You are on page 1of 17

NEPEAN ENGINEERING

PTY LTD

NEPEAN ENGINEERING Pty Ltd ABN 53 088 292 013


23 Graham Hill Road (PO Box 56) Narellan NSW 2567 Australia

M: 0407236576 T: F: E: W: +61 2 4646 1511 +61 2 4648 2505 tcb@nepeaneng.com.au www.nepeaneng.com.au

Safe Work Method Statement


Project: Principal Contractor: Work Activity/Task: Area: SWMS No. Revision No: Prepared By: Date: Signature: CBA Commercial Building 6 Bovis Lend Lease Pty Ltd ERECTION AND WELDING OF ATRIUM LIFT STEEL WORK BUILDING 6 ATRIUM STEELWORK BUILDING 6 CBA BUILDING 6 SWMS 003 CBA001-REV02 Tom Buchanan 27/12/2007

Tom Buchanan

Task Details:
Expected start date: 27/11/2007 Expected duration of work; 50 Days Manager: Tom Buchanan 0407236576 No of employees on site: 2 (min) to 10 (max)

Skills/Training Details:
All Personnel must be inducted & added to the Nepean Engineering Project S-Pack prior to commencement of work.

Resources:
Trade(s) involved: Riggers, Crane Drivers, TAs Equipment used: Hydraulic Wrench, Welders Plant required: Crane Truck/s, Crane/s, EWPs, and Mobile Scaffold. Maintenance checks: Electric register for leads & power tools, Log book for applicable plant Materials used: Grout & Bolts & Electrodes

Page 1 of 18

NEPEAN ENGINEERING
PTY LTD

NEPEAN ENGINEERING Pty Ltd ABN 53 088 292 013


23 Graham Hill Road (PO Box 56) Narellan NSW 2567 Australia

M: 0407236576 T: F: E: W: +61 2 4646 1511 +61 2 4648 2505 tcb@nepeaneng.com.au www.nepeaneng.com.au

LEGISTRATION, CODES OT PRACTICE & GUIDELINES REGISTER


The following Legist ration, Standards, Code Of Practice, Guidelines are provided as being relevant to the activities in this SWMS OH&S Act (NSW) 2000 WORKCOVER APPROVED INDUSTRY CODES OF PRACTICE Code Of Practice: Amenities for construction work ( No. 317) Code Of Practice: Electrical practices for construction work (No. 301) Code of practice: Noise Management and protection of hearing at work (No. 150) Code of practice: OHS Consultation (No. 311) Code of practice: OHS Induction training for construction work (No. 302 Code of practice: Overhead protective structures (No. 17) Code of practice: Tunnels Under Construction (No. 10) Code of practice: Work in hot or cold environments (No. 309) Code of practice: Moving Plant on Construction sites. OH&S Regulation 2001 GUIDES Use of personal protective equipment at work - a guidance note. Skin cancer and outdoor workers - a guide for workers - the choice is ours (No. 117) Shin cancer and outdoor workers - a guide for employers (No. 116) Dust in the workplace (No. 351) Hazpak! Making our workplace safer (No. 228) High visibility clothing OHS Safety Guide Standards and codes offer practical guidance on health and safety for construction work. However, these are subject to change from time to time. For further information contact the workcover assistance services on: 131050

Page 2 of 18

AUSTRALIAN STANDARDS REGISTER


The following Legist ration, Standards, Codes Of Practice, Guidelines are provided as being relevant to the activities in this SWMS

AUSTRALIAN STANDARDS
Standards mat be obtained directly from Standards Australia (www.standards.com.au) National Standard for Construction Work [NOHSC:1016 (2005)

AS/NZS 1576.1:1995 Scaffolding - General Requirements AS 1657-1992 Fixed platforms, walkways, stairways and ladders - design, construction and installation (an approved industry code of practice) AS/NZS 1800:1998 Occupational protective helmets - selection, care and use AS/NZS 1801:1997 Occupational protective helmets AS/NZS 1336:1997 Recommended practices for occupational eye protection AS/NZS 1337:1992 Eye protectors for industrial applications AS/NZS 1338.2:1992 Filters for eye protectors - filters for protection against ultraviolet radiation AS/NZS 1338.3:1992 Filters for eye protectors - Filters for protection against infra-red radiation AS 1269.3:1998 Occupational noise management - Hearing protectors program AS 1270:2002 Acoustics - Hearing protectors (an approved industry code of practice) AS/NZS 1715:1994 Selection, use and maintained of respiratory protective devices AS/NZS 1716:2003 Respiratory protective devices (an approved industry code of practice) AS 1891.4:2000 Industrial fall-arrest systems and devices (an approved industry code of practice) AS/NZS 1906.4:1997 Retro reflective materials and devices for road traffic control purposes - high visibility materials for safety garments AS/NZS 4602:1999 High visibility safety garments AS/NZS 2161.2:1998 Occupational protective gloves - general requirements AS/NZS 2161.3:1998 Occupational protective gloves - Protection against mechanical risks

Page 3 of 18

NEPEAN ENGINEERING
PTY LTD

NEPEAN ENGINEERING Pty Ltd ABN 53 088 292 013


23 Graham Hill Road (PO Box 56) Narellan NSW 2567 Australia

M: 0407236576 T: F: E: W: +61 2 4646 1511 +61 2 4648 2505 tcb@nepeaneng.com.au www.nepeaneng.com.au

AUSTRALIAN STANDARDS REGISTER


The following Legislation, Standards, Codes of Practice, Guidelines are provided as being relevant to the activities in this SWMS AS/NZS 2161.5:1998 Occupational protective gloves - Protection against the cold AS 2225:1994 Insulating gloves for electrical purposes AS 2359.2:1985 Industrial trucks known as the SAA industrial code of operation. (an approved industry code of practice) (this covers forklift use) AS 2550.1-2002 Cranes, hoist and winches - Safe use part 1: General requirements (an approved industry code of practice) NZS/AS 2865:2001 Safe work in a confined space

TRAFFIC CONTROL STANDARDS


AS 1742.1-2003 Manual of uniform traffic control devices - General introduction and index of signs AS 1742.2-1994 Manual of uniform traffic control devices - Traffic control devices for general use AS 1742.10-1990 Manual of uniform traffic control devices - Pedestrian control and protection

Page 4 of 18

NEPEAN ENGINEERING
PTY LTD

NEPEAN ENGINEERING Pty Ltd ABN 53 088 292 013


23 Graham Hill Road (PO Box 56) Narellan NSW 2567 Australia

M: 0407236576 T: F: E: W: +61 2 4646 1511 +61 2 4648 2505 tcb@nepeaneng.com.au www.nepeaneng.com.au

Skills/Training Details:
Employee Name Qualifications On-site experience Additional training required for this task

Page 5 of 18

Risk Score Calculator


Disaster Likelihood Almost certain Likely Possible Remotely possible Practically impossible Very Serious Consequence Substantial Serious Minor

Likelihood/ Consequence
The hazard has the potential to: - permanently disable or kill; - cause major damage to structure; - have significant impact on surrounding population and environment. The hazard has the potential to: - temporarily disable or seriously injure; - cause minor damage to the structure; - breach the site boundary and pollute local environment. The hazard has the potential to: - cause minor injury; - be contained within the site boundary.

Risk Class

1 1 1 2 2

1 1 2 2 3

1 2 2 2 3

2 2 2 3 3

2 2 3 3 3

1 2 3

Installation Procedure, Hazard Identification & Risk Control


Job Step (Break the job down into steps) Site Induction Potential Hazard (What can harm you?) General. Risk Class Controls (What you are going to do to make the job as safe as possible All personnel to be inducted into company EHS plan prior to induction All personnel to be inducted to the SWMS before being site inducted All personnel are to attend a Site Specific Induction. 2 . 2 Personal Protective Equipment (PPE) Various. 2 The Following PPE is to be used during this taskHardhats to be worn at all times, brim attachment to be worn when working outdoors. Safety footwear & high visibility protective clothing to be worn at all times. 30+ sunscreen to be applied regularly to all exposed skin whilst working outdoors. Riggers Gloves to be worn at all times Safety glasses are now mandatory on all Nepean Engineering projects Glasses to be worn at all times UV protection glasses to be worn when excessive sun glare and glare from visible radiation is present. Hearing protection to be worn whilst operating (or near) noisy machinery etc.and whilst drilling anchors Higher rated protection may be required in an Page 6 of 18 TOM BUCHANAN Person (Who will ensure this happens?) TOM BUCHANAN

Item 1 . 1

extremely noisy environment. Above 80 dsi Dust/face mask, respirator or similar to be worn when working in area where inhalation danger is present, this includes concrete dust, welding fumes and chemicals A harness to be worn whilst operating boom type EWPs personnel to be trained in safe use of harness TOM BUCHANAN

Delivery of Lift Shafts

Transport arrival route

As per RTA Permit transport truck will arrive via Home Bush bay drive onto Australia Ave then turn into Herb Elliott Ave at 4 am Transport Pilot vehicles will secure Herb Elliott Ave and stay in place to Nepeans Two warning Vehicles are in place and implement traffic control plan Clearwater will provide Traffic Management Services from 0400 hrs to 0800 hrs

Unload Trucks and move materials (incl steelwork) to work areas.

Load falling Loading & Unloading Transport.

All Steel Members must be removed from transport vehicle with BLL Crane Crew and lowered into position to works area Lifts will not be removed until all Traffic Management Plan 84 has been implemented and all Clearwater employees are ready to start Once load has been removed transport truck is to remove itself from Herb Elliott Ave and clear all road ways All traffic control area will be cleared and road cleared for all traffic

Tom Buchanan

Straining/pulling muscles - Manual Lifting. Traffic control

Ensure an adequate quantity of personnel carry out lifting within safe work practice guidelines. Otherwise mechanical lifting only Ensure TCP is Current and approved by BLL before delivery

TOM BUCHANAN TOM BUCHANAN

Page 7 of 18

Working with ewps to erect lift shaft members

Delivery

Operator be trained and be familiar with controls and general requirements of machine. EWP must have a checklist from hire company that confirms EWP is safe to use and signed by a licensed mechanic. Certificate of competency (EWP) required to operate boom lifts over 11M

TOM BUCHANAN

Pre-Start Daily inspection

Death or serious injury

Carry out daily inspection / checks as per manufacturers recommendations in the operators manual EWP log book to be filled out daily and all safety checks completed as per logbook. Ensure that the EWP services have been completed as per manufactures requirements.

TOM BUCHANAN

Read and familiarize yourself with any safety stickers and hazard stickers that you may find on the EWP Record inspections in the machines log book and sign off accordingly. Any faults or mechanical problems to be reported immediately. Operating EWP - Fall from platform. - Tip m/c over. - Collision injury 1 Never stand or sit on kick boards, handrails or mid-rails, Ensure gate is securely closed. Ensure tyres are inflated to correct pressures. Never operate when wind speeds are above 12.5m/sec. Ensure outriggers (if fitted) are fully extended and on a solid bearing. Ensure you look up, down, forward, backwards, left and right when driving. -Structural failure 1 Machinery loads on slab to be approved by Structural Engineer prior coming to site TOM BUCHANAN

Working from EWP

- Tip over, injury to people below. - Fall from platform.

Do not use EWP as a crane, do not overload the platform, observe and do not exceed SWL.

TOM BUCHANAN

Page 8 of 18

-tools falling Never use to push or pull other objects. Ensure all tools and materials are safely secured with lanyards at all times Set up an exclusion zone around the base of the EWP and display signage if necessary. Keep away from pinch points. Safety harness to be worn and connected at all times in boom type EWPs. Never enter or exit platform when extended. Never use ladders or other objects in the EWP to gain additional height. Securing the EWP after use. Unauthorised use. 1 Lower platform at end of shift. Position m/c in safe location. Remove keys and secure Refueling the EWP. -Fire -Slips, trips, falls -Spills. -Contact with chemical. -Inhaled petrol vapor. 1 Equipment is to be turned off and shut down. Do not use mobile phones. Avoid sources of ignition, heat, sparks. Ensure fully charged carbon dioxide, Dry chemical or foam extinguisher is in close proximity when refueling. Ensure funnel or nozzle attachment is used when refueling. Avoid contact with eyes, eye protection to be worn. Over spills to be immediately cleaned up. A spill kit (cats Litter) is to be in tool box at all times ready for spillages Remove any contaminated clothing and wash prior to re-use. Do not intentionally inhale vapors. Charging batteries Electrocution 1 Use only earth leakage supply. Extension leads to be inspected before use, and elevated off the ground using insulated hooks or stands. All electrical equipment to be tested & tagged every month. Page 9 of 18 TOM BUCHANAN TOM BUCHANAN TOM BUCHANAN

Keep away from water and damp areas.

Securing the EWP after use.

Unauthorised use.

Lower platform at end of shift. Position m/c in safe location. Remove keys and secure.

TOM BUCHANAN

Erecting steel using crane

Nepean Engineering Pty Ltd Employees and Contractors not aware of the current site work activities, hazards and risks.

All Employees and Contractors reporting for work at the site must possess the necessary trade qualifications to meet the requirements of competent person definition under the regulation for the work they will perform, a valid Construction Industry General Induction Card and be inducted into the Principal Contractor Project On arrival at the worksite report to the Site Supervisor Via 2 - way radio. Follow instructions for access to the site and meet with the Site Supervisor. Flashing lights on vehicles must be turned on and all personnel are to wear high visibility vest, hard hats, safety boots, and eye protection and riggers gloves at all times. Drivers and pedestrians must observe the site traffic rules and the directions of spotters/traffic controllers. install signs and barriers to provide an exclusion zone for the job On their initial arrival on site all Nepean Engineering Employees and Contractors must attend a toolbox meeting to:

TOM BUCHANAN

Discuss the identified hazards * Assess the risk's Use the information contained in this SWMS, Industry Codes of Practice and Standards, To: Agree on the risk control Measures Document them on the JSA and Sign the Tool Box Talk before starting Any work at the job site.

Pre-start daily inspection

Death or serious injury.

Carry out daily inspection / checks as per manufacturers recommendations in the operators crane manual

Page 10 of 18

Crane log book to be filled out daily and all safety checks completed as per logbook. Lifting schedule to be completed. Read and familiarize yourself with any safety stickers and decals on the crane Record inspections in the machines log book and sign off accordingly. Any faults or mechanical problems to be reported immediately. Machine not to be used until faults are fixed and/or a service is carried out Operation of the Crane Traffic Movement on site. Failure of the Crane 2 Observe site traffic rules, the directions of traffic controllers and/or rigger/Dogman. Unsure that the crane is big enough to lift the load. Crane driver and Rigger/Dogman determine the crane capacity to lift the load within the correct SWL of the Crane. You will ensure that outrigger are set as per structural Engineers specs two forward working outriggers must have plates underneath wooden packers The crane has current approval by a statutory authority. A hired in plant inspection report has been carried out for the crane by a competent person. Records of crane inspections, services record, changes to ropes, are maintained. A.S. 2250 is the applicable standard. A competency assessment has been carried out for the crane driver that matches the requirements for operating the crane. A competency assessment has been carried out for the Rigger / Dogman that matches the requirements for the lift to be undertaken. Ensure that the lift has been assessed and the method agreed between the crane driver and Rigger / Dogman prior to the lift being made Asses load for potential movement before loosening restraints. Do not stand on or amongst load when restraints are being loosened. TOM BUCHANAN

Outrigger compaction failure

Failure of Lifting gear

Failure of driver

Failure of Rigger/Dogman

Failure of the Operating system

Movement of load when removing restraints

Page 11 of 18

Placement of Materials

Ensure Materials are stored well clear of vehicle and pedestrian traffic ways. Store materials in a manner that will prevent unexpected movement under the influence of gravity. If there is any risk of unexpected movement the materials must be adequately restrained.

Pinch and crush points in formed by the slewing action of the crane

Ensure direct eye contact is maintained with the Rigger Dogman at all times and do not allow access to the danger area formed by the slewing action of the crane. It is essential that all parties agree, understand and obey the work method and communication selected for the lift

Rigging, Slinging and Dogging Securing the Crane after use.

Load or parts of load slipping and/or falling Edges on load causing damage to load lifting equipment Inappropriate work practices using crane to work at height Inappropriate rope fastening

Secure every part of a load whilst raised or lowered to prevent danger from slipping or displacement. Take adequate precautions to prevent the edges of a load from damaging any sling, rope or chain Prohibit people being suspended from the hook of any crane to do any work.

TOM BUCHANAN

Use only rope clips of approved design and construction, and only for such purposes and in such way as is approved. Prohibit Riggers from A) Riding the hook or the load B) Sliding down lines and guys C) Descending by "skinning" Columns D) Jumping from elevated surfaces

Unaccredited Rigger / Dogman or not working to accreditation criteria

Rigger / Dogman using Tag Lines Unauthorised use.

Use clean, dry tag lines made from natural fibre or non-conductive materials. Position crane in safe location. Remove keys and secure.

Page 12 of 18

Refueling the Crane.

-Fire

Crane is to be turned off and shut down. Do not use mobile phones. Avoid sources of ignition, heat, sparks. Ensure fully charged carbon dioxide, Dry chemical or foam extinguisher is in close proximity when refueling.

-Slips, trips, fall. -Spills. -Contact with chemical.

2 2 2

Ensure funnel or nozzle attachment is used when refueling. Avoid contact with eyes, eye protection to be worn. Over spills to be immediately cleaned up. A spill kit (cats Litter) is to be in tool box at all times ready for spillages Remove any contaminated clothing and wash prior to re-use.

-Inhaled petrol vapor. 6 Install Chemset/Hold down Bolts Mark Chemset locations on the slab using paint. Chemset Locations checked. Drill & Install Chemical Anchors Reaction to chemicals Using marking paint Structural damage to slab Electrocution Using electrical equipment.

Do not intentionally inhale vapors.

TOM BUCHANAN

Personnel to be trained in the use of the product per the attached MSDS.

TOM BUCHANAN

Noise

Chemset Locations to be checked by Post-Tensioning Contractor. Written confirmation required prior to drilling slab. All electrical leads and equipment to be tagged monthly by a licensed electrician. and, A safety overload device is to be used on all electrical equipment. and, Personnel to be aware of danger of electrocution from over-head or hidden cables, if in doubt ask then insulate/isolate. All workers must where hearing protection at all times whilst working with drills.

TOM BUCHANAN TOM BUCHANAN

TOM BUCHANAN

Dust Inhalation

Dust mask to be worn if excessive dust is created whilst drilling holes. and, Whilst cleaning out drilled holes with a puffer.

TOM BUCHANAN

Page 13 of 18

Dust/Foreign body blown into eyes. Sunburn Working Outdoors. Reaction to chemicals Installing Hilti chemsets. 6 Install lift shaft Members Lifting steel Members into location

Safety Glasses to be worn whilst cleaning out drilled holes with a puffer. Wide brim hat, tinted UV safety glasses & full length clothing to be worn at all times, 30+ sunscreen to be applied regularly to all exposed skin. Personnel to be trained in the use of the product per the attached MSDS.

TOM BUCHANAN TOM BUCHANAN

TOM BUCHANAN

Set up an exclusion zone around the atrium area and display signage if anyone comes into the exclusion zone BLL to be informed and a near miss / hazard identification form filled out and Given to site safety officer to take action BLL will lift steel that has been unloaded and place it into works area Nepean will secure the lift shaft with our crane and lift into position. Once steel members are at correct position and surveyed. members to be secured down to hold down bolts before crane releases the weight off the hook Once crane has released the weight riggers to check again all connections are correct, once checked then hook can be released Steel to be surveyed again to ensure correct positions and RLs Sent to BLL

TOM BUCHANAN

Welding and oxy cutting steel shs to fit lift shaft

Install shs members and weld into place at all levels

After each section of lift shaft members have been erected, welding of the shs stubs will be required. Access will be gained to areas using only telescopic booms or spider booms All areas are to be confirmed to be barrier tape off and signs up Flash shield to be installed before welding starts shield is to be continually monitor for effectiveness

TOM BUCHANAN

2 2 2

Page 14 of 18

Damage to steel structure.

1-3

Builder to approve all site-welds prior to commencement (unless shown on shop drawings). Site Welding only to be completed by a qualified welder, NDT is reqd for 100% of all butt welds. All repairs to be painted with cold gal (final touch up painting to be completed following installation)

TOM BUCHANAN

Electrocution Using electrical equipment.

1-2

All electrical leads and equipment to be tagged monthly by a licensed electrician. A safety overload device is to be used on all electrical equipment.

TOM BUCHANAN

Welding flash, sparks or fire Stick (Arc) Welding.

Safety work clothes to be worn by operator i.e. long sleeve shirt, long pants or overalls, safety footwear, welding gloves and helmet. Work area to be examined and all external fuels removed (i.e. cardboard, timber, fabric, general rubbish, petrol). Fire extinguisher is to be on hand at all times. Welding screen used to block arc when area is exposed to others. All welds to be marked HOT with chalk upon completion. Fire blanket to be used to contain sparks (if required). Area below to be cordoned off & warning signage displayed and/or, Extra person positioned to act as a spotter.

TOM BUCHANAN

Fire/Explosion Oxy Cutting

Gas bottles to be stored/moved/operated in a safe manner, Flash-back arrestors to be used, and regulators/hoses/torches to be inspected for damage prior to use. and, Work area to be examined and all external fuels removed (i.e. cardboard, timber, fabric, general rubbish, petrol). Gas bottles to be stored separately when not in use in a lockable cage and fire extinguisher attached

TOM BUCHANAN

Page 15 of 18

All signage to be attached to gas cage Supervisors contact details to be attached to gas cages also Sparks/ hot metal Oxy Cutting 2 Safety work clothes to be worn by operator i.e. long sleeve shirt, long pants or overalls, welding gloves, safety footwear and dark protective eyewear. Fire extinguisher is to be on hand at all times. All cut steel pieces to be marked HOT with chalk upon completion. Area below to be cordoned off & warning signage displayed and/or, Extra person positioned to act as a spotter. Area to be re-inspected 30 mins after work has nee completed to ensure no fire has started Reaction to chemicals - Using Cold-Gal touchup paint. 8 Plumb/Align Steelwork and Fully Tension all bolted connections. Damage to steel structure. And Noise from Tighten up bolts 3 Personnel to be trained in the use of the product per the attached MSDS. TOM BUCHANAN TOM BUCHANAN

1-3

Plumb/Align steelwork to erection Tolerances as per AS4100. and QA plan All bolted connections are to be installed as per shop drawings. Joints containing a number of bolts shall be tightened from the centre outwards (per 15.2.4/AS4100). All bolts are to be wrench tight using only a hydraulic wrench no electric or air compressed wrenches to be used

TOM BUCHANAN

Grout & Tidy Up.

Reaction to chemicals Installing grout.

Personnel to be trained in the use of the product per the attached MSDS.

TOM BUCHANAN

Slips, trips & falls

1-3

Personnel are to ensure the work area is kept clean and free from trip hazards at all times.

TOM BUCHANAN

Page 16 of 18

I have read and understood the above SWMS and I will carry out all work in accordance with the procedures and safety controls listed. If the work or conditions differ to that stated above, I will consult with the Project/Site Manager to seek directions prior to continuing work.
NAME DATE SIGN

Page 17 of 18

You might also like