You are on page 1of 5

CHAPTER 5-COLLECTION OF MATERIALS

Notes: 1. The rates are for collection of materials at Quarry. 2. The payment for collection will be made after delivery of materials at specified sites. The payment for collection of materials at quarry or source shall not be made without the written permission of the Superintending Engineer/Chief Engineer. The rates include(a) (b) (c) (d) (e) (f) (g) 4 All lead and lift involved for collection purpose at quarry. screening to remove dust, etc. Removal of unsuitable material or weathered stuff. Royalty ,VAT & other charges as fixed by Govt. Stacking and Boxing Opening of quarry and removal of overburden Making approach road to the quarry

3.

Though separate rate for stacking,boxing,screening,washing etc.have been specified in respect of this chapter ,however in principle all the rates for collection of different materials given in this chapter are inclusive of stacking, boxing, screening, washing etc. Measurements- (a) The following deductions will be made from stack measurements. (i) Metal, Kankar, gravel, shingle, stone chips and quarry spalls (ii) Moorum, sand, boulders, masonry stones, pitching stones and rubble. (iii) Puddle earth. 8% 16% 25%

5.

(b) Metal, moorum and sand for use on roadwork will be boxed for measurement in boxes measuring 1.5m X 1.5m X 0.5m. (c) Boulders for use on roadwork will be stacked in regular stacks measuring 2.5 m X 5 m X 0.5 m. (d) for other works if (b) and (c) cannot be followed the materials may be stacked in stacks with length and breadth in multiple of 1 m. 6. (a) Boulders mean stones of any type, which have been weathered and rounded off due to action of sun, wind and rain and which occur in natural condition, either on the surface of earth or buried below the surface. (b) Quarried stones mean stones of suitable sizes, which have been broken from much bigger boulders, stones or rock extracted from quarries. The

criteria for this is that more than 50% of the surface of each stone should be broken surface. 7. Blasting: - Blasting rate is payable for item 503 for collection from quarries of massive hard rock or compact lime stone, hard sand stones or similar formations for the extraction of which blasting is actually done. 8. Size of metal should conform to the grading as per table below:Single size coarse aggregate of nominal size Nominal size of Passing through Retained on aggregate in mm. mesh size in mm square mesh size in mm 100 110 80 80 90 60 60 75 40 40 50 25 25 40 20 20 25 12 12 20 6 10 12 6 6 10 3.5 Item No. 501 502 503 Item Collection of puddle earth (a) Collection of soft moorum (b) Collection of hard moorum Collection of hard metal other than black trap basalt and granite (a)100 mm nominal size (b)80 mm nominal size (c)60 mm nominal size (d)40 mm nominal size (e)25 mm nominal size (f) 20 mm nominal size (g)12 mm nominal size (h)10 mm nominal size (i)6 mm nominal size Collection of shingle or gravel including screening(a)100 mm nominal size Unit cum cum cum Rate 30.00 30.00 34.00 Remark

cum cum cum cum cum cum cum, cum cum

86.00 94.00 120.00 189.00 248.00 320.00 394.00 465.00 539.00

504

cum

66.00

Item No.

Item (b)80 mm nominal size (c)60 mm nominal size (d)40 mm nominal size (e)25 mm nominal size (f)20 mm nominal size (g)12 mm nominal size (h)10 mm nominal size Deduct from item 503 above for metal breaking with Govt. boulders and excavated rock. Collection of boulders at source (maximum size 0.014 cum), without quarrying i.e. picked up boulder. (a)Collection of quarried stones Maximum size 0.014 cum.) (b)Collection of quarried stones( size 0.014 cum. to .06 cum) Collection of stone chips, quarry spalls or rubble (maximum size 0.004 cu m)(a) Black trap, basalt or granite (b)Other than black trap, basalt or granite. Collection of size stones for coursed rubble masonry rectangular in shape (size 0.014 to 0.06 cu m) including 20% headers(a) Black trap, basalt or granite (b)Other than black trap, basalt or granite. Collection of rubble for masonry (size 0.014 to 0.06 cu m) other than black trap, basalt or granite.

Unit cum cum cum cum cum cum cum cum

Rate 66.00 66.00 84.00 101.00 101.00 119.00 119.00 51.00

Remark

505

506

cum

44.00

507

cum cum

118.00 205.00

508

cum cum

84.00 76.00

509

cum cum cum

443.00 403.00 304.00

510

Item No. 511

Item Collection of face stones for dam masonry hammer dressed on face, with one line chisel dressed 75 mm depth from face. On bed, top and sides and hammer dressed below 75 mm depth of the stone up to rear face. Beyond this depth of 75 mm the stones may taper but the tail end of the stone shall be at the minimum length specified having at least half the area of the face, comprising of (a)Stretcher-size 55x35x30 cm (b)Header-size 60 to 45x30x30 cm (c)Bond stone-size 70 to 60x30x30 cm. Note-10% of the face stones should be bond stones.) Collection of pitching stones of size 20 to 25cm and not less than 0.021 cum(without dressing) (a)Black trap, basalt or granite (b)Other than black trap, basalt or granite. Collection of pitching stone, size 28 to 32 cm and not less than 0.024 cu m (without dressing)(a)Black trap, basalt or granite (b)Other than black trap. Basalt or granite. Extra rate for blasting for item 503 (a) Black Trap, basalt or granite (b)Other than black trap, basalt or granite Extra rate for black trap, basalt or granite for items 503, 507, 510 & 511. Stacking and boxing (a)Moorum or sand

Unit

Rate

Remark

each each each

85.00 90.00 100.00

512

Cum Cum

346.00 315.00

513

Cum Cum

369.00 335.00

514

Cum Cum Cum

88.00 35.00 10% of respective items 7.40

515

516

Cum

Item No. 517

Item (b)Metal & Shingle or gravel Stacking without boxing (a) Puddle earth, moorum,sand or Kankar (b) Metal, Shingle, stone ships or quarry spalls (c)Masonry stones, pitching stones or boulders Screening (a) Metal, shingle or gravel (b) Sand Washing sand, metal, shingle or gravel Collection of boulders or rubble from excavated materials.

Unit Cum Cum Cum Cum

Rate 12.00 4.80 6.30 12.00

Remark

518

519 520

Cum Cum Cum Cum

18.00 13.00 34.00 23.00 For use of boulder toe, boulder soiling etc.

521

Collection stones

of

through/bond

Cum

599.00

You might also like