330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

Part III

Commissioning Scheme for Excitation System

Sichuan Tongneng Electric Science &Technology co., ltd August 2008

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

Contents
1. 2. 3. 4. Overview Purpose of Commissioning Basis of compilation General Situation and Basic Technical

Parameters of Equipment 5. Instruments & Equipment for

Commissioning 6. 7. 8. 9. Scope of Commissioning Organization and work division Requirements for commissioning Commissioning Method and Working

Procedures 10. Quality Control Measures 11. Safety Precautions in Commissioning

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

1. Overview

The excitation device of India Tengda (2330MW) Coal-fired Power Plant is a kind of microcomputer excitation regulation device (inclusive of a field regulator screen, a rectifier cabinet and a field suppression panel) supplied in complete sets by a generator plant. A generator outputs voltage via an excitation transformer at its terminal, and the voltage is rectified by a static bridge-type controlled silicon rectifier and finally supplied for excitation, which is the so-called self-shunt excitation.

2. Test content and purpose Through a full-group dynamic starting test of the excitation system, to inspect the cooperation of diverse parts of the excitation system and the full-group property and to check whether or not the excitation system is able to meet the machine sets actual operation requirement under diversifying operating conditions and whether or not the specification is satisfied, in order to make the machine set able to combined to the grid and to operate normally.

3. Basis of compilation 3.1 Regulations on the Starting and Acceptance of the Basic Constructions of Thermal

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

Power Plant (1996 version), D.L.B.D.J [1996] No.159 3.2 Regulations on the Starting Commissioning of Thermal Power Plants, J.Z [1996] No. 40, issued by the Construction Coordination Division of Ministry of Water Resources and Power 3.3 Standards for the Quality Inspection and Evaluation of the Commissioning and Trial Run of Thermal Power Plants, J.Z.[1996] No.111, issued by the Construction Coordination Division of Ministry of Water Resources and Power 3.4 Standards for the Quality Inspection and Evaluation of the Construction of Thermal Power Projects (Electric Section) 3.5 Regulation of Safety Operation in Power Engineering Construction, DL5009.96 (Part of Thermal Power Plant) 3.6 Code of Safety Operation in Power Engineering Construction (Electric Part of Power Plants and Substation) 3.7 Standard for the Evaluation of the Commissioning of Thermal Power Units (1998 version) (Ministry of Power Industry) 3.8 Standard for the Dynamic Evaluation of the Commissioning of Thermal Power Units (Trial) (1998 version) (State Power Corporation) 3.9 Technical Specification for Power Construction and Acceptance (Electric Part) 3.10 Typical Outlines for the Quality Supervision and Inspection of Key Items of Thermal Power and Power Transmission and Conversion Projects 3.11 Typical Outlines for the Quality Supervision and Inspection of the Full-load Trial Run of Complete Devices of Fundamental Projects in Power Construction

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

3.12 Standard for Hand-over Test of Electric Equipment in Electric Equipment Installation Engineering, GB50150 3.13 Electrical Relay 3.14 Regulation on the Inspection of Electrical Indicating Instruments 3.15 Regulations on the Inspection on the Full-automatic Devices Regarding Relay Protection and Power Grid Safety 3.16 Technical Conditions for the inverter power supply of Static Relay Protection Devices 3.17 Key Points of Anti-Accident Measures by Power System Relaying and Security Automatic Equipment 3.18 Technical Regulation for Relaying and the Safety Automatic Equipment of Electricity Grid, DL 400-91 3.19 Technical Conditions of Static Self Shunt Excitation System for Large Turbine Generator 3.20 Safety Regulations on the Site Work of Full-automatic Devices Regarding Relay Protection and Power Grid Safety 3.21 The technical data provided by the factory and relevant design drawings provided by the design unit 3.22 Relevant quality management documents of the company 4. General Situation and Basic Technical Parameters of Equipment (parameters are not available at present)

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

5. Instruments & Equipment for Commissioning Two-channel memory digital oscillograph: 1 Microcomputer protection check gauge: 1 Digital insulated resistance tester: 1 Multi-channel transient coulometric analysis instrument: 1 Phase sequence indicator: 1 Digital clamp current phase meter: 1 Digital multimeter: 1

6. Scope of Commissioning 6.1 The primary electric equipment involved in the Commissioning mainly refers to a generator, the CT, PT and lightning arrester at the generator side as well as those items arranged at the neutrality point side of the generator, namely, a grounding transformer, cables, enclosed busbar, the magnetic blow-out switch, rectifying device, overvoltage protection and demagnetization resistance. 6.2 The secondary equipment involved in the Commissioning mainly include a generator-transformer unit relay protector, an automatic field regulator, a DCS electrical control system, a DCS electrical data collecting system, electric measuring instruments, direct current systems secondary equipment, etc.

7. The work and conditions should be finished or available before the commencement of the test

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

7.1 The conditions should be available prior to the test 7.1.1 The primary and secondary equipment of the generator-transformer unit system have been installed and debugged and verified in inspection to comply with the requirements of the design specification. 7.1.2 The primary and secondary equipment of all units of the excitation system have all been tested and their properties have been verified to comply with the requirements; the Commissioning records are complete; and the excitation system agrees with the requirement of commission and is verified in inspection to be consistent with relevant national standard and with the design specification. 7.1.3 The test on the excitation systems static property has been finished and the property of the excitation system has been verified to agree with the design specification. 7.1.4 The interlocking tests of the excitation device and the generator-transformer unit protector have been done, and the acceptances were qualified. 7.1.5 All inspections have been finished before the starting of the machine set. Upon the instruct of the trial run command center, the complete machine set has been in a status of starting test, and the turbine is in a starting acceleration with a rotating speed stabilized at 3000r.p.m. 7.2 Main inspection items before the test 7.2.1 The local and remote operations of the excitation system were tested to be correct, and the systems all control signals and measurement circuits meet the

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

requirement of commission. 7.2.2 In endeavor to avoid the wrong voltage increase of the generator, inspections should be made to make sure that all switches of the console, the DCS computer, the voltage regulation cabinet, the rectifier cabinet and the field discharge cabinet are consistent with the requirement of commission and in a disconnected or forbidden status. 7.2.3 After the test on the generator property, inspection should be done to the generators residual voltage (for sake of safety, it is necessary to measure the secondary value before the primary value. Once the primary value measured is lower than 500V, the phase of the residual voltage at the primary side of the generator should be measured). Data shall be put down when the rotating speed is 3000r.p.m. 7.2.4 The design drawings and manufacturer data as well as diverse fuses and fuse protectors should be well prepared. 7.3 Work should be finished before the starting 7.3.1 The diesel generator was debugged and verified to be qualified in the inspection. 7.3.2 The security of the emergency power supply is reliable according to the test. 7.3.3 The direct current system (storage battery) is tested to be reliable. 7.4 The inspections prior to the starting 7.4.1 Primary system 7.4.1.1 Make sure the breaker of the main transformers high-voltage side is at the switching-off position;

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

7.4.1.2 Make sure isolating switch of the main transformers high-voltage side is on the off-position; 7.4.1.3 Make sure the grounding disconnecting links at both sides of the isolating switch of the main transformers high-voltage side are on the off-position; 7.4.1.4 The grounding disconnecting links of the neutral point of the main transformer are switched on; 7.4.1.5 The breakers of the excitation system are at the at the switching-off position; and the disconnecting link at the AC/DC side of the rectifier cubice is on the off-position; 7.4.1.6 The voltage mutual inductor of the incoming wire of the 6kV station-service working power supply is at the operating position and the secondary fuse (switch) is in the state of commission; 7.4.1.7 The main transformer and the station-service hypervariable cooling system are in the state of commission. 7.4.2 The second order system 7.4.2.1 Inspect to make sure the direct current switch for controlling the breaker at the high-voltage side of the main transformer is quit; 7.4.2.2 Inspect to make sure the direct current switch for controlling the breaker of the magnetic field is quit; 7.4.2.3 Inspect and make sure the direct current switch of the signal loop is put into operation; 7.4.2.4 Inspect and make sure the protective direct current power switch is put into

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

operation; 7.4.2.5 The PT secondary fuse at the generators exit is put into operation. 7.4.2.6 Protection 7.4.2.6.1 Inspect and confirm the protection items in need: including heat engineering protection, generator water beak protection, generator stator overcurrent protection, generator stator overloading protection, generator negative-sequence overcurrent protection, generator-transformer unit differential protection, main transformer differential protection, generator differential protection, overexcitation protection, overvoltage protection, main transformer non-electric quantity protection, exciting converter overcurrent protection, exciting converter overloading protection, exciting converter fault protection and so on. The keep plates of the magnetic field breakers of the protective exits above are put into operation. 7.4.2.6.2 Inspect and make sure the protection or protective keep plates which shall quite, including the stator grounding protection, the reverse power protection, the field loss protection, the loss of synchronism protection of generator, the breaker failure protection. Inspect and make sure the interlocking protection keep plate (the main valve is switched off) of the turbine is on the off-position.

8. Organization and work division 8.1 The measure should be discussed by related departments and countersigned by relevant units. It can be executed when it is approved by the command center after the trial run.

10

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

8.2 In order to shorten the test time and assure the test safety, all units and test personnel involved in the starting test should cooperate mutually. 8.3 The test operation is executed by the Commissioning unit, with the cooperation of the installation unit. 8.4 The operation and patrolling of primary equipment are undertaken by the line personnel of the power plant and the installation unit jointly. 8.5 The shift supervisor of the power plant takes charge of all matters with regards to dispatching and contact. 8.6 The line personnel of the power plant are responsible to execute the excitation systems operations according to the operation regulations after the paralleling of the generators.

9. Commissioning Method and Working Procedures 9.1 The electromagnetism excitation pressurizing of the generator and the no-load test of excitation system 9.1.1 Inspect the electromagnetism excitation power supply. The AC major loop and DC operational power supply should be put into operation normally. 9.1.2 Inspect and make sure the 220V DC control power supply of the control signal loop of magnetic blow-out switch has been put into operation. After the DC control and DC signal air switch on the field suppression panel is switched on, the switching-off indicator lamp of the magnetic field breaker on the excitation panel should be on. When operation is performed to the

11

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

remote/local option switch on the field suppression panel and the local mode is chosen, and the magnetic field breaker is switched on, the switching-on indicator lamp for the magnetic field breaker on the field suppression panel should be on. Select the Current Regulate mode on the excitation regulation cabinet to reach electromagnetism excitation under the FCR control manner, and increase the voltage manually to 20% of the rated voltage. At this time, check the amplitude, phase and phase sequence of the PT secondary loop to make sure they are correct. After that, raise the voltage manually to the rated value and switch on the No.1 and No.2 fan start switches on the rectifier cubice to start the fan. When the voltage gets steady, measure the no-load setting range under the FCR control manner, and the result should comply with the set parameters. Finally, bring down the excitation manually to zero. 9.1.3 Put the generators electromagnetism excitation power supplies (including the 380V AC main power supply and the 220V DC operational power supply) into service. And then choose the Voltage Regulate for AVR and select Local Operation button on the excitation regulation screen to make the generator undertake electromagnetism excitation under the control mode of AVR. Take magnetic field voltage curve, magnetic field current curve and generator terminal voltage curve in the generators electromagnetism excitation course. Make sure the voltage overshoot of the generators stator should be smaller than 5% and record the overshoot time. After the electromagnetism excitation is confirmed to be successful, regulate the

12

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

magneto-increasing/magneto-decreasing switch and observe carefully to see whether or not the contents displayed on the automatic field regulator such as the generators excitation current, excitation voltage and stator voltage are normal. 9.1.4 Measure the no-load setting range under the control manner of AVR, and the result should meet the set parameter. 9.1.5 Decrease the generators voltage to the lowest level. After the contravariant field suppression, put down the magnetic field voltage curve, magnetic field current curve and generator terminal voltage curve in the field suppression, measure the de-excitation time-constant and check the operating status of the field suppression device. 9.1.6 After the electromagnetism excitation reaches to the rated voltage (select the Remote Operate button under the control manner of AVR and operate on the electric control DCS for electromagnetism excitation), conduct the contravariant field suppression manually. Take the magnetic field voltage curve, magnetic field current curve and generator terminal voltage curve in the field suppression. 9.1.7 After the electromagnetism excitation reaches to the rated voltage (select the Remote Operate button under the control manner of AVR and operate on the computer for electromagnetism excitation), conduct the field suppression by switching off the magnetic blow-out switch manually. Take the magnetic field voltage curve, magnetic field current curve and generator terminal voltage curve in the field suppression. 9.1.8 Employ the soft start function of the system and conduct the electromagnetism

13

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

excitation locally under the control manner of AVR. Take the magnetic field voltage curve, magnetic field current curve and generator terminal voltage curve in the generators electromagnetism excitation course. Pay attention to compare the changes of the voltage overshoot and the overshoot time. 9.1.9 The frequency property and V/Hz limit test under the control manner of AVR Make the turbine change the generators rotating speed, make a frequency change range of 3Hz, measure the alteration value of the generator terminal voltage and calculate the change ratio between the generator terminal voltage and frequency. Bring down the generators rotary speed continuously to V/Hz limiter action. The actually measured frequency at this time should be 45.5Hz or so. Resume the generators rotating speed to the rated value and lift the generators voltage to V/Hz limiter action. And the generators voltage at this time should be 110% or so. 9.2 The property test of the field regulator on the condition of the generators rated rotating speed 9.2.1 Test on the mutual switching of the regulators No.1 online passage and No.2 online passage Under the control manner of AVR, the electromagnetism excitation advances till the generators voltage reaches the rated value. At this time, the automatic voltage regulator No.1 passage is the online passage and the automatic voltage regulator No.2 passage is a hot standby passage. The mutual switching between these two passages should not result in any change of the generators voltage. When the online passage regulator is removed a failure of the online passage regulator is simulated, the

14

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

online passage will send out a failure signal and the hot standby passage will come into service automatically. At this time, the hot standby passage will execute the control signal and the online passage control signal is locked. Take the generators magnetic field voltage curve, magnetic field current curve and terminal voltage curve. The generators voltage during this process should have no change. If any abnormal situation emerges from the switching test, conduct the contravariant field suppression and switch off the magnetic blow-out switch manually. Test should be conducted again when the abnormal situation disappear in the inspection. 9.2.2 Test on the mutual switching of the regulators AVR passage and FCR passage Conduct electromagnetism excitation and lift the generators voltage to the rated value under the control manner of AVR. Switch AVR to FCR manually and take the generators magnetic field voltage curve, magnetic field current curve and terminal voltage curve. No any voltage change of the generator should occur in the switching. Switch FCR to AVR when the present control manner is FCR and take the generators magnetic field voltage curve, magnetic field current curve and terminal voltage curve. No any voltage change of the generator should occur in the switching. 9.2.3 Test on the overshoot and regulation time in a 10% step response Conduct electromagnetism excitation and lift the generators voltage to the rated value under the control manner of AVR. In the system, the step response parameters are selected and the step response test is conducted, ranging from 5% to 10% in turn. Take the generators magnetic field voltage curve, magnetic field current curve and terminal voltage curve. Pay attention to measure the overshoot and regulation

15

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

time. 9.2.4 Inspection on the voltage regulation of the automatic voltage regulators (one set of regulators is removed or one set of failures is simulated) The automatic voltage regulator s No.1 passage work separately. When Magneto-increasing and Magneto-decreasing switches are used to increase or decrease the excitation current of the generator, the voltage changes of the generator should be stable. When the No.1 passage is switched into the No.2 passage of the automatic voltage regulator, the generator s voltage should be stable and see no fluctuation. Remove the No.1 passage and make the No.2 passage operate separately. When Magneto-increasing and Magneto-decreasing

switches are used to increase or decrease the excitation current of the generator, the voltage changes of the generator should be stable. 9.2.4 Test on the power source of the regulator: switch off the DC mains switch of the regulator (the +24V power sources air switches B5.1 and B5.2) and inspect the operating status of the regulator. 9.2.5 PT wire break test: under the control manner of AVR, disconnect the switches at the secondary sides of the two PT loops to simulate the PT wire break, and the regulator should be able to switch automatically in this situation. Take the generator s magnetic field current and the magnetic field voltage. Observe the generator s magnetic field current

16

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

to make sure there is no fluctuation. 9.3 Test on the excitation regulator when the generator is loaded

Make further inspection to see the regulation quality of the regulator in case of loading and check all protections as well as the correctness and valuing of functions such as low excitation limit and passage switching test. 9.4 Switching test (at a full load) 9.4.1 The test on the mutual switching of the regulators No.1 passage and No.2 passage 9.4.2 The test on switching of the regulators operation mode between the microcomputer passage mode AVR and the passage mode FCR 9.5 Test on the load field suppression of the generator When the generator operates under the rated working condition of loading, switch off the breaker at the exit of the generators magnetic blow-out switch manually as well as the breaker at the generators exit at the same time. Take the magnetic field voltage curve, magnetic field current curve and generator terminal voltage curve in the generators field suppression course. 9.6 The load throw-off test of the generator After being combined into the grid, the generator should take a load throw-off test in cooperation with the turbine. Put down the curve of the generator terminal voltage changes in the load throw-off course. 10. Quality Control Measures

17

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

10.1 Before the test, operate on the electric DCS to finish the analog test of the excitation system and check the correctness and completeness of the relevant secondary loops through inspections. 10.2 The instruments and equipment used in the test should be sent for detection in advance and complete verification reports should be available. Inspections should be done well before the test. 10.3 In the test, put down all necessary data clearly without any missing. 10.4 The budding should strictly comply with relevant regulations and control documents with regards to quality management.

11. Safety Precautions in Commissioning 11.1 Personal safety 11.1.1 Persons appearing on the construction site must wear safety helmet. 11.1.2 The operation should strictly comply with the requirements of Code of Safety Operation in Power Engineering Construction and Safety Regulations on the Site Work of Full-automatic Devices Regarding Relay Protection and Power Grid Safety. 11.2 Equipment safety 11.2.1 The test personnel must study the Commissioning measures and test plans carefully and get familiar with the test methods, steps and safety cautions stipulated in the measures. 11.2.2 Each person taking part in the test must do well in the inspections and

18

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

preparations before the test in accordance with his or her responsibility. 11.2.3 The main equipment used in the test should be under the charge of special persons. And the test should follow the scheduled procedures. 11.2.4 Any operation in the test should be done by two persons at the same time. Furthermore, safety measures should be taken. 11.2.5 When executing the test on the excitation property of the loaded generator (mainly the low excitation limit test and the load throw-off test), the test should be reported to the procurement division as soon as possible. The approval of the procurement division should serve as a basis for the implementation of the test under the uniform coordination of the trial run command center. 11.2.6 When performing the test on the generators short circuit property, raise the current of the generators stator to the current limit of stator before starting. And the current of the generators stator at this time should be 1.05Ign. 11.2.7 The wiring in the test should agree with the drawings strictly, leaving neither CT open circuit nor PT short circuit. The test should be stopped immediately in the event of any abnormality. The test can continue when the cause of the abnormality is found out. 11.2.8 It is necessary to disconnect the power supply and all temporary wiring for the test after the completion of the test. 11.2.9 Measures should be taken against fire, guard against theft and taken for security work. 11.3 The measuring instruments should be safe.

19

India Tengda 2

330MW Coal-fired Power Plant ProjectElectrical Commissioning Scheme

11.3.1 Operations should be performed in accordance with the operating instructions and operation regulations of the instruments. 11.3.2 The mains voltage applied in the test should comply with the requirements of instruments. 11.3.2 After use, the instruments should have their surfaces wiped before being packed and put into the instrument cases.