You are on page 1of 13

9.

Open pit mining


9.1 Introduction

9.1.1 Basic description of open pit mining

Open pit mining is applied to the extraction of near­surface deposits. Overburden removal 
(stripping) and mining are carried out systematically from a series of benches (steps) as the pit is 
progressively deepened. The bench layout is designed to produce an overall slope angle that is 
compatible with slope stability so that an open pit resembles an inverted cone. As the base of the 
pit is deepened, the upper benches are pushed out so as to maintain the required slope angle. 
Overburden is stripped from benches to uncover the deposit and transported to a dump at some 
point remote from the operation itself. As the depth increases the ratio of overburden to volume of 
ore extracted steadily increases and, at a certain point, the cost of overburden removal makes the 
operation uneconomic. The remainder of the deposit might then be worked by underground 
mining.
Advantages of surface mining compared with underground mining.
• Higher Productivity ­ due to: greater degree of mechanisation, larger equipment can be used ­ 
economies of scale, fewer personnel required
• Lower operating costs per tonne ­ due to: higher productivity, concentration of production, 
less constraint on production level (easier materials handling)
• Lower grade deposits can be mined
• Reduced development time (generally). Therefore more favourable cash flow and quicker 
repayment of capital investment.
• Greater geological certainty.
• Safer operations
Disadvantages of surface mines:
• Large proportion of waste to ore.
• High level of environmental impact. 
• Affected by climatic conditions.
• Depth limit

Fig. 9.1: Palabora open pit copper mine, South Africa

59530725.doc 8 8/3/2011
9.1.2 Pit Limits

The pit limits are the vertical and lateral extent to which the open pit mining may be economically 
conducted. Establishment of the pit limits is the first stage in mine planning (Laurich 1990). They 
determine the:
• amount of economically recoverable ore,
• metal content,
• volume of waste to be excavated and moved,
• location of waste dumps, tailings lagoons, processing plant, access roads and all other surface 
facilities.

9.2 Stripping ratio

9.2.1 Definitions

The pit limits and sequence of mining are determined ultimately by economics. The concept of 
stripping ratio (SR) is the method of analysis used. It is a measure of the amount of waste that 
must be removed in order to mine one unit of ore. 

Grade The content of valuable metal (%, g/t or kg/t) in a mineral.
Cut­off grade The grade at which the value of the metal equals the cost of mining and 
processing the mineral.
Ore Mineral that is above the cut­off grade
Waste Mineral that is below the cut­off grade

The SR at any level of the pit is defined as:

volume of waste removed  m3 


SR = 
 t 

tonnes of ore recovered  

SR  is   also  sometimes   expressed   as   tonnes/tonne   (tonnage   of   ore   removed   per   tonne   of   ore). 
However, the first definition is more convenient as the costs of waste removal are directly related 
to its volume and the revenue from the ore is directly related to its mass.

The Pit Limit is defined by the economic stripping ratio SRecon. This value is the stripping ratio at 
which the costs of mining and processing the ore and stripping the waste are equal to the revenue 
from the ore.

revenue from ore ($/t) - ore mining cost ($/t) - ore processing cost ($/t)
SR econ (Bm 3 /t) =
waste stripping cost ($/Bm 3 )

9.2.2 Simple stripping ratio calculation

To determine the pit limit for a simple orebody (Figure 9.2) 
• Calculate the economic  SR:
• Multiply by ore density to convert to m3/m3 (multiplying top line of SR equation to obtain net 
value of ore in $/Bm3

59530725.doc 9 8/3/2011
• Estimate on the orebody section where the pit limit may lie and draw in line ABC at the 
required slope angle
• The SR at this point = AB/BC m3/m3
• Compare with economic SR; if lower, move line down to, say A1B1C1; if higher, move back up 
to A2B2C2
• Continue until SR represented by line on section equals economic SR

In practice, the procedure is much more complicated; for example, the ore grade will usually 
vary throughout the orebody. A simple solution is to express the economic SR as a function of 
grade  then draw  a straight  line  graph  of  economic  SR vs  grade.  For  any grade  value  in  the 
orebody, the corresponding economic SR can be read off the graph.

Fig. 9.2: Simple pit limit estimation

9.3 Overburden stripping strategies

Described below are the four basic types of stripping schedule. The first two are extreme cases and 
would not be applied in practice. (Bucyrus­Erie 1979, Fourie & Dohm,1992)

9.3.1 Declining Stripping Ratio Method (Figure 9.3)

As each bench of ore is mined, all the waste on that bench is removed to the pit limit.

Advantages:
• good operating space
• good accessibility to ore on next bench,
• all equipment working on same level,
• no contamination from waste blasting above the ore,
• equipment requirements a minimum towards the depletion of the orebody.
• operating costs tend to be constant in later years as the increased mining cost with depth is 
offset by the decreased stripping ratio.

Disadvantage: overall operating costs are maximum during the initial years when maximum 
profits are required to handle interest charges and repay the project capital investment.

59530725.doc 10 8/3/2011
Fig. 9.3: Reducing stripping ratio method

9.3.2 Increasing Stripping Ratio Method (Figure 9.4)
Only sufficient stripping required to uncover the ore is carried out. This method allows for 
maximum profit in the initial years of operation and greatly reduces the investment risk in waste 
removal for ore to be mined at a later date. It may be applied where the economics of the 
operation and cut­off stripping ratio is liable to change on very short notice. The main 
disadvantage is the impracticability of operating a large number of stacked narrow benches 
simultaneously to meet regular production requirements.

Fig. 9.4: Increasing stripping ratio method

9.3.3 Constant Stripping Ratio Method (Figure 9.5)
Waste is removed at a rate approximately equal to the overall stripping ratio. The method is a 
compromise that removes the extreme conditions of the former two methods described. 
Equipment fleet size and labour requirements are relatively constant.

Fig. 9.5: Constant stripping ratio method
59530725.doc 11 8/3/2011
9.3.4 Phased Mining Sequence (Figure 9.6)
In practice, the optimum stripping sequence for a large deposit would feature a low stripping ratio 
in the initial and final years of operation. This plan has the following advantages.
• A high level of profit can be generated at the outset to improve the cash flow.
• The labour and equipment fleet can be built up to maximum size over a period of time. This 
approach is also advantageous from a cashflow point of view.
• Labour and equipment requirements decrease gradually towards the end of the mine life.
• Distinct mining and stripping areas can be operated simultaneously, allowing for flexibility in 
planning.
• The number of mining and stripping faces required is not too high.
• In a large orebody, the mining and stripping areas are sufficiently wide to create good 
operational conditions.

Fig. 9.6: Phased mining sequence

9.4 Bench design

9.4.1 Bench height

Bench height is the most important parameter as it largely determines the other dimensions. 
Values range from about 2.5 m for small gold mines to 20 m for large open pits. The final bench 
height may be sub­divided for extraction purposes into a number of sub­benches or flitches. 
Bench height is influenced by:
1. excavating equipment dimensions (reach, operating height)
2. size and geometry of orebody ­ small benches used for narrow lodes or lenses in order to 
minimise dilution and facilitate good grade control.
Bench height is no longer limited by drilling depth. The prime determining parameter is the 
maximum digging height dimension of a shovel. Table 9.1 gives some advantages and 
disadvantages of maximizing the bench height.
Table 9.1: Features of high wide benches
Advantages Disadvantages
High productivity and efficiency Less selectivity
Can use large scale equipment More dilution
Larger blasts Fewer working places, therefore less flexibility
Fewer equipment moves and setups Flatter working slopes (larger shovels)
Facilitates more effective supervision

59530725.doc 12 8/3/2011
Generally, it is more advantageous, in terms of drilling and shovel efficiency, to design benches as 
high as possible. 

a) Drilling Efficiency

A greater bench height reduces set­up time per meter drilled. Also, for a given blast design, the 
subgrade drilling required is independent of the bench height. This means that the greater the 
bench height, the greater the ‘tonnage yield’ per meter drilled or per kg of explosive used. 
Consider bench heights of 10m and 12m, each to be drilled on a 5m x 5m pattern with a 1m 
subgrade. The respective drilling yields are:

Burden x S pacing x B ench Heigh t x Densit y


Drilling Y ield =
Hole Depth

Assuming rock density = 2.5 tonnes/m3, for a 10m bench:

5 x 5 x 10 x 2.5
Drilling Y ield = = 56.8 tonnes / m
10 + 1

For a 12m bench:
5 x 5 x 12 x 2.5
Drilling Y ield = = 57.7 tonnes / m
12 + 1

The yield for the 12 m bench represents an increase in drilling yield of some 1.6%. Although 
seemingly small, for 10,000m of drilling, it would result in an extra 9000 tonnes production. 
Similarly, drilling costs per tonne are reduced as bench height is increased

b) Shovel Efficiency

Increased bench height also improves overall productivity of shovels, FELs, or excavators. The 
number of rows in a blasting pattern is generally governed by the hole diameter and explosive 
type. If these parameters are fixed for a given operation, the total volume of bench that can be 
blasted at once depends on the bench height. The greater the volume of broken ground, the lower 
the number of times a shovel has to be moved in order for blasting operations to be carried out.

9.4.2 Bench width

Figure 9.7a shows the common terminology for open pit slopes. A bench is a horizontal ledge from 
which drilling, blasting, excavation and loading of ore or waste is carried out. A Working bench is 
one that is in the process of being mined. The width extracted from the working bench is called the 
cut. The working bench width is determined by the dimensions of trucks and the required reach of 
excavating equipment. Figure 9.7b illustrates a slope profile cutting across an operating bench. It 
shows a narrow bench width of only some 3m, not sufficiently wide to accommodate equipment. 
However, each bench is systematically mined from one end, giving adequate room for drilling 
rigs, shovels and trucks. 

After the cut has been removed a bench of width typically 2.5­3.0 m is left to catch and collect 
material, which slides down from upper benches. Normally, the bench slope angle is 75­80 o and a 
berm every second or third bench is sufficient.

59530725.doc 13 8/3/2011
9.4.3 Bench angle

Bench faces are normally mined as steeply as possible. The steeper the bench angle, the smaller the 
stripping ratio. Safe angles are determined by:
• geotechnical considerations, taking into account the cohesive and frictional properties of the 
rock and the character, spacing and orientation of joints and bedding planes.
• the dip of the orebody.
There are two angles which define a bench design:

Overall slope angle The angle consistent with slope stability over the full height/depth of the 
mine. Usually lies between 45o and 60o. The overall angle is a function of 
the bench face angle and the bench width. Note that  a haul road on a pit 
slope will flatten the overall slope angle.
Bench face angle The maximum angle consistent with stability of a single bench (say, 5 to 
10 m in height). Typical values lie between 60o and 80o.

The overall slope angle is less than the bench face angle because the larger the slope, the more 
planes of weakness it has.

Fig. 9.7a: Pit slope cross­section, with typical dimensions Fig. 9.7b Geometry of working bench 
(Atkinson 1992)

9.5 Method of working benches

Operations on each bench are conducted in cycles; typically:
1. Grade control ­ mark out ore zones with tape or survey staffs
2. Drill blastholes
3. Charge holes
4. Fire holes
5. Excavate blasted material and load into trucks for haulage out of pit 
6. Clean bench and prepare for drilling

59530725.doc 14 8/3/2011
9.5.1 Mining direction

Orebody lenses may be excavated in either a transverse or longtudinal direction. A transverse 
mining direction (digging in a direction normal to the ore vein) is more suitable for thin lenses. It 
allows better grade control and less dilution. With a thicker lens, it may be possible with 
longitudinal extraction to blast and load the ore, leaving the waste temporarily in­situ. The 
number of working faces is determined by the required production rate and equipment capacities. 
Figure 9.8 illustrates how excavation can take place simultaneously and on multiple levels. 

Fig. 9.8: Mining on multiple benches (Hustrulid & Kuchta 1995)

9.5.2 Selection of excavating equipment

In a mine, certain production requirements have to be satisfied and in a civil construction project 
the operation will have to comply with the project schedule. As equipment is very expensive in 
terms of capital or contract and operating costs, its utilisation should be maximised in order to 
minimise the unit costs of earth moving.

Table 9.2: Guidelines for selection of excavating equipment
Type of machine Application
Electric rope shovel Large benches
Hydraulic excavator (front end loader)
Back hoe ­ sits on top of bench, digging down Small benches only (< 5.0 m)
Ripper , Impact ripper Medium­hard material, low depth
Mechanical cutter (drum laced with picks) Medium­hard material
Permits very selective mining
Bulldozer, Scraper Soft material, low depth

In rock and earth­moving projects, planners are usually concerned with in­situ volumes as the 
quantities can readily be determined from excavation or mine plans. The basic unit of 
measurement is termed the bank cubic meter (BCM or Bm3). However, manufacturers give 
equipment bucket capacities in terms of the nominal bucket capacity, the volume enclosed within 
the perimeter of the bucket. The first task in a productivity determination exercise is to convert 
this measurement into BCM units. The tables given in this section are from Atkinson (1992), unless 

59530725.doc 15 8/3/2011
otherwise stated. Figure 9.9 shows the two alternative methods of excavating a bench and of 
spotting trucks.

a) Parallel cut b) Front cut
Fig. 9.9: Methods of excavating benches (Hustrulid & Kuchta 1995)

9.6 Haul road layout

The form of haul roads may be spiral or switchback (zig­zag). They may also be either temporary 
or permanent, depending on the configuration of the orebody. Where benches are being 
systematically worked all round the pit as it is deepened, haul roads will be mined through and 
new ones formed as the pit develops. Often, however, it is possible to construct permanent haul 
roads at one side of the pit. This would be the case for a dipping orebody, where the permanent 
haul road could be located at the footwall and extended as the pit deepened (figure 9.10).  Note 
that the inclusion of a haul road in a pit wall will lower the overall slope angle and hence increase 
the stripping ratio. Where the orebody dips at a shallower angle than the stable pit slope, 
constructing the haul road as a switchback on the footwall will take the overall pit slope close to 
the orebody dip. The hanging wall slope, formed without a haul road, can be made as steep as 
possible, consistent with slope stability. 

Fig. 9.10: Illustration of how permanent haul roads can be established in a footwall

Factors determining selection of layout include the following. (Atkinson 1992)
1. The switchback layout allows a permanent haul road to be located at one side of the pit.
2. In large pits, a spiral layout can result in a haulage distance that is too great.
3. Areas where potential slope stability hazards exist should be avoided, possibly eliminating the 
spiral option.
59530725.doc 16 8/3/2011
4. The pit walls may be too steep to allow suitable bends to be formed for a switchback layout 
without greatly increasing the stripping ratio.
5. Tight bends associated with a switchback may be detrimental to truck and tyre life.
9.7 Haul road Construction

9.7.1 Road base

Good haul road design and construction promotes lower haulage costs and improved safety. 
Roads are constructed with three or four layers (figure 9.10):
1. Subgrade
2. Sub­base (optional)
3. Base
4. Wearing surface
The subgrade is the foundation layer, usually comprising compacted rock or soil. It must be 
strong enough to bear the loads associated with vehicles, which are transmitted from the road 
surface.
A sub­base may or may not be present, depending on local conditions. It is used where there is 
very weak subgrade material or in areas subject to severe frost. It is generally constructed from a 
clean, granular material.

Fig. 9.11: Haul road construction (Hustrulid & Kuchta 1995)
The base is a layer of very high stability and density. Its main purpose is to distribute the load 
from vehicle tyres. It also serves to insulate the subgrade from frost penetration and protect the 
upper wearing surface from any swelling or softening of the subgrade.
The top road layer is the wearing surface, which should provide traction, reduce rolling 
resistance, and resist abrasion, raveling and shear. It is formed usually of crushed rock.

9.7.2  Straight sections

The cross­section of an open pit haul road features a one or two­way travel lane, a safety berm and 
a drainage ditch (figure 9.11). For determination of lane width, a number of rules of thumb can be 
applied, in which the widest vehicles determine the road width. Three of these rules are:
• The clearance on each side of a truck should be equal to about half the truck width.
• For 2­way traffic, the lane width should be grater than or equal to 4 x the truck width.

59530725.doc 17 8/3/2011
• For a straight, even grade, one­lane haul road, the minimum road width is 2 times truck 
width; for two lanes, 3.5 times truck width. The road cross­section should also be raised or 
‘crowned’ slightly, to facilitate water run­off. The height of the crown is expressed in mm per 
meter of road width. A figure of 45 mm/m is typical.

Fig. 9.12: Typical 2­way road section (Hustrulid & Kuchta 1995)

Road Grade is determined from the truck performance charts with respect to speed and braking. 
Gradients of 4.5 to 6o (8 to 10%) are usually adopted, with rear­dump trucks being the preferred 
haulage unit. A 12% grade may be used for trolley­assist trucks. (Atkinson 1992)

9.7.3 Curves

For sharp curves, additional width must be included, both on the curve and the tangent to the 
curve, to cover the front and rear overhangs of the vehicle and the difficulty of negotiating the 
curve. A recommended additional allowance for a rear­dump truck on a 6m radius is 125% and a 
45m radius 118%. (Atkinson 1992.) Table 9.3 gives minimum turning radii for a range of trucks, 
classified according to gross weight. These radii can then be used in table 9.4 to find the 
recommended design width for single and double­lane curves of a particular minimum radius.

Table 9.3: Minimum truck turning radius (adapted from Hustrulid & Kuchta 1995)
Vehicle weight class Gross vehicle weight (tonnes) Minimum turning radius (m)
1 <45.5 5.8
2 45.5 – 91 7.3
3 91 – 181 9.4
4 >181 11.9

Table 9.4: Design widths for curves – rigid body trucks (adapted from Hustrulid & Kuchta 1995)
Radius on inner  Single­lane road Double­lane road
edge of road (m) Truck category Truck category
1 2 3 4 1 2 3 4
Minimum 8.8 10.4 13.7 21.3 15.5 18.3 24.1 37.5
7.6 8.2 10.4 13.4 20.7 14.6 18.3 23.2 36.3
15.2 7.6 9.4 12.5 19.2 13.4 16.5 21.9 33.5
30.5 7.3 8.8 11.9 18.0 12.8 15.5 21.0 31.4
45.7 7.3 8.8 11.9 17.7 12.5 15.2 20.7 30.8
61.0 7.0 8.8 11.6 17.4 12.2 14.6 19.8 29.9
59530725.doc 18 8/3/2011
Tangent 7.0 8.5 11.3 17.1 12.2 14.6 19.8 29.9

Depending on vehicle speeds and bend radius, a curve may also have to be banked (super 
elevation). Typical super elevations for mine haul roads and trucks are around 40mm per meter of 
road width (Hustrulid & Kuchta 1995). The distance required to make the transition from the 
normal cross­slope section to the super elevated section and back again (super elevation run­out) 
also needs to be considered.

9.8 Equipment

The following diagrams illustrate some modern equipment currently operating in Australian 
mines.
Fig. 9.13: Hitachi 20 m3 
hydraulic shovel loading into 
Komatsu 240 tonne truck

Fig. 9.14: The KOMATSU 
DEMAG H655S is the worlds 
largest proven hydraulic shovel 
at over 685t gross weight and 
35m3 bucket.

Fig. 9.15: The KOMATSU 
HAULPAK 930E is the largest 
truck in mining today and was 
the first to use AC drive. Over 
100 930E’s are operating 
worldwide, providing 
production up to 320t per cycle.

59530725.doc 19 8/3/2011
9.9 References

Atkinson T. Design and layout of haul roads. SME Mining Engineering Handbook, Vol 2, Chapt 13.4, 
pp1334­1342. SME (1992).
Bucyrus­Erie Company. Mine Planning. Surface Mining Supervisory Training Programme, Chapt 
3. Bucyrus­Erie Co. (1979).
Fourie GA, Dohm GC. Open pit planning and design. SME Mining Engineering Handbook, Vol 2, 
Chapt 13.1, pp1274­1297. SME (1992).
Hartman HL. Introductory Mining Engineering. Wiley (1987).
Hustrulid W, Kuchta M, (1995), Open Pit Mine Planning and Design, A A Balkema, Rotterdam.
Laurich R. Ultimate pit definition. Surface Mining, 2nd Edition, pp465­469. SME (1990).

59530725.doc 20 8/3/2011

You might also like