You are on page 1of 107

Rules for Classification and Construction

I Ship Technology

5 Underwater Technology
1 Diving Systems and Diving Simulators

Edition 1998
The following Rules come into force on June 1st , 1998.

"General Terms and Conditions" of the respective latest edition will be applicable
(see Rules for Classification and Construction, I – Ship Technology, Part 0 – Classification and Surveys).

Reproduction by printing or photostatic means is only permissible with the consent of Germanischer Lloyd.

Germanischer Lloyd AG
Head Office Hamburg
Vorsetzen 35, D-20459 Hamburg

Telefon +49 40 3 61 49-0


Telefax +49 40 3 61 49-2 00
headoffice@gl-group.com
http://www.gl-group.com

Published by: Germanischer Lloyd AG, Hamburg Printed by: Gebrüder Braasch GmbH, Hamburg
I - Part 5 Table of Contents Chapter 1
GL 1998 Page 3

Table of Contents

Section 1 Rules for Classification of Diving Systems and Diving Simulators


A. Classification and Characters of Classification .......................................................................... 1- 1
B. Classification of Diving Systems built or converted under the Survey of and in
Accordance with the Rules of GL .............................................................................................. 1- 2
C. Classification of Diving Systems not built under the Survey of GL ........................................... 1- 2
D. Surveys of Maintenance of Class ............................................................................................... 1- 3
E. Surveys other than for Classification .......................................................................................... 1- 5

Section 2 Rules for Construction of Diving Systems


A. General Rules and Instructions ................................................................................................... 2- 1
B. Principles for the Design and Construction of Diving Systems .................................................. 2- 7
C. Pressure Vessels and Apparatus ................................................................................................. 2- 9
D. Pipes, Valves, Fittings, Hoses and Umbilicals ........................................................................... 2- 13
E. Compressors ............................................................................................................................... 2- 17
F. Life Support Systems ................................................................................................................. 2- 19
G. Automation, Communication and Locating Equipment ............................................................. 2- 22
H. Electrical Equipment .................................................................................................................. 2- 25
I. Fire Protection ............................................................................................................................ 2- 30
J. Handling, Transfer and Mating Equipment ................................................................................ 2- 32
K. Hyperbaric Evacuation System .................................................................................................. 2- 33
L. Wet Bells .................................................................................................................................... 2- 34

Section 3 Rules for Construction of Diving Simulators


A. General Rules and Instructions ................................................................................................... 3- 1
B. Principles of Design and Construction of Diving Simulators ..................................................... 3- 6
C. Pressure Vessels and Apparatus ................................................................................................. 3- 8
D. Pipes, Valves, Fittings and Hoses .............................................................................................. 3- 9
E. Compressors ............................................................................................................................... 3- 10
F. Life Support Systems ................................................................................................................. 3- 10
G. Automation and Communications Equipment ............................................................................ 3- 13
H. Electrical Equipment .................................................................................................................. 3- 14
I. Fire Protection ............................................................................................................................ 3- 14
J. Hyperbaric Evacuation System .................................................................................................. 3- 16

Section 4 Rules for Construction of Diver Pressure Chambers


A. General Rules and Instructions ................................................................................................... 4- 1
B. Principles for Design and Construction ...................................................................................... 4- 3

Appendix A Calculation and Pressure Hulls under External Pressure


A. Introduction ................................................................................................................................ A- 1
B. Stiffened and Unstiffened Cylindrical Shells ............................................................................. A- 1
C. Ring Stiffeners ............................................................................................................................ A- 4
Chapter 1 Table of Contents I - Part 5
Page 4 GL 1998

D. Stiffened and Unstiffened Conical Shells ................................................................................... A- 8


E. Dished Ends and Spheres ............................................................................................................ A- 8
F. Openings and Discontinuities ..................................................................................................... A- 10
G. Elasticity Moduli ......................................................................................................................... A- 10
H. Out-of-Roundness of Cylinders and Spheres .............................................................................. A- 11
I. Tolerances of Ring Stiffeners ..................................................................................................... A- 13
J. Program Sequences for Iterative Calculations ............................................................................ A- 14
K. Symbols and Units ...................................................................................................................... A- 17
L. References ................................................................................................................................... A- 19

Appendix B Acrylic Plastic Windows


A. General ........................................................................................................................................ B- 1
B. Material ....................................................................................................................................... B- 1
C. Manufacture of Windows ............................................................................................................ B- 1
D. Window Shapes and Sizes .......................................................................................................... B- 2

Appendix C Design and Manufacture of GRP Constructions


A. Principles for the Manufacture of GRP Constructions ................................................................ C- 1
B. Company Authorization .............................................................................................................. C- 1
C. Workshop Requirements ............................................................................................................. C- 1
D. Construction Process ................................................................................................................... C- 2
E. Materials ..................................................................................................................................... C- 3
I - Part 5 Index Chapter 1
GL 1998 Page 5

Index

A
Access openings ..................................................................................................................................................... 3-9
Access ports ......................................................................................................................................................... 2-10
Acrylic plastic windows ................................................................................................................................ 2-12, 3-9
Air ...................................................................................................................................................................... 2-22
Alarm systems ...................................................................................................................................................... 2-31
Analyzers ............................................................................................................................................................. 3-13
Analyzing equipment ........................................................................................................................................... 2-21
Ancillary equipment ............................................................................................................................................... 2-5
Annual survey ................................................................................................................................................. 1-3, 1-4
Antechambers ........................................................................................................................................................ 4-1
Apparatus ............................................................................................................................................................... 2-5
Application for classification ................................................................................................................................. 1-2
Area of installation of diving system ........................................................................................................... 2-30, 2-31
Area of installation of the diving simulator ................................................................................................. 3-14, 3-15
Areas not subject to an explosion hazard ............................................................................................................... 2-9
Areas subject to explosion hazard ................................................................................................................... 2-1, 3-1
Assignment of class ................................................................................................................................................ 1-3
Authorized workshop ............................................................................................................................................. 1-3
Automation .............................................................................................................. 2-2, 2-4, 2-6, 2-22, 3-2, 3-3, 3-5
Automation and communications equipment ....................................................................................................... 3-13
Automation equipment ......................................................................................................................................... 3-13
Average commissioner ........................................................................................................................................... 1-3

B
Ballast weights ....................................................................................................................................................... 2-5
Bayonet locks ......................................................................................................................................................... 2-3
Block diagrams ...................................................................................................................................................... 2-3
Bolts ..................................................................................................................................................................... 2-12
Bottles ..................................................................................................................................................... 2-1, 3-1, 3-2
Breathing connection ............................................................................................................................................. 4-1
Breathing gas ......................................................................................................................................................... 2-6
Breathing gas supply ............................................................................................................................................ 2-35
Breathing gas systems ..................................................................................................................................... 2-2, 3-2
Breathing gas treatment and mixing ..................................................................................................................... 2-20
Breathing gas/breathing mixture ..................................................................................................................... 2-1, 3-1
Chapter 1 Index I - Part 5
Page 6 GL 1998

Breathing rate per minute AMV ................................................................................................................. 2-19, 3-10


Buoyancy ............................................................................................................................................................... 2-5
Bursting pressure ................................................................................................................................................... 2-6

C
Cables ........................................................................................................................................................... 2-6, 2-29
Calculation of pipe wall thicknesses ........................................................................................................... 2-15, 2-16
Calculations ......................................................................................................................................................... 2-12
Cast steel .............................................................................................................................................................. 2-15
Category A machinery space ................................................................................................................................. 2-2
Central control position ............................................................................................................ 2-20, 2-21, 2-22, 3-11
Certificate of classification ............................................................................................................................. 1-1, 1-3
Certification ........................................................................................................................................................... 1-5
Chamber conditions ............................................................................................................................................... 3-7
Chamber equipment ........................................................................................................................................ 2-9, 3-7
Chamber windows ................................................................................................................................. 2-10, 3-5, 4-2
Change of vessel .................................................................................................................................................... 1-3
Characters of classification ............................................................................................................................. 1-1, 1-3
Circuitry ............................................................................................................................................................... 2-23
Class renewal survey ............................................................................................................................... 1-2, 1-3, 1-4
Classification ......................................................................................................................................................... 1-1
CO ............................................................................................................................................................ 2-22, 3-13
CO2 ..................................................................................................................................................................... 2-22
CO2 analyzing system ......................................................................................................................................... 2-21
CO2 levels ........................................................................................................................................................... 2-21
Communication systems ................................................................................................................................. 2-2, 3-2
Communications ............................................................................................................ 2-4, 2-6, 2-22, 2-24, 4-2, 4-5
Communications equipment ............................................................................................... 2-24, 3-3, 3-5, 3-13, 3-14
Compact umbilicals ................................................................................................................................. 2-2, 2-6, 3-2
Components ........................................................................................................................................................... 2-6
Compressed air ...................................................................................................................................................... 4-5
Compressed air storage .......................................................................................................................................... 4-1
Compression chamber system ................................................................................................................................ 1-4
Compression chamber windows .............................................................................................................. 2-5, 3-5, 4-2
Compression chambers ................................................................. 2-1, 2-2, 2-9, 2-20, 2-31, 3-1, 3-2, 3-8, 3-11, 3-16
Compressors ................................................................................................. 2-3, 2-5, 2-17, 2-18, 3-2, 3-5, 3-10, 4-2
Conditioning of chamber atmosphere ......................................................................................................... 2-20, 3-11
Conditions in chamber ........................................................................................................................................... 2-8
Construction ........................................................................................................................................................ 2-11
I - Part 5 Index Chapter 1
GL 1998 Page 7

Constructional test ................................................................................................................................................. 2-5


Consul .................................................................................................................................................................... 1-3
Control .................................................................................................................................. 2-2, 2-20, 3-11, 4-2, 4-5
Control equipment .............................................................................................................................. 2-22, 3-2, 3-13
Control position ................................................................................................................................................... 2-22
Control station ...................................................................................................................................................... 2-35
Cooling .................................................................................................................................................................. 2-4
Copper ................................................................................................................................................................. 2-15
Copper alloys ....................................................................................................................................................... 2-15
Corrosion protection ............................................................................................................................. 2-9, 2-10, 3-7
Coupling clamps .................................................................................................................................................... 2-3

D
Damage survey ................................................................................................................................................ 1-3, 1-5
Deck compression chambers ........................................................................................................................... 4-1, 4-4
Demand breathing system ...................................................................................................................................... 4-1
Depth .............................................................................................................................................................. 2-2, 3-2
Description of the system ....................................................................................................................................... 2-3
Design and construction of diving systems ............................................................................................................ 2-7
Design pressure ...................................................................................................................................................... 2-5
Design principles ................................................................................................................................................... 2-9
Detection ......................................................................................................................................................... 2-3, 3-2
Disposal system ..................................................................................................................................................... 2-4
Diver heating systems ..................................................................................................................................... 2-2, 3-2
Diver pressure chambers ................................................................................................................................. 4-1, 4-2
Diving bells .................................................................................................................... 2-2, 2-5, 2-9, 2-10, 2-20, 3-2
Diving procedure ................................................................................................................................................... 2-3
Diving simulators ............................................................................................................. 1-1, 3-1, 3-2, 3-6, 3-7, 3-11
Diving support vessels ........................................................................................................................................... 2-1
Diving system certificate ......................................................................................................................... 1-1, 1-2, 1-3
Diving systems ................................................................................................................. 1-1, 2-1, 2-2, 2-5, 2-7, 2-31
Documents ............................................................................................................................................................. 1-4
Documents for approval .......................................................................................................................... 2-3, 3-2, 4-1
Door leaves ............................................................................................................................................................ 2-3
Door leaves and frames .......................................................................................................................................... 3-3
Doors ................................................................................................................................................................... 2-10
Drawings ................................................................................................................................................................ 2-5
Drawings of consoles ............................................................................................................................................. 2-3
Drawings of supply and disposal systems .............................................................................................................. 2-3
Duration of class .................................................................................................................................................... 1-1
Chapter 1 Index I - Part 5
Page 8 GL 1998

E
Earthing ............................................................................................................................................................... 2-29
Electrical equipment ................................................................................................. 2-4, 2-6, 3-4, 3-5, 3-14, 4-3, 4-5
Electrical Equipment ........................................................................................................................................... 2-25
Electrical machines ................................................................................................................................................ 2-6
Electrical penetrations ......................................................................................................................................... 2-29
Electrical systems .................................................................................................................................................. 2-2
Electrical systems and equipment .......................................................................................................................... 3-2
Emergency communication ................................................................................................................................. 2-25
Emergency lighting .............................................................................................................................................. 2-30
Emergency location ............................................................................................................................................. 2-24
Emergency power supply ..................................................................................................................................... 2-27
Enclosures for electrical equipment ..................................................................................................................... 2-28
Ends ..................................................................................................................................................................... 2-11
Energy balance ...................................................................................................................................................... 2-4
Engine plant ........................................................................................................................................................... 2-1
Environmental conditions ............................................................................................................................... 2-8, 3-7
Equipment list ........................................................................................................................................................ 2-3
Evacuation chamber ............................................................................................................................................ 3-16
Evacuation system ............................................................................................................................................... 2-34
Evacuation units .................................................................................................................................................. 2-33
Expert .................................................................................................................................................................... 1-3
Extinguishing equipment ................................................................................................................................ 2-3, 3-2

F
Facilities ................................................................................................................................................................ 3-7
Fire behaviour ........................................................................................................................................................ 2-6
Fire detection ....................................................................................................................................................... 2-31
Fire detection and alarm systems ......................................................................................................................... 3-15
Fire detection systems ................................................................................................................................. 2-31, 3-15
Fire extinguishing equipment .............................................................................................................................. 3-15
Fire extinguishing systems ................................................................................................................................... 2-31
Fire loads ...................................................................................................................................................... 2-9, 2-31
Fire prevention ............................................................................................................................................... 2-3, 3-2
Fire protection ........................................................................................................ 2-4, 2-6, 2-30, 3-4, 3-6, 3-14, 4-3
Fire protection equipment .................................................................................................................... 2-32, 3-16, 4-6
Fire surveillance ......................................................................................................................................... 2-31, 3-15
Fittings ........................................................................................................................... 2-2, 2-9, 2-13, 2-14, 3-2, 3-9
Fixed system .......................................................................................................................................................... 2-2
I - Part 5 Index Chapter 1
GL 1998 Page 9

Foundation drawings .............................................................................................................................................. 2-3


Frames .................................................................................................................................................................... 2-3
Functional efficiency .............................................................................................................................................. 1-2
Functional test ........................................................................................................................................................ 2-5

G
Gas analysis ........................................................................................................................................................... 2-3
Gas analyzing systems .................................................................................................................................... 2-2, 3-2
Gas bottles ..................................................................................................................................... 2-2, 2-7, 2-13, 3-9
Gas distribution ........................................................................................................................................... 2-19, 3-10
Gas mixers ...................................................................................................................................................... 2-3, 3-2
Gas piping .............................................................................................................................................................. 2-5
Gas storage facilities ........................................................................................................................... 2-5, 2-19, 3-10
Gas storage facility ................................................................................................................................................ 3-1
Gas supply ............................................................................................................................. 2-2, 2-3, 2-19, 3-3, 3-10
Gas supply system ................................................................................................................................................ 3-10
Gas venting system .............................................................................................................................................. 2-19
Gas-air mixture ...................................................................................................................................................... 2-1
Guidelines for the explosion protection of electrical equipment ............................................................................ 2-9

H
Handling ................................................................................................................................. 2-3, 2-4, 2-6, 2-7, 2-32
Handling and transfer systems ........................................................................................................................ 2-1, 3-1
Handling system ........................................................................................................................... 2-2, 2-5, 2-33, 2-34
Hatch trunks ......................................................................................................................................................... 2-10
Hatches ......................................................................................................................................................... 2-10, 3-9
He/N2/CO2 mixtures ........................................................................................................................................... 2-22
Heating ................................................................................................................................................................... 2-4
Helium reclaim system .................................................................................................................................... 2-3, 3-2
Helium-oxygen mixtures ...................................................................................................................................... 2-22
Hose lines ............................................................................................................................................................. 2-14
Hoses ............................................................................................................................... 2-2, 2-6, 2-13, 3-2, 3-5, 3-9
Hull ........................................................................................................................................................................ 2-1
Hydraulic pressure test .................................................................................................................................... 2-5, 2-6
Hydrocarbons ....................................................................................................................................................... 3-13
Hyperbaric evacuation system ....................................................... 2-2, 2-3, 2-4, 2-7, 2-33, 2-34, 3-2, 3-4, 3-6, 3-16
Hyperbaric evacuation units ................................................................................................................................. 2-33
Hyperbaric self-propelled lifeboats ...................................................................................................................... 2-33
Chapter 1 Index I - Part 5
Page 10 GL 1998

I
IMO code of safety ................................................................................................................................................ 2-1
Impact energy ...................................................................................................................................................... 2-10
Inclined positions ................................................................................................................................................... 2-8
Indicating instruments ......................................................................................................................... 2-21, 3-12, 4-5
Installation drawings .............................................................................................................................................. 2-3
Instrumentation .................................................................................................................................. 2-20, 3-11, 3-12
Insulation ............................................................................................................................................................. 2-31
Insurance company ................................................................................................................................................ 1-3
Integral opening reinforcements ............................................................................................................................ 2-3
Interior lighting .................................................................................................................................................... 2-30
Interiors ...................................................................................................................................................... 2-31, 3-15
Intermediate survey ........................................................................................................................................ 1-3, 1-4
Internal facilities .................................................................................................................................................... 2-3
Internal survey ....................................................................................................................................................... 1-3
Interrogator/receiver ............................................................................................................................................ 2-25
ISO V-notch ........................................................................................................................................................ 2-10

L
Launching devices ............................................................................................................................................... 2-35
Leaks ..................................................................................................................................................................... 2-5
Life support systems ................................................................................................... 2-2, 2-3, 2-5, 2-6, 3-2, 3-3, 3-5
Life Support Systems .................................................................................................................................. 2-19, 3-10
Lifting equipment .................................................................................................................................................. 2-4
Lifting point ......................................................................................................................................................... 2-10
Lighting ............................................................................................................................................................... 2-30
Lines .................................................................................................................................................................... 2-29
Living compartment ................................................................................................................................. 2-2, 3-2, 3-8
Living compartment of compression chambers ..................................................................................................... 2-9
Locating equipment ........................................................................................................................ 2-2, 2-4, 2-6, 2-22
Location ................................................................................................................................................................. 2-9
Lock for materials .................................................................................................................................................. 3-8
Locking mechanism ............................................................................................................................................. 2-10
Locks ............................................................................................................................................................ 2-10, 3-8
Log-book ............................................................................................................................................................... 1-1
Lowering ................................................................................................................................................................ 2-6

M
Main chambers ...................................................................................................................................................... 4-1
Main components of a diving system .................................................................................................................... 2-2
I - Part 5 Index Chapter 1
GL 1998 Page 11

Main power supply .............................................................................................................................................. 2-27


Manufacture ......................................................................................................................................................... 2-11
Manufacturer .......................................................................................................................................................... 1-2
Manufacturer's works ............................................................................................................................................. 1-3
Marking ................................................................................................................................................... 2-7, 3-6, 4-3
Marking of gas systems ................................................................................................................................... 2-7, 3-6
Material testing ........................................................................................................................................... 2-11, 2-15
Materials ..................................................................................................................................................... 2-10, 2-15
Materials test certificates ....................................................................................................................................... 2-5
Mating .................................................................................................................................................................... 2-6
Mating and handling systems ............................................................................................................................... 2-34
Mating appliances .................................................................................................................................................. 2-7
Mating device ................................................................................................................................................. 2-1, 3-1
Mating equipment ................................................................................................................................................ 2-32
Mating systems ....................................................................................................................... 2-3, 2-4, 2-6, 2-34, 4-3
Maximum operating depth ..................................................................................................................................... 2-5
Maximum operating depth of the diving system ............................................................................................. 2-2, 3-1
Maximum permissible operating voltages ............................................................................................................ 2-26
Maximum permissible working pressure ........................................................................................................ 2-5, 4-1
Mechanical strength ............................................................................................................................................... 1-2
Minimum pipe wall thickness .............................................................................................................................. 2-16
Mixed gas ............................................................................................................................................................... 2-8

N
Name plate ............................................................................................................................................................. 2-7
National regulations ............................................................................................................................................... 2-1
NO ............................................................................................................................................................. 2-22, 3-13
Nodular cast iron .................................................................................................................................................. 2-15
Non-destructive testing of welds ............................................................................................................................ 2-5
Non-metals ........................................................................................................................................................... 2-15
NOx ............................................................................................................................................................ 2-22, 3-13
Nozzles ................................................................................................................................................................ 2-12

O
Office of authority .................................................................................................................................................. 1-3
Operator ................................................................................................................................................................. 1-2
Oxygen ................................................................................................................................................................... 2-6
Oxygen supply ....................................................................................................................................................... 4-5
Ozone ................................................................................................................................................................... 3-13
Chapter 1 Index I - Part 5
Page 12 GL 1998

P
Performance of surveys ......................................................................................................................................... 1-4
Permissible stress ........................................................................................................................................ 2-16, 2-17
Pipe classes .......................................................................................................................................................... 2-14
Pipe connections .................................................................................................................................................. 2-14
Pipes ............................................................................................................................................... 2-2, 2-13, 3-2, 3-9
Piping diagrams ..................................................................................................................................................... 2-3
Piping systems ................................................................................................................................ 2-6, 2-13, 3-5, 4-2
Power distribution ............................................................................................................................................... 2-27
Power supply .............................................................................................................................................. 2-23, 2-26
Pressure chambers ................................................................................................................................. 2-33, 4-1, 4-2
Pressure drop ......................................................................................................................................................... 2-5
Pressure vessels ................................................................................................................. 2-1, 2-2, 2-5, 2-7, 3-1, 3-2
Pressure vessels and apparatus ......................................................................... 2-5, 2-9, 2-13, 3-3, 3-4, 3-8, 3-9, 4-2
Procedure for classification ................................................................................................................................... 1-3
Purity test ............................................................................................................................................................... 2-6

R
Raising ................................................................................................................................................................... 2-6
Reclassification survey .......................................................................................................................................... 1-2
Register book ........................................................................................................................................... 1-1, 1-2, 1-3
Reinforcement of cutouts ..................................................................................................................................... 2-11
Release .................................................................................................................................................................. 2-6
Repairs ................................................................................................................................................................... 1-3
Replacements ......................................................................................................................................................... 1-3
Rescue chambers ............................................................................................................................................ 4-1, 4-6
Retaining rings ....................................................................................................................................................... 2-3
Rules of construction ............................................................................................................................................. 2-1

S
Safety equipment ............................................................................................................................................ 2-5, 4-2
Sanitary systems ............................................................................................................................................. 2-2, 3-2
Screws ................................................................................................................................................................. 2-12
Sea trials ................................................................................................................................................................ 2-5
Shower ................................................................................................................................................................... 2-9
Shutoff-devices .................................................................................................................................................... 2-14
Signalling systems ............................................................................................................................................... 2-24
SOLAS .................................................................................................................................................................. 2-2
Sources of ignition ............................................................................................................................................... 2-31
Special survey ................................................................................................................................................. 1-3, 1-5
I - Part 5 Index Chapter 1
GL 1998 Page 13

Stability .................................................................................................................................................................. 2-5


Steel ..................................................................................................................................................................... 2-15
Storage batteries ................................................................................................................................................... 2-27
Structural fire protection ............................................................................................................................. 2-30, 3-14
Supervision during construction ............................................................................................................................ 1-2
Supply locks .................................................................................................................................................... 2-3, 4-4
Supply systems ..................................................................................................................................................... 2-26
Surface compression .............................................................................................................................................. 2-9
Surface compression chamber ........................................................................................................ 2-1, 2-2, 2-8, 2-31
Surveillance ........................................................................................................................................................... 3-2
Surveillance system ................................................................................................................................................ 2-2
Survey by special agreement .................................................................................................................................. 1-5
Surveyor ................................................................................................................................................................. 1-2
Surveyor's report on the assignment of class .......................................................................................................... 1-3
Surveys ................................................................................................................................................................... 1-3
Surveys of maintenance of class ............................................................................................................................ 1-3
Surveys other than for classification ...................................................................................................................... 1-5
Surveys relating to the safety of equipment ........................................................................................................... 1-5
Switchgear ........................................................................................................................................................... 2-27
Switching and protective devices ......................................................................................................................... 2-28

T
Television surveillance equipment ....................................................................................................................... 3-14
Temporary system .................................................................................................................................................. 2-2
Test chambers ................................................................................................................................................. 3-2, 3-8
Test pressure .......................................................................................................................................................... 4-1
Test pressure/time curve ...................................................................................................................................... 2-30
Test schedule ......................................................................................................................................................... 2-3
Tests ....................................................................................................................................................................... 2-5
Tightness test ......................................................................................................................................................... 2-6
Toilet ...................................................................................................................................................................... 2-9
Total system ........................................................................................................................................................... 2-3
Transfer .......................................................................................................................................... 2-3, 2-4, 2-6, 2-32
Transponder ......................................................................................................................................................... 2-24
Transporting ........................................................................................................................................................... 2-7
Treatment and mixing of breathing gases ............................................................................................................ 3-11
Trials ...................................................................................................................................................................... 2-5
Chapter 1 Index I - Part 5
Page 14 GL 1998

U
Umbilicals .................................................................................................... 2-2, 2-3, 2-6, 2-13, 2-14, 2-34, 3-2, 3-5
Underwater plug connections .............................................................................................................................. 2-29

V
Valves ................................................................................................................................... 2-2, 2-13, 2-14, 3-2, 3-9
View ports ........................................................................................................................................... 2-10, 2-12, 3-8
Voice communication systems .................................................................................................................... 2-24, 3-13

W
Water supply .......................................................................................................................................................... 2-4
Water systems ........................................................................................................................................................ 3-2
Weight ................................................................................................................................................................... 2-5
Welded structures ................................................................................................................................................ 2-10
Welding ............................................................................................................................................................... 2-11
Welding gas absorbers ........................................................................................................................................... 3-2
Wet bells ............................................................................................................................... 2-2, 2-5, 2-7, 2-34, 2-35
Wet test chambers .................................................................................................................................................. 3-8
Window flanges ..................................................................................................................................................... 2-3
Windows ................................................................................................................................. 2-3, 2-12, 3-3, 3-5, 4-2
Working gas .......................................................................................................................................................... 3-1
Working pressure ................................................................................................................................................... 4-1

X
X-ray test ............................................................................................................................................................... 2-6
I - Part 5 Section 1 A Rules for Classification of Diving Systems and Diving Simulators Chapter 1
GL 1998 Page 1–1

Section 1

Rules for Classification of Diving Systems and Diving Simulators

A. Classification and Characters of 1.9 For the purpose of these Rules, diving simu-
Classification lators are pressure chambers or pressure chamber sys-
tems in which diving conditions can be simulated.
1. Classification
2. Characters of classification
1.1 The following Rules for Classification and
Construction constitute the basis for the classification 2.1 The character of classification is:
of diving systems on seagoing ships and for diving
simulators. TAZ

The term "Rules for Construction" includes Rules for 2.2 For diving systems of non-standard design,
Materials and Welding as well as other Rules for Con- GL reserves the right to subject the systems to addi-
struction issued by Germanischer Lloyd (GL). tional tests, to order a special survey schedule and to
make special entries in the diving system certificate
1.2 For the purpose of these Rules, diving sys- and the Register Book.
tems comprise:
Diving systems which are permanently installed on a 2.3 Diving systems built under the survey and in
ship or similar floating structure. accordance with the Rules of GL using materials and
components tested by GL in conformity with its Rules
Diving systems which are assembled to meet receive the notation  in front of the character of
particular service requirements and are installed for a classification.
limited period on a ship or similar floating structure.
2.4 Diving systems built under the survey and in
1.3 The classification covers all equipment of the
accordance with the rules of another recognized classi-
ship, machinery and electrical installation of diving
systems. fication society receive, on being awarded GL classifi-
cation, the notation  in front of the character clas-
1.4 The Certificate of Classification for diving sification.
systems is issued by the Managing Directors of GL or
by their Representatives. It is to be kept on board ship. 3. Duration of class

1.5 Diving systems classified by GL are entered 3.1 The validity of the class of permanently in-
in the Register Book with a note of the relevant char- stalled diving systems is always identical to that of the
acter of classification and are included in the list of machinery plant of the ship or floating structure. The
chips with a diving system certificate. class will be maintained as long as the diving system
is subjected to all prescribed surveys, and any
1.6 The ship is required to carry a diving system modifications and repairs found to be necessary are
log-book in which are entered details of diving opera- carried out to the satisfaction of GL.
tions, repairs etc. The diving system log-book is to be
submitted to the Surveyor on request. 3.2 If the diving system is not subjected to the
prescribed surveys at their due dates, the class will be
1.7 Diving systems which are not to be classified suspended.
by GL but which are constructed in accordance with
the Rules and under the Survey of GL may receive an 3.3 If the diving system has suffered damage
appropriate Diving System Certificate from GL (cf. affecting its class or if such damage may be assumed,
Subsection E.). a survey must be performed before diving operations
begin. The Society is to be notified of such damage as
1.8 Diving simulators are not generally subject to a matter of course.
classification by GL. Where a plant is to be classified
at the request of the operator, the Rules for Classifica- 3.4 Where it is found that the diving system no
tion of Diving Systems shall be applied as and where longer complies with the requirements of the Rules on
relevant. the basis of which the class was assigned, or if the
Chapter 1 Section 1 C Rules for Classification of Diving Systems and Diving Simulators I - Part 5
Page 1–2 GL 1998

operator fails to carry out repairs or alterations consid- 2.4 The Surveyors of GL will supervise the as-
ered necessary by GL within a specified period to be sembly of the diving system, will examine the work-
agreed upon, the diving system will lose its class. manship and will carry out the required tightness and
service tests.
3.5 If the repairs or modifications required by GL
have been carried out and the system is subjected to a 2.5 Upon completion, the entire diving system
Reclassification Survey, the original character of clas- will be subjected to a final test under working condi-
sification may be reinstated. This survey is to be car- tions in accordance with the Rules for Construction,
ried out in accordance with the requirements for a Section 2, A.5.
Class Renewal Survey.
2.6 To enable the Surveyor to fulfil his duties, he
3.6 If for some reason the class has expired or is to be given free access to the ship and the work-
has been withdrawn by GL, this will be indicated in shops where parts requiring approval are manufac-
the Register Book. The Certificates of Classification tured, assembled or tested. To enable the Surveyor to
shall be returned to GL. carry out the required tests, the shipyard or the manu-
facturers are to give him every assistance by providing
the staff and equipment necessary for such tests.

B. Classification of Diving Systems built or


converted under the Survey of and in Ac-
cordance with the Rules of GL
C. Classification of Diving Systems not built
under the Survey of GL
1. General
1. General
1.1 Application for the classification of a diving
system is to be submitted to GL in writing by the
manufacturer or operator. 1.1 Applications for the classification of diving
systems not built under the survey of GL are to be
1.2 In general, particulars of the diving system submitted to GL in writing.
are to be submitted to GL in triplicate for examination.
1.2 With the application for classification docu-
1.3 Any deviation from the approved drawings ments relating to the diving system are to be submitted
and documents are subject to the approval of GL be- for examination the scope of which shall be as stated
fore work is commenced. in the Rules for Construction. The documentation
relating to functional tests is to be submitted and,
1.4 The Surveyor is to be advised in good time of where necessary, individual tests are to be repeated.
tests to be performed under the supervision of GL:
1.3 Particulars are to be submitted as to existing
1.5 On the completion and successful testing of class and period of class, as well as any requirements
the diving system, GL will issue the Diving System upon which the maintenance of the existing class has
Certificate. been made conditional.

1.4 Where the diving system has existing class


2. Supervision during construction awarded by a recognized classification society, it may
in exceptional cases be sufficient to forward a set of
2.1 Proof is to be provided that the materials to the necessary documents.
be used for new constructions, replacements and
repaired parts have been tested in accordance with the
requirements of GL Rules for Materials. 2. Procedure for classification

2.2 Parts of the diving system requiring approval 2.1 For the assignment of class the diving system
will be checked during manufacture for conformity is to be surveyed in accordance with the provisions for
with the approved documents. a Class Renewal Survey.

2.3 The separate components of the diving 2.2 If the diving system holds the class of another
system are to be tested on the manufacturer's test bed recognized classification society, GL may not require
for mechanical strength and, where appropriate, for all parts to be surveyed, and the survey of individual
functional efficiency. Where components are novel in parts may be deferred pending the next due date of a
design or have not yet sufficiently proved their effi- regular survey. GL may then consent to a survey in
ciency on board ship or in diving systems, GL may accordance with at least the requirements of an
demand more extensive tests. Annual Survey.
I - Part 5 Section 1 D Rules for Classification of Diving Systems and Diving Simulators Chapter 1
GL 1998 Page 1–3

2.3 A Diving System Certificate will be issued on The Register Book shall also state the month and year
the basis of a satisfactory Surveyor's Report on the of the last Annual Survey or the last Class Renewal
assignment of class. Once a diving system has been Survey.
classed with GL, the same regulations will apply as
for diving systems built under survey of GL. 2.3 The reports prepared by the Surveyors are
checked by GL. The results of surveys carried out are
published in the Register Book, Part 2, upon accep-
tance.
D. Surveys of Maintenance of Class
2.4 Where defects are repaired provisionally
1. Kinds of surveys only, or where the Surveyor does not consider imme-
diate repairs or replacements necessary, the class of
Diving systems classed with GL are to be subjected to the diving system may be confirmed for a certain lim-
the following surveys, if their class is to be main- ited period by marking an entry in the Certificate of
tained: Classification. Upon withdrawal of such restrictions, a
corresponding record will be entered in the Certificate
1.1 Annual survey (cf. 3.1). of Classification.

1.2 Intermediate survey (cf. 3.2). 2.5 Where parts are damaged or worn to such an
extent that they no longer comply with the require-
The intermediate survey falls due nominally 2,5 years ments of GL, they are to be repaired or replaced.
after commissioning and each class renewal and may
be carried out on the occasion of the second or third 2.6 If a diving system has to be surveyed in a
annual survey. port where, or near which, there is no Agent or
Surveyor of GL, the locally responsible Consul, a
1.3 Class Renewal Survey after five years (cf. competent Office or Authority, or the Average
3.3). Commissioner of the Insurance Company concerned is
to be requested to cause a survey by an expert. The
1.4 Damage survey, where the diving system has commission of the expert is to be confirmed by the
been damaged or where the hull or parts of the ma- Consul, the Office of Authority, or the Average
chinery plant have suffered damage liable to affect the Commissioner. The expert shall be requested to
diving system (cf. 3.4). forward to GL forthwith a report on the condition of
the diving system and on the repairs as well as on the
1.5 Special Survey, before the start of diving decision arrived at. A copy of the report is to be
operations with a modified diving system or after re- retained on board ship. The decision of the expert is
assembly or change of vessel in the case of a mobile subject to the approval of GL, who will decide on
diving system (cf. 3.5). whether the diving system has to be surveyed again.

1.6 GL reserve the right to demand surveys to be 3. Performance of surveys


held between the due dates of regular surveys, if this is
considered necessary. Such surveys may be taken into
account for the prescribed regular surveys. 3.1 Annual Survey
The Annual Survey of the diving system shall include
1.7 If it is either impracticable or excessively at least the following tests and checks:
costly to prepare units and components for internal
survey on board, surveys may also, on application by 3.1.1 Examination of the documents relating to the
the operator, be performed in the manufacturer's diving system and scrutiny of the operational records.
works or other authorized workshop.
3.1.2 The entire compression chamber system in-
2. Explanatory notes on surveys cluding all fixtures, penetrations, doors and covers,
seals, locking systems etc. is to be inspected for
2.1 The locally responsible Surveyor of GL is to visible damages, cracks, deformation, corrosion
be given timely notice when regular surveys become attacks and fouling.
due or when it is intended to carry out repairs or al-
terations, so that the work can be supervised. 3.1.3 All other pressure vessels and apparatus,
valves, fittings and safety equipment are to be sub-
2.2 The records of each survey, as well as special jected to external inspection.
requirements upon which the maintenance of class has
been made conditional, will be entered in the Diving 3.1.4 The entire power supply system, including
System Certificate. In addition to the character of the emergency supply, of the diving system is to be
classification and the month and year of classification, subjected to external inspection.
Chapter 1 Section 1 D Rules for Classification of Diving Systems and Diving Simulators I - Part 5
Page 1–4 GL 1998

3.1.5 Switching from the main to the emergency 3.3.1 A tightness test is to be performed on the
electricity supply is to be tested. compression chamber system at 1,1 times the maxi-
mum permissible operating pressure using air.
3.1.6 Insulation measurements are to be performed
on the electrical equipment. 3.3.2 Dimensional checks and non-destructive wall
thickness tests are to be performed on the diving bell.
3.1.7 The accuracy of all important instrument Where necessary, buoyancy aids, cladding and layers
readings is to be checked (e.g. depth gauge, gas ana- of thermal insulation are to be removed for this pur-
lyzer, etc.). pose.

3.1.8 All emergency systems are to undergo a 3.3.3 Emergency ballast release and buoyancy tests
functional test (e.g. the autonomous gas supply of the are to be performed with the diving bell.
diving bell).

3.1.9 The handling system is to be checked for 3.3.4 Pressure vessels and apparatus not capable of
visible damages, cracks and deformations and is to satisfactory internal inspection and those whose satis-
undergo a functional test including a brake test (power factory condition cannot be definitely established by
failure). internal inspection are to be inspected by another non-
destructive method of examination or are to be sub-
3.1.10 All high-pressure gas supply and charging jected additionally to a hydraulic pressure test.
hoses and the hoses belonging to the heating system
and the umbilical are to be checked for visible damage 3.3.5 Acrylic viewport windows are to be dis-
and tightness. mounted and examined for incipient cracks. Window
seatings are to be examined for corrosive attack.
3.2 Intermediate Survey
3.3.6 If, within the period of class, surveys are
An Intermediate Survey is an Annual Survey extended performed on a diving system or parts thereof which
as follows unless it coincides with the Class Renewal are equivalent in scope to a Class Renewal Survey, the
Survey in accordance with 3.3: regular Class Renewal Survey of the parts concerned
may, on application by the operator, be deferred ac-
3.2.1 Performance of a tightness test on the com- cordingly.
pression chamber system at maximum permissible
operating pressure using air.
3.4 Damage Survey
3.2.2 Verification of the set pressures and reset
pressures of compression chamber relief valves and of 3.4.1 If a diving system has suffered damage af-
safety and warning systems. fecting its class or if such damage may be assumed, or
if the hull or parts of the machinery of the support
3.2.3 Functional tests on mechanical and electrical vessel have received damage affecting the diving sys-
equipment. tem a Damage Survey is to be carried out.

3.2.4 Functional tests on life support systems 3.4.2 Following damage, the diving system is to be
presented for survey in such a way that a satisfactory
3.2.5 Functional tests on fire warning and extin- inspection can be carried out. The extent of the Dam-
guishing systems. age Survey will be determined by GL in each
individual case.
3.2.6 Functional tests on all alarm systems.
3.5 Special Survey
3.2.7 Functional test and purity check on all
breathing gas compressors.
3.5.1 When any modification is made in respect of
design, mode of operation or equipment, and after
3.2.8 After ten years, all compression chambers are major repairs to pressure vessels, the diving system is
to undergo a hydrostatic internal pressure test. to be subjected to a Special Survey.
3.2.9 Check of acrylic viewport windows
(maximum service period: 10 Years). 3.5.2 In addition, mobile diving systems are to
undergo a Special Survey equivalent in scope to an
Extended Annual Survey after each re-assembly and
3.3 Class Renewal Survey whenever there is a change of ship.
A Class Renewal Survey is performed every five
years. The following tests and examinations are to be 3.5.3 A further check shall be made to ensure that
carried out in addition to the inspections called for the diving system is properly installed and secured on
under 3.2: the ship or floating structure.
I - Part 5 Section 1 E Rules for Classification of Diving Systems and Diving Simulators Chapter 1
GL 1998 Page 1–5

E. Surveys other than for Classification all the necessary surveys, acceptance tests and pres-
sure tests and issue the relevant certificates.
1. Survey by special agreement
2.2 On application, the Society will also perform
Where surveys are required by official ordinances, the subsequent surveys required for pressure vessels
international agreements or other provisions, GL will and apparatus.
undertake them on application, or by official order in
accordance with the relevant provisions. 3. Certification
On application, GL will issue an appropriate certi-
2. Surveys relating to the safety of equipment ficate in respect of diving systems or parts thereof
which, while not classified by GL, are built under the
2.1 For all components with an important safety survey of and in accordance with the Rules of GL or
aspect (e.g. pressure vessels and apparatus etc.), GL other recognized rules for the construction of diving
will, on application, examine the drawings, carry out systems.
I - Part 5 Section 2 A Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–1

Section 2

Rules for Construction of Diving Systems

A. General Rules and Instructions 2. Definitions


For the purpose of these Rules the terms used have the
1. General meanings defined in the following paragraphs unless
expressly provided otherwise:
1.1 The following Rules of Construction apply to
diving systems which are permanently installed on a 2.1 Mating device
ship or similar floating structure and which are classi- The equipment necessary for the connection and dis-
fied by GL. connection of a diving bell to a surface compression
chamber.
They also apply to diving systems which are classified
by GL but which are assembled and installed on a ship 2.2 Breathing gas/breathing mixture
or similar floating structure for a limited period as
required by the operating conditions. All gases/mixtures which are used for breathing dur-
ing diving operations.
They likewise apply to diving systems subject to a
declaration of class equivalent by GL. 2.3 Handling and transfer systems
The plant and equipment necessary for raising, lower-
1.2 The hull and engine plant of diving support ing and transporting the diving bell between the work
vessels are subject to GL Rules for the Classification location and the surface compression chamber.
and Construction, Part 0 – Classification and Surveys
and Part 1 – Seagoing Ships.
2.4 Surface compression chamber

1.3 Designs differing from the Rules of Con- A pressure vessel for human occupancy with means of
struction may be permitted provided their suitability controlling and monitoring the pressure within the
has been verified by GL and they have been recog- chamber.
nized as equivalent.
2.5 Pressure vessel
1.4 Diving systems and parts thereof whose de- A container capable of withstanding an internal work-
velopment is based on new principles and which have ing pressure of 1 bar or over.
not yet been sufficiently tested in practical operation
require special approval by GL. 2.6 Bottle
A pressure container for the storage and transport of
1.5 In the case mentioned in 1.3 and 1.4 GL is gases under pressure.
entitled to require the submission of additional docu-
mentation and the performance of special tests. 2.7 Compression chamber
A pressure vessel for human occupancy under pres-
1.6 GL reserve the right to impose demands
sure.
additional to those contained in the Rules in respect of
all types of systems when such action is necessitated
by new knowledge or practical experience or for the 2.8 Areas subject to explosion hazard
purpose of sanctioning departures from the Rules in Those locations in which an explosive gas-air mixture
specially justified cases. is continuously present, or present for long periods
(zone 0), in which an explosive gas-air mixture is
1.7 National regulations existing alongside GL's likely to occur in normal operation (zone 1); in which
Rules are unaffected. an explosive gas-air mixture is not likely to occur and,
if it does, will persist for only a short time (zone 2).
1.8 Diving systems conforming to these Rules for
2.9 Fixed system
Construction also comply with the requirements of the
IMO Code of Safety for Hyperbaric Evacuation Sys- A diving system installed permanently on ships or
tems, Resolution A.831(19) of 23 November 1995. floating structures.
Chapter 1 Section 2 A Rules for Construction of Diving Systems I - Part 5
Page 2–2 GL 1998

2.10 Maximum operating depth of the diving 2.20 Temporary system


system
A diving system installed on ships or floating struc-
The depth in metres of seawater equivalent to the tures for a period not exceeding one year.
maximum pressure for which the diving system is
designed. 2.21 Umbilical

2.11 Main components of a diving system The link between the diving support unit and the div-
ing bell which may contain surveillance, communica-
Surface compression chamber, diving bell, handling tion and power supply cables, breathing gas, and hot
system and fixed gas storage facilities. water hoses. The strength member for hoisting and
lowering the diving bell may be part of the umbilical.
2.12 Hyperbaric evacuation system
2.22 Living compartment
A system whereby divers under pressure can be safely
evacuated from a ship or floating structure to a posi- The part of the surface compression chamber which is
tion where decompression can be carried out. intended to be used as the main habitation for the di-
vers during diving operations and which is equipped
2.13 Compact umbilical for such purpose.
A link cable with a protective sheath combining in one
assembly the power supply, surveillance and commu- 3. Components of diving systems
nication lines, the breathing gas and hot water hoses
Where present, the following components form part of
and the hoisting and lowering strength member.
the diving system and are to be designed, constructed
and tested in accordance with these Rules:
2.14 Life support system
– Compression chambers
The gas supply, breathing gas system, surveillance
system and equipment required to provide a safe envi- – Wet bells
ronment for the diving crew in the diving bell and the
surface compression chamber under all possible pres- – Diving bells
sures and conditions to which they may be exposed
during diving operations. – Permanently installed gas bottles
– Pressure vessels
2.15 Category A machinery space
– Pipes, valves, fittings and hoses
Category A machinery space means spaces and pas-
sageways as defined in the 1974 International SOLAS – Umbilicals
Convention.
– Breathing gas systems
2.16 Wet bell
– Life support systems
Open submersible device, including accessories, for
the carriage of divers at the ambient pressure prevail- – Diver heating systems
ing between a mobile or stationary platform and the
underwater site. – Sanitary systems
– Communication systems
2.17 Diving bell
– Control, automation and locating equipment
A submersible compression chamber, including its
ancillary equipment, for transfer of divers under pres- – Gas analyzing systems
sure between the work location and the surface com-
pression chamber. – Electrical systems and equipment
– Fire prevention, detection and extinguishing
2.18 Diving system
equipment
The whole plant and equipment necessary for the con-
duct of diving operations using transfer under pressure – Compressors
techniques. – Gas mixers

2.19 Depth – Helium reclaim system


The pressure, expressed in metres of seawater to – Handling, transfer and mating systems
which the diver is exposed during a dive or inside a
surface compression chamber or diving bell. – Hyperbaric evacuation system.
I - Part 5 Section 2 A Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–3

4. Documents for approval – Proposed materials, thermal insulation materials,


paints, buoyancy material
4.1 General
– Welding specifications
4.1.1 Before the start of manufacture, plans and – Heat treatment
drawings of all components subject to compulsory
inspection, to the extent specified below, are to be – Manufacturing tolerances
submitted to Germanischer Lloyd in triplicate.
– Non-destructive tests.
4.1.2 The drawings must contain all the data neces-
4.3.2 Drawings are also to be submitted of individ-
sary to check the design and the loading of the equip-
ual items of vessel equipment such as:
ment. Wherever necessary, calculations relating to
components and descriptions of the system are to be – Windows, window flanges, retaining rings
submitted.
– Door leaves and frames
4.1.3 Once the documents submitted have been
– Bayonet locks
approved by GL, they become binding on the manu-
facturer. Any subsequent modifications require GL's – Coupling clamps
consent before they are implemented.
– Integral opening reinforcements
4.2 Total system – Supply locks
The following documents are to be submitted. – Internal facilities.
4.2.1 A description of the system together with the
essential design data including: 4.4 Gas supply

– Diving procedure 4.4.1 Piping diagrams, block diagrams and de-


scriptions are to be furnished for the entire gas supply
– Maximum diving or observation depths, as ap- system, including a list of valves and fittings.
plicable
– Maximum operating time 4.4.2 Details of the umbilical structure.

– Maximum number of divers per diving bell 4.4.3 Description of proposed cleaning procedure
– Maximum number of divers in system. for breathing gas system.

4.2.2 General arrangement drawings of the diving 4.4.4 Details of the gas analysis, including an
system (block diagrams) equipment list.

4.2.3 Installation drawings 4.4.5 Description of compressors and compressor


drives including longitudinal and transverse sectional
4.2.4 Foundation drawings showing fixed points drawings of the compressors and a workshop drawing
of the compressor crankshaft.
4.2.5 Drawings of supply and disposal systems
(water and electricity) 4.5 Life support systems

4.2.6 Drawings of consoles showing controls and The following documents are to be submitted:
instrument displays
4.5.1 Piping diagrams, block diagrams and descrip-
4.2.7 Test schedule tions of systems and equipment.

4.5.2 Calculations of the cooling and heating re-


4.3 Pressure vessels and apparatus
quirements.
4.3.1 Drawings are to be submitted of pressure
vessels and apparatus giving full details for appraising 4.5.3 Description and drawings of the water supply
the safety of the equipment. and disposal system.

The information provided shall include the following: 4.5.4 Description and design details of the diver
heating system.
– Application of equipment
– Capacities of individual compartments 4.6 Automation, communications and locating
equipment
– Media contained, together with operating pres-
sures and temperatures The following documents are to be submitted:
Chapter 1 Section 2 A Rules for Construction of Diving Systems I - Part 5
Page 2–4 GL 1998

4.6.1 General arrangement drawings/block dia- – Fire extinguishing system(s)


grams of control equipment, including lists of meas-
uring points. – Fire alarm equipment.

4.6.2 Equipment list covering sensors, indicating 4.9 Handling, transfer and mating systems
instruments etc.
4.9.1 A description of the system with details of
4.6.3 Drawings and descriptions of electronic com- operating conditions.
ponents such as instrument amplifiers, computers and
peripheral units. 4.9.2 Installation drawing.
4.6.4 General arrangement drawings and equip- 4.9.3 Construction drawings of:
ment lists for communications systems and signalling
equipment. – Transfer equipment
4.6.5 Arrangement drawing and description of the – Lifting equipment
TV system.
– Mating equipment
4.7 Electrical equipment – Substructures of handling gear, including
The following documents are to be submitted: winches.

4.7.1 A general arrangement drawing of the electri- 4.9.4 Detailed drawings of interchangeable compo-
cal equipment containing at least the following infor- nents and fittings.
mation:
– Voltage rating of systems 4.9.5 Drawings of mechanical equipment items
such as winches, drives etc.
– Power or current ratings of electrical consumers
– Switchgear, indicating settings for short-circuit 4.9.6 Piping and instrumentation diagrams of the
and overload protection; fuses with details of hydraulic or pneumatic system, as applicable.
current ratings
4.9.7 Control system diagram and description of
– Cable types and cross-sections. safety equipment.
4.7.2 The energy balance of the main and emer-
gency power supply systems for diving systems with 4.9.8 Details or ratings and protection class of
their own generating plant. electrical appliances.

4.7.3 Drawings of switchgear and distribution 4.9.9 Details of hoisting and guide ropes.
equipment.

4.7.4 Complete documentation for electric motor 4.10 Hyperbaric evacuation system
drives with details of control, measuring and moni- The following documents are to be submitted:
toring systems.
4.10.1 Description of system
4.7.5 Battery installation drawing with details of
battery types, chargers and battery room ventilation.
4.10.2 Arrangement drawing
4.7.6 Details of electrical penetrations through
compression chamber walls. 4.10.3 Construction drawing of evacuation system

4.7.7 Drawings and descriptions of all electrical 4.10.4 Drawing of the handling system, including a
components installed in compression chambers. description of the power supply.

4.8 Fire protection 4.11 Wet bells


The following documents are to be submitted: To be submitted:

4.8.1 A description of the preventive fire protection 4.11.1 System description


measures taken.
4.11.2 Arrangement plan
4.8.2 Details of the fire loads in the system.

4.8.3 Drawings and descriptions of: 4.11.3 Construction drawings (bell, handling sys-
tem, control platform, gas supply, umbilical, electrical
– Fire detection system equipment)
I - Part 5 Section 2 A Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–5

5. Tests and trials 5.2.5 Diving bells and vessels which may be ex-
posed to an external pressure in service are also re-
5.1 General quired to undergo an external pressure test. The exter-
nal test pressure used shall normally be equivalent to
5.1.1 Diving systems and their ancillary equipment 1,3 times the design pressure.
are subject to constructional and material tests as well
as to pressure and tightness tests and trials. All the 5.2.6 The weight and buoyancy of diving bells are
tests called for in the following paragraphs are to be to be measured and their stability in normal and emer-
performed under GL supervision. gency operation is to be checked. The release of bal-
last weights and the operation of the device for the
5.1.2 For series-manufactured parts, test proce- emergency release of the hoisting rope and the umbili-
dures other than those prescribed may be agreed with cal are to be tested in shallow water.
GL provided that they are recognized as equivalent by
GL. 5.2.7 The gas storage facilities, diving system and
life support systems including the gas piping are to be
5.1.3 Germanischer Lloyd reserves the right to subjected to a tightness test at the maximum permissi-
extend the scope of the tests where necessary and also ble working pressure using the appropriate breathing
to subject to test those parts for which testing is not gas or a gas mixture with similar properties.
expressly prescribed in the Rules.
The maximum permissible leakage rate is represented
by a 1 % pressure drop in 24 hours for the entire com-
5.1.4 Parts subject to compulsory inspection are to
be replaced with tested parts. The same also applied to pression chamber system.
spare parts.
5.3 Compression chamber windows
5.1.5 After the compression chambers and ancillary
equipment have been installed on board, the diving 5.3.1 Each compression chamber window must
system together with its ancillary plant is to be sub- undergo a hydraulic pressure test which may be per-
jected to functional test. All items of safety equipment formed after installation together with the compres-
are to be tested except where an adequate trial has sion chamber or in a testing device. The test pressure
already been performed on the manufacturer's prem- shall normally be equivalent to 1,5 times the design
ises in the presence of GL's representatives. pressure.

5.1.6 During sea trials the handling system is to be 5.3.2 After the pressure test windows may exhibit
subjected to a test in which the diving bell loaded to no scratches, cracks or permanent deformations.
its maximum weight is lowered to its maximum op-
erating depth. Thereafter, the diving bell is to be in- 5.4 Compressors
spected for leaks and the communication system is to
be tested. 5.4.1 Compressor components subjected to pres-
sure are to undergo a hydraulic pressure test at a test
pressure equal to 1,5 times the delivery pressure of the
5.2 Pressure vessels and apparatus
compressor stage concerned.
5.2.1 On completion, pressure vessels and appara-
tus are to be subjected to a constructional test. 5.4.2 On completion, compressors are to be sub-
jected to a tightness test at their maximum working
The constructional test includes verification that the pressure. In addition, a performance test is to be car-
vessel conforms to the approved drawings and that the ried out in which the final moisture content and any
workmanship is satisfactory. All components must be possible contamination of the compressed gas are to
accessible to allow adequate inspection. be determined. The safety devices are to be checked.

5.2.2 The materials test certificates for the materi- 5.5 Piping systems
als used and the reports on the non-destructive testing
of welds are to be submitted together with the results 5.5.1 On completion of manufacture but before
of inspections of workmanship and evidence of the insulation or painting, all piping systems are to un-
heat treatments applied, where appropriate. dergo a hydraulic pressure test at 1,5 times the design
pressure.
5.2.3 A hydraulic pressure test is to be performed
prior to insulation and preservation treatment of the 5.5.2 For the tightness test, see 5.2.7.
vessels. Each compression chamber compartment is to
be tested individually. The walls may exhibit no per- 5.5.3 Wherever possible, all butt welds in LSS
manent deformation or leakage. piping systems are to be subjected to 100 % X-ray
test.
5.2.4 For vessel and apparatus, the test pressure
shall normally be equivalent to 1,5 times the maxi- 5.5.4 Piping systems for breathing gas and oxygen
mum permissible working pressure. are to be subjected to a purity test.
Chapter 1 Section 2 A Rules for Construction of Diving Systems I - Part 5
Page 2–6 GL 1998

5.6 Hoses, umbilicals 5.9.3 Electrical protective devices are to be


checked; in addition, an insulation test is to be per-
5.6.1 Evidence of the bursting pressure of each formed on the electrical equipment in the compression
hose type is to be submitted to GL. For liquids, hoses chambers.
must withstand at least 4 times, and for gases at least 5
times, the maximum permissible working pressure. 5.10 Fire protection

5.6.2 Each hose is to be subjected to a hydraulic 5.10.1 The fire behaviour of the chamber equipment
pressure test at least 2 times the maximum permissible is to be checked by reference to the relevant test cer-
working pressure. tificates and symbols, as applicable.

5.10.2 A check is to be made as to whether the elec-


5.6.3 For hoses exposed to external pressure, proof
trical heating systems and heaters are fitted with pro-
is required that a differential ratio of 1,5 between the
tection against overheating.
internal and external pressures can be withstood with-
out failure. 5.10.3 Fire alarm, detection and extinguishing appli-
ances are to be subjected to a functional test.
5.6.4 As proof of their mechanical properties, com-
pact umbilicals are to be subjected to alternating bend 5.11 Handling, transfer and mating systems
tests and rupture tests.
5.11.1 After installation on board, the handling sys-
In addition, compact umbilicals are to undergo a tight- tem is to be loaded statically with a test load equal to
ness test in which all hoses are to be subjected simul- 2,2 times the working load. In addition, a dynamic
taneously to their maximum permissible working pres- load test (braking test) is to be carried out at 1,25
sure and the electrical lines are to be checked for com- times the working load.
pliance with the specified insulation and impedance
values. 5.11.2 A test is to be performed to ensure that the
mating, release, transfer, lowering and raising of the
5.7 Life support systems diving bell proceed smoothly and safely under normal
and emergency operating conditions.
A functional test is to be carried out to verify the satis-
factory functioning of the life support systems under 5.11.3 A test is to be performed to verify that the
normal and emergency conditions. mating device can be released and the diving bell
transported only when the trunk is not under pressure.
5.8 Automation, communications and locating
equipment 5.12 Hyperbaric evacuation system

5.8.1 Indicating and monitoring instruments are to A functional test is to be performed to demonstrate
be tested for the accuracy of their readings and their that the hyperbaric evacuation system is able to con-
limit value settings. vey divers under pressure from the ship or floating
structure to a safe position where they can be moni-
5.8.2 Automatic control systems are to be checked tored and supplied.
for satisfactory performance under service conditions.
5.13 Wet bells
5.8.3 Normal and emergency communications During operational trials proofs are to be furnished of:
equipment is to be subjected to a functional test. The
effectiveness of the helium speech unscrambler is to – Launching and recovery of wet bell under
be demonstrated for the maximum operating depth of maximum load and, where practicable, down to
the diving system. maximum depths
– Main and emergency breathing gas supply, in-
5.8.4 Proof is required of the autonomy of the cluding control and monitoring equipment
safety systems.
– Equipment for salvaging divers heaving suffered
an accident
5.9 Electrical equipment
– Communication equipment.
5.9.1 Electrical machines, components, cables and
lines are to be tested in the manufacturer's works in 6. Marking
accordance with the Rules for Classification and Con-
struction, Part 1 – Seagoing Ships, Chapter 3 – Elec-
6.1 All diving bells and surface compression
trical Installations.
chambers are to be fitted in a prominent position with
a permanently mounted name plate containing at least
5.9.2 All electrical systems and equipment are to the following details:
be inspected and tested before the diving system is put
into service. – Name of manufacturer
I - Part 5 Section 2 B Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–7

– Serial number and year of manufacture – Static test load


– Maximum permissible working pressure or – Operational test load
operating depth
– Maximum working load
– Test pressure
– Date of test and test stamp.
– Capacity (in litres) (of each chamber compart-
ment)
– Maximum permissible number of divers B. Principles for the Design and Construction
– Date of test and test stamp. of Diving Systems

6.2 All other pressure vessels and gas bottles are 1. General principles
to be prominently and permanently marked with the
following details: 1.1 Wherever expedient and feasible, diving
– Name of manufacturer systems are to be designed and constructed in such a
way that failure of any single component cannot give
– Serial number and year of manufacture rise to a dangerous situation.
– Capacity (in litres)
1.2 Diving systems and their components are to
– Test pressure (bar) be designed to meet the service conditions stated in
the specification of the system.
– Empty weight (of gas bottles)
– Date of test and test stamp. 1.3 Diving systems are to be constructed to en-
sure that persons under pressure can be safely con-
6.3 Permanently installed gas bottles, gas con- veyed from the surface compression chamber to the
tainers and gas piping systems are, in addition, to be underwater work location (and back).
marked with a permanent colour code in accordance
with Table 2.1 and with the chemical symbol desig- 1.4 Diving systems are to be designed and built
nating the type of gas concerned. The marking of gas to ensure safe operation and facilitate proper mainte-
bottles must be visible from the valve side. nance and the necessary surveys.

Table 2.1 Marking of gas systems 1.5 All parts of a diving system are to be de-
signed, constructed and mounted in such a way as to
facilitate cleaning and desinfection.
Chemical
Type of gas Colour code
symbol
2. Environmental conditions
Oxygen O2 white
2.1 Diving systems together with their accesso-
Nitrogen N2 black
ries and ancillary equipment are to be designed for the
Air --- white & black environmental conditions likely to occur at the pro-
posed point of installation or work location. As a
Helium He brown minimum requirement, allowance is to be made for the
following conditions:
Oxygen/
Helium-Gas O2/He white & brown 2.2 The inclined positions stated in Table 2.2.
mixture
2.3 The other environmental conditions stated in
6.4 All valves, fittings, controls, indicators and Table 2.3.
warning devices are to be provided with identification
plates made of a material which is at least flame retar-
3. Conditions in chamber
dant. The identifying marks are to be clear and un-
mistakable (e.g. stating the short designation and/or
the function of the item concerned). 3.1 Diving systems are to be so equipped that a
breathable atmosphere can be maintained in surface
6.5 The handling, transporting and mating appli- compression chambers and diving bells throughout the
ances are to be fitted with a prominent and perma- entire operating period.
nently mounted name plate containing at least the
following information in easily legible characters: 3.2 Facilities must be provided for keeping the
partial pressure of the CO2 in the chamber atmosphere
– Name of manufacturer
permanently below 0,005 bar assuming a CO2 produc-
– Serial number and year of manufacture tion rate of 0,05 Nm3/h per diver.
Chapter 1 Section 2 B Rules for Construction of Diving Systems I - Part 5
Page 2–8 GL 1998

Table 2.2 Inclined positions

Angle of inclination [°]


Components Athwarthships For-and-aft
static dynamic static dynamic
Compression chambers and
other deck installations on ships ± 15 ± 22,5 ± 5 ± 10
on semi-submersible ± 15 --- ± 15 ---
Diving bells ± 22,5 ± 45 --- ---

Table 2.3 Environmental conditions

Location Temperature Humidity Other conditions


In chambers 5 to 55 °C 100 %
Outside chambers in air 1 2 - 10 to + 55 °C 100 % salty air
salt water containing
Outside chambers in water - 2 to + 32 °C ---
3,5 % salt
Control rooms 5 to 55 °C 80 % ---
1 In the case of facilities installed on the open deck, allowance is to be made for icing and temporary inundation with salt water and
spray.
2 Other values may be permitted for installation in closed spaces.

In diving bells it must be possible to keep the partial Chapter 2 – Guidelines for the Explosion Protection of
pressure of the CO2 below 0,015 bar as a minimum Electrical Equipment.
requirement. Under emergency conditions it must be 4.2 As far as possible, the area in which the div-
possible to hold the partial pressure of the CO2 below ing system is installed is to be kept free of fire loads.
0,02 bar for at least 24 h.
In addition, only those electrical cables needed to
operate the diving system should be routed through
3.3 Diving systems using mixed gas and de- this area.
signed for operating periods of more than 12 hours at
a time must be capable, under steady conditions, of 4.3 Diving systems and breathing gas storage
keeping the temperature in the surface compression facilities may not be located in engine rooms unless
chamber constant to ± 1 °C in the 27 - 36 °C range the engine plant is connected to the diving system.
while maintaining a relative humidity of at least 50 %.
4.4 Diving systems and breathing gas storage
3.4 Surface compression chambers are to be facilities are to be located in spaces which can be
designed and equipped in such a way that a homoge- adequately ventilated and provided with suitable elec-
neous atmosphere (CO2 and O2 concentrations, tem- tric lighting.
perature and humidity) can be maintained in the cham-
ber. 4.5 Where parts of the diving system are located
on the open deck, these are to be protected against
damage due to other shipboard activities.
3.5 In the steady state, the permanent noise level
(over 8 hours) in the living compartment and surface
compression chamber may not exceed 65 dB(A). 5. Chamber equipment and fittings

5.1 The equipment and fittings of surface com-


4. Location pression chambers and diving bells must be suitable
for operation in hyperbaric atmospheres. Under these
4.1 Diving systems on ships and other floating conditions they shall not give off any toxic or strongly
structures may only be located and operated in areas irritant gases. The same also applies to protective
not subject to an explosion hazard. In exceptional coatings and paints used inside the chambers.
cases, installation subject to special conditions may be
permitted in zone 2 as defined in VI – Additional 5.2 Only incombustible or at least flame retardant
Rules and Guidelines, Part 8 – Electrical Technology, materials should be used in the chambers (cf. I.2.2.1).
I - Part 5 Section 2 C Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–9

6. Corrosion protection 1.2.1.5 Locks are to be designed to prevent acci-


dental opening under pressure: if necessary, suitable
6.1 Diving systems and all their accessories are interlocks are to be fitted.
to be effectively protected against corrosion.
1.2.1.6 Each compression chamber compartment is
to be provided with view ports enabling all occupants
6.2 Anti-corrosion coatings exposed to the con-
to be observed from outside.
ditions within the chambers must conform to the re-
quirements stated in 5. In addition, they may not tend 1.2.1.7 Wherever necessary, compression chamber
to blister of flake under hyperbaric conditions. windows are to be protected against mechanical dam-
age from inside and outside.
1.2.1.8 Each compression chamber compartment is
C. Pressure Vessels and Apparatus to be adequately lit.

1.2.2 Diving bells


1. Compression chambers and diving bells
1.2.2.1 Each diving bell is to be so equipped that it is
1.1 General fully protected against excessive working pressures
and inadmissible pressure drops.
1.1.1 The following Rules are applicable to com-
pression chambers and diving bells which are used in 1.2.2.2 Each diving bell is to be provided with an
diving systems and in which persons live in breathable extra lifting point designed to take the entire dry
atmosphere at pressures exceeding atmospheric pres- weight of the bell including ballast and equipment
sure. plus the weight of the persons inside the bell.

1.1.2 The documents to be submitted to GL for 1.2.2.3 Close to main lift attachment, the diving bell
approval are listed in A.4. is to be provided with spare connections for hot water
(3/4" NPT female thread) and breathing gas (1/2" NPT
1.1.3 The necessary tests and markings are stated female thread). The manifold is to be clearly marked
in A.5. and A.6. and effectively protected.
1.2.2.4 Diving bells are to be designed to allow entry
1.2 Design principles and exit even in an emergency.
1.2.1 Compression chambers 1.2.2.5 Diving bells are to be equipped with a device
for the recovery of an unconscious diver.
1.2.1.1 Each compression chamber or compartment
thereof is to be so equipped that it is fully protected 1.2.2.6 The dimensional design of diving bells shall
against excessive working pressures and inadmissible be such as to provide adequate space for the proposed
pressure drops. number of divers and their equipment.
1.2.1.2 Compression chambers are to be so designed 1.2.2.7 Seating is to be provided for each diver in the
that at least two persons can simultaneously pass in or diving bell.
out through the locks without exposing the other di-
vers in the system to a pressure change. 1.2.2.8 Diving bells are to be provided with view
ports so that divers working outside the bell can be
1.2.1.3 In diving systems where divers are required observed from within the chamber.
to remain under pressure for a continuous period of
more than 12 hours, the living compartment of the 1.2.3 Doors and access ports
compression chamber is to be so designed and
equipped that persons are able to stand upright in it 1.2.3.1 Diving bell hatches and mating devices
and each diver is provided with a bunk on which he is which are not sealed by pressure are to be fitted with a
able to stretch out comfortably. A toilet and shower locking mechanism which precludes opening under
are also to be provided. The toilet and shower are to pressure. The locking mechanism is to be so designed
be accommodated in a separate compartment. Toilet that the correct closure position is clearly apparent
facilities capable of discharging the waste to outside before pressure is applied.
are to be equipped with suitable interlocks to prevent
pressure losses in the chamber system. 1.2.3.2 Devices are to be fitted to enable doors to be
opened from both sides. Hatch trunks are to be fitted
1.2.1.4 The living compartment of compression with pressure compensating valves.
chambers and other compression compartments are to
be provided with a lock through which provisions, 1.2.3.3 Doors and hatches for persons are required to
medicines and equipment items can be passed to and have a clear opening at least 500 mm in diameter. For
for without exposing the occupants of the chamber to diving bell lockout/-in hatches the clear diameter shall
a pressure change. be at least 600 mm.
Chapter 1 Section 2 C Rules for Construction of Diving Systems I - Part 5
Page 2–10 GL 1998

1.2.3.4 The length of the hatch trunk should not ex- 1.3.2 Approved materials
ceed the hatch diameter.
The materials stated in Table 2.4 are to be used for
compression chambers and diving bells.
1.3 Materials

1.3.1 General requirements 1.3.3 Material testing

1.3.1.1 The materials for pressure vessels must be 1.3.3.1 Tests in accordance with the Rules for Clas-
suitable for the proposed application and must con- sification and Construction, II-Material and Welding
form to the Rules for Classification and Construction, Technology, Part 1 and 2, are performed on materials
II – Materials and Welding, Part 1 – Metallic Materi- for:
als and Part 2 – Non-metallic Materials. Unless other- – all walls subjected to pressure with the excep-
wise specified, the stipulated impact energy is to be
tion of small parts such as welding lugs, rein-
verified on ISO V-notch specimens at the following forcing plates, pipe connections and flanges
test temperatures:
with DN ≤ 32 mm
– forged flanges where the product of PB [bar]
Product thickness Test temperature [°C] DN [mm] is > 2500 or the nominal bore DN is
≤ 20 mm 0 > 250 mm
> 20 ≤ 40 mm - 20 – screws and nuts of size M 30 and over where
> 40 ≤ 60 mm - 40 made of steels with a tensile strength of more
> 60 mm by agreement than 500 N/mm2 and for sizes > M 16 in the
case of nuts over 600 N/mm2 and screws made
1.3.1.2 For parts welded directly to pressure vessel of alloy or quenched and tempered steels.
walls, e.g. reinforcing rings, mountings, brackets etc.,
use is to be made of materials with guaranteed weld- 1.3.3.2 For all parts not subject to materials testing
ing properties which are compatible with the base by GL, some other proof of the material characteristics
material. such as acceptance test certificates to EN 10204 - 3.1
B is to be supplied.
1.3.1.3 Welded structures are also subject to the
Rules for Classification and Construction, II –Mate- 1.3.3.3 Components such as mountings, brackets and
rials and Welding, Part 3 – Welding. the like which are not subject to materials testing must
be manufactured from materials compatible with their
1.3.1.4 For corrosion protection, see B.6. of these application in accordance with good engineering prac-
Rules. tice.

Table 2.4 Approved materials

Types of material in accordance with the Rules for Classification


Material and product form and Construction, II-Materials and Welding,
Part 1, Chapter 2
Plates of unalloyed steels to Section 1, E. Specially killed steels to
Steel plates, section and bars Section 1, B. and C. (within inspection of each rolled plate). Austenitic
stainless pipes to Section 1, C.
Seamless and welded pipes of ferritic steels to Section 2, B. and C.
Pipes
Austenitic stainless pipes to Section 2, E.
Forgings Forgings to Section 3, E.
Screws and nuts to Section 6, C. recognized standards, e.g. DIN 367 or
Screws and nuts
ISO 898
Steel castings To Section 4.
Non-ferrous metals Only with the Society's special consent
The use of materials not mentioned in this Table, e.g. special grain refined structural steels, is subject to the
Society's special consent.
I - Part 5 Section 2 C Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–11

1.4 Principles of manufacture and construc- 1.4.6.2 For the testing of screws and bolts, see 1.3.3.
tion
1.4.7 View ports
1.4.1 Manufacturing processes
1.4.7.1 For the purpose of these Rules, view ports are
The manufacturing processes applied to materials sealed, pressure-tight windows of flat or curved
must conform to good engineering practice. Materials acrylic plastic installed in the walls of surface com-
whose grain structure has been impaired by hot or cold pression chambers or diving bells and used respec-
working are to be heat treated in accordance with tively for observing the divers in the chamber and at
Rules for Classification and Construction, II – Materi- the work location (cf. Appendix B).
als and Welding, Part 1 – Metallic Materials, Chap-
ter 2 – Steel and Iron Materials, Section 6, A. 1.4.7.2 In the design and construction of view port
flanges it is to be borne in mind that the acrylic plastic
1.4.2 Welding windows make no contribution to reinforcing the cut-
out in the wall of the compression chamber. Where the
1.4.2.1 The execution of welds, the approval of clear diameter of view port flanges is greater than
welding ships and the testing of welders are subject to 350 mm, the permissible radial deformation and the
the Rules for Classification and Construction, II – angular tolerances of the window seating are subject
Materials and Welding, Part 3 – Welding. to more stringent requirements which are to be agreed
with GL in each case.
1.4.2.2 Welds are to be executed and inspected in
such a way as to warrant the allocation of a weld fac- 1.4.7.3 The dimensions of the window seating in the
tor v = 1,0. view port flange shall be such as to provide adequate
support for the window at maximum working pres-
1.4.3 Reinforcement of cutouts sure. The seating dimensions for various standard
windows are specified in Appendix B.
Due to allowance is to be made of the weakening of
walls by cutouts, and reinforcement is to be provided 1.4.7.4 For flat windows with a rectangular edge and
where necessary (cf. Rules for Classification and Con- an O-ring seal, the diameter of the seating in the view
struction, Part 1 – Seagoing Ships, Chapter 2 – Ma- port flange is to be within + 0,25/- 0,00 mm of the
chinery Installations, Section 7a, D. nominal value; where a flat seal is used the tolerances
are + 0,75/- 0,00 mm.
1.4.4 Ends
1.4.7.5 With spherical shell windows having a coni-
1.4.4.1 The nuckle area of dished ends shall not be cal seating, the larger diameter of the conical seating
unduly inhibited by fixtures of any kind such as re- in the view port flange shall lie within + 0,002 Do/-
straining plates, stiffeners etc. Supporting legs may 0,000 mm of the nominal value.
only be fixed to ends which have been adequately
dimensioned for this purpose. The included conical angle of the window seating of
the view port flange shall be within + 0,000/- 0,25
1.4.4.2 Where covers or ends are secured by swing degrees of the nominal value.
bolts, measures are to be taken to prevent these slip-
1.4.7.6 The surface roughness of the window seating
ping off.
shall not exceed 1,5 µm.
1.4.5 Nozzles 1.4.7.7 The window seating must be permanently
protected against corrosion (e.g. a corrosion-resistant
1.4.5.1 The wall thickness of nozzles must be de- weld overlay).
signed to withstand safely any additional external
loads. The wall thickness of welded-in nozzles shall 1.4.7.8 A soft sealant may be used for the primary
be compatible with that of the component into which seal of standard windows according to Appendix B,
they are welded. The walls must be securely welded Tables 2 and 3. The seal must be thick enough to ab-
together. sorb reasonable deformation without permanent set.
1.4.5.2 Pipe connections in accordance with the 1.4.7.9 For flat windows with a rectangular edge a
Rules for Classification and Construction, Part 1 – second seal is required, which is to be stuck to the
Seagoing Ships, Chapter 2 – Machinery Installations, window seating using contact adhesive. The second
Section 11 are to be provided for nozzles. seal also acts as the window supporting seal and may
not be more than 3 mm thick.
1.4.6 Screws and bolts
1.4.7.10 Neither the window seating nor the metal
1.4.6.1 Stud bolts screwed directly into the wall of a flange seat may contain sealing grooves.
pressure vessel must have within the vessel wall a
load-bearing length at least equal to the bolt diameter. 1.4.7.11 Retaining rings must be capable of sustaining
Bolt holes shall not perforate the vessel wall. the necessary initial compression of the window seals.
Chapter 1 Section 2 D Rules for Construction of Diving Systems I - Part 5
Page 2–12 GL 1998

1.4.7.12 When fitting acrylic plastic windows, care is – Buckling of the shell reinforced with heavy
to be taken to ensure the scrupulous cleanliness of all stiffeners (where applicable, transverse bulk-
seating surfaces. The compatibility with acrylic plastic heads or ends).
of cleaning agents, window seating greases and adhe-
sives for window seals is to be checked before use. The safety factors against elastic buckling are speci-
fied in Chapter 2 – Submersibles, Section 4, E.4.
1.5 Calculations 1.5.2.3 For design temperatures, see B.2.3.

1.5.1 Principles of calculation 1.5.3 Permissible stresses


1.5.1.1 Pressure vessels, hatches, locks, windows, The lesser of the following two values is applicable:
suspensions etc. are to be calculated in accordance
with Germanischer Lloyd Rules (see 2. and Appen- R m,20° = guaranteed minimum ten-
dix B) of other engineering codes, and only the values where Rm,20°
A sile strength [N/mm2] at
stated in 1.5.3 are to be regarded as permissible room temperature (may
stresses. Diving bells for external pressure are to be be dispensed with for es-
calculated according to Appendix A. The collapse tablished grain refined
loading case is not applicable. steels where ReH ≤
360 N/mm2)
1.5.1.2 The calculations underlying the dimensional
design are to be submitted to GL. Where the calcula- R eH,t ° = guaranteed yield point or
where ReH,t°
tions are to be performed by computer, proof of the B minimum value of 0,2 %
suitability of the programs is to be furnished to GL. proof stress at design
temperature
1.5.1.3 Load factors for dynamic loads are to be
agreed with GL. Safety factors A, B see Table 2.5.

1.5.1.4 Allowance is to be made for the fatigue


strength of the material. Surface compression cham- Table 2.5 Safety factors
bers and diving bells are to be designed for at least
5000 operating cycles. Operation Test
Material
1.5.1.5 For the efficiency of welds, see 1.4.2.2. A B B‘
Ferritic material 2,7 1,7 1,1
1.5.1.6 The allowance (c) for corrosion and war is Austenitic material 2,7 1,7 1,1
normally 1 mm. This allowance may be dispensed Aluminium 3,0 – 1,1
with in the case of plate with a thickness of 30 mm
and over and with stainless steels and other corrosion-
resistant materials. 2. Pressure vessels and apparatus and gas
bottles
1.5.1.7 The wall thickness of the casings and ends of
seamless and welded vessels should not normally be Pressure vessels and apparatus and gas bottles are to
less than 3 mm. A smaller wall thickness may be be manufactured in accordance with the Rules for
agreed for tubular and corrosion-resistant vessel cas- Classification and Construction, Part 1 – Seagoing
ings. Ships, Chapter 2 – Machinery Installations, Section 8.

1.5.2 Design data

1.5.2.1 The design pressure (internal pressure, exter- D. Pipes, Valves, Fittings, Hoses and
nal pressure) is to be determined by reference to the Umbilicals
system specification. Where applicable, allowance is
to be made for additional forces. The design pressure
is normally the maximum permissible working pres- 1. General
sure or the maximum operating depth of the diving
system as defined in A.2.10. 1.1 These Rules apply to piping systems, includ-
ing valves and fittings, needed for the operation of the
1.5.2.2 For pressure vessels subjected to external diving system and its ancillary equipment. All other
excess pressure, the calculation is to encompass the pipelines are to conform to the Rules for Classification
following cases: and Construction, Part 1 – Seagoing Ships, Chapter 2
– Machinery Installations, Section 11.
– Buckling of the unstiffened shell
– Buckling of the shell reinforced with light stiff- 1.2 The documents to be submitted to GL for
eners approval are listed in A.4.
I - Part 5 Section 2 D Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–13

1.3 The necessary tests and markings are stated 2.1.8 Pipelines for mixed gases containing more
in A.5. and A.6. than 25 % oxygen are to be treated as pure oxygen
lines.
1.4 Pipes are subdivided in three pipe classes in
accordance with Table 2.6 2.1.9 Wherever possible, the pressure in oxygen
lines is to be reduced at the gas storage facility to a
pressure which is still compatible with an adequate
2. Design principles gas supply to the diving system.

2.1 Piping systems 2.1.10 Gas lines and electrical cables are to be
routed separately.
2.1.1 Piping systems are to be constructed and
manufactured on the basis of standards generally used 2.2 Pipe connections
in shipbuilding.
2.2.1 Wherever possible, pipes should be joined by
full-penetration butt welds.
Table 2.6 Classification of pipes into "pipe
classes" 2.2.2 Screwed pipe connections may only be made
using bite joints approved by GL.
Medium carried/ Design pressure
type of line PR [bar] 2.2.3 Flanged connections may be used provided
that the flanges and flange bolts conform to a recog-
Air, gas
nized standard.
Lubricating oil
2.3 Valves and fittings
Hydraulic oil PR > PR ≤ PR ≤
40 40 16
Brine in refrigerating 2.3.1 Shutoff-devices must conform to a recog-
systems nized standard. Valves with screw-down bonnets or
spindles are to be protected against unintentional un-
Refrigerants --- all --- screwing of the bonnet.
Open-ended lines (with- 2.3.2 Manually operated shutoff devices are to be
out shutoff) such as closed by turning in the clockwise direction.
drains, vent lines over- --- --- all
flow lines and blow-off 2.3.3 The closed and open positions of functionally
lines important shutoff valves must be clearly indicated.
Pipe class I II III 2.3.4 Oxygen lines may only be fitted with screw-
down valves, although ball valves may be used for
2.1.2 Expansion in piping systems is to be com- emergency shutoff at the chamber wall.
pensated by pipe bends or compensators. Attention is
to be given to the suitable siting of fixed points. 2.3.5 Hose fittings are to be made of corrosion-
resistant material and are to be so designed that they
2.1.3 Means must be provided for the complete cannot be disconnected accidentally.
evacuation, drainage and venting of pipelines.
2.4 Hose lines and umbilicals
2.1.4 Pipelines which may be subjected in service
to pressures higher than the design pressure must be 2.4.1 Except for umbilicals, non-metal hoses are to
fitted with overpressure protection. be reduced to a minimum and are only to be installed
in short lengths.
2.1.5 Pipe penetrations in the compression cham-
bers and diving bells must be fitted with 2 shut-off 2.4.2 Hose lines, including their connectors, must
devices located immediately at the chamber wall. be of proven suitability for the media, pressures and
Wherever possible, one of these devices must be a temperatures concerned. When selecting the material,
non-return valve. special attention is to be paid to toxicity, incombusti-
bility, gas permeability and, where applicable, to com-
2.1.6 Suction ends in compression chambers and patibility with oxygen. Only types approved by GL
diving bells are to be protected against inadvertent may be used.
covering and suction.
2.4.3 Hose lines for liquids/gases are to be de-
2.1.7 Pipelines carrying gas or oxygen under high signed for a bursting pressure equivalent to at least 4
pressure shall not be routed through accommodation and 5 times respectively the maximum permissible
spaces, engine rooms or similar compartments. working pressure.
Chapter 1 Section 2 D Rules for Construction of Diving Systems I - Part 5
Page 2–14 GL 1998

2.4.4 Hoses are to be permanently coupled to their 3.2.3 Nodular cast iron, cast steel
connectors.
3.2.3.1 Ferritic nodular cast iron valves and fittings
2.4.5 Systems with hose lines are to be fitted with a are permitted only in special cases.
device for relieving the pressure before the hoses are
disconnected. 3.2.3.2 Cast steel is approved for general application
up to design temperatures of 300 °C.
2.4.6 Unless equipped with load cables, umbilical
hose lines must be fitted with load relieving devices. 3.2.4 Non-metals
Non-metal pipes, valves and fittings are permitted
2.4.7 Umbilicals must be protected against abra-
only in special cases.
sion and damage. Where protective sheathing is used,
care is to be taken to ensure that minor leaks cannot
lead to an internal pressure build-up. Metal inserts are 3.3 Material testing
to be avoided.
3.3.1 For piping systems belonging to class I and II
2.4.8 Electrical cables in the umbilical must con- the components listed below are to be subjected to
form to the requirements stated in H. tests in accordance with the Rules for Classification
and Construction, II – Materials and Welding, Part 1 –
Metallic Materials, Chapter 1 – Principles and Test
3. Materials
Procedures, Section 2:
3.1 General requirements – Pipes, bends, fittings
3.1.1 Materials must be suitable for the proposed – Valve bodies and flanges of nominal bore
application and must conform to the Rules for Classi- ≥ DN 32:
fication and Construction, II – Materials and Welding, made of steel, cast steel or nodular cast iron
Part 1 – Metallic Materials and Part 2 – Non-metallic where PB [bar] ⋅ DN [mm] is > 2500 or the
Materials. nominal bore DN is > 250 mm;
3.1.2 Welds are to conform to the Rules for Clas- made of copper alloy where PB [bar] ⋅ DN [mm]
sification and Construction, II – Materials and Weld- is > 1500
ing, Part 3 – Welding. – Bolts and nuts of M 30 and above made from
steel with a tensile strength above 500 N/mm2,
3.1.3 Materials for breathing gas systems shall not
600 N/mm2 for nuts, and bolts made of alloy or
form any toxic or combustible products.
quenched and tempered steels of M 16 and
3.1.4 In oxygen systems, only those materials may above.
be used which are approved for use with oxygen and
3.3.2 For parts not subject to materials testing by
which are suitable for the proposed operating condi-
GL, proof of quality is to be supplied in some other
tions.
form e.g. Acceptance Test Certificate in accordance
with EN 10204-3.1 B.
3.2 Approved materials
3.3.3 Welded joints in pipes of classes I and II are
3.2.1 Steel to be inspected in accordance with the Rules for Clas-
3.2.1.1 Carbon and carbon-manganese steels may be sification and Construction, II – Materials and Weld-
used for pipes, valves and fittings. Pipes belonging to ing, Part 3 – Welding, Chapter 3 – Welding in the
classes I and II must be seamless drawn or produced Various Fields of Application, Section 4, G.
by a welding procedure approved by GL.
3.3.4 Valves and fittings in pipe classes I and II are
3.2.1.2 For oxygen lines with an operating pressure to be subjected to a hydraulic pressure test at 1,5 times
of more than 40 bar, use is to be made of high-alloy the nominal pressure on the manufacturer's premises
CrNi steels with an aggregate chromium and nickel in the presence of a GL Surveyor. The tightness of the
content of at least 22 %, or of CrSi steels with a chro- closure is to be tested with air at 0,5 bar and at 1,1
mium content of at least 22 %. times the nominal pressure.

3.2.2 Copper and copper alloys


4. Calculation of pipe wall thickness
Copper and copper alloy pipes in pipe classes I and II
must be seamless drawn pipes which meet the re- 4.1 Minimum wall thickness
quirements of the Rules for Classification and Con-
struction, II – Materials and Welding, Part 1 – Metal- 4.1.1 The minimum wall thicknesses stated in Ta-
lic Materials, Chapter 3 – Non-Ferrous Metals, Sec- ble 2.7 are to be adhered to unless the strength calcu-
tion 2 in respect of ductility, freedom from stress and lation demands greater wall thicknesses. Slightly
resistance to hydrogen embrittlement. They may be smaller wall thicknesses can be permitted for pipes
used for systems carrying oxygen. manufactured to a recognized standard.
I - Part 5 Section 2 D Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–15

4.1.2 Where it is proposed to use smaller wall R [mm] = radius of bend


thicknesses, elasticity calculations are required to
prove that the permissible stresses specified in 4.3 are 4.3 Permissible stress σzul
not exceeded when allowance is made for the internal
excess pressure, deformations of the ship's hull, ther- 4.3.1 Steel pipes
mal expansion and the effect of the dead weight of the
pipelines. The smallest of the following values is to be substi-
tuted for the permissible stress σzul in formula (1a):
4.2 Calculation of pipe wall thicknesses
For design temperatures of ≤ 350 °C
4.2.1 The following formula is applicable to the
calculation of the wall thicknesses of cylindrical pipes R m,20° = guaranteed minimum
where Rm,20°
and bends subjected to internal excess pressure: A tensile strength at room
temperature
s = so + c + b [mm] (1) R eH,t = guaranteed minimum
where ReH,t
yield point at design
da ⋅ pc B
so = [mm] (1a) temperature
20 ⋅σzul ⋅ v + pc
R p0,2, t = minimum value of
where Rp02,t
B 0,2 % proof stress at
s [mm] = minimum wall thickness
design temperature
so [mm] = calculated wall thickness
For pipelines for which
da [mm] = (nominal) outside diameter
of pipe – a detailed stress analysis recognized by GL is
available and
pc [bar] = design pressure
– whose material has been tested by GL may, on
σzul [N/mm2] = permissible stress application, approve the substitution of value of
b [mm] = allowance for bends 1,5 for the safety factor B (for A and B, see Ta-
ble 2.8).
v = weld efficiency factor
4.3.2 Pipes of metals without a clear yield point
c [mm] = corrosion allowance
Table 2.9 is applicable to materials without a clear
4.2.2 In the case of straight cylindrical pipes which yield point. For other materials, the permissible stress
are to be bent, an allowance b is to be made for the is to be agreed with GL subject to the requirement
bending of the pipes. The value of b shall be such that that
the stress due to the bending of the pipe does not ex-
ceed the permissible stress σzul. The allowance b can R m, t
σ zul ≤
be calculated as follows: 4
da where Rm,t is the minimum tensile strength at design
b = 0,4 ⋅ ⋅ so (2)
R temperature.

Table 2.7 Minimum pipe wall thickness s [mm]

Outside diameter of
pipe Steel Austenitic steels Copper Copper alloys
da [mm]

8 – 10 1,6 1,0 1,0 0,8


12 – 20 1,8 1,2 1,2 1,0
20 – 44,5 2,0 1,6 1,5 1,2
50 – 76,1 2,6 2,0 2,0 1,5
88,9 – 108 2,9 2,3 2,5 2,0
Chapter 1 Section 2 E Rules for Construction of Diving Systems I - Part 5
Page 2–16 GL 1998

Table 2.8 Factors A and B for determining the effective corrosion protection, may be reduced, though
permissible stress σzul not by more than 50 %.

I II, III 4.6.2 With GL's consent, the corrosion allowance


Pipe class
may be dispensed with in the case of pipes made of
corrosion-resistant materials (e.g. austenitic steels and
Material A B A B copper alloys).
Unalloyed and alloyed
2,7 1,6 2,7 1,8 4.7 Tolerance allowance t
carbon steel
The negative wall thickness tolerances allowed by
Stainless rolled and pipe manufacturer's supply specifications are to be
2,4 1,6 2,4 1,8
forged steel
added to the calculated wall thickness (so) as the
Steel with σs,20°1 stated tolerance allowance (t). This allowance can be
3,0 1,7 3,0 1,8 calculated as follows:
> 400 N/mm2
Nodular cast iron --- --- 5,0 3,0 a
t= ⋅ so [mm] (3)
100 − a
Cast steel 3,2 --- 4,0 ---
1 Minimum yield point or minimum 0,2 % proof stress at a [%] = negative wall thickness
20 °C. tolerance
so [mm] = wall thickness calculated in
4.4 Design temperature accordance with 4.2.1.
The design temperature is the maximum temperature
of the medium carried.
E. Compressors
4.5 Weld efficiency factor v

4.5.1 For seamless pipes v = 1,0. 1. General

4.5.2 For welded pipes, the value of v shall be that 1.1 These Rule apply to compressors, including
determined by GL's qualification test. valves, used in diving systems for compressing breath-
ing gases.
4.6 Corrosion allowance c Where the compressors are electrically driven, the
motors and other electrical equipment must comply
4.6.1 The value substituted for the corrosion allow- with the Rules for Classification and Construction,
ance c shall be that shown in Table 2.10. With GL's Part 1 – Seagoing Ships, Chapter 3 – Electrical Instal-
consent, the corrosion allowance for steel pipes with lations.

Table 2.9 Permissible stress σzul for copper alloys (material condition soft annealed) 1

Minimum
Pipe material tensile Permissible stress σzul [N/mm2]
stress

[N/mm2] 50 °C 75 °C 100 °C 125 °C 150 °C 175 °C 200 °C

Copper 215 41 41 40 40 34 27,5 18,5

Aluminium brass
325 78 78 78 78 78 51 24,5
CuZn20Al

Copper- CuNi10Fe
275 68 68 67 65,5 64 62 59
Nickel- CuNi10Fe
alloys CuNi30Fe 365 81 79 77 75 73 71 69
1 For other material conditions higher strength values may be permitted.
I - Part 5 Section 2 F Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–17

Table 2.10 Corrosion allowance c for carbon 4. Equipment


steel pipes
4.1 Compressors must be equipped with ade-
Nature of pipe system Corrosion allowance c quately designed suction filters, coolers and water
[mm] separators.

Compressed air 1 4.2 Each compressor stage must be equipped


Fresh water 0,8 with a pressure relief valve or rupture disc, neither of
which can be disabled. This safety device must be
Seawater 3,0 designed and set in such a way that the specified pres-
sure in the compressor stage concerned cannot be
Hydraulik oil 0,3 exceeded by more than 10 %. The setting must be
safeguarded against unauthorized alteration.
1.2 The documents to be submitted to GL for 4.3 Each compressor stage must be provided with
approval are listed in A.4. a suitable pressure gauge indicating clearly the final
pressure of that stage.
1.3 The necessary tests are stated in A.5.
4.4 Where a compressor stage comprises more
than one cylinder and each cylinder can be closed off
2. Design principles individually, a pressure relief valve and a pressure
gauge must be provided for each cylinder.
2.1 Compressors are to be designed for the re-
quired delivery rates, types of gas and delivery pres- 4.5 Cooling liquid systems with a shutoff device
sures. must be so designed that the specified coolant pressure
cannot be exceeded.
2.2 Compressors are to be so designed that no
lubricating oil can penetrate the gas circuit. 4.6 Dry-running reciprocating compressors must
be equipped at each stage with a device which acti-
vates a warning signal and shuts down the drive motor
2.3 Compressors are to be so installed that no
if the final compression temperature stated in the oper-
harmful gases can be sucked in.
ating instructions is exceeded.

2.4 Where a compressor is used for the divers' air 4.7 Diaphragm-type compressors must be
supply, a receiver must be interposed for the compen- equipped at each stage with a diaphragm rupture indi-
sation of pressure variations. cator which shuts down the compressor as soon as
damage occurs to the drive or compressor diaphragm.
2.5 Oxygen compressors are to be installed in
separate spaces with adequate ventilation. 5. Marking
A manufacturer's data plate containing the following
3. Materials details must be permanently fixed to each compressor:
– type designation
3.1 The materials of compressor parts must be
suitable for the application concerned. They are to be – manufacturer's name
specified with due attention to the operating condi-
tions and the nature of the gas. Rules for Classification – serial number
and Construction, II – Materials and Welding, Part 1 – year of manufacture
and 2 are to be complied with. Compliance with the
Oxygen Safety Regulations (UVV-Sauerstoff-VBG – capacity
62) is also required in the case of oxygen compres-
– delivery pressure
sors.
– revolutions per minute
3.2 Proof is to be furnished of the quality of the
materials used for all components under pressure.
F. Life Support Systems
3.3 A materials test is to be performed on the
crankshafts of reciprocating compressors with a cal-
culated crank pin diameter of more than 50 mm. 1. General

Finished shafts are to undergo magnetic particle in- 1.1 These Rules apply to all those plant compo-
spection. nents and parts which are needed to ensure life support
Chapter 1 Section 2 F Rules for Construction of Diving Systems I - Part 5
Page 2–18 GL 1998

and a safe environment for the occupants of a diving bell can be reduced to 1 bar at a rate of at least
system. 1 bar/min.

1.2 The documents to be submitted to GL for 2.2.1.3 Sets of breathing apparatus which, activated
approval are listed in A.4. by respiration, supply breathing gas to persons ex-
posed to excess pressures and also remove exhaust gas
1.3 The necessary tests and markings are stated independently of the chamber atmosphere are to be
in A.5. and A.6. designed for a gas flow equal to 3 times the required
breathing rate per minute (AMV).

2. Gas supply The required breathing rate per minute depends on the
proposed activity and the environmental conditions.
2.1 Gas storage facilities
When designing the supply and exhaust facilities for
breathing masks, the number of persons simultane-
2.1.1 Each diving system is to be provided with a
permanently installed gas storage facility or with a ously connected to the system is to be allowed for as
follows:
suitable place for the storage of portable gas contain-
ers.
Number of persons Quantity of
2.1.2 The capacity of the gas store shall be such breathing gas
that, for all the planned diving operations, a sufficient [operating litres/min]
number and quantity of gas mixtures are available to
supply all the compression chambers, diving bells and 1 1 x AMV x 3
divers with an adequate quantity of the correct gases at 2 2 x AMV x 1,8
all operating depths and under normal and emergency 3 3 x AMV x 1,6
conditions (for determining the minimum quantities of 4 4 x AMV x 1,4
gas required, see European Diving Technology Com- 5 5 x AMV x 1,3
mittee: Guidance Notes for Safe Diving, Appendix 2 6 6 x AMV x 1.2
to Chapter 5, p. 70, Oct. 1984). 7 7 x AMV x 1,1
8 8 x AMV x 1,1
2.1.3 The gas supply for the provision of emer- z>8 z x AMV x 1,0
gency breathing gas is to be stored separately in bot-
tles which must not be opened for normal operation.
2.2.1.4 The gas circulating systems are to be so de-
2.1.4 The diving bell is to be provided with its own signed that the chamber conditions stated in B.3. are
bottles so that the occupants of the chamber can in an maintained.
emergency be supplied with a sufficient quantity of
breathing gas mixture for at least 24 hours at the 2.2.1.5 Each compression chamber compartment and
maximum operating depth. An oxygen bottle for sup- each diving bell is to be equipped with at least the
plementing the oxygen supply is also to be carried on following gas systems:
the diving bell.
– 2 independent gas supply systems for compres-
sion which may deliver into a single inlet pipe
2.1.5 Oxygen bottles are to be placed in well ven-
immediately at the chamber
tilated positions and may not be stored close to com-
bustible materials. – 1 chamber exhaust gas system
2.1.6 Spaces in which oxygen is stored must be – 1 built in breathing systems (BIBS)
separated from the adjoining spaces by bulkheads and
decks of Type "A"-60 and must be arranged to facili- – 1 mask exhaust gas system
tate speedy exit in case of danger.
– 1 gas circulating system for maintaining the
breathable chamber atmosphere.
2.2 Gas distribution
Where pure oxygen or gas containing more than 25 %
2.2.1 General O2 by volume is supplied to the chamber, a separate
piping system is to be provided for this purpose.
2.2.1.1 The gas supply is to be designed so that a
pressure increase up to 2 bar in the living compart- 2.2.1.6 Valves in gas systems are to be so arranged
ment of the compression chamber can be effected at a that a valve leakage cannot lead to an unintended
rate of at least 2 bar/min followed by a rate of mixture of gases and oxygen or oxygen-like gas can-
1 bar/min. not penetrate into lines intended for other gases. Inter-
sections between oxygen and non-oxygen systems are
2.2.1.2 The gas venting system is to be designed so to be isolated by twin shutoffs with venting valves in
that the pressure in a compression chamber or diving between.
I - Part 5 Section 2 F Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–19

2.2.1.7 Filters and automatic pressure reducers are to can be regulated. The rate of circulation shall be such
be so arranged that they can be dismounted without as to satisfy the conditions stated in B.3.
interrupting vital gas supplies.
2.3.2 Each diving system is to be equipped with at
2.2.2 Compression chambers least 2 chamber gas treatment units so arranged that
they can be switched to adjacent chambers.
2.2.2.1 At least one breathing mask is to be provided
for each occupant inside each separately pressurized 2.3.3 Diving bells are to be equipped with a cham-
chamber compartment. ber gas treatment unit and also with an autonomous
reserve CO2-absorption unit for emergency use.
2.2.2.2 The masks are to be connected to the mask
gas supply and exhaust gas system either permanently 2.3.4 Diving bells are to be equipped with a heat-
or by plug and socket connectors. ing system provided with redundant supplies and so
2.2.2.3 The exhaust gas (exhalation line) side of the designed that the divers in the diving bell and in the
masks is to be protected against any inadmissible pres- water are maintained in a thermal balance. For diving
sure drop or inadmissible pressure difference. operations at depths greater than 100 m breathing gas
preheaters are also to be provided for the divers in the
2.2.2.4 The supply of gas to the chamber is to be water.
arranged so as to ensure a homogeneous gas distribu-
tion inside the chamber is achieved as quickly as pos- 2.3.5 Measures are to be taken to enable the divers
sible. within the diving bell to be maintained in a safe ther-
mal balance for at lest 24 hours in an emergency.
2.2.3 Diving bells
2.4 Breathing gas treatment and mixing
2.2.3.1 Besides their normal breathing gas supply
diving bells and divers in the water must also carry an The use of closed breathing gas circuits, gas mixing
independent reserve gas supply. systems for direct breathing gas supply and helium
reclaim systems requires GL's approval.
2.2.3.2 The supply of breathing gas to the diving bell
is to be designed in such a way that, should the diving 3. Control and instrumentation
bell umbilical fail, the reserve chamber supply can be
switched manually or automatically to the divers with- 3.1 Central control position
out flowing back into the chamber umbilical.
3.1.1 Diving systems are to be so arranged and
2.2.3.3 The divers' umbilical system is to be so de- equipped that centralized control of the safe operation
signed that each diver has his own independent sup- of the system can be maintained under all weather
ply. conditions.
2.2.3.4 In the diving bell at least one breathing mask
3.1.2 For monitoring and controlling the diving
is to be provided for each diver, and this must be con- system, a central control position is to be provided at
nected to both the normal and the reserve gas supply.
which all important data relating to the chambers and
Divers' masks and helmets with a gas supply may be
the operating states of the ancillary equipment are
recognized as breathing masks.
displayed and where the chamber pressures can be
2.2.3.5 Automatic pressure reducers are to be pro- controlled and the gases distributed to the various
vided for the breathing masks. chambers.

2.2.3.6 The emergency oxygen supply is to be fitted 3.1.3 At the Central Control Position are to be
with a dosage system to enable the oxygen in the div- grouped all the controls needed for the operation of
ing bell to be maintained at the correct partial pres- the diving system, including the TV monitoring and
sure. communications equipment.

2.2.3.7 The diving bell is to be equipped with two 3.1.4 Only those items of equipment may be in-
independent exhaust gas lines, which must be ar- stalled at the Central Control Position which are es-
ranged to avoid flooding of the electrical equipment. sential to the operation of the diving system and do
An exhaust gas valve is to be mounted close to the not impair its surveillance and control.
divers' exit.
3.1.5 The Central Control Position is to be sepa-
rated from the other spaces in the ship or floating
2.3 Conditioning of chamber atmosphere structure by bulkheads and decks of type "A"-60.
2.3.1 Each compression chamber living compart- 3.1.6 The Central Control Position is to be
ment is to be equipped with an oxygen dosing device equipped with a separate ventilation system, the intake
and a chamber gas circulating unit in which the CO2 duct of which must be routed from an area not subject
can be absorbed and the air temperature and humidity to an explosion hazard.
Chapter 1 Section 2 F Rules for Construction of Diving Systems I - Part 5
Page 2–20 GL 1998

3.2 Instrumentation Diving bells are to be equipped with instruments indi-


cating the internal and external pressure and the pres-
3.2.1 Indicating instruments sure of the independent gas supply. In addition, the
diving bell is to be equipped with an autonomous unit
3.2.1.1 Instruments for the surveillance, control and for monitoring the oxygen and CO2 levels.
operation of the diving system are to be grouped and
arranged in the Central Control Position in accordance 3.2.1.7 Pressure gauges connected directly to the
with the principles of safety technology and ergonom- compression chamber system are to be fitted with a
ics. shutoff valve.
3.2.1.2 The Central Control Position is to be 3.2.2 Analyzing equipment
equipped with suitable instruments for the surveillance
of each manned compression chamber compartment 3.2.2.1 Each diving system is to be equipped with at
and each diving bell (cf. Table 2.11). least one oxygen and one CO2 analyzing system.
3.2.1.3 The instrument indicating the pressures in 3.2.2.2 Throughout the entire operating period, the
compression chambers and diving bells must be accu- oxygen analyzing system must give a reading accurate
rate to ± 0,3 % of the whole scale with a maximum to ± 0,015 bar partial oxygen pressure.
deviation of 30 cm water column. All other pressure
readings shall be accurate to ± 1 % of the whole scale. 3.2.2.3 Throughout the entire operating period the
CO2 analyzing system must give a reading accurate to
3.2.1.4 The Central Control Position is also to be ± 0,001 bar partial CO2 pressure.
equipped with indicating instruments for the following
parameters: 3.2.2.4 In addition, autonomous instruments for
monitoring the oxygen and CO2 levels are to be pro-
– pressure of connected breathing gas receiv- vided in diving bells and the living compartments of
ers/bottles compression chambers.
– pressure downstream of pressure reducers 3.2.2.5 Where gases other than air, helium-oxygen
– oxygen content in supply lines to: mixtures or He/N2/CO2 mixtures are used for diving
operations, the instrumentation required shall be
umbilical agreed with GL in each case.
chamber compartments 3.2.2.6 A system is to be provided for analyzing the
breathing masks in chambers chamber atmosphere for impurities such as CO, NO,
NOx and hydrocarbons. Test tubes may be recognized
3.2.1.5 Inadmissible deviations from the reference for this purpose.
values of the vital parameters shall actuate a visual
and audible alarm at the Central Control Position. 3.3 Control equipment
Automatically actuated switching operations in the gas
supply system and similar functions shall also trip 3.3.1 The Central Control Position is to be fitted
such alarm. with controls fore at least the following functions:
3.2.1.6 The compartments of compression chambers – pressurization and pressure control for each
are to be fitted with pressure and temperature gauges compression chamber compartment capable of
which can be read from inside. independent operation and for each diving bell

Table 2.11 Operating parameters to be monitored

Compression chamber
Parameter Diving bell
compartments
Pressure or depth 1 X X2
Temperature 1 X
Humidity X
O2 partial-pressure 1 X X
CO2-partial pressure X X
1 These parameters are to be displayed continuously.
2 The pressure or depth inside and outside the diving bell are to be indicated.
I - Part 5 Section 2 G Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–21

– decompression of each compression chamber 2.1.6 Automation equipment must be compatible


compartment capable of independent operation with the operating conditions of the diving system.
and of each diving bell
2.1.7 Any inadmissible variations in the operating
– pressure equalization between chamber com- parameters must actuate an automatic /visual and
partments audible) alarm at the Central Control Position. The
– supply of oxygen to the chamber compartments same shall also occur in the event of automatic switch-
ing operations in the gas and power supply systems or
– control of gas supply to breathing masks faults in the control and surveillance system.
– control of temperature and humidity in com-
pression chambers 2.1.8 In addition to electronic control and surveil-
lance equipment, independent safety devices must be
3.3.2 To the gas distribution control position is to fitted which prevent a fault in one system from pro-
be fitted a mimic diagram showing the functions of the voking an improper response in another system.
various valves and the different gas lines in colour.
2.1.9 Automatic surveillance and control equip-
ment must be capable of being switched to manual
operation at all times.
G. Automation, Communication and Locating 2.1.10 The response values of automation equipment
Equipment must be so coordinated with each other that, when a
threshold is reached, a warning is initiated, followed,
1. General after a certain warning period or if the process variable
continues to change at a preset speed, by the actuation
1.1 The following Rules supplement the Rules of safety devices.
for Classification and Construction, Part 1 – Seagoing
Ships, Chapter 3 – Electrical Installations and 2.1.11 The integral operation of automation systems
Chapter 4 – Automation and are to be applied to the must be designed to take account of the lags and time
construction and use of surveillance, control, commu- constants of the units and elements making up the
nications, TV monitoring and locating equipment in system (e.g. by allowing for the length and cross-sec-
diving systems holding GL class. tion of piping systems and the response times of gas
analyzers).
1.2 The documents to be submitted to GL are
listed in A.4. 2.1.12 It must be possible to check the function of
important indication lamps during operation.
1.3 The necessary tests and markings are stated
in A.5. and A.6. Only components and units approved 2.2 Construction
by GL may be used.
2.2.1 Electronic automation systems should com-
prise easily replaceable assemblies, of the plug-in type
2. Automation equipment wherever possible. Standardization of units is to be
encouraged and the number of assembly types is to be
2.1 Design principles kept small in order to minimize the spare parts inven-
tory.
2.1.1 All equipment for the automatic surveillance
and control of diving system operating parameters is 2.2.2 Plug-in cards must be clearly marked or
to be designed and constructed so that it works prop- coded to prevent inadvertent confusion.
erly under the design and environmental conditions
specified for the diving system. 2.2.3 Measures must be taken to prevent condensa-
tion inside electronic units, even when switched off.
2.1.2 All items of surveillance and control equip- Shutdown heating is recommended.
ment are to be clearly inscribed and identified.
2.2.4 Wherever possible, automation equipment
2.1.3 Indicating instruments and synoptic displays should be capable of operation without forced ventila-
are to be designed and inscribed in such a way that tion. Any cooling system used is to be monitored.
they can be read quickly and clearly.
2.2.5 Components must be effectively secured.
2.1.4 Any fault or failure which may occur in the Any mechanical loading of wires and soldered con-
automation system shall not provoke a critical operat- nections due to vibration or jolting is to be reduced to
ing condition in the compression chamber or diving a minimum.
bell.
2.2.6 The construction of systems and units is to be
2.1.5 As far as possible, automation equipment is simple and straightforward. Good accessibility is to be
to be safeguarded against faulty operation. ensured to facilitate measurements and repairs.
Chapter 1 Section 2 G Rules for Construction of Diving Systems I - Part 5
Page 2–22 GL 1998

2.3 Circuitry 2.4 Power supply

2.3.1 Signalling equipment and control systems 2.4.1 Mains units for automation equipment must
with a safety function must be designed on the fail- contain at least one short-circuit protection and one
safe principle, i.e. faults due to short-circuit, earthing overload protection device.
or circuit breaks shall not be capable of provoking
situations hazardous to personnel and/or the system. In 2.4.2 The reference conductor system is to be de-
this respect, it is to be assumed that faults occur sin- signed to preclude circuit breaks as far as possible.
gly. This may, for example, be achieved by duplicating
exposed reference conductor joints and connections.
The failure of one unit, e.g. due to short-circuit, shall
not result in damage to other units. 2.4.3 Automation equipment must be capable of
reliable operation under the conditions of voltage and
2.3.2 In stored-program control systems, the elec- frequency variation stated in the Rules for Classifi-
trical characteristics of the signal transmitters shall cation and Construction, Part 1 – Seagoing Ships,
conform to the safety requirements for instruction and Chapter 3 – Electrical Installations, Section 3.
control devices. This means principally
2.5 Tests
– activation at H level, i.e. by energization across
NO contacts Automation equipment of novel design must have
been type-tested by GL.
– deactivation at L level, i.e. by deenergization
The nature and scope of the type-test will be deter-
across NC contacts
mined by GL in each case.
The requirements of 2.3.1 are unaffected.
3. Communication equipment
2.3.3 Instruction and control units for safety func-
tions, e.g. emergency stop buttons, shall be independ- 3.1 Voice communication systems
ent of stored-program control systems and shall act
directly on the output unit, e.g. the STOP solenoid. 3.1.1 Diving systems are to be equipped with a
suitable communication system providing direct voice
2.3.4 Stored-program control systems should be communication between the control stand and
reactionless and, in case of fault, should cause no
– divers in water
malfunctions in program-independent safety interlocks
or stepped safety circuits for fixed subroutines. – diving bell

2.3.5 Freely accessible potentiometers and other – each compartment of the chambers
units for equipment trimming or operating point set- – diving system handling position
tings must be capable of being locked in the operation
position. – dynamic positioning room
– bridge, ship's command centre or drilling floor
2.3.6 Interfaces with mechanical switchgear must
be so designed that the operation of the system is not 3.1.2 In diving systems using helium, gas mixtures,
adversely affected by contact chatter. each compression chamber compartment and the div-
ing bell are to be connected to a speech unscrambler.
2.3.7 Conductive tracks forming part of circuits The unscrambling devices should be designed to
which extend outside the enclosure housing the circuit achieve maximum noise suppression and the auto-
boards must have qualified short-circuit protection, i.e. matic compensation of sound level fluctuations.
in case of an external short-circuit only the safety
devices provided may respond without destroying the 3.1.3 It is recommended that the Central Control
conductive tracks. Position should be equipped to record all voice com-
munications with the divers.
2.3.8 The equipment shall not be damaged by brief
overvoltages in the ship's power supply, due for exam- 3.1.4 Voice communications between the compres-
ple to switching operations. The design is to allow for sion chamber compartments and the Control Position
overvoltages equal to approximately 2,5 times the and between the diving bell and the Control Position
rated voltage and lasting 1 ms. must be provided by a communication system with
loudspeaker which is permanently switched to "Re-
Where systems are supplied by static converters, it ceive" on the control console. Switches for reversing
may be necessary to make allowance for periodic the direction of communication must be of the self-
voltage pulses lasting about 0,5 ms. The pulse ampli- resetting type. In addition, each compression chamber
tude depends on the converter type and is to be inves- compartment is to be provided with at least one head-
tigated in each case. set.
I - Part 5 Section 2 G Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–23

3.1.5 A telephone link independent of the mains ble, be interchangeable with those of the diver and
power supply must also be provided in addition to the surface interrogator/receiver.
communication system specified in 3.1.4.
4.1.1.2 The transponder should be designed to oper-
3.1.6 Electrically powered voice communication ate with the following characteristics:
systems shall be provided with a reliable power sup-
ply. This normally means that the equipment shall be common emergency reply 37,5 kHz
supplied from a storage battery with a parallel con- frequency
nected mains unit and battery charger supplied with
energy in accordance with H. individual interrogation
frequency
3.1.7 In wet rooms microphone and receiver sys- – channel A 38,5 ± 0,05 kHz
tems must be constructed to prevent the penetration of – channel B 39,5 ± 0,05 kHz
water. Where considerations of design render this
impossible, the penetration of water shall not perma- receiver sensitivity + 15 dB referred to
nently impair the serviceability of the equipment. 1µ bar
3.1.8 Microphone and receivers in diver's masks minimum interrogation 4 ms
and helmets are to be functionally separated from each pulse width
other.
turnaround delay 125,7 ± 0,2 ms
3.2 Television surveillance equipment
reply frequency 37,5 ± 0,05 kHz
3.2.1 Diving bells are to be equipped with an inde-
pendent underwater communication systems for use in interrogation rates:
emergencies. – more than 20 % of once per second
battery life remaining
3.2.2 Suitable alternative communication equip- – less than 20 % of once per 2 seconds
ment (e.g. a 3-button signalling system) is to be pro- battery life remaining
vided in all compression chamber compartments and
in the diving bell. minimum transponder 85 dB referred to
output power 1 µ bar at 1 m
3.3 Other signalling systems
minimum transducer polar - 6 dB at ± 135° solid
3.3.1 Diving bells are to be equipped with an inde- diagram angle, centred on the
pendent underwater communications system for use in transponder vertical axis
emergencies. and transmitting towards
the surface
3.3.2 Suitable alternative communications equip-
ment (e.g. a 3-button signalling system) is to be pro- minimum listening life in 10 weeks
vided in all compression chamber compartments and water
in the diving bell.
minimum battery life re- 5 days
plying at 85 dB
4. Emergency location and communication
4.1.2 Diver-held interrogator/receiver
4.1 Emergency locating equipment
Subject to the IMO Code of Safety for Diving Sys- 4.1.2.1 The interrogator/receiver should be provided
tems, Resolution A.831(19) of 23 November 1995, with a pressure housing capable of operating to a
each diving bell is to be equipped with an emergency depth of at least 200 m with pistol grip and compass.
locating device with a frequency of 37,5 kHz designed The front end should contain the directional hydro-
to enable contact to assist personnel on the surface in phone array and the rear end the 3-digit LED display
establishing and maintaining contact with the sub- readout calibrated in metres. Controls should be pro-
merged diving bell, if the umbilical to the surface is vided for "on/off receiver gain" and "channel selec-
severed. The device should include the following tion". The battery pack should be of the readily avail-
components: able "alkaline" type and, if possible, be inter-
changeable with that of the interrogator and trans-
4.1.1 Transponder ponder.
4.1.1.1 The transponder should be provided with a 4.1.2.2 The interrogator/receiver should be designed
pressure housing capable of operating to a depth of at to operate with the following characteristics:
least 200 m containing batteries and equipped with
salt water activation contacts. The batteries should be common emergency 37,5 kHz
of the readily available "alkaline" type and, if possi- reply frequency
Chapter 1 Section 2 H Rules for Construction of Diving Systems I - Part 5
Page 2–24 GL 1998

individual interrogation 1.3 The necessary tests and markings are stated
frequencies: in A.5. and A.6.
– channel A 38,5 kHz
– channel B 39,5 kHz 2. Design principles
minimum transmitter out- 85 dB referred to 2.1 General principles
put power 1 µ bar at 1 m
transmit impulse 4 ms 2.1.1 All electrical systems and equipment are to
be constructed and installed in such a way that they
directivity ± 15° are serviceable and perform satisfactorily under the
design conditions specified for the diving system.
capability to zero range on transponder
maximum detectable 2.1.2 Provision must be made for maintaining the
more than 500 m
range diving system in a normal operating condition without
recourse to the emergency power supply.
4.2 Emergency communication
2.1.3 Even under emergency conditions, the opera-
In addition to the communication systems referred to tion of equipment important to the divers' safety must
above, a standard bell emergency communication be guaranteed.
tapping code should be adopted, as given below, for
use between persons in the bell and rescue divers. 2.1.4 Measures must be taken to exclude any elec-
A copy of this tapping code should be displayed inside trical hazards either to divers or to personnel operating
and outside the bell and also in the dive control room. diving systems.

Tapping code Situation 2.2 Materials and insulation


3.3.3 Communication opening procedure 2.2.1 The materials used in the construction of
1 Yes or affirmative or agreed electrical machines, cables and apparatus must be
resistant to moist and salty sea air, seawater and oil
3 No or negative or disagreed vapours. They may not be hygroscopic and must be
flame-retardant and self-extinguishing. In addition,
2.2 Repeat please materials installed inside compression chambers and
2 Stop diving bells must be approved for operation in hyper-
baric atmospheres and shall not liberate toxic gases or
5 Have you got a seal? fumes under these conditions.
6 Stand by to be pulled up
2.2.2 Materials with high tracking resistance are to
1.2.1.2 Get ready for through water trans- be used for the supports of live parts.
fer (open your hatch)
Leakage paths and air gaps are to be calculated in
2.3.2.3 You will not release your ballasts! conformity with IEC rules.
4.4 Do release your ballast in 30 min-
utes from now! 2.2.3 Materials and insulations for electrical
equipment used in water are to be agreed with GL in
1.2.3 Do increase your pressure each instance.
3.3.3 Communication closing procedure
2.3 Supply systems

2.3.1 Approved supply systems are:


H. Electrical Equipment
– direct current and single-phase alternating cur-
rent:
1. General 2 conductors insulated from ship's hull

1.1 The following Rules supplement the Rules – three-phase alternating current:
for Classification and Construction, Part 1 – Seagoing 3 conductors insulated from ship's hull
Ships, Chapter 3 – Electrical Installations and are to
be applied to the construction of diving systems hold- 2.3.2 The use of the diving system, the ship's hull
ing GL class. or parts thereof for the return of electrical current is
not permitted.
1.2 The documents to be submitted to GL are
listed in A.4. 2.3.3 Systems earthing is not permitted.
I - Part 5 Section 2 H Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–25

Exceptions may be allowed in the case of subsystems 3.1.4 The following may be used as an independent
using isolating transformers and high-resistance sys- emergency power source:
tems earthing.
– an electrical generator with its own drive
2.4 Maximum permissible operating voltages – an emergency battery of sufficient capacity

2.4.1 The following maximum voltages are per- – the emergency power supply of the support
mitted for electrical equipment inside compression vessel provided that this is designed to meet the
chambers (only in dry chamber compartments): additional emergency power requirements of the
diving system
– for permanently installed electrical drives and
heating systems: 250 V rms 3.1.5 The emergency power source for the diving
system must be installed in a space separated from the
– for lighting networks and socket circuits, com- main power source and the main switchboard so that it
munications and display equipment and all con- remains operational in case of a fire or other major
sumers supplied via cables not permanently in- damage affecting the main power supply.
stalled: 30 V rms
3.2 Main power supply
2.4.2 30 V is the maximum permissible voltage for
all electrical equipment in diving bells and wet cham- 3.2.1 A power balance must be prepared to prove
bers. that units for the generation, storage and conversion of
electric power are adequately rated. This balance shall
2.4.3 Voltages higher than those stated in 2.4.1 and take account of the full power consumption of those
2.4.2 may be approved where additional safety meas- consumers which are permanently required in service.
ures are taken which afford an equivalent level of
safety. 3.2.2 The power consumption of consumers which
are connected for limited periods may be determined
2.4.4 The permissible voltages for electrical by applying a simultaneity factor.
equipment used in water are to be agreed with GL in
each case. 3.2.3 Evidence is required of the availability of
reserve capacity to meet the power requirements dur-
2.5 Protective measures ing brief peak loads, e.g. when motors are started
automatically.
2.5.1 All electrical equipment is to be protected in
accordance with the Rules for Classification and Con- 3.2.4 The main power supply must be designed to
struction, Part 1 – Seagoing Ships, Chapter 3 – Elec- ensure that an adequate supply of energy to all con-
trical Installations, Section 1. sumers important to the operation of the diving system
can be maintained should a generator or its prime
2.5.2 To protect divers against excessive contact mover fail.
voltages and electric shock, additional safety measures
are to be taken to avoid or restrict dangerous fault 3.2.5 The generating equipment of the main power
currents. These measures are to be agreed with GL in supply is to be so designed that the voltage and fre-
every distance. quency variations allowed by the provisions of the
Rules for Classification and Construction, Part 1 –
Seagoing Ships, Chapter 3 – Electrical Installations,
3. Power supply Section 3.
3.1 Principles 3.3 Emergency power supply
3.1.1 All electrical equipment important to the 3.3.1 The emergency power supply must be able to
safety of divers and diving operations is to be con- meet the emergency power requirements of the diving
nected to a mutually independent main and emergency system for a period of at least 48 hours.
power supply.
3.3.2 The emergency power supply must be able to
3.1.2 Where provision is made for automatic meet simultaneously the requirements of at least the
switching from the main to the emergency power following items of equipment:
supply, each such switching operation must actuate in
the diving system control room a (visual and audible) – emergency lighting systems in compression
signal requiring acknowledgement. An indicator must chambers and diving bells
show which supply is connected. – emergency communication systems
3.1.3 The main power supply to the diving system – emergency life support systems
can be taken direct from the main switchboard of the – emergency diving system handling equipment
support vessel or from the main power source of the
diving system. – emergency surveillance and alarm systems
Chapter 1 Section 2 H Rules for Construction of Diving Systems I - Part 5
Page 2–26 GL 1998

3.3.3 In the design of the emergency power supply gear. Circuits at protective low voltage may not be
system, appropriate reserve capacity is to be provided routed with circuits at higher voltage in a joint con-
to meet peak loads (e.g. caused by the starting of elec- ductor bundle or cable duct.
tric motors).
Terminals for different voltage levels are to be ar-
In determining the necessary battery capacity, allow- ranged separately and are to be clearly identified.
ance is also to be made for the cut-off voltage and
voltage drop of battery. 4.1.6 Switchgear units for a connected load of
100 kW and over are to be tested in the manufacturer's
3.3.4 Diving bells are to be equipped with their
works in the presence of a GL Surveyor. The test shall
own independent emergency power supply capable of
be performed in accordance with the Rules for Classi-
meeting the power requirements of the autonomous
fication and Construction, Part 1 – Seagoing Ships,
life support system of the diving bell for at least 24
Chapter 3 – Electrical Installations, Section 5, H.
hours.

3.4 Storage batteries 4.1.7 Switchgear units for a connected load of less
than 100 kW are to undergo an internal works test of
3.4.1 When installing storage batteries, the relevant the same scope. These tests are to be certified by a
provisions of the Rules for Classification and Con- Works Test Certificate issued by the manufacturer.
struction, Part 1 – Seagoing Ships, Chapter 3 – Elec- Test certificates are to be submitted to GL not later
trical Installations, Section 2 are to be complied with. than the trial of the diving system. For voltage ratings
below 60 V, the voltage test is to be performed at a
3.4.2 In the case of battery installations equipped power-frequency withstand voltage of 500 V plus
with a catalytic converter which ensures that at least twice the rate voltage.
95 % of the hydrogen produced is recombined, sepa-
rate ventilation of the battery room can be dispensed 4.2 Switching and protective devices
with. The same applies when gastight battery casings
are used. 4.2.1 Each circuit is to be protected against over-
load and short-circuit.
4. Power distribution
4.2.2 All consumers circuits are to be fitted with
4.1 Distribution and switchgear switches. The switching action must be on all poles.
4.1.1 Electrical distribution systems are to be so 4.2.3 Electrical switches for circuits with a current
designed that a fault or failure in one circuit cannot rating above 0,5 A are permitted inside compression
impair the operation of other circuits or the power chambers and diving bells only subject to the use of
supply. additional safety features (such as pressurized enclo-
4.1.2 The following consumers at least are to be sure in protective gas).
supplied via individual circuits equipped with all nec-
essary safety devices and switchgear from a distribu- 4.2.4 Electrical fuses may not be located inside
tion panel supplied direct from the main switchboard compression chambers and diving bells. Wherever
of the support vessel: possible, fuses for the independent emergency power
supply to the diving bell are to be located outside the
– the diving system handling equipment on the chamber. If installed inside the diving bell, special
support vessel protective measures are necessary. The fuses shall in
any case be protected against intervention by the occu-
– the compression chamber and diving bell light-
pants of the chamber.
ing system
– the electrical consumers of the life support sys- 4.2.5 Electric motors installed inside chambers are
tems to be fitted with an overcurrent alarm. The alarm must
be tripped in good time before the motor protection
– the communication systems
responds. This does not apply to those electric motors
4.1.3 In normal operation the emergency power which cannot be endangered by overcurrent. For mo-
distribution system may be supplied via a transfer line tors in the diving bell, the alarm may take place in the
from the main power distribution system. diving bell.

4.1.4 Distribution boards with their own individual 4.2.6 Devices are to be fitted which, in the event of
feed circuits may not be mounted in a shared casing, danger, enable the power supply to all the electrical
i.e. each of these switchgear units must have its own consumers in the compression chamber to be quickly
enclosure. disconnected. The switches needed for this purpose
are to be mounted at the Central Control Position.
4.1.5 Effective measures are to be taken to prevent Means must be provided to enable the disconnection
the occurrence of vagabond voltages inside switch- separately for each chamber.
I - Part 5 Section 2 H Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–27

4.2.7 All unearthed distribution systems, including bers and diving bells are considered to be effectively
the groups of consumers and individual consumers earthed only if the contact surfaces are permanently
supplied via isolating transformers, safety transform- free from rust, scale and paint and the casings are
ers, rectifiers and inverters, are to be equipped with a fastened with at least two corrosion-resistant screws
continuously operating insulation monitoring system. secured to prevent accidental loosening.
For systems using protective low voltage, an alarm
If these conditions are not met, earthing must be ef-
must be actuated at the Central Control Position if the
fected by separate earthing conductors.
insulation value drops below a preset limit. For higher
voltage systems, the insulation monitor must trip an 4.4.4 The casings of electrical equipment in water
alarm at the Central Control Position when a prede-
are always to be earthed by an earthing conductor
termined fault current is reached, and the system con- included in the supply cable. Where this is not possi-
cerned must be automatically disconnected. ble, casings mounted on the outside of the diving bell
For the electrical equipment of the diving bell, the may also be provided with a separate external earth. In
alarm actuated by the insulation monitoring system this case, however, the entire earth connection (con-
may take place in the diving bell. necting screws and earthing conductor) is to be corro-
sion-resistant.
Note:
4.4.5 Earth connections must be accessible for
The current/time characteristics of insulation moni- maintenance and inspection. Wherever possible, they
toring systems directly concerned with personnel are to be marked. Earthing conductors in multi-core
safety must meet the requirements of diver protection. cables are to be marked green and yellow, at least at
In assessing the time characteristics, account is to be the terminals.
taken of the response time of the insulation monitoring
system and of the tripping time of the switching de- 4.4.6 Earthing conductors are to be provided with
vices which it actuates. corrosion protection compatible with their place of
installation.
4.3 Enclosures for electrical equipment
4.4.7 Copper earthing conductors are subject to the
4.3.1 All items of electrical equipment belonging following minimum cross-sections:
to a diving system are to be encased or sealed in a
suitable enclosure compatible with their nature, loca- – external connections on ship and water: 10 mm2
tion and protection class. – external connections inside chambers and living
compartments: 6 mm2
4.3.2 The enclosures of electrical equipment in-
stalled inside compression chambers and diving bells – separate earthing conductors inside switchgear
or operated in water must have been approved by GL. and casings: 4 mm2

4.3.3 Pressure-tight enclosures inside compression – Earthing conductors in multi-core cables up to a


chambers and diving bells are to be tested at 1,5 times conductor cross-section of 16 mm2 must corre-
the maximum working pressure of the chamber. En- spond to the cross-section of the main conductor
closures mounted on the outside of diving bells are to subject to a minimum of 1 mm2.
be tested at 1,3 times the design pressure of the diving – earthing conductors in multi-core cables with a
bell. conductor cross-section of more than 16 mm2
equal to at least half that of the main conductor
4.4 Earthing
If other materials are used, the minimum cross-section
4.4.1 Diving bells are to be equipped with an is to be determined by the ratio of the electrical con-
earthing and potential equalizing system. Connections ductivity of these materials to the electrical conductiv-
for external earthing are to be provided in all cham- ity of copper.
bers.
4.4.8 Cable sheaths and armouring may not be used
4.4.2 The connections between the earthing con- as earthing conductors.
ductor and the chamber and to the ship's earth are to
be made with corrosion-resistant screw unions effec- 4.5 Cables and lines
tively safeguarded against accidental loosening. The
dimensions of the screw unions are to be compatible 4.5.1 Cables and lines for diving systems must be
with the requisite cross-sections of the earth conductor suitable for the proposed application. Their use is
to be connected and may not be used for other pur- subject to approval by GL.
poses.
4.5.2 The selection, dimensions and installation of
4.4.3 All metal parts of electrical installations – cables and lines shall comply with the provisions of
with the exception of live components – are to be the Rules for Classification and Construction, Part 1 –
earthed. The casings of electrical equipment mounted Seagoing Ships, Chapter 3 – Electrical Installations,
directly against the inside wall of compression cham- Section 12 and 20, E.
Chapter 1 Section 2 H Rules for Construction of Diving Systems I - Part 5
Page 2–28 GL 1998

4.5.3 In addition, the materials of cables and lines In all pressure and tightness tests on compres-
inside compression chambers and diving bells and in sion chamber wall penetrations, the pressure
water must meet the requirements stated in 2.2. must in each case be applied from the pressure
side of the wall penetration.
4.5.4 Underwater cables and lines must be de- – high-voltage test at an AC voltage of 1000 V
signed for an external hydrostatic excess pressure plus twice the rated voltage. This test is per-
equal to 1,3 times the maximum permissible operating formed at the rated frequency and is to be car-
depth. The pressure resistance is to be verified by ried out for 1 minute in each case between all
pressure-testing each made-up length after the con- the conductors mutually and between the con-
nectors have been fitted. ductors and the casing. The test is performed in
the disconnected state. The connection side of
4.5.5 Electric umbilicals are to be tested in the the compression chamber wall penetration may
manufacturer's works in the presence of a Ger- be fully wired for the high-voltage test. The
manischer Lloyd Surveyor. sealing of the connector shells and the like is
permitted where this is stipulated by the manu-
4.5.6 In cables for winding on drums, no mechani- facturer in the relevant data sheet.
cal forces may be transmitted by electrical compo-
nents of the cable. The test voltage for plug connections rated at
more than 500 V is to be agreed with GL.

4.6 Electrical penetrations in compression – measurement of insulation resistance


chamber walls, underwater plug connec- The minimum value of the insulation resistance
tions between the conductors mutually and between
the conductors and the casing shall be 4 MΩ.
4.6.1 Penetrations in compression chamber walls
must be gas- and watertight. Their tightness must be The insulation resistance is to be measured with
guaranteed even should the connected cables be dam- an instrument using 500 V DC.
aged or shorn off.
With wet plug connections, the minimum insu-
lation resistance is also to be measured after the
4.6.2 compression chamber wall penetrations and connection has been made once in salt water.
underwater plug connections must have been type-
tested. – visual check against manufacturer's documenta-
tion.
Type-testing is performed, on application, in the
manufacturer's works and comprises at least the fol- 4.6.3 All electrical penetrations in compression
lowing individual tests: chamber walls and all plug connections are to be sub-
jected to individual inspection by the manufacturer. A
– hydraulic pressure test, in which the test pres- Works Test Certificate is to be issued by the manu-
sure must equal twice the design pressure. The facturer in respect of this inspection.
test is to be conducted in accordance with the
test pressure/time curve shown in Fig 2.1, the 4.6.4 The necessary test conditions applicable to
changes in pressure being applied as quickly as plug connections in medium voltage systems are to be
possible. agreed with GL in each case.

– gastightness test with shorn, open cable ends. 4.7 Interior lighting in compression chambers
This test may be performed alternatively under and diving bells
air or helium pressure. If compressed air is used,
the test pressure must be equal 2 times the de- 4.7.1 Each compression chamber compartment and
sign pressure; if helium is used, 1,5 times. each diving bell is to be equipped with a suitable nor-
mal and emergency lighting system.

4.7.2 The normal lighting system is to be so de-


signed and installed that the intensity of the lighting
P [bar]

inside the chamber is at least 300 lux. As far as possi-


ble, interior lighting should be free from glare.

4.7.3 The emergency lighting system is to be de-


0 signed and installed in such a way that a diver inside
the chamber is fully able to take readings and operate
0 5 10 15 20 25 30 35 40 45 50 55
controls in every compartment.
t [min]
4.7.4 Safeguards against the bursting of light fit-
Fig. 2.1 Test pressure/time curve tings are to be agreed with GL in each case.
I - Part 5 Section 2 I Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–29

I. Fire Protection 2.2.3 Components and materials are to be selected


with a view to minimizing the danger of static
1. General charges.

1.1 The Rules of this Section apply to the fire 3. Fire surveillance
protection of diving systems holding GL class which
are permanently or temporarily installed on a ship or 3.1 Fire detection and alarm systems
similar floating structure.
3.1.1 Interior spaces containing diving equipment
1.2 The documents to be submitted to GL for
such as surface compression chambers, diving bells,
approval are listed in A.4.
gas storage facilities, compressors and control stands
are to be monitored by an automatic fire detection
1.3 The necessary tests are stated in A.5. system.

2. Structural fire protection 3.1.2 The occurrence of fire must be signalled


visually and audibly in at least one permanently
2.1 Area of installation of diving system manned control room.

2.1.1 The ship or floating structure on which the 3.1.3 The fire alarm may be actuated manually
diving system is installed is required to conform to the from the permanently manned control room or may be
fire protection regulations of the classification society automatically activated by the fire detection system.
responsible and, where applicable, to the relevant
provisions of the 1974 International Convention for
3.2 Fire detection systems
the Safety of Life at Sea.

2.1.2 In the areas of installation of the diving sys- 3.2.1 Fire detection systems including central fire
tem, the gas storage facility and the control room, detection stations, fire detectors and the wiring of the
sources of ignition and fire loads must be reduced to a detection loops require the approval of GL.
minimum. As far as possible, materials which are at
least flame-retardant are to be used. Heat insulation is 3.2.2 Fire detection systems must be so constructed
to be made of incombustible materials. that any fault, e.g. supply failure, short-circuit or wire
breakage in the detection loops, or the removal of a
2.1.3 Diving systems on ships and other floating detector from its base triggers a visual and audible
structures may only be installed and operated in areas signal at the central fire detection station.
not subject to an explosion hazard in accordance with
B.4. 3.2.3 The design and arrangement of fire detection
and alarm systems are to conform to the Rules for
2.1.4 Where diving systems or parts thereof are Classification and Construction, Part 1 – Seagoing
installed in enclosed spaces, these spaces are to be Ships, Chapter 3 – Electrical Installations, Section 9,
separated from the deck and the rest of the ship by C. and Chapter 4 – Automation.
partitions of type "A"-60.

2.1.5 Enclosed spaces for diving systems or parts 4. Fire extinguishing systems
thereof are to be provided with a forced ventilation
system capable of effecting at least 8 changes of air 4.1 Area of installation of diving system
per hours. The air must be drawn from an area not
subject to an explosion hazard. 4.1.1 Every ship or floating structure on which a
diving system is installed must be equipped with a
2.2 Interiors of compression chambers and general water fire extinguishing system as well as with
diving bells portable and mobile fire extinguishers and extinguish-
ing equipment in accordance with the Rules for Clas-
2.2.1 As far as possible, all materials used in com- sification and Construction, Part 1 – Seagoing Ships,
pression chambers or diving bells must be at least Chapter 2 – Machinery Installations, Section 12.
flame-retardant (for the purpose of these Rules,
"flame-retardant" refers to materials which do not 4.1.2 Where pressure vessels are situated in en-
continue to burn spontaneously in a compressed air closed spaces, a permanently installed water spray
atmosphere of at least 6 bar).
system having an application rate of 10 A/m2/minute
2.2.2 As far as possible, fire loads and sources of related to the horizontal projected area is to be pro-
ignition are to be avoided. Electrical heating appli- vided for cooling in the event of fire. These water
ances and heaters are to be fitted with protection spray systems may be manually activated and oper-
against overheating. ated.
Chapter 1 Section 2 J Rules for Construction of Diving Systems I - Part 5
Page 2–30 GL 1998

4.1.3 For pressure vessels installed on the open safe transfer of the diving bell between the work loca-
deck, cooling by means of fire hoses connected to the tion and the surface compression chamber
general fire extinguishing system is permitted.
2.2 The handling system shall provide means for
4.1.4 Interior spaces containing diving systems or the safe and easily controllable transport of the diving
parts thereof are to be additionally equipped with ap- bell.
proved manual fire extinguishers. One of the portable
fire extinguishers shall in every case be situated close
2.3 For the eventuality of single component fail-
to the entrance to the space concerned.
ure in the main handling system, an alternative means
is to be provided to enable the divers to be brought
4.2 In compression chambers back to the surface compression chamber. This alter-
native system must be supplied with power independ-
4.2.1 Each compartment of a surface compression ently of the main handling system. In addition, provi-
chamber is to be equipped with suitable means for sion is to be made for emergency retrieval of the bell
extinguishing a fire in the interior by providing for the should both the main and alternative systems fail.
rapid and efficient distribution of the extinguishing
agent to any part of the chamber. Diving bells whose emergency ascent is initiated by
the release of ballast must be equipped with devices
4.2.2 The fire extinguishing system is to be de- for releasing the hoisting and lowering strength mem-
signed and constructed in such a way that it can safely ber/umbilical and the ballast weight. The equipment
deal with every conceivable outbreak of fire under all shall be so designed that two mutually independent
the environmental conditions for which the diving operating actions have to be performed inside the
system is designed. Actuation of the fire extinguishing chamber to initiate the release of ballast.
system may not cause any unacceptable pressure drop
inside the chamber. The extinguishing system may be After release of the ballast weights, the diving bell, at
actuated by hand. It must at all times be possible to its maximum service weight and with its trunk
stop the extinguishing operation from the chamber and flooded, must exhibit a positive buoyancy equal to at
from the control room. least 3 % of its displacement at maximum operating
depth. In these circumstances, the bell should have
4.2.3 Water is the preferred extinguishing agent. sufficient stability to maintain a substantially upright
Extinguishing agents with a toxic or narcotic effect are position.
not permitted.
2.4 The mating system shall enable the connec-
5. Other fire protection equipment tion and disconnection of the diving bell and surface
compression chamber to be effected easily and se-
Diving system control rooms are to be equipped with curely even under conditions where the support ship is
at least one independent compressed air respirator of rolling, pitching or listing to predetermined degrees.
approved design having an operating capability of at
least 30 minutes and fitted with equipment for voice 2.5 Where a power actuating system is used for
communication with the divers. mating operations, an auxiliary power actuating sys-
tem or an appropriate means is to be provided to con-
nect the diving bell to the surface compression cham-
ber in the event of failure of the normal power actuat-
J. Handling, Transfer and Mating Equip- ing system.
ment
2.6 The mating system is to be provided with a
1. General safety interlock between the diving bell and the sur-
face compression chamber.
1.1 These Rules apply to all equipment for the
handling, transfer and mating of the diving bells of 2.7 Unless otherwise stated in the following Sec-
diving systems holding GL class. tions, the mechanical equipment of the handling sys-
tem is to conform to VI – Additional Rules and Guide-
1.2 The documents to be submitted to GL are lines, Part 2 – Life Saving Appliances, Lifting Appli-
listed in A.4. ances, Accesses, Chapter 2 – Guidelines for the Con-
struction and Survey of Lifting Appliances, Section 9.
1.3 The necessary tests and markings are stated
in A.5. and A.6. 3. Calculations

2. Design principles 3.1 The "working load" of the handling system


comprises the weight of the diving bell, the total
2.1 Diving systems are to be provided with han- weight of the fully equipped divers at 150 kg each, the
dling and transfer equipment capable of ensuring the weight of the equipment and the ballast weights.
I - Part 5 Section 2 K Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–31

The "dead load" is the weight of the handling system. K. Hyperbaric Evacuation System

3.2 Regardless of the tape of handling system and


1. General
the size of the working load, the dimensional design of
the handling system is to allow for a working load
factor Ψ = 2,7 and a dead load factor ϕ of 1,5. It is 1.1 With reference to the "Guidelines and Speci-
assumed here that the use of the system in a seaway fications for Hyperbaric Evacuation Systems", Reso-
will be limited to significant wave heights of 2 m or lution A.692(17) of 6 November 1991, the IMO Code
less. Where it is proposed that handling operations of Safety for Diving Systems, Resolution A.831(19)
should be performed in even more unfavourable con- of 23 November 1995 stipulates for diving systems in-
ditions, previous agreement with GL is necessary. stalled on board ships or offshore platforms an
evacuation system enabling divers in saturation to be
rescued in the event of their having to abandon the
3.3 Calculations are to be based on the assump-
ship or the platform.
tion that the angle of engagement of the hoisting and
lowering strength member may be 12° off perpen-
dicular in any direction. 1.2 Depending on the local, geographical and
other service conditions, different kinds of evacuation
3.4 The maximum static tensile stress imposed systems are conceivable, including:
on steel wire ropes by the working load may not ex-
ceed 1/8 of the proven rupture strength of the ropes. 1.2.1 Hyperbaric self-propelled lifeboats

3.5 Where ropes made of natural or synthetic 1.2.2 Towable hyperbaric evacuation units
fibres are used, the maximum static tensile stress im-
posed by the working load may not exceed 1/10 of the 1.2.3 Hyperbaric evacuation units, which may or
proven rupture strength of the ropes. may not be towable, suitable for offloading onto an
attendant vessel
3.6 The stress limits for components are specified
in VI – Additional Rules and Guidelines, Part 2 – Life 1.2.4 Transfer of the diving bell to another facility
Saving Appliances, Lifting Appliances, Accesses,
Chapter 2 – Guidelines for the Construction and Sur- 1.2.5 Transfer of the divers from one diving bell to
vey of Lifting Appliances, Section 2. another when in the water and under pressure

4. Construction 1.2.6 Negatively buoyant unit with inherent re-


serves of buoyancy, stability and life support capable
of returning to the surface to await independent recov-
4.1 The handling system must be provided with
ery.
suitable means for preventing any excessive rotation
of the diving bell (e.g. non-spin rope).
1.3 If a self-propelled or towable hyperbaric
4.2 The use of fibre ropes is permitted only in evacuation system permanently connected to the div-
special cases with the consent of GL: ing system is provided, the following requirements are
to be applied.
4.3 Precautions are to be taken to prevent the
diving bell from jarring against the ship's hull or the 1.4 The necessary tests are stated in A.5. Official
handling gear. regulations may necessitate further tests.

4.4 All interchangeable components such as 2. Design principles


blocks, hooks, shackles etc. are to conform to recog-
nized standards and must be designed for twice the
working load. 2.1 Pressure chamber

4.5 The driving power of the handling system 2.1.1 The pressure chamber of the hyperbaric
must be sufficient to lift 1,5 times the working load. evacuation system shall be so designed that all the
divers in the diving system can be rescued simultane-
The strength of the mechanical brake must be suffi- ously at maximum operating depth. At least one seat
cient to hold the test loads specified in A.5.11. with safety harness is to be provided for each diver.

4.6 Before assembly, all interchangeable compo- 2.1.2 The pressure chamber is to be equipped with
nents are to be subjected to individual component load a supply lock.
testing.
2.1.3 The connection flange of the pressure cham-
4.7 The rupture strength of ropes is to be verified ber is to be so designed that it is also able to mate to a
by a full tensile breaking test. different system.
Chapter 1 Section 2 L Rules for Construction of Diving Systems I - Part 5
Page 2–32 GL 1998

2.1.4 The pressure chamber is to be fitted with 2.3.3 The handling system must be capable of
view ports in such a way that, wherever possible, all safely launching the hyperbaric evacuation system
the occupants can be observed from outside. and, where applicable, of effecting also the retrieval
and mating operatings.
2.1.5 The pressure chamber is to be provided with
the necessary connections to enable the internal pres- 2.3.4 Disconnection and launching of the system
sure, temperature, gas composition and humidity to be must also be possible in the event of failure of the
maintained. ship's power supply.
2.1.6 The pressure chamber is to be adequately lit.

2.2 Hyperbaric evacuation system L. Wet Bells


2.2.1 The hyperbaric evacuation system is to be so
designed that its behaviour in a seaway corresponds to 1. General
that of an enclosed lifeboat.
1.1 Wet bells serve the purpose of safely carrying
2.2.2 The system must be self-propelled and capa- divers and their equipment from a ship's deck or a
ble of navigation or must be provided with means (e.g. platform to and from the site, using either compressed
suitably equipped ancillary boat) enabling the hyper- air or gas mixtures as breathing gas, depending on the
baric evacuation system to be towed away quickly depth, however, without saturation being reached.
after launching.
1.2 The documents to be submitted to GL for
2.2.3 The hyperbaric evacuation system must be
approval are listed in A.4.11.
equipped with its own life support system enabling the
pressure, temperature, humidity and gas composition
in the pressure chamber to be maintained for at least 1.3 The testings required are defined in A.5.13.
72 hours. The life support systems are to be provided
with connections for external supply and surveillance. 2. Design principles
2.2.4 The hyperbaric evacuation system must be
equipped with the controls needed to maintain a safe 2.1 Wet bells should be designed for the carriage
environment for the divers. of at least two divers, including their equipment. Nor-
mally, they consist of an upper part at head and shoul-
2.2.5 The hyperbaric evacuation system must be der level supporting a gas pocket and an open lower
equipped with a communication system for talking to part provided with a platform enabling the divers to
the divers. stand safely.

2.2.6 The hyperbaric evacuation system is to be 2.2 Wet bells and the persons inside are to be
equipped with its own power supply capable of keep- adequately protected against impacts during lowering
ing the electrical installations in operation for at least or recovering.
72 hours.
2.3 The supply lines for breathing gas, hot water,
2.2.7 The hyperbaric evacuation system is to be etc. are to be arranged from the surface through the
provided with lifting attachments enabling it to be wet bell to the divers. Alternatively, supply by a joint
hoisted by a standard ship's crane. umbilical is possible, which is connected to the bell
connections for the individual diver umbilicals.
2.2.8 The hyperbaric evacuation system must be
constructed of materials which are at least flame-retar- The bell is to be equipped with devices for opening up
dant and must be equipped with a water spray system the diver supply lines.
for cooling the surface in the event of fire.
2.4 Wet bells are to be provided with emergency
2.3 Mating and handling systems supplies of breathing gas sufficient to supply the di-
vers at maximum depth for a period of two hours and
2.3.1 The mating system of the hyperbaric evacua- with an emergency breathing mask for each diver.
tion system must be designed to permit rapid and safe
connection and disconnection.
2.5 The upper part of the bell supporting the gas
2.3.2 The design and testing of the handling system pocket must be equipped for scavenging with the re-
must conform to VI – Additional Rules and Guide- spective breathing gas employed.
lines, Part 2 – Life Saving Appliances, Lifting Appli-
ances, Accesses, Chapter 1 – Guidelines for Life Sav- 2.6 The wet bells must be equipped with appro-
ing Launching Appliances and, where applicable, to priate devices for the salvaging and securing of divers
the relevant national regulations. having suffered an accident.
I - Part 5 Section 2 L Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–33

2.7 Lighting is to be installed in the wet bell for of breathing gas of appropriate composition are to be
working and for emergency purposes. In addition a kept available.
surface communication line is to be provided.
4.2 Where during a diving operation and the
2.8 Wet bells are to be provided with appropriate pertinent decompression phases different kinds of
devices ensuring indication of the respective diving breathing gas are employed, it is to be ensured that
depth in the surface control station. each of the gases employed can at any time be identi-
fied at the control station.
3. Launching devices

3.1 Launching devices for wet bells have to safe- 5. Control station
guard safe launching and recovery under all admissi-
ble seaway and weather conditions. The control station at the surface is to be equipped
with all necessary devices ensuring that the parameters
3.2 The launching device must facilitate the de- quoted below are at any time adhered to and moni-
compression stops in the water to be reliably and ex- tored:
actly observed. Jerky motions of the wet bell due to
ropes becoming slack in a seaway are to be avoided by – supply of divers with adequate quantities of the
appropriate structural measures. proper breathing gas

– possibly supply of divers' thermal suits with an


3.3 Where the hoisting rope and the supply lines
adequate quantity of hot water of adequate tem-
are arranged separately appropriate measures are to be
perature
taken for preventing these from twisting and from
damaging each other during launching and/or recovery
operations. – indication of diving depth of bell

– adherence to decompression stops and periods


3.4 It is to be ensured that upon recovery the wet
bell will be deposited on deck without jerks and im-
– uninterrupted communication with divers
pacts.
– insulation values of the wet bell's electrical
4. Equipment for breathing gas supply equipment

4.1 For the wet bell system in accordance with Visual monitoring of the bell and the operating site by
the design diving depths and service periods supplies VHF TV system.
Chapter 1 Section 2 L Rules for Construction of Diving Systems I - Part 5
Page 2–32 GL 1998

2.1.4 The pressure chamber is to be fitted with 2.3.3 The handling system must be capable of
view ports in such a way that, wherever possible, all safely launching the hyperbaric evacuation system
the occupants can be observed from outside. and, where applicable, of effecting also the retrieval
and mating operatings.
2.1.5 The pressure chamber is to be provided with
the necessary connections to enable the internal pres- 2.3.4 Disconnection and launching of the system
sure, temperature, gas composition and humidity to be must also be possible in the event of failure of the
maintained. ship's power supply.
2.1.6 The pressure chamber is to be adequately lit.

2.2 Hyperbaric evacuation system L. Wet Bells


2.2.1 The hyperbaric evacuation system is to be so
designed that its behaviour in a seaway corresponds to 1. General
that of an enclosed lifeboat.
1.1 Wet bells serve the purpose of safely carrying
2.2.2 The system must be self-propelled and capa- divers and their equipment from a ship's deck or a
ble of navigation or must be provided with means (e.g. platform to and from the site, using either compressed
suitably equipped ancillary boat) enabling the hyper- air or gas mixtures as breathing gas, depending on the
baric evacuation system to be towed away quickly depth, however, without saturation being reached.
after launching.
1.2 The documents to be submitted to GL for
2.2.3 The hyperbaric evacuation system must be
approval are listed in A.4.11.
equipped with its own life support system enabling the
pressure, temperature, humidity and gas composition
in the pressure chamber to be maintained for at least 1.3 The testings required are defined in A.5.13.
72 hours. The life support systems are to be provided
with connections for external supply and surveillance. 2. Design principles
2.2.4 The hyperbaric evacuation system must be
equipped with the controls needed to maintain a safe 2.1 Wet bells should be designed for the carriage
environment for the divers. of at least two divers, including their equipment. Nor-
mally, they consist of an upper part at head and shoul-
2.2.5 The hyperbaric evacuation system must be der level supporting a gas pocket and an open lower
equipped with a communication system for talking to part provided with a platform enabling the divers to
the divers. stand safely.

2.2.6 The hyperbaric evacuation system is to be 2.2 Wet bells and the persons inside are to be
equipped with its own power supply capable of keep- adequately protected against impacts during lowering
ing the electrical installations in operation for at least or recovering.
72 hours.
2.3 The supply lines for breathing gas, hot water,
2.2.7 The hyperbaric evacuation system is to be etc. are to be arranged from the surface through the
provided with lifting attachments enabling it to be wet bell to the divers. Alternatively, supply by a joint
hoisted by a standard ship's crane. umbilical is possible, which is connected to the bell
connections for the individual diver umbilicals.
2.2.8 The hyperbaric evacuation system must be
constructed of materials which are at least flame-retar- The bell is to be equipped with devices for opening up
dant and must be equipped with a water spray system the diver supply lines.
for cooling the surface in the event of fire.
2.4 Wet bells are to be provided with emergency
2.3 Mating and handling systems supplies of breathing gas sufficient to supply the di-
vers at maximum depth for a period of two hours and
2.3.1 The mating system of the hyperbaric evacua- with an emergency breathing mask for each diver.
tion system must be designed to permit rapid and safe
connection and disconnection.
2.5 The upper part of the bell supporting the gas
2.3.2 The design and testing of the handling system pocket must be equipped for scavenging with the re-
must conform to VI – Additional Rules and Guide- spective breathing gas employed.
lines, Part 2 – Life Saving Appliances, Lifting Appli-
ances, Accesses, Chapter 1 – Guidelines for Life Sav- 2.6 The wet bells must be equipped with appro-
ing Launching Appliances and, where applicable, to priate devices for the salvaging and securing of divers
the relevant national regulations. having suffered an accident.
I - Part 5 Section 2 L Rules for Construction of Diving Systems Chapter 1
GL 1998 Page 2–33

2.7 Lighting is to be installed in the wet bell for of breathing gas of appropriate composition are to be
working and for emergency purposes. In addition a kept available.
surface communication line is to be provided.
4.2 Where during a diving operation and the
2.8 Wet bells are to be provided with appropriate pertinent decompression phases different kinds of
devices ensuring indication of the respective diving breathing gas are employed, it is to be ensured that
depth in the surface control station. each of the gases employed can at any time be identi-
fied at the control station.
3. Launching devices

3.1 Launching devices for wet bells have to safe- 5. Control station
guard safe launching and recovery under all admissi-
ble seaway and weather conditions. The control station at the surface is to be equipped
with all necessary devices ensuring that the parameters
3.2 The launching device must facilitate the de- quoted below are at any time adhered to and moni-
compression stops in the water to be reliably and ex- tored:
actly observed. Jerky motions of the wet bell due to
ropes becoming slack in a seaway are to be avoided by – supply of divers with adequate quantities of the
appropriate structural measures. proper breathing gas

– possibly supply of divers' thermal suits with an


3.3 Where the hoisting rope and the supply lines
adequate quantity of hot water of adequate tem-
are arranged separately appropriate measures are to be
perature
taken for preventing these from twisting and from
damaging each other during launching and/or recovery
operations. – indication of diving depth of bell

– adherence to decompression stops and periods


3.4 It is to be ensured that upon recovery the wet
bell will be deposited on deck without jerks and im-
– uninterrupted communication with divers
pacts.
– insulation values of the wet bell's electrical
4. Equipment for breathing gas supply equipment

4.1 For the wet bell system in accordance with Visual monitoring of the bell and the operating site by
the design diving depths and service periods supplies VHF TV system.
I - Part 5 Section 3 A Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–1

Section 3

Rules for Construction of Diving Simulators

A. General Rules and Instructions 2.3 Breathing gas/breathing mixture


All gases/mixtures which are used for breathing during
1. General diving operations.

1.1 The following Rules of Construction apply to 2.4 Handling and transfer system
diving simulators which are permanently installed in a
building or similar structure and which are built under The plant and equipment necessary for raising, lower-
the survey and in accordance with the Rules of GL ing and transporting the diving bell between the work
with a view to the issue of an appropriate Certificate. location and the surface compression chamber.

1.2 On application by the operator, diving simu- 2.5 Compression chamber


lators built in accordance with 1.1 may also be classi-
fied by GL. A pressure vessel for human occupancy equipped with
means for controlling and monitoring the pressure
within the chamber.
1.3 Buildings, power generating plants, fuel stor-
age and gas storage facilities etc. are required to com-
ply with the relevant national regulations of the coun- 2.6 Pressure vessel
try in which the facilities are established. A container capable of withstanding an internal work-
ing pressure of 1 bar or over.
1.4 Designs other than those stated in the Rules
of Construction may be approved provided their suit- 2.7 Bottle
ability has been verified by GL and they have been
recognized as equivalent. A pressure container for the storage and transport of
gases under pressure.
1.5 GL reserve the right to impose requirements
additional to those contained in the Rules in respect of 2.8 Compression chamber
all types of facility should this become necessary in
the light of new knowledge or practical experience. A pressure vessel for human occupancy under pres-
GL likewise reserves the right to sanction exceptions sure.
to the Rules in specially justified cases.
2.9 Areas subject to explosion hazard
1.6 National regulations existing alongside the Those locations in which an explosive gas-air mixture
GL Rules are unaffected. is continuously present, or present for long periods
(zone 0); in which an explosive gas-air mixture is
2. Definitions likely to occur in normal operation (zone 1); in which
an explosive gas-air mixture is not likely to occur and,
For the purpose of these Rules the terms used therein if it does, will persist for only a short time (zone 2).
shall have the following meanings in the absence of an
express statement to the contrary: 2.10 Gas storage facility

2.1 Mating device Bottles permanently installed in the open or inside


which contain the store of breathing and working gases
The equipment necessary for the connection and dis- needed for operation of the simulator.
connection of a diving bell to a surface compression
chamber. 2.11 Maximum operating depth of the diving
system
2.2 Working gas
The depth in metres of seawater equivalent to the
All gases needed for performing underwater opera- maximum pressure for which the diving system is
tions such as torch work, cutting, welding etc. designed.
Chapter 1 Section 3 A Rules for Construction of Diving Simulators I - Part 5
Page 3–2 GL 1998

2.12 Hyperbaric evacuation system 3. Components of diving simulators

A system whereby divers under pressure can be safely 3.1 Where present, the following components
evacuated to a position where decompression can be form part of the diving simulator system and are to be
carried out. designed, manufactured and tested in accordance with
these Rules:
2.13 Compact umbilical
– compression chambers
A link cable with a protective sheath combining in one
assembly the power supply, surveillance and commu- – bottles
nication lines, the breathing gas and hot water hoses – pressure vessels
and the hoisting and lowering strength member.
– pipes, valves, fittings and hoses
2.14 Life support system
– breathing gas systems
The gas supply, breathing gas system, surveillance
– life support systems
system and equipment required to provide a safe envi-
ronment for the diving crew in the diving simulator – welding gas absorbers
under all possible pressures and conditions to which
they may be exposed during diving operations. – diver heating system
– sanitary systems
2.15 Diving bell
– communication systems
A submersible compression chamber, including its
ancillary equipment, for transfer of divers under pres- – surveillance, automation and control equipment
sure between the work location and the surface com-
pression chamber. – gas analyzing systems

– electrical systems and equipment


2.16 Diving simulator
– fire prevention, detection and extinguishing
A compression chamber system in which both manned equipment
and unmanned tests can be carried out in a wet or dry
environment under conditions simulating those at sea. – compressors

– gas mixers
2.17 Depth
– helium reclaim system
The pressure, expressed in metres of seawater, to
which the diver is exposed at any time during a dive or – water systems
inside a compression chamber.
– hyperbaric evacuation system

2.18 Umbilical
4. Documents for approval
The link between the diving support unit and the div-
ing bell which may contain surveillance, communica- 4.1 General
tion and power supply cables, breathing gas and hot
water hoses. The strength member for hoisting and 4.1.1 Before the start of manufacture, plans and
lowering the diving bell may be part of the umbilical. drawings of all components subject to compulsory
inspection, to the extent specified below, are to be
2.19 Test chamber submitted to Germanischer Lloyd in triplicate.

A compression chamber in which manned and un- 4.1.2 The drawings must contain all the data neces-
manned tests can be carried out under the conditions sary for checking the design, the loads and the stresses
prevailing in the sea. imposed. Where necessary, design calculations relat-
ing to components and descriptions of the plant are
2.20 Living compartment also to be supplied.

The part of the surface compression chamber which is 4.1.3 Once the documents submitted have been
intended to be used as the main habitation for the di- approved by GL, they become binding on the manu-
vers during diving operations and which is equipped facturer. Any subsequent modifications require GL's
for such purpose. consent before they are implemented.
I - Part 5 Section 3 A Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–3

4.2 Total system – integral opening reinforcements


The following documents are to be submitted: – internal facilities

4.2.1 Description of plant stating the essential de- 4.4 Gas supply
sign parameters such as:
– purpose of the diving simulator 4.4.1 Piping diagrams and descriptions are to be
furnished for the entire gas supply system, including a
– diving or operating procedure list of valves and fittings.
– maximum operating depth
4.4.2 Description of proposed cleaning procedure
– maximum operating period for breathing gas system.
– maximum number of divers in system 4.4.3 Details of gas analysis, including an equip-
– maximum rates of pressure change ment list.

4.2.2 General arrangement drawings of the diving 4.4.4 Description of compressors and compressor
simulator (block diagram). drives together with longitudinal and transverse sec-
tional drawings of the compressor crankshaft.
4.2.3 Installation drawings.
4.5 Life support systems
4.2.4 Foundation drawings, showing fixed points.
The following are to be submitted:
4.2.5 Drawings of supply and disposal systems
(water and electricity). 4.5.1 Piping diagrams, block diagrams and descrip-
tions of systems.
4.2.6 Identification system
4.5.2 Descriptions of system components and
4.2.7 Test schedule. equipment.

4.3 Pressure vessels and apparatus 4.5.3 Calculation of cooling and heating require-
ments.
4.3.1 Drawings are to be submitted of pressure
vessels and apparatus giving full details for appraising 4.5.4 Description and drawings of the water supply,
the safety of the equipment. disposal, circulation and treatment systems.

The information provided shall include the following: 4.5.5 Description and design details of the diver
– application heating system.

– capacities of individual compartments 4.6 Automation and communications equip-


– media contained, together with operating pres- ment
sures and temperatures The following are to be submitted:
– proposed materials, thermal insulation materials,
paints, buoyancy material 4.6.1 General arrangement drawings/block dia-
grams of control equipment, including lists of meas-
– welding specifications uring points.
– heat treatment
4.6.2 Equipment list for sensors, indicating instru-
– manufacturing tolerances ments etc.
– non-destructive tests 4.6.3 Drawings and descriptions of electronic com-
ponents such as instrument amplifiers, computers and
4.3.2 Drawings are also to be submitted of individ- peripheral units.
ual items of vessel equipment such as:
– windows, window flanges, retaining rings 4.6.4 General arrangement drawings and equipment
lists for communication systems and signalling equip-
– door leaves and frames ment.
– bayonet locks
4.6.5 Arrangement drawing and description of the
– coupling clamps TV system.
Chapter 1 Section 3 A Rules for Construction of Diving Simulators I - Part 5
Page 3–4 GL 1998

4.7 Electrical equipment 4.9.2 Arrangement drawing.


The following are to be submitted:
4.9.3 Construction drawings of evacuation system.
4.7.1 A general arrangement drawing of the elec-
trical equipment containing at least the following in- 4.9.4 Drawings of mating and handling system.
formation:
– voltage rating of systems 5. Tests and trials

– power or current ratings of electrical consumers 5.1 General


– switchgear, indicating settings for short-circuit
and overload protection; fuses with details of 5.1.1 Diving simulators and their ancillary equip-
current ratings ment are subject to constructural and materials tests as
well as to pressure and tightness tests and trials. All
– cable types and cross sections the tests called for in the following paragraphs are to
be performed under GL supervision.
4.7.2 The energy balance of the main and emer-
gency power supply system.
5.1.2 For serial manufactured parts, test procedures
other than those prescribed may be agreed with GL
4.7.3 Drawings of switchgear and distribution
provided that they are recognized as equivalent by the
equipment part lists.
Society.
4.7.4 Complete documentation for electric motor
drives with details of control, measuring and monitor- 5.1.3 GL reserve the right to increase the scope of
ing systems. the tests, if necessary, and also to extend tests to parts
for which testing is not expressly required according to
4.7.5 Battery installation drawing with details of the Rules.
battery types, chargers and battery room ventilation.
5.1.4 Parts requiring approval are to be replaced
4.7.6 Details of electrical penetrations through with tested parts. The same applies to spare parts.
compression chamber walls.
5.1.5 After the compression chambers and their
4.7.7 Drawings and descriptions of all electrical ancillary equipment have been installed in the opera-
components installed in compression chambers. tions building, the diving simulator and its auxiliary
systems are to be subjected to a functional test. All
4.7.8 Drawing showing the utilization of electrical items of safety equipment are to be tested except
penetrations through compression chamber walls. where an adequate test has already been carried out in
the manufacturer's works in the presence of a repre-
4.8 Fire protection sentative of GL.

The following are to be submitted:


5.2 Pressure vessels and apparatus
4.8.1 A description of the preventive fire protection
measures taken. 5.2.1 On completion, pressure vessels and appara-
tus are to be subjected to a constructural test.
4.8.2 Details of the fire loads in the system.
This test covers verification that the vessel conform to
4.8.3 Drawings and descriptions of: the approved drawings and that the workmanship is
satisfactory. All components must be accessible to
– fire detection system allow proper inspection.
– fire extinguishing system(s)
5.2.2 The materials test certificates for the materi-
– fire alarm equipment als used, the reports on the non-destructive testing of
welds and, where applicable, the results of inspection
– building of workmanship are to be submitted together with
– drawings of fire protection and fire escapes evidence of any heat treatments applied.

4.9 Hyperbaric evacuation system 5.2.3 A hydraulic pressure test is to be performed


prior to insulation and preservation treatment of the
The following are to be submitted: vessels. Each compression chamber compartment is to
be tested individually. The walls may exhibit no per-
4.9.1 Description of system. manent deformation or leakage.
I - Part 5 Section 3 A Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–5

5.2.4 The test pressure normally applied to vessels 5.6 Hoses, umbilicals
and apparatus shall be 1,5 time the maximum permis-
sible working pressure. 5.6.1 Proof of the bursting pressure of each type of
hose is to be submitted to GL. For liquids, hoses must
5.2.5 Diving bells and vessels which may be ex- be able to withstand at least 4 times, and in the case of
posed in service to external excess pressure are, in gases at least 5 times, the maximum permissible work-
addition, to be subjected to an external pressure test. ing pressure.
The external test pressure shall normally be equal to
1,3 times the design pressure. 5.6.2 Each hose is to be subjected to a hydraulic
pressure test at least 2 times the maximum permissible
5.2.6 Gas storage facilities, diving simulator and working pressure.
life support systems, including piping systems, are to
be subjected to a tightness test at the maximum per- 5.6.3 Where hoses are subjected to external pres-
missible working pressure using the appropriate sure, proof is required that a differently ratio of 1,5
breathing gas or gas mixture possessing similar prop- between the internal and external pressures can be
erties. withstood without failure.
The maximum permissible leakage rate is equivalent
to a 1 % pressure drop in 24 hours for the whole com- 5.7 Life support systems
pression chamber system. A functional test is to be performed to demonstrate the
satisfactory operation of the life support systems under
5.3 Compression chamber windows normal and emergency operating conditions.
5.3.1 Each compression chamber window must be
5.8 Automation and communications equip-
subjected to a hydraulic pressure test which may be
ment
performed in a testing device or on the window and
compression chamber together after assembly. The test 5.8.1 Indicating and monitoring instruments are to
pressure shall normally be equal to 1,5 times the de- be checked for the accuracy of their readings and their
sign pressure. limit settings.
5.3.2 After the pressure test, the windows shall not
5.8.2 The satisfactory operation of automatic con-
exhibit any scratches, cracks or permanent deforma-
trol systems is to be checked under service conditions.
tion.
Proof is required of the autonomy of safety systems.
5.4 Compressors 5.8.3 The communications equipment for normal
and emergency operation is to be subjected to a func-
5.4.1 Compressor components subjected to pres-
tional test. The suitability of the helium speech un-
sure are to undergo a hydraulic pressure test at a test
scrambler is to be verified at the maximum operating
pressure equal to 1,5 times the delivery pressure of the
depth of the facility.
stage concerned.

5.4.2 On completion, compressors are to be sub- 5.9 Electrical equipment


jected to a tightness test at the maximum permissible
working pressure applicable. A performance test shall 5.9.1 Electrical machines, components, cables and
also be performed during which the final moisture lines are to be subjected to testing in the manufac-
content and any possible contamination of the com- turer's works in accordance with the Rules for Classi-
pressed gas shall also be determined. fication and Construction Part 1 – Seagoing Ships,
Chapter 3 – Electrical Installations.
5.5 Piping systems
5.9.2 All electrical systems and equipment are to be
5.5.1 On completion but before the application of surveyed and tested before the diving simulator is
insulation or paint, all piping systems are to be sub- placed in service.
jected to a hydraulic pressure test at 1,5 times the
design pressure. 5.9.3 The electrical safety devices are to be tested
and, in addition, the electrical equipment in the com-
5.5.2 Tightness test, cf. 5.2.6. pression chambers is to be subjected to an insulation
test.
5.5.3 Wherever possible, all butt welded joints in
LSS gas lines are to be subjected to 100 % X-ray ex- 5.10 Fire protection
amination.
5.10.1 The fire behaviour of the chamber equipment
5.5.4 Piping systems for breathing gas and oxygen is to be checked by reference to the relevant test cer-
are to be subjected to a purity test. tificates and symbols.
Chapter 1 Section 3 B Rules for Construction of Diving Simulators I - Part 5
Page 3–6 GL 1998

5.10.2 A check is to be made as to whether the elec- Table 3.1 Marking of gas systems
trical heating systems and heaters are fitted with pro-
tection against overheating. Type of Chemical
Colour code
gas symbol
5.10.3 Fire alarm, detection and extinguishing appli-
ances are to be subjected to a functional test. Oxygen O2 white

Nitrogen N2 black
5.11 Hyperbaric evacuation system
Air --- white and black
A functional test is to be carried out to demonstrate
that the hyperbaric evacuation system is able to convey Helium He brown
divers under pressure to a safe position where they can
Oxygen/
be supplied and kept under surveillance.
Helium
O2/He white and brown
Gas
6. Marking mixture

6.1 A name plate containing at least the following


details is to be permanently fitted to all compression
chambers in a prominent position:
B. Principles of Design and Construction of
– name of manufacturer Diving Simulators

– serial number and year of manufacture


1. General principles
– maximum permissible working pressure or oper-
ating depth
1.1 Wherever appropriate and practicable, diving
– test pressure simulators are to be designed and built in such a way
that the failure of any single component cannot cause a
– capacity (in litres) of each chamber compartment dangerous situation.

– maximum permitted number of divers


1.2 Diving simulators and their components are
– date of test and test stamp to be designed for the conditions of service described
in the equipment specification.
6.2 All other pressure vessels and gas bottles are
to be prominently and permanently marked with the 1.3 Diving simulators are to be so designed that
following details: the proposed tests can be performed with maximum
safety for the simulator crew.
– name of manufacturer
– serial number and year of manufacture 1.4 Diving simulators for technical experiments
are to be equipped with suitable test chambers which
– capacity (in litres) must be separable from the remaining chamber system
in respect of operating services, pressure and atmos-
– test pressure (bar) pheric conditions.
– empty weight (of gas bottles) The living compartment of the simulator is to be so
arranged that its occupants are not endangered or in-
– date of test and test stamp
convenienced by the experiments.

6.3 Permanently installed gas bottles, gas con-


1.5 Diving simulators which can be operated with
tainers and gas piping systems are also to be perma-
simultaneously differing chamber pressures must be
nently colour-coded in accordance with Table 3.1 and
provided with effective means of preventing any un-
are to bear the chemical symbol of the type of gas
intentional pressure drift within the chamber system.
concerned. The marking of gas bottles must be visible
from the valve side.
1.6 Diving simulators must be designed in such a
6.4 All valves, fittings, controls, indicators and way that injured divers can be carried on a stretcher
warning devices are to be fitted with identification inside the compression chamber system.
plates made of material which is at least flame-retar-
dant. The marking shall be easily legible and clear (i.e. 1.7 It is recommended that diving simulators be
abbreviated designation and/or functional description). equipped with a hyperbaric evacuation system.
I - Part 5 Section 3 B Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–7

1.8 Diving simulators are to be designed and built 4.4 The area of installation of diving simulators is
to facilitate safe operation, adequate maintenance and to be separated from other operational facilities. The
necessary surveys. partition must, as a minimum requirement, possess
Class F 30 fire resistance as defined in DIN 4102.
1.9 All parts of a diving simulator are to be de-
signed, constructed and mounted in a way which fa-
cilitates cleaning and disinfection. 5. Chamber equipment and facilities

2. Environmental conditions 5.1 Compression chamber equipment and facili-


ties must be suitable for operation in hyperbaric at-
Diving simulators, including their accessories and
mospheres. Under these conditions they shall not lib-
ancillary equipment, are to be designed for the envi-
erate any toxic or strongly irritant gases. This also
ronmental conditions likely to be encountered at the
applies to protective coatings and paints used inside
operating site or under the planned test conditions.
chambers.

3. Chamber conditions
5.2 Only incombustible, or at least flame-retar-
3.1 Diving simulators are to be equipped in such dant, materials should be used in the chambers (cf.
a way that a breathable atmosphere can be maintained Section 2, I.2.2.1).
in the compression chambers throughout the period of
operation.
5.3 Permanently installed chamber facilities are
to be so designed that they suffer no damage when the
3.2 Means must be provided for keeping the chamber is subjected to hydraulic pressure tests.
partial pressure of CO2 below 0,005 bar at all times
and for this purpose a CO2 production of 0,05 Nm3/h
per diver shall be assumed. 5.4 Equipment items in experimental chambers
are to be designed and installed in such a way as to
minimize the danger of injury to the divers and leave
3.3 Under steady conditions, diving simulators
sufficient room for movement. In addition, chamber
must be capable of keeping the temperature in the
equipment and experimental apparatus shall not pre-
compression chamber constant to ± 1 °C in the range
vent or limit unduly the possibility of observing the
from 27 to 36 °C while maintaining a relative atmo-
divers from outside the test chamber, where necessary
spheric humidity of at least 50 %.
with the aid of TV equipment.
3.4 Compression chambers are to be so arranged
and equipped that a uniform chamber atmosphere can 5.5 Ancillary systems and equipment needed to
be maintained (CO2 and O2 levels, temperature and perform tests or create experimental boundary condi-
humidity). tions are to be designed and constructed so that they
are able to perform their functions safely without dan-
3.5 Under steady conditions, the permanent noise ger to the divers. The relevant requirements will be
level (over 8 hours) in the living and compression stipulated by GL in each case.
chambers shall not exceed 65 dB(A).

3.6 Deviations from the aforementioned chamber 6. Corrosion protection


conditions are permitted where this is essential to the
performance of the tests and where additional meas- 6.1 Diving simulators and all their ancillary com-
ures are taken to ensure the divers' safety. ponents are to be effectively protected against corro-
sion. The corrosion protection must be capable of
4. Arrangement being repaired or retouched at a later stage.

4.1 Diving simulators may only be installed and


operated in areas not subjected to an explosion hazard. 6.2 Anti-corrosion coatings exposed to the cham-
ber conditions must meet the requirements stated in 5.
In addition, they shall not tend to blister or flake off
4.2 As far as possible, the area of installation of under hyperbaric conditions. In wet test chambers it
diving simulators is to be kept free of fire loads. may be necessary to make special provision for the
effect of helium-saturated seawater.
4.3 Diving simulators and breathing gas storage
facilities are to be located in areas which can be ade-
quately ventilated and provided with suitable electric 6.3 Wet test chambers are to be provided with an
lighting. adequate anodic protection system.
Chapter 1 Section 3 C Rules for Construction of Diving Simulators I - Part 5
Page 3–8 GL 1998

C. Pressure Vessels and Apparatus 1.2.2 Test chambers


1.2.2.1 Test chambers are to be designed and built in
1. Compression chambers such a way that the proposed tests can be performed
safely and any danger to the rest of the chamber sys-
1.1 General tem is avoided.

1.1.1 The following Rules apply to pressure vessels 1.2.2.2 The dimensional design of test chamber walls
used as compression chambers in diving simulators. is to allow for possible additional loads due to test
equipment.
1.1.2 The documents to be submitted to GL for
approval are listed in A.4. 1.2.2.3 Test chambers are to be separated by double
doors from the rest of the chamber system.
1.1.3 The necessary tests and markings are stated in
A.5. and A.6. 1.2.2.4 Manned test chambers for technical experi-
ments are to be provided with a lock for materials.
1.2 Design principles 1.2.2.5 Test chambers compartment are to be pro-
vided with sufficient mountings for experimental
1.2.1 Compression chambers equipment. Adequate means are also to be provided
for the transport and handling of experimental equip-
1.2.1.1 Each compression chamber and chamber
ment.
compartment is to be equipped with reliable safe-
guards against an excessive working pressure and any 1.2.2.6 Each test chamber compartment is to be
inadmissible pressure drop. equipped with separate gas analysis connection.
1.2.1.2 Compression chambers are to be designed to 1.2.2.7 All open penetrations for gas, measurements
allow at least two persons to pass in or out simultane- and analysis are to be protected by replaceable filters
ously through the locks without subjecting the other mounted on the inside of the chamber.
divers in the system to a change of pressure.
1.2.2.8 Each test chamber compartment is to be pro-
1.2.1.3 The living compartment of compression vided with separate connections for communications
chambers shall be so designed and equipped that the equipment. In addition, at least one blind flange each
occupants can stand upright and each diver is provided is to be fitted for power and data transmission.
with a bunk on which he is able to stretch out com-
fortably. A toilet and shower are also to be provided. 1.2.2.9 Where water partitions are fitted in wet test
The toilet and shower are to be located in a separate chambers, an access opening with a clear diameter of
space. Toilets with arrangements for the external dis- at least 800 mm must be provided. The water level
charge of human waste are to be equipped with suit- control system is to be so designed, that no water can
able interlocks to prevent pressure losses in the cham- penetrate into dry compartments in the event of pres-
ber system. sure variations.

1.2.1.4 The living compartment of compression 1.2.2.10 Test chambers are to be provided with drain-
chambers and other compartments used for decom- age connections at their lowest points. Sumps and
pression are to be provided with a lock through which other drains are to be protected to prevent impurities
provisions, medicines and equipment can be passed in being sucked in.
and out without subjecting the occupants of the cham-
ber to a change of pressure. 1.2.2.11 Water circuits for test chambers are to be
designed and constructed so that switching from high-
1.2.1.5 Locks are to be designed to prevent acci- pressure to low-pressure circuits cannot cause any
dental opening under pressure; if necessary, suitable inadmissible pressure drop in the test chamber. Fur-
interlocks are to be provided. thermore, such switching operations shall not cause
any unacceptable rise in pressure in low-pressure cir-
1.2.1.6 Each compression chamber compartment is to cuit.
be fitted with view ports so that, wherever possible, all
the occupants can be observed from outside. 1.2.2.12 Test chambers are to be provided with exter-
nal insulation compatible with the test conditions and
1.2.1.7 Wherever necessary, the view ports of com- with the environmental conditions at the locations
pression chambers are to be protected internally and where the simulator is installed.
externally against mechanical damage. View ports are
also to be protected against ultraviolet radiation and 1.2.3 Hatches and access openings
unacceptably high temperatures.
1.2.3.1 Hatches and mating devices in diving simu-
1.2.1.8 Each compression chamber compartment is to lators which are not sealed by pressure are to be
be adequately lit. equipped with a closing mechanism which precludes
I - Part 5 Section 3 F Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–9

opening under pressure. The closing mechanism is to 1.4 Principles of manufacture and construc-
be so designed that the correct position of closure is tion
clearly indicated before pressure is applied.
Pressure vessels for diving simulators are to be manu-
1.2.3.2 Means are to be provided to enable hatches to factured and constructed in accordance with Section 2,
be opened from both sides. C.1.4 of these Rules.

Hatch trunks are to be provided with pressure equal- 1.5 Calculations


izing valves.
Calculations relating to diving simulator pressure
Devices are to be fitted which hold hatches in the open vessels are to be performed in accordance with Sec-
position. tion 2, C.1.5 of these Rules.

Hatches which open or close under their own weight 1.6 Acrylic plastic windows
are to be so designed that divers are not endangered
when operating them. Acrylic plastic windows are to be designed and manu-
factured in accordance with Appendix B of these
1.2.3.3 Hatches and access openings for persons Rules.
should have a clear diameter of at least 500 mm, or at
least 700 mm in the case of test chambers. 2. Pressure vessels and apparatus and gas
bottles
1.2.3.4 The length of hatch trunks should not exceed
the trunk diameter. Pressure vessels and apparatus and gas bottles are to
be manufactured in accordance with the Rules for
1.2.3.5 For hatches in wet test chambers, the sealing Classification and Construction, Part 1 – Seagoing
groove and seal counterface should be made of non- Ships, Chapter 2 – Machinery Installations, Section 8.
corroding materials.

1.2.3.6 Hydraulically operated hatches have to meet


the following additional requirements: D. Pipes, Valves, Fittings and Hoses
– The hatches must be capable of being opened
manually if the hydraulic system fails. Pipes, valves, fittings and hoses for diving simulators
are to be designed and manufactured in accordance
– Steps must be taken to ensure that hatches which with Section 2, D. of these Rules.
open under their own weight if the hydraulic sys-
tem fails cannot endanger the divers.

– Steps must be taken to ensure that the opening E. Compressors


action can only be initiated after the pressure has
been equalized. Breathing gas compressors for diving simulators are to
be designed and manufactured in accordance with
– Operating elements fitted outside chambers are
Section 2, E. of these Rules.
to be arranged so that the operations of opening
and closing the hatch can be observed through
the view ports provided in the chamber.

The design and dimensions of the hydraulic F. Life Support Systems


system for internal hatches shall be compatible
with the specified working pressures and with
1. General
the boundary conditions of the compression
chamber system. The hydraulic fluid must be
suitable for use in the chambers and shall not 1.1 These Rules apply to all parts and compo-
under hyperbaric conditions release gas or va- nents of the system which are necessary to ensure the
pours which are toxic or capable of supporting life support and safe environment of the occupants of a
combustion. diving system.

1.3 Materials 1.2 The documents to be submitted to GL for


approval are listed in A.4.
The materials used for diving simulators are required
to comply with the provisions of Section 2, C.1.3 of 1.3 The necessary tests and markings are stated in
these Rules. A.5. and A.6.
Chapter 1 Section 3 F Rules for Construction of Diving Simulators I - Part 5
Page 3–10 GL 1998

2. Gas supply 2.2 Gas distribution

2.1 Gas storage facilities 2.2.1 General

2.2.1.1 The gas supply system shall be so designed


2.1.1 Each diving system is to be provided with a that the pressure in the living compartment of the
permanently installed gas storage facility or with a compression chamber can be raised at a rate of at least
suitable location for the storage of mobile gas bottles. 2 bar/min up to 2 bar and thereafter at a rate of
1 bar/min.
2.1.2 The capacity of the gas storage facility shall
be such that a sufficient number and quantity of gas 2.2.1.2 The gas venting system shall be so designed
mixtures are available for all planned diving opera- that the pressure in a compression chamber or diving
tions to ensure that an adequate volume of the appro- bell can be lowered to 1 bar at a rate of at least
priate gases can be supplied to all compression cham- 1 bar/min.
bers and divers at all operating depths under both nor-
mal and emergency conditions (for determination of 2.2.1.3 Sets of breathing apparatus activated by respi-
the minimum quantities of gas required, see: European ration which supply breathing gas to persons under
Diving Technology Committee: Guidance Notes for pressure and also remove the exhaust gas independ-
Safe Diving, Appendix 2, to Chapter 5, p. 70, Oct. ently of the chamber atmosphere are to be designed for
1984). a gas flow equivalent to 3 times the required breathing
rate per minute (AMV).
2.1.3 The emergency breathing gas supply is to be
stored separately in bottles which shall not be opened The required breathing rate per minute depends on the
for normal operation. activity to be performed and the environmental condi-
tions (where heavy work is performed in open water,
the rate may be as much as 75 operating li-
2.1.4 Wherever possible, the gas storage facility is tres/min/person).
to be housed in a separate building. Rooms for the
storage of oxygen must be constructed of components When designing the breathing mask gas supply and
having at least class F 30 fire resistance to DIN 4102. exhaust gas disposal system, the number or persons
simultaneously connected to the system is to be al-
2.1.5 The gas storage facility is to be separated lowed for as follows:
from adjoining rooms by fireproof partitioning (F 90
to DIN 4102) if these rooms are subject to a fire or ex- Quantity of breathing gas
plosion hazard. Number of persons
[operating litres/min]
1 1 x AMV x 3
2.1.6 The roofing of the gas storage facility must
have adequate resistance to airborne incandescent 2 2 x AMV x 1,8
particles and radiant heat. The floor covering must be 3 3 x AMV x 1,6
at least flame-retardant. 4 4 x AMV x 1,4
5 5 x AMV x 1,3
6 6 x AMV x 1,2
2.1.7 Gas store-rooms must be adequately venti-
7 7 x AMV x 1,1
lated. The exits are to be so arranged that it is possible
8 8 x AMV x 1,1
to quit the rooms quickly in case of danger.
z>8 z x AMV x 1,0

2.1.8 No combustible materials may be stored in


the gas storage facility. 2.2.1.4 The gas circulating systems are to be so de-
signed that the chamber conditions stated in B.3. are
2.1.9 Gas stores in the open must be established in maintained.
such a way that they are protected from mechanical
damage and the action of outside fires. The containers 2.2.1.5 Each compression chamber compartment and
must be readily accessible from all sides. The valves each diving bell is to be equipped with at least the
must be capable of being operated from a fixed control following gas systems:
point.
– 2 independent gas supply systems for compres-
sion which may deliver into a single inlet pipe
2.1.10 Gas storage facilities are to be safeguarded immediately at the chamber
against unauthorized entry. In addition, warning no-
tices are to be mounted prohibiting the introduction of – 1 chamber exhaust gas system
mobile fire loads as well as the use of open fires and
smoking inside the gas store. – 1 built in breathing system (BIBS)
I - Part 5 Section 3 F Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–11

– 1 mask exhaust gas system Such test chambers are also to be provided with purifi-
cation systems (welding gas absorbers) for keeping the
– 1 gas circulating system for maintaining a
chamber atmosphere breathable, inert and within the
breathable chamber atmosphere
permitted temperature limits, e.g. during welding op-
Where pure oxygen or gas containing more than 25 % erations. In addition to this, such test chambers must
O2 by volume is supplied to the chamber, a separate be equipped with a personal breathing system and
piping system is to be provided for this purpose. respirators independent of the chamber atmosphere.
Additional equipment is to be provided to enable not
2.2.1.6 Valves in gas systems are to be arranged so only the chamber atmosphere but also the breathing
that a leaking valve cannot cause any unintended mix- gases supplied to the divers to be permanently moni-
ing of gases and no oxygen or oxygen-like gas can tored directly at the mask when work or tests are being
penetrate into lines intended for other gases. Inter- carried out in a non-breathable atmosphere.
sections between oxygen and non-oxygen systems are
to be isolated by twin shutoff valves with a vent valve 2.4 Treatment and mixing of breathing gases
placed between them.
The use of closed breathing circuits, gas mixing sys-
2.2.1.7 Filters and automatic pressure reducers are to tems for direct breathing gas supply and helium re-
be fitted in such a way that they can be dismounted claim systems is subject to approval by GL.
without having to interrupt major gas supply lines.
2.2.1.8 All gas supply and exhaust lines are to be 3. Control and instrumentation
effectively protected against mechanical damage.
When routed through zones subject to fire hazard they 3.1 Central Control Position
shall, in addition, be provided with fireproof cladding.
3.1.1 Diving simulators are to be arranged and
2.2.2 Compression chambers equipped in a manner which enables the entire simu-
2.2.2.1 At least one breathing mask is to be provided lator operation to be centrally monitored.
for each occupant of each separately pressurized The Central Control Position must be equipped with
chamber compartment. all the necessary means for the surveillance, control
2.2.2.2 The masks are to be joined either perma- and coordination of the various operating functions.
nently or by plug connectors to the mask gas supply Measures are necessary to ensure that:
and exhaust system.
– the Central Control Position is adequately
2.2.2.3 The exhaust gas (exhalation line) side of the shielded from other service rooms (protection
masks is to be protected against any inadmissible pres- against noise and visual interference, separate
sure drop or inadmissible pressure difference. ventilation system, no access or thoroughfare to
2.2.2.4 The supply of gas to the chamber is to be other service rooms)
arranged so as to ensure that a homogeneous gas dis- – the Central Control Position is free from items of
tribution inside the chamber is achieved as quickly as equipment and components which do not belong
possible. to, or are not needed in the Central Control Po-
sition
2.3 Conditioning of chamber atmosphere
– the Central Control Position is provided with
2.3.1 Each compression chamber living compart- effective all-round fire protection
ment is to be equipped with an oxygen dosing device
and a chamber gas circulating unit in which the CO2 – the atmosphere in the Central Control Position is
can be absorbed and the air temperature and humidity regulated to provide optimum conditions for
can be regulated. The rate of circulation shall be such human beings and equipment
as to satisfy the conditions stated in Section 2, B.3. – the Central Control Position is designed on er-
gonomic principles and the main units are laid
2.3.2 Each diving simulator is to be equipped with
out and arranged in a manner compatible with
at least 2 chamber gas treatment units which are to be
the test work to be performed (e.g. relative posi-
so arranged that they can be switched to adjoining
tioning of the chamber control consoles)
chambers.
– the Central Control Position is provided with a
2.3.3 Test chambers for the performance of manned sufficiently secure emergency power supply
experiments in which gases, vapours, dust or fumes (electricity, compressed air)
injurious to health are generated are to be equipped
with extraction systems capable of aspirating the harm- – the Central Control Position is provided with a
ful substances as close as possible to their point of sufficiently bright emergency lighting system
origin. with a back-up power supply
Chapter 1 Section 3 F Rules for Construction of Diving Simulators I - Part 5
Page 3–12 GL 1998

– as far as possible, the pipes and cable runs in the 3.2.1.4 The instrumentation of compression cham-
Central Control Position are installed separately bers used exclusively for unmanned tests shall be
according to system so that faults in one system compatible with the test conditions.
cannot lead to the failure of others
3.2.1.5 The pressure gauges of compression cham-
– the Central Control Position has communication bers must give a reading accurate to ± 0,3 % of the full
links not only with the compression chambers instrument scale subject to a maximum deviation of
but also with the ancillary units and general op- 30 cm water column. All other pressure readings may
erations rooms be accurate ± 1 % of the full instrument scale.
– the Central Control Position contains the central
3.2.1.6 Inadmissible deviations from reference values
fire alarm station for the compression chamber
of the vital parameters shall actuate a visual and audi-
fire detection system, where such a system is in-
ble alarm at the Central Control Position. Automati-
stalled, as well as the release valves of the com-
cally actuated switching operations in the gas supply
pression chamber water spray extinguishing sys-
system and similar functions shall also trip such
tem
alarms.
– the Central Control Position is itself provided
with a fire detection system and with the means 3.2.1.7 Compression chamber compartments are to
for combating effectively a fire in the Central be equipped with pressure and temperature gauges
Control Position without endangering the safe which can be read from inside.
operation of the compression chamber system as
3.2.1.8 Pressure gauges connected directly to the
a whole
compression chamber system are to be fitted with a
– effective stops are taken to prevent operations in shutoff valve.
the Central Control Position from being im-
paired by telephones, the activation of alarms 3.2.2 Analyzers
and general noise.
3.2.2.1 Each diving simulator is to be equipped with
3.2 Instrumentation at least one oxygen and one CO2 analyzing system.

3.2.1 Indicating instruments 3.2.2.2 Throughout the entire period of operation, the
oxygen analyzer must give a reading accurate to at
3.2.1.1 The instruments for the surveillance, control least ± 0,015 bar partial oxygen pressure.
and operation of the diving simulator are to be
grouped and arranged in the Central Control Position 3.2.2.3 Throughout the entire period of operation, the
in accordance with the principles of safety technology CO2 analyzer must give a reading accurate to at least
and ergonomics. ± 0,001 bar partial CO2 pressure.
3.2.1.2 In the Central Control Position a separate
3.2.2.4 Compression chamber living compartments
control console is to be provided for each independ-
are to be equipped in addition with independent in-
ently operated compression chamber compartment.
struments for monitoring the oxygen and CO2 levels.
For test chambers, an additional independent control
stand should be placed in the immediate vicinity of the 3.2.2.5 Where gas mixtures other than air or helium-
test chambers. oxygen are to be used for diving, suitable additional
3.2.1.3 At least the following operating parameters equipment is to be provided for analyzing the gases
are to be displayed at the Central Control Position for used.
each manned compression chamber compartment:
3.2.2.6 Test chambers in which welding operations
– pressure or depth are performed are to be equipped with analyzers for
continuously monitoring the chamber atmosphere for
– temperature
impurities such as CO, NO, NOx, hydrocarbons and
– humidity ozone. It is necessary to ensure that the analyzers are
– partial oxygen pressure also able to monitor the chamber atmosphere of the
other compression chambers. Apparatus is also to be
– partial CO2 pressure provided for the analysis of the pure gases. The
breathing gas mixtures and the purified helium gases.
– pressure of connected breathing gas contain-
ers/bottles 3.2.2.7 The accuracy of the analyzer readings shall
– pressure at pressure reducer outlets be such that the discrepancy between the partial pres-
sure in the gas and the partial pressure readings on the
– oxygen content in supply lines to instrument does not exceed 10 %.
– chamber compartments
3.2.2.8 For diving simulators where the chamber
– breathing masks in chambers atmosphere is not subject to contamination as a result
I - Part 5 Section 3 G Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–13

of technical experiments, test tubes may be recognized 3. Communications equipment


as a suitable means of monitoring the chamber atmos-
phere for contamination. 3.1 Voice communication systems

3.3 Control equipment 3.1.1 Diving simulators are to be equipped with a


suitable communications systems allowing direct
3.3.1 The Central Control Position is to be communication between the control stand and:
equipped with controls for at least the following func-
– each compartment of compression chambers and
tions:
test chambers
– pressurization and pressure control of each inde- – test equipment control positions
pendently operated compression chamber com-
partment and each diving bell – test chamber control stands
– decompression of each independently operated – ancillary units
compression chamber compartment and each
diving bell – offices and service rooms (e.g. the operations
manager's office and mechanical and electrical
– pressure equalization between chamber com- workshops)
partments
3.1.2 Where diving simulators are operated with
– oxygen supply to the chamber compartments helium gas mixtures, each compression chamber com-
partment is to be connected to a helium speech un-
– control of gas supply to breathing marks scrambler. The speech unscramblers should be de-
signed for maximum noise suppression and automatic
– control of temperature and humidity in the com-
compensation of changes in signal level.
pression chambers
3.1.3 It is recommended that the Central Control
3.3.2 The control stand for the gas distribution Position be equipped to record all communications
system is to be provided with a mimic diagram show- with the divers.
ing the functions of the various valves and the differ-
ent gas lines marked in colour.
3.1.4 Voice communications between the compres-
sion chamber compartments and the Control Position
must be provided by a communication system with
loudspeaker which is permanently switched to "Re-
G. Automation and Communications Equip- ceive" at the control console. Switches for reversing
ment the direction of communication must be of the self-
resetting type. In addition, each compression chamber
compartment is to be provided with at least one head-
1. General set.

1.1 The following Rules supplement of GL Rules 3.1.5 A mains-independent telephone link must be
Part 1 – Seagoing Ships, Chapter 3 – Electrical Instal- provided in addition to the telephone system called for
lations are to be applied to the construction and appli- in 3.1.4.
cation of equipment for the surveillance and control of
diving simulators and their communications and TV 3.1.6 Electrically powered telephone systems are to
monitoring systems. be provided with a reliable power supply. This nor-
mally means that they are to be supplied from a stor-
1.2 The documents to be submitted to GL are age battery with a parallel-connected mains unit and
listed in A.4. battery charger supplied with energy in accordance
with Section 2, H.
1.3 The necessary tests and markings are stated in 3.1.7 In wet rooms microphone and receiver sys-
A.5. and A.6. Only components and units which have tems must be designed to prevent the penetration of
been approved 'by GL may be installed. water. Where this cannot be ensured by the design, the
penetration of water shall not render the equipment
2. Automation equipment permanently unserviceable.

Automation equipment for diving simulators is to be 3.1.8 The microphone and receiver in diver's masks
designed and constructed in accordance with Sec- and helmets are to be functionally separated from each
tion 2, G.2. of these Rules. other.
Chapter 1 Section 3 I Rules for Construction of Diving Simulators I - Part 5
Page 3–14 GL 1998

3.2 Television surveillance equipment 2. Structural fire protection

3.2.1 Diving simulators are to be equipped with a 2.1 Area of installation of the diving simulator
television surveillance system.
2.1.1 Buildings for diving simulators and their
3.2.2 The number of cameras and their angles of ancillary units are to be designed and constructed in
view shall be chosen to give, wherever possible, a accordance with the building regulations in force at the
complete picture of the whole interior of the diving site where the diving simulator is to be installed.
simulator. In test chambers, allowance is to be made
for the fact that the chambers may be partially filled 2.1.2 Diving simulators may only be installed and
with water and adjustable test equipment may obstruct operated in areas not subject to an explosion hazard.
the view.
2.1.3 The rooms in which the diving simulator, the
3.2.3 A sufficient number of TV monitors must be Central Control Position and the gas storage facility
provided. Each TV monitor must indicate clearly are installed are to be separated from other service
which compartment is being viewed at any time. rooms by floors and walls with class F 30 fire protec-
tion to DIN 4102. If the adjoining rooms are consid-
3.2.4 The image reproduced on the monitors must ered to be subject to a fire hazard, the relevant parti-
show up the necessary detail. tions are to be fireproof (F 90).
3.2.5 It is recommended that a video recorder is
2.1.4 The rooms in which diving simulators and
installed.
their ancillary units are installed are to be provided
with forced ventilation systems capable of effecting at
3.3 Other communications equipment least 8 changes of air per hour. The air must be aspi-
rated from an area not subject to an explosion hazard.
3.3.1 All compression chamber compartments are
to be provided with suitable alternative communica- The rooms are also to be equipped with an effective
tions equipment (e.g. a 3-button signalling system). smoke extraction system.

3.3.2 Diving simulators should be provided with 2.1.5 In the area of installation of the diving simu-
equipment for transmission of radio, television and lator, the gas storage facility and the Central Control
video programmes which can, if necessary, carry op- Position, sources of ignition and fire loads must be
erational telephone communications as priority traffic. reduced to a minimum. Wherever possible, materials
which are at least fire-retardant are to be used. Heat
insulation is to be made of non-combustible materials.

H. Electrical Equipment 2.2 Compression chamber interiors

Electrical installations and equipment for diving simu- 2.2.1 Wherever possible, all materials used in com-
lators are to be designed and constructed in ac- pression chambers must be at least flame-retardant.
cordance with Section 2, H. of these Rules. (For the purpose of these Rules, flame-retardant refers
to materials which do not spontaneously sustain com-
The electrical components and equipment to be in- bustion in a compressed air atmosphere of at least
stalled outside compression chambers must, as a 6 bar).
minimum requirement, conform to a recognized stan-
dard, e.g. VDE, DIN or IEC standards. 2.2.2 As far as possible, fire loads and sources of
ignition are to be avoided. Electrical heating appli-
ances and heaters are to be fitted with protection
against overheating.
I. Fire Protection
2.2.3 Components or materials are to be selected
1. General with a view to minimizing the acquisition of static
charges.
1.1 The following Rules apply to the fire protec-
tion of diving simulators built in accordance with the 3. Fire surveillance
Rules of GL.
3.1 Fire detection and alarm systems
1.2 The documents to be submitted to GL for
approval are listed in A.4. 3.1.1 The rooms in which diving simulators and
their ancillary units are installed are to be protected by
1.3 The necessary tests are stated in A.5. an automatic fire detection system.
I - Part 5 Section 3 J Rules for Construction of Diving Simulators Chapter 1
GL 1998 Page 3–15

3.1.2 The fire detection system must trip visual and with approved hand extinguishers. In each case, one of
audible signals in at least one permanently manned the portable extinguishers is to be mounted close to the
control room. entrance to the room concerned.

3.1.3 The fire alarm can be activated manually 4.1.5 Where the room in which the diving simulator
from the permanently manned control room or auto- is installed is also used wholly or in part as a work-
matically by the fire detection system. shop, the room in question is to be additionally
equipped with at least one mobile 50 kg dry extin-
3.2 Fire detection systems guisher.
3.2.1 Fire detection equipment such as the central
fire detection station, the detectors and the wiring of 4.2 In compression chambers
the detection loops must have the approval of GL.
4.2.1 Each compartment inside a compression
3.2.2 Fire detection systems must be constructed so chamber is to be equipped with suitable means of
that any faults, e.g. failure of the power supply, short- extinguishing a fire in the interior and such means
circuit or wire breakage in the detection loops or the shall be capable of applying the extinguishing agent
removal of a detector from its base, trip visual and quickly and effectively to all parts of the chamber.
audible signals in the central fire detection station.
4.2.2 The fire extinguishing system is to be de-
3.2.3 The installations and arrangement of fire signed and constructed in such a way that it is fully
detection and signalling systems are to conform to GL able to deal with any conceivable case of fire under all
Rules for Classification and Construction Part 1 – the environmental conditions for which the diving
Seagoing Ships, Chapter 3 – Electrical Installations, simulator is designed. Activation of the fire extin-
Section 9 and Chapter 4 – Automation. guishing system shall cause no inadmissible loss of
pressure in the chamber. The extinguishing system
4. Fire extinguishing equipment may be activated by hand.

4.1 Area of installation of the diving simulator 4.2.3 The preferred extinguishing agent is water.
Extinguishing agent with a toxic or narcotic effect are
4.1.1 The area of installation of the diving simula- not allowed.
tor and its ancillary units is to be equipped with a
water fire extinguishing system as well as with port-
able and mobile fire extinguishers and extinguishing 5. Other fire protection equipment
appliances.
The Central Control Position of the diving simulator is
4.1.2 The water fire extinguishing system is to be to be provided with at least one independent com-
fed by a wet 100 mm ID ring main in the building. The pressed-air respirator of approved design having an
ring main is to be fitted with hose connections in a way operating capability of at least 30 minutes and fitted
which ensures that a fire inside the building can be with equipment for voice communication with the
effectively and safely combated. Hose connections are divers.
to conform to DIN 14461, Part 3. Suitable hose boxes
(e.g. to DIN 14461, Part 1) containing hoses and noz-
zles are to be placed close to the hose connections.
In addition, a non-freeze water hydrant is to be placed J. Hyperbaric Evacuation System
close to the diving simulator operations building (e.g.
an underfloor hydrant to DIN 3221 or an above-floor 1. General
hydrant to DIN 3222).

4.1.3 In the case of diving simulators without a 1.1 Where a hyperbaric evacuation system per-
hyperbaric evacuation system, the compression cham- manently connected to the diving simulator is pro-
ber system is to be provided with means of cooling in vided, the following Rules are to be applied.
case of fire in the form of a permanently installed
water spray system with a capacity of at least 1.2 Where the evacuation chamber is also to be
10 A/m2/minute related to the projected horizontal area used as a compression chamber the relevant sections
of the Rules of Construction for Diving Simulators are
concerned. The water spray system must encompass at
also to be applied.
least all the living areas. These spray systems may be
activated and operated by hand.
1.3 The documents to be submitted to GL for
4.1.4 The rooms in which diving simulators and approval are listed in A.4. The necessary tests are
their ancillary units are installed are to be equipped stated in A.5.
Chapter 1 Section 3 J Rules for Construction of Diving Simulators I - Part 5
Page 3–16 GL 1998

2. Design principles chamber is to be provided with connections for exter-


nal supply and surveillance.
2.1 Evacuation chamber
2.1.7 The evacuation chamber must be equipped
2.1.1 The hyperbaric evacuation chamber is to be externally with regulating and control devices enabling
designed for the simultaneous rescue of all the divers a safe environment for the divers to be maintained.
in the diving simulator at the maximum operating
depth. At least one seat with safety harness is to be
2.1.8 The evacuation chamber is to be equipped
provided for each divers.
with a telephone system allowing communication with
2.1.2 The evacuation chamber is to be provided the divers.
with a lock for supplies.
2.1.9 The evacuation chamber is to be provided
2.1.3 The evacuation chamber is to be equipped with its own power supply enabling the electrical sys-
with view ports enabling all the occupants to be ob- tem to be kept operational for at least eight hours.
served from outside.
2.1.10 The evacuation chamber is to be so designed
2.1.4 The chamber connections for gas, water and that it can be operated in the open air.
electricity are to be designed for rapid coupling and
uncoupling.
2.1.11 The evacuation chamber is to be equipped
2.1.5 The evacuation chamber is to be adequately with a mating and handling system enabling it to be
lit. quickly and safely connected and disconnected and
conveyed to a position of safety without external
2.1.6 The evacuation chamber must be equipped power.
with an autonomous life support system enabling the
pressure, temperature and gas composition in the com- 2.1.12 The evacuation chamber is to be provided
pression chamber to be maintained for at least eight with attachment points enabling it to be hoisted by a
hours. The life support system or the evacuation standard crane.
I - Part 5 Section 4 A Rules for Construction of Diver Pressure Chambers Chapter 1
GL 1998 Page 4–1

Section 4

Rules for Construction of Diver Pressure Chambers

A. General Rules and Instructions 2.8 Test pressure


The excess pressure to which a component is sub-
1. Scope jected for test purposes.

1.1 The following Rules apply to diver pressure 2.9 Diver pressure chamber
chambers (deck compression, rescue chambers) which
are intended for the treatment or rescue of sick divers Pressure chamber intended for the treatment or rescue
under pressure in accordance with UVV "Taucherar- of sick divers under pressure in accordance with UVV
beiten" (VBG 39) (Accident Prevention Regulations "Taucherarbeiten".
for Work Performed by Divers), and which are con-
structed under survey of and in conformity with the 2.10 Rescue chamber
Rules of GL and are to be certified accordingly. They
also apply to all equipment necessary to the safe op- Pressure chamber intended for the transport of sick
eration of the diver pressure chambers. divers to a treatment chamber under pressure.

1.2 Diver pressure chambers, including their 2.11 Antechamber


ancillary equipment, which are constructed in accor-
dance with 1.1 may also be classified by GL on appli- Part of pressure chamber for the lock in and out of
cation by the operator. persons and equipment.

2. Definitions 2.12 Maximum permissible working pressure


The maximum permissible working pressure dictated
2.1 Breathing connection by safety considerations.
Connection between the demand breathing system and
the user's respiratory passages. 3. Documents for approval

2.2 Working pressure 3.1 General


The internal excess pressure in part of the system
3.1.1 Before the start of manufacture, plans and
intended to facilitate the performance of one or more
drawings of all components subject to compulsory
basic operations.
inspection are to be submitted to GL in triplicate.
2.3 Deck compression chamber 3.1.2 The drawings must contain all the data neces-
Diver pressure chamber intended for the treatment of sary to check the design and the loading of the equip-
sick divers under pressure. ment. Wherever necessary, calculations relating to
components and descriptions of the system are to be
2.4 Pressure chamber submitted.

Pressure vessel for human occupancy. 3.1.3 Once the documents submitted have been
approved by GL, they become binding on the manu-
2.5 Compressed air storage facturer. Any subsequent modifications require GL's
consent before they are implemented.
Total quantity of stored compressed air.
3.2 Pressure chambers, pressure vessels and
2.6 Main chamber apparatus
Part of pressure chamber used for carrying out treat-
ment under pressure. 3.2.1 Drawings are to be submitted of pressure
chambers, pressure vessels and apparatus giving full
2.7 Demand breathing system details for appraising the safety of the equipment.
Component drawings of the equipment of pressure
Respiration-controlled metering system. chambers and vessels are also to be submitted.
Chapter 1 Section 4 A Rules for Construction of Diver Pressure Chambers I - Part 5
Page 4–2 GL 1998

3.2.2 Plans, block diagrams and descriptions, in- 4.3 Compression chamber windows
cluding lists of valves and fittings are to be submitted
for the supply, operating and control systems. 4.3.1 Each compression chamber window must
undergo a hydraulic pressure test which may be per-
formed after installation together with the compres-
4. Test and trials sion chamber or in a testing device. The test pressure
shall normally be equivalent to 1,5 times the design
4.1 General pressure.

4.3.2 After the pressure test, windows may exhibit


4.1.1 Diver pressure chambers and their ancillary no scratches, cracks or permanent deformation.
equipment are subject to preliminary examination,
constructional and materials tests as well as to pres-
sure and tightness tests and trials. All the tests called 4.4 Compressors
for in the following paragraphs are to be performed Compressors are to be subjected to a tightness test at
under GL supervision. their maximum working pressure. In addition, a per-
formance test is to be carried out in which the final
4.1.2 After the diver pressure chambers and ancil- moisture content and any possible contamination of
lary equipment have been installed on board, the sys- the compressed gas are to be determined. The safety
tem is to be subjected to functional test, and all items devices are to be checked.
of safety equipment are to be tested except where this
has already been done on the manufacturer's premises 4.5 Piping systems
in the presence of GL's representatives.
On completion of manufacture but before insulation or
painting, all piping systems are to be subjected by the
4.2 Diver pressure chambers, pressure vessels manufacturer to a hydraulic pressure test at 1,5 times
and apparatus the design pressure and are to be cleaned. A certificate
in accordance with EN 10204-2.2 is to be issued to
4.2.1 On completion, pressure chambers, pressure this effect.
vessels and apparatus are to be subjected to a con-
structional test. 4.6 Control, communications and safety
equipment
The constructional test includes verification that the
vessel conforms to the approved drawings and that the 4.6.1 Indicating and monitoring instruments are to
workmanship is satisfactory. All components must be be tested for the accuracy of their readings and their
accessible to allow adequate inspection. limit value settings.

4.2.2 The materials test certificates for the materi- 4.6.2 Automatic monitoring systems are to be
als used and the reports on the non-destructive testing checked for satisfactory performance under service
of welds are to be submitted together with the results conditions.
of inspections of workmanship and evidence of the
heat treatments applied, where appropriate. 4.6.3 Normal and emergency communications
equipment is to be subjected to a functional test.
4.2.3 A hydraulic pressure test is to be performed
prior to preservation treatment of the vessel. Each 4.6.4 Proof is required of the autonomy of the
pressure chamber compartment is to be tested indi- safety systems.
vidually. The walls may exhibit no permanent defor-
mation or leakage. 4.7 Electrical equipment

4.7.1 All electrical systems and equipment are to


4.2.4 The test pressure shall normally be equivalent be inspected and tested before the diver pressure
to 1,5 times the maximum permissible working pres- chamber is put into service.
sure.
4.7.2 Electrical protective devices are to be
4.2.5 The gas storage facility and the diver pressure checked; in addition, an insulation test is to be per-
chamber including the gas piping are to be subjected formed on the electrical equipment in the pressure
to a tightness test using air at the maximum permissi- chambers.
ble working pressure.
4.8 Fire protection
4.2.6 Gas bottles are to be checked to determine
whether they bear the test date and marking applied by 4.8.1 The fire behaviour of the chamber equipment
a recognized expert and whether the test period has is to be checked by reference to the relevant test cer-
not yet expired. tificates and symbols, as applicable.
I - Part 5 Section 4 B Rules for Construction of Diver Pressure Chambers Chapter 1
GL 1998 Page 4–3

4.8.2 A check is to be made as to whether the elec- B. Principles for Design and Construction
trical heating systems and heaters are fitted with pro-
tection against overheating.
1. General principles
4.8.3 Fire extinguishing appliances are to be sub-
jected to a functional test. 1.1 Diver pressure chambers are to be designed
and built to ensure safe operation and facilitate proper
maintenance and the necessary surveys.
4.9 Mating systems
1.2 All parts of diver pressure chambers are to be
A check is to be carried out to verify that the bayonet
designed, constructed and mounted in such a way as to
flange connection cannot be subjected to pressure until
facilitate cleaning and disinfection.
the inner ring of the bayonet mechanism has turned
fully home, and that the bayonet flange connection
cannot be opened until the pressure has been relieve. 1.3 Diver pressure chambers must be so designed
that a working pressure of at least 5 bar can be reached
Furthermore, the pressure relief device of the flange and maintained without fail. Provision must be made
connection is to be checked. for raising the working pressure form 0 bar to 5 bar
within 6 minutes. A pressure reduction from 0,4 bar to
0,2 bar must be possible within one minute.
5. Marking
1.4 Diver pressure chambers must be equipped
5.1 All diver pressure chambers are to be fitted in with a suitable safety device which automatically
a prominent position with a permanently mounted prevents the maximum permissible working pressure
name plate containing at least the following details: from being exceeded by more than 10 %.

– name of manufacturer In addition, diver pressure chambers must be equipped


with a reliable safeguard against any inadmissible
– serial number and year of manufacture pressure drop.

– maximum permissible working pressure 1.5 Safety valves must be so designed that they
respond only when the maximum permissible working
– test pressure pressure has been exceeded and close before the pres-
sure drops below this level.
– capacity (in litres) (of each chamber compart-
ment) Safety valves are to be mounted in such a way that
they are protected from mechanical damage and acci-
– maximum permissible number of persons (in the dental operation.
case of deck compression chambers)
The connection of safety valves on diver pressure
– date of test and test stamp chamber are to be so designed that they cannot be
sealed off unintentionally.

5.2 All other pressure vessels and gas bottles are


1.6 Instead of the pressure relief device, equip-
to be prominently and permanently marked with the
ment may be fitted which automatically interrupts the
following details:
pressure supply when the maximum permissible work-
ing pressure is exceeded and simultaneously trips a
– name of manufacturer
visual and audible alarm. The alarm signal shall be
such that it is at all times clearly perceptible to the
– serial number and year of manufacture operating personnel.
– capacity (in litres)
1.7 The door opening of diver pressure chamber
– test pressure (bar) shall allow the passage of a patient laying flat on a
stretcher to DIN 13024. Round door openings must
– empty weight (of gas bottles) have a clear diameter of at least 0,70 m. Doors fitted
with an interlock must be capable of being operated
– date of test and test stamp from both sides when the pressure has been equalized.

Diver pressure chambers operated on ships, floating


5.3 All valves and fittings, operating elements, structures or in containers have to be fitted with a
indicators and warning devices are to be clearly and device that avoids swinging of the doors also in the
plainly marked. open position.
Chapter 1 Section 4 B Rules for Construction of Diver Pressure Chambers I - Part 5
Page 4–4 GL 1998

1.8 Diver pressure chambers are to be fitted with 2.1.7 Each person to be accommodated must be
observation windows giving a good view of all the provided in the main chamber with a source of oxygen
occupants of deck compression chambers and of the supplying at least 75 A/min at atmospheric pressure.
head of the occupant of rescue chambers. The win- The oxygen is to be supplied to the breathing connec-
dows must be made of acrylic plastic. tion via a demand breathing system at the pressure
prevailing in the chamber. The exhaled gas may not be
1.9 Each pressurized gas supply and exhaust line introduced in the chamber atmosphere.
must be fitted with a shutoff valve immediately at the
pressure chamber wall. This shutoff valve may be
2.1.8 Main chamber and antechamber must be
deleted if the connection between the pressure cham-
separately supplied with air and oxygen for breathing.
ber and the line valve is short and well protected.
Means must be provided to prevent the pressure in the
antechamber exceeding that in the main chamber.
1.10 Diver pressure chambers are to be so de-
signed and equipped that the noises in the chamber do
2.1.9 The main chamber must be equipped with
not exceed a peak level of 90 dB(a) measured as an
heating. The heating capacity must be equivalent to at
A(pulse) acoustic pressure level to DIN 45645, part 1,
least 0,25 kW per m3 of chamber volume and must
or an evaluation level (to DIN 45645, part 1, over 3
have at least 3 settings.
hours) of 70 dB(A). These values apply to the head
level of persons seated in the deck compression cham-
ber and to the head area of the person in the rescue 2.1.10 The main chamber is to be provided with a
chamber. supply lock. The dimensions of the supply lock must
not be less than 200 mm in diameter and 300 mm in
length. The means of closure of the supply lock must
1.11 The interior equipment of diver pressure be interlocked in such a way that they can on no ac-
chambers should be made of materials which are at count open simultaneously. Pressure equalizing aper-
least flame-retardant (class B1 to DIN 4102 or to ISO tures must be safeguarded to prevent them from being
6941). The use of plastics for the interior equipment of rendered ineffective by obstructions. The pressure in
chambers is to be kept to a minimum. the supply lock chamber must be indicated by a pres-
sure gauge mounted externally close to the lock con-
2. Deck compression chambers trols.

2.1 General requirements 2.1.11 The vessel wall of the main chamber must be
fitted with at least one DN 80 blind flange for later
2.1.1 Deck compression chambers must comprise installations.
at least a main chamber and an antechamber. They
should also be equipped with a connecting flange for 2.1.12 The main chamber must be provided with
rescue chambers subject to DIN 13256, Part 6, easily accessible means of mounting a pressure gauge
(NATO flange). for test purposes.

2.1.2 The inside diameter of the deck compression 2.1.13 The configuration of the antechamber shall
chamber should be at least 1,48 m. be such that it can accommodate two seated persons.

2.1.3 The configuration of the main chamber shall


2.2 Compressed air and oxygen supply
provide space for one person laying down and two
persons seated.
2.2.1 A supply of compressed air is to be provided
The number of occupants allowed in the main cham- for the operation of the deck compression chamber
ber is to be stated on a plate prominently and perma- which is sufficient to
nently fixed above the entrance.
– raise the pressure in the main chamber once and
2.1.4 Seats must be provided in sufficient number in the antechamber twice from 0 bar to 5 bar ex-
for the number of persons admitted. Seats must be cess pressure
designed to provide each person with a seat width of
– hold an overpressure of 5 bar in the main cham-
at least 0,5 m and a seat depth of at least 0,4 m and
ber for 30 minutes with an adequate rate of air-
must avoid loss of body heat due to contact with cold
change
surfaces.
– hold an overpressure of 1 bar in the main cham-
2.1.5 After deduction for interior equipment, the ber for 300 minutes with an adequate rate of air-
chamber must provide at least 0,5 m3 of space for each change
person to be accommodated.
The design of the air-change system is adequate if it is
2.1.6 The main chamber must be equipped with capable of exchanging 40 litres of air per minute per
means of changing the air. person at working pressure.
I - Part 5 Section 4 B Rules for Construction of Diver Pressure Chambers Chapter 1
GL 1998 Page 4–5

In the main chamber it must be possible to effect the 2.4.2 The pressure in each antechamber and main
aforementioned pressure rise within 6 minutes. chamber must be indicated by at least one class 0,25
pressure gauge.
2.2.2 The air supply system is also to be equipped
with an air compressor at least capable of meeting the 2.4.3 A facility must be provided for continuously
air-change requirements stipulated in 2.2.1. recording the pressure in the main chamber. The sys-
tem must register pressure variations of 0,03 bar and
time intervals of 1,0 min in a manner which enables
2.2.3 The capacity of the air compressor called for
the data to be evaluated. The pressure variations over
in 2.2.2 may be reduced provided that the deck com- the previous 2 hours must be visible.
pression chamber is equipped with an efficient CO2
absorber and suitable quantities of lime are carried. 2.4.4 The console is also to be fitted with indica-
tors registering the following:
2.2.4 Notwithstanding 2.2.2 an air compressor may
be dispensed with if an additional emergency air sup- – the pressure in the compressed air storage con-
ply is carried in compressed air containers which cor- tainers
responds to at least 50 % of the quantity of air speci- – the pressure in the oxygen storage containers
fied in 2.2.1.
– the air-change flow rate
2.2.5 The air supply system is to be provided with – the inside temperature in the main chamber
an additional inlet for compressed air.
– the volumetric concentration or partial pressure
2.2.6 The air supplied to the deck compression of the oxygen
chamber must conform at least to the purity require-
ments specified in EN 12021 "Compressed Air for 2.4.5 A clock with a second hand, independent of
Breathing Apparatus". the mains supply, must be mounted where it can be
seen by the operator at the control console. Clocks
with a digital display as the sole indicator are not per-
2.2.7 For oxygen treatment a supply of oxygen of mitted.
at least 20 m3 has to be provided.
2.5 Communications
2.3 Electrical equipment
2.5.1 A communication system with loudspeaker
2.3.1 All electrical equipment including lighting must be provided between antechamber and control
must conform to DIN 57100 part 706/VDE 0100 part console and between main chamber and control con-
706 and VDE 0100. sole. The communication system must be permanently
switched to "Receive" on the control console, and
2.3.2 All electrical equipment is to be safeguarded reversal of the direction of communication shall be
to prevent overheating. possible only by self-resetting switches.

2.5.2 A telephone link independent of the mains


2.3.3 The lighting in the antechamber and main
supply must be provided in addition to the communi-
chamber of deck compression chambers must provide
cation system called for in 2.5.1.
a nominal illuminance of at least 200 lux at the seating
level. It must be possible to illuminate lying surfaces 2.5.3 At least one emergency signalling system
with an illuminance of 500 lux (e.g. by adjustable each must be installed between the antechamber and
spotlight). the control console and between the main chamber
and the control console. The signal buttons in the
2.3.4 An emergency power supply must be pro- chambers must be clearly marked and easily accessi-
vided to illuminate the deck compression chamber, the ble.
control console and all consumers necessary to opera-
tional safety. In case of mains failure, this must take 2.6 Fire protection equipment
over the power supply to the consumers and must
ensure continued operation for at least 5 hours. Deck compression chambers are to be equipped with
suitable fire-extinguishing appliances (e.g. deluge
2.4 Controls and indicating instruments system, bucket spray, fire-extinguishing blanket).

2.4.1 The controls and indicating instruments for 3. Rescue chambers


the antechamber and main chamber must be grouped
in one control console. They must be clearly marked, 3.1 For consideration of safety the use of one-
arranged according to function and must be illumi- man rescue chambers should no longer be envisaged.
nated in accordance with DIN 5035, part 2. The nomi- In addition to the sick diver the rescue chamber should
nal illuminance required is 300 lux. be capable of accommodating a non-injured person.
Chapter 1 Section 4 B Rules for Construction of Diver Pressure Chambers I - Part 5
Page 4–6 GL 1998

Apart from the General Principles according to 1. the 3.10 The controls and indicating instruments must
following requirements apply. continue to be capable of being operated or observed
when the rescue chamber is coupled to the deck com-
3.2 Rescue chambers must have an inside length pression chamber. They are to be located close to a
of at least 2,0 m and must have an access port with a window in the vessel in such a way that the operating
clear diameter of at least 0,5 m. personnel can observe the occupants of the rescue
chamber without having to change position.
3.3 It must be possible to lodge the diver in the
rescue chamber securely enough to prevent injury due 3.11 It must be possible to adjust the flow of re-
to motions during transfer. Suitable restraints are to be newal air to at least 25 litres per minute per person
provided. (measured at the chamber pressure) at each pressure
stage.
3.4 Rescue chambers must regarding their total
weight and dimensions be designed such that they can 3.12 For the purpose of scavenging rescue cham-
be carried or moved otherwise by helpers over short bers may be operated only with breathing air meeting
distances and loaded onto a transport vehicle without the purity requirements as per EN 12021, "Com-
the assistance of a crane. pressed Air for Breathing Apparatus". Connections for
sources of oxygen as per 2.1.7 are to be provided.
3.5 Rescue chambers must be equipped with
lifting handles, at least two fastening eyes and the
necessary hoisting sling. 3.13 A communication system with loudspeakers
must be provided between the inside of the rescue
chamber and the outside controls. On the outside, the
3.6 Rescue chambers are to be fitted with a bayo- system must be permanently switched to "Receive",
net flange connection as per DIN 13256, Part 6, to and reversal of the direction of communication shall
enable them to be coupled to a deck compression only be possible by the operation of a self-resetting
chamber. switch mounted on the outside. On the outside the
communication system must also be equipped with a
3.7 The design must ensure that, in normal op- head-set.
eration, the means of closure of the rescue chamber
cannot be opened until it is subjected to the same pres-
sure from inside and out. 3.14 Rescue chambers are to be provided with a
supply lock as per 2.1.10.
3.8 Rescue chambers are to be equipped with
compressed air containers with at least 8000 litres air 4. Materials
supply.
The materials used for walls subjected to pressure are
This supply of air is intended for the sole purpose of subject to the requirements set out in Section 2, C. of
renewing the atmosphere in the event of an interrup- these Rules.
tion of the normal air supply. Adequate renewal of the
atmosphere means 25 litres per minute per person
measured at the maximum pressure in the vessel. 5. Manufacture

3.9 Rescue chambers must be equipped with at 5.1 The manufacture of diver pressure chambers
least the following controls and monitoring instru- is subject to the requirements set out in Section 2, C.
ments: of these Rules with the following exceptions.
– air inlet valve
5.2 A weld factor of 0,85 is sufficient for welded
– exhaust air valve
seams on diver pressure chambers provided that at
– pressure gauge (class 0,25) for chamber pressure least all intersections of longitudinal and circumferen-
tial seams are subjected to X-ray inspection.
– pressure-reducing valve, with inlet and outlet
pressure gauge, to which the compressed air
containers called for in 3.8 are connected 5.3 Flat disk windows which have only been
machined professionally on the edges do not have to
– an additional means of connection, with shutoff be subjected to heat treatment after manufacture.
device, comprising a suitable high-pressure hose
at least 1,5 m in length for connecting the opera-
tional compressed air supply to the pressure-re- 6. Calculations
ducing valve
Calculations relating to diver pressure chambers are
– measuring instrument for monitoring of the subject to the requirements set out in Section 2, C.1.5
oxygen volume concentration or partial pressure of these Rules.
I - Part 5 Appendix A B Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–1

Appendix A

Calculation and Pressure Hulls under External Pressure

A. Introduction assumption that the behaviour of the material is


elastic.
A method of calculation for designing the pressure
hulls of submersibles is described below, which can be – at the collapse pressure, the stress may lie in the
used for the three loading conditions: elastic or the elastic-plastic range of the mate-
rial.
– nominal diving pressure pN
In the elastic-plastic range, use of the method requires
– test pressure pP the determination of values by a process of iteration.
– collapse pressure pZ The modulus of elasticity E and the Poisson's ratio ν
shall be substituted by the values E' and ν' according
to investigate the stresses in the pressure hull and the to G. The corresponding iteration techniques are
corresponding states of stability: shown as program sequences at the end of the Appen-
– asymmetric buckling between stiffeners (axial dix (Figs. 9 - 11).
buckling) When calculating a pressure hull use is to be made of
– symmetric buckling between stiffeners (circular design data corresponding to the proposed service
buckling) conditions of the submersible in accordance with
Chapter 2 – Submersibles, Section 4, E. of these
– general instability of pressure hull design Rules.
– tripping of stiffening rings It is advisable to use a programmable computer for
– buckling of dished ends. performing the calculations.

The method of calculation presented takes limited Pressure hulls subjected to internal overpressure are,
account of fabrication relevant deviations from the in addition to be designed in accordance with GL
ideal shape of the shell (out-of-roundness). Methods Rules for the Classification and Construction, Part 1 –
of verifying the roundness of hull shells are also de- Seagoing Ships, Chapter 2 – Machinery Installations,
scribed. Section 8.

Conical shells are calculated in sections, each of


which is treated as a cylindrical shell.
Overall collapse of the design is regarded as buckling B. Stiffened and Unstiffened Cylindrical
of the hull structure between bulkheads or dished Shells
ends.
With regards to the stresses in the pressure hull the 1. General
permissible values are those stated in Chapter 2 – For the loading conditions mentioned in A. Cylindri-
Submersibles, Section 4, E. cal shells are to be checked for excess stresses and
For the states of stability described, proof is required asymmetric and symmetric buckling.
of sufficient safety in respect of the particular form of The method of calculation presented below is for stiff-
damage concerned. ened cylindrical shells. In the case of unstiffened cy-
When using the method of calculation it is to be re- lindrical shells with dished ends, the calculations are
membered that both elastic and elastic-plastic behav- performed in a similar manner, the cross-sectional
iour can occur in the materials of the shell structure. area of the ring stiffener being A = A1 = 0 and the
spacing between stiffeners being defined by the ends.
It is generally the case that: Where the spacing between stiffeners is defined by
dished ends 40 % of the depth H of each dished end is
– at nominal diving pressure, the stress is within to be added to the cylindrical length (see Fig. 1). The
the purely elastic range of the material; "general stability" state is considered in C.3.3.
– at test pressure, the stress may lie at the com- for the calculation of buckling in the elastic-plastic
mencement of the elastic-plastic range of the
range the modulus of elasticity E and the Poisson's ν
material;
is determined by applying formulae (65) - (68) and by
However, calculations relating to the permissi- means of the stress σi formula (1) in the centre of the
ble stress being exceeded can be based on the section and the centre of the plate.
Chapter 1 Appendix A B Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–2 GL 1998

The calculations allow for an out-of-roundness of the σϕ = σo (1 − C10 ⋅ F2 ± ν ⋅ C10 ⋅ C11 ⋅ F4 ) (2b)
shell of maximum u = 0,005. If larger tolerances are
planned, or if the method of measurement described in
H.1 results in greater out-of-roundness values, then the In the area of stiffening the following applies:
permissible pressure is to be checked in accordance
1 
with H.2. σ x = σo  ± C10 ⋅ C11 ⋅ F3  (2c)
2 
2. Stresses in the cylindrical shell
σϕ = σo (1 − C10 ± ν ⋅ C10 ⋅ C11 ⋅ F3 ) (2d)
The stress intensity (at the centre of the plate at mid-
bay position between ring stiffeners) is determined by
applying formulae (1) - (14).  
4  cosh 2 C8 − cos 2 C9 
In formulae (2a) to (2d) the bending component is F1 = (3a)
C5  cosh C8 ⋅ sinh C8 + cosC9 ⋅ sin C9 
expressed by the plus sign on top for the outside of the  C6 C7 
cylindrical shell and by the minus sign below for the
inside. The stresses in the centre of the plate are de-
termined by omitting of the expressions after the  cosh C8 ⋅ sin C9 + sinh C8 ⋅ cosC9 
=  cosh C 7⋅ sinh C 
C C6
plus/minus signs. F2 (3b)
 8 8 + cos C9 ⋅ sin C9 
 C6 C7 
σi = σ x 2 + σ ϕ 2 − σ x ⋅ σϕ (1)
 − cosh C8 ⋅ sinh C8 + cos C9 ⋅ sin C9 
p⋅R 3  C6 C7 
F3 = (3c)
σo = −
s
(2)
(1 − ν )2  cosh C8 ⋅ sinh C8 + cosC9 ⋅ sin C9
 C6 C7

In the centre of the section the following applies:


 cosh C8 ⋅ sin C9 − sinh C8 ⋅ cosC9 
3  C7 C6 
1  F4 = (3d)
σx = σo  ± C10 ⋅ C11 ⋅ F4 
2 
(2a)
(1 − ν )2  cosh C8 ⋅ sinh C8 + cosC9 ⋅ sin C9
 C6 C7

L3

L2 L2 L2

ϕ
L1 s
s
s

0,4 H
0,4 H
R

R
R

H H

Fig. 1 Spacing between stiffeners in pressure vessel subject to external pressure


I - Part 5 Appendix A B Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–3

R2 4. Asymmetric buckling
A = A1 ⋅ (4)
R o2 The buckling pressure pn is calculated with formulae
(17) - (19) for the integer value n ≥ 2 corresponding to
C5 = α ⋅ L1 (5) the lowest value of pn. The relevant stresses of the
centre of the plate are determined in accordance with
1 2.
C6 = 1− G (6)
2 The program sequence (see Fig. 9) shows the method
of calculation used to determine the buckling pressure
1 pn in the elastic-plastic range.
C7 = 1+ G (7)
2
E ⋅ s ⋅βn1
pn = (17)
C8 = C5 ⋅ C 6 (8) R

= C5 ⋅ C7  2
( ) 
−2 2
C9 (9) s 2 ⋅ n 2 −1 + λ12
 n  
 +  +
( )
 λ 2 1 
 ν A  1  12 ⋅ R 2 ⋅ 1 − ν 2 
1 − 2  ⋅ s ⋅ L βn1 = (18)
C10 =
A

b 
 1
b 
(10) (
n 2 −1 + 0,5 ⋅λ12 )
+ + 1 −  F1
s ⋅ L1 L1  L1 
π⋅ R
λ1 = (19)
L1
0,91
C11 = (11)
1− ν 2
5. Provision against asymmetric buckling

2 ⋅ s2 ⋅ E The buckling pressure for the three loading conditions


p* = (12) is obtained from formula (17). Sufficient safety
(
R 2 ⋅ 3⋅ 1− ν2 ) against asymmetric buckling is provided if the condi-
tions (20a, b, c) are met.
p p n ≥ p N ⋅ Sk
G = (13) (20a)
p* (for the nominal diving pressure load condition)

α = 4
(
3⋅ 1− ν 2 ) (14)
p n ≥ p P ⋅ Sk ' = p N ⋅ S1 ⋅ Sk '
(for the test diving pressure load condition)
(20b)

s2 ⋅ R 2
pn ≥ pZ = p N ⋅ S2 (20c)
σϕ (for the collapse pressure load condition)
Ko = (15)
σx
6. Symmetric buckling
3. Provision against excess stresses The buckling pressure pm is calculated with formulae
(21) - (33) and (15) for the lowest integer value of m
The stress intensity for the three loading conditions is
at which conditions (33) is met. The values Es and Et
obtained from formula (1). Sufficient safety against
are determined in accordance with G. The relevant
exceeding the permissible stress is provided if the
stresses of the centre of the plate are calculated in
conditions (16a, b, c) are met. In formulae (2a) to (2d)
accordance with 2. In the elastic range Es = Et = E and
where load p = pZ the binding component can be dis-
regarded. ν' = ν.
The program sequence (see Fig. 10) shows the method
k = ≥ σi ⋅ S (where p = p N ) (16a) of calculation used to determined the buckling pres-
sure pm in the elastic-plastic range.
k = ≥ σi ⋅ S' (where p = p P ) (16b)
 α ⋅ L  2 1  π⋅ m  2 
k = ≥ σi (where p = p Z ) = p **⋅ Co ⋅   
1 1
(16c) pm  + ⋅ (21)
 π⋅ m  4  α1 ⋅ L1  
 
The program sequence (see Fig. 9) shows the method
of calculation used to obtain, for the loading condi-
tions collapse pressure, the stress intensity and the 2 ⋅ s2 ⋅ Es
p ** = (22)
maximum permissible pressures for the permissible
stresses. (
R 2 ⋅ 3 ⋅ 1 − ν '2 )
Chapter 1 Appendix A C Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–4 GL 1998

C. Ring Stiffeners
C1 ⋅ C2 − ν '2 ⋅ C32
Co = (23)
1 − ν '2 1. General
It is the purpose of ring stiffeners to reduce the buck-
H 2 ⋅ H4 ling length of cylindrical shells. A distinction is made
C1 = 1− 2 (24)
H1 between "heavy" and "light" ring stiffeners. "Heavy"
ring stiffeners are stiffeners which are able to reduce
the significant mathematical length of the pressure
H 32 ⋅ H 4
C2 = 1− (25) hull as this relates to the failure described in 2.3. The
H1 dimensions of "heavy" stiffeners are not to be smaller
than the "light" stiffeners.
H 2 ⋅ H3 ⋅ H 4 For a terminal section, the length to be used is that
C3 = 1 + (26)
ν ' ⋅ H1 between the end and the stiffener. (In the case of
dished ends, the buckling length is to take account of
the instruction in B.1 and Fig 1.)
H1 = 1 + H 4 ⋅  H 2 2 − 3 ⋅ (1 − ν '2 )  (27)
  For the loading conditions mentioned in A., stiffeners
are to be designed for safety against excess stresses,
H2 = ( 2 − ν ') − (1 − 2ν ') K o (28) buckling and tripping. Unreinforced cut-outs in the
girth or web are to be considered for calculation.

H3 = (1 − 2ν ') − ( 2 − ν ') K o (29)


2. "Light" stiffeners

Et 2.1 Stresses in "light" stiffeners


1−
Es
H4 = (30) The stresses are calculated using formulae (4), (14),
(
4 ⋅ 1 − ν '2 ⋅ K1 ) (35 - (37) and the values of pn1 and n according to 2.3.
If n = 2 determined also n = 3 has to be calculated. In
formula (37), L = L1. Where the distances L1 to the
K1 = 1− K o + Ko2 (31) two adjoining stiffeners are unequal, the calculation
shall make use of the arithmetic mean value of both
distances. In the elastic-plastic range the values E and
 C  C 2  ν are replaced by E' and ν' respectively. The elasticity
3⋅  2 −  v '⋅ 3  
 C1  C1   modulus E' and the Poisson's ratio ν' are calculated in
α1 =
4
  (32) accordance with G. In relation to stress σf.
s2 ⋅ R 2
The program sequence (see Fig. 11) shows the method
of calculation in the elastic-plastic range.
α1 ⋅ L1 m
≤ ( m +1)
( )
(33)
π 2 p ⋅ R 2 ⋅ 1 − ν2
σf = − (35)
 A 
7. Provisions against symmetric buckling R1 ⋅  s + 
 b + 2α⋅ N 
The buckling pressure pm for the collapse pressure

( )
condition is obtained from formula (21). Sufficient
safety against symmetric buckling is provided if the p ⋅ n 2 −1 ⋅ E ⋅ e 2 ⋅ U
σfb = ± (36)
conditions (34a, b, c) are met.
( pn − p ) ⋅ R o2
pm ≥ p N ⋅ Sk (34a)
cosh ( α ⋅ L ) − cos ( α ⋅ L )
N = (37a)
pm ≥ p P ⋅ Sk ' = p N ⋅ S1 ⋅ Sk ' (34b) sinh ( α ⋅ L ) + sin ( α ⋅ L )

pm ≥ pZ = p N ⋅ S2 (34c) N = 1for α ⋅ L > 5,5 (37b)


I - Part 5 Appendix A C Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–5

Le
b

e1
ew = b

s
ew

e
dw

h
dw

e2
df

df b
ef

ef

R
R0
R1
A1

Area for which Ie is calculated

Fig. 2 Stiffeners

2.2 Provision against excess stresses


p1 =
( n −1) ⋅ E ⋅ I
2
e
(42)
For the three loading conditions, formulae (35) and R o ⋅ L1
3

(36) give the stresses σf and σfb, the absolute values of


which are related to the yield strength k in conditions
p n1 = po + p1 (43)
(38a, b, c).

k ≥ σf ⋅ S + σfb ⋅ Sk (for p = p N ) (38a) A1 ⋅ e2 L e ⋅ s3


Ie = A
+ I1 + (44)
1 + L 1⋅s 12
e
k ≥ σf ⋅ S' + σfb ⋅ Sk ' (for p = p P ) (38b)
Le = 2⋅ R ⋅s + b (45a)
k ≥ σf + σfb (for p = p Z ) (38c)
In addition with light stiffeners

2.3 Buckling Le ≤ L1 (45b)


The "light" stiffeners are to be calculated using for-
mulae (39) - (45) for the integer n ≥ 2 which produces 2.4 Provision against buckling
the lowest value of pn1. In formula (41) L = L2, and, in
the absence of "heavy" stiffeners, L = L3. In the elas- The calculation of the buckling pressure pn1 for the
tic-plastic range, E' according to G. is to be substituted three loading conditions is performed in accordance
for E in formulae (39) and (42). The necessary stress with 2.3. Sufficient safety against buckling is provided
calculation is performed in accordance with 2.1. if the conditions (46a, b, c) are met.

E ⋅ s ⋅βn2 p n1 ≥ p N ⋅ Sk (46a)
po = (39)
R (for the nominal diving pressure load condition)

λ 24 p n1 ≥ pP ⋅ Sk ' = p N ⋅ S1 ⋅ Sk ' (46b)


βn2 = (40)
(n 2
)(
−1 + 0,5 ⋅λ 2 ⋅ n + λ 2
2 2
)
2 2
(for the test diving pressure load condition)

p n1 ≥ p Z = p N ⋅ S2 (46c)
π⋅ R
λ2 = (41)
L (for the collapse pressure load condition)
Chapter 1 Appendix A C Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–6 GL 1998

3. "Heavy" stiffeners (for the nominal diving pressure load condition)

3.1 Stresses in "heavy" stiffeners pg ≥ p P ⋅ Sk ' = p N ⋅ S1 ⋅ Sk ' (50b)


The stresses are calculated using formulae (35) - (37) (for the test diving pressure load condition)
and the values pg and n according to 3.3. In formulae
(37) and (41) L = L2. If the distances L2 to the two
pg ≥ p Z = p N ⋅ S2 (50c)
adjoining stiffeners (or ends) are unequal, the calcula-
tion shall make use of the arithmetic mean value of (for the collapse pressure load condition)
both distances. In the elastic-plastic range the values E
and ν are replaced by E' and ν'. The elasticity modulus
E' and the Poisson's ratio ν' are calculated in accor- 4. Tripping of ring stiffeners
dance with G. in the relation to the stress σf.
4.1 Tripping pressure and general conditions
3.2 Provision against excess stresses
The tripping pressure pk of flat bar stiffeners is to be
For the three loading conditions, formulae (35) and calculated using formulae (4), (14), (37) and (51) and
(36) give the stresses σf and σfb, the absolute values of Fig. 3 or 4. The value of n is to be that used in 2.3 or
which are related to the yield strength k in conditions 3.3 for calculations in the elastic-plastic range, E and
(38a, b, c). ν in the aforementioned formulae are to be replaced
by E' and ν' in accordance with G. The necessary
3.3 Buckling (general stability) stress calculation is performed in accordance with 2.1
Using formulae (39) - (42) and (47) - (49), the overall or 3.1. The maximum allowable value of (k1/E) ⋅
stability of the design is to be calculated for the inte- (h/b)2 is 1,14 in each case.
ger n ≥ 2 at which the buckling pressure pg attains its
lowest value. The calculation factor C4 in formula Calculation of the tripping pressure using the formulae
(47) becomes C4 = - 4 for internal stiffeners and C4 = referred to above necessitates maintaining the toler-
n2 for external stiffeners. Where only one "heavy" ances stated in I.
stiffener is located midway between two bulkheads,
the total buckling pressure pg formula (49) can be k1 ⋅ R1  A 
pk = ⋅  s +  (51)
R 2 (1 − ν2 )  b + 2N
increased by a membrane stress element po in accor-
dance with formulae (39) - (41) where L = L3. Where α 
there are no "heavy" stiffeners, the buckling pressure
pg is obtained from formula (43): The tripping pressure pk of L-, T- and I-section ring
stiffeners can be calculated by the method described in
pg = pn1 [3] or [5] (see L. or 4.2).

p2 =
( n −1) ⋅ E ⋅ I
2
e
(47) 4.2 Resistance of tripping
Ro 2
( R + e1 ⋅ C4 ) ⋅ L2
For flat bar stiffeners, the tripping pressure pk for the
po ⋅ p2 three loading conditions is obtained from formula
pn 2 = (48) (51). Sufficient resistance to tripping is provided if the
po + p 2 conditions (52a, b, c) are met.

pg = p1 + p n 2 (49) p k1 ≥ p N ⋅ Sk (52a)
(for the nominal diving pressure load condition)
3.4 Provision against buckling
The calculation of the total buckling pressure pg for p k1 ≥ p P ⋅ Sk ' = p N ⋅ S1 ⋅ Sk ' (52b)
the three loading conditions is performed in accor-
dance with 3.3. Sufficient safety against buckling is (for the test diving pressure load condition)
provided if the conditions (50a, b, c) are met.
p k1 ≥ p Z = p N ⋅ S2 (52c)
pg ≥ p N ⋅ Sk (50a)
(for the collapse pressure load condition)
I - Part 5 Appendix A C Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–7

1,0
K1 2
h 20
E b
15
0,5
10
0,4

0,3 5
4
0,2
3
0,15

0,10 n=2

0,05
0,04

0,03

0,02

0,015

0,01
0 0,05 0,10 0,15 0,20
h/R

Fig. 3 Stresses k1 for the calculation of internal flat bar stiffeners

1,0
10
9
8

K1 2
h
7

E b
6

0,5
0,4
4

0,3
3

0,2
0,15
2
n=

0,10

0,05
0,04

0,03

0,02

0,015

0,01
0 0,05 0,10 0,15 0,20
h/R

Fig. 4 Stresses k1 for the calculation of external flat bar stiffeners


Chapter 1 Appendix A E Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–8 GL 1998

Proof of the sufficient resistance to tripping of L-, T- beside the transition to the cylinder a coefficient β =
and I-section stiffeners can be provided by applying 1,1 is valid.
formula (53).
R ⋅p
σ = − (54)
E ⋅ I1' 2⋅s
k ⋅ Sk ≤ (53)
A1 ⋅ R ⋅ e p ⋅ R ⋅1, 2 ⋅β
σ = − (55)
Proof can be dispensed with if minimum seven of the 2⋅s
following eight conditions are met:

ew ≥ s 3. Provision against excess stresses


The stress for the three loading conditions is obtained
ef ≥ ew , ef ≤ 2 ⋅ s by applying formula (54) and (55). Sufficient safety
against excess stresses is provided if the conditions
d w ≤ 20 ⋅ e w , d w ≤ R / 2 (56a, b, c) are met, allowing for the absolute values of
σ.
d f ≤ 10 ⋅ ef , d f ≤ d w / 2, df ≥ dw / 4
k ≥ σ ⋅ S (for p = p N ) (56a)

k ≥ σ ⋅ S' (for p = pP ) (56b)

D. Stiffened and Unstiffened Conical Shells k ≥ σ (for p = p Z ) (56c)


The procedure to be applied to conical shells is similar
to that for cylindrical shells. Conical shells are re- 4. Buckling
placed in sections by cylinders having the mean di-
ameter and by multiplying the actual external pressure The buckling pressure pn in the dished section for the
by 1/cosϕ. It is assumed that the ends of the cone are nominal diving pressure and test diving pressure load
fitted with "heavy" ring stiffeners. If not, a stress conditions is determined by applying formula (57).
analysis has to be performed in accordance with F.1. 2
s
Ring stiffeners are to be calculated in the manner de- pn = 0,366 ⋅ E ⋅   (57)
scribed in C. The instructions given in B.1 are applica- R
ble to out-of-roundness values in conical shells.
The buckling pressure pn in the dished section for the
collapse pressure load condition is calculated with
formula (58). The elasticity moduli Es and Et are cal-
E. Dished Ends and Spheres culated in accordance with G. allowing for the stress
determined with formula (54).
1. General s
pn = 0,84 ⋅ Es ⋅ E t ⋅   2 (58)
Dished ends and spheres are to be examined for excess R
stresses and buckling under the loading conditions
stated in A. In the case of dished ends, the stresses in
the crown radius and in knuckle radius are to be inves- 5. Provision against buckling
tigated. Spheres are to be treated in the same way as The buckling pressure for the nominal diving pressure
the crown radius of dished ends. and test diving pressure load conditions is calculated
The calculation allow for out-of-roundness of the shell with formula (57). Sufficient safety is provided if the
up to a maximum of u = 0,04 ⋅ s/R. If larger tolerances conditions (59a, b) are met.
are planned, or if the method of measurement de- The buckling pressure for the collapse pressure load
scribed in H.3 results in greater out-of-roundness val- condition is calculated with formula (58). Sufficient
ues, than the permissible pressure is to be checked in safety is provided if conditions (59c) is met.
accordance with H.4.
p n ≥ p N ⋅ Sk (59a)
2. Stresses (for the nominal diving pressure load condition)
For the dished sections the stress is obtained by ap-
plying formula (54). For the knuckle radius the stress p n ≥ p P ⋅ Sk ' = p N ⋅ S1 ⋅ Sk ' (59b)
is obtained with formula (55), the radius R being the (for the test diving pressure load condition)
radius of the adjoining cylindrical jacket. The coeffi-
cient β are to be taken from reference [2] or Fig. 5. p n ≥ p Z = p N ⋅ S2 (59c)
For hemispherical ends in the range of 0,5 s ⋅ R (for the collapse pressure load condition)
I - Part 5 Appendix A E Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–9

6,5

6,0

5,5

5,0
Calculation coefficient β

4,5

4,0

3,5

βο
3,0

s
___
Da =
2,5

≥ 0,04

0,02
2,0
0,01

1,5
0,005

0,002

1,0
0,15 0,2 0,25 0,3 0,35 0,4 0,45 0,5

Ratio H / Da

Fig. 5 Values of β for the calculation of dished ends


Chapter 1 Appendix A G Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–10 GL 1998

F. Openings and Discontinuities G. Elasticity Moduli

1. Discontinuities The elasticity modulus for calculations in the elastic


region up to the limit of proportionality is to be taken
Discontinuities such as from the standard specifications for the materials con-
– Connections between cylinders and conical cerned. For design temperatures up to 50 °C, a value
segments of E = 206.000 N/mm2 can generally be accepted for
ferritic steels. For steel, a Poisson's ratio of ν = 0,3 is
– Reinforcing rings (rings other than the ring stiff- to be used.
eners dealt with in C.)
– Flanges for fixing spherical shell windows In the elastic-plastic range, the elasticity moduli Esc
and Et for steel between the limit of proportionality σe
must be subjected to a stress and elongation analysis and the yield point k according to the stress-strain
similar to that specified in [19] and [11] for the nomi- curve σ = f (ε, k, E) are to be determined by applying
nal diving pressure and test diving pressure load con- formulae (63) - (66).
ditions. The comparison stress is determined by ap-
plying formula (1). Sufficient safety is provided if the σe
conditions (16a, b) are met. In case of an interruption z =
of stiffeners an adequate reinforcing has to be pro- k
vided.
  E⋅ε z 
σ = k ⋅  z + (1 − z ) ⋅ tgh  −   (63)
2. Cylinder/cylinder penetrations   (1 − z ) ⋅ k (1 − z )  
Cutouts in cylinders are to be made in accordance with
the Rules Part 1 – Seagoing Ships, Chapter 2 – Ma- k   σ z 
chinery Installations, Section 7a, D.2.3.4 and using as ε = ⋅  z + (1 − z ) ⋅ artgh  −   (64a)
internal pressure a design pressure pc calculated by E   (1 − z ) ⋅ k (1 − z )  
applying formulae (60) and (61) - minimum with the
relevant pressure of the load case. Reinforcements are k
to be provided as integral reinforcements. ε min = z ⋅ (64b)
E
2 ⋅ p N2 ⋅ R ⋅S
pc = (60a) k
k ⋅ F ⋅ sA ε max = Min [ max.remaining elongation + ,
E
2 ⋅ pP 2 ⋅ R ⋅ S'
pc = (60b) ε = f ( σ → k )  (64c)
k ⋅ F ⋅ sA

2 ⋅ pZ2 ⋅ R
pc = (60c) k   E⋅ε z 
k ⋅ F ⋅ sA Es = ⋅  z + (1 − z ) ⋅ tgh  − 
 (1 − z ) ⋅ k (1 − z )  
(65)
ε   
 0, 4 ⋅ R  R
F = 1+ 3 ⋅ u ⋅ 1− ⋅
 L1  s A   E ⋅ε z 
E1 = E ⋅ 1 − tgh 2  − 
 (1 − z ) ⋅ k (1 − z )  
(66)
L   
for 1 ≥ 0, 4 (61a)
R
For calculations in the elastic-plastic range which
L1
F = 1 for < 0, 4 (61b) were originally developed for the elastic range, the
R term E is to be replaced by the term E' from formula
(67).
3. Sphere/cylinder penetrations
Cutouts in spheres are to be made in accordance with E' = Es ⋅ E t (67)
GL Rules for the Classification and Construction,
Part 1 – Seagoing Ships, Chapter 2 – Machinery In- With GL's agreement, the stress-strain curve actually
stallations, Section 7a, D.4.3.3 and using as internal measured may b e used to determine the elasticity
pressure an increased design pressure pc calculated by moduli in the elastic-plastic range.
applying formula (62).
In the elastic-plastic range, the Poisson's ratio is to be
pc = 1, 2 ⋅ p N (62a) calculated using formula (68).

pc = 1, 2 ⋅ p P (62b) 1 1  E
ν' = −  −ν ⋅ s (68)
pc = 1, 2 ⋅ p Z (62c) 2 2  E
I - Part 5 Appendix A H Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–11

H. Out-of-Roundness of Cylinders and Table 1 Influence factors Ci where J = 24


Spheres
i-j C i− j i-j C i− j
Cylindrical shells and dished ends subjected to exter-
nal pressure are to be checked for out-of-roundness. If 0 1,76100 12 0,60124
the tolerances are exceeded, the permissible external 1 0,85587 13 0,54051
pressure is to be reduced to the value p'. 2 0,12834 14 0,36793
3 – 0,38800 15 0,11136
4 – 0,68359 16 – 0,18614
1. Measuring the out-of-roundness of cylin- 5 – 0,77160 17 – 0,47097
drical shells 6 – 0,68487 18 – 0,68487
7 – 0,47097 19 – 0,77160
The number of planes used for measuring the out-of- 8 – 0,18614 20 – 0,68359
roundness of cylindrical pressure vessels is to be 9 0,11136 21 – 0,38800
10 0,36793 22 0,12834
agreed with GL. For each plane, the number of meas-
11 0,54051 23 0,85587
uring prints (J) shall be at least 24, and these shall be
evenly distributed round the circumference. The
height of arc x (j) is measured with a bridge extending 2. Calculation of permissible pressure for
over a string length y = 4 ⋅ π ⋅ (R + s/w)/J (cf. Fig. 6). cylindrical shell with an out-of-roundness
Form the values x (j) and the influence coefficients C, u > 0,005
the out-of-roundness values can be calculated by ap-
The bending stress is determined for al measuring
plying formula (69). Table 1 gives the influence coef- points by the choice of a reduced permissible pressure
ficients #C where J = 24. If the out-of-roundness U (j) p' and by applying formula (70). The total stress is
at any measuring point exceeds a value of U = 0,005 ⋅ found with formula (74) and the reduced permissible
R, then a reduced permissible pressure p' is to be de- pressure p' with formula /75) by a process of iteration,
termined in accordance with 2. the n-related value for formula (17) being substituted
for the pressure pn. The mean radius R' is to be deter-
mined by measuring the circumference.

  
2
E ⋅s
( ) 
 n 2 − 1 + ν  π⋅ R  
J/2
σb = Σ
(
2 R 2 1 − ν2 ) n=2 
  L1  

 p' 
⋅  ⋅ a n ⋅ sin ( n ⋅ γ ) + bn ⋅ cos ( n ⋅ γ )  (70)
y
j=0

 pn − p ' 
j=1

x
2
j=

γ 2 ⋅π
γ = ⋅ i (71)
J

R' 2 J −1
an = ⋅ Σ ( R ' + Ui ) ⋅ sin ( n ⋅ γ ) (72)
J i =0

2 J −1
Fig. 6 Measuring the out-of-roundness of bn = ⋅ Σ ( R ' + Ui ) ⋅ cos ( n ⋅ γ )
a cylindrical shell J i =0

for n ≠ J / 2 (73a)
J −1
J −1
= Σ xi ⋅ C i − j 1
Uj
i=0
(69)
bn = ⋅ Σ ( R ' + Ui ) ⋅ cos ( n ⋅ γ )
J i =0

for n = J / 2 (73b)
Example of the out-of-roundness U at measuring point
j = 2 where J = 24:
p '⋅ R
k ≥ + σb (74)
s
U2 = x 0 ⋅ C 2 + x1 ⋅ C1 + x 2 ⋅ C0 + x 3 ⋅ C1 + ...

+ x 21 ⋅ C19 + x 22 ⋅ C20 + x 23 ⋅ C 21
p' ≥
p'
S
+ (p − ) p'
S

0, 005 ⋅ R
U max
(75)
Chapter 1 Appendix A I Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–12 GL 1998

3. Measuring the out-of-roundness of spheres  s


y = 2 ⋅  R +  ⋅ sin δ (76)
 2 
The height of arc x' is measured with a bridge gauge
 s
x =  R + 2  ⋅ (1 − cos δ )
(cf. Fig. 7), the string length y being calculated with (77)
formulae (76) and (79). The out-or-roundness U is  
determined with formula (78). If the out-of-roundness
U = x − x '= u⋅R (78)
is greater than u = 0,04 ⋅ s/R, a reduced permissible
pressure p' is to be determined in accordance with 4. 1,1 s
δ = ⋅
( )
(79)
1− ν 2 R + 2s
y
the distribution of the measuring points is shown in
Fig. 8. Two measurements are to be made at each
point: one in the plane of the central axis, the other at
right angles to it.

4. Calculation of permissible pressure for


spheres with an out-of-roundness
u > 0,04 ⋅ s/R
The reduced permissible pressure p' is calculated with
U

formula (80) allowing for the actual radius of curva-


x
x'

ture R' and the minimum wall thickness s' occurring in


s' s the measuring range y (taking account of any reduc-
tions for wear and corrosion). The radius of curvature
R' is determined with formula (81).
2
 R + 2s   s ' 2
2
s/
R'

p' = p ⋅   ⋅  ≤ p
+

(80)
δ  R'  2
R

 

x' y2
R' = + (81)
2 8⋅ x'

Fig. 7 Measuring the out-of-roundness of a sphere


I. Tolerances of Ring Stiffeners

A check is to be carried out on ring stiffeners to de-


termine whether the following tolerances have been
maintained:
– Girth width (on T-section flanges, the whole
width): - 0/+ 5 mm
30° – Girth and web thickness: - 0/+ t
30°
15° The tolerance t depends on the conditions of
R' supply for the material. (If the material supply
specification allows negative tolerances, these
are to be allowed for in the calculations)
– Height of ring (in the case of built-up profiles
the height of the entire ring): - 2 %/+ 5 % of the
total height
– Uneveness of web and girth (measured over
height of web and girth respectively): 0/1 % of
web and girth height respectively
Measuring point
– Symmetry of flange in relation to web (applica-
ble to I- and T-section stiffeners: the difference
Fig. 8 Distribution of measuring points from the edge of the girth to the web on both
over hemisphere sides of the web): 0/4 mm difference
I - Part 5 Appendix A I Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–13

– L1 distances (distances between "light" stiffen- – Angularity of flange in relation to web: - 3°/+ 3°
ers and separating "light" from "heavy" stiffen-
ers): - 5,0/+ 5,0 mm All dimensional deviations are to be measured eight
times on each stiffener at points equally spaces round
– L2 distances (distances between "heavy" stiffen- the circumference. If the aforementioned tolerances
ers or ends or separating "heavy" stiffeners from
are exceeded, corrective machining and/or manual
ends): - 15,0/+ 5,0 mm
work is to be carried out on the stiffener and/or the
– Angularity of web in relation to wall or main calculation is to be repeated with corrected dimen-
axis: - 2°/+ 2° sions.
Chapter 1 Appendix A J Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–14 GL 1998

J. Program Sequences for Iterative Calculations

n = nel' p = pe = f (s = s ) (1, 2a, 2b)


i e
e = emin : (64b) emax : (64c)
Dp = 0,001 De = 0,000001 X1, X2 Control values
p = pe + Dp e = emin + De p1, p2 Calculation values
si = f(p, E' = E) s1 = si'
sx = se Ds = (1-z) * k
x1 = '0' x2 = '0' p1 = p p2 = p

yes
pe ³ pz
x2 = 1
no

x1 = 'a' or yes
x1 = 'd' ?
pn : (17, 18, 19)
no E' = f (e) (65, 66, 67)
sx : (63)
si : (1,2a, 2b)
x1 = '0'
e ³ emax yes

?
no
p ³ pZ and yes

x2 = '0' ?
si (p = pZ) : (1)
no
x2 = '1' x1 = '4'

Ds > 0 and
yes
si > sx and Ds < si - sx x1 = '1'
and x1 = '0' ?

no

Ds < 0 and
yes
si < sx and Ds > si - sx x1 = '2'
and x1 = '0' ?

no

e = e + De
Ds ³ 0 and
yes Ds = si - sx
si > sx
s1 = si, x1 = 'a'
and x1 = '0' ?
p2 = p1

no

p1 = p
Ds < 0 and
yes p = p + Dp
si < sx
Ds = si - sx
and x1 = '0' ?
s1 = si, x1 = 'b'

no

p1 = p
Ds < 0 and
yes p = p + Dp
si > sx
Ds = si - sx
and x1 = '0' ?
s1 = si, x1 = 'c'

no

e = e + De
Ds < 0 and
yes Ds = si - sx
si < sx
and x1 = '0' ? s1 = si, x1 = 'd'
p2 = p1

no

no This sheme is valid for the centre of the


x1 £ '4' ?
section. For stress in the area of stiffening
the sheme is to be repeated with si (1,2c, 2d)
yes without pn .
no yes
acceptable x2 = '0' ? not acceptable

pmax = p2

Fig. 9 Cylindrical shells, stresses and asymmetric buckling in the elastic-plastic range
I - Part 5 Appendix A J Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–15

m1 = 0+1 p = p = f (si = se) (1, 2a, 2b)


e
e = emin : (64b) emax : (64c)
Dp = 0,001 p3, pm = 999
De = 0,000001
p = p e + Dp
e = emin + De m1 = 0
si = f(p, E' = E)
s1 = si
sx = se
x1 = '0' Ds = (1-z) * k
m1 , p 1 , p 2 , p 3
Calculation values
x1 Control value

x1 = 'a' or yes E' = f (e)


(65, 66, 67)
x1 = 'd' ? sx : (63)

no
yes
e ³ emax
si : ( 1, 2a, 2b )
?
x1 = '0'
no

p3 : ( 21, 22 ) x1 = '4'

yes
p2 ³ p 3 ? x1 = '3'

no

Ds > 0 and
yes
si > sx and Ds < si - sx x1 = '1'
and x1 = '0' ?

no

Ds < 0 and
yes
si < sx and Ds > si - sx x1 = '2'
and x1 = '0' ?

no

e = e + De
Ds ³ 0 and yes Ds = si - sx
si > s x
and x1 = '0' ? s1 = si, x1 = 'a'
p2 = p 1

no

p1 = p
Ds ³ 0 and yes p = p + Dp
si < s x Ds = si - sx
and x1 = '0' ?
s1 = si, x1 = 'b'

no

p1 = p
Ds < 0 and yes p = p + Dp
si < s x
Ds = si - sx
and x1 = '0' ?
s1 = si, x1 = 'c'

no

e = e + De
Ds < 0 and yes Ds = si - sx
si > s x
and x1 = '0' ? s1 = si, x1 = 'd'
p2 = p 1

no

no
x1 £ '4' ?

yes

pm < 999 no p2 < pm and


and formula (33)
p3 > p m met ?

yes

END pm = p3
pmax = Min (pm, po) m = m1
po = p 2

Fig. 10 Cylindrical shells, symmetric buckling in the elastic-plastic range


Chapter 1 Appendix A J Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–16 GL 1998

n = nel' p = pe = f (sf = se) (35)

e = emin : (64b) emax : (64c)


Dp = 0,001 De = 0,000001

p = pe + Dp e = emin + De
si = f(p, E' = E) s1 = si'
sx = se Ds = (1-z) * k
x1 = '0' x2 = '0'
x1, x2 Control values
yes p1, p2 Calculation values
pe ³ pz ?
x2 = 1
no

x1 = 'a' or yes E' = f (e) (65, 66, 67)

x1 = 'd' ? sx : (63)

no e ³ emax yes

?
no

si = sf (35) E'
x1 = '0' pn1 = __ • pn el (43)
E

x1 = '4'

p ³ pZ and yes

x2 = '0' ? sf + sb = f (p = pZ) (35, 36 )


x2 = '1'
no

Ds > 0 and
yes
si > sx and Ds < si - sx x1 = '1'
and x1 = '0' ?

no

Ds < 0 and
yes
si < sx and Ds > si - sx x2 = '2'
and x1 = '0' ?

no

e = e + De
Ds ³ 0 and yes Ds = si - sx
s i > sx
s1 = si, x1 = 'a'
and x1 = '0' ?
p2 = p1

no

p1 = p
Ds ³ 0 and yes p = p + Dp
si < sx Ds si - sx
and x1 = '0' ?
s1 = si, x1 = 'b'
no

p1 = p
Ds < 0 and
yes p = p + Dp
si < sx
Ds si - sx
and x1 = '0' ?
s1 = si, x1 = 'c'

no

e = e + De
Ds < 0 and Ds = si - sx
yes
si > sx
s1 = si, x1 = 'd'
and x1 = '0' ?
p 2 = p1

no

no
x1 £ '4' ?

yes

no yes
acceptable x2 = '0' ? not acceptable

pmax = p2
END

Fig. 11 "Light" stiffeners in the elastic-plastic range


I - Part 5 Appendix A K Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–17

K. Symbols and Units I1 [mm4] second moment of area of stiff-


ener ring cross-section about axis
A [mm2] modified area of stiffener ring through centroid parallel to cyl-
inder axis
A1 [mm2] cross-sectional area of stiffener
ring I1 ' [mm4] second moment of area of stiff-
ener ring cross-section about axis
b [mm] width of stiffener ring in contact through centroid vertical to cyl-
with shell inder axis
C [1] influence coefficient for calcu- Ie [mm4] second moment of area of stiff-
lating out-of-roundness ener ring cross-section, including
C0... C3 [1] calculation factors for symmetric effective length of shell acting
buckling with stiffener ring, about axis
through centroid parallel to cyl-
C4 [1] calculation factor for asymmetric inder axis
buckling, "heavy" stiffener rings
J [1] number of measuring points for
C5... C11 [1] calculation factor for stress in checking out-of-roundness
cylindrical shell
j [1] number (0 ... J-1) of measuring
df [mm] width of girth of L-, T- or I-stiff- point used to check out-of-
ener ring from web to edge of roundness
flange
k [N/mm2] yield strength ReH20
dw [mm] height of web L-, T- or I-
stiffener ring k1 [N/mm2] stress in flat bar, cf. formula (51)
and Abb. 3 and 4
ef [mm] girth thickness of L-, T- or I-
stiffener Ko [1] stress ratio, cf. formula (15)
ew [mm] web thickness of L-, T- or I- K1 [1] stress coefficient, cf. formula
stiffener (31)
e [mm] distance from stiffener ring cen- L [mm] spacing between effective stiff-
troid to centre of cylindrical wall eners
e1 [mm] distance from stiffener ring cen- L1 [mm] spacing between two "light"
troid to centre of cylinder wall stiffeners
including effective length of
shell Le L2 [mm] spacing between two "heavy"
stiffeners
e2 [mm] distance between stiffener ring
centroid, including effective L3 [mm] total length or length between
length of shell Le, and flange bulkheads
face facing away from cylinder
Le [mm] effective length of shell
wall
E [N/mm2] modulus of elasticity m [1] mode of collapse, symmetric
buckling
E' [N/mm2] modulus of elasticity elastic-
plastic range, see formula (67) n [1] mode of collapse, asymmetric
buckling
Es [N/mm2] secant modulus, see formula (65)
N [1] coefficient, cf. formula (37)
Et [N/mm2] tangent modulus, see formula
(66) p [N/mm2] external design pressure

F [1] factor for calculations in plastic p' [N/mm2] external pressure reduced owing
range, see formula (61) to out-of-roundness

F1... F4 [1] geometric factors, see formulae po [N/mm2] pressure, membrane stress part
(3a) to (3d) pc [N/mm2] design pressure for calculation of
G [1] pressure ratio, see formula (13) opening
h [mm] height of stiffener ring pe [N/mm2] pressure in which the stress
reaches the elastic-plastic range
H [mm] depth of dished end
pg [N/mm2] total buckling pressure
H1... H4 [1] calculation factors for symmetric
buckling pk [N/mm2] tripping pressure
Chapter 1 Appendix A L Calculation and Pressure Hulls under External Pressure I - Part 5
Page A–18 GL 1998

pm [N/mm2] buckling pressure, symmetric  1 


buckling α  mm  shape factor, cf. formula (14)
 
pn [N/mm2] buckling pressure, asymmetric
buckling  1 
α1  mm  shape factor, cf. formula (32)
pn1 [N/mm2] buckling pressure, asymmetric  
buckling, "light" stiffener
β [1] coefficient for dished ends, cf.
pn2 [N/mm2] buckling pressure, asymmetric reference [2] or Fig. 5
buckling, "heavy" stiffener
pN [N/mm2] nominal diving pressure (1st load βn1 [1] coefficient, cf. formula (18)
condition)
βn2 [1] coefficient, cf. formula (40)
pP [N/mm2] test diving pressure (2nd load
condition) γ [rad] angle used in increasing the out-
of-roundness of cylinders
pZ [N/mm2] collapse pressure (3rd load con-
dition) δ [rad] angle used in measuring out-of-
roundness of spheres
p* [N/mm2] critical pressure, cf. formula (12)
p** [N/mm2] critical pressure, elastic-plastic, λ [1] coefficient, cf. formulae (19),
cf. formula (22) (41)

R [mm] mean radius of wall ν [1] Poisson's ratio, elastic


Ro [mm] radius of stiffener ring centroid ν' [1] Poisson's elastic-plastic, cf. for-
including effective length Le mula (68)
R1 [mm] radius of standing flange of stiff- ϕ [rad] angle of cone (between wall and
ener ring axis)
R' [mm] measured outside radius
σb [N/mm2] bending stress in case of out-of-
s [mm] thickness of shell/sphere without roundness
abrasion and corrosion
σe [N/mm2] proportional limit
s' [mm] measured wall thickness without
abrasion and corrosion σf [N/mm2] compression stress in girth
sA [mm] thickness of shell/sphere adjoin- σfb [N/mm2] bending stress in girth
ing opening
S [1] safety factor applied to yield σi [N/mm2] stress intensity
strength ReH20 at nominal pres-
σo [N/mm2] stress (calculate value)
sure
S' [1] safety factor applied to yield σx [N/mm2] stress in longitudinal direction
strength ReH20 at test diving
pressure σϕ [N/mm2] stress in circumferential direction

Sk [1] safety factor against instability at σzul [N/mm2] permissible stress


nominal pressure
S'k [1] safety factor against instability at
test diving pressure
L. References
t [mm] tolerance
U [mm] out-of-roundness: U = u ⋅ R [1] Germanischer Lloyd: Rules for the Classifica-
tion and Construction, Part 1 – Seagoing Ships,
u [1] out-of-roundness in relation to R Chapter 2 – Machinery Installations
x [mm] theoretic height of arc [2] AD Merkblätter, Reihe B, Berechnung von
x' [mm] effective height of arc Druckbehältern, Herausgeber: Arbeitsgemein-
schaft Druckbehälter
y [mm] string dimension of measurement
device [3] The Stress Analysis of Pressure Vessels and
Pressure Vessel Components, published by S.S.
z [1] proportional ratio (= σe/k) Gill, Pergamon Press, 1970
I - Part 5 Appendix A L Calculation and Pressure Hulls under External Pressure Chapter 1
GL 1998 Page A–19

[4] John C. Pulos and Vito L. Salerno: Axisymmet- [9] Krenske, Martin A. and Kierman, Thomas J.:
ric Elastic Deformations and Stresses in a Ring- The Effect of Initial Imperfections on the Col-
Stiffened, Perfectly Circular Cylindrical Shell lapse Strength of Spherical Shells, DTMB-Re-
under External Hydrostatic Pressure, DTMB- port No. 1757
Report No. 1497
[10] ASME Boiler and Pressure Vessel Code, Sec-
[5] Development in Pressure Vessel Technology, tion VIII, Division 2, 1989 Edition
published by R.W. Nichols, Applied Science
Publishers, 1983 [11] Raymond J. Roark and Warren C. Young: For-
mulars for Stress and Strain, MC Graw-Hill
[6] European Recommendations for Steel Construc-
Book Company
tion: Buckling of Shells, published by ECCS-
CECM-EKS, Brüssel, 1984 [12] William F. Blumenberg: The Effect of Interme-
[7] DIN 4114, Blatt 2: Stabilitätsfälle (Knickung, diate Heavy Frames on the Elastic General In-
Kippung, Beulung), 2.53 Edition stability Strength of Ring-Stiffened Cylinders
Under External Hydrostatic Pressure, DTMB-
[8] Myron E. Lunchick: Plastic Axisymmetric Report No. 1844
Buckling of Ring-Stiffened Cylindrical Shells
Fabricated from Strainhardening Materials and [13] Thomas E. Reynolds: Inelastic Labor Buckling
Subjected to External Hydrostatic Pressure, of Cylindrical Shells under External Hydrostatic
DTMB-Report No. 1393 Pressure, DTMB-Report No. 1392
I - Part 5 Appendix B C Acrylic Plastic Windows Chapter 1
GL 1998 Page B–1

Appendix B

Acrylic Plastic Windows

A. General – number and date of certificate


– manufacturer's name and address
1. For the purpose of these Rules, acrylic plastic
windows are flat or curved windows for the view ports – designation and application of casting type
of pressure hulls which are made of cast, unlaminated – batch number, quantity, shape and size of cast-
polymethyl methacrylate plastic. ings
– marking of castings
2. For acrylic plastic windows following operat-
ing limits apply: – results of tests applied in accordance with Ta-
ble 1
– designed service life 10 or 20 years
(see explanatory notes below) – stamp and signature
– temperature range - 18°C to + 66°C
4. Where a material certificate of the kind re-
– rate of pressurization max. 10 bar/sec quired is not available for the acrylic plastic or where
the conditions for recognition of the material certifi-
– pressure cycles at design cate are not satisfied, the tests are to be extended in a
pressure max. 10.000 manner to be agreed with GL in each case.
– period under pressure at
design pressure max. 40.000 h 5. Each casting is to be provided at at least one
point with a marking which identifies the type of cast-
– max. working pressure max. 1.380 bar
ing, the batch number, the date of manufacture and the
The design service life depends on numerous factors, name of the manufacturer.
in particular on the kind of loading. The maximum
design service life to be assumed for spherical or cy-
lindrical windows subjected to external overpressure,
which are exclusively exposed to compressive stresses C. Manufacture of Windows
or minor bending stresses only, generally is 20 years,
while for flat windows with flat fit it is 10 years. 1. The manufacture of acrylic plastic windows
covered by these Rules may only take place in spe-
Depending on the previous actual loads acting on the cialized workshops which have been approved by GL
windows and following testings to be agreed with GL for that purpose. Such approval can be granted only to
in detail, extension of the service life of acrylic plastic those companies which employ properly trained spe-
windows may be approved. cialists and which have available the necessary techni-
cal facilities enabling them to undertake the expert
forming, machining, heat treatment and quality control
of acrylic plastic windows.
B. Material
Application for approval is to be made to GL before
the manufacture of windows commences.
1. The material of acrylic plastic windows must
be manufactured in accordance with a recognized
2. The acrylic plastic to be used must meet the
standard (e.g. ANSI/ASME PVHO 1, Section 2). The
requirements stated in B. After machining and any
producer is required to certify this before manufacture
necessary forming operations, each window is to be
commences.
subjected to heat treatment (tempering) in accordance
with the acrylic plastic manufacturer's specification.
2. Acrylic plastic windows must meet the mini- After tempering no further mechanical polishing may
mum physical requirements stated in Table 1. be carried out on the window.

3. For each batch of acrylic plastic to be made 3. Window surfaces are to be polished in such a
into windows the manufacturer is to issue a material way as to meet the optical clarity requirement stated in
certificate containing at least the following details: Table 1.
Chapter 1 Appendix B D Acrylic Plastic Windows I - Part 5
Page B–2 GL 1998

4. For each window or series of windows the by GL on application, provided that they are designed
window manufacturer is to be issue a component cer- and manufactured to a recognized standard.
tificate specifying all the stages of manufacture such
as cutting, sticking, polishing, forming and tempering.
3. The design temperature to be assumed for
The certificate shall also indicate the tests carried out,
acrylic plastic windows should be the mean value of
the test results, the marking of the windows and the
the maximum external and internal temperatures to be
date of manufacture.
expected under design pressure conditions.

5. Each window is to be permanently marked


with at least the following details: 4. Windows subjected to pressure from both
sides are to be designed for the maximum pressure
– Design pressure [bar] applied, regardless of whether this pressure is external
or internal.
– Design temperature [°C]
– Germanischer Lloyd approval stamp 5. Pressure may only be applied to the convex
– Manufacturer's name or identifying mark side of spherical shell windows.

– Serial number and year of manufacture.


6. The thickness of the window must be every-
Wherever possible, the marking is to be engraved in where equal to, or greater than, the minimum value
the non-load-bearing portion of the window edge. The determined by reference to Tables 2 and 3.
use of punches is not allowed.
7. With flat windows having right-angled edge
6. The acrylic plastic windows are to be pre- and an O-ring seal, the outside diameter of the disk
sented to GL for an inspection of manufacture. In shall be within + 0,00/- 0,25 mm of the nominal value,
addition, each window is to be subjected, in the pres- or within + 0,00/- 0,75 mm where flat gasket seals are
ence of Germanischer Lloyd Surveyor, to a pressure used.
test in accordance with Chapter 2 – Submersibles,
Section 2, D.3.3 of these Rules. 8. The major diameter of the conical bearing
surface of an acrylic plastic window shall be within
+ 0,000/- 0,002 Do of the nominal value.

D. Window Shapes and Sizes The included conical angle of the window shall be
within + 0,25/- 0,00 degrees of the nominal value.
1. the standard shapes and sizes shown in Ta-
ble 2 and 3 are to be selected for the acrylic plastic 9. The concave or convex surface of the win-
windows. dow shall not differ from an ideal spherical sector by
For design pressure in general the nominal diving more than ± 0,5 % of the nominal external spherical
pressure is to be used. radius.

2. Acrylic plastic windows of other shapes and 10. The surface roughness (Ra) of the window
sizes or for other ranges of pressure may be approved bearing surface shall be 0,75 µm or better.
I - Part 5 Appendix B D Acrylic Plastic Windows Chapter 1
GL 1998 Page B–3

Table 1 Mechanical and optical properties of acrylic plastic

Properties Specified values Test method ASTM

Ultimate tensile strength ≥ 62 N/mm2 DIN 53 455 1


specimen type 3
Elongation at break
(in relation to necking zone) ≥ 2 % test velocity II D 638 1
standard 23/50 atmosphere
Modulus of elasticity
≥ 2760 N/mm2 DIN 53 457
measured by tensile test

Compressive yield strength ≥ 103 N/mm2 DIN 53 454 1


standard 23/50 atmosphere
size of test specimen: D 695 1
25 x 12,5 x 12,5 mm
Modulus of elasticity ≥ 2760 N/mm2 DIN 53457 1
measured by compression
test
constant compressive stress 1 of D 621 1
Compressive deformation ≤ 1 % 27,5 N/mm2 for 24 h at 50 °C
test cube: 12,5 mm edge length

Ultraviolet transmittance ≤ 5 % UV-spectrophotometer


wave length range: 290 - 370 nm E 308
thickness of specimen: 12,5 mm

Visual clarity legibility a25 x 25 mm standard layout comprising 7


lines of 16 letters each must be clearly
D 702
legible through the acrylic plastic pane at a
distance of 500 mm.

Total residual monomers


methyl methacrylate ≤ 1,6 % gas chromatograph
ethyl acrylate
1 The mechanical properties are to be verified on at least 2 specimens.
Chapter 1 Appendix B D Acrylic Plastic Windows I - Part 5
Page B–4 GL 1998

Table 2 Standard dimensions for flat disk windows

Range of application :
Do
Minimum wall thickness : s ³ 12,5 mm
Slenderness ratio : s/Do ³ 0,125

s
Edge radius : 1 mm £ R1 £ 2 mm R1
Window seating : 1,25 £ Do / Df £ 1,5
Di = D a
Max. working pressure : p £ 170 bar

Design pressure Minimum wall thickness / inside diameter of seat s/Di


Pc
at
[bar]
10 °C 24 °C 38 °C 52 °C 66 °C

5 0,134 0,146 0,154 0,164 0,188


10 0,154 0,173 0,188 0,201 0,226
15 0,173 0,195 0,210 0,223 0,253
20 0,188 0,210 0,226 0,240 0,281
25 0,201 0,223 0,240 0,257 0,305
30 0,210 0,233 0,253 0,274 0,324
35 0,219 0,243 0,267 0,292 0,344
40 0,226 0,253 0,281 0,305 0,363
45 0,233 0,264 0,295 0,317 0,383
50 0,240 0,274 0,305 0,329 0,402
60 0,253 0,295 0,324 0,354 0,441
70 0,267 0,310 0,344 0,378 0,480
80 0,281 0,324 0,363 0,402 0,520
90 0,295 0,339 0,383 0,427 0,559
100 0,305 0,354 0,402 0,451 0,598
110 0,315 0,368 0,422 0,476 0,637
120 0,324 0,383 0,441 0,500 0,676
130 0,334 0,398 0,461 0,524 0,715
140 0,344 0,412 0,480 0,549 0,754
150 0,354 0,427 0,500 0,573 0,793
160 0,363 0,441 0,520 0,598 0,832
170 0,373 0,456 0,539 0,622 0,871
I - Part 5 Appendix B D Acrylic Plastic Windows Chapter 1
GL 1998 Page B–5

Table 3 Standard dimensions for spherical shell windows with conical seat

Range of application : α
Opening angle : α ≥ 60 °
s
Minimum of wall thickness : s ≥ 12,5 mm
Ri
Minimum values for s/Ri :

α ≥ 60° ≥ 90°
Df
s/Ri 0,09 0,06
Di

Window seating : Di / Df ≥ 1,02


Maximum working pressure : p ≤ 170 bar

Design Minimum wall thickness / Design Minimum wall thickness /


pressure inside diameter of seat s/Di pressure inside diameter of seat s/Di
where α = 60 ° at where α = 90 ° at
Pc Pc

[bar] 10 °C 24 °C 38 °C 52 °C 66 °C [bar] 10 °C 24 °C 38 °C 52 °C 66 °C

5 0,090 0,090 0,090 0,090 0,090 5 0,042 0,042 0,042 0,042 0,049
10 0,090 0,090 0,090 0,090 0,112 10 0,042 0,043 0,049 0,054 0,070
15 0,090 0,090 0,097 0,108 0,140 15 0,043 0,052 0,060 0,067 0,089
20 0,090 0,097 0,112 0,126 0,166 20 0,049 0,060 0,070 0,080 0,107
25 0,090 0,108 0,126 0,143 0,191 25 0,054 0,067 0,080 0,091 0,124
30 0,097 0,119 0,140 0,160 0,215 30 0,060 0,075 0,089 0,102 0,142
35 0,104 0,129 0,153 0,176 0,238 35 0,065 0,082 0,098 0,113 0,160
40 0,112 0,140 0,166 0,191 0,259 40 0,070 0,089 0,107 0,124 0,177
45 0,119 0,150 0,179 0,206 0,279 45 0,075 0,095 0,116 0,135 0,194
50 0,126 0,160 0,191 0,221 0,298 50 0,080 0,102 0,124 0,146 0,210
60 0,140 0,179 0,215 0,248 0,332 60 0,089 0,116 0,142 0,168 0,242
70 0,153 0,197 0,238 0,274 0,363 70 0,098 0,128 0,160 0,190 0,272
80 0,166 0,215 0,259 0,298 0,391 80 0,107 0,142 0,177 0,210 0,300
90 0,179 0,232 0,279 0,320 0,416 90 0,116 0,155 0,194 0,230 0,327
100 0,191 0,248 0,298 0,340 0,439 100 0,124 0,168 0,210 0,250 0,351
110 0,203 0,264 0,315 0,359 0,460 110 0,133 0,181 0,226 0,269 0,373
120 0,215 0,279 0,332 0,377 0,480 120 0,142 0,194 0,242 0,287 0,393
130 0,227 0,293 0,348 0,394 130 0,151 0,206 0,257 0,304 0,411
140 0,238 0,307 0,363 0,410 140 0,160 0,218 0,272 0,320
150 0,248 0,320 0,377 0,425 150 0,168 0,230 0,287 0,336
160 0,259 0,332 0,391 0,439 160 0,177 0,242 0,300 0,351
170 0,269 0,344 0,404 0,452 170 0,185 0,254 0,314 0,365
Chapter 1 Appendix B D Acrylic Plastic Windows I - Part 5
Page B–6 GL 1998

Table 3 Standard dimensions for spherical shell windows with conical scat (contd.)

Range of application : α
Opening angle : α ≥ 60 °
s
Minimum of wall thickness : s ≥ 12,5 mm
Ri
Minimum values for s/Ri :

α ≥ 120° ≥ 180°
Df
s/Ri 0,06 0,03
Di

Window seating : Di / Df ≥ 1,02

Maximum working pressure : p ≤ 170 bar

Design Minimum wall thickness / Design Minimum wall thickness /


pressure inside diameter of seat s/Di pressure inside diameter of seat s/Di
where α = 120 ° at where α = 180 ° at
Pc Pc

[bar] 10 °C 24 °C 38 °C 52 °C 66 °C [bar] 10 °C 24 °C 38 °C 52 °C 66 °C

5 0,021 0,023 0,025 0,028 0,034 5 0,018 0,018 0,019 0,021 0,026
10 0,025 0,030 0,034 0,038 0,050 10 0,019 0,023 0,026 0,030 0,041
15 0,030 0,036 0,042 0,048 0,067 15 0,023 0,028 0,034 0,039 0,056
20 0,034 0,042 0,050 0,059 0,083 20 0,026 0,034 0,041 0,049 0,071
25 0,038 0,048 0,059 0,069 0,100 25 0,030 0,039 0,049 0,058 0,086
30 0,042 0,054 0,067 0,079 0,117 30 0,034 0,045 0,056 0,068 0,101
35 0,046 0,061 0,075 0,090 0,131 35 0,038 0,051 0,064 0,077 0,115
40 0,050 0,067 0,083 0,100 0,146 40 0,041 0,056 0,071 0,086 0,129
45 0,054 0,073 0,092 0,110 0,161 45 0,045 0,062 0,079 0,096 0,142
50 0,059 0,079 0,100 0,119 0,175 50 0,049 0,068 0,086 0,105 0,155
60 0,067 0,092 0,117 0,138 0,204 60 0,056 0,079 0,101 0,122 0,182
70 0,075 0,104 0,131 0,157 0,232 70 0,064 0,090 0,115 0,139 0,207
80 0,083 0,117 0,146 0,175 0,259 80 0,071 0,101 0,129 0,155 0,232
90 0,092 0,127 0,161 0,193 0,285 90 0,079 0,112 0,142 0,172 0,256
100 0,100 0,138 0,175 0,211 0,310 100 0,086 0,122 0,155 0,188 0,278
110 0,108 0,149 0,190 0,228 0,334 110 0,094 0,132 0,168 0,204 0,299
120 0,117 0,161 0,204 0,245 0,357 120 0,101 0,142 0,182 0,220 0,319
130 0,123 0,171 0,218 0,262 0,379 130 0,108 0,152 0,194 0,235 0,337
140 0,131 0,182 0,232 0,278 0,400 140 0,115 0,162 0,207 0,250 0,352
150 0,138 0,193 0,245 0,294 150 0,122 0,172 0,220 0,264 0,366
160 0,146 0,204 0,259 0,310 160 0,129 0,182 0,232 0,278
170 0,153 0,214 0,272 0,325 170 0,135 0,191 0,244 0,292
I - Part 5 Appendix C C Design and Manufacture of GRP Constructions Chapter 1
GL 1998 Page C–1

Appendix C

Design and Manufacture of GRP Constructions

A. Principles for the Manufacture of GRP throughout the moulding area during the lay-up and
Constructions curing periods. By agreement with the Surveyor a
small deviation from the above temperatures will be
Apart from the selection of suitable and approved considered depending on the resin manufacturer's
materials, special attention is to be paid to be process- recommendations.
ing operation in view of its major influence on the
characteristics of the product. Where other moulding processes are to be used, the
moulding shop temperature will be determined ac-
The instructions of the raw materials manufacturers cordingly.
and the requirements of the competent authorities and
Berufsgenossenschaften are to be observed in the The relative humidity in the moulding shop is to be
storage, preparation and processing of the reactive kept as low as practicable, preferably below 70 %, and
resin compounds and reinforcing media. no substantial variation shall be permitted which
would cause moisture to condense on modulus and
materials.
Temperature and humidity monitoring equipment is to
B. Company Authorization be provided in sufficient quantity and appropriate
The manufacture of GRP components for submersi- locations. Where dictated by the environmental condi-
bles in accordance with these Rules may only take tions, continuous recording monitoring equipment
place in specialist companies which have been author- may be required. The measuring instruments are to be
ized by GL to carry out such work. Authorization will recalibrated at intervals of not more than 2 years.
be restricted to companies possessing suitably trained The ventilation system shall not cause excessive
specialist personnel and the necessary technical evaporation of the resin monomer, and precautions are
equipment for moulding, machining, heat treating and to be taken to ensure the exclusion of draughts.
quality assurance in accordance with the best modern
practice. The working areas are to be suitably illuminated. Pre-
cautions are to be taken to prevent the resin cure from
Authorization by GL is to be applied for before manu- being affected by direct sunlight or artificial lighting.
facture begins.
Machines which generate dust may not be operated
until the laminating and sticking phases have been
fully concluded. It is recommended that machines of
this type should be installed in separate rooms.
C. Workshop Requirements
3. Storage areas
1. General
The resin are to be stored in dry, well ventilated con-
The production and storage buildings are to be of suit- ditions at temperatures between 10 °C and 20 °C or in
able construction and equipped to provide the required accordance with the resin manufacturer's recommen-
environment. Contamination is to be minimized by dations.
subdivision into separate materials storage and manu-
facturing areas, or acceptable alternative arrangements Where the resins are stored outside the moulding shop,
are to be made. they are to be brought into the moulding shop to allow
the resin to reach the required working temperature
Workshops and equipment are to be maintained in before being used.
clean, efficient working order and are to be essentially
free from hardened resin debris, surplus glass fibre Catalyst and accelerators are to be stored separately in
and any other material or equipment not essential to clean, dry and well ventilated conditions in accor-
the moulding process. dance with the manufacturer's recommendations.
Fillers and additives are to be stored in closed contain-
2. Moulding shop ers which are impervious to dust and humidity.
Where the conventional hand lay-up process is used a Reinforcements are to be stored in dust-free and dry
uniform shop temperature of not less than 16 °C and conditions in accordance with the manufacturer's rec-
in general not less than 25 °C is to be maintained ommendations.
Chapter 1 Appendix C D Design and Manufacture of GRP Constructions I - Part 5
Page C–2 GL 1998

Where the glass materials are stored outside the cut- consolidated to give the required glass content by
ting area, they are to be brought into the cutting area weight.
to allow the material to reach the workshop tempera-
ture before being used. The amount of material laid "wet-on-wet" is to be
limited to avoid excessive heat generation.

4. Materials handling Laminating is to be carried out in a sequence such that


the time lapse between the application of the succes-
The arrangements for the reception and handling of sive layers is within the prescribed limits. Forming
materials are to be such that the materials suffer no and bonding of structural members are to be kept
contamination or degradation and are properly identi- within these limits, and, where this is not practicable,
fiable at all times. Storage is to be so arranged that the surface of the laminate is to be abraded to improve
materials are used in order of receipt, wherever possi- the bond.
ble. Materials are not to be used after the manufac-
turer's expiry date except with the prior agreement of When laminating is interrupted, so that the exposed
the manufacturer of the material and the Surveyor. resin gels, the first of any subsequent layers of rein-
forcement to be laid in that area is to be of the
The arrangements for the release of materials from chopped glass fibre type.
store are to ensure that they are of the appropriate
grade or formulation. Any surplus resin or ancillary Reinforcements are to be arranged to maintain a conti-
material issued is not to be returned to the parent stock nuity of strength throughout the laminate.
or bulk storage. At joints and seams, each reinforcement layer must be
overlapped by at least 25 mm for each 600 g/m2 of
glass reinforcement. If it is impossible to avoid cutting
into reinforcement layers, the cut edges must be ap-
D. Construction Process propriately overlapped or reinforcing strips must be
provided.
1. Moulds When the quality of the laminates being produced is in
Moulds are to be constructed of a suitable material and doubt, GL may request that suitable test panels similar
adequately stiffened to maintain their overall shape to the actual construction be manufactured and tested.
and fairness of form. GL's previous consent is required where laminating
The materials used for the construction of the moulds processes other than the hand lay-up process re to be
are not to affect the resin curs. used. In such cases GL reserve the right to demand
that special process test are to be performed.
Sufficient external and internal staging is to be pro-
vided to allow satisfactory access to the work of lami- 3. Construction detail
nation.
Changes in laminate thickness are to be effected by a
2. Laminating (hand lay-up process) gradual taper of not less than 25 mm per 600 g/m2.
Where the construction changes from sandwich lami-
Moulds are to be thoroughly cleaned, dried and al- nate to a solid laminate, the thickness of the core ma-
lowed to condition to the ship temperature before terials is to be reduced by a gradual type of not less
being treated with a suitable release system. Release than 2 : 1.
agents are to have no inhibiting effect on the gel coat
resin. In general framing and stiffening sections are to be
built up layer by layer on to the laminate while it is
The gel coat resin is to be applied by brush, roller or still in the uncured state. Where these sections inter-
spraying device to give a uniform film thickness of sect, particular attention is to be given to ensuring
between 0,4 and 0,6 mm. continuity of strength.
Gel coats are not be left exposed longer than is rec- Discontinuities and hard points in the structure are to
ommended by the resin manufacturer before the appli- be avoided, and where the strength of a stiffening
cation of the first layer of reinforcement. The gel coat member is impaired by attachment of fitting, openings
is to be backed up by a lightweight reinforcement, not etc., compensation is to be provided.
exceeding 450 g/m2 in weight, which is to be applied
and consolidated by gentle rolling to give a glass con- Where items are prefabricated outside the mould they
tent not exceeding 0,4 by weight. are to be connected by angles formed by layers of
reinforcement rolled up in situ and moulded to the
Sandwich constructions built on a male plug mould adjacent structure within the acceptable cure period.
have to be given a heavy coat of resin or resin-based
compound on the outer surface prior to painting. Laminates may be fastened mechanically provided
that the strength of the joint is not impared, that the
All mouldings are to be manufactured from layers of fastenings are of a corrosion resistant metal and are
reinforcement, laid in the approved sequence and di- spaced and positioned to meet the design require-
rection, each layer being thoroughly impregnated and ments. The fastenings are to be of an acceptable type
I - Part 5 Appendix C E Design and Manufacture of GRP Constructions Chapter 1
GL 1998 Page C–3

with washer plates of compatible material. The cut 1.6 The cast resin characteristics required by 1.4
edges of the laminate and the fastening holes are to be and 1.5 are to be those obtained from tests conducted
sealed. on specimens prepared using a conventional cold
curing system, matured at a room temperature of not
Backing and/or insert pads of adequate strength are to
less than 18 °C for 24 hours before being post-cured at
be fitted at the attachment of fittings. The contact area
a temperature not exceeding 40 °C for a period of 16
of these pads is to be suitably prepared and free from hours. The tests are to be conducted in accordance
contamination.
with the relevant ISO standards.
In sandwich laminates, inserts of a material capable of
resisting crushing and design loads are to be fitted at 1.7 Laminates manufactured from the above
bolted connections and fittings. The insert is to be well resins are to have mechanical properties in accordance
bonded to the core material and to the laminate skins. with 7.2. The material manufacturer's documentary
evidence of these properties is to be submitted before
4. Release and curing construction begins.

After completion of the lay-up the moulding is to be


left in the mould for a period to allow the resin to 2. Catalysts and accelerators
harden before being removed. This period can vary
with the type of resin and the complexity of the 2.1 A catalyst is a material which initiates po-
moulding, but is to be not less than 12 hours or that lymerization of the resin.
recommended by the resin manufacturer. An accelerator is a material which increases the hard-
Large assemblies are to be adequately braced and ening rate of the catalyzed resin.
supported for removal from the moulds and also dur-
ing the fitting-out period. 2.2 The type and amount of the catalyst and ac-
celerator are to be those indicated by the resin manu-
Mouldings are to be stabilized in the moulding envi- facturer for the particular application, so that the resin
ronment for at least 24 hours, or that recommended by will cure without the application of local heat.
the resin manufacturer before the application of any
special cure treatment, details of which are to be sub-
mitted. 3. Colour pigments

3.1 The pigment types are to be such that the


final cure of the resin is not affected.
E. Materials
3.2 The pigment may be added to the resin by the
manufacturer or the moulder and when added by the
1. Unsaturated polyester resin moulder, is to be a paste dispersal in the same of a
compatible polyester resin.
1.1 The unsaturated polyester resin systems used
are to be of a type that will cure without the applica-
3.3 The amount of pigment added is not to ex-
tion of local heat.
ceed that indicated by the resin manufacturer for a
satisfactory depth of colour, and in no case is to ex-
1.2 The laminating and gel coat resins, as sup- ceed 5 % by weight of the resin in the system.
plied by the manufacturer, are to be of a type recom-
mended for marine application and are to have good
3.4 No pigments are to be used in the laminating
abrasion resistance and ageing stability Orthophatalic
resins forming the internal surface of fuel and water
resins are not to be used for the gel coat of outer part.
tanks.
1.3 The only additives in the gel coat resin are to
be colour pigments and thixotropic agents. 4. Fillers

1.4 The minimum characteristics of the cast lami- 4.1 Fillers are not to prejudice the characteristics
nating and gel coat resin are to be: of the resins.
Elongation at break
4.2 The type and amount of filler which may be
Minimum 2,5 % for gel coat resins
added to a resin are not to alter significantly the vis-
2,0 % for laminating resins
cosity of the resin, and the amount is not to exceed
Water absorption 13 % (including 3 % thixotropic filler) by weight of
Maximum 60 mg after 7 days the resin or the proportion recommended by the manu-
facturer, whichever is less.
1.5 In addition to the requirements of 5.1.4 the
cast laminating resin is to have a heat distortion tem- 4.3 Fillers are not to be used in the structural
perature of not less than 53 °C. laminates of oil fuel and water tanks.
Chapter 1 Appendix C E Design and Manufacture of GRP Constructions I - Part 5
Page C–4 GL 1998

4.4 Fillers are to be uniformly dispersed in the laminating resins and the heat distortion temperature
resin mix. of the laminating resin.

4.5 Fillers of calcium carbonate or similar alka- 7.2 The laminates manufactured from the resins
line type are not to be used in fire retardant laminates. and reinforcements indicated in 1. and 6. are to have a
minimum glass content by weight of 0,30 and me-
chanical properties not less than the following:
5. Fire retardants
Where fire retardant laminates are obtained by incor- Ultimate tensile strength 85 N/mm2
porating additives in the resin system the type and Tensile modulus 6350 N/mm2
quantity of the additives are to be those recommended
by the manufacturer and are not to alter significantly Ultimate flexural strength 152 N/mm2
the viscosity of the resin or the mechanical properties Flexural modulus 5206 N/mm2
of the laminates produced.
Ultimate compressive strength 117 N/mm2
6. Glass fibre reinforcements Compressive modulus 6000 N/mm2

6.1 Glass fibre reinforcements are to be manu- Ultimate shear strength 62 N/mm2
factured from low-alkaline borosilicate "E" glass with Shear modulus 2750 N/mm2
an alkali content of not more than 1 % expressed as
Na2O. Interlaminar shear strength 17,25 N/mm2

6.2 Glass fibre reinforcements are to have been 7.3 Where the glass reinforcement content by
treated with a sized, finish and binder as appropriate weight in a laminate is other than 0,30, it is to be as-
and are to be suitable for use with polyester resin and sumed for scantling calculations that the basic me-
to be of a type that will provide good wet strength and chanical properties are as determined the following
ageing properties when the reinforcements are incor- formulae:
porated in a laminate.
Ultimate tensile strength
6.3 Glass reinforcements are to be of the above 1278G 2c − 510 G c + 123 N/mm2
type and grade and may consist of:
Tensile modulus
– Chopped strand or continuous filament mat
( 37, 0 G c − 4, 75)103 N/mm2
– Woven rovings
Ultimate flexural strength
– Unidirectional rovings
502 G 2c + 106,8 N/mm2
– Cloth fabrics
Ultimate compressive strength
– Composite reinforcements.
( 33, 4 G 2
c )
+ 2, 2 103 N/mm2
6.4 The materials are to be sufficiently free from
Ultimate compressive strength
imperfections, discolorations, foreign matter, moisture
and other defects as not to affect the quality of the 150G c + 72 N/mm2
laminates produced.
Compressive modulus
6.5 The reinforcements when moulded into a ( 40, 0 G 2
c )
+ 6, 0 103 N/mm2
laminate are to have mechanical properties in accor-
dance with 7.2. The material manufacturer's docu- Ultimate shear strength
mentary evidence of these properties is to be submit- 80 G c + 38 N/mm2
ted before construction begins.
Shear modulus
7. Laminate material properties (17 G c + 2, 24 )103 N/mm2

7.1 The mechanical properties of laminates, con- Interlaminar shear strength


structed with the unsaturated polyester resin systems 22,5 − 17,5 G N/mm2
and glass fibre reinforcements indicated in 1. to 6. can
vary considerably depending upon the actual types of For unidirectional rovings the tensile properties are to
material, methods and conditions under which they are be determined by applying the following formulae:
manufactured. When selecting the resin system, con- Ultimate tensile strength (UDR)
sideration should be given by the builder to the com-
patibility of the elongation at break of the gel coat and 1900 G 2c −1500 G c + 560 N/mm2
I - Part 5 Appendix C E Design and Manufacture of GRP Constructions Chapter 1
GL 1998 Page C–5

Tensile modulus (UDR) not exceeding 40 °C for a period of 16 hours. When


the flexual properties are determined, the moulded
(143G 2
c )
− 42, 7 103 N/mm2 surface is to be in tension. The tests are to be con-
ducted in accordance with ISO standards.
where
7.8 In composite laminates, woven reinforcement
Gc glass content of laminate by weight provided that the interlaminar shear strength is not less
(exlcuding gel coat) determined by than that required for the particular laminate (see 7.3).
formula:
7.9 The tests are to be carried out on specimens
2,56 cut from laminates manufactured by the builder from
Gc =
+ 1,36
3072T the same materials and construction sequences as are
W
proposed for the construction proper.
where
T [mm] nominal laminate thickness determined 8. Core materials for sandwich construction
in accordance with 7.4
8.1 Rigid expanded plastics are to satisfy the
W [g/m2] total weight of glass reinforcement in following requirements. They shall
laminate.
a) be of closed-cell type and impervious to water,
The required values shall be the minimum values, in fuel and oil with good ageing stability,
both the 0° ad 90° orientations for bidirectional and
random in place reinforcements and 0° for unidirec- b) have low water absorption,
tional reinforcements. c) be compatible with the polyester resin,

7.4 The nominal laminate thickness T (excluding d) have good strength retention at 60 °C,
the gel coat) for an assumed specific gravity of glass c) have characteristics and mechanical properties
and resin of 2,56 and 1,2 respectively, is the aggregate not less than those indicated in Table 1.
of the thickness t of each layer of reinforcement in the
laminate calculated as follows: 8.2 End-grain balsa is to satisfy the following
requirements. It shall
w 2,56
t = ⋅ −1,36 mm a) have been chemically treated against fungal and
3072 g c
insect attack and kiln dried shortly after felling,
where b) have been sterilized,
w [g/m2] weight of reinforcement layer c) have been homogenized,
gc glass content of layer by weight. d) have an average moisture content of 12 %,
e) if manufactured into formable sheets of small
7.5 Reinforcements are to be thoroughly impreg- blocks, the open weave backing material and ad-
nated with resin and consolidated so that the glass hesive are to be respectively compatible and
content by weight of the various reinforcements gener- soluble with the polyester laminating resin,
ally does not exceed the following:
f) have characteristics and mechanical properties
Chopped strand mat or sprayed fibres 0,34 not less than those indicated in Table 2.
Woven rovings 0,50
8.3 Other core materials will be individually
Unidirectional rovings 0,54 considered by reference to their characteristics and
Cloth fabrics 0,50 intended applications.

7.6 The laminate mechanical properties, the 9. Materials for integrated structural mem-
nominal thickness and the weight, type and glass con- bers
tent of the individual reinforcements to be used are to
be indicated on the construction drawings. Metals such as steel or aluminium alloys used in the
construction are to be of a quality suitable for the pur-
pose intended. Where structural members or compo-
7.7 If the mechanical properties of proposed
nents manufactured from these materials are to be
laminates differ from those determined in accordance
encapsulated or structurally bonded to laminates, the
with 7.3 the properties and glass content will be sub-
material shall not adversely affect the cure of the resin
jected to compulsory confirmation by testing.
system, and the surface area of the component that
The test specimens are to be cut from laminates ma- will be in contact with the resin is to be thoroughly
tured at a room temperature of between 16 °C to 20 °C cleaned, degreased and, where practicable, either shot
for 24 hours before being post-cured at a temperature blasted or abraded to provided a key.
Chapter 1 Appendix C E Design and Manufacture of GRP Constructions I - Part 5
Page C–6 GL 1998

Table 1

Apparent Strength values Modulus of elasticity


density [N/mm2] [N/mm2]
Material
[kg/m3] Tensile Compressive Shear Compressive Shear
Polyurethane (PU) 96
0,85 0,60 0,50 17,2 8,5
Polyvinylchloride (PVC) 60

Table 2 Minimum characteristics and mechanical properties of end-grain balsa

Strength values [N/mm2] Compressive Shear


modulus of modulus
Apparent elasticity of elasti-
Compressive Tensile city
density [N/mm2]

Direction of stress Shear Direction of stress

[kg/m3] Parallel to Perpendicu- Parallel to Perpendicu- Parallel Perpen- [N/mm2]


grain lar to grain grain lar to grain to grain dicular
to grain
96 5,00 0,35 9,0 0,44 1,10 2,275 35,2 105

You might also like