You are on page 1of 82

ABSTRACT

This project titled “Designing of storage tank for storing furnace oil” gives
and insight into the designing of a storage tank for storing furnace oil. Storage tanks
are constructed to store huge quantities of various petroleum products. Volatile
petroleum products are stored in floating roof tanks. In this project we intend to do
the design of floating roof tank for storage of crude oil.

The tank is designed according to API 650 (11TH Edition) Standards. Furnace
oil comes under Class B category; hence a cone roof type storage tank was selected.
The shell of the tank was designed in the most cost effective manner.

The height of the tank is 16m and Diameter is 12 m. Due to stability problem
the Height of the tank is restricted. The shell plates were designed according to their
availability. The wind guiders are provided for providing stiffness to the shell. The
roof was designed according to API 650 Standards.

The project deals with the design features of a fixed cone roof namely bottom
and annular plates, shell plates, wind girder, cooling water system, roof drain and
firefighting equipment.

KARPAGAM COLLEGE OF ENGINEERING 1


INTRODUCTION

COCHIN REFINERIES LIMITED was incorporated in the joint sector as a public


limited company in September 1963 at Ernakulam with technical collaboration and financial
participation from Philips Petroleum Company of USA and Duncan brothers of Kolkata.
Former Indian Prime Minister Mrs. Indira Gandhi dedicated KRL to the nation on 23
September 1966.
The name of the company was changed to Kochi Refineries Limited in May 2000.
KRL became a subsidiary company of Bharath Petroleum Corporation limited in April 2002.

Philips Petroleum International Corporation was the prime contractor for the
construction of our refinery. They entrusted the work to Pacific Procon Limited. Construction
work started in March 1964 and the first unit came on stream just after 29 months in
September 1966.

From the commissioning to date, the refinery under took three expansions in the
refining capacity and the installation of secondary processing facilities .The refinery then had
a design capacity of 2.5 metric million tons per annum (mmtpa) which was increased to 3.3
mmtpa in 1973. Production of liquefied petroleum gas (LPG) and aviation turbine fuel (ATF)
commenced after this expansion. Mumbai high court was first processed in 1977.

Refining capacity was further enhanced to 4.5 mmtpa in November 1984 when a
fluidized catalytic cracking unit (FCCU) was added. The secondary processing facilities (fpu,
fccu, lpg and gasoline merox unit) with a capacity of processing 1 mmpta VGO was
commissioned in 1985. It entered the petrochemical sector in 1989 when an aromatic
production facility with a design capacity of 87,200 tons per annum of benzene and 12,000
tons per annum of toluene was commissioned.

In Dec 1994, refining capacity was increased to 7.5 mmtpa (150,000 bpsd). A
fuel gas de-sulphurisation unit was installed as part of this project to minimize sulphur
dioxide emission. A captive power plant of 26.3 MW was commissioned in 1991. An
additional captive power plant of 17.8 MW was commissioned in 1998. KRL is now self
-sufficient in power

KARPAGAM COLLEGE OF ENGINEERING 2


Bharat Petroleum Corporation Limited acquired the Government of India's shares in KRL in
March 2001. With this the company has become a subsidiary of BPCL.

PROJECTS COMPLETED

CEMP PHASE-1
The phase 1 of the capacity-expansion-cum-modernization project (CEMP) that
envisaged refinery modifications required to meet BS-II Product Specifications, has met the
target. Supply of auto fuels like petrol and diesel confirming to Bharath Stage-II
specifications began in April 2005.

Rainwater Harvesting
Kochi Refinery has one of the largest rainwater reservoirs in the state with a
detention pond of 1, 25,000 KL capacity to collect surface run off water from around 8.0
lakhs.sq.m of land. The integrated rainwater harvesting system to collect, conserve and
protect rainwater for effective utilization has been constructed and commissioned.
The project will enable (i) using rainwater collected from roof- top during the monsoon for
the process and drinking requirement and thereby reducing the intake of water from Periyar
river, (ii) charging the ground water table using the collected roof rainwater (iii) harvesting
around 1, 25,000 KL of rainwater per annum falling on the land area by collecting the surface
runoff and thereby augmenting the quality of existing water bodies and to replenish the
ground water table.

Eco Park
The Ecological Park within Kochi Refinery premises spreads over a land area of 5.50
acres with a view to restore the healthy ecosystem, control pollution, develop clean
environmental condition and prevent soil erosion. Around 3750 numbers of wide ranges of
forest species, ornamental trees, fruit trees and attractive flowering plants along with
medicinal herbs have found a place in the Eco Park. Treated effluent water is being utilized
to feed the dry land plants. Available resources is also being used to develop scrap land to
green belts which in-turn would promote environmental awareness, enhance the
environmental quality of region, develop habitat for rare migratory species and also increase
tree coverage.

KARPAGAM COLLEGE OF ENGINEERING 3


ONGOING/UPCOMING PROJECTS

CEMP PHASE-II PROJECT


The object of the project is to upgrade auto fuels i.e. Motor spirit diesel from the
present BS-II specifications to Euro-III specification and to increase the capacity of the
refinery from 7.5 MMTPA to 9.5 MMTPA. Consent to establish the project facilities have
been obtained from State Pollution Control Board and clearance from Ministry of
Environment & Forests. The investment clearance for the project has also been obtained.
Estimated cost of the project is Rs.2592crores.
The major project facilities include revamp of CDU-II for capacity expansion by 2.0
MMTPA, VGO HDS unit, CCR Reformer unit and a GT for power generation. The project is
scheduled to be completed by September 2009.

Single Point Mooring Project


This project is to set up Crude Oil Receipt Facilities (CORF) consisting of Single
Point Mooring (SPM) for berthing Very Large Crude Carriers (VLCC). Shore Tank Farm
and associated pipelines and facilities. The job is progressing as per scheduling. Pilling jobs
for tank foundations are in progress. Orders have been released for Single Point Buoy. SPM
Project is scheduled for completion by May 2007.Community development schemes have
been activated along with the construction activities of the SPM. As part of its commitment
towards community development in the region, KRL has agreed to undertake schemes that
include; development of roads, drainage facilities and Fish landing Centre, improvement of
Health Care Centers including the deployment of an ambulance at Puthuvypeen, assistance
for educational facilities, augmentation of Water supply and street lighting.

Gas Task Force


The Gas Task Force (GTF) formed by BPCL and erstwhile KRL have been
signing Heads of Agreement (HOA) with major industrial customers in the States of Kerala,
Tamil Nadu, Karnataka. The HOA contains principal terms and conditions viz., term Sheet,
for the sale and purchase of Regasified Liquefied Natural Gas (RLNG) between the customer
and BPCL. The HOA shall be in force till such time a long term Gas Sales agreement is

KARPAGAM COLLEGE OF ENGINEERING 4


entered in between the parties. As the gas availability is limited, the HOA acts as a formal
document by which the quantity of RLNG required by the customer is reserved in advance.
Ti is anticipated that PLL and would be able to supply RLNG from its Kochi terminal by
2009 end.
The GTF intends to market the RLNG in the state of Kerala and adjoining areas of the States
of Tamil Nadu and Karnataka, amongst major industrial customers whose Gas requirement is
more than 12,500 TPA. Distribution of Gas in the city of Kochi, Compressed Natural Gas
(CNG) for automotive sector, Piped Natural Gas (PNG) for domestic use and Regasified
Natural Gas (RNG) for industrial/commercial customers whose usage is below 12,500 TPA
would be done by a separate Joint Venture Company to be formed by BPCL & GAIL.

Propylene Recovery Unit


LPG from Fluidized Catalytic Cracking Unit is a major source of propylene and
separating this propylene form LPG is a proven route to value addition. A detailed feasibility
report on setting up Propylene recovery unit at KRL was prepared with the help of
consultants. The investment approval for the same was received from the KRL Board and
action has been initiated for implementation of the project.

FUTURE PLANS

In the view of the declining market for furnace oil with high sulphur content and
reducing availability/increasing prices of light and low sulphur crudes, a suitable residue up
gradation facility has been found essential for Kochi Refinery. The proposed capacity
expansion of the refinery by the year 2010 will result in generation of additional quantities of
high sulphur heavy residue.

Delayed coking has been identified as an option for up gradation of refinery residue to
value added distillate products. A detailed feasibility study for refinery bottoms up gradation
is being carried out with the help of consultants. The possibility of transporting and
processing some short residue from BPCL-Mumbai Refinery is also being studied.

KARPAGAM COLLEGE OF ENGINEERING 5


UTILITIES

Utilities section provides the utilities such as steam. Compressed air and cooling
water required for various process units and other facilities in the refinery. A
demineralization plant treats and supplies feed water to boilers and water for process
requirement facilities and for power generation also come under this section. Power
requirements of the entire refinery can be met by the internal generation.

Steam- It is generated and consumed in the refinery is classified into three


depending on the pressure i.e., low-pressure @ 5kg/cm2, medium pressure @ 18kg/cm2 and
high pressure having pressure above 18kg/cm2.Medium pressure and low pressure steam are
used for various process requirements. Medium pressure steam is used for driving turbines
used as prime movers in the process units and other facilities. High pressure steam is mainly
used for power generation.

CPP-1: It has capacity of 26.3 MW. The unit was commissioned in 1991.It consists of
gas turbine for power generation and heat recovery steam generator.

CPP-2: The 17.8 MW steam turbo generator was commissioned in 1998.Refinery fuel oil
is used as fuel for generating high pressure steam in the boiler. UB7 and steam is used for
driving the-turbine.

COMPRESSED AIR: It is used as instrument air and plant air. Instrument air is required
for operating the instruments and plant air is used for general cleaning, blowing, and
operating pneumatic tools and other process requirement. The supply of plant air and
instrument air is done by separate air compressor.

COOLING WATER: - Water serves for various purposes such as cooling medium for
process steam, making boiler feed water to produce steam etc. Total consumption of water is
about 2.5 million gallon per day. Water is received from Periyar river basin. Water is stored
in two quarries from where it is pumped to process area and colony after treatment.

KARPAGAM COLLEGE OF ENGINEERING 6


DEMINERALISATION PLANT

The natural water obtained from various sources contains a member of dissolved salts
such as bicarbonates, carbonates, sulphates, chlorides, and nitrates of calcium, magnesium,
and sodium. For high-pressure boilers, steam is put to use in condensing turbines and for
laboratory purpose the dissolved impurities in water are objectionable and complete removal.

The complete demineralization or de-mineralization is carried by passing water


through a series of ion exchange beds where all the dissolved ions are removed. The essential
steps followed are: dosing of Na2SO3 to remove excess chlorine, filtration through a strong
acid cation exchanger, weak base anion exchanger in series, and removal of free carbon
dioxide in the decationised water in a mixed bed containing a mixture of cation and anion
resins.

KARPAGAM COLLEGE OF ENGINEERING 7


SULPHUR RECOVERY UNIT

Petroleum products are finding increasing use in the day to day activities of mankind
includes personnel and commercial needs. Coupled with the increasing demand for fuels is
the problem of deteriorating quality of air in the environment. One of the largest contributors
to the poor quality of air is vehicular exhaust. Due to the increased pressure on the
environment from various exhaust gases significant reduction in emissions of SO2 and NO2
are required. There is a general agreement that reducing sulphur content is an effective means
of improving air quality.

It is in this context that the sulphur recovery unit comes into perspective. The sulphur
recovery unit is the process unit setup for the removal hydrogen sulphide from the refinery
fuel gas steam. KRL has setup a diesel desulphurization unit of 2 mmtpa capacity to reduce
the sulphur content in diesel from 1 weight % to 0.25 weight %. The input of fuel gas to the
SRU comes in two streams. High pressure steam comprising of gas from CC discharge,
sponge gas from naphtha stabilizer in PU –2 and merge streams from NHDS and KHDS.
Overhead non-condensable of visbreaker along with gas from LV1 constitute steam. The
high pressure gas steam out of SRU has various consumption points of fuel gas.

LIGHT END FEED PREPATION UNIT

A Light End Feed Preparation Unit (LELPU) to supply polybutenes was


commissioned in March 1993. BPCL also commissioned a raffinate purification unit for the
manufacture of petroleum hydrocarbon solvent in January 1994. BPCL started production of
mineral turpentine oil in March 1996 and mixed aromatic solvent in March 1996.

The main areas of concern for BPCL are


 Water requirement
 Crude oil receipt facilities
 Pollution control and environment care

The organizational structure of BPCL consists of various departments as follows:

KARPAGAM COLLEGE OF ENGINEERING 8


 Manufacturing
 Stock and oil department
 Maintenance
 Technical service department
 Projects
 Materials & Services
 Quality Control
 Research & Development
 Oil Economics
 Vigilance
 Power and utilities
 Computer and automation
 Corporation planning
 Marketing
 Finance and accounts
 Secretarial
 Human Resource Management
 Security

Each department is performing certain specific objectives in coordination with the


others in achieving the organizational goals.
BPCL'S MISSION

• To strengthen the presence in petroleum refining and marketing of


petroleum products and to grow into the energy and petrochemical sectors.
• To realign orientation of thinking and philosophies to become a market
driven and customer friendly organization with focus on total quality
management.
• To enhance shareholder value and maximize returns through the best use
of resources.

KARPAGAM COLLEGE OF ENGINEERING 9


• To recognize employees as the most valuable asset of the organization and
foster a culture of participation and innovation for employee growth and
contribution.
• To achieve global standards of excellence through R & D efforts,
technology up-gradation, safety management and environmental
protection.
• To be a major contributor towards community development and welfare of
the society at large.

ENVIRONMENTAL POLICY

BPCL engaged in petroleum refining activity is committed to:


» Strive for continual improvement of the environment performance at
BPCL and prevent pollution
» Comply with regulatory & legal requirements of oil industry
o Respect the interests of customers, employees and other interested parties
o Promotion and development of greenery in the surrounding areas
o Select cleaner technologies & avoid environmental degradation
o Conserve natural resources and reduce energy consumption
o Print and distribute BPCL's environmental policy to all employees
and make them available to public
o Safe disposal of hazardous waste

Our environmental objectives:


• Treatment and disposal of 10000 MT of accumulated oily sludge after
mechanical recovery of oil by December 2003.
• Decommissioning of equalization pond at ETP-I by Dec 2002 to
reduce fugitive emissions at KRL.
• De-silting of water channel from outlet `B` to outlet `C` during the year
2002-03.
• Reduce specific energy consumption of BPCL from the present level.
• Conducting training programs on ISO 14001 EMS awareness.

KARPAGAM COLLEGE OF ENGINEERING 10


ISO 14001

The company has been awarded the prestigious ISO 14001 certificate in
recognition of the company’s environment management measures.

Environment auditors M/s Bureau Veritas Quality International (BVQI) certified


that the management system of the company had been assessed and found it to be in
accordance with the requirements of the environmental standards ISO 14001.

ISO 14001 is an international standard for environment management system,


(EMS), issued by the International Organization for Standardization, Geneva. It provides a
systems approach to handling the impact of an organization’s activities and the use of its
product services on the environment.

This standard requires formation of short-term and long-term environmental


policy, environmental objectives, and compliance with legislative requirements and
addressing significant environmental impacts with solutions.

BPCL is the first company in Kerala to get this environment management


standard BPCL took the road of quality and responsibility. And it paid rich dividends of
goodwill and progress. It was thirty-five years back that BPCL, formerly known as Cochin
Refineries Ltd, started as a refinery with a capacity of 2.5 million metric tons per annum.
Now we refine more than 7.5 million metric tonnes every year.
Its turnover was Rs. 104802 million. Its profit for the year 2002-03 was
Rs. 6965 million. We have been paying rich dividends consistently.

BPCL AT A GLANCE
Location: Ambalamugal in Kochi
Refining capacity: 7.5 million metric tonnes per annum
Products: LPG, petrol, diesel, kerosene, naphtha, benzene, toluene,
LSHS, furnace oil, ATF, specialty solvents, bitumen,
rubberized bitumen etc.

KARPAGAM COLLEGE OF ENGINEERING 11


Turnover: Rs.104802 million (2002-2003)
Profit before tax: Rs.6965 million (2002-2003)

KRL is the only company in Kerala with a turnover of over Rs.10000 million. We
have been paying rich dividends to our shareholders consistently. The Board of Directors
has recommended a Dividend of Rs.10/- per share (100%) for the year 2002-03 as against
Rs. 2.20 per share during 2001-02.

Government of India has rated our performance for the year 2002-2003 as
'Excellent'. The turnover during 2002-2003 was Rs 104802 million. The profit before tax
was Rs.6965 million.

New proposals are:

 Capacity Expansion Project (CAPEX) for expanding capacity from 7.5


MMTPA to 13.5 MMTPA
 500 MW power generation project.
 Kochi – Karur products pipeline project
 A mandatory crude oil tankage project

KARPAGAM COLLEGE OF ENGINEERING 12


INTRODUCTION TO STORAGE TANKS

Petroleum storage tank are an indispensable part of petroleum refining industries.


They are used for intermediate and final product storage in a process plant or for storing
petroleum products and chemicals at terminals. They can also be used as process equipment
in non-ferrous plants where open top tanks are used for mixing, blending, precipitation and
settling process or as chemical reactor vessels.

Tanks are classified according to their construction, and the construction is on the
basis of the product which is to be stored in them.

CLASSIFICATION OF PETROLEUM PRODUCTS

Petroleum products are classified on the basis of their Flash Points.

FLASH POINT

"Flash point" of any petroleum liquid is the minimum temperature at which the liquid
yields vapour in sufficient concentration to form an ignitable mixture with air and gives a
momentary flash on application of a small pilot flame under specified conditions of test.

Petroleum products are classified according to their flash points as follows:

Class A Petroleum: Liquids which have flash point below 23 degree C - crude (Bombay
High), gasoline, naphtha, low aromatic naphtha, high aromatic naphtha.

Class B Petroleum: The Liquids that have flash point of 23 degree and above but below 65
degree C . E.g.: superior kerosene oil, high speed diesel, light diesel oil, aviation turbine fuel,
and jet propulsion-5.

Class C Petroleum: The Liquids that have flash point of 65 degree C and above but below

KARPAGAM COLLEGE OF ENGINEERING 13


93 degree C. E.g. Furnace oil, low sulphur heavy stock, asphalt, seal oil, plant fuel.

Excluded Petroleum: The liquids that have flash point 93 degree C and above. E.g.
Liquefied gases including LPG do not fall under this classification but form separate
category.

KARPAGAM COLLEGE OF ENGINEERING 14


TYPES OF STORAGE TANKS

I. Cone roof tanks


2. Floating roof tanks
3. Floating cum cone roof tanks
4. Spherical vessels

1. CONE ROOF TANKS

Fig:1 cone roof tank


The cone roof tanks have fixed roof and are in a sense closed vessels. They are
vertical cylindrical vessels having a conical top and made of welded steel plates and used
mainly for storing less volatile products. The fixed cone roofs have truss suppOl1S. Tanks
meant for storing products like asphalt, vacuum gas oil etc. at high temperature is fully
insulated externally. There are 32 cone roof tanks in KRL at present. Depending on the
service the cone roof tanks will have the following accessories:

• Man ways to go in- on the shell and roof


• Vent with flame alerter or mesh roof vents
• Pressure cum vacuum relief vents with flame arrestor to
prevent excessive pressure build up of vacuum pulling inside.
• Gauging datum plate
• Gauge hatch with reference mark

KARPAGAM COLLEGE OF ENGINEERING 15


• Auto gauges
• Dial thermometer
• Mixing devices
• Steam heating coils with inlet and outlet nozzles
• Product inlet or outlet headers, the inlet header with jet nozzles
• Gas fired burners with steam heating coil for heating the
product (asphalt /LSHS)
• Water draw
• Stairway
• Earthing facilities

KARPAGAM COLLEGE OF ENGINEERING 16


2. FLOATING ROOF TANKS

Fig:2 Floating roof tank


Floating roof tanks are intended for storing products having high vapour pressure like
HSD and gasoline. They have a movable roof that floats on the surface of the tank contents.
Thus the vapour space is kept constant and minimum. Roofs are pontoon type having
enclosed air chambers. Foam type neoprene seal is used to seal off the clearance between the
rim of the roof and the tank shell in these tanks. As long as the pontoons do not leak the roof
will not sink.

The roof is supported when it is not afloat by a number of adjustable legs with low
and high position. Normally roofs are kept on low legs. When a tank is to be taken out of
service for cleaning or repairs, the roof will be put on high legs to provide space for people to
work inside. Pump out vents in the roof permit the escape of air when an empty or near-

KARPAGAM COLLEGE OF ENGINEERING 17


empty tank is filled and the roof is afloat. Roof drains are provided to drain water that is
collected on the roof during rains. This is done by providing hoses or pipes with swivel joints
from the roof to the outside of the tank shell near the bottom. A non-return valve on the
hose/pipe at the roof end and a gate valve at the bottom prevent escape of oil from the tank in
case the hose develops leak. In certain cases the roof is also provided with an emergency
drain having water seal. In cases the rainwater does not flow freely through the roof drain it
can get into the tank through the emergency drain. Access to the floating roof is by an inside
stairway, one end if which is hinged at the gauge’s platform at the top of the outside stairway
and the other end is free to move on rollers on a runway fixed to the roof as the roof moves
up and down To maintain the shape of the tank when it is subjected to wind loads the tank is
reinforced with stiffening rings called wind girders.

There are 51 floating roof tanks in KRL at present. The following arc the accessories
provided on floating roof tanks:
• Man ways to go in - on the shell and roof.
• Gauging datum plate.
• Gauge hatch with cover and reference mark.
• Auto gauges (in certain tanks).
• Dial thermometer.
• Mixing devices.
• Water draw.
• Roof drain.
• Inlet pipe header with jet nozzle and outlet.
• Gas fired burners with steam heating coil for heating the product.
• (Asphalt /LSHS).
• Outside stairway.
• Inside stairway.
• Gauging platform.
• Roof legs and pump-out vents.
• Roof guides to keep the roof in position.
• Roof shoe with neoprene seal.
• Metal conductors over the roof seal to dissipate electric charge to the

KARPAGAM COLLEGE OF ENGINEERING 18


earthing.
• Earthing facilities.

3. FLOATING CUM CONE ROOF TANKS

They have fixed cone roof in addition to a floating roof and they are intended for
storing toxic products having high vapour pressure. Products like benzene and toluene are
carcinogenic and should be prevented from escaping into the atmosphere. So they are stored
in floating cum cone roof tanks. These tanks prevent product from contamination and are
used to store class A and class B products. There are 13 floating cum cone roof tanks in KRL
at present.

KARPAGAM COLLEGE OF ENGINEERING 19


LAYOUT OF STORAGE TANKS BASED ON OISD

• DYKED ENCLOSURES

 Petroleum storage tanks shall be located in dykes enclosures with roads all
around the enclosure. Aggregate capacity of tanks located in one dyked
enclosure shall not exceed following values:
For a group of floating roof tanks: 120000cu.m.
For a group of fixed roof tanks: 60000cu.m.
If a group of tanks contains both fixed and floating roof tanks then it shall
be treated as a group of fixed roof tanks for the purpose of above limits.

 Dyked enclosure should be able to contain the complete contents of the


largest tank in the tank farm in case of any emergency. Enclosure capacity
shall be calculated after deducting the volume of the tanks (other than the
largest tank) up to the highest of the enclosure. A free board of 200mm
above the calculated liquid level shall be considered for fixing the height
of the dyke.
However for excluded petroleum, the capacity of the
dyked enclosure should be based on spill containment but not
for containment on tank rupture.

 The height of tank enclosure dyke shall be at least one meter and shall not
be more than 2.0m above average grade level; inside. However, for
excluded petroleum the minimum height of dyke wall shall be 600mm.
 Inter-distance between the nearest tanks located in two dykes shall be
equivalent to the largest tank diameter or 30m, whichever is more.
 The dykes should be of earthen construction havl11g trapezoidal cross -
section. The dyke shall not have slope steeper than 1.5 horizontal to 1.0
ve11ical. The top flat surface of dykes up to 1m and up to 2m height, top
flat surface shall have 1000mm width. Brick or stone masonry wall may
be provided where space does not permit construction of earthen dykes.
 Pump stations should be located outside dyke areas by the side of roads.

KARPAGAM COLLEGE OF ENGINEERING 20


 Tanks located overhead for process considerations shall meet safety
distance and shall also have dyked enclosure of RCC construction and
provided with drain valves at suitable height for easy operation.

Grouping of Tanks

 Grouping of petroleum products for storage shall be based on product


classification. Class A and/or class B petroleum can be stored 111 the same
dyked enclosure. Class C petroleum should be stored separate enclosure.
However, where class C petroleum is stored in a common dyke along with
class A and / or class B petroleum, all safety stipulations applicable for class
A and/or class B respectively shall apply.
 Excluded petroleum shall be stored in a separate dyked enclosure and shall
not be stored along with class A, B or C petroleum.
 Tanks shall be arranged in maximum 2 rows so that each tank is
approachable from the road surrounding the enclosure. However, tanks
having capacity 50000cum and above shall be laid in single row.

Fire Walls

In an enclosure where more than one tank is located, firewalls of 600mm should be
provided as explained below:
 Any tank having a diameter more than 30m should be separated with fire
walls from other tank
 Firewalls should be provided by limiting the aggregate capacity of group of
tanks within, to 20000cu.m.

General

 The tank height should not exceed one and a half times the diameter of the

KARPAGAM COLLEGE OF ENGINEERING 21


tank or 20m whichever is less.
 Piping from/to any tank located in a single dyked enclosure should not pass
through any other dyked enclosure. Piping connected to tanks should run
directly to outside of dyke to the extent possible to m1l11mise piping
withll1 the enclosures.
 No fire water/foam ring main shall pass through dyked enclosure.
 The minimum distance between a tank shell and the inside toe of the dyke
wall shall not be less than one half the height of the tank

Inter distances for tanks/offsite facilities

The following stipulations shall apply for the inter-distances for above ground tanks
storing petroleum:
Inter distances for storage tanks
Sl.no Item FRT
CRT(Class A&B Class C
Petroleum) Petroleum

1 All tanks with


diameter upto (D+d)/4 (D+d)/4 (D+d)/6
50m
2 All tanks with
diameter (D+d)/4 (D+d)/3 (D+d)/4
exceeding 50m
Table:1

• This table is applicable for


installations where aggregate storage capacity of class A&B petroleum stored above
ground exceeds 5000cu.m or where the diameter-of any such tank for the storage of
petroleum exceeds 9m.
• Distances given are she!] to shell in
the same dyke
• Notation

KARPAGAM COLLEGE OF ENGINEERING 22


o FRT: Floating roof tank
o CRT: Cone roof tank
o D: diameter of larger tank in meters
o d: diameter of smaller tank in meters
• If the inter-distance (for class A&B) calculated as above is less than 15m, then
minimum of 15m or 0.50 or d shall be followed.
• Inter-distance between class A/B storage tanks and class C storage tanks shall not
be less than 6m.

KARPAGAM COLLEGE OF ENGINEERING 23


PARTS OF STORAGE TANK

BOTTOM PLATES AND ANNULAR PLATES

Bottom plates are those plates which are laid at the bottom of the tank. These plates
are lap welded to each other. All bottom plates have a nominal thickness of 6 mm excluding
of corrosion allowance specified by the purchaser.

Bottom plates get corroded rapidly if the fluid is having sea water content (crude
petroleum). Bacterial corrosion of the bottom plates is generally observed in crude and HSD
tanks having high sulphur content. The bottom plates develop deep isolated pits which
eventually puncture and bottom starts leaking. So the proper corrosion allowance should be
provided.

Annular plates are those bottom plates on which the shell plates rest. Annular bottom
plates should be capable of withstanding the weight of the shell plates and the appurtenance.

According to API 650 (3.5.2), annular bottom plates shall have a radial width that
provides at least 600 mm between the inside of the shell and any lap welded joint in the
remainder of the bottom and at least a 50 mm projection outside of the shell.

The projecting out portion of the annular bottom plates are prone to corrosion at the
edges due to accumulation of water between the foundation and the annular bottom plates. So
here also appropriate corrosion allowance should be given.

DRAW OFF SUMP

A draw off sump is provided at the bottom of the tank such that a sl11a'll inclination
is given to the bottom plates towards the sump. Sump shall be placed in foundation before
bottom placement. A neat excavation shall be made to conform to the shape of the draw off
sump. The sump shall be put in place, and the foundation shall be compacted around the
sump after placement and the sump shall be welded to the bottom.

KARPAGAM COLLEGE OF ENGINEERING 24


Draw off sump is provided in order to collect the water particles in the oil. A draw
off nozzle is provided on the shell plate to remove the water collected in the draw off sump.
The sump and nozzle are connected by means of an internal pipe.

SHELL

Shell is the major portion of the tank which is exposed to the atmosphere. The
major problem that may arise is corrosion. Shell plates generally get corroded internally
where liquid-vapour is maintained. Internal corrosion in the vapour space is most commonly
caused by hydrogen sulphide vapour, water vapour and oxygen giving pitting type corrosion.
Atmospheric corrosion can occur on all external parts of the tank. This type of corrosion may
range from negligible to severe depending on upon the atmospheric condition of the locality.
All vertical and horizontal shell joints shall be full penetration and full fusion welds. Shell
joints shall be double welded butt joints. . Wind girders shall be welded to the tank at the
location designed. Welding shall be of the same quality as used for the shell. The necessary
shell openings such as manholes, nozzles, drain holes etc. shall be provided to the horizontal
plates.

SHELL OPENINGS

The important shell openings are shell man hole, yield and suction nozzles, water
drain and rain drain.

1. SHELL MANHOLE

One manhole is provided to the tank shell at the bottom shell course for the entry of
humans into the tank for maintenance or other purposes. Here a 600mm dia. manhole is
provided.

KARPAGAM COLLEGE OF ENGINEERING 25


Fig:3 shell manhole
2. YIELD AND SUCTION NOZZLES

Three yield nozzles and one suction nozzle arc provided for the tank. These nozzles
are also fixed at the bottom shell course. Yield nozzle is provided for receiving finished,
intermediate or unfinished products into the tank. This nozzle is designed according to the
velocity of yielding and need for agitation. Suction nozzle is designed according to capacity
of the tank and according to place to where the oil is transferred.

3. WATER DRAIN AND ROOF DRAIN

Three nozzles for water draw off and two nozzles for roof drain are provided. The
three water drains are fixed at 120 degree apart on the bottom shell course.
Even though one roof drain is sufficient for proper working two roof drains are
provided. As per the API standards the other is provided as a 100% Standby. Roof drain
outlets are provided at the opposite sides of the bottom shell course.

WIND GIRDER

KARPAGAM COLLEGE OF ENGINEERING 26


Wind girder or stiffening rings are provided on storage tanks to prevent the buckling
of tanks against wind loads. Wind girders are usually constructed as walkways to facilitate
the inspection and repair of storage tank.

SEAL

The space between the outer rim of roof and shell should be sealed by an approved
sealing device and sea1ing material should be resistant to the stored product and durable
against friction due to roof movement. Sealing system should exert sufficient sealing
pressure in all directions to prevent any evaporation losses and the arrangement should touch
the product during the operation.

Fig:4 seal
Foam seals have excellent flexibility and recovery from compression and at the same
time permit the roof movement up and down freely with the level of tank contents.

AUTOMATIC TANK GAUGING

Automatic Tank Gauging (A TG) is carried to obtain information about the total
volume or weight of the product in the tank. This information is obtained from four
parameters i.e., liquid level, tank capacity table, average temperature and relative density of
individual tank.

KARPAGAM COLLEGE OF ENGINEERING 27


ADVANTAGE'S OF TANK GAUGING

1) Accurate and better inventory control


2) Reduction of work load
3) Tank level is displayed at the tank site and at the central monitoring unit for
prompt attention
4) Accurate level measurements even under turbulent product condition
5) Accurate water bottom level detection
6) It can be used in high safety hazards environments
7) Remote repeatability tests

COOLING SYSTEM

Storage tanks are equipped with water cooling system to bring down the temperature
of the tank shell & protect them from damage when a fire hazard occurs to a neighboring
tank. The system consists of rings fitted around the tank. Numerous nozzles are fixed into the
rings through which water is sprayed to the tank shell at a particular pressure. Water is
supplied to the cooling rings by means of 2 risers which arc placed diametrically opposite to
each other.
FOAM SYSTEM

KARPAGAM COLLEGE OF ENGINEERING 28


Fig:5 foam system
Foam for firefighting purposes is an aggregate of air filled bubbles formed from aqueous
solutions and is 100ver in density than the lightest flammable liquid. It is principally used to
form a coherent floating blanket on flammable and combustible liquids lighter than water and
prevents or extinguishes fire by excluding air and cooling the fuel it also prevents re-ignition
by suppressing formation of flammable vapour. It has the property of adhering IO surfaces,
providing a degree of exposure protection from adjacent fires.

The foam generally used in modem tanks is AFFF (Aqueous Film Forming Foam). It
is a synthetic film forming concentrate and is based on fluorinated surfactants plus foam
stabilizers and is diluted with water to a 3% to 6% solution. The foam formed acts as 'a
barrier to exclude air or O2 and to develop an aqueous film on the fuel surface capable of
suppressing the evolution of fuel vapour. The foam produced with AFFF concentrate is dry
chemically compatible and thus is suitable for combined use with dry chemicals.

MATERIAL SPECIFICATION FOR STORAGE TANKS

The materials used in the construction of storage vessels are usually metals, alloys,
clad-metals, or materials with linings that are suitable for containing the fluid. Where no
appreciable corrosion problem exists the cheapest and most easily fabricated construction
material is usually hot rolled mild (low carbon) steel plate.

Low carbon steels are rather soft and ductile and are easily rolled and formed into the
various shapes used in fabricating vessels. These steels are also easily welded to give joints
of uniform strength relatively free from localized stresses. The ultimate tensile strength is
usually between 380Mpa and 450Mpa and the carbon content between 0.15% and 0.25%.

The material generally used for manufacturing storage tanks in India is IS2062 grade
A. It is a low carbon, hot rolled steel with the following specifications.

Carbon (max.) 0.23%

Manganese (max.) 1.50%

KARPAGAM COLLEGE OF ENGINEERING 29


Sulphur (max.) 0.050%

Phosphorous (max.) 0.050%

Silicon (max.) 0.40%

Table:2

It has a minimum ultimate tensile strength of 410.6 Mpa and yield strength of
247.6 Mpa.
The pipe material used for making roof legs is AI 06 grade B. The chemical
composition is given below:

Carbon (max.) 0.03%

Manganese (max.) 1.06%

Phosphorous (max.) 0.048%

Sulphur (max.) 0.058%

Silicon(min.) 0.1%
-

Table:3
The minimum tensile strength is 414 Mpa and the minimum yield strength is 241 Mpa

KARPAGAM COLLEGE OF ENGINEERING 30


DESIGN OF STORAGE TANK

Design and construction of storage tank for storing furnace oil.

1. Tank selection

The furnace oil is a highly volatile; the flash point of furnace oil is 66ºC. So it
comes under class C of petroleum products and has to be stored in a fixed cone roof tank.

2. Height and Diameter

For fixing the height and the diameter of the tank, the criterion to be maintained as
per API 650 is that the ratio of the total height of the tank to the internal diameter must be
less than 1.5.

Height of the tank/Diameter of tank <1.5


i.e.; H/D<1.5
Height and diameter mostly depends upon the space available on the site, distance between
two consecutive tanks etc. It also depends on the judgment of the designer, by studying the
H/D ratio of the existing tanks in refinery. We selected the diameter as

Height of the tank = 14m

Diameter of the tank = 36m

Here H/D ratio = 14/36=.3889<1.5

(Hence condition H/D < 1.5 is satisfied)

KARPAGAM COLLEGE OF ENGINEERING 31


So it is possible according to API 650.

Volume, V=πR2H

V = 3.14*(18*18)*14
= 14243.04 m3

BOTTOM PREPERATION

Cone penetration test

To assess the soil bearing capacity of soil at locations under the bottom plate
penetration test was conducted by IIT Madras. Cone penetration resistance (CPR) was
calculated by determining the number of blows required to attain a 300 mm penetration by
test cone.
The cone penetration resistance is found to vary between 20 and 40 which indicates
that the maximum settlement to be less than 100mm which is permitted for large diameters.
(Present tank being of 50m diameter)

Soil testing

The test sample of soil is collected from various positions of tank bottom and is sent
to IIT Madras. It was tested and certified OK for the construction of the above mentioned
tank.

Bitumen carpeting

KARPAGAM COLLEGE OF ENGINEERING 32


Sieved river sand is mixed with 8-10 % volume of Bitumen (80/100 grade) and is
laid on the site and consolidation, rolling, tamping etc. are done. A slope of 1:100 is
maintained towards the shell from the core of the tank.

KARPAGAM COLLEGE OF ENGINEERING 33


DESIGN DATA

Design code: API 650 (11th edition)


Diameter: 36 m
Height: 14 m
Product stored: Furnace oil
Specific gravity of product: 0.95
Design specific gravity: 0.95
Corrosion allowance: 2 mm for annual and bottom plate
: 2 mm for shell plates
: 2 mm for roof plates
Design pressure: Atmospheric pressure
Material specification: ASTM A537 grade 1 (As per API 650 Table 3.2). ASTM A537 grade
1 is the Pressure Vessel Plates, Heat-Treated, Carbon-Manganese-Silicon Steel and also it
has got an acceptable value of yield strength (50,000 psi or 345 Mpa) and tensile strength
(70,000 psi or 485 Mpa)

Wind speed: 185 kmph (max)


Maximum rain fall intensity: 57 mm in one hour or 254 mm in 24 hours

DESIGN OF BOTTOM PLATES

According to API 650 standards, bottom plates shall have a minimum nominal
thickness of 6mm exclusive of any corrosion allowance.

So the bottom plate thickness = 6 + 2 = 8 mm

So the thickness of bottom plate is selected as 8mm. (Since the thickness of shell plates
available in market are of sizes 6, 8, 10, 14, 12, 18, 20, 24 mm etc.)

Bottom plates of sufficient size shall be ordered so that when trimmed at least a 25 mm width
will project beyond the outside edge of the weld attaching the bottom to the shell plate. The

KARPAGAM COLLEGE OF ENGINEERING 34


commonly available sizes of plates in market are off length 6m to 10 mm and of width I- 5m,
2m, 2.5m etc. Bottom plate preparation involves shot blasting and Bituminized painting.

DESIGN OF SHELL PLATES

Tank is made of plates. Plates of same width have been welded together to form a
course of equal diameter. The course contains a number of vertical joints of length = plate
width. A number of courses are welded together horizontally to form the total height of the
tank.
According to API 650, the shell thickness for a tank of diameter in the range of 36-60 m
should not be less than 8 mm. (For tank diameter less than 36 m, the shell thickness should
not be less than 6 mm).

The shell thickness is calculated taking into account the material specification and allowable
stresses. The maximum allowable product design stress Sd (API 50 CI.3.6.2.1), shall be either
two-third the yield strength or two-fifth the tensile strength whichever is less, the maximum
allowable hydrostatic test stress St (API 50 CI.3.6.2.1), shall be either three-fourth the yield
strength or three-seventh the tensile strength whichever is less.

Yield strength of selected material (IS2062) = 247.60 Mpa

KARPAGAM COLLEGE OF ENGINEERING 35


Tensile strength of selected material l= 410.6 Mpa

Maximum allowable design stress (Sd)

Sd=2/3* yield strength

Sd=2/3*247.60 = 165 Mpa

Or

Sd = 2/5*Tensile strength

Sd = 2/5*410.6=164.24 Mpa

So design stress is taken as 165 Mpa

Maximum allowable hydrostatic stress (St)

St = 3/4*yield strength

S = 3/4*247.60=185.70 Mpa

Or

St = 3/7*Tensile strength

St = 3/7*410.6=175.9 Mpa

So Hydrostatic stress is taken as 176 Mpa

According to API 650 thicknesses of tanks less than 60 m in diameter is calculated using

KARPAGAM COLLEGE OF ENGINEERING 36


1-foot method, and if the diameter is above 60 m, the thickness is found out using variable
design point method. So here I-foot Method is used.

I-foot method calculates the thickness required at the design point 0.3 m (1 ft) above the
bottom of each shell course. In this method we find out the design shell thickness (td) and the
hydrostatic test shell thickness (tt) and the maximum of the two values is taken.

Here,

Td =4 .9*D*(H-0.3)*G/Sd + CA

Tt = 4.9*D*(H-0.3)/St

Td = Design shell thickness in mm

Tt = Hydrostatic shell thickness in mm

D = Nominal tank diameter in m=36 m

H = height from the bottom of the course under consideration to the top of the shell.

G = Design specific gravity of the liquid to be stored=0.95

CA = Corrosion allowance in mm =1.6 mm

Sd = Allowable design stress=165 Mpa

St = Allowable hydrostatic stress=176 Mpa

Since the height of the tank is 14 m, we have to divide it into a number of courses
considering the economic conditions. This is done by trial and error method. It is to be noted
that the standard thickness available in market are 6, 10, 12, 14, 16, 20, 25 mm. Values of

KARPAGAM COLLEGE OF ENGINEERING 37


thickness obtained by calculation are rounded off to the nearest size of the metal plate
available in the market.

We select a number of random cases with varying number of courses and course width. The
total weight of the metal used and cost in each case is also calculated to determine the most
economical case of shell structure.

Case 1

We divide the total Height 14 m to 6 courses of 2, 2, 2.5, 2.5, 2.5, and 2.5 m respectively.

From the above formula shell thickness is calculated.

Shell thickness.

1st Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under = 14.00 m
consideration to the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 13.80 mm
Tt =(4.9D(H – 0.3))/St = 11.60 mm

Max thickness = 13.80 mm


Thickness selected t = 14 mm
= 0.014 m
Width of shell course W = 2.00 m
Volume of Shell course V1 = 3.14 *D*W* t = 3.17 m3

KARPAGAM COLLEGE OF ENGINEERING 38


2nd Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 12.00 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 12.08 m
Tt =(4.9D(H – 0.3))/St = 9.91 m
Max thickness = 12.08 mm
Thickness selected t = 14 mm
= 0.014 m
Width of shell course W = 2.00 m
Volume of Shell course V2 = 3.14 * D * W * t = 3.17 m3

3rd Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 10.00 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 10.36 m
Tt =(4.9D(H – 0.3))/St = 8.21 m
Max thickness = 10.36 mm
Thickness selected t = 12 mm
= 0.012 m
Width of shell course W = 2.50 m
Volume of Shell course V3 = 3.14 * D * W * t = 3.39 m3

KARPAGAM COLLEGE OF ENGINEERING 39


4th Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 7.50 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 8.20 m
Tt =(4.9D(H – 0.3))/St = 6.10 m
Max thickness = 8.20 mm
Thickness selected t = 10 mm
= 0.010 m
Width of shell course W = 2.50 m
Volume of Shell course V4 = 3.14 * D * W * t = 2.83 m3

5th Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 5.00 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 6.05 m
Tt =(4.9D(H – 0.3))/St = 3.98 m
Max thickness = 6.05 mm
Thickness selected t = 8 mm
= 0.008 m
Width of shell course W = 2.50 m
Volume of Shell course V5 = 3.14 * D * W * t = 2.26 m3

KARPAGAM COLLEGE OF ENGINEERING 40


6th Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 2.50 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 3.90 m
Tt =(4.9D(H – 0.3))/St = 1.86 m
Max thickness = 3.90 mm
Thickness selected t = 8 mm
= 0.008 m
Width of shell course W = 2.50 m
Volume of Shell course V6 = 3.14 * D * W * t = 2.26 m3

Total Volume V = V1+ V2 + V3+V4+V5+V6 = 17.07 m3

Case 2

We divide the total Height 14 m to 6 courses of 1.5, 1.5, 2.5, 2.5, 2.5 and 3.5 each
respectively.

Shell Thickness

1st Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 14.00 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

KARPAGAM COLLEGE OF ENGINEERING 41


Specific Gravity G = 0.95 Kg/mm3
Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 13.80 m
Tt =(4.9D(H – 0.3))/St = 11.60 m
Max thickness = 13.80 mm
Thickness selected t = 14 mm
= 0.014 m
Width of shell course W = 1.50 m
Volume of Shell course V1 = 3.14 * D * W * t = 2.37 m3

2nd Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 12.50 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 12.51 m
Tt =(4.9D(H – 0.3))/St = 10.33 m
Max thickness = 12.51 mm
Thickness selected t = 14 mm
= 0.014 m
Width of shell course W = 1.50 m
Volume of Shell course V2 = 3.14 * D * W * t = 2.37 m3

3rd Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 11.00 m
the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

KARPAGAM COLLEGE OF ENGINEERING 42


Specific Gravity G = 0.95 Kg/mm3
Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 11.22 m
Tt =(4.9D(H – 0.3))/St = 9.06 m
Max thickness = 11.22 mm
Thickness selected t = 12 mm
= 0.012 m
Width of shell course W = 2.50 m
Volume of Shell course V3 = 3.14 * D * W * t = 3.39 m3

4th Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 8.50 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 9.07 m
Tt =(4.9D(H – 0.3))/St = 6.94 m
Max thickness = 9.07 mm
Thickness selected t = 10 mm
= 0.010 m
Width of shell course W = 2.50 m
Volume of Shell course V4 = 3.14 * D * W * t = 2.83 m3

5th Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 6.00 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa

KARPAGAM COLLEGE OF ENGINEERING 43


Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 6.91 m
Tt =(4.9D(H – 0.3))/St = 4.83 m
Max thickness = 6.91 mm
Thickness selected t = 8 mm
= 0.008 m
Width of shell course W = 2.50 m
Volume of Shell course V5 = 3.14 * D * W * t = 2.26 m3

KARPAGAM COLLEGE OF ENGINEERING 44


6th Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 3.50 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 4.76 m
Tt =(4.9D(H – 0.3))/St = 2.71 m
Max thickness = 4.76 mm
Thickness selected t = 8 mm
= 0.008 m
Width of shell course W = 3.50 m
Volume of Shell course V6 = 3.14 * D * W * t = 3.17 m3

Total Volume : V1+V2+V3+V4+V5+V6 = 16.39 m3

Case 3

We divide the total Height 16 m to 6 courses of 1, 1.5, 2.5, 2.5, 3, and 3.5 respectively.
Shell Thickness

1st Course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to = 14.00 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

KARPAGAM COLLEGE OF ENGINEERING 45


Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 13.80 m
Tt =(4.9D(H – 0.3))/St = 11.60 m
Max thickness = 13.80 mm
Thickness selected t = 14 mm
= 0.014 m
Width of shell course W = 1.00 m
Volume of Shell course V1 = 3.14 * D * W * t = 1.58 m3

2nd course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration to
the top of shell H = 13.00 m

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95


Max hyd stress to be considered St = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 12.94 m
Tt =(4.9D(H – 0.3))/St = 10.75 m
Max thickness = 12.94 mm
Thickness selected t = 14 mm
= 0.014 m
Width of shell course W = 1.50 m
Volume of Shell course V1 = 3.14 * D * W * t = 2.37 m3

3rd course

KARPAGAM COLLEGE OF ENGINEERING 46


Nominal Tank Diameter in meters D = 36.00 m
Height from bottom of the course under consideration to = 11.50 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered St = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 11.65 m
Tt =(4.9D(H – 0.3))/St = 9.48 m
Max thickness = 11.65 mm
Thickness selected t = 12 mm
= 0.012 m
Width of shell course W = 2.50 m
Volume of Shell course V1 = 3.14 * D * W * t = 3.39 m3

4th course

Nominal Tank Diameter in meters D


36.0
= 0 m
Height from bottom of the course under consideration to = 9.00 m
the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95


Max hyd stress to be considered St = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 9.50 m
Tt =(4.9D(H – 0.3))/St = 7.37 m
Max thickness = 9.50 mm
Thickness selected t = 10 mm
= 0.010 m
Width of shell course W = 2.50 m
Volume of Shell course V1 = 3.14 * D * W * t = 2.83 m3

5th course

KARPAGAM COLLEGE OF ENGINEERING 47


Nominal Tank Diameter in meters D = 36.00 m
Height from bottom of the course under consideration = 6.50 m
to the top of shell H
Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered St = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 7.34 m
Tt =(4.9D(H – 0.3))/St = 5.25 m
Max thickness = 7.34 mm
Thickness selected t = 8 mm
= 0.008 m
Width of shell course W = 3.00 m
Volume of Shell course V1 = 3.14 * D * W * t = 2.71 m3

6th course

Nominal Tank Diameter in meters D = 36.00 m


Height from bottom of the course under consideration = 3.50 m
to the top of shell H

Design stress to be considered Sd = 194 Mpa

Corrosion Allowance = 2.00 mm

Specific Gravity G = 0.95 Kg/mm3


Max hyd stress to be considered St = 208 Mpa
Td=((4.9*D*(H-0.3)*G)/Sd))+CA = 4.76 m
Tt =(4.9D(H – 0.3))/St = 2.71 m
Max thickness = 4.76 mm
Thickness selected t = 8 mm
= 0.008 m
Width of shell course W = 3.50 m
Volume of Shell course V1 = 3.14 * D * W * t = 3.17 m3

Total Volume V1+V2+V3+V4+V5+V6 = 16.05 m3

KARPAGAM COLLEGE OF ENGINEERING 48


KARPAGAM COLLEGE OF ENGINEERING 49
ECONOMIC CONSIDERATION

For selecting the optimum combination we are considering the material cost and
fabrication cost for each case

Case 1

The total volume of shell plate required = 17.07m³

The total weight of shell plates = volume*density

= 16.05 * 9.50

= 162.16 tonnes

Material cost per metric tonne = Rs 40,000

So overall material cost of shell plates = 40,000 * 162.16

= Rs 64.86 lakhs

Case 2

The total volume of shell plate required = 16.39m³

The total weight of shell plates = volume*density

= 16.39* 9.50

= 155.71 tonnes

KARPAGAM COLLEGE OF ENGINEERING 50


Material cost per metric tonne = Rs 40,000

So overall material cost of shell plates = 40,000 * 155.71

= Rs 62.29 lakhs

Case 3

The total volume of shell plate required = 16.05m³

The total weight of shell plates = volume*density

= 16.05* 9.50

= 152.49 tonnes

Material cost per metric tonne = Rs 40,000

So overall material cost of shell plates = 40,000 * 152.49

= Rs 60.99 lakh

KARPAGAM COLLEGE OF ENGINEERING 51


TABLE

CASE NO OF SHELL TOTAL VOLUME TOTAL MATERIAL


COURSES OF SHELL PLATE COST (lakhs)

1 6 1 64.86

2 6 16.39 62.29

3 6 16.05 61.00

Table:4
SELECTION OF SHELL

Here we are selecting case 3 because case 2 and case 1 are more expensive.

KARPAGAM COLLEGE OF ENGINEERING 52


So taking the case 3 conditions :

1st shell course thickness = 14.00 mm


2nd shell course thickness = 14.00 mm
3rd shell course thickness = 12.00 mm
4th shellcourse thickness = 10.00 mm
5th shell course thickness = 8.00 mm
6th shellcourse thickness = 8.00 mm

KARPAGAM COLLEGE OF ENGINEERING 53


3.5 m
8mm

3m
8 mm

2.5m
10 mm

12 mm 2.5 m

14mm 1.5 m

14 mm 1m

KARPAGAM COLLEGE OF ENGINEERING 54


DESIGN OF ANNULAR PLATE

As per table 3.1 of API 650 the minimum annular plate thickness is 6 mm.

So minimum thickness required = 6 + 2.0(C.A) = 8 mm

Here we provide 8 mm thick plate for annular plate, since it has to withstand the entire load
carried from the shell.

RADIAL WIDTH OF BOTTOM PLATE

Radial width is calculated using 2 methods and the greater value is selected.

1st method

According to API 650, the minimum radial width is the sum of the projection from outer
surface of the shell plate, dimension between the inner surface of the shell plate and lap
joint, lap of the annular and bottom plate and the 1st shell course thickness.

KARPAGAM COLLEGE OF ENGINEERING 55


Minimum radial width = minimum projection from outer surface of the shell plate

+ Minimum dimension between surfaces of shell plate to lap joint

+ lap of annular and bottom plate + 1st shell course


thickness

From API 650 standards,

The minimum projection from outer surface of the shell plate = 65 mm (min50mm)

Minimum dimension between inside surface of shell plate to lap joint =

610mm (min600)

Lap of annular and bottom plate = 65 mm (standard)

1st shell course thickness =14 mm

So required minimum radial width = 65 + 610 + 65 + 14 = 744 mm

2nd method

The minimum radial width is given by the formula R = (215tb)/ (HG) 0.5

Tb - thickness of annular plate in mm = 8mm

H- Maximum design liquid level in m = 12.5 m

G- Design specific gravity of liquid to be stored =0.95

So radial width = (215*8)/ (14*0.95)0.5 )= 471.63 mm

KARPAGAM COLLEGE OF ENGINEERING 56


As per the above 2 methods the greater of required radial width = 754mm

KARPAGAM COLLEGE OF ENGINEERING 57


DESIGN OF WIND GIRDER

Basic wind speed

It is based on peak guest velocity averaged over a short time interval of about 3 seconds
and corresponds to mean heights above ground level in an open terrain.

Design speed of wind, V = 185 km/hr

Section modulus required for primary girder =D2H2/17 * (V/160)2 cm³ (API 650
3.9.6.1)

D = Nominal tank diameter in meters = 36 m

H = Height of tank shell, including any free board provided above the maximum
filling height = 14 m

Section modulus Z = 1426.88 cm³

Portion of tank shell to be considered for calculating L=13.4(D*t) ^0.5 mm

D = nominal diameter of tank =36 m

t = shell thickness at the attachment = 8 mm

Portion of tank shell to be considered for calculating L=13.4(D*t) ^0.5

=13.4* (36*8) ^0.5 = 227.41 = 227mm (approx)

(The section is taken as per cl 3.9.7.6.2 and cl 3.9.7.7 of API 650.pg 3-44)

Centre of lamina = Ʃax/Ʃa

KARPAGAM COLLEGE OF ENGINEERING 58


= (a1x1 + a2x2 + a3x3)/ a1 + a2 + a3

= 333 mm

Moment of inertia

Moment of inertia (Ixx) = (Ah²+bd³)/12

Ixx = (BD3/12) – [(B-b) (D-d)3/12] {B = 227 mm, D = 666 mm, b = 8 mm,


d = 16 mm}
=66777.57 cm4

Distance from neutral axis to extreme fiber, Y = 33.3 cm

Section modulus of the above I section Zxx=Ixx/Y

Zxx = 66777.57 /33.3 = 2005.33 cm3

Zxx = 2005.33 cm3 > 1426.88 cm3

So design is feasible (as per API requirements Zxx should be greater than
section modulus Z

KARPAGAM COLLEGE OF ENGINEERING 59


Figure

8 mm 8 mm

650 mm

227
mm

666 mm

Location of Primary Wind Girder

The primary wind girder is provided as a walkway at a distance of 1000 mm from the top.

Requirement of Second wind girder (According to API 650, cl3.9.7.1)

KARPAGAM COLLEGE OF ENGINEERING 60


Maximum height of the unstiffened shell = Hi=9.47*t *[(t/d)3]0.5 *(V/160)2

T=Thickness of top shell course =8 mm

D = Nominal tank diameter = 36 m

HI = 9.47 *8 * [(8/36)³]0.5 * (185/160)2 = 10.61 m

(According to API 650 code 3.9.7.1 pg 3-40)

Transformed shell

As per API codes the transformed shell shall be calculated as the change in actual width of
each shell course into a transformed width of shell course having a top shell thickness by
the equation.

(API 650 01.3.9.7.2)

Where;

Wtr = transformed shell course in mm

W = Actual width of each shell course in mm

tuniform = Thickness of top shell course in mm excluding the corrosiom allowance.

= 8 - 2 = 6 mm

KARPAGAM COLLEGE OF ENGINEERING 61


Tactual = Ordered shell course thickness excluding the corrosion allowance in mm for which
Wtr is being calculated.

Shell course Provided Course width Transformed Cumulative


No thickness –CA w mm width wtr mm transformed
mm width mm
6 6.00 3500 3500 3500
5 6.00 3000 3000 6500
4 8.00 2500 1217.848224 7717.848224
3 10.00 2500 697.1370023 8414.985226
2 12.00 1500 265.1650429 8680.150269
1 12.00 1000 176.7766953 8856.926965
Table:5
Since cumulative transformed width is not greater than maximum unstiffened height an
intermediate wind girder is not required( 8.86 < 10.61 )

DESIGN OF FOAM SYSTEM

Foam application rate = 5ir/min/m2 as per (OISD166)


Foam area = ᴨ D2/4
When D = tank diameter = 36
Foam area = 1017 m3
Total foam flow required = Foam area * 5 lpm = 5087 lpm
No of foam makes provided = 4
Foam maker capacity required = 5087/4
= 1272 lpm
DIAMETER OF RISER PIPE
Capacity of each foam maker = 1272
Maximum velocity allowed = 5 m/s
Discharge Q = ᴨd2v/4

KARPAGAM COLLEGE OF ENGINEERING 62


=5087
Diameter of riser pipe = (Q * 4)*(ᴨ *V * 60000)
= 21.6 mm
Diameter of riser pipe provided = 2 inch

SHELL OPENINGS

MAN HOLE (SHELL)


One-man hole is provided to the tank shell at the bottom shell course. It is enough to provide
600mm manhole.
Dimensions required for the manhole according to API 650
Minimum thickness of cover plate, tc = 14mm
Thickness of bolting flange tf = 11mm [API 650 table 3.3]
Bolt circle diameter, Db = 756 mm
Cover plate diameter, Dc = 820 mm [API 650 table 3.5]
Neck thickness, tn = 6 mm [API 650 table 3.4]
Distance from shell to flange face, J = 300 mm.
Distance from bottom of tank to centre of manhole, Hn = 700 mm [API 650 table 3.6]

BOLTS
Number of bolts = 28 mm
Diameter of bolts = 20 mm
Diameter of hole = 24 mm

NOZZLE
One yield nozzle and one suction nozzle are provided for the tank. They are fixed in the
bottom shell courses. Also three nozzles for water draw off and two nozzles for roof drain are
provided. According to BPCL requirements, the size of nozzle are selected as
Yield nozzle size = 200mm
Suction nozzle size = 350 mm

KARPAGAM COLLEGE OF ENGINEERING 63


YIELD NOZZLE

Size of nozzle mm 200


Nominal thickness of flange nozzle pope wall, tn mm 12.7
Diameter of reinforcing plate, Do mm 222
Diameter of hole of reinforcing plate, Dr mm 485
Distance from shell to flange face, J mm 200
Width of reinforcing plate W 590
Distance from bottom of tank to centre of nozzle, Hn mm 325
Thickness of flange, Q mm 28
Outside diameter of flange, A mm 345
Diameter of raised face, D mm 270
Diameter of bolt circle, C mm 300
No of holes 8
Diameter of holes mm 23
Diameter of bolts mm (API 650 table 3.8) 20

SUCTION NOZZLE

Size of nozzle mm 350


Nominal thickness of flange nozzle pope wall, tn mm 12.5
Diameter of reinforcing plate, Do mm 750
Diameter of hole in reinforcing plate Dr 359
Width of reinforcing plate W 915
Distance from shell to flange face, J mm 250
Distance from bottom of tank to centre of nozzle, Hn mm 450
Thickness of flange, Q mm 35
Outside diameter of flange, A mm 415
Diameter of bolt circle, = C mm 475
No of holes 12
Diameter of holes mm 27
Diameter of bolts mm(API 650 table 3.8) 24

KARPAGAM COLLEGE OF ENGINEERING 64


WATER DRAIN

Two water drains are provided to the tank. These are fixed at 180 degrees apart
on the bottom shell course.

Size of drain hole mm is feasible 150


Nominal thickness of flanged nozzle pipe wall, tn mm 10.97
Diameter of hole in reinforcing plate Dr mm 171
Width of reinforcing plate W 495
Diameter of reinforcing plate, Do mm 400
distance from bottom of tank to centre of nozzle, Hn mm 275
Minimum thickness of flange, Q mm 25
Outside diameter of flange, A mm 280
Deameter of raised face, D mm 216
Diameter of bolt circle mm 240
No of holes 8
Diameter of holes mm 23
Diameter of bolts mm 20

DRAW OFF SUMP

One or two draw off sumps are provided at the bottom plate in order to stop the
water content in the product and to remove it

Diameter of nozzle for draw off mm 75


Diameter of sump for draw off, A mm 910
Depth of sump for draw off , B mm 450
Minimum internal pipe thickness mm 6.35
Minimum nozzle neck thickness mm 7.62
Size of drain hole mm is feasible 10
Nominal thickness of flanged nozzle pipe wall, tn mm 10.97
Diameter of reinforcing plate, Do mm 400
Minimum distance from shell to flange face, J mm 200
distance from bottom of tank to centre of nozzle, Hn mm 275

KARPAGAM COLLEGE OF ENGINEERING 65


Minimum thickness of flange, Q mm 25
Outside diameter of flange, Amm 280
Deameter of raised face, D mm 216
Diameter of bolt circle mm 240
No of holes 8
Diameter of holes mm 23

Distance from Centre pipe to shell m 1.5


Thickness of Plates in Sump mm 10
Diameter of bolts mm (API 650 t5able 3.8) 20

DESIGN OF COOLING-WATER SYSTEM

Cooling water system is provided with the tank as per OISD codes. The cooling
water is sprayed onto the tank with the help of nozzles.
INPUT DATA
Type of tank: Fixed cone roof
Diameter of tank: 36m
Height of tank: 14m
Height of wind girder from bottom: 10.61m
Maximum operating height = 14m
Design code OISD 116
CALCULATIONS
D, diameter of the tank = 36m

Height below the top wind girder H1=10.61m

The cooling water is sprayed on the tank with the help of nozzles on two sets of pipelines
around the shell as per the new design aspects.

Total surface area of the tank: 3.14DH

KARPAGAM COLLEGE OF ENGINEERING 66


= 3.14*36*14=1583m

Since OISD specifies a minimum of 3 liters has to be sprayed per minute per unit area of the
shell, the total amount of water required = 1583 * 3
= 4748 lr/min

Considering pressure losses in the pipes connecting the rig and the water tank,operating
pressure of the nozzle is calculated to be between 1.5 to 3.5 kgicm^2.

Ring no:1

Surface area to be cooled by the water from top ring= ᴨ*D*h

D = Diameter of the tank =36m

H = Distance between the two wind girders = 9m

Surface area = ᴨ*36*9 = 1017m^2

Water required = 3*1017 = 3052 lpm

Ring no:2

Surface area to be cooled by the water from top ring= ᴨ*D*h

D = Diameter of the tank =36m

H = Distance between the two wind girders = 9m

Surface area = ᴨ*36*9 = 1017.36m2

Water required = 3*1017 = 3052 lpm

KARPAGAM COLLEGE OF ENGINEERING 67


Selection of nozzles

The nozzles are provided around the shell in an identical manner above top set of nozzle , but
just below the secondary wind grider. Nozzle is separated by a distance of 2.4m on the ring.

No. of nozzles per ring = 3.14*(36+2)/2.4=49.72

Working pressure = 1.5 kg/cm2

Average flow per nozzle = 3052/50


= 61.8 lr/min/nozzle

K- factor of nozzle = flow per nozzle / (working pressure)0.5


= 61.8/(1.5)0.5
= 50.52 = 51

Orifice diameter = 7.5mm

Deflection angle = 120ᵒ


Let the nozzle be provided at a distance of 1m from shell

DIAMETER OF FIRST RING

Max. velocity allowed V =5m/sec

Discharge through the top ring, Q =3052 lr/min


Since water is provided to the ring by two tubes, discharge in one quadrant is calculated as,

Q/4 = 3052/4
= 763 lr/min

KARPAGAM COLLEGE OF ENGINEERING 68


Area A = ᴨd2/4
Let d = diameter of the ring

Also Q/4 = area * velocity


= (ᴨ d2* V)/4
763 = (ᴨ * d2 * 5 * 60000)/4
d = 770.3 mm

So pipe of d = 770.3mm is required

DIAMETER OF SECOND RING

Discharge through the second ring, Q =3052 lr/min


Since water is provided to the ring by two tubes, discharge in one quadrant is calculated as,

Q/4 = 3052/4
= 763 lr/min

Area A = ᴨd2/4
Let d = diameter of the ring

Also Q/4 = area * velocity


= (ᴨ d2* V)/4
763 = (ᴨ * d2 * 5 * 60000)/4
d = 770.3 mm
ie a pipe having diameter of 770.3mm is required.

DESIGN OF ROOF

KARPAGAM COLLEGE OF ENGINEERING 69


Total weight of roof = ᴨ/4 * d2 * 0.005 * 7.85
= ᴨ/4 *36 * 0.005 * 7.85
= 39.93 MT

Live load = 0.46 KPA

Dead load = 4.43 * 0.133 = .589

For designing the roof the combination of live load + dead load < 2.2
i.e. 0.46 + 0.58919 < 2.2

1.04919 < 2.2

So the design is feasible

The slope of the roof shall be 19 mm in 300mm (3/4 in 12 inch) or graeater.


Roof plates shall have a minimum nominal thickness of 5 mm (3/6 inch) 7-gauge
sheet . Thick roof plates are needed for self- supporting roof. Corrosion allowance should
be added with minimum nominal thickness. All internal and external structure members
have a minimum nominal thickness of 4.3mm (0.17 inch).roof plates shall be attached to
the top angle of the tank with a continuous fillet weld on the top side only.

INSPECTION PROCEDURE

Before commencing the inspection of a tank, all detail given in its history card
and records shall be gone thoroughly.

VISUAL INSPECTION

KARPAGAM COLLEGE OF ENGINEERING 70


Visual external inspection of each tank shall be made once a year. During the visual
inspection, following shall be checked:

1. Protective coatings
Condition of paint shall be checked visual for rust spots, mechanical damage, blisters
and film lifting.

2. Roof plates
Roof plates shall be inspected for defects like pin holes, weld cracks, pitting etc., at
water accumulated locations.

3. Ladder, Strairways, Platforms and Structural


These shall be examined for corroded or broken parts. Free movement and alignment
of wheels on rolling ladder shall be checked. Ladder and staircase steps shall be checked for
wear and corrosion. In addition to loss of strength caused by loss of metal, treads becomes
slippery when the surface is worn. Hand rails shall be checked for firmness. Platform and
walkways shall be inspected for thinning, water accumulation areas and general corroded
areas.

4. Tank pads
i) Tanks pads shall be visually checked for settlement, sinking, tilting, spalling, cracking and
general deteriorations.
ii) Proper sealing of opening between tank bottom and the concrete pad shall be checked (no
water shall flow under the tank bottom).
iii) Slops of tank pad shall be checked to ensure water drainage.

5. Anchor Bolts
Anchor bolts where ever provided shall be checked for tightness, and integrity by
hammer testing. These shall also be checked for thinning/bending. Deterioration of bolts is
an indication of excessive settlement. Concrete foundation at anchor bolt shall be checked for
cracks.

KARPAGAM COLLEGE OF ENGINEERING 71


6. Fire Fighting System
General condition of fire fighting facilities and sprinkler systems provided on the tank
with respect to clogging of spray nozzle, perforation of foam connections, etc., shall be
checked. Frequency and procedure for checking shall be as per OSID –Std-142 (Inspection of
Fire Fighting Equipment).

7. Vents & Pressure Relieving Devices


All open vents, flame arrestors and breather valves shall be examined to ensure that the
wire mesh and screens are neither torn or clogged by foreign matter or insects. Rim and
bleeder vents for floating roof tanks shall be examined for proper working. All vents and
pressure relieving devices shall be inspected as per the frequency and procedure outline in
OSID-Std-132 (Inspection of Pressure Relieving Devices).
8. Insulation
If a tank is insulated ,the insulation and weather proof sealing shall be visually inspected
for damage.The water proof sealing of the insulation shall be examined every year, since the
entry of moisture will greatly reduce the insulating properties and may also result in serious
un detected corrosion of the tank plates underneath the insulation. Cracks in the water proof
sealing are apt to occur and wind may enlarge small tears rapidly. It is suspected that
moisture has penetrated through the cracks, a small area of the plates shall be uncovered and
examined for signs of corrosion.
9. Grounding Connection
Grounding connection shall be visually checked for corrosion at the points where they
enter earth and at the connection to the tank. The resistance of grounding connection shall be
annually before monsoon. The total resistance from tank to earth shall not exceed the value
given in OSID-Std-137 (Inspection of Electrical Equipment).
10. Leaks
The tanks shall be inspected for any obvious leakage of the product. Valves and fitting
shall be checked for tightness and free operations.

EXTERNAL INSPECTION

KARPAGAM COLLEGE OF ENGINEERING 72


The detailed external inspection of the tank shall be carried out as per the frequency
mentioned while the tank is in commission.
The following should be checked/inspected during external inspection, besides the visual
inspection.
1. Tank fittings, Accessories and Pipe Connections

All nozzles shall be visuall inspected for corrosion / distortion.


Thickness measurements shall be taken with ultrasonic thickness meter. On
nozzles of 50 mm and above, minimum four readings should be taken.

2. Tank Shell

The tank shell shall be visually examined for external corrosion,


seepage, crack, bulging and deviation from the vertical. Cracks mostly occur
at the welded connections of nozzles to the tank, in welded seams, at the weld
connections of brackets or other attachments to the tank and fillet welds of
shell to the bottom plates.

Shell wall thickness survey should be carried out using ultrasonic


thickness meter. External thickness survey shall be carried out all around for
the first and second bottom shell courses. For the rest of the shell courses,
thickness survey shall be done along the staircase and three compass
directions. An extensive scanning shall be done if there is an indication of
appreciable thickness loss.

The following minimum requirement for thickness survey is


recommended on all tanks:

• All the plates of first and second course of the shell thickness should
be surveyed.

KARPAGAM COLLEGE OF ENGINEERING 73


• On the first course, 3 to 4 readings should be taken on each plate
diagonally. The bottom, middle and top positions of the plate must be
checked.

• On the second course, two readings should be taken on each plate.


One reading shall be near the lower weld joint and other at
approachable height.

• Three readings should be taken on one plate on all the courses along
the staircase and three compass directions. Bottom, middle and top
portion of the plates should be covered.

For tanks having light produces services like gasoline and naphtha,
pitting generally observed in the middle courses of shell. In such
cases, thickness survey should be more extensive on middle courses.
If significant internal corrosion of roof is observed, then top shell
courses should be examined for thickness. In case of eternally
insulated tanks, suitable inspection windows shall be provided to
facilitate wall thickness survey. For the tanks which are likely to have
water at the bottom, the bottom shell courses near the annular ring
welding joint should be thoroughly checked ultrasonically within 150
mm of the bottom plate.

3. Water Draw-off

Water draw-off is subjected to internal to internal and external


corrosion as well as cracking. They shall be visually inspected and
hammer tested along with thickness survey as feasible. Bottom plate
under dip hatch shall be checked for dents etc.

The bottom plates of tank having water at bottom (such as crude oil)
shall be inspected visually in details for internal corrosion or pitting.

KARPAGAM COLLEGE OF ENGINEERING 74


The bottom plates where bacterial corrosion may be suspected (such
as crude oil and HSD tanks) shall be gauged in more detail.

Drain sumps shall be carefully checked for cracks, pitting, leak in the
weld and measured in particular when corrosion at the underside of
the tank bottom plate has been suspected or found.

4. Linings

When the inside surface of a tank are lined with corrosion

resistant material such as sheet lead, rubber, organic and

inorganic coatings, or concrete inspection shall be made to

ensure that the lining is in good condition, that is in proper

position and it does not have holes or cracks in the rubber

lining as evidenced by bulging.

Hardness testing of the rubber lining shall be carried out

while inspecting the tank internally. Care shall be taken

while cleaning the painted surface so that no mechanical

damage takes place.

5. Roof Drains

Roof drains on the floating roof can be designed in many ways.

They can be simple open drain pipes, swivel joints or flexible hose

KARPAGAM COLLEGE OF ENGINEERING 75


drains that keep the water from contaminating the contents. Proper

functioning of the roof drains shall be ensured otherwise this may

lead to sinking or over-turning of the floating roof. The drain lines

shall be checked for blockage before pressure test. All swivel

joints shall be thickness surveyed and serviced during every

outage and individually hydro tested. After assembly of the roof

drain system, complete system shall be hydro tested. In fixed cone

roof tanks slope of the roof should be checked and blockages

should be removed.

KARPAGAM COLLEGE OF ENGINEERING 76


TESTING METHODS

1. DYE PENETRANT TESTING

 Used for detecting discontinuities open to the surface.

Basic Process
 Surface penetration and pre-cleaning.

 Applying a visible or fluorescent liquid penetrant to surface.

 Wait for the penetrant to enter surface breaking discontinuities.

 Removing excess penetrant from the surface.

 Applying a developer to the examination surface.

 Interpretation of indication.

Advantages
 Easy to apply and cheap.

 Interpretation is easier.

 Can be used for any metal.

Disadvantages
 Can detect only surface discontinuities.

2. MAGNETIC PARTICLE TESTING

 Use to detect surface and subsurface discontinuities.

KARPAGAM COLLEGE OF ENGINEERING 77


Basic Process
 Magnetic field is included in the specimen.

 The discontinuities lying in a direction transverse to the field will cause a leakage flux
to develop around it.

 Fine magnetic powder is sprinkled on to this will adhere on the vincity of leakage
flux.

Materials Required
 Magnetic yoke

 Fluorescent iron powder

 Backlight source

 Both AC and DC current can be used for producing magnetic field.

 Permanent magnets can be used for the same.

Advantages
 Can be used for surface and subsurface discontinuities up to 5 mm.

 Interpretation easy

Disadvantages
 Can be used only for ferrous metals.

 Residual magnetism is a problem.

 Power requirement.

3. ULTRASONIC TESTING

KARPAGAM COLLEGE OF ENGINEERING 78


 Ultrasonic waves are sound waves with frequency above the audible
range i.e. above 20000 Hz.

 This method is used to detect all types of defects.

Basic Process
 Ultrasonic wave is propagated through the material.

 Any change of medium reflects the waves due to change in acoustic impedance.

 Defects or change of materials are known by change in acoustic impedance.

 The reflected waves are detected using cathode ray tube.

 The amplitude and distance in the CRT will give an indication on the type and
position of defect.

4. RADIOGRAPHIC TESTING

 Used to detect all kinds of defects

Basic Process
 It is a volumetric examinations using X-ray radiation or nuclear radiation that
penetrates through the specimen and produces an image on the film.

 Radiation is absorbed as it passes through the material.

 The absorption depends on the amount, density and atomic number of the material.

 A discontinuity causes a condition of less material of lesser density.

 The image depends on the amount of transmitted rays that strikes the film.

 Radiographic source can be either X-ray tubes or gamma radiation source.

KARPAGAM COLLEGE OF ENGINEERING 79


 X-ray gives better quality of image.

 Gamma ray sources contain radioactive isotopes of iridium 192 or cobalt 60.

Advantages

 Any kind of defects can be detected.

 Gives a permanent record.

 Defect location and positioning is more accurate.

 One of the widely used methods in construction sites.

Disadvantages

 Radiation safely is an area of concern especially in case of gamma ray sources.

 The operation is likely to be exposed to radioactive radiation and need constant


monitoring.

CONCLUSION

As per the requirement of BPCL (Kochi Refinery), tank for storing furnace oil was
designed. The design was based on API 650 codes. Our design of tank include all main
parts such as fixed supported cone roof , shell plates , bottom and annular plates , wind

KARPAGAM COLLEGE OF ENGINEERING 80


girder and the various accessories like foam system and cooling system. The design
calculations were verified and necessary corrosion allowances were provided to the tank
parts. The tank meets all required safety standards.

KARPAGAM COLLEGE OF ENGINEERING 81


REFERENCE

• API 650 STANDARDS (11th EDITION)


• BOOK OF ABOVE GROUND STORAGE TANKS
• API STANDARDS FOR CONE ROOF TANKS
• www.bpcl.co,in
• OISD 115

KARPAGAM COLLEGE OF ENGINEERING 82

You might also like