Professional Documents
Culture Documents
The Royal Society of Edinburgh, Scotlands National Academy, is Scottish Charity No. SC000470
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Natural flow hydro electric generators are only ROC accredited if under 20MW capacity (Declared Net Capacity). Systems with greater capacity than 20MW are not thought to need subsidy. Unless the operational capacity of each natural flow hydro station below and above 20MW is known it will not be possible either to determine the % of electricity generated by Hydro or other renewable energy sources. The correct method of defining the operational capacity of each category of generation must be identified. Arrangements for meeting peak demand in Scotland have not been determined. The following section shows, for each year between 2002 and 2006, the installed capacity and the contribution to the grid from all sources, with a breakdown between different renewable sources. The paper then presents the outcome of submitted proposals for wind farms between 2004 and 2007.
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Table 17: Wind Energy in Scotland, 2008 On-shore (MW) Off-shore (MW) 1,171.28 (54 farms) 10 (1 farm) 651.9 (13 farms) 180 (2 farms) 1,474.45 (48 farms) 0 4,146.72 (90 farms) 0 Source: http://www.bwea.com/ukwed/index.asp
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
Statistical issues
A more comprehensive set of statistics are clearly required. Such a compilation should take the following into account: The operational capacity of each generation source in Scotland must be determined for each annual period. All statistics should be reported as transparently as possible and aggregated to address concerns regarding commercial sensitivity. A more detailed statistical analysis of the data regarding renewable and non-renewable energy sources is required. The categories used to describe generator connections to transmission and distribution networks should be carefully reviewed to determine the actual capacity installed. Such figures should be compared to data published by the British Wind Energy Association and other industry bodies. To determine the actual % of Scotlands generated electricity that comes from each source (both renewable and non-renewable) will require the capacity of natural flow hydro power stations above and below 20MW to be known and the corresponding energy production of each group. The national energy statistics should only include operational generators, additional data should be supplied on planned, consented and in construction generators. The actual performance of each generation source (both renewable and non-renewable) should be monitored to determine the annual capacity factor of each and the contribution to the electricity generated in Scotland. Assumptions regarding capacity factor should not be used to provide the share of electricity generated from renewables. It is important that the true performance of a multisource renewable portfolio is assed by technology and for the renewable sector as a whole.
Discussion Paper: Energy delivered to the Scottish electricity grid 2002-2006, July 2008
10