........................

$255,B01 $768,5S') $_., 5S5 .... SO

NOSE FO_:WAF'D S}:IF:T AFI SKIRT ATTACHMENTS INTE) STABE OXIDIZEkSYSIEM


===================_====

$59,12B $435,75_ $I0,069 $74,350 S3,6561 $26,902 $56,337 $4,04'_,234

OXIDIZE_IANK TANk:LINER OXIDIZERPIPING OX ISO VALVE OX PYRO VALVE OX SERVICEVALVE OX RE6UALTOR OX RELIEF VALVE PROPANETANK PRO THROTTLEVALVE PRO ISO VALVE PRO PYRO VALVE PRO RELIEF VALVE HE TANK HE TANK LINEN HE ISO VALVE HE PYRD VALVE HE REGULATOR

I 1 I0 IO I0 I0 I0 10 I I0 IO I0 I0 I I I0 I0 I0

IO_ fOX fOX 10% I0_ I0_ IOX I0_ fOX 10% !Ol IOZ IOZ I0_ lot I0%

253C 25: 25:6 25_ 25t 25X 50Z 257. 25Z 25Z 25_ 501{ 50'( 25Z 25Z 25Z

SO $I,017,039 $0 $528,171 $29,842 $421,446 $2,2!3 $31,253 ii,537 $21,706, SI,660 18, 9 _8.. $1,BSB $9,384 $53.1 $2,697 SO $0 $e54 SO $0 sO S12,061 $0 SO $0

sO $I,763,062 $0 $34,813 sO $0 $I,572 $I, $13,029

Figure

B-21.

Reusable

Booster

Inputs.

ORIGINAL PAGE IS OF POOR QUALITY

O_mmDmI_BB

"t ......

! .......

' ....

_P ....

I .......

I_1 ....

....

_2

'

"

" 2

............

....

....

......

....

.....

.....

..........

..........

.....

...............

L;

+C

i,_

= 2
(c. = 0 ,_ ,C

2 2 2

1_

d d

+ 2

_ _

2 2

2 _

d 2

1.

_.

cl:

=
Ix

m0 _

: 2 : 2 21:2
oooo_ooooooooooooooooooooooooo

S : :12

2 : 2 2,2 _ 2 S 2,2 2 _ 2 _,2 2 2 2 2

r_

:::::::::::::::::::::::::::::::::.
O00000000iO0000100000

+
o o ...........o o o o o o o o !o _ o _ o _ o _ o _'_ o o o _ _ o _ o_o _ o o o _ _

I
olo d _ o o _ _ o _ o _ ,i o o o o o o o o o o o o , o o o . o o o o o o o o o

'
..... o o q0 _ o o , o o o o o o o o o ..... o o _ o o o , o o o o o o o o o o Io o , o o o .... o o o o _ o o o o , ..... o o o o ID o o o o o o o o o o

I
| .... Io o qo o |o o

...........

........

ORIC_iNAL PAGE IS OF POOR QUALITY

g g g g g
II,

...........

d g g d'd

g g g g g d

....
_ _ .........

"1.....
--,1_1 _ -_ _ )1. I .... _1

I.....
o11_ o m _ _ I .... "_ll

+--------.+++m.o++m'++'o++++_++'+o"

....

_o+o

....

!!!ii,iiiii:iiii

iiiimiiiiili ........

............................

gggggg

,.t;

:t. 0

,C Z

Z:

31:

o ......

o i

o o

o o .....

o i

o ........

o _ o. .o. o

0. o._+ _o.,o o.+o. o o.

:+ .

I+*I

-++ ))))) ))))++

)))))
.+, ., ., + +_
000000000 * , 0m 0,

)))))

i ..... i .....

m | .....

,,,1

,,-i

0 0 o 0 0 o

0 0 o

0 0 o

0m 0 0 o

0 o o

* 0 o o

* 0 0 o

, 0 0 o

.m o 0 o

0 O o

0 0 o

o 0 o

0 o o

31:

.....

.....

.....

Q._..

! /

.........................

.........

q,

r.

e-l_e-

r-

e-

roll

o,

t"

_ II,

oooo. ooooooooooooooo. o.!oooooooooooo


* " "_ ..... ' ...... I ..... ..... *! ......

"

roll-,

o,

t,,llO,

e,

F-" ......
/

J_

--

--'I"

B,

_.i_

......

......

......

......

......

......

--

1-11111
_......
......

_~I:11;

..............

.......
I ......
I ....................

'......
J ......

I ......
_____
, ......

I ............
I ......

_..._
......

....
, ......

: ....
,

5_7_
......

-!
, ............

oooo ..........

oo!o!o!_!o!o!o2!2!2o2o

= ..........
i

.._..._

iiiiiiiiiiiiiiiiiiiiiiiiiii
" dgggg2

_
.......... 0 0 0 0

_'_""
. 0 0 0 0 0 0 0 ..... 0 0 0

_1._t _'"
. 0 0 ..... 0 0 0 0 |. ) 0 * 0

::o.i_o..
, 0 0 *. 0 ..... 0 0 0 0

4_

_=
D.

iiiii
0 ..... 0 0 0 0 I 0 ..... 0 0 0 0 00000 ..... i 00000 ..... i 0 ..... 0 0 0 0 i

iiiii
0000 ..... 0

iiiiiIiiiiiiiiii
000000000000000 i I

.....

.....

....

....

.....

....

........

....

.......
........... ...... o ......... i .........

I-

o o

.........

i .........

,( 0

-1

*-;

.J

,J

.1

,J

,.1

,.1

,.I

111_111_
........ ooooooooo

"'''"
, ...... oooooooo ooooo_oo oooo_Ooo

t
' I
m

.............

....

........

0000000001000000000

22

.......

"

a .........

_ r .........
I

o .......

!
J
_00000000!0000o0000

iii

........
00000000000000000

+
I

::::::::::::::::::::::::::::::::::::::::
+

:+

. + + +++++++++++++++++ +++++++++++t+++++++++++: ++++++++


_NgNNNNgNN_N_N_NgN_NgNNNNNNgggNNNNNNg
000000000_000000000000000000000000_0o

.........
......... 0o0000000_0000000000000000000000000ool 000000000|000000000000000000000000000

:....
I .........

__
| * * ......

......
"

___
.........

_0000000000000000001000000000000000000 *_0000000000000000000000000000_000_0 _O000000000000000_O00000000_O0000C_O

:_: _-_-_.: '... :_-,. _- _ ii_i_ __


...... 0 0 0 0 O O,O I * O ' 0 i 0 , 0 . 0 .I 0 0 O ' 0 0

_ii_iii
* I 0 O 0 , 0 * 0 * 0 0 gO _ IBtn O00000s

I
II 0

o, __
0 0 0 .

=_ 0 0 ....... 0

o
0

_
0 0

- o
0 0

I,

a_ anl
000 0 trt; O @ O_

Ill

00000

00000

o,,

......

.,

_:_'
o -. ...... _ -. -. , -. ......... -. -:. ........... ......

i!!!!!!!!!!!!!!!!!!!!!!!, !I!g!!!!!!!!!! " , , ,


_ _ 0 0 "o o 0 0 o 0 _ 0 0 0 0 0 0 0 0 0 0 0 0 0 0

......

......

......

............

.....

.........

.....

........

'_r

_*

--

,"_

r'*

--

..........
...... _ _ _* _ _'_ _ _ _C _G 0 ........... 0 0 0 0

......

o ...... o..... oooooooooooooo


u . , .... l ...... I ...... I ..... ' C _ 0 0 0 0 0 0 0 0 0 _ r_ qr _* r_ _ 0 o 0 o 0 0 0 o o 0 0 0 " 0 ............. 0 i0 0 0 0 0 0 0 ' 0 .............. 0 0 0 0 i0 0 0 0 0 0 .0 . 0 . 0 . 0 . 0 . 0 .

" 0 .... io

_m !mmmm_m

_i

_:_

000000000_00000000

O0000_O000OO000000 ..**.m

......

......

...... 000000 000000 _000000

............ _00000000_00000000000000_0000 00000000000000000000000_0000_ _00000o00000000000o0_0000o0o

I*

.,**0l.*0'o'l'0"00*

_
J . . . oi ._ .... J " " " "

e
i ' * *

g
" J "I * * *

-@
m J' * * " "

....... I-I... .
..... . o ....

I ...... _-.I ....


, , ....

mm_mmc._amm| 040 0 0 0 OI 10 0 0 0

o,ooooo.,ooooo_oooo _lJ _'" rt "" rl ........


m_ }_ lib m ID im J m'| II Ill _ J I_ II _ _ m ...... I " " " .....

oooo
_ il_ im " "

io

"

__'
2 2 '2

I_
' 2 '

i_

'

0 Z

.....

.....................

..J :6J

.J

: .J .J

,_ ..... , ..... , .....

I0_ ,

am, .....

0 , ..... , .....

.....

.....

.....

.....

.....

.....

00000_0000_0000000000000000000

2 212 2 2 2 2 2 S 2 = 2 :

2 = .............

__ 00000

o00000000__0000o000 O0000OO000OO00_O000"O0000

O_

R RR
.... ....... | .......

"-

.............

.....

.....

.....

.....

....

e
_"_ .....
..................

.8
o,, ......

@-

-e
.......

b
.... :-

1 .... ,-_l.--o,a-_

_____1___

.... ".... "'1 ..... 1"''" "F'" "'"["" """

::t:t, tttt:, .... _....oo.......... :::_:'::::_'12222222...._..a


0

2 2

;I;

_ 2

212

2 _12

212

_ JI2

2 _

..........

.....

.....

.....

; .....

e_

.........................
,4 d:

L.o..

lI;. --" 0

=..................... _ _ I__
I

".....I.....1.... 'r .
i= ..... i ..... i ..... i ..... i .....

(_.

ID

__,

" _, _-,,_'_,

'" _.,',,_.

_"

2"''.-

! --

ID

00000

000000000000000!00000

00000

:::::i::::

__i__

.....

.....

.....

.....

_Bim_mm_smmDmm_mID_Immmms_mB_m

.....

[ l

.....

l I

.....

I I

.....

.....

.....

+++++++_'++++++- +.+--.. ==_.= + o. .= ...+. ++_+=+ +


&J 1,4 I ,< I I

..... t......... i::: i..... .


.............. I + ,.....
t
f ..... | ..... n ..... * " -" "

+"
(.. r... ._ Cm

4:

:_ +-.. N O C=

p_. ,=,
i. .m:

++
C+

LJ " I,,X i..i !

++-m+a+_+
O Z

_.:+m

++ .+=mm::=

.-m

N O CI

1!22,_!1!!.2_12'15121,_!215
. +o ,

)))))))
_)))),)
.........

++++_)) ): )_ii) P_
,oo,

)))))
* * ,

..t

_)+)+ _))))
i

<_

ooooooooooooo_ooooo__o o o o o o o o o o o o o o o o] o o o o o-o
..... ! ..... u.o,,.,*_.,*'''** 00000_00000000000

o o o o o

: .................

i=_

__.__

_
_ ....

-* ,

' --.-.-o----:__
.... ,0 .... , ....

:11

00000 ......

......

.....

-_-_--_ -_ __
...... 0 ...... i i ...... u ...... i ...... i ......

_--===:==_'_..
...... _ ...... i ............ i * * *i ..... W N ........................ i ...... i ......

0 p

...... _ Z rx ......

......

....

..................

......

............

............

......

....

-_2

......

__

"

i-iiiiii_iii iii_ "

00o00000000o0000000000000000 0o000_0_0000 000000000000

000000000000000 000000000000000

0_000o000000 000o00000000

000000000000000 000000000000000

!_!!:
O Z ..........

!!!!_ ..
N _ . . . , --

" $ " " 1


:11;
_ _'_ _ _ _ _
J

_ _

_o
_OQO

_ _

_'_

"i
__ W .....

.........................

I-

_
iiiii

_i _-____
'_

i
i

....

_! ..... o_:

o
o='I
,,I

G
: o,olo"_JI:--: " "
,4 ,,4 _

........

=
IO'

................................

=
I-, E 4_ e, I

_'.__
_---_
I

:_:::,:_::_,:_:::

:_::::_::_

_-._:_
m

iiiii
...ooo_0
0_000 00000

iiiii
0000_

iiii_
0000_ . , 0 .

iiiii

_ : _-: o
00000 I I

.0_0000000!

"

!if!ill
...... -, . 0 Z

!0

ii!*
_:-;_.
.

....

.....

I-

.........

.......... !
_ZXEE

!!!!! !!!!!
. .,,o

p.

t-* .C

g g,2

X X,2

X 2

"

..:

>.

=
Z

_:

(-

................

i'* K s-

-_.

. _. .....

_. .._..
. -.

22222222:2
4_ m

Ib

_,

e..

=_;===
.....

22o_
0 I . _

_!!!!
..... * 0 * *! * ' * * ,.*,..,. .... 0 .| * , 0 *

__,__
.......... . .... 0

_3r
r

1.1

.....

......

....

.._**

....

i.

....

.....

,..,,.

0!

.!

01

....

++++o+: o+o++o: o+-o+ _+_- : ___. +- +o++ : ++ + ++ ++_ +_o+o_ + +++___ i.d In ............

' 2

" 2

2'

" 2

..........

,,,,: ...........,

. |

......

+-

o
14

I..,

r..

1.

_,( is: I-

..: O 1+-4

[..

_.2222:2:'222"22.2222".'2222!_2212222!_
_ _ _ _ _ _'_ _ * _ " _'_ o _ _ _ _!o _ _ _ _ o

______
D. K O

I< O ............... i

__:._-__._::.::::::
::i::':
w w

:::::_:::_:,
..... ,| . , , , !- O O O O O O O O O O O

oooooooooooooooooo .....

......

......

. 1

, o o

. o

.,...|,..,.,|., ooooooooooo_ooooo_

....

o:::o
O i o o o o o o ooooooooooooo_oooo

::_:_._:::::,:::_::

,.} I_

I_

N N 4_

I" , :'

_2;_j

............

r.

l"

dE )< O

X O .: VI * .... -

: .....
0000000000

I.....

00000000000_00000000 .....

.....

..........

O000000000

000

000

......

2222"

........... iiiilI:::::
OF POOR QUAi._TY

0 z

.....

_m_mmDMm_

W .......... _f .................

! w ..... n ..... a ..... u" .......... ! _ .....

CO W

0 u

Z N

I"

iiiiiiiiiiiiiiiiliiiiiiiiiiiiill
0

,L
0
m

-_ _
w

_ _

_ .......

_ ......................
..... a ..... i ....... |

I ...........
'| ....

.....

i .....

.,

.....

.....

_ .....

--I r,*

o_
N

0 Z

'

i R

Z_mo

0 Z

T._r.
t _

_00 -t<,.

_m _'_ i o

000

z_

o _o G

o _

= 0 F-

.......
i

.......

, .

LJ c. =

IZ C t-

;;21 ......

i..

.0

(-

mmw x _

I",

ORIGINAL OF POOR

PAGE IS QUALITY

..

-_J

fl

I-

O_'Q_"'_AL

PAGE IS

OF POOR QUALITY

0 z

.....

G,

(= p

-,

n O

_ _

o t-

_ooooc o

O_00D

iiiiii

m ...1 ....

....

o_

c:_ II c.. n III E; =

.-

_.

=_.;_
{= c :.a

z:

->-

z .1:

I o

oooo

,=

I"

1:

=:

0-

,.,,*;,_,=_;-... I"_'AGE IS OF POOR QUALITY

mmm oo

d i-* --

"

II |

I-

r_

I"

to

1.1

You might also like