Technical Proposal Report
____________________________________________________________________________________________________________________
Contents
Page
1.0 Eltop Difference 1
1.1 Eltop quality Assurance 1
1.2 International standard 1
1.3 Local knowledge 1
1.4 Quality Confirmation from Kumho & Doosan 1
1.5 Why ELTOP? 2
2.0 Information 3
2.1 Eltop Architecture Vietnam Co., Ltd. 3
2.2 Eltop Architects & Planners Co., Ltd. 5
3.0 Scope of Services 7
3.1 Pre-design 7
3.2 Schematic Design 7
3.3 Design Development 8
3.4 Construction Documents 9
3.5 Construction Administration 10
3.6 As-Built drawings 10
4.0 Organization Chart 12
5.0 Memorandum of Understanding 13
6.0 Company Information 14
6.1 Eltop Architecture Vietnam Co., Ltd. 14
6.2 Eltop Architects & Planners Co., Ltd. 15
6.3 NewCC Construction Consultants Co., Ltd. 16
7.0 Key personnel 17
8.0 Selected works 24
Appendix 1 Services Flowchart 39
Appendix 2 Detailed description of services 40
____________________________________________________________________________________________________________________
ELTOP Architecture Vietnam Co., Ltd.
April 2011
1.0 Eltop Difference
Technical Proposal Report
_____________________________________________________________________________________________________________________
ELTOP Architecture Vietnam has its own distinctive design methodology by utilizing a
variety of design solutions and covers the full spectrum from initial feasibility studies
through schematic design, design development, detailed design and supervision during
the construction stage.
ELTOP was conferred The Whole Architectural Consulting Activity License including
design and supervision in Vietnam (No. 411022000089) and in Korea (No. 15874.14236)
With slogan “We Make Difference”, we wish to bring best profit to the Client from the
creativity in design and thus increase Economic value of the project.
Also we ourselves are practiced in obtaining Permissions and Approvals from authorities
of all kinds for a number of projects, namely Kumho Asiana Plaza, Doosan Vantuong
Apartment.
_____________________________________________________________________________________________________________________
Page 1 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
Page 2 ELTOP Architecture Vietnam Co., Ltd.
April 2011
2.0 Introduction
Technical Proposal Report
_____________________________________________________________________________________________________________________
2.0 Information
2.1 ELTOP Architecture Vietnam Co., Ltd.
2.1.1 Introduction
ELTOP Architecture is an architectural design firm, Joint Venture Company, established
by a Korean based design firm ELTOP Architects and Planners Co., Ltd. and a
Vietnamese Investment Company MIJIN Global Co., Ltd.
Based on our experienced professional technicians and directors, ELTOP Architecture
keeps trying to do our best in field of architecture and construction quality assurance.
The key to ELTOP’s success is the uniqueness and high quality of the design derived
from our clients needs and from our experiences. Our aim is to assist our clients in
realizing their needs and goals by helping them turn their vision into an architectural
reality.
The design methodology employed by ELTOP includes extensive use of models and
computers, in order to explore a variety of design solutions for our clients. ELTOP’s
scope of professional service covers the full spectrum of architectural design activities,
from initial feasibility studies through schematic design, design development, detailed
design and supervision during the construction stage.
• Outline Specification
• Preliminary Cost Study
• M&E / Structure Conceptual Design
(c) Design Development
• Development of the Owner’s Requirements
• Development of Architectural Design
• Interior Design
• Development of M&E / Structural Design
• Cost Estimate
• Design Development Drawing and Presentation.
(d) Construction Documentation/Detailed Design
• Architectural Detail Study and Drawings
• Material Selections and Preparation of Specifications
• Construction Permit Submission
• Detailed Interior Design and Drawings
• Working Drawings and Documentation
• Detailed Cost Estimate
• Tender Evaluation and Recommendation
(e) Supervision
• Site Supervision
• Top Supervision
• Review and Approval of Shop Drawings
• Approval of Material Samples
2.1.5 Associates
KUMHO Engineering & Construction
DOOSAN Heavy Industries & Construction
SIAPLAN Architects & Planners
____________________________________________________________________________________________________________________
Page 4 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
_____________________________________________________________________________________________________________________
MEIHARDT International
C S Structural Engineering
GIA TRI CONIC ARCH
New CC Construction Consultants Co., Ltd.
2.2.2 Services
(a) Project Development Consulting
• Feasibility Study / Market Analysis
• Market Analysis
• Concept Development
• Program Development
• Strategy Development
• Project Financing
(b) Building & Environmental Design
• Architectural Planning & Design
• Interior Design
• Master Planning
• Site Planning
• 3D Rendering & Modeling
• Specification
(c) Construction Management & Supervision
• Quality & Safety Management
• Schedule & Cost Management
• Design Supervision & Tendering
• Material Test & Inspection
____________________________________________________________________________________________________________________
Page 5 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
_____________________________________________________________________________________________________________________
• QA/QC
• Shop Drawing Review
2.2.3 Offices
SEOUL 7F/9F Junghwa Bldg, 132-19 Cheongdam-dong, Gangnam-gu,
Seoul, Korea
T/82-2-519-1000 F/82-2-519-1007 Http://www.eltop.ac
HCM City Saigon Trade Center #1111, 37 Ton Duc Thang, Dist 1,
Hochiminh City
T/84-8-3910-3472 F/84-8-3910-3474
Almaty S240, Furmanov str., Almaty, Kazakhstan
T/7-7272-647282 F/7-7272-644177
____________________________________________________________________________________________________________________
Page 6 ELTOP Architecture Vietnam Co., Ltd.
April 2011
3.0 Scope of Services
Technical Proposal Report
____________________________________________________________________________________________________________________
3.2.1 Architectural
(a) Title Sheet
(b) List of Drawings
(c) Project Summary
(d) Location map
(e) Site layout plan
(f) Floor Plans
(g) Elevations
(h) Sections
(i) Colored Perspective
The Architect shall prepare presentation materials by using Microsoft Power Point
program and will make presentation to the third parties such as government authorities
The Architect shall submit to the Client a Statement of Probable Construction Cost
based on current area, volume or other unit costs.
Schematic Design shall be developed on the Design Development stage upon concepts,
ideas, design criteria and design guideline confirmed by the Client.
____________________________________________________________________________________________________________________
Page 7 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
All plans for Design Development including Schematic Design drawings and drafted Site
Plan shall be submitted to the Client for decision-making before developing such
concepts and ideas on the Design Development stage.
The Architect shall make presentation on the Schematic Design to the Client when the
Schematic Design is completed.
Schematic Design shall be developed on the Design Development Stage based upon
concepts, ideas, design criteria and design guideline confirmed by the Client.
The Design Develop shall be submitted to the Client for his confirmation, which shall be
developed on the Construction Document Stage.
Once the Design Development is fixed, the Architect could prepare the perspective
and/or model upon the Client’s request.
The following works are deemed to be included, but not limited to, within the scope of
Design Development:
3.3.1 Architectural:
(a) Site Plan
(b) Floor Plan
(c) Elevation
(d) Sections
(e) Major finishing materials
(f) Perspective and/or Model(if the Client requests)
3.3.2 Structural:
(a) Structure frame
(b) Major material list
3.3.3 Electrical:
(a) Power Supply
3.3.4 Mechanical
(a) Supply and Exhaust Ventilation and Air conditioning Systems
(b) Sanitary plumbing
(c) Fire fighting protection
(d) Machinery list
____________________________________________________________________________________________________________________
Page 8 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
3.3.5 Landscape
(a) Landscaping plan
(b) Civil work for landscaping
3.3.6 Civil
(a) Drainage and sewage water treatment plan
(b) Portable water supply plan
____________________________________________________________________________________________________________________
Page 9 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
3.6.1 The Architect shall make arrangements for obtaining from Contractors and
other parties information certified by them on all changes made during
____________________________________________________________________________________________________________________
Page 10 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 11 ELTOP Architecture Vietnam Co., Ltd.
April 2011
8.0 Selected Works
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 24 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 25 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 26 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 27 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 28 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 29 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 30 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 31 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 32 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 33 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 34 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 35 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 36 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 37 ELTOP Architecture Vietnam Co., Ltd.
April 2011
Technical Proposal Report
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
Page 38 ELTOP Architecture Vietnam Co., Ltd.