Professional Documents
Culture Documents
Transmission Lines
Volume-5 Stringing
Construction Management
Vol.5 : Page #
Vol.5 : Page #
CONTENTS
CHAPTER 1 CONDUCTOR AND EARTHWIRE SELECTION CONDUCTOR CREEP AND SAG-TENSION CALCULATION PAGE NO. 1.1 1.1.1 1.1.2 1.1.3 1.1.4 1.2 1.2.1 1.2.2 1.2.3 1.3 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.4 1.4.1 1.4.2 1.4.3 SELECTION OF CONDUCTOR POSSIBLE TYPES OF CONDUCTORS SUB-CONDUCTOR SPACING ELECTRICAL CONSIDERATION STRUCTURAL CONSIDERATION SELECTION OF EARTHWIRE FUNCTION OF GROUND WIRE HOW GROUND WIRE PROTECTS SHIELDING ANGLE AND MID SPAN CLEARANCE ORIGIN OF CONDUCTOR CREEP PRIMARY AND SECONDARY CREEP EFFECT OF CREEP CREEP ALLOWANCE COMPARISON OF METHODS PRECAUTIONS DURING STRINGING SAG TENSION CALCULATION CATENARY AND PARABOLIC FORMULAE COORDINATION OF SAGS STRINGING CHARTS
Vol.5 : Page #
1 1 4 7 9 10 10 12 13 14 14 15 16 17 17 18 18 21 22
CHAPTER 2 DEFINITIONS AND TERMINOLOGY PAGE NO ACSR CONDUCTOR BLOCK BULL WHEEL CLIPPING IN CONDUCTOR CAR CONDUCTOR GRIP RUNNING GROUND TRAVELLER GROUND COMPRESSION JOINT PROTECTOR JOINT PILOT WIRE BULL WHEEL PULLER REEL STAND RUNNING BOARD BULL WHEEL TENSIONER TRAVELER UPLIFT ROLLER 24 25 27 29 30 33 35 36 37 38 40 43 46 47 53 54 55
Vol.5 : Page #
CHAPTER 3 STRINGING METHODS AND GENERAL ASPECTS 3.1 3.1.1 3.1.2 3.2 3.2.1 3.2.2 3.2.3 3.3 3.4 METHODS OF STRINGING MANUAL METHOD TENSION METHOD GROUNDING DURING STRINGING INTRODUCTION SOURCE OF HAZARDS GROUNDING PROCEDURE COMMUNICATIONS SPECIAL REQUIREMENTS FOR MOBILE EQUIPMENT 3.4.1 3.4.2 DRUM OR REEL STAND TENSIONER BULLWHEEL CHARACTERISTICS 63 64 57 57 58 59 59 61 61 62 63
3.4.3
66
3.5
68
78 78 78 79
4.2.3 4.2.4 4.2.5 4.3 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 4.3.8 4.3.9 4.3.10 4.3.11 4.3.12 4.3.13 4.3.14 4.3.15 4.3.16 4.4 4.5
SAGGING AND FINAL TENSIONING CLIPPING FIXING OF HARDWARE STRINGING OF CONDUCTOR GUYING OF TOWERS INSULATOR HOISTING PAYING OUT OF PILOT WIRE POSITION OF TENSIONER AND PULLER PAYING OUT OF CONDUCTOR REPAIRING OF CONDUCTOR JOINTING OF CONDUCTOR ROUGH SAGGING OF CONDUCTOR FINAL SAGGING OF CONDUCTOR REGULATION CLIPPING OF CONDUCTOR FIXING OF LINE SPACER INSTALLATION OF DAMPERS JUMPERING PAYING OUT THROUGH ANGLE TOWERS TRANSPOSITION ARRANGEMENT STRINGING OVER RIVER CROSSING STRINGING OVER POWER LINE CROSSING
81 83 84 85 85 86 90 90 92 96 97 100 101 104 105 106 108 108 110 111 113 116
Vol.5 : Page #
CHAPTER 5 GUIDE LINES GL - 1 GL - 2 GL - 3 GL - 4 GL - 5 GL - 6 PRE STRINGING CHECKS PAYING OUT OF EARTHWIRE PAYING OUT OF CONDUCTOR FINAL TENSIONING OF EARTHWIRE AND CONDUCTOR 119 125 128 135
CLIPPING AND FIXING OF EARTHWIRE ACCESSORIES 140 CLIPPING AND FIXING OF CONDUCTOR ACCESSORIES 143 ANNEXURE S/1 FOR STRINGING ANNEXURE S/2 FOR STRINGING CHAPTER 6 REQUIREMENT OF MANPOWER 153 REQUIREMENT OF TOOLS AND PLANTS 149
154 170
(v)
Vol.5 : Page #
_____________________________________________________________________ Chapter-1 _
Conductor & Earthwire Selection Conductor CHAPTER Creep & Sag-Tension Calculation _____________________________________________________________________
_ CONDUCTOR AND EARTHWIRE SELECTION CONDUCTOR CREEP AND SAG-TENSION CALCULATION Back to Contents Page 1.1 ONE
1.1.1
(i)
Up to 220 kv lines, the basic criteria for selecting the size of conductor is its continuous and short-term current carrying capacity both under normal and short circuit conditions. However, for EHV lines this
criteria does no longer hold good, as corona and its effects come into picture which voltage. For 400 kV lines, are function therefore, of line size of
conductor is determined not only from current carrying capacity considerations but also from corona and radio interference established satisfactory considerations. that the size corona and of RI The experience has
conductor performance
adequate current carrying capacity also. The size of conductor so determined would normally be larger than
Vol.5 : Page #
that
selected
from
considerations
of
power
transmission capability. (ii) One of the methods to achieve this would be to have a single conductor with large diameter. However, heavier weight of such a conductor, its handling, transportation and stringing due to
manufacture, would be
therefore, not considered for 400 kv lines. (iii) Another method of increasing the size of conductor, which some utilities in America have tried, is to use expanded aluminum conductor, necessary to in which the minimum power is amount of
carry
retained,
and inert low cost filler material is stranded around the aluminum portion to increase the overall of the conductor. However, its use has diameter not found
popular support even in America, due to manufacturing and other problems. This conductor was also,
therefore, not considered for 400 kv lines. (iv) The only other alternative of 2,3 was or 4 to use bundle sub-
consisting to obtain
small
size
required
effective
overall
the conductor. For EHV lines, this is the suitable, to economical bulk and commonly over long
technically method
adopted
transmit
power
distance. The bundling reduces the inductive reactance loading and improves the stability of the line. The
Vol.5 : Page #
voltage thereby
gradient improving
is the
to and
limit,
performance.
Studies
that
Table 1.1 gives the number, size and other physical properties of various conductors. Table 1.1: Number, Size and Physical properties of Conductors
-----------------------------------------------------------------------------------------------Code No. of SubStranding Overall Unit weiU.T.S. Approximate Name conductors (mm) dia. ght (kg/m) (kg) current carry(mm) ing capacity 40C ambient temperature -----------------------------------------------------------------------------------------------Goat 3 30/7/3.71 25.97 1.492 13780 680 Sheep Deer Zebra Elk Camel Moose Bersimis 3 2 & 3 2 & 3 2 & 3 2 2 2 & 4 30/7/3.99 30/7/4.27 54/7/3.18 30/7/4.50 54/7/3.35 54/7/3.53 42/4.57 7/2.54 AAAC 2 61/3.55 31.95 1.666 16307 ----------------------------------------------------------------------------------27.93 29.89 28.62 31.50 30.15 31.77 35.10 1.726 1.977 1.625 2.196 1.804 2.002 2.181 15910 18230 13316 20240 14750 16450 15715 745 806 795 860 900 -
1.1.2
(i)
After having selected the conductor with twin arrangement, decided. the sub-conductor spacing spacing had the
bundle to be
Sub-conductor
influences
surge
impedance loading (SIL) of the line, corona and radio interference performance, line losses and the of towers. The cost of series and shunt weight
compensation,
affected to some extent. A phenomenon known as subspan oscillation is also related to sub-conductor affect
spacing.
the cost per MW capability of line. (ii) From the experience and practices adopted by
different countries for 400/500 kv lines, it was found that the optimum sub-conductor spacing would vary sub-
between 30
to 45 cm.
conductors spacing form 20 to 50 cm was considered. (iii) Figure 1.1 shows the surge impedance loading of twin
'Moose' conductor bundle with different sub-conductor spacings spacing varying from 20 to 50 cm, and from 10 to 16 m. With increased inter phase
spacing and reduced bundle spacing, the capability reactance line. is and reduced reduced the due to
capacitive amount of
Accordingly,
and
shunt
Vol.5 : Page #
Vol.5 : Page #
(iv)
The
in
the sub-conductor spacing due to following reasons: (a) With given configuration of towers, and specified with
the increase in sub-conductor spacing. This involves an increase in the height and hence the weight of
towers. (b) With increase in cross-arm length, the torsional load increases under broken wire conditions, resulting increase in the weight of bracings. (v) The IR and corona losses also get affected with SIL in
Apart from the above, sub-conductor oscillations have also been found to be related to sub-conductor
spacing. These are low frequency and high amplitude oscillations which may be so severe under certain wind conditions as to cause clashing of sub-conductors in
the mid sub-span, and thus resulting in damages to the suspension conductors. fittings, Through spacers and subsequently research to and
extensive that
reduced and
spacing
increased, by
considerably
keeping
sub-conductor 400 KV
lines constructed by CEGB in U.K. with 300 mm subconductor experienced oscillations. spacing with due twin to they "Zebra' such are bundle have
trouble
Subsequently,
have increased the sub-conductors spacing to (20 in.) increasing the spacing-to-diameter
from 10.4 to over 17. (vii) For twin 'Moose' bundle, the optimum sub-conductor shown in
spacing
Figure 1.2. The decision, however, went in favour of 45 cm sub-conductor spacing in view of the reasons. (a) For most of the European and American utilities spacing for 400/500 kv lines the was 45 following
Vol.5 : Page #
(b)
As
design
and
performance
of spacers and
hardwares
at
this
spacing were well-known. (c) The corona and radio interference performance was
than 14. (viii) The horizontal configuration of bundling was for for
selected, as it is the most common arrangement twin bundle conductors, although in some cases
lower voltages upto 345 Kv, vertical bundling has also been adopted. 1.1.3 Electrical Considerations : Back to Contents Page (i) Current Carrying Capacity The conductor selected for EHV lines should be
capable of carrying currents under normal as well as peak loads, without getting overheated. of the line state should and not be The stability both The under surge
disturbed, conditions.
steady
transient
impedance loading, in which reactive power consumed by the line reactance equals the reactive power generated by MW with the line capacitance, has been calculated as 505
(in Figure 1.1) for twin bundle, 'Moose' conductor 45 cm sub-conductor spacing, which meets the
for
reactive
emergency peak
affecting the stability of the line. The excessive temperature rise over the some ambient time, be the
which
can ACSR,
transmitted.
However,
'Moose'
carrying capacity for a temperature on an ambient temperature of 40C is This provides a limit of power
amps.
transmission of 1250 MW from thermal considerations, which is much of more than normal and peak load
requirement (ii)
our line.
Corona and Radio-Interference When the electric field on the surface of the
conductor exceeds the disruptive field of surrounding air, corona effect takes place with discharges
surface root
gradient of line of
under to
voltage
inversely
proportional
diameter
therefore,
necessary to limit the surface gradient by increasing the diameter of conductor. The bundling of conductor is the most suitable choice, as already stated in
para.1.1.1
Vol.5 : Page #
---------------------------------------------------------------Items Italy France 380 kv Finland 400 kv Sweden 380 kv U.S.A. 500 kv U.S.A 500 kv U.K. 400 kv
---------------------------------------------------------------Line Voltage 380 kv Year of construction 1963 Nature of Conductor No. of subcondu ctors per phase
1963
1960
1965
1965
1966
1965
ACSR
ACSR
ACSR
ACSR
AL-alloy ACSR
ACSR
4.87
7.9
7.7
12.5
7.71
40
45
45
45.7
45.7
30.4
---------------------------------------------------------------1.1.4 Structural Considerations : Back to Contents Page The electrical advantages of bundle to a great extent The mechanical increase by conductors the are
loadings
structures
considerably
bundle conductors which result in heavier towers and foundations. The bundling of conductors also
necessitates complicated
thereby increasing the cost of line. However, we have to reach to the compromise for optimum choice conductor. 1.2 Selection of Ground wire Back to Contents Page
Vol.5 : Page #
of
1.2.1
(i)
As
is
are
the
conductors at
arranged every
above the phase conductors and grounded They mainly afford the
tower.
protection current
distributing the
in two or more paths, thus reducing the voltage drop. Another nature, function is to of the groundwire, voltage of a on minor the
reduce
induced
Voltages, the over voltages due to direct or induced lightning strokes are not the governing factors and the insulation selection is based on switching
overvoltage, the ground wire still protects the line and equipment from damage due to direct or induced lightning strokes by shielding. It also reduces strain across the to its insulator string, in case of stroke, due coupling with the conductor. To
inherent
perform this, it must meet the following requirements: (a) It must be able to carry the maximum lightning
current, without undue overheating. (b) (c) It must be strong mechanically. It the must be high enough to afford protection line to conductors a line at mid-span to prevent the to a all side
flash
conductor
during
interval to
mid-span and relieve the voltage stress there. (d) Tower footing resistance should be low. Size of Earthwire for EHV lines : G.S. 7/3.66mm,
overall dia. 10.98mm, wt. 0.583 Kg/m, UTS 6980 Kgs. (ii) In addition groundwires exercise a number of
subsidiary effects, some of which are: (a) (b) (c) (d) (e) (f) 1.2.2. Telephone and radio interference. Corona. Relaying possibilities. Zero sequence impedance of the line. Attenuation of travelling waves. Reduction in surge impedance. How Groundwire Protects: Back to Contents Page (i) In case of lightning stroke on a transmission line, the line can be struck either at tower point or at mid span. When the ground wire is struck at mid - span
the current divides in two parts and flows towards both towers and at the tower the current again
divides into two parts, one going to the tower and the other to outgoing portion of the ground wire. If
the tower is struck and there is one overhead ground wire, the current divides into three parts, one in the tower and two in the groundwire on either side of the tower. The strokes on the tower and within a quarter be on
tower middle
The strokes
on
the
mid-span
and dealt with as such. (ii) In case of from stroke, the the lightning surge the voltage ground
travels
point struck to
through tower.
reflected, and this reflected wave, though reduced in magnitude depending out to a great on footing resistance, cancels the incident wave. The
extent,
therefore,
at tower top or mid-span, for a time taken by surge to reach the tower footing and surge to reach the point struck.
incident
the reflected
time the point struck will be stressed voltage i.e., of there surge wave and be no no should not
should and
insulation
for mid
insulation surges).
clearance is also kept during the time, the the mid-span. 1.2.3
no flashover occurs
(i)
defined as the angle between a vertical line through the groundwire and the slanting line connecting the earthwire and conductors (outer conductors in case of bundles). The protective zone of groundwire is the
cone with the groundwire at its apex and the shield angle as to its slanting all angle. the The earthwire within is this
supposed zone
protect direct
conductors In actual
from
strokes.
practice, with
On the other hand, lower the shield angle, higher is the tower, and hence higher the cost of line. So a
compromise has to be reached between the line cost and protection afforded. (ii) Mid - span Clearance: In case of stroke on mid-span, very high voltage is on the may, to
impressed on the groundwire. The voltage remains the groundwire, till such time the reflection of wave returns. The voltage on the from groundwire groundwire
cause
flashover
This clearance
not cause flashover during the time it is impressed on 1.3 the earthwire.
1.3.1
Creep is time-dependent strain occurring under stress. A bare overhead line conductor will suffer a permanent increase in sag from non-elastic stretch caused by
following: (a) Short time loading such as from wind and/or ice loads, or after being subjected to installation. In these tension cases the during conductor difference is and of
initial and final modulus of elasticity (b) Long time loading at any tension
involved. temperature
level, which is known as 'long-term tensile creep' or, simply as 'Creep'. (c) The first stage Creep' [para-(a)] in which is the generally conductor known as
'Primary
initially creep
rate. This mainly represents a considerable amount of strand tightening and settlement, adjustment of load between layers, stress shifting between components of a composite (e.g., ACSR) conductor, and partial
metallurgical creep. (d) The second stage [para (b)] is known as 'Secondary
Creep' in which the creep is more stable and is mainly metallurgical. In this case the creep and the decrease
Vol.5 : Page #
in creep rate are both very slow. 1.3.2 Effect of Creep Back to Contents Page As mentioned in above, conductor creep sag results and, if in not permanent properly
increase
controlled, can cause irregular bundle sags, smaller electrical clearance to ground and to earthed metal
parts; and may require re-sagging operation at a later stage. The amount of this creep during the estimated or considered line life will depend upon everyday
stress and everyday temperature operating. 1.3.3 Creep Allowance : Back to Contents Page There are two below. methods Both It is sag are of in creep regular convenient in adjustment use to terms and as are
popular. or
most
express of a
permanent
increase
temperature-increase above the ambient. (i) Overtensioning : In this first method, allowance for creep during
sagging is made either by including creep correction in the stringing charts thereby producing 'Erection' or Initial Stringing Charts, or by reading the sag from 'final as or design' Stringing Charts (hereafter at ambient
referred
design minus
stringing the
charts)
temperature
established
temperature
Vol.5 : Page #
correction for creep. (ii) Allowance in Design : In the second methods, sagging is done to design is
stringing allowed
charts for in
increase by
providing
equivalent extra clearance from the 1.3.4 Comparison of the Two Methods :
bottom cross-arm.
Back to Contents Page The first method will initially result in some overloading though it also results in savings tower from
reduced tower height. The second with method finally results in lower tower age, which means the be line life and
loadings
stability can
be expected to
achieved with the first method due to reduced tension and vibration effects. At the same time, there is no chance lighter required. The first method normally requires erection stringing charts, whereas the second method requires furnishing of only design stringing charts which have to be of design tensions being exceeded. equipment Further, will be
and
cheaper
tensioning
furnished in either case. 1.3.5 Precautions during Stringing Back to Contents Page Prestressing as per stringing charts effectively
Vol.5 : Page #
stabilizes
the
conductor
from
creep
during
its
conductors
in a sagging section are handled uniformly as regards tension and time during stringing, prestressing and of
sagging. The subconductors of a phase should be the same make out of the same process of (e.g. wire drawn from either extruded and drawn rod.) 1.4 Sag-Tension Calculations hot-rolled
manufacture rod, or
Back to Contents Page 1.4.1 A proper evaluation of sags and tensions is necessary at the design stage for fixing up the ruling span and structural requirements of line supports. During
erection of the overhead lines, the sags and tensions to be allowed for various spans under will also have to be properly the lines may give long and the ambient
conditions so that
service.
have been devised to determine the sag and tensions. If the flexible conductor, whose weight is distributed uniformly along its length, is suspended rigid supports at the same level between two and is in
equilibrium, conforms
which longer
quite
the span, the greater the degree of conformity. The transmission line conductor is usually
Vol.5 : Page #
subjected
to the following external forces: (i) a horizontal force due to wind pressure,
Vol.5 : Page #
(ii)
vertical
force
due
to
the
dead
weight
of
the
conductor, and (iii) A vertical force due to the deposit of ice conductor (in areas subject to snow fall) If w is the weight of conductor per metre length on the
(including the weight of ice deposit, if any) and p the horizontal force due to the wind pressure acting on the ice-coated conductor per meter length, the
resultant force q on the conductor per unit length is q = ( w + p) and the catenary which lies in the plane of the at
an angle which is given by the equation. p Tan = --w Figure 1.3 represents a span of transmission line
conductor strung between two points of supports A and B at the same elevation. The length, sag and tension catenary
of the conductor are given by the following formulae: L = 2H ---q H ---q H ---q H ---q Sin h + Cos h + Cos h aq ---2H
aq + ---- -1 2H + aq ---2H
T ---q T ---q
b +
with reference to the points of support. L T H = = = length of the conductor in span. tension at either point of support, and horizontal tension at the lowest point O.
Vol.5 : Page #
For spans of the order of 300 meters and characteristics of the conductor
are
sufficient degree of accuracy by the following simpler parabolic formulae, which can be derived by expanding
the hyperbolic functions in the above equations in the forms of a series and neglecting all terms except the first two: L a3q = a + ---24H = aq ---8H aq ---8H + H ---q used case in of
above parabolic formulae are generally and tension calculations except in the
very long spans. 1.4.2 Co-ordination of Sags Back to Contents Page The spacing at required between the ground midspan to ensure that a wires and
conductors
stroke which hits the ground wire does not to the conductor, is referred to as the
lightning
strung
sag
percent)
than
conductor
than at the supports. Certain steps are involved in determining the midspan spacing factors which, while satisfying the requirements of safety under the worst condition and of the tower
Back to Contents Page The initial sag-tension charts give sags and tensions for new ACSR before it has been subjected The final to the
assumed
maximum
loading
stresses.
charts
give sags and tension after the conductors have been stressed conditions, due to the assumed maximum loading
the initial charts. The initial charts are used for determining sags for the use of stringing the conductors in a particular ruling span, determined for a section of line between two dead-end points. The final charts are used determining clearances. They are also used for for
stringing when the conductors are prestressed before or during erection at tensions which will subject them to the same stress they would receive with the assumed maximum loading conditions. An example of using the sag-tension chart for the
circuit
line is given below. The initial sag-tension chart for the conductor is
given in Figure 1.4. Corresponding to the stringing temperature of 32C (on the right corner) and a ruling span of 350 meters on the X-axis, the tension is 4,010 kg. as read off on
the ordinate. Corresponding to this stringing tension and the actual span hand corner of the of 400 meters (on the chart), the sag is top read left as 10
Vol.5 : Page #
Vol.5 : Page #
Vol.5 : Page #
_____________________________________________________________________ _ CHAPTER TWO _____________________________________________________________________ _ DEFINITIONS AND TERMINOLOGY Back to Contents Page Terminology installation for of equipment overhead and procedures associated with the
transmission
line
conductors
varies
widely throughout the utility industry. Therefore, definitions and terminology the have been included used in to this provide manual a correlation industry
between
terminology
and
synonyms. Note that the synonyms are terms that are commonly used, although many are not necessarily good usage not be taken as equivalents to and should
Definitions & Terminology for Conductor Stringing Equipment. AAAC. AAC. Concentric-lay-stranded all aluminum alloy conductor. Concentric-lay-stranded all aluminum conductor.
Aluminum Conductor, Steel Reinforced (ACSR) Back to Contents Page A composite conductor made up of a combination of aluminum and coated steel wires. In the usual construction, the aluminum
wires surround the steel. Aluminum Alloy Conductor, Steel Reinforced (AACSR) Back to Contents Page A composite conductor made up of a combination of aluminum alloy
Vol.5 : Page #
and coated steel wires. In the usual construction, the aluminum wires surround the steel. Aluminum Conductor, Aluminum Alloy Reinforced (ACAR) A composite conductor made up of a combination of aluminum and aluminum alloy wires. In the usual construction, the aluminum wires surround the aluminum alloy. Anchor A device that serves as a reliable support to hold an object firmly in place. The general term "anchor" is normally
associated with cone, plate, screw, or concrete anchors. The terms snub, deadman, and anchor log are usually associated with pole stubs or logs set or buried in the ground to serve as temporary anchors. The latter are often used at pull and
tension sites. Syn: anchor log, deadman, snub. Block Back to Contents Page A device designed with one or more single sheaves, a wood or metal shell, and an attachment hook or shackle. When rope is reeved through two of these devices, the assembly is commonly
referred to as a block and tackle. A set of fours refers to a block and tackle arrangement utilizing two 4 in double sheave blocks to obtain four load-bearing lines. Similarly, a set of fives or a set of sixes refers to the same number of loadbearing lines obtained using two 5 in or two 6 in double sheave blocks, respectively. Syn: Set of fours, set of fives, sixes. (Fig. 2.1, 2.2 & 2.14)
Vol.5 : Page #
set
of
Hold-down block A device designed with one or more single groove sheaves to be placed on the conductor and used as a means of holding it down. This device functions essentially as a traveller used in an
inverted position. It is normally used in midspan to control conductor uplift caused by stringing tensions, or at splicing locations to control the conductor as it is allowed to rise
after splicing is completed. Syn:block, splice release; roller, hold-down; Snatch Block A device normally designed with a single sheave, wood or shell, and hook. One side of the shell usually metal to traveler, hold-down.
opens
eliminate the need for threading of the line. It is commonly used for lifting loads on a single line or as a device to
control the position or direction, or both, of a fall line or pulling line. Syn: Skookum, Washington, Western.
Vol.5 : Page #
Vol.5 : Page #
Bonded The mechanical interconnection of conductive parts to maintain a common electrical potential. Syn: Connected. Bullwheel Back to Contents Page A wheel incorporated as an integral part of a bullwheel puller or tensioner to generate lines, pulling or braking tension on
conductors or pulling
arranged in tandem incorporated in its design. The physical size of the wheels will vary for different designs, but 17 in (43 cm) face widths and diameters of 5 ft. (150 cm) are common. The wheels are power driven or retarded and lined with single or multiple groove neoprene or urethane linings. Friction is
accomplished by reeving the pulling line or conductor around the groove of each pair. Two-Conductor, Three-Conductor, Four-Conductor, Multiconductor Bundle A circuit phase consisting of more than one conductor. Each
conductor of the phase is referred to as a subconductor. A twoconductor bundle has two subconductors per phase. These may be arranged in a vertical or horizontal configuration. Similarly a three-conductor bundle has three subconductors per phase. These usually are arranged in a triangular configuration with the has
bundle
square possible,
other most
configurations
are
common.
Syn:twin-bundle,
tri-bundle, quad-bundle. Strand restraining Clamp An adjustable circular clamp commonly used to keep the
individual strands of a conductor in place and to prevent them from spreading when the conductor is cut. Syn: block, cable
binding; clamp, hose; clamp, plier; grip, vise. Clearance 1 The condition in which a circuit has been deenergized to enable work to be performed more safely. A clearance is normally hazard obtained prior to on a circuit work. presenting Syn: a source of
starting
outage,
permit,
restriction. 2 The minimum separation between supports or two conductors, or between between
and
other the
objects,
and ground or
clear
Back to Contents Page The transferring of sagged conductors from the and the travellers to
installing of the
Syn:Clamping-in, clipping.
Clipping Offset A calculated distance, measured along the conductor conductor from the the
at which
center
Vol.5 : Page #
to
be placed. may
When stringing in
clipping offsets
be required to balance
another, suitable for carrying an electric be, however, bare or Conductor car. insulated.
It may
Back to Contents Page A device designed to carry workmen and ride on sagged bundle conductors, thus enabling them to inspect damage and install spacers and dampers where devices may car, spacer 2.11) Connector rope A special high strength steel link used to join two lengths of end. Although of the be manual or powered. the conductors for required. These
pulling rope by means of the eye splice at each designed to pass the easily puller, through the
grooves
bullwheels on
load. Syn: Peanut. Crossing structure A structure built of poles and, sometimes, rope nets. used whenever conductors are being strung lines, communications is normally circuits, highways, over roads, It is power
or railroads, and
constructed
in such
Vol.5 : Page #
falling onto or into any of these facilities in failure, guard broken pulling structure, lines, loss rider
tension,
H-frame,
structure, temporary structure. Deenergized Free from any electric connection to charge; The a source of potential
current-carrying parts that are sometimes alive To state that a circuit has been circuit has been disconnected it deenergized from could all be
the
electrical
sources.
However,
electrically charged through induction from energized circuits in proximity to it, particularly if the circuits are
parallel. Syn: dead. Dynamometer A device designed to measure loads or tension on conductors. Various models of these devices are used to conductors. Syn: Clock, load cell. (Fig. 2.9) Energized Electrically connected to a source of potential difference, or tension guys or sag
electrically charged so as to have a potential different from that of the ground. Syn: alive, current carrying, hot, live. Equipotential An identical state of electrical potential for two or more items. Explosives
Vol.5 : Page #
instantaneously
products that are mostly gaseous and that occupy much greater volume than the original mixtures. This transformation generates heat, which rapidly expands enormous pressure. Dynamite the gases, causing and Primacord are them to exert as in
explosives
manufactured. Aerex, Triex, and Quadrex are manufactured two components and are not true explosives until
mixed.
Explosives are commonly used to build construction roads, blast holes for anchors, structure footings, etc. Syn: Aerex,
dynamite, fertilizer, power, Primacord, Quadrex, Triex. Conductor grip Back to Contents Page A device designed to permit the pulling of splicing on fittings, eyes, etc. It conductor without
continuous conductor where threading is designs of these grips vary considerably. Klein (Chicago) with opposing conductors,
and Crescent utilize an open-sided rigid body jaws and swing latch. In addition to to pulling
this
in some cases, pull wire rope. The design of the come-along (pocket-book, attached to suitcase, the body four of a bolt, clamp etc.) that incorporates folds to a bail
completely to
envelope the
come-along; Klein;
Crescent;
Kellem;
Vol.5 : Page #
pocketbook; seven bolt; six bolt; slip-grip; suitcase. (Fig. 2.4) Woven wire grip A device designed to permit the temporary joining of conductors without the need Syn: basket; Chinese of or pulling
grips.
sock. (Fig. 2.6 & 2.12) Grounded Connected serves to earth or to some of the earth, extended whether conducting body the connection that is
instead
intentional or accidental.
Vol.5 : Page #
Vol.5 : Page #
surface of the earth. Normally, it is bonded to ground rods driven around and within its perimeter to increase its grounding capabilities and provide convenient connection points for
grounding devices. The primary purpose of the grid is to provide safety for workmen by limiting potential differences within its perimeter to safe levels in case of high currents that could
flow if the circuit being worked became energized for any reason or if an adjacent energized circuit faulted. Metallic surface mats and gratings are sometimes utilized for this same
purpose.
When used, these grids are employed at pull, tension, Syn: counterpoise, ground gradient
and midspan splice sites. mat, ground mat. Personal ground A portable device piece designed of
to
connect or
(bond) to
a an
deenergized electrical
conductor
or
equipment,
both,
become
energized.
Syn:ground
stick;
red head.
driven solid
into
the
ground rod,
terminal,
such
as rod,
a or
rod,
copper
galvanized are
iron
commonly used
during
conductor
stringing
operations
to
provide
means
of
obtaining an electrical ground using portable grounding devices. Syn: ground electrode. Running Ground Back to Contents Page A portable device designed to connect a moving wire conductor or
rope, or both, to an electrical ground. These devices are on the conductor or wire rope adjacent to the sag for
normally placed
pulling and tensioning equipment located at either end of a section. personnel They are primarily used or to provide safety
during
construction
reconstruction
operations.
Syn: ground, moving; ground roller; ground, traveling. (Fig. 2.13). Structure base Ground A portable device designed to connect (bond) a to an electrical ground. It is
rolling; ground,
metal structure
for personnel during construction, reconstruction or maintenance operations. Syn: ground, butt; ground chain; ground,
structure; ground, tower. Traveller ground Back to Contents Page A portable device designed to connect a moving conductor or
wire rope, or both, to an electrical ground. It is primarily used to provide safety for personnel during reconstruction operations. This device is construction placed on or the where
traveler (sheave,
an
electrical
ground
is
required.
Syn:
ground, block;
ground, rolling; ground, sheave. Hoist An apparatus for moving a load by the application force and not including a car or These devices are normally to of a pulling
platform running
in guides.
designed using roller or link chain enable heavy loads to be lifted conductor or
during
during tugger;
puller, drum. Conductor lifting hook A device resembling an open boxing glove designed the lifting of conductors from a to permit It is
Syn:
conductor Isolated i)
from
all sources of electrical energy. Such separation may not eliminate the effects of ii) An object that is not electrical induction. readily accessible to persons
unless special means for access are used. Compression joint Back to Contents Page A tubular compression fitting designed and fabricated from
Vol.5 : Page #
aluminum,
copper,
or
steel
to
join
conductors
or
overhead
or mechanical presses. However, in some cases, automatic, wedge, and explosive-type joints are utilized. Syn:Conductor splice,
sleeve, splice.
Protector joint Back to Contents Page A split sleeve that fits over a conductor compression if joint
or damage
the joint
must pass through travellers. The joint protector usually has split rubber from Jumper i) The conductor that connects the conductors on opposite collars at each end to protect the conductor
sides of a deadend structure. Syn: Deadend loop. ii) A conductor placed across the clear space between the ends of two conductors or metal pulling lines that are being spliced together. Its purpose, then, is to act as a shunt to prevent workers from accidentally placing themselves in series between the two conductors. Tower ladder A ladder complete with hooks and safety chains attached to one end of the side rails. These units are normally fabricated from fiberglass, wood, or metal. The ladder is suspended from the arm or bridge of a structure to enable workers to work at the
Vol.5 : Page #
conductor operations,
level, etc.
to
hang
travellers,
perform are
a string
to their intended position on a structure. Syn:Insulator saddle, potty seat. Bull line A high-strength line normally synthetic fiber rope, used for
pulling and hoisting large loads. Syn: Bull rope; line pulling; line, threading. Finger line A lightweight line, normally sisal, manila, or synthetic fiber
rope, that is placed over the traveller when it is hung. It usually extends from the ground and passes through the
the need for workmen on the structure. These lines required if pilot lines are installed when the
Syn:
Finger rope.
to the
pull heavier pilot wire that, in conductor. finger Pilot or ropes by may
lines
helicopter Syn:
travellers
are
hung.
Vol.5 : Page #
P-line. Pilot wire / Pulling line Back to Contents Page A high-strength line, normally wire rope, used conductor. However, on reconstruction jobs in to pull the which a
conductor is being
the pilot wire for the new conductor. In such cases, the old conductor must be closely examined for any damage prior to the pulling operations. Syn: Line, bull; line, hard; line, light; line, sock; pulling rope. Safety / life line A safety device normally constructed from synthetic fiber rope and designed to be connected between a fixed object and the body belt of a worker working in an elevated position when his/her
regular safety strap cannot be utilized. Syn: Line, life; line, safety; scare rope. Tag line A control line, normally manila or synthetic fiber rope,
attached to a suspended load to enable a worker to control its movement. Syn: Tag rope. Threading line A lightweight flexible line, normally manila or synthetic
fiber rope, used to lead a conductor through the bullwheels of a tensioner or pulling line through a bull wheel puller. Syn:
rigid
pilot
wires
and relieve
Bullet,
Swivel link A swivel device designed to connect pilot wires and conductors together in series or to connect one pulling line to the drawbar of a pulling vehicle. The device will spin and help relieve the torsional forces that build up in the line or conductor under tension. Syn: Swivel. OPGW Concentric-lay-stranded composite conductor for use as groundwire with telecommunication constructed with a helically laid central optical capability. fiber core overhead
aluminum-clad
wires,
aluminum
wires,
galvanized steel wires, or combinations thereof. Overhead Groundwire (OHGW) (Lightning Protection) Multiple for grounded wire or wires placed intercepting above phase conductors
the purpose of
Aerial Platform A device designed to be attached to the boom tip of a crane aerial lift and support a worker in an elevated or
working
position. Platforms may be constructed with surrounding railings that are fabricated from aluminum, steel, or fiber reinforced plastic. Occasionally, a platform is suspended from the load
Vol.5 : Page #
structure, or both, to serve as workers insulator engaged work, Some in etc. deadending The
designs short
considerably. resemble as 40
resemble
cantilever
others
swimming (12 m)
pool diving boards, and still others as long are truss structures resembling wood, bridges.
ft.
fiberglass,
platform, diving board. Plumb mark A mark placed on the conductor located vertically below the and vertically for wood pole of
insulator point of support for steel structures above the pole center structures the used as line at ground to level
a reference
suspension clamp.
Bullwheel Puller Back to Contents Page A device designed to pull pulling lines and operations. It normally conductors during one or more
stringing
incorporates
pairs of urethane or
neoprene-lined, in
the pulling line that is reeved around the grooves of a of the bullwheels. The own engine, which puller drives is the
pair
hydraulically, or through a combination of both. devices Syn: function as either a puller or tensioner.
Puller.
operations. It is normally equipped with its own engine, which drives the drum mechanically, hydraulically, or through a
combination of both. It may be equipped with synthetic fiber rope or wire rope to be used as the pulling line. The pulling line is payed out from the unit, pulled through the travellers
in the sag section, and attached to the conductor. The conductor is then pulled in by winding the pulling line back onto the drum. This unit is sometimes used with acting as a pilot line to pull canyons, rivers, etc. synthetic fiber rope
winch, single drum. Reel puller A device designed to pull a conductor during stringing which
operations. It is normally equipped with its own engine, drives the supporting shaft for the reel
hydraulically, or through a combination of both. turn, drives the reel. The application of
essentially the
same as
Some of
Vol.5 : Page #
these
Two drum, Three drum Puller The definition and application for this unit is essentially in that this
the same as that for the drum puller. It differs unit is equipped with two or three drums
one, two, or three conductors individually or simultaneously. Syn: Hoist, double drum; hoist, triple drum; winch, double drum; winch, three drum; winch, triple drum; Pulling vehicle Any piece of mobile ground equipment capable of pulling pilot lines, pulling lines, or conductors. However, helicopters may be considered purpose. as a pulling vehicle when utilized for the same winch, two drum; tugger.
Reel Stand Back to Contents Page A device designed to support one or more conductor or groundwire reel having the possibility of being skid,trailer, or truck
mounted. These devices may accommodate rope or conductor reels of varying sizes and are usually equipped with reel brakes to
prevent the reels from turning when pulling is stopped. They are used for either slack or tension stringing. The designation reel trailer or reel has been equipped reel transport truck implies that of
with or
a reel stand (jacks) and may serve as a payout unit, or both, for stringing crane,
the reel to be
from single-axle
with trailers
Ruling Span A calculated span length that will have the same changes in conductor tension due to changes of temperature and conductor loading as will be found in a series of spans of varying lengths between deadends. Running Board Back to Contents Page A pulling device designed to permit stringing conductor simultaneously with a single more than line. one For
pulling
distribution stringing, it is usually made of lightweight tubing with the forward transition stringing, transversely over the end pole curved gently upward to provide smooth
crossarm
rollers.
For
transmission hinged
sections a
rigid design, both having a from the rear. from twisting This together
configuration stops
sheaves of bundle travellers. Syn: Alligator, bird, equilizer pully, monkey tail, sled. (Fig. 2.7) Sag The distance measured vertically from a conductor
to
the
Vol.5 : Page #
straight line joining two points of support. Unless otherwise stated, the sag referred to Sag Section The section of line between snub structures. More than one sag section may be required in order to sag properly the actual length of conductor that has been strung. Syn: Pull setting, stringing section. Sag Span A span selected within a sag section and used as a control to establishing is at the midpoint of the span.
conductor level and tension. A minimum of two, but are required within a sag section in
properly. In mountainous terrain or where span radically, more than three sag spans could be
Vol.5 : Page #
Vol.5 : Page #
Self-damping Conductor (SDC) ACSR that is designed to control aeolian vibration by integral damping. Trapezoidal aluminum wires and annular gaps are
utilized. (Fig.2.3) Shaped wire compact Conductor(TW) ACSR or AAC that is designed to increase the aluminum area for a given diameter of conductor by the use aluminum wires. Sheave 1) The grooved are wheel of a traveller referred to or as rigging sheaves. block. Syn: of trapezoidal shaped
Travelers
frequently
Pulley, roller, wheel, traveller. 2) A shaft-mounted wheel used to transmit a belt, chain, band, etc. Pull Site The location on the line where the puller, reel winder, and anchors (snubs) are located. This site may also serve as the power by means of
pull or tension site for the next sag section. Syn: Reel setup, tugger setup. Tension Site The location on the line where the tensioner, reel stands, and anchors (snubs) are located. pull or tension payout site for This the site may next also serve as the section. Syn:
sag
Conductor
and considered
as a zero point for sagging and clipping offset calculations. The section of line between two such structures is the sag
section, but more than one sag section may be required in order to sag strung. properly the actual length of conductor that has been Syn: O structure, zero structure.
Wire rope Splice The point at which of two wire ropes are joined wire together. ropes The
various include
methods hand
joining woven
(splicing) splices,
together that
tucked
compression
splices
utilize compression fittings but do not incorporate loops (eyes) in the ends of the ropes, and mechanical splices that are made through the use of loops (eyes) in the ends of the ropes held in place by either compression fittings or wire rope clips. The latter are joined together with connector links or steel bobs and, in some cases, are rigged often eye to eye. Woven splices are splice varies in
length from 7 to 17 ft. (2 to 5 m) for 0.25 to 1.5 in (6 mm) diameter ropes, respectively, from 15 to 45 ft. (4 to 14 m) Splicing Cart A unit that is equipped with a hydraulic compressor (press) all other necessary on equipment Syn: for Sleeving performing trailer, while
to 38
and
splicing splicing
operations
conductor.
trailer, splicing truck. Steel Supported Aluminum Conductor (SSAC) ACSR with the aluminum wires annealed.
Vol.5 : Page #
Step Voltage The potential difference between two points on the to earth's be 1
gradient. current
This flows
potential
could
dangerous
particularly under fault conditions. Syn: Step Potential. Stringing The pulling of pilot lines, pulling lines, and travellers supported on structures of conductors over
overhead
transmission
lines. Quite often, the entire job of stringing conductors is referred to as stringing operations, beginning with the planning phase and terminating after the conductors have been in the suspension clamps. Slack Stringing The method of stringing conductor slack without the use of a installed
tensioner. The conductor is pulled off the reel by a pulling vehicle and is dragged carried along the line along on the ground, or the reel is
deposited on the ground. As the conductor is dragged to, or past, each supporting structure, the conductor is placed in
the travelers, normally with the aid of finger lines. Tension stringing The use of pullers and tensioners to keep the conductor under
tension and positive control during the stringing phase, thus keeping it clear of the earth and other obstacles that could
Vol.5 : Page #
cause damage. Switching Surge A transient wave of overvoltage in an electrical circuit caused
by a switching operation. When this occurs, a momentary voltage surge could be induced in a circuit adjacent and parallel the switched circuit in excess of the voltage during steady state conditions. If the induced to
normally is
adjacent
circuit be
operations should
minimized
is
placed on one structure of the sag span. The sagger, on the other structure of the sag span, can use it as a reference to
determine the proper conductor sag. Syn: Sag board,target Bullwheel Tensioner Back to Contents Page A device designed to hold tension against a pulling line or
conductor during the stringing phase. Normally, it consists of one or more pairs of single arranged generated grooves of or in urethane or neoprenelined, power-braked,
around
tensioners
equipped with their own engines, which retard the bullwheels mechanically, hydraulically, or through Some of these devices function as a combination of both. either a puller or
Vol.5 : Page #
tensioner. type
Other
tensioners
are
only
equipped
with
friction
retardation.
Touch Voltage The potential difference between a grounded metallic structure and a point on the earth's surface separated by a distance equal to the normal maximum horizontal reach, approximately 3 ft. (1 m). This potential difference could be dangerous and could
result from induction or fault conditions, or both. Syn: Touch Potential. Transit An instrument primarily used during construction of a line survey the route, to set hubs and locations, to plumb for locations of sag conductors. Traveller Back to Contents Page A or sheave complete with suspension arm or frame in groups and suspended from structures used separately to permit the point on tangent to
(POT)
anchors at the pull and tension sites, and to Syn: Level, scope, site marker.
conductors sheaves
urethane. or cushion
Vol.5 : Page #
passes
over
the sheave. in
with
electrical ground.
block, stringing sheave, stringing traveller. (Fig. 2.8) Traveller Sling A sling of wire to rope, support it sometimes the is utilized in place of
during insulators
Normally, or
available
when
adverse
might impose severe downstrains and failure of the insulators. Uplift roller
cause damage
Syn: Choker.
Back to Contents Page A small single-grooved above wheel designed to fit in or the
immediately
traveller
and keep
Vol.5 : Page #
Vol.5 : Page #
Reel winder A device designed to serve as a recovery unit for a pulling line. It is normally equipped with its own engine, which drives
a supporting shaft for a reel mechanically, hydraulically, or through a combination of both. The shaft, in turn, drives the reel. It is normally used to rewind a pulling line as it stringing a puller, operations. but This
sometimes
serves this functions where only low tensions are involved. Syn: Takeup Reel.
Vol.5 : Page #
Vol.5 : Page #
Vol.5 : Page #
_____________________________________________________________________ _ CHAPTER THREE _____________________________________________________________________ _ Stringing Methods & General Aspects Back to Contents Page 3.1
Methods of stringing. Back to Contents Page There are basically two methods of stringing. These are i) ii) Slack or Manual methods Tension method
3.1.1
Manual method : Back to Contents Page Using this method, the conductor is pulled along the ground by means of a pulling vehicle,or the drum is carried along the line on a vehicle and the conductor is deposited on the ground. The conductor drums are positioned on drum stands or jacks, either placed on the ground or mounted on a transporting vehicle. These stands are designed to support the drum on an arbor,
thus permitting it to turn as the conductor is pulled out. Usually, a braking device is provided to
prevent overrunning and backlash. When the is dragged past a supporting structure, and the conductor is placed
conductor pulling is
stopped
in
travelers
Vol.5 : Page #
attached
to
the
next structure. This method is chiefly applicable to the construction of new lines in cases in which maintenance of
where
terrain is easily accessible to a pulling vehicle. The method is not usually economically applicable in urban locations where hazards exist from traffic or where
there is danger of contact with energized circuits, nor it is practical in mountainous regions
inaccessible to pulling vehicles. 3.1.2 Tension Method : Back to Contents Page Using this method, the conductor is kept under
tension during the stringing process. Normally, this method ground surface is and used to keep the which of conductor might clear of the
obstacles, and
cause
conductor It
damage
clear
energized
circuits.
requires the pulling of a light pilot line into the travelers, which in turn is used to pull in a heavier pulling line. The pulling line is then used to pull
in the conductors from the drum stands using specially designed tensioners and pullers. For lighter
conductors, a lightweight pulling line may be used in place of the pilot line to directly pull in the
to Where
pull or lay out a pilot line or pulling line. a helicopter is used to pull out a line, line
to the helicopter and prevent the pulling or pilot line from flipping into the rotor blades upon release. The tension method of stringing is applicable where it is desired to keep minimize surface the conductor off or in areas the ground to where frequent
damage
crossings are encountered. The amount of right-of-way travel this by heavy equipment is also reduced. method provides the most economical conductor. The in helicopter rugged or Usually, means use of is
stringing particularly
advantageous
poorly
accessible terrain. 3.2 Grounding during stringing Back to Contents Page 3.2.1 Introduction : Back to Contents Page For any given situation, the bonding together of equipment and electrical grounds in a common array of major importance. However, such bonding offers assurance between that a hazardous potential will not the bonded items and the earth. all is no
exist It is
impractical
around available fault currents or calculated effects. Such a design would require precise knowledge of
Vol.5 : Page #
many
variables
and
would
result
in
different
grounding scheme for each location. The degree of grounding protection is required for a
given
construction
project
dependent
upon
the
exposure to electrical hazards that exist within the project area. For a project remote from other lines
and at a time of low probable thunderstorm activity, minimal grounding requirements are in order. Minimum grounding requirements include bonding and grounding of all machines involved in stringing of the
conductor,
running grounds should be installed on all lines in front of the pulling and
equipment. On the contrary, for a project in congested area with exposure to numerous and parallel lines of and crossing
situations, activity
with probability
thunderstorm extensive
conditions,
grounding requirements are called for. the most significant hazard results
proximity to energized lines. Under any circumstance, in addition to open jumpers, measures must be grounding employed and to other ensure
protective
reasonable and adequate protection to all personnel. In addition to the grounding system, the best
safety precaution is to respect all equipment as if it could become energized. The degree of protection
Vol.5 : Page #
provided for a specific project must be a decision of project supervision of 3.2.2 based on a clear understanding
Source of Hazards : Back to Contents Page Electrical charges may appear on a line due to one or more of the following factors. i) Charges induced on the line by a
caused between
flashover
the
neighboring
Grounding procedure : Back to Contents Page Grounding cables must be connected to the ground
source first, then to the object being grounded. When removing grounds, the ground must be removed from the grounded object first and then from the ground source. The object being grounded should not be teased with the ground clamp. The clamp must be poised by the
tightened.
If an arc is drawn, the clamp should not be withdrawn, but should be kept on the conductor, thus grounding the line. 3.3 Communications Back to Contents Page 3.3.1 Slack stringing requires a minimum of communications. It is, however, desirable to have communication the
between the pulling vehicle and the personnel at drum location. 3.3.2 Tension stringing requires good
communications
between the personnel at the tensioner end and those at the puller end and at intermediate check points
at all times during the stringing operation. During the stringing of bundled conductors with a running
board, it
as it passes through
board observer(s) should have reliable communications with both pulling and tensioning ends. When following the board from the ground is not practical, this can
be accomplished with the aid of helicopters. 3.3.3 During helicopter reliable stringing of the pilot all line or
conductor,
ground
dedicated single-use frequency, should be available in case one system fails, particularly during the actual
Vol.5 : Page #
stringing operation. 3.4 Special requirements for mobile equipment : Back to Contents Page 3.4.1 Drum or reel Stand. Back to Contents Page Drum stands are designed to be used with tensioners to supply the necessary back tension to the conductor.
The stand(s) are selected to accommodate the conductor (or groundwire) reel dimensions and gross weight.
Some drums are not designed to withstand the forces developed by braking during tension stringing at be
operations. Direct tension stringing from the drum transmission line stringing tensions should not
attempted. The conductor may be pulled directly the drum stand when employing slack stringing If the drum stand is not self loading,
from
methods. a crane,
forklift, or other suitable equipment is used to load the drum into the stand. 3.4.2 Tensioner Bullwheel Characteristics. Back to Contents Page The depth, Dg, and flare of grooves in the bullwheels are not critical. Semicircular grooves with depths in the order of 0.5 or more times the conductor diameter and with flare angles in the order of 5 to 15 the vertical generally have been found to from be
satisfactory.
Vol.5 : Page #
The
number
of to
grooves prevent
in
the outer
bullwheel layer of
must wires
be of
sufficient multilayer
the from
conductors
slipping the
over
underlying of the
bottom
grooves, Db, should be 30 to 40 times the diameter of conductor. Details are shown in fig - 3.1. Tandem bullwheels offset spacing. direction should be will be should be so aligned one-half a that the the
approximately
groove
wires,
arranged of pull,
that,
when
facing will
direction
conductor
enter
bullwheel on the left and pull off from the right side as shown in left fig. 3.1. For any conductors having a
hand direction
conductor should enter on the right and pull off from the left. This arrangement is necessary to avoid any
tendency to loosen the outer layer of strands as the conductor passes over the bullwheels. Similarly
stranded conductor or wire should be wound on a drum according to the lay and direction of travel. Note
the convenient thumb rule as shown in Fig.3.2.Clench the hand into a fist, with the thumb and index finger Use the right hand for right lay and for the of left barrel pull off. lay. and The The the clenched index the
represent direction
finger to
thumb
points
Vol.5 : Page #
proper
attachment site.
Vol.5 : Page #
such
not to mar the surface of the conductor. Elastlined grooves but are are recommended for all for
conductors, nonspecular
particularly Should a
important
conductors.
semiconducting
elastomer be used for lining the grooves, it should not be relied Difficulties upon for grounding. have been experienced with single V-
groove type bullwheels on some multilayer and special construction should only conductors. These types be used with the of bullwheels of the
concurrence
conductor manufacturer. 3.4.3 Puller and tensioner operating characteristics. Back to Contents Page The pulling and braking systems should operate or be a
smoothly and should not cause any sudden jerking bouncing of the conductor. Each system should
maintaining
Vol.5 : Page #
Vol.5 : Page #
Vol.5 : Page #
Pullers and tensioners may be mounted separately or in groups controls for bundled conductor installation. The of
tension in each conductor. It is recommended that the tensioner bullwheels bundled have for an each independently subconductor operated when set of
subconductors per phase are being installed. should be equipped with load indicating and
Pullers limiting
devices. The load limiting device should automatically stop the puller from acting further if a preset be
maximum load has been exceeded. Tensioners should equipped with tension indicating devices. Capacity dependent selection upon of the puller and tensioner to
is be
strung, and the stringing tensions. The capacities of the puller and span tensioner should be length, terrain, based and on the
general, sag
tensions.
tensions should never be exceeded during stringing. There are basically two types of pulling machines
used in the construction of transmission lines being strung under tension. These are defined as bullwheel and reel drum type or reel type pullers. Some drum-type or type pullers are available with level wind
Vol.5 : Page #
features to provide uniform winding of the line. Some drum-type and all reel-type pullers provide easy
removal of the drum (or reel) and line to highway mobility. This feature also
facilitate the
provides
advantage of interchangeability of drums. The control of payout tension of the pulling line is a desirable and
feature of many pullers. Mobility of the pullers tensioners is important to minimize downtime pulls. Also critical are the setup and
between leveling
features of the units. 3.5 Travelers Back to Contents Page 3.5.1 Diameter. diameters are gained: (i) The radius bending of the conductor is increased, so the amount of strain between and the amount wires of in It is generally recognized that as are made larger, the following sheave
advantages
relative
movement
individual
the conductor are reduced. This, in turn, reduces the amount of energy required to bend and
straighten the conductor as it passes through the travelers. The such bending force and and energy required for regards the
straightening
passage of the conductor in much the same way as friction in the bearing of the travelers. (ii) The bearing pressures between conductor strand
Vol.5 : Page #
layers
are
reduced,
thus
reducing damage.
potential This is
conductor
internal
strand
commonly known as
strand notching.
(iii)The force required to overcome friction in the bearings is reduced because of the greater moment arm for turning. (iv) The number of rotations and speed of rotation grooves
The obvious disadvantages of larger sheaves are cost and added weight. The minimum sheave diameter, Ds, at the bottom of the groove, as for shown in Fig 3.3, should be
satisfactory
typical
conductor
stringing
stringing conductors in
excess of approximately 3km or over substantially uneven terrain, the recommended minimum bottom Dc-4) Dc inches for
stands
diameter.
arduous times
circumstances,
accurate
some
be very difficult with sheaves having diameters of less than 19 Dc or 20 Dc. 3.5.2 Configuration of Groove. The minimum radius at the base of the groove, Rg, recommended to be 1.10 times the radius of is the
Vol.5 : Page #
conductor as shown in Fig 3.3. Sheaves may, having with a groove radius as be used discussed with above smaller
limitations,
conductors.
Vol.5 : Page #
Vol.5 : Page #
the diameter of the conductor. The sides of the groove should flare between 12 and 20 form the vertical to facilitate the passage of swivels, grips etc., and to contain the conductor within the groove, particularly at line angles. 3.5.3 Bearings. The bearings should preferably be ball or roller type with adequate provisions for lubrication and must
be suitable for the temperature range involved; and, where sealed bearings are not used, care should be taken to ensure subsequent lubrication with the same type of grease. Mixing of greases of different types (that is, lithium base and calcium base) may cause of the lubricant and subsequent bearing
Bearings should have sufficient capacity to running or static loads without damage.
Proper maintenance is essential. 3.5.4 Material and Construction. Travelers may be of any suitable material, with given to weight. conductors Unlined should sheaves be made due for of
aluminum
should
recommended other
ensure that the manufacturer's safe working load the traveler is not exceeded. This is
important for situations in which travelers are on heavy line angles or on the first or last
at which the conductor comes to ground level. Maximum loads usually will result when the conductor
is being pulled up to sag tensions. It is recommended that clearances between the sheave (s) and frame, particularly in the traveler throat
area, be kept as small as possible. This will prevent the pilot line from jamming should the come out of the pulling line pilot line It is
sheave.
recommended stringing
that the vertical throat opening of the block be kept as small as possible while
still allowing the safe passage of the pulling line, swivels, and the running board. This practice need to will be
minimize the
distance
the conductors
lifted during the clipping-in operation. For bundle conductor configurations, the traveler that the
frame and shaft should be sufficiently sized so deflection due to load, particularly during
sagging operation, does not cause adjacent sheaves to contact. Excessive deflection can cause difficulty
with
elastomer provides cushioning to increase bearing area and precludes damage to the conductor from scratched or marred to groove scratch surfaces. or mar Steel the pulling surface lines or are
likely
unlined in
grooves; therefore, when such lines are to be used the same groove as conductor, grooves
definitely all
sheaves be lined. It is recommended that the total surface of the groove, including lined The to give maximum elastomer used protection for sheave the to top lip, be
linings
capable of withstanding all anticipated without becoming brittle or developing flat areas. It should be
sufficiently
prevent
the groove. 3.5.6 Electrical Characteristics. Neither lined nor unlined travelers should be on for grounding the conductor being relied
installed.
Greased bearings do not provide necessary conductivity and may be damaged by relatively small currents
passing from the sheave to the body of the traveler. Semiconductive linings, commonly referred to as
conductive linings, tested to date are reported burned with currents as low as 20 mA.
Vol.5 : Page #
The
induced
electrical
charges when
on
conductor in
and the
pulling
lines,
particularly
stringing
proximity of energized lines, must be with traveler grounds that bypass the
greased bearings, or both. Traveler grounds provide a means to bypass electrically the sheaves and ground the conductor directly to a ground source. After grounding device has experienced fault current, any it
3.5.7
Bundled Configurations. Bundle conductor type travelers for stringing two more subconductors When simultaneously even numbers require of or
special are
considerations.
conductors
strung, a symmetrical arrangement may be used with an equal pulling number line. of An conductors on each center side of the is
independent
sheave
provided only
for the pulling line and should be of to withstand the abrasion of the
strung,
the
center one could follow the pulling line in the center sheave. However, this is usually not desirable because of by the
Offset-type bundle
conductor travelers are used that balance the load by properly conductors spacing on the even side and of the odd number(s) of
each
pulling
force. color-
orientation. When multiple type between even conductors are strung reduced result light in in bundled
conductor spacing
oscillation, severe to
crosswind, sagging.
permit
satisfactory 5.4
spacing of of
conductor in a
diameters crosswind
sagging
conductors
condition that
diameters
conductor oscillation.)
When stringing multiple conductors around line angles in excess of 5, bundle conductor travelers are the
until the running board passes through but should be replaced prior travelers to provide to
sagging wire
single-type
proper
It is spacing
desirable of the to
spacing
aid in preventing subconductor sag mismatch. Some bundle conductor travelers may be converted to
Multisheave running
bundle
conductor
type
travelers complement
and each
to line up the conductors with an anchor running boards should be not pulled
sideways.) load
Running
working
displayed.
and swivel links be proof tested to 50% over the safe working speeds load. During stringing, normal running pulling board
approaches a traveler. 3.5.8 Helicopter Travelers. Helicopter guide the travelers utilize outrigger arms of that the
area
brightly SpringFor be
bundle conductor travelers, additional guides may utilized to funnel the lines into the proper The that during design of helicopter travelers should are not required on the After
groove. be such
personnel
structure initial
placement of the line by helicopter, normal stringing practices are employed. Helicopter travelers are directional, and care
Vol.5 : Page #
must
be
exercised
to
orient
them
properly
on
the
structures. if the
Due to the rotor wash of the helicopter , attachment method of travelers does not
travelers
may
be
converted
to
helicopter type by the addition of accessory parts. 3.5.9 Uplift Rollers and Hold-Down Blocks. Uplift rollers that attach to the traveler or hold-
down blocks that are separate devices must be used at positions where uplift might occur. Uplift can occur
with the pulling line during the stringing operation, due to its higher tension to weight ratio and, much occur points rollers uplift flatter sag. in of hilly the thus, to low
pull.
Hold-down
blocks
should
condition
arrive, to
hold-down
blocks the
that
the arrival of
without stopping the pulling should be used. devices that directional, pulling breakaway pulling attach to bundle travelers are and are usually positioned should of
towards have of
end. feature
These in the
devices event
fouling
Vol.5 : Page #
Vol.5 : Page #
_____________________________________________________________________ _ CHAPTER FOUR _____________________________________________________________________ _ STRINGING PROCEDURE Back to Contents Page 4.1
Steps of stringing : Back to Contents Page The stringing procedure is broadly divided into the
following steps. i) ii) Paying out & stringing of earth wire. Paying out & stringing of conductor.
iii) Final sagging of earthwire & conductor. iv) v) 4.2 Regulation. Clipping and fixing of accessories.
4.2.1
Paying out of earthwire Back to Contents Page Normally stringing of earthwire is done manually
provided towers
the
suspension earthwire
from
friction. during
This
will
ensure operation
correct to be
sag
as
measured
sagging to may be
available A to
and whistle. is
the starting end of a section, earthwire reel on roller jacks or horizontal turn
mounted
table. manually
tractor. After reaching the next tower is passed through the suspended
polypropylene
paying out is continued further. Care should that the earthwire is not pulled over
After one length of earthwire reel is exhausted, second section. length of wire is paid out for the
the
balance
compressed
on the ground joining the two lengths. 4.2.2 Jointing of earthwire : Back to Contents Page Midspan joints for earthwire consists of a galvanised MS tube with internal diameter matching with sleeve plugs as the is a
outer
provided
Vol.5 : Page #
Relevant approved
drawings are referred for the details. The aluminium sleeve and one plug are first inserted and The the the the
through one end of the earthwire. The other plug steel cutting earthwire edge. The sleeve are inserted to the other end.
of the earthwire is done after gripping with binding wire say 25 mm away from binding wire shall be removed after
edge is inserted into the tube. The cut edge of the wire shall be free from burring of edges. The ends of the wires are inserted into the sleeve equal in length from both sides. This can by marking half the length of the be ensured
with the help of a hydraulic compressor using suitable sized dies to a compression of 100 T/sqare inch. The
compression should start from the centre of the tube and continued the progressively outwards. & After cross checked by the
elongation
recommended
manufacturer. All sharp edges on the surface of the joint shall filed off and smoothened. The aluminum sleeve be is
passed over steel portion and end plugs are at both ends. The compression is done with
Vol.5 : Page #
inserted suitable
size
dies
similarly as explained
above
for
steel
portion cross
and the surface is smoothened and length & section of the compressed joint verified with
cone and earthwire jumper cones. In case any crack in any one of the 7 strands is observed, a joint be provided. Any sharp kink in the earthwire should should
be cut and joined with a midspan joint. 4.2.3 Sagging and final tensioning Back to Contents Page After paying out the earthwire over the length of the section, one end of the earthwire is connected to the earth cone. From the tension tower on the other side of the peak of the tower with compressed dead end
to a rough
tension at
less than final tension. By holding the earthwire this tension on the ground, bolted come-along
clamps 60
mtrs (depending on the rough sag condition and height of tower this may be varied) from the sagging tower. The come-along clamp is connected with 10 dia steel wire rope through a set of or two 12mm sheave of to
pulleys and the wire rope is passed through a set single sheave pulleys along the body of the tower
Vol.5 : Page #
hand
of
the
tower. The earthwire is tensioned by pulling the wire rope initially by a Tractor until approximate sag achieved. Finally, the rope is pulled through is the The
free end of the earthwire hanging from the come-along clamp is picked up and passed through a pulley placed on the earthwire peak of the tower. The wire free end is pulled along the catenary rope from the come-along clamp to curve the of
earth
peak making provision for the length of tension clamp with dead end cone. This point is marked of the by an
adhesive
tape/wire
and
wire
is brought down. The earthwire is cut at the marking and the dead end cone is compressed. The compressed cone is hoisted to the earthwire rope peak by
passed
through
hand winch is further tightened to pull up earthwire length to cone facilitate bolting of winch
some the is
tension released
come-along
clamps are removed. Suitable adjustment in the aerial roller can difference board be done to equalize the length or can be considered while measuring the any sag
placement
conductor
can
be
Back to Contents Page After to be final sagging is completed, the earthwire transferred from the aerial rollers on has the
suspension towers to the earthwire suspension clamps. The point where the earthwire touches the the aerial
roller
pulley
suspension
clamp in correct vertical position. The earthwire is lifted from roller by means of a of
ratchet
peak
the tower and roller is removed. The earthwire is fixed to the tower body by D shackle and then centre marked of the earthwire clamp is matched of the earthwire. The saddle with of
point
clamp is tightened with U bolts. The lever released to let the earthwire freely hang
hoist in
suspension
earthwire peak to the saddle where earthwire finally rests should be equal to the length of the aerial
roller from cotter of earthwire peak to the top side groove of the pulley wheel. 4.2.5 Fixing of hardware accessories
Vol.5 : Page #
Back to Contents Page Earthwire vibration on either the distance is adopted is provided The with stock bridge be type fixed
dampers.
no. of dampers to
side of the tension/suspension tower and from the suspension clamp/tension as per the manufacturer's span length. The cone
depending fixing
upon
of vibration
dampers
should be
immediately after fixing of suspension clamps. Flexible copper bonds are provided to connect the
conductivity FCB is
earth. For each suspension/tension clamp one provided. As copper bond is theft prone, it
better if this is fixed just before charging of line. At of tension towers, the tension clamps on both earthwire peak are joined by an earthwire at both ends by galvanised the continuity of jumper the sides jumper, cone
compressed for
maintaining
earthwire
between the two substations. The length of the earthwire reels normally in
manufactured
normal sections, midspan joints are used in reaches exceeding sections earthwire restringing 2000 for mtrs major length. rivers, But the in river crossing joint in
midspan
Vol.5 : Page #
4.3.1
Guying of Towers Back to Contents Page Before where commencement of stringing, the the stringing is to be started angle have towers to be
phases.
The guys used generally are 20mm steel wire rope. The guys cross are arms attached to the tower at the tip of the
strain
plates with suitable D shackles. The guys are anchored in the ground at an angle of 45 degrees end or less from the horizon, attached For making dead end anchors to in dead the
anchors.
ground, pits of 1.5mx0.6m, for a depth of 1.5m can be dug. fig.4.1 A set of steel beam and channels as tied in the centre with 16mm wire shown rope, in is
compacting. wire
The guy wire is attached to the dead end anchor with the help of turn buckles of 10 tonnes Alternately, dead instead of burried ground
capacity. anchors, a on
the ground and sag wire attached to them securely. After pulling up the slackness in the guy, it is
Vol.5 : Page #
tightened by the turn buckle. Excessive tightening of the guy should be avoided. It is advisable to tighten the guy progressively at the time of rough sagging of the conductor. 4.3.2 Insulator hoisting : Back to Contents Page 4.3.2.1 Transportation of Insulators The required no. of insulators shall be to the tower locations In transported
packing
avoid
during transport. The crates shall be opened at the tower location. The Insulator hoisting of is done well out in advance of Hence, of
commencement
paying
operation.
Vol.5 : Page #
Vol.5 : Page #
In 400 KV S.C
we use V strings consisting of 2 strings of 90 KN insulators suspended from both ends of the joined in the strings 400KV For centre by Yoke plate. bridge and Recently, V used in
for all the three phases are being single and double circuit suspension
is
All the insulator strings consist of 23 no. of in series. At major river crossings for
suspension utilised
towers
for reasons of more safety. 4.3.2.2 Hoisting After opening of the crates, insulators shall be laid in series, on wooden planks below the suspension with grease water and or
points.
oil. Insulators shall be checked for any chipping crack and shall be replaced with new one if
found string be 6
shall be joined and `R' clips in the clevis shall expanded to avoid slippage of the pin. 4 to
insulators are generally joined at the works and packed in a crate. The
manufacturer's of all be to
joints
insulators should be checked and `R' clips should expanded. If any `R' clip is missing, the same is
Vol.5 : Page #
be made good. The hardware of the string on the tower side by is assembled and joined to the first ball eye. The details of hardware insulator for
fitting The
insulator is joined to the twin moose aerial The 3 wheels of the aerial rollers should be for free running. The neoprene rubber cushion on the outer
rollers shall
As mentioned earlier the position of the conductor in the centre of suspension clamp of the fitting shall
grooves. of
Vol.5 : Page #
Vol.5 : Page #
A single sheave pulley is fixed to the cross arm very near to the suspension hanger. A 20 mm passed brought firmly complete through the pulley and polypropylene rope both the ends rope is are is The by of
to the ground. One end of the tied below the 3rd or 4th
insulator. up
pulling the rope through a pulley attached to one the shows tower the legs by using hoisting After to the of tractor/manually. insulators the top with the and
Fig.4.3 tension is is
fittings. attached
reaching
string string
suspension
hanger
released slowly to hang free. In hoisting the V string for centre phase, the method is in general same but 2 pulleys are to be attached rope string the the both plate
near the suspension point of the V string and a is away waist the attached from to pull side ways and keep the tower until it is clear the of
string, yoke
and the aerial roller is suspended from the centre of the yoke plate.
Vol.5 : Page #
Vol.5 : Page #
4.3.3
Paying out of pilot wire Back to Contents Page In tension stringing, a pilot wire is used the conductor. The pilot wire is to pull laid
initially
through the centre wheel of the aerial roller. A 12 mm dia pilot wire is generally used for of laid pulling be wire the
twin moose ACSR conductor. The pilot wire can length by length and joined with pilot
connectors
section after each drum is paid out. At power line crossings, the pilot wire is laid both the sides and free ends are joined after from
obtaining
provided for P&T and road crossings before paying out of the pilot wire. 4.3.4 Position of tensioner and puller : Back to Contents Page The paying out of conductor is done generally between two tension towers. The puller machine can be
positioned
the tensioner in front of the tension tower on the other side. bull wheels The of entry of the pilot wire into the out
machine should be as nearly horizontal Both the machines should be securely ground
and slackness
shall be positioned at convenient distance of say 10 to to 15 mtrs behind the puller. Conductor drums have
be transported to the tensioner site as per the drum schedule for the section to avoid
approved wastage
For twin moose stringing of one phase, two drums are mounted on two roller jacks. The
of drum shall be such that no midspan joint will come within 30 mtrs of any tower. The placement of drum jacks should be such that angle of conductor approach into the to of of the bull avoid the the 30 of reel the
through guide rollers is low enough on the sides and creating loosening strands and birdcaging. The distance
from the tensioner shall be at least 25 to so as to distribute the effect of due to low back tension. sliding The in
strands
same direction as the bull wheels. 4.3.5 Paying out of conductor : Back to Contents Page For passing the conductor through the bull wheels of
the tensioner, a 25 mm polypropylene rope is initially wound over each bull wheel pair in the same way as the conductor will pass during running. The ropes are
Vol.5 : Page #
connected to the conductors. The conductor run be from the top side of the drum. The rope is by pass
starting the tensioner at low pay out tension the conductor out through the bull guide to wheels rollers. the means and The
brought conductors
through are
attached by
equalizer of wire
pulley/running mesh/endsocks
board and
swivel joints.
is
pulled
to wire and
remove all slackness using the reel winder. The is passed through bull wheels of the puller
connected can be
tensioner to 2.5
tonnes. Caution should be made over the wireless hand set the to all the staff who are at middle points and tensioner operator that pulling is about so that they can stay clear of pilot to to be
started
wire.
The puller is started to draw up the pilot wire until the bull wheels of the tensioner start moving.
Fig.4.4
Bundle
conductors
scaffoldings,
aerial
rollers etc.
going
during tensioning. This can be monitored by the staff who are posted in between the section and guiding the
Vol.5 : Page #
puller of the
operator over the wireless sets. The conductor may be done at a moderate
pulling speed
while the running board is passing through the aerial rollers. The tension in the tensioner must be adjusted so that the conductors travel well over the ground. In long
spans where conductor is likely to touch the ground rollers may be placed so that the
ground, conductor
Vol.5 : Page #
Vol.5 : Page #
Vol.5 : Page #
The back tension of the conductor behind the tensioner has to be maintained as per the requirement of the tensioner deployed. The back tension is adjusted by
means of brakes provided on the drum jack. A ground shall be connected to the conductor and wire before paying out near the tensioner and which shall be earthed at the nearest tower.
Both the sub-conductors of one phase which are to pulled should be from the same and preferably
be
avoid different conductor sag characteristics. The speed of pulling of the conductor should be that to achieve smooth operation. Slower speeds such may and can
cause significant swinging of the running blocks insulator hardware assemblies. Higher speeds
create greater damage in case of malfunction. The tension applied during stringing generally is of may
about half the sagging tension. When long lengths conductors are strung, the tension at the puller
be higher than that at tensioner due to the length of conductor travellers, strung, number in and performance of of
differences
elevation
supporting
structures etc. Light and steady back tension should be maintained on the conductor reels at all times sufficient to
prevent over-run in case of sudden stoppage. It must also be sufficient to cause the conductor
Vol.5 : Page #
to
lie
snugly in the first groove of the bull wheel slack in the conductor between bull
to
prevent
It may be necessary periodically to loosen the on the reel stand as the conductor is paid
Fig.4.6 indicates paid out bundle conductors. As the conductor is unwound from the reel loose, in at and a
large the
conductor
enters the bull wheel groove, the pressure of contact tends to push the loose outer strands back towards to this get has
the reel where the looseness accumulates, leading a condition commonly known as bird caging. is not controlled, the strands If can
condition
damaged to the extent that the damaged conductor to be cut and removed.
Vol.5 : Page #
This
problem
can
be remedied
by
allowing
enough
distance between the reel and tensioner to permit the strand looseness to distribute along the length enough and of conductor and simultaneously intervening maintaining core outer
strands. Sub may conductor oscillation or clashing of occur or in bundled conductor lines. to conductors Temporary prevent
spacers
damage of conductor surfaces prior to installation of spacers. Temporarily positioning of one sub conductor above another is to be avoided as different may produce sub conductor mismatch tensions the
unless
tensions are low and duration short enough so that creep does the strands not set in. Conductor clashing can and produce slivers which can damage result
Vol.5 : Page #
Vol.5 : Page #
Platforms
shall
be
erected
with
sturdy
bellies, where
roads, rivulets, channels, telecommunication or overhead power lines, railway lines, etc. have to operations. interrupted 4.3.6 It or shall be seen that be crossed during stringing normal services are not
Repairing of conductor : Back to Contents Page Repairs to conductors, in the event of damage being the
course of erection, if necessary, shall be carried out during the running out operations, with repair
sleeves. Repairing of conductor surface shall be done only in case of minor damage,scuff marks etc. keeping in view both electrical sleeves and may mechanical be used when safe the
Repair
is limited to the outer most layer of the and is equivalent to not more than one
Jointing of conductor : Back to Contents Page Just before one length of the conductor paying out is completed another drum has to be deployed in beside stopped puller the by first drum. The paying out has advance to be the of
stopping conductor
simultaneously.
distance
of
tensioner.
The
anchor
stays. The conductor of the first drum is held and the free end is cut. The free end of the second drum is
also prepared. The two ends are joined with a wire mesh midspan releasing
socks.
the come along clamps until the midspan socks emerges outside the tensioner and pulling is stopped. After
anchoring, the conductor is slowly drawn out from the two end socks. The midspan socks is removed and in
Various steps
making compression joints are shown in Fig 4.7. Maximum conductor length shall be made use of in
order to reduce the number of joints. All the on the conductor shall be of compression with for the which recommendations all necessary
type, of
accordance manufacturer
tools
equipments like compressor, die sets of correct size etc. The shall be arranged. conductor any surface shall be clean smooth and cuts, with
without abrasions an
projections,
sharp
points,
etc. Conductor joint shall be coated mix of linseed oil and as be zinc
approved
chromate by
before Surplus
final mix
assembly shall
recommended removed
after
Vol.5 : Page #
The aluminum filler holes in the MSCJ should be to verify the centering of the joint. It that the filler holes are should
used be
ensured starting
filled
before The
compression
of the Aluminium
sleeve.
conductor joints shall be minimum 30 meters away from any towers. No joints or splices is allowed in single spans. Midspan joints shall not be used in any single span crossings such as major power lines, major fitting should the or
rivers, used be
taken to mark the conductors to indicate when is centered properly. During compression
fitting
splicing operation, the conductor shall be handled in such a manner as to prevent lateral or vertical
Vol.5 : Page #
sleeve sharp
shall edges
rounded,
burrs
and
smoothened
using
smooth
files. Similar practice is used for pressing dead end cone of the tension insulator hardware. After making midspan joint, the joint is covered with joint over protector sleeves which is designed to pass the is
the aerial roller grooves without compression until sufficient joint. The
damaging out
paying
the conductor reaches the puller length to be connected is held to the come to and
The
conductor
with
ground anchors.
paying out of next phase can be started or machines shifted to next reach. 4.3.8 Rough sagging of conductor Back to Contents Page Before sagged final to sagging the conductor, it is the rough final of to
tension. Since final sagging is done from one end the section, the conductor is initially attached
the double tension string assembly on the other end. For doing rough sagging, initially the double tension string assembly is assembled with insulators and
hardware and hoisted to the cross arms/bridge as done in the case of suspension towers. The dead end
Vol.5 : Page #
cones
are
ends.
The
5 to 6 mtrs from the dead end cones and with of a pulley connected to a ground is pulled to slacken the anchor, free end to
conductor
conductor (sufficient length to be attached hoisted insulator string assembly). By holding the conductor with pulley, the
dead
end
cones are attached to the tension string. The is slowly released and the conductor will
itself
etc. are removed. 4.3.9 Final sagging of conductor Back to Contents Page The sagging sagging conductor of the conductor shall After being be done sagged using the the
winches. shall
rough
stringing blocks for more than 96 hours before being pulled The to the specified sag. and sagging shall be done in
tensioning
accordance the
conductors the
through conductor
insulator
strings.
Only
after
is rough
Vol.5 : Page #
operation, a span has to be selected in the section to fix the sag board and check the sag.
In the event of using sag tension charts showing sags in each of the actual spans and tension in each
section, usual practice is to place the sag boards in the longest span of the section, and in a span the difference of elevation in the two where
suspension
for spans with 5 mtr increment in length and 2 degree centigrade raise of temperature, the equivalent has to be calculated for all the spans in span the
section. The following formula is used. L13 + L23 +... Equivalent Span (L) = (sq. root of) ------------- L1 + L 2 L1, L2 - Individual spans in a section A span in the section is to be chosen which is to the equivalent span with a maximum equal of
variation
required
are to be noted for the prevailing actual temperature at the time of checking the sag. Sag board is to be
fixed to a tower on one side of the span by measuring the level sag length using after steel taps from the cross vertical insulator arm and
adjusting for
(sighting
end), a thread is to be horizontally tied at the same measured elevation from the cross arm. The tension insulator strings are hoisted on the tower. The details The with of all
tension are
conductors to
four sheave pulleys at sufficient distance of say to 50 mtrs depending upon rough sag of the tower. The other ends condition of the side The
wires of the four sheave pulley are passed through set tower done of single sheave pulleys along the body to with the ground level. The initial the help of tractor/truck of
pulling .Then
pulling ropes are attached to hand winches mounted on the legs of the tower or power winches duly
cross pulley to
sheave pulley and twisting of the pulling wires. of final sagging is shown in fig.4.9.
The conductor is brought into final sag position with the help of winches and the sag is checked by end the
sighting sag
far end sag board from behind the near by matching Sighting elevation tangent of
thread
conductor curve.
should be done
keeping
Vol.5 : Page #
sufficient
distance
from
the
sag
line
to
avoid
parallax error.
Vol.5 : Page #
Vol.5 : Page #
After
reaching is
the final sag, the free end up and the pulled line by of
of rope the
picked
along
string.
marked at the point where cutting is to dead end cone is to be pressed. The
and
free ends of the conductors are brought down and cut near the marking and dead end cones are pressed. The four sheave pulley is slightly tightened to
facilitate attaching the dead end cone to the tension assembly. slowly pulleys 4.3.10 After fixing, brought the four and sheave all pulley clamps is and
released,
down
are removed.
Regulation : Back to Contents Page If the running blocks/aerial rollers which are used to string conductor are not frictionless, it can cause problems during sagging operation. If one or more of the travellers become jammed, sagging can become very difficult. A running block swinging in the direction of the pull can be an indication sagging of a defective occur, the block. the If
unforeseen
difficulties
block
conductor sudden,
abrupt movement of the conductor in the sag spans and quickly cause loss of sag, particularly, if the
Vol.5 : Page #
conductor is already very close to final sag. Care shall be taken to eliminate the sub-conductor as far as differential sags in However, sag
possible.
mismatching more than 40 mm shall not be allowed. For checking the mismatch of the sub conductors horizontal, a theodolite shall be placed in with the
vertical
angle is raised to match the horizontal cross hair to touch the tangent of the sub conductors. Mismatch can be corrected by adjusting the sag using the sag
adjustment plates. 4.3.11 Clipping of conductors : Back to Contents Page The clipping of the conductor follows sagging
operation. This entails removing the conductors from the rollers attached up to and placing them in suspension Before is clamps taking earthed
clipping
conductor
properly on held
suspension towers.
with hooks
the cross arm tip in series with a pull-lift/ratchet lever hoist/four or two sheave pulley. The centre of the aerial roller is marked on the
mm and the aerial roller is removed and rope and pulley. The suspension clamp
lowered and
by
armoured
rods are fixed with neoprene rubber cushions centered over the marking. The suspension clamp is placed over the armored and clamped to with U bolts. The suspension the string and the lifting clamp device rods is is with The
connected
released. The insulator string will hang freely the conductors suspended in the clamps.
verticality of the string may be checked with plumbbob. Care should be taken to prevent any damage to the
conductor while being lifted by hooks. Gunny bags or rubber pads may be used around the conductor to
prevent damage to the outer strands. 4.3.12 Fixing of line spacers : Back to Contents Page Following the clipping operations for bundled
conductor lines, spacers are usually installed. This is done by placing personnel on the conductors with the use of a to conductor ride from cycle normally to known as
spacer-cycle
structure
structure.
Depending on the length of line to be spaced and the equipment available, or diesel powered. cycles may be hand powered
load of the man, car and equipment does the sag sufficiently to cause hazards (spacers, repair sleeves, midspan
not
increase
joints
which the cycle will pass. The installation of the spacers on the conductor of with
varies with span length, the type and manufacture the spacer and is normally done in accordance
the manufacturer's recommendations duly approved. The spacer cycle is hoisted on the bundle at one the
tension
cycles,
meter, re-
quired distances as per the placement chart. In case of hand powered cycles, the personnel pulling the
cycle with rope measure the distances on ground and placement is done on the top. A number of models of spacers are being manufactured and the method of
installation varies with the design of the spacers. After reaching the next suspension tower, the is transferred clamp to the next span with the help of by crossing crossing cycle the ropes
suspension
provided in the cycle. In case of spans crossing HT/LT lines, care should be taken while drawing the spacer cycle with rope. electrical spacer clearance should be maintained to Safe the the
lines,
after crossing the line, keeping sufficient clearance from the to line. The person on the cycle cross over the section above can the travel power
Installation of dampers : Back to Contents Page Vibration dampers/spacer dampers are normally on the conductors immediately following placed to
clipping
prevent any possible damage because of vibrations to the conductors, which at critical tensions and wind conditions can occur in a matter of hours. In lines where dampers and spacer dampers are installed, number per the
vibration of dampers
instructions of the manufacturer. 4.3.14 Jumpering Back to Contents Page The jumpers at the section/angle towers shall be
formed to parabolic shape to ensure minimum clearance requirements. Pilot suspension insulator string shall be used if found necessary (Generally where angle deviation is more than 45 degrees), to restrict of the
jumper swings to the design values at both middle and outer ground, phases. Clearance between the jumpers conductors shall and be the
line. While jumpering is made, a local earthing should made due to avoid any static discharge that might to the voltage induced on the line by be
occur
existing
power lines in the vicinity. Care should be taken to leave jumpers for one angle as
to prevent transmission of electric shock. These left out jumpering can be taken up during final
inspections. The individual sections jumpered shall be kept earthed commissioning. The Hence jumpers in general are 10 to 15 mtrs in length. for and earth shall be removed only before
distance
between the jumper pads of dead end cones is measured by passing a rope in the shape of a jumper and by end. length
checking Conductor
vertical clearance from the cross arm is cut after making adjustment in
for the jumper cone dimension. The inner and outer conductor of the bundled jumper are of different lengths, which shall be measured plane of the
separately. the
jumper bundle when installed. After cutting jumper cone is pressed using
conductor,
hydraulic
compressor. The conductors are laid out on the ground parallelly and spacers are fixed as per
Vol.5 : Page #
the
fixing
instructions. The jumper is hauled up from both of the tension clamps and jumper cone is attached the connector of the dead end cone.
ends to
Clearance to the
tower body shall be checked as per the drawing. 4.3.15 Paying out through angle towers : Back to Contents Page In order to of reduce wastage of of conductor, the
possibility
paying-out
conductor
through
angle towers using TSE may be considered. Here the running blocks or rollers are fixed to the
steelropes may be
mm dia measuring maximum 30 cm. care that the pulling is done slowly and
taken
smoothly
stays may be provided as a precautionary measures. If substantial line angles are involved, two blocks bending in tandem of may the be required or to running the each
reduce on
radius
conductor
load
blocks are used at line angle more than 5, it is advisable to change to individual single conductor
running blocks after passage of the running board to facilitate sagging match accurate for the sagging. It is of desirable the during to
horizontal
spacing
sheaves to
final
subconductor
spacing
avoid
Vol.5 : Page #
subconductor sag mismatch. However, if any noticeable damage is sustained to the conductor, this procedure should be abandoned. 4.3.16 Transposition arrangement : Back to Contents Page In 400 KV S/C and D/C lines, the 3 phases are
transposed in equal lengths of 1/3rd distance of the line to achieve equal mutual coupling between the
deviation are placed at 1/3rd, 2/3rd and at the end of the transmission line (about 2 to 3 spans before tower tower save are
the terminal gantry).If possible, transposition should be placed at section tower where B type with 0 degree is already proposed otherwise, to the cost. In lines where double circuit portions constructed in forest reaches, major river
crossing
reaches etc. if it is possible, the transposition can be done while changing over from double circuit without providing circuit any to
single
extra
transposition tower. The arrangement of transposition involves jumpering to change the phases in the required position. The centre phase and one of the side phases is transposed to the other side of the tower by means of jumper attached to a pilot insulator
Vol.5 : Page #
suspended
tips. The 3rd phase is transposed from one side the tower to the opposite side of the
of
where a small line is strung between the earthwire peaks with two turn are single tension fittings with type T sag and
buckle. on
provided
conductors
jumpers
are
connected of T
using
compressed on the
jumper line
cones.
Compressing
connectors
brought down or the compressor machine has to and joint made at line elevation.
hoisted
Fig.4.10 is a view
Vol.5 : Page #
Vol.5 : Page #
4.4
Stringing over river crossing. Back to Contents Page In major river crossings having multi-span section
with suspension towers, there are special arrangements and It dry water have some precautions to be taken during stringing. during there the is
is better to plan stringing activity seasons of the year. In rivers where extra
precautions major
navigable rivers having flow of water through out the year, is explained below. In case of navigable local areas. about
rivers prior intimation should be given to the authorities and boat operators in the nearby
Caution signals shall be raised with red flags 1 km up and down streams of the alignment. 4.4.1 Earthwire
length as is normally done in ordinary sections. As explained earlier, special drums having full length of the sections are procured for stringing. polypropylene through carrying the the rope of say over 1 km Initially, a is passed by the
length aerial
section rope in
the
rollers out
boats.
After
paying
polypropylene rope the earthwire is attached from one end of the section and pulled by the rope through the
Vol.5 : Page #
be frictionless.
rope may be passed to the next span manually and may be continued. The T&P
tower heights are very large. 4.4.2 Paying out of conductor Back to Contents Page In multispan reaches of major river crossings the stringing paid the
equipment. The pilot wire has to be initially out case total one from one end of the section as is done in
of earthwire by using polypropylene rope. The pilot wire reels required have to be end of the section and joined with after each length is kept at wire
pilot
connectors
pulled.
Conductor It
paying out can be done by normal stringing method. is better to procure conductor of
normally supplied, to avoid midspan joint of conductor in the river crossing reaches. However, the conductor reels should not be too heavy and cause difficulty in handling and transporting. In case the dead end towers used for the river
crossing
normal
towers, it is advisable
to
Thus using of long stays which are Also, long stays bending
not reliable
moment experienced by the tower For high. with any long spans in river crossings, the sag Care should be taken while checking is the very sag for is near in time
help of sag board so as not to give chance error due to wind load on the conductor. to wind carry out the sagging operation condition. Sub conductor in It
mismatch
of erection itself since differential creepage in the conductors may cause large difference in the
becomes
very difficult in approaching the tower from Also pulling from the ground may to flow of water. Under these
conditions, good
it is
better
All bolts & nuts of hardware shall be doubly for tightness, provision of spring washers,
pins etc. to avoid tower failure. 4.5 Stringing over power line crossings
Vol.5 : Page #
Back to Contents Page In the alignment of the Transmission line, many power line EHV. crossings While are encountered ranging from major power lines, LT due to to
crossing
limitations reasons
mtrs is provided from the 400 KV line. be very accurate shall and be physical checked
power
line
sagging
encountered
action should be taken to obtain line clear permit to work from the utility operating line wire, clear the power line. of The pilot can
be joined after obtaining the shutdown. In case of power lines upto 33 KV, it is easier and two and
economical to bring down the LT/HT conductors at or three poles. In case of lines of 132 KV
above, bringing down the conductor is very and in many cases the utilities will not
doing so. of
inconvenience and unnecessary outage of the line. It is suggested to request utility to arrange measure few hardware fittings as a and
precautionary
Vol.5 : Page #
insulator in order to replace them, if necessary. such cases, special cylindrical rollers
In
fabricated
out of soft wood about 50 cms in length and 30 cms in dia split in cross section with a groove at the may
rollers of to
can be mounted on
the
conductor and
or the
over
these done at
Normally, crossings of major lines is or two spans only with dead end towers
and commonly with a special extension tower Tension stringing difficult and
unwarranted since the no. of spans is normally limited to two only. placement completed be very
All the activities of paying out, sagging, of line hardware & accessories shall shutdown period since it to carry out operations be will
during
the
difficult afterwards. or it
without
shutdown 18
25 mtrs, the conductor slope is very high very difficult for placement of bundle
Precautions should be
cycle
Vol.5 : Page #
Chapter-5 Guidelines
Vol.5 : Page #
Back to Contents Page NAME OF LINE ...... SECTION - LOC. NO....... Following preparations need to NAME OF CONTRACTOR ...... TO be made LOC. NO....... before taking up
stringing work. 1.1 1.1.1 Foundation checks Backfilling of soil of foundation should be done
might have
settled down with the passage of time. Area should be fairly levelled within four legs. 1.1.2 Revetment / Benching wherever required shall be completed so that there is no danger to foundation during and after stringing work. However, if it is is felt not
that, non-completion of Revetment / Benching going to harm foundation during and after the date. 1.2 Tower checks
Vol.5 : Page #
stringing, on later
same
executed
1.2.1
The tower shall be checked by two supervisors starting simultaneously from the bottom of the diagonally carried opposite legs. The tower at two be the the
checking tower
shall and
through
of
bolts/nuts
are used and fully tightened. 1.2.3 It shall also be ensured that all bolts/nuts have been provided with spring washers. 1.2.4 A torque wrench may be used at random to ensure
sufficient tightness. 1.2.5 Any missing members shall be provided with correct
size member. 1.3 1.3.1 Way leave clearance In order to maintain cordial relations with the owners for smooth completion of stringing, field it is
desired that compensation of damage of crops during foundation and tower erection is paid to the field owners before taking up stringing work. 1.3.2 Also, wherever of possible and if found necessary, stringing
compensation
may be processed in advance for prompt payment. 1.3.3 Advance precautions should be taken to handle way
leave problem. Rough handling of the issue may spread to nearby villages along the line resulting into total
Vol.5 : Page #
stopage of site activities. 1.4 1.4.1 Tree cutting Immediately after completion issual of detailed survey, Revenue
tree cutting. 1.4.2 The tree cutting so may be carried out alongwith before
foundations
completed
tower erection. 1.4.3 Any left over tree may be removed well in advance order to achieve smooth stringing and in
requisite
electrical clearance. 1.4.4 Tree compensation should be paid possible to gain confidence of as field promptly owners as for
smooth completion of balance construction work. 1.5 1.5.1 Line material & drawings It shall be ensured that all approved line material are and stringing at charts site to drawings with of
latest
revision
available
facilitate
Book shall be available at site with each line material shall be available at site as
requirement. 1.5.3 Though all the line materials are checked for any is
necessary
to keep
line
material be at
It shall used
1.6 1.6.1
Tools and plants All the tools and plants shall tools be and required for at is safe and A at
efficient list of
stringing necessary
available plants
site. given
Annexure-S/1. 1.6.2 All the tools and plants shall be tested as per
In addition to above,
testing of tools and plants shall be carried out its safe working capacity shall be worked out
recorded. 1.6.3 It shall be ensured that Tension stringing equipments and other measuring instruments are properly
calibrated and relevant certificates are available. 1.7 1.7.1 Personal protective equipments All the persons working on tower or
conductor/Earthwire shall wear safety helmet, safety belt and safety shoes. Similarly all the persons
1.7.2
Safety equipments shall be tested as per safety norms and necessary test certificate shall be available.
Also, a periodic check shall be carried out to ensure requisite strength. 1.8 1.8.1 Manpower Manpower be engaged for the purpose of stringing and competent enough to ensure shall safe,
skilled
smooth and efficient stringing activity. 1.8.2 A list of necessary manpower required for is given at Annexure-S/2. 1.9 1.9.1 Misc Shutdown well in of power line crossings shall Shutdown should be be planned in stringing
advance.
obtained
writing 1.9.2
Similarly for Railway crossing, necessary block shall be planned well in advance. Proper shall be provided before protection taking / up
Telephone
line crossings
shall
also
be
provided proper scaffolding and warning signals. 1.9.4 Tower vulnerable both for one side load shall be so guyed as to
properly
avoid any untoward incident. 1.9.5 Wireless communication (walky - talky ) sets in proper working condition. 1.9.6 It shall be ensured that tower footing resistance has
Vol.5 : Page #
shall be
been
of
10 ohm. 1.9.7 It shall be and well verified earthwire in advance. that have Drum been is schedules submitted compulsory for and for
This
Vol.5 : Page #
GUIDELINES GL-2 PAYING OUT OF EARTH WIRE Back to Contents Page NAME OF LINE ...... SECTION - LOC. NO....... 2.1 Safety precautions Safety shall be given utmost importance during NAME OF CONTRACTOR ...... TO LOC. NO.......
stringing. The following need to be ensured 2.1.1 Safe working conditions shall be provided at the
stringing site 2.1.2 All persons on tower/earthwire helmet, safety belt and shall wear safety all the
persons on ground shall wear safety helmet and safety shoes 2.1.3 Immediate Medical Care shall be provided to First Aid Box shall be workmen available
Traveller ground shall be provided between drum and the section tower to avoid any
Earthwire potential
hazards. 2.1.5 Foolproof exist public 2.2 2.2.1 in communication through walkie talkie order to avoid any danger to shall or
workmen
Vol.5 : Page #
a)
b)
It shall be made sure that paying out is carried as per approved drum schedule.
out
c)
All the pulleys fixed on towers for paying out should move freely to avoid any damage to earthwire or
pulley and to achieve correct final sagging. d) One person on each tower shall be available with and green flags and whistle for supervision red and
for smooth communication between pulling tractor unwinding of E/W drum. f) Earthwire unwound or loose shall be checked constantly as it
is
from earthwire drum for any broken, damage strand. If any defect is noticed and then mid
portion
has to be removed
provided.
there is no repair sleeve for earthwire. g) Necessary arrangement shall be made to avoid any
rubbing of earthwire against ground or hard so that earthwire is not damaged. 2.2.2 Details of earthwire Details Location of nos. Manufacturer, between which Drum No., is
surfaces
Length paid
and out,
earthwire
that
any
problem
encountered
during
operation
and
Details of M.S. Joint M.S. Joint shall be provided strictly as per approved drawings and technical specifications.
b)
Following details of MS Joint shall be recorded. i) Manufacturer's name and batch number No.1 or 2 and Location nos. between provided. of M.S.Joint before and after
compression shall also be recorded and shall be within permissible limits as per approved
drawings. c) M.S.Joint shall be provided from tower. d) There shall not be any M.S.Joint over Road e) Crossing. one Rly/River/Main atleast 30 meters away
Not more than one M.S.Joint shall be provided in span for each earthwire.
Vol.5 : Page #
GUIDELINES GL-3 PAYING OUT OF CONDUCTOR Back to Contents Page NAME OF LINE ...... SECTION - LOC. NO....... 3.1 Safety precaution Safety shall be given utmost importance during NAME OF CONTRACTOR ...... TO LOC. NO.......
stringing. 3.1.1.
3.1.2
on tower/conductor
shall
wear and
safety
persons on ground shall wear safety helmet and safety shoes. 3.1.3 Immediate medical care shall be provided to First Aid Box shall be workmen available
Traveller ground shall be provided between Tensioner/ Puller hazards. and section tower to avoid any potential
3.1.5
Fool proof communication through walkie talkie shall exist in order to avoid any danger to workmen public on ground. or
3.2 3.2.1
3.2.2
It
shall
be
confirmed
that
Tensioner/Puller
are
firmly anchored with ground with wire rope of atleast 20 mm diameter in order to hold them in place. 3.2.3 It shall be verified that suitable earthing by copper cable of cross section of atleast for both puller and Tensioner. 3.2.4 Slope of pilot wire/conductor between Tensioner/puller and section tower shall be approximately three This 64 mm is provided
horizontal is essential
traveller
and section towers. 3.2.5 It is also necessary that horizontal angle of pilot
avoid damages to pilot wire/conductor and grooves of bull wheels. 3.3 3.3.1 Conductor drum placing It shall be ensured that there is enough
distance avoid
between brid
caging
Generally
a distance of 25 to 30 meters
the purpose. 3.3.2 Horizontal tensioner angle should of conductor as it approaches rubbing
conductor
drum
should
be
small enough to
avoid
rubbing
of
functioning properly for conductor drum to get desired level of control during paying out operation. 3.4 3.4.1 Sequence of paying out It shall be ensured that earthwire is already paid
out before taking up paying out of conductors. 3.4.2 It out shall be checked that proper sequence of paying and of
conductor shall be from top to downwards. b) In case of S/C line, sequence of paying out of outer phases are completed
conductor is that
before taking up middle phase. 3.5 3.5.1 a) Insulator hoisting Checking of Insulators Insulators shall be completely cleaned with soft clean cloth. b) It shall be verified that there is no crack or any and
This is a security
measure to avoid disconnection of insulator discs. d) Necessary damage precautions shall be taken so that no In
case of damage, the same needs to be replaced. e) Details of insulators (i.e. Type, Make, KN, & Batch )
are to be properly recorded. 3.5.2 a) Checking of Suspension Fitting It shall be verified that necessary hardware as per approved drawings is provided for fitting insulator
component of hardware fittings. c) It shall be verified that all nuts and bolts are
tightened properly. d) It shall be made sure that all the necessary pins (split pins) are fixed properly as per drawings. e) Details No.), of suspension fitting (Type, Make, be Batch security approved
recorded. 3.6 3.6.1 a) Checking paying out process General Relevant approved drawings as mentioned in para 1.5.1 shall be referred to. b) It shall be made sure that paying out is carried
Vol.5 : Page #
out
as per approved drum schedule. c) All the Travellers fixed on tower for paying out
should
conductor
or Traveller and to achieve correct final sagging. d) One person on each tower shall be available with and green flags and whistle for supervision red and
for smooth communication between Tensioner and Puller. f) Conductor shall be checked constantly as it is
If any
then the defective portion has to be removed and mid span joint minor nature more than provided. i.e. 1/6th However if the defect is of not outer
layer, g)
Necessary
rubbing of conductor against ground or hard so that conductor is not damaged. 3.6.2 Details of conductor Details Location of nos. Manufacturer, between which Drum No.,
surfaces
Length is paid
and out,
conductor
shall be recorded in order to maintain traceability so that any problem encountered during operation and
Vol.5 : Page #
Details of M.S. Joint M.S. Joint shall be provided strictly as per approved drawings and technical specification.
b) i) ii)
Following details of MS Joint shall be recorded Manufacturer's name and batch number Conductor No.1 or 2, phase R,Y,B and Location nos.
between which MSJ is provided. iii) Dimensions of MSJ before and after compression also be recorded and shall be within shall
permissible
limits as per approved drawings. c) M.S.Joint from tower. d) There shall not be any M.S.Joint over Road Crossing. e) Not more than one M.S.Joint shall be provided in span for each conductor. one Rly/River/Main shall be provided atleast 30 meters away
Vol.5 : Page #
GUIDELINES GL-4 FINAL TENSIONING OF EARTHWIRE AND CONDUCTOR Back to Contents Page NAME OF LINE ...... SECTION - LOC. NO....... 4.1 4.1.1 General All the approved stringing charts and other drawings shall be available at site before the final tensioning. 4.1.2 Final sagging in a particular section shall be done relevant taking up NAME OF CONTRACTOR ...... TO LOC. NO.......
only after verifying that conductor and earthwire are already rough sagged in adjacent sections. This is to
very important to avoid overloading of towers due one side load. 4.1.3 It shall be ensured that all safety precautions
are
being taken as detailed in GL-2 & GL-3. 4.1.4 Final Tensioning and sagging shall be carried out in
a calm weather when rapid changes in temperatures are not likely to occur. 4.2 4.2.1 Fixing of sag boards Thermometer elevation the shall be installed on tower at the as that of conductor and far to avoid the effect of enough ground same above heat
ground
radiation. 4.2.2 The atmospheric just temperature prior to shall final be read from The
thermometer
sagging.
Vol.5 : Page #
value be
of
sags from
for
earthwire
and
shall
noted
approved
stringing
chart
shall be referred
conductor
earthwire. earthwire sag length shall be measured by from earthwire peak after adjusting for be
On other the
tower at the same elevation as that of sag board. (b) In case of conductor, sag length shall be measured steel tape from cross arm after adjusting for of sag suspension board insulators and hardware by
length The of
sagging span. On other side of sagging span, a thread shall be tied on the tower at the same that of sag board. 4.2.4 a) Sag boards are to be fixed as per following For a section having length upto 8 spans, the sag elevation as
boards shall be fixed in first and last span. b) For a section having length more than 8 spans, the and
sag boards shall be fixed in first, intermediate last span. 4.3 4.3.1 Final sagging of earthwire Rough sagged earthwire shall be tightened further
Vol.5 : Page #
by
winch machine fixed on tower till, the final position is achieved. 4.3.2 The sag final sag shall be checked by sighting board from behind the near end elevation shall be tangent taken to of sag the
sagging
far thread
end by
avoid
correctly as
after per
approved drawings. 4.3.4 The earthwire shall be cut at the marked point and
Tension clamp provided. a) Following clamp. i) All the components of tension clamp are properly shall be checked in respect of Tension
fitted as per approved drawing. ii) iii) All Nuts and Bolts have been properly tightened None case of the components of the clamp is damaged. In of any damage, the same shall be replaced by
Following shall be recorded regarding tension clamp. Earth wire No. and location No. between which it is
provided. ii) iii) Batch No., Make etc. Dimensions before and after compression.
Vol.5 : Page #
4.3.5
Sag shall again be checked after fixing tension clamp in order to ensure that no error is introduced by
fixing tension clamp. 4.4 4.4.1 Final sagging of conductor Rough sagged subconductors of one phase shall fixed be on
simultaneously
tower till the desired final sag is achieved. 4.4.2 The final sag shall be checked as mentioned in para
adjusting length of Tension fittings. 4.4.4 The conductor shall be cut at the marked point and
Dead end joint provided. a) Following fittings. i) Insulators 3.5.1 ii) Tension fittings shall be checked in accordance para 3.5.2 b) The following shall be recorded in respect of Tension fittings. i) Wire No., Phase and location of towers on which it is provided. ii) iii) Batch No., Make etc. Dimension of Dead end joint before and after as with shall be checked as detailed in para shall be checked in respect of tension
per approved drawings. 4.4.5 Sag mismatching shall be checked by sighting through the Teodolite placed on ground near the tower. Any adjustment
plate in Tension fittings. It shall be verified that sag mismatch is not more than permissible limit of 40 mm.
Vol.5 : Page #
GUIDELINES GL-5 CLIPPING AND FIXING OF ACCESSORIES OF EARTHWIRE Back to Contents Page NAME OF LINE ...... SECTION - LOC. NO....... 5.1 5.1.1 NAME OF CONTRACTOR ...... TO LOC. NO.......
Clipping and Checking of Suspension clamps It shall be ensured that correct marking on earthwire is done to fix suspension clamp. The suspension clamp after fixing shall be in exact vertical position.
5.1.2
a)
b)
All the components of suspension clamp are properly fitted as per approved drawings.
c) d)
All Nuts and Bolts have been properly tightened None of the components of the clamp is damaged. In replaced by
case of any damage, the same shall be good one. e) 5.1.3 a) Split pin has been properly provided.
Following shall be recorded for suspension clamps: Earthwire No and location No. of tower in which
suspension clamp is provided . b) 5.1.4 Batch No., Make etc. Sag shall be rechecked to ensure that no
Vol.5 : Page #
error
is
introduced after clipping operation. 5.2 5.2.1 Checking of vibration Dampers Following Dampers: a) Vibration Dampers are provided as per approved checks shall be carried out for vibration
placement chart. b) c) 5.2.2 a) b) 5.3 5.3.1 a) All Nuts and Bolts have been tightened properly There is no damage to V.D. Following shall be recorded: Make, Batch No. etc. Wire No., Loc. No. of Dampers provided. Checking of Earthwire Jumpers Following shall be checked: Earthwire jumper is provided on all tension towers as per approved drawings and technical specification. b) c) 5.3.2 All Nuts/Bolts have been properly tightened Split pin provided properly Dimensions of jumper cone before and after
compression shall be recorded. permissible limits. 5.4 5.4.1(a) Checking of Copper Bonds
It shall be within
It shall be ensured that one copper bond is for each suspension and tension clamp as drawing.
provided
per approved
b)
It
shall
be
no
damage
to
copper Bond.
Vol.5 : Page #
c) 5.4.2 a) b)
All the Nuts/Bolts are properly tightened Following shall be recorded: Make, Batch No. etc. Wire No., Location No. of tower on which it is
provided.
Vol.5 : Page #
GUIDELINES GL-6 CLIPPING AND FIXING OF CONDUCTOR ACCESSORIES Back to Contents Page NAME OF LINE ...... SECTION - LOC. NO....... 6.1 6.1.1 Conductor Clipping Before taking up clipping, the conductor should be NAME OF CONTRACTOR ...... TO LOC. NO.......
earthed to avoid any electrical hazards. 6.1.2 Conductor placing shall be marked properly so that after fitting
insulator
hangs in exact vertical position. 6.1.3 Following clamps. a) Armour rods have been properly provided as per shall be checked in respect of suspension
been properly provided as per approved drawings c) None of the components of suspension clamp is to
damaged.
be replaced. d) e) 6.1.4 All Nuts/Bolts have been properly tightened. All the split pins have been provided. Since, the suspension clamp is part the details of clamp may be of suspension with
fittings,
clubbed
6.2 6.2.1
Fixing of Vibration Dampers Following Dampers: checks shall be carried out for vibration
(i)
Vibration
Dampers
are
provided
as
per
approved
placement chart. (ii) (iii) 6.2.2 (i) (ii) 6.3 6.3.1 All Nuts and Bolts have been tightened properly There is no damage to V.D. Following shall be recorded: Make, Batch No. etc. Wire No., Loc. No. of Dampers provided. Fixing of Spacer Spacers chart. 6.3.2 Necessary any LT/HT precautions shall be taken while line to avoid any electrical crossing by shall be provided as per approved placement
hazards
accidental touching of ropes. 6.3.3 All components of spacer shall be properly fitted per approved drawing. 6.3.4 None of the components shall be damaged. In case of as
any damage, the same shall be replaced by good one. 6.3.5 6.3.6 a) b) All Nuts/Bolts shall be properly tightened. The following shall be recorded. Make, Batch No. etc. Details of span, phase, no. of spacers provided,
be
provided,
the
guide line for fixing of spacer as per para 6.3 shall also be applicable for spacer dampers.
6.4 6.4.1
Fixing of Jumper and Jumper Spacer Before taking up Jumpering work, necessary earthing
of conductor shall be provided to avoid any potential hazards. 6.4.2 Length that metal drawing. it of Jumper shall be carefully is in parabolic shape so as clearance and Jumper drop as selected to per give such live
approved of a
bundle shall be properly co-ordinated so that spacers possible. 6.4.3 Jumper cone shall lie in horizontal position as far as
jumper
drawings. Its dimension before and after compression shall be recorded and shall be within permissible
limits. Since Jumper cone is part of Tension fitting, the details of cone shall be clubbed with fitting as per para 4.4.4 6.4.4 All nuts and bolts shall be properly tightened. is very essential to ensure tightness of jumpers This to that of
avoid arcing and flashover which may result in damage of tension fittings and undesirable tripping of line. 6.4.5 Jumper spacers shall be provided as per technical
a) i) ii)
Following shall be checked. All components have been properly provided. No component is damaged. shall be replaced. In case of damage, the same
All Nuts and Bolts have been properly tightened Following shall be recorded for Jumper spacer Make, Batch No. Loc. No., Phase, No. of spacer. Pilot Fittings Following fittings. shall be checked in respect of pilot
a)
Insulators 3.5.1
shall
be checked as
detailed
in
para
b)
Fittings 3.5.2
shall
be checked in accordance
with
para
6.6 6.6.1
Checking of Transposition Tower Before taking up transposition job, at site. sides the following
b)
The
tower
having
all the relevant details. c) The approved drawings of various line material to employed for transposition arrangement. 6.6.2 It shall be ensured that jumpers provided for The be
point of fixing
of The be
jumper shall be strictly as per approved drawing. live metal clearance of different phases shall
recorded.
clearance
approved drawings. b) Dimensions recorded. c) 6.6.4 a) before and after compression shall be
All Nuts/Bolts shall be properly tightened Pilot Fitting & Balancing Weight Pilot Fittings Following fittings. shall be checked in respect of pilot
i)
Insulators 3.5.1
shall
be checked as
detailed
in
para
ii)
Fittings 3.5.2
shall
be checked in accordance
with
para
b) i)
Balancing Weight It shall be ensured that Balancing weights have provided as per approved drawings. been
ii)
There
shall
be no damage to Balancing
weight. In
case of damage, the same shall be replaced. 6.6.5 a) Single Tension Fitting Following shall be checked in respect of tension
Vol.5 : Page #
fittings. i) Insulators 3.5.1 ii) Tension fittings shall be checked in accordance para 3.5.2 and 4.4.4 (b). 6.6.6 It shall of be ensured that earth mast on earthwire as per with shall be checked as detailed in para
peaks
provided
approved drawing.
Vol.5 : Page #
Annexure - S/1 Back to Contents Page POWERGRID CORPORATION OF INDIA LTD. (CONSTRUCTION MANAGEMENT) LINE CONSTRUCTION STRINGING ACTIVITY Tools and Plants required for Stringing Gang for Tension Stringing 1. TSE Sets. (Tensioner & Puller of 8 t/10 t Cap.) 2. 3. 4. 5. 6. 7. Running Block for conductor. Running Block for earthwire. Head Board. Pilot wire each of 800 m length. Pilot wire joint. Grnd. roller for Tension/Manual Stringing. 8. Wire mesh pulling grip (One end open of reqd. dia. for conductor). 9. Wire Mesh Pulling Grip (One end open of reqd. dia. For earthwire). 10. Wire Mesh Pulling Grip (Double end open of reqd. size for conductor.) 11. Articulated Joint. Heavy duty (20 t).
Vol.5 : Page #
set
100 60 2 10 12
30/100 nos.
6 nos.
2 nos.
4 nos.
10 nos.
Medium duty (10 t). Light duty (5 t). 12. Drum mounting jack for conductor drum of 10 t capacity. 13. 14. Turn Table (5 t.capacity). Anchor Plate (1.5 m.x1.0 m. x8 mm) with 15 Nos. Anchor Pins (45 mm dia. And 850 mm long). 15. Hydraulic compressor Machine 100 T capacity with die sets. 16. 17. Travelling Grnd. Dynamometer - 10 T. 18. 19. 2 T.
10 nos. 5 nos.
4 sets 2 nos.
10 sets
Pilot wire reel stand. Four sheave pulley with 9 mm dia. & 300 m length wire rope.
6 sets
20.
Four sheave pulley with 12 mm dia. and 300 m length wire rope. 2 sets
21.
Four sheave pulley with 12 mm dia. and 150 m. length wire rope. 4 sets 16 nos. 4 sets
Equiliser pulley (10 T. capacity). Conductor Lifting tackle. Winch - Motorised/Manual - 10 T capacity.
4 nos.
25.
26.
(Bolted type/Automatic). 27. 28. 29. 30. Trifor (5 T. Capacity) Aerial Chair for conductor. Aerial Trolley. Turn Buckle - 10 T. 31. 3 T.
Tension/Sag PlateFor Tensioning Purpose). 6 nos. 8 nos. 4 nos. 2 nos. 6 nos. 4 sets 1 no. 3 no. 1 nos. 2 nos. 3 nos. 30 nos. 10 nos. 6 nos.
32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45.
Sag Board. Marking Roller. Mismatch Roller. Joint Protector. Walkie Talkie Set. Theodolite with stand. Thermometer. Survey Umbrella. Hydraulic Wire cutter. Binocular. Flag (Red and Green) Crow Bar (1.8 m Length). Nail Puller. Wire Rope. (19 mm. dia.). (16 mm. dia.). (14 mm. dia.).
46.
500 m.
(19 mm. dia.). 47. D Shackle. (190 mm Long). (150 mm Long). (100 mm Long). 48. 49. Bulldog Clamp 100 mm Long. Hammers, spanners,( Both Flat and ring) round files, flat files, screw drivers, cutting pliers, Steel and Metallic Tapes, Hecksaw frames and Blades, Deadmen, Scaffolding,Slings, etc. 50. Tents, Buckets, water drums, camping cots, tables, chairs, petromax lamps etc. 51. Safety equipments: i) ii) Safety helmets Safety belts
500 m.
40
nos.
As per reqmt.
As per reqmt.
Note: The quantity of safety equipment may be changed as per manpower engaged.
Vol.5 : Page #
ANNEXURE - S/2 Back to Contents Page POWERGRID CORPORATION OF INDIA LTD. (CONSTRUCTION MANAGEMENT) LINE CONSTRUCTION Man Power Requirement For Stringing Gang 1. Manpower requirement and average output per gang is given as under:Sl. No. Description of line Manpower Nos. Average output KM per month 1. 2. 3. 4. 5. 6. 132 KV S/C Line 132 KV D/C Line 220 KV S/C Line 220 KV D/C Line 400 KV S/C Line 400 KV D/C Line 85 85 110 110 200 200 30 15 30 15 15 8
2.
Breakup of Manpower is as follows : 400KV S/C or D/C Line i) ii) Engineer. Supervisors. 2 Nos. 10 Nos. 220KV S/C or D/C Line 2 Nos. 6 Nos. 132KV S/C or D/C Line 1 No. 4 Nos.
iii) Skilled Manpower. (a) (b) (c) Fitters. 30 Nos. 20 Nos. 2 Nos. 3 Nos. 15 Nos. 2 Nos. 2 Nos.
(d) (e)
Carpenters.
2 Nos.
2 Nos.
1 No.
Skilled workers for misc. works. 110 Nos. 50 Nos. 25 Nos. 40 Nos. 20 Nos.
iv)
Vol.5 : Page #
Vol.5 : Page #
_____________________________________________________________________ _ CHAPTER SIX _____________________________________________________________________ _ CHECK FORMAT Back to Contents Page POWERGRID CORPORATION OF INDIA LIMITED (CONSTRUCTION MANAGEMENT) LINE CONSTRUCTION Check Format NAME OF LINE...... SECTION LOC. NO....... NAME OF CONTRACTOR...... To LOC. NO.......
---------------------------------------------------------------ITEM CHECKED RESULT OBSERVATION, IF ANY ---------------------------------------------------------------(A) 1) Pre-stringing checks: Backfilling of soil and revetment/Benching wherever required is done. 2) Towers are tightened properly and all the members, Nut/Bolts are provided. 3) Trees in the corridor removed to facilitate smooth stringing. 4) All Line materials, tested T & P, safety equipments
Vol.5 : Page #
Yes/No
Yes/No
Yes/No
Yes/No
and relevant drawings are available for stringing. 5) Shutdown of Powerline/ Railway block if required, is arranged. 6) Necessary Protection/ scaffolding/warning signals provided for Railway/Power line/P&T line/Road Crossing. 7) Towers vulnerable for one side load is guyed properly. 8) Tower footing resistance is within permissible limit of 10 ohms. Yes/No Yes/No Yes/No Yes/No
Vol.5 : Page #
(B) 1)
Paying Out of Earthwire Work is being carried out with full safety measures as per guide line. Yes/No
2)
3)
4)
All pulleys fixed on towers for paying out are moving freely. Yes/No
5)
Effective communication exists through walkieTalkie and through persons on towers. Yes/No
6)
Earthwire is being constantly checked as it is unwound. Damaged portion, if any, is removed. Yes/No
7)
Necessary arrangement have been provided to avoid rubbing of earthwire against hard ground. Yes/No
8)
Yes/No
recorded as per AnnCF-I & CF-II. (C) 1) Paying out of Conductor Work is being carried out with full safety measures as per guide line. 2) Tensioner/puller are properly placed, firmly anchored and earthed. 3) Conductor drums are placed properly to avoid bird caging 4) Sequence of paying out is such that to avoid unbalanceing of load on tower. 7) Details of insulators and fitting are recorded as per Ann. CF-III & CF-IV. 8) Paying out is carried out as per approved drum schedule. 9) Travellers fixed on towers are moving freely. 10) Effective communication exists through walkie-talkie and through persons standing on towers for smooth
Vol.5 : Page #
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
and safe paying out. 11) Conductor is checked continuously as it is unwound from drum. Damaged portion, if any, is removed/repaired. 12) Proper arrangements made to avoid rubbing of conductor on ground/hard surfaces. 13) Details of conductor and M.S.J/repair sleeve is recorded as per Ann. CF-I & CF-II. (D) 1) Final Sagging and Tensioning of Earthwire and Conductor Sag board is fixed correctly after taking into account length of suspension clamp/fittings. 2) No. of sag boards fixed in a section is as per technical specification. 3) Sag is measured correctly at prevailing temperature. Details recorded as Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No
permissible limits of 40mm as checked with Theodolite. 5) After measuring sag, marking/cutting of Earthwire/ conductor is done correctly to fix tension clamp/fittings) 6) Details of tension clamp/ fitting are recorded as per Ann. CF-VI, CF-III, & CF-IV. (E) 1)
Yes/No
Yes/No
Yes/No
Clipping of Earthwire and Conductor For clipping, the marking is done correctly so that suspension clamp/ fitting hangs exactly vertical. Yes/No
2)
3)
Following line material provided as per specification. Details recorded as shown below.
a)
Suspension clamp of Earthwire and conductor as per Ann.CF-IV & CF-VI. Yes/No
b)
Earthwire and Conductor as per Ann. CF-VII c) Details of spacer/spacer damper/jumper spacer recorded as per Ann. CF-VIII. d) Jumpers for Earthwire/ Conductor as per Ann. CF-IV & CF-VI. e) Pilot fitting, wherever necessary as per Ann. CFIII & CF-IV. 4) Sag/Tension again measured after clipping and found o.k. Details recor-
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
5)
Transposition done as per specification. Details of line material recorded properly. Yes/No
6)
All line materials provided are as per specification and approved drawings. All necessary details recorded for traceability. Yes/No
7)
Yes/No
are as per specification. 8) Minimum Ground Clearance, Clearances over Power line/ Railway line/River Crossing are as per specification. Yes/No
Certificate: Stringing is completed in all respect. FOR CONTRACTOR SIGNATURE NAME DESIGNATION DATE FOR POWERGRID SIGNATURE NAME DESIGNATION : E1/E2/E3 DATE VERIFIED SIGNATURE NAME DESIGN:E4/E5 DATE APPROVED SIGNATURE NAME DESIGN: E6/E7 DATE
Vol.5 : Page #
4.
There
during stringing.Strands are in perfect position. FOR CONTRACTOR SIGNATURE NAME DESIGNATION DATE FOR POWERGRID SIGNATURE NAME DESIGNATION : E1/E2/E3 DATE
Vol.5 : Page #
ANNEXURE CF- II Details of M.S. Joint for Earthwire/Conductor Sleeve for Conductor 1. 2. 3. Sl. No. Make Batch No. Location Between Loc. No. Phase Wire No. and Repair
4. 5. 6. 7. 8.
Dimension - Recorded as per Ann.CF-IX M.S. Joint has been provided at least 30 meters away from tower. There is no M.S. Joint over Railway/River/Main road crossing Not more than one M.S. Joint provided in one span for each Earthwire/Conductor. Repair sleeve shall be used if number of damaged strands is not more than 1/6th of the total strands in the outer layer. If damage is more, then the damaged portion shall be removed and M.S. Joint provided.
ANNEXURE CF - III Records of Insulators 1. 2. Type - Glass/Porcelain, Suspension/Tension/Pilot Make Vol.5 : Page #
3. 4. 5. Sl. No.
Batch No. Electro Mechanical Strength Quantity and Location Loc. No. Qty. as per drg. Qty. in CKT-I Phases R Y B Qty. in CKT-II Phases R Y B Remarks
6.
Insulators are completely cleaned with soft cloth. Glazing is proper. There is no crack, scratch or white spot on its surface.
7. 8.
`R' Clips in Insulators are fitted properly. While Hoisting, no damage caused to insulators.
Vol.5 : Page #
ANNEXURE CF - IV Details of Hardware Fitting 1. 2. 3. 4. Sl. No. Make Batch No. Type of fitting - I/V, Single/Double, Suspension/Tension. Quantity and Location. Loc. No. No. of fittings Phases R Y B Remarks
5. 6.
All Nuts/Bolts properly tightened All components of fittings have been provided as per approved drawings. Dimensions and galvanizing are O.K. any component. and
Fitting is cleaned and there is no damage to 7. 8. All split pins properly provided. In case
after compression recorded as per Ann.CF-IX FOR CONTRACTOR SIGNATURE NAME DESIGNATION DATE
Vol.5 : Page #
ANNEXURE CF - V Sag Measurement for Earthwire and Conductor 1. 2. 3. Sag board fixed between Temperature Measurement of Sag/Tension. Item Sag Tension 4. During conductor 5. paying out/ rough sagging, tension in Phase/Wire No. As per Sag/Tension Chart Actual Loc. No......... and .... ........C
For final sagging, initial stringing chart for conductor and final stringing chart for Earth Wire are used.
ANNEXURE CF - VI Suspension/Tension Clamps for Earthwire 1. 2. 3. Make Batch No. Quantity & Location No. Wire No. Loc. No. Remarks
Sl. No.
4.
All
components
of
clamps
have
been
provided
as
per
Vol.5 : Page #
approved Clamp 5. 6. 7.
drawings.
Dimensions
and
galvanizing
are
O.K.
any component.
All Nuts & Bolts have been properly tightened. Split pins have been properly fixed. In case of Tension clamp, Dimensions before and after compression recorded as per Ann.CF-IX
Vol.5 : Page #
ANNEXURE CF - VII Records of V.D. for Earthwire/Conductor 1. 2. 3. Sl. No. Make Batch No. Quantity & Location Fixed on Loc. No. Fixed towards Loc. No. Phase/wire No. No. of V.D.
4.
All components of V.D.have been provided as per approved drawings. Dimensions and galvanizing are O.K. V.D. is cleaned and there is no damage to any component.
5. 6.
Vol.5 : Page #
ANNEXURE CF - VIII Records of Line spacer/spacer Damper/Jumper spacer 1. 2. 3. Make Batch No. Quantity & Location Span/Loc. No. Phase No. of Spacer
Sl. No.
4.
All
components
of
spacer
have and
been
provided
as are
per O.K.
approved 5. 6.
drawings.
Dimensions
galvanizing
any component.
Vol.5 : Page #
ANNEXURE CF - IX Dimensions for M.S. Joints/tension sets for earthwire and conductor. i) ACSR (Mid span jt./dead end jt./jumper cone/)/ E/W (Mid span jt./ dead end jt./jumper cone)/ ACSR Repair sleeve/T-Clamp. ii) Locn. No. ... ..... ..... ..... ..... iii) Span Loc. No. ..... to .. .. .. .. .. iv) Apprd. drg. Nos...................... v) Details of dimensions
Steel portion As per drg. Bef. Comp. Length Outer dia Aft. Comp. Length C-C F-F Aluminium portion As per drg. Bef. Comp. F-F Length Outer dia Aft. Comp. Length C-C F-F
Type of joint
Vol.5 : Page #
vi) vii)
Bores in the sleeves are perfectly clean. The following may be checked as per approved drawing: a) b) c) d) e) f) Marking and cutting. Correct sizes of dies Centering & fixing of sleeves. Fixing of all the components i.e. Aluminium end pipes, hole plugs etc. Compression of sleeves at specified pressure. Application of filler paste (Zinc chromate). is no crack, bend or any damage to joint
viii) ix)
All the sharp edges have been filed after compression. There after compression.
Vol.5 : Page #
Bibliography
Vol.5 : Page #
"Transmission line structures" by S.S. Murthy and A.R. SanthaKumar. "Manual on Transmission Line Towers" - CBI&P - Technical Report No.9. "Workshop on transmission line"-CBI&PVadodara (29th Nov.- 2nd Dec.,94). "Symposium on Design & Protection of 400 kV Transmission Lines" - CBI&P - Publication No.131 . "Overhead line Practice" by John Mccombe. "Guide to the installation of overhead transmission line conductors" - IEEE Std. -524 - 1992. "Code of practice for line Design, installation and maintenance of overhead power lines"-IS:5613:1989. "Transmission Generating 2, Rev. 6 . construction"-Electricity Thailand Specification No.CPower in of by Grid NR-I" India WR Line Authority,
(9) (10)
Vol.III"
(11) (12)
"List
of
prepared
- Power Grid Corporation of India Ltd. Indian Electricity rules 1956. Indian Electricity Act, 1910.
Vol.5 : Page #
OUR TEAM (1) Sh. V.C. Agarwal, AGM, is B.E. (Civil) and M.E. (Hons.) in Soil Mech. and Fndns. Engg. From Univ. of Roorkee, Roorkee. He (2) Sh. He has 28 yrs. of vast Sr. varied experience Manager, in is in Construction, B.Sc. Engg. & of Planning and Monitoring of large Transmission Projects. D.K. has 17 Valecha, yrs. of
(Electrical) from Reg. Engg. College, Kurukshetra. experience & Planning Monitoring, Construction, Operation Maintenance
Transmission Lines and Substations. (3) Sh. J.K. Parihar, Manager, is B.E. Elect. (Hons.) from Univ. of Jodhpur, Jodhpur. He has 14 yrs. of varied experience & in Planning & of Monitoring, Construction, Operation Maintenance
Transmission Lines and Substations. (4) Sh. R. Nagpal, Engg. 12 Manager, is B.E. Elect. and MBA in (Hons.) from from
Punjab He has
College of
Chandigarh varied
Indira & of
Gandhi National Open Univ., New Delhi. yrs. experience & Planning Monitoring, Construction, Operation Maintenance
Transmission Lines and Substations. (5) Sh. N.K. Rai, Dy. Manager, is B.Sc. Engg. (Mech.) from Birla Institute of Technology, Mesra, Ranchi. He has 19 yrs. of varied experience including 8 yrs. in Indian Army in Stores Management, 11 yrs. in Power Sector in Planning, Monitoring and Contracts Deptt. at Corporate Center.
Vol.5 : Page #
(6)
Sh. B.K. Jana, Dy. Manager, is B.E. (Civil) from Regional Engineering College Durgapur and M.Tech. in Applied Mechanics from I.I.T. Delhi. He has 14 yrs. of varied experience in Design, Planning & Coordination of Sub-station works, TL Fndns., Pile Fndns. & other special heavy Foundations.
(7)
Sh. He
S.K. has 7
Niranjan, yrs. of
is
B.Tech.
(Civil) in design
from of of
Hydro-Electric projects.
Vol.5 : Page #
Transmission Line (Part-1) Vol. 1 Line Survey Vol. 2 Env. Mgmt. Vol. 1 Land & Infrastr.
General Support (Part-3) Vol. 1 MB (Procedures & G. Lines) Vol. 3 Contracts Mgmt. Vol. 4 Budget & Finance
Vol.5 : Page #
Vol. 5 Stringing
Vol.5 : Page #