You are on page 1of 4

METHOD STATEMENT

CORING ON ASPHALT PAVEMENT


Document No. AAS-MS38/2010 Rev. 1

SYPNOSIS
This method statement provides the work procedures for the coring works on
the asphalt concrete pavement as required for the below project.

PROJECT : Bahrain International Airport,


Investigation of Taxiway Shoulders

CLIENT : Materials Engineering Directorate,


Ministry of Works and Housing
(MED)

________________________________________________________________________________________________________________________________________
METHOD STATEMENT – CORING ON ASPHALT PAVEMENT AAS-MS38/2010 Rev. 1/PM
Page 1 of 4
1. SCOPE

Two cores shall be taken adjacent to the 17 trial pit locations to give a total of 34
cores (17 for Al Hoty’s testing and the other 12 & 5 as reserved for the specialist
consultant, RSK STATS, and MED, respectively). The material to be sampled will be
an asphalt concrete pavement including the base/sub-base course.

2. REFERENCES (Attach hard copies of all drawings/layout to method statement i.e.


bullets 2, 3 & 4)

• Technical Submission No. 281210-001 dated March 2010


• As Built Drawing General Arrangement of Pavement Type, Drainage Layout &
Delethalisation Area, Drg. Nos. J20327A/GAB/AB/001 to 007 Revision 1
• Drg. No. BIA/AAS-RSK/002 Proposed Trial Pit Locations (7sheets)
BIA / CAA Existing Airport Layout
3. RESOURCES

Major plant to be used includes:


• Generator 3500HP
• Concrete Drill Machine with core barrels & drill bits
• Plate compactor
• Pick-up vehicle for hauling/transporting

4. RESPONSIBILITIES

General Manager : Ensures that resources are available and sufficient to meet the
work program. Reviews and monitors the resources, work
schedule and accomplishments on a daily basis.

Site Engineer : Liaise with CAA/SPD/MED personnel, arrange work permits,


overall supervision of the works to ensure work procedures are
being followed and works are executed as per the arranged
schedule.

Geologist : Records all cored sample information to include proper


identification of strata, thickness and other relevant information.

Supervisor/Sr. Inspector: Direct supervision of the area and ensure proper working
practices. Also acts as safety officer to ensure safe moving of
plants/equipments within the work area/and that PPEs (spell out
what are these) are worn at all times.

Technician : Receives and executes the instruction from the senior inspector
or site engineer for the proper execution of all in-situ testing and
inspection.

Airside Escort : An airport authority provided by CAA/SPD who shall coordinate


with the control tower and guide the working team in their
movement in the area.

________________________________________________________________________________________________________________________________________
METHOD STATEMENT – CORING ON ASPHALT PAVEMENT AAS-MS38/2010 Rev. 1/PM
Page 2 of 4
5. HEALTH & SAFETY

Access to the work area will be through the designated route as escorted by
airport authority assigned to this project.

Safety procedures shall be explained to the supervisor/engineer and relayed to all


the staff during the tool box meeting which shall be done prior to each day’s work.

CAA Contractors Safety Guidelines shall be implemented.

Proper PPEs shall be worn at all times in the work area.

6. SEQUENCE OF WORK

6.1 Position the core drill with the core barrel perpendicular to the asphalt
concrete surface at the specified sampling location, approximately
100mm from the edge of the trial pit. The machine shall be fixed on the
pavement with anchor bolts.
6.2 Turn on the core barrel equipment and lower the rotating barrel steadily
with just sufficient pressure to start cutting.
6.3Continue the coring until the core barrel projects through the pavement
layers up to the top of subgrade level (elevation as determined in the
trial pit).
6.4 Stop the barrel rotation and turn off the equipment. Raise the core
barrel and remove the core from the hole using core retrieval
equipment.
6.5 Immediately collect the cores and put into plastic bag. Mark the plastic
bag containing the cored sample with appropriate sample number
identification.
6.6 Place the sample in a container to maintain the temperature for
the cores until delivered to the laboratory for testing.
6.7 Backfill the core holes with cold asphalt mix and compact with hand held
compactor. Core holes shall be dry and clean prior to backfilling.
6.8 The geologist records all details regarding the cored sample.

RECORDS on the cored sample will include but not limited to the following
information;
✔ Project Name / Contract No.
✔ Core sample reference Number
✔ Date of Execution / Completion
✔ Dimensions and sketch of cored sample
✔ Description of strata including its thickness
✔ Details of services encountered, if any
✔ Photographic records

7. ASSUMPTION OF WORKING TIME

________________________________________________________________________________________________________________________________________
METHOD STATEMENT – CORING ON ASPHALT PAVEMENT AAS-MS38/2010 Rev. 1/PM
Page 3 of 4
Each day works for the above sequence of work will be contained within the time
window provided by BAC/SPD. To date time window is from 0300H to 0600H.

MINIMUM duration / time frame budget for the above sequence of work are
distributed as follows:
a. Mobilization / setting-up.
b. Coring works = approx. 30 mins. each
(full depth of approx. t=300mm, wearing course down to subgrade level).
c. Retrieval of cored sample & tagging = approx. 5 mins. each
d. Core logging by Geologist = approx. 5 mins. each.
e. Reinstatement works (backfilling, levelling, compacting) – approx. 10 mins.
each.
f. Demobilization from the work area .

________________________________________________________________________________________________________________________________________
METHOD STATEMENT – CORING ON ASPHALT PAVEMENT AAS-MS38/2010 Rev. 1/PM
Page 4 of 4

You might also like