Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
C. Remedial action other lines. The system configuration and vector diagram after
This incident was discussed in detail with Grid Authorities the incident are shown in Fig. 4 and Fig. 5
and provision of back up DEF protection along with main-1 &
main-2 distance protection for all the lines was agreed upon.
411
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008