Professional Documents
Culture Documents
This project titled “Designing of storage tank for storing furnace oil” gives
and insight into the designing of a storage tank for storing furnace oil. Storage tanks
are constructed to store huge quantities of various petroleum products. Volatile
petroleum products are stored in floating roof tanks. In this project we intend to do
the design of floating roof tank for storage of crude oil.
The tank is designed according to API 650 (11TH Edition) Standards. Furnace
oil comes under Class B category; hence a cone roof type storage tank was selected.
The shell of the tank was designed in the most cost effective manner.
The height of the tank is 16m and Diameter is 12 m. Due to stability problem
the Height of the tank is restricted. The shell plates were designed according to their
availability. The wind guiders are provided for providing stiffness to the shell. The
roof was designed according to API 650 Standards.
The project deals with the design features of a fixed cone roof namely bottom
and annular plates, shell plates, wind girder, cooling water system, roof drain and
firefighting equipment.
Philips Petroleum International Corporation was the prime contractor for the
construction of our refinery. They entrusted the work to Pacific Procon Limited. Construction
work started in March 1964 and the first unit came on stream just after 29 months in
September 1966.
From the commissioning to date, the refinery under took three expansions in the
refining capacity and the installation of secondary processing facilities .The refinery then had
a design capacity of 2.5 metric million tons per annum (mmtpa) which was increased to 3.3
mmtpa in 1973. Production of liquefied petroleum gas (LPG) and aviation turbine fuel (ATF)
commenced after this expansion. Mumbai high court was first processed in 1977.
Refining capacity was further enhanced to 4.5 mmtpa in November 1984 when a
fluidized catalytic cracking unit (FCCU) was added. The secondary processing facilities (fpu,
fccu, lpg and gasoline merox unit) with a capacity of processing 1 mmpta VGO was
commissioned in 1985. It entered the petrochemical sector in 1989 when an aromatic
production facility with a design capacity of 87,200 tons per annum of benzene and 12,000
tons per annum of toluene was commissioned.
In Dec 1994, refining capacity was increased to 7.5 mmtpa (150,000 bpsd). A
fuel gas de-sulphurisation unit was installed as part of this project to minimize sulphur
dioxide emission. A captive power plant of 26.3 MW was commissioned in 1991. An
additional captive power plant of 17.8 MW was commissioned in 1998. KRL is now self
-sufficient in power
PROJECTS COMPLETED
CEMP PHASE-1
The phase 1 of the capacity-expansion-cum-modernization project (CEMP) that
envisaged refinery modifications required to meet BS-II Product Specifications, has met the
target. Supply of auto fuels like petrol and diesel confirming to Bharath Stage-II
specifications began in April 2005.
Rainwater Harvesting
Kochi Refinery has one of the largest rainwater reservoirs in the state with a
detention pond of 1, 25,000 KL capacity to collect surface run off water from around 8.0
lakhs.sq.m of land. The integrated rainwater harvesting system to collect, conserve and
protect rainwater for effective utilization has been constructed and commissioned.
The project will enable (i) using rainwater collected from roof- top during the monsoon for
the process and drinking requirement and thereby reducing the intake of water from Periyar
river, (ii) charging the ground water table using the collected roof rainwater (iii) harvesting
around 1, 25,000 KL of rainwater per annum falling on the land area by collecting the surface
runoff and thereby augmenting the quality of existing water bodies and to replenish the
ground water table.
Eco Park
The Ecological Park within Kochi Refinery premises spreads over a land area of 5.50
acres with a view to restore the healthy ecosystem, control pollution, develop clean
environmental condition and prevent soil erosion. Around 3750 numbers of wide ranges of
forest species, ornamental trees, fruit trees and attractive flowering plants along with
medicinal herbs have found a place in the Eco Park. Treated effluent water is being utilized
to feed the dry land plants. Available resources is also being used to develop scrap land to
green belts which in-turn would promote environmental awareness, enhance the
environmental quality of region, develop habitat for rare migratory species and also increase
tree coverage.
FUTURE PLANS
In the view of the declining market for furnace oil with high sulphur content and
reducing availability/increasing prices of light and low sulphur crudes, a suitable residue up
gradation facility has been found essential for Kochi Refinery. The proposed capacity
expansion of the refinery by the year 2010 will result in generation of additional quantities of
high sulphur heavy residue.
Delayed coking has been identified as an option for up gradation of refinery residue to
value added distillate products. A detailed feasibility study for refinery bottoms up gradation
is being carried out with the help of consultants. The possibility of transporting and
processing some short residue from BPCL-Mumbai Refinery is also being studied.
Utilities section provides the utilities such as steam. Compressed air and cooling
water required for various process units and other facilities in the refinery. A
demineralization plant treats and supplies feed water to boilers and water for process
requirement facilities and for power generation also come under this section. Power
requirements of the entire refinery can be met by the internal generation.
CPP-1: It has capacity of 26.3 MW. The unit was commissioned in 1991.It consists of
gas turbine for power generation and heat recovery steam generator.
CPP-2: The 17.8 MW steam turbo generator was commissioned in 1998.Refinery fuel oil
is used as fuel for generating high pressure steam in the boiler. UB7 and steam is used for
driving the-turbine.
COMPRESSED AIR: It is used as instrument air and plant air. Instrument air is required
for operating the instruments and plant air is used for general cleaning, blowing, and
operating pneumatic tools and other process requirement. The supply of plant air and
instrument air is done by separate air compressor.
COOLING WATER: - Water serves for various purposes such as cooling medium for
process steam, making boiler feed water to produce steam etc. Total consumption of water is
about 2.5 million gallon per day. Water is received from Periyar river basin. Water is stored
in two quarries from where it is pumped to process area and colony after treatment.
The natural water obtained from various sources contains a member of dissolved salts
such as bicarbonates, carbonates, sulphates, chlorides, and nitrates of calcium, magnesium,
and sodium. For high-pressure boilers, steam is put to use in condensing turbines and for
laboratory purpose the dissolved impurities in water are objectionable and complete removal.
Petroleum products are finding increasing use in the day to day activities of mankind
includes personnel and commercial needs. Coupled with the increasing demand for fuels is
the problem of deteriorating quality of air in the environment. One of the largest contributors
to the poor quality of air is vehicular exhaust. Due to the increased pressure on the
environment from various exhaust gases significant reduction in emissions of SO2 and NO2
are required. There is a general agreement that reducing sulphur content is an effective means
of improving air quality.
It is in this context that the sulphur recovery unit comes into perspective. The sulphur
recovery unit is the process unit setup for the removal hydrogen sulphide from the refinery
fuel gas steam. KRL has setup a diesel desulphurization unit of 2 mmtpa capacity to reduce
the sulphur content in diesel from 1 weight % to 0.25 weight %. The input of fuel gas to the
SRU comes in two streams. High pressure steam comprising of gas from CC discharge,
sponge gas from naphtha stabilizer in PU –2 and merge streams from NHDS and KHDS.
Overhead non-condensable of visbreaker along with gas from LV1 constitute steam. The
high pressure gas steam out of SRU has various consumption points of fuel gas.
ENVIRONMENTAL POLICY
The company has been awarded the prestigious ISO 14001 certificate in
recognition of the company’s environment management measures.
BPCL AT A GLANCE
Location: Ambalamugal in Kochi
Refining capacity: 7.5 million metric tonnes per annum
Products: LPG, petrol, diesel, kerosene, naphtha, benzene, toluene,
LSHS, furnace oil, ATF, specialty solvents, bitumen,
rubberized bitumen etc.
KRL is the only company in Kerala with a turnover of over Rs.10000 million. We
have been paying rich dividends to our shareholders consistently. The Board of Directors
has recommended a Dividend of Rs.10/- per share (100%) for the year 2002-03 as against
Rs. 2.20 per share during 2001-02.
Government of India has rated our performance for the year 2002-2003 as
'Excellent'. The turnover during 2002-2003 was Rs 104802 million. The profit before tax
was Rs.6965 million.
Tanks are classified according to their construction, and the construction is on the
basis of the product which is to be stored in them.
FLASH POINT
"Flash point" of any petroleum liquid is the minimum temperature at which the liquid
yields vapour in sufficient concentration to form an ignitable mixture with air and gives a
momentary flash on application of a small pilot flame under specified conditions of test.
Class A Petroleum: Liquids which have flash point below 23 degree C - crude (Bombay
High), gasoline, naphtha, low aromatic naphtha, high aromatic naphtha.
Class B Petroleum: The Liquids that have flash point of 23 degree and above but below 65
degree C . E.g.: superior kerosene oil, high speed diesel, light diesel oil, aviation turbine fuel,
and jet propulsion-5.
Class C Petroleum: The Liquids that have flash point of 65 degree C and above but below
Excluded Petroleum: The liquids that have flash point 93 degree C and above. E.g.
Liquefied gases including LPG do not fall under this classification but form separate
category.
The roof is supported when it is not afloat by a number of adjustable legs with low
and high position. Normally roofs are kept on low legs. When a tank is to be taken out of
service for cleaning or repairs, the roof will be put on high legs to provide space for people to
work inside. Pump out vents in the roof permit the escape of air when an empty or near-
There are 51 floating roof tanks in KRL at present. The following arc the accessories
provided on floating roof tanks:
• Man ways to go in - on the shell and roof.
• Gauging datum plate.
• Gauge hatch with cover and reference mark.
• Auto gauges (in certain tanks).
• Dial thermometer.
• Mixing devices.
• Water draw.
• Roof drain.
• Inlet pipe header with jet nozzle and outlet.
• Gas fired burners with steam heating coil for heating the product.
• (Asphalt /LSHS).
• Outside stairway.
• Inside stairway.
• Gauging platform.
• Roof legs and pump-out vents.
• Roof guides to keep the roof in position.
• Roof shoe with neoprene seal.
• Metal conductors over the roof seal to dissipate electric charge to the
They have fixed cone roof in addition to a floating roof and they are intended for
storing toxic products having high vapour pressure. Products like benzene and toluene are
carcinogenic and should be prevented from escaping into the atmosphere. So they are stored
in floating cum cone roof tanks. These tanks prevent product from contamination and are
used to store class A and class B products. There are 13 floating cum cone roof tanks in KRL
at present.
• DYKED ENCLOSURES
Petroleum storage tanks shall be located in dykes enclosures with roads all
around the enclosure. Aggregate capacity of tanks located in one dyked
enclosure shall not exceed following values:
For a group of floating roof tanks: 120000cu.m.
For a group of fixed roof tanks: 60000cu.m.
If a group of tanks contains both fixed and floating roof tanks then it shall
be treated as a group of fixed roof tanks for the purpose of above limits.
The height of tank enclosure dyke shall be at least one meter and shall not
be more than 2.0m above average grade level; inside. However, for
excluded petroleum the minimum height of dyke wall shall be 600mm.
Inter-distance between the nearest tanks located in two dykes shall be
equivalent to the largest tank diameter or 30m, whichever is more.
The dykes should be of earthen construction havl11g trapezoidal cross -
section. The dyke shall not have slope steeper than 1.5 horizontal to 1.0
ve11ical. The top flat surface of dykes up to 1m and up to 2m height, top
flat surface shall have 1000mm width. Brick or stone masonry wall may
be provided where space does not permit construction of earthen dykes.
Pump stations should be located outside dyke areas by the side of roads.
Grouping of Tanks
Fire Walls
In an enclosure where more than one tank is located, firewalls of 600mm should be
provided as explained below:
Any tank having a diameter more than 30m should be separated with fire
walls from other tank
Firewalls should be provided by limiting the aggregate capacity of group of
tanks within, to 20000cu.m.
General
The tank height should not exceed one and a half times the diameter of the
The following stipulations shall apply for the inter-distances for above ground tanks
storing petroleum:
Inter distances for storage tanks
Sl.no Item FRT
CRT(Class A&B Class C
Petroleum) Petroleum
Bottom plates are those plates which are laid at the bottom of the tank. These plates
are lap welded to each other. All bottom plates have a nominal thickness of 6 mm excluding
of corrosion allowance specified by the purchaser.
Bottom plates get corroded rapidly if the fluid is having sea water content (crude
petroleum). Bacterial corrosion of the bottom plates is generally observed in crude and HSD
tanks having high sulphur content. The bottom plates develop deep isolated pits which
eventually puncture and bottom starts leaking. So the proper corrosion allowance should be
provided.
Annular plates are those bottom plates on which the shell plates rest. Annular bottom
plates should be capable of withstanding the weight of the shell plates and the appurtenance.
According to API 650 (3.5.2), annular bottom plates shall have a radial width that
provides at least 600 mm between the inside of the shell and any lap welded joint in the
remainder of the bottom and at least a 50 mm projection outside of the shell.
The projecting out portion of the annular bottom plates are prone to corrosion at the
edges due to accumulation of water between the foundation and the annular bottom plates. So
here also appropriate corrosion allowance should be given.
A draw off sump is provided at the bottom of the tank such that a sl11a'll inclination
is given to the bottom plates towards the sump. Sump shall be placed in foundation before
bottom placement. A neat excavation shall be made to conform to the shape of the draw off
sump. The sump shall be put in place, and the foundation shall be compacted around the
sump after placement and the sump shall be welded to the bottom.
SHELL
Shell is the major portion of the tank which is exposed to the atmosphere. The
major problem that may arise is corrosion. Shell plates generally get corroded internally
where liquid-vapour is maintained. Internal corrosion in the vapour space is most commonly
caused by hydrogen sulphide vapour, water vapour and oxygen giving pitting type corrosion.
Atmospheric corrosion can occur on all external parts of the tank. This type of corrosion may
range from negligible to severe depending on upon the atmospheric condition of the locality.
All vertical and horizontal shell joints shall be full penetration and full fusion welds. Shell
joints shall be double welded butt joints. . Wind girders shall be welded to the tank at the
location designed. Welding shall be of the same quality as used for the shell. The necessary
shell openings such as manholes, nozzles, drain holes etc. shall be provided to the horizontal
plates.
SHELL OPENINGS
The important shell openings are shell man hole, yield and suction nozzles, water
drain and rain drain.
1. SHELL MANHOLE
One manhole is provided to the tank shell at the bottom shell course for the entry of
humans into the tank for maintenance or other purposes. Here a 600mm dia. manhole is
provided.
Three yield nozzles and one suction nozzle arc provided for the tank. These nozzles
are also fixed at the bottom shell course. Yield nozzle is provided for receiving finished,
intermediate or unfinished products into the tank. This nozzle is designed according to the
velocity of yielding and need for agitation. Suction nozzle is designed according to capacity
of the tank and according to place to where the oil is transferred.
Three nozzles for water draw off and two nozzles for roof drain are provided. The
three water drains are fixed at 120 degree apart on the bottom shell course.
Even though one roof drain is sufficient for proper working two roof drains are
provided. As per the API standards the other is provided as a 100% Standby. Roof drain
outlets are provided at the opposite sides of the bottom shell course.
WIND GIRDER
SEAL
The space between the outer rim of roof and shell should be sealed by an approved
sealing device and sea1ing material should be resistant to the stored product and durable
against friction due to roof movement. Sealing system should exert sufficient sealing
pressure in all directions to prevent any evaporation losses and the arrangement should touch
the product during the operation.
Fig:4 seal
Foam seals have excellent flexibility and recovery from compression and at the same
time permit the roof movement up and down freely with the level of tank contents.
Automatic Tank Gauging (A TG) is carried to obtain information about the total
volume or weight of the product in the tank. This information is obtained from four
parameters i.e., liquid level, tank capacity table, average temperature and relative density of
individual tank.
COOLING SYSTEM
Storage tanks are equipped with water cooling system to bring down the temperature
of the tank shell & protect them from damage when a fire hazard occurs to a neighboring
tank. The system consists of rings fitted around the tank. Numerous nozzles are fixed into the
rings through which water is sprayed to the tank shell at a particular pressure. Water is
supplied to the cooling rings by means of 2 risers which arc placed diametrically opposite to
each other.
FOAM SYSTEM
The foam generally used in modem tanks is AFFF (Aqueous Film Forming Foam). It
is a synthetic film forming concentrate and is based on fluorinated surfactants plus foam
stabilizers and is diluted with water to a 3% to 6% solution. The foam formed acts as 'a
barrier to exclude air or O2 and to develop an aqueous film on the fuel surface capable of
suppressing the evolution of fuel vapour. The foam produced with AFFF concentrate is dry
chemically compatible and thus is suitable for combined use with dry chemicals.
The materials used in the construction of storage vessels are usually metals, alloys,
clad-metals, or materials with linings that are suitable for containing the fluid. Where no
appreciable corrosion problem exists the cheapest and most easily fabricated construction
material is usually hot rolled mild (low carbon) steel plate.
Low carbon steels are rather soft and ductile and are easily rolled and formed into the
various shapes used in fabricating vessels. These steels are also easily welded to give joints
of uniform strength relatively free from localized stresses. The ultimate tensile strength is
usually between 380Mpa and 450Mpa and the carbon content between 0.15% and 0.25%.
The material generally used for manufacturing storage tanks in India is IS2062 grade
A. It is a low carbon, hot rolled steel with the following specifications.
Table:2
It has a minimum ultimate tensile strength of 410.6 Mpa and yield strength of
247.6 Mpa.
The pipe material used for making roof legs is AI 06 grade B. The chemical
composition is given below:
Silicon(min.) 0.1%
-
Table:3
The minimum tensile strength is 414 Mpa and the minimum yield strength is 241 Mpa
1. Tank selection
The furnace oil is a highly volatile; the flash point of furnace oil is 66ºC. So it
comes under class C of petroleum products and has to be stored in a fixed cone roof tank.
For fixing the height and the diameter of the tank, the criterion to be maintained as
per API 650 is that the ratio of the total height of the tank to the internal diameter must be
less than 1.5.
Volume, V=πR2H
V = 3.14*(18*18)*14
= 14243.04 m3
BOTTOM PREPERATION
To assess the soil bearing capacity of soil at locations under the bottom plate
penetration test was conducted by IIT Madras. Cone penetration resistance (CPR) was
calculated by determining the number of blows required to attain a 300 mm penetration by
test cone.
The cone penetration resistance is found to vary between 20 and 40 which indicates
that the maximum settlement to be less than 100mm which is permitted for large diameters.
(Present tank being of 50m diameter)
Soil testing
The test sample of soil is collected from various positions of tank bottom and is sent
to IIT Madras. It was tested and certified OK for the construction of the above mentioned
tank.
Bitumen carpeting
According to API 650 standards, bottom plates shall have a minimum nominal
thickness of 6mm exclusive of any corrosion allowance.
So the thickness of bottom plate is selected as 8mm. (Since the thickness of shell plates
available in market are of sizes 6, 8, 10, 14, 12, 18, 20, 24 mm etc.)
Bottom plates of sufficient size shall be ordered so that when trimmed at least a 25 mm width
will project beyond the outside edge of the weld attaching the bottom to the shell plate. The
Tank is made of plates. Plates of same width have been welded together to form a
course of equal diameter. The course contains a number of vertical joints of length = plate
width. A number of courses are welded together horizontally to form the total height of the
tank.
According to API 650, the shell thickness for a tank of diameter in the range of 36-60 m
should not be less than 8 mm. (For tank diameter less than 36 m, the shell thickness should
not be less than 6 mm).
The shell thickness is calculated taking into account the material specification and allowable
stresses. The maximum allowable product design stress Sd (API 50 CI.3.6.2.1), shall be either
two-third the yield strength or two-fifth the tensile strength whichever is less, the maximum
allowable hydrostatic test stress St (API 50 CI.3.6.2.1), shall be either three-fourth the yield
strength or three-seventh the tensile strength whichever is less.
Or
Sd = 2/5*Tensile strength
Sd = 2/5*410.6=164.24 Mpa
St = 3/4*yield strength
S = 3/4*247.60=185.70 Mpa
Or
St = 3/7*Tensile strength
St = 3/7*410.6=175.9 Mpa
According to API 650 thicknesses of tanks less than 60 m in diameter is calculated using
I-foot method calculates the thickness required at the design point 0.3 m (1 ft) above the
bottom of each shell course. In this method we find out the design shell thickness (td) and the
hydrostatic test shell thickness (tt) and the maximum of the two values is taken.
Here,
Td =4 .9*D*(H-0.3)*G/Sd + CA
Tt = 4.9*D*(H-0.3)/St
H = height from the bottom of the course under consideration to the top of the shell.
Since the height of the tank is 14 m, we have to divide it into a number of courses
considering the economic conditions. This is done by trial and error method. It is to be noted
that the standard thickness available in market are 6, 10, 12, 14, 16, 20, 25 mm. Values of
We select a number of random cases with varying number of courses and course width. The
total weight of the metal used and cost in each case is also calculated to determine the most
economical case of shell structure.
Case 1
We divide the total Height 14 m to 6 courses of 2, 2, 2.5, 2.5, 2.5, and 2.5 m respectively.
Shell thickness.
1st Course
3rd Course
5th Course
Case 2
We divide the total Height 14 m to 6 courses of 1.5, 1.5, 2.5, 2.5, 2.5 and 3.5 each
respectively.
Shell Thickness
1st Course
2nd Course
3rd Course
4th Course
5th Course
Case 3
We divide the total Height 16 m to 6 courses of 1, 1.5, 2.5, 2.5, 3, and 3.5 respectively.
Shell Thickness
1st Course
2nd course
3rd course
4th course
5th course
6th course
For selecting the optimum combination we are considering the material cost and
fabrication cost for each case
Case 1
= 16.05 * 9.50
= 162.16 tonnes
= Rs 64.86 lakhs
Case 2
= 16.39* 9.50
= 155.71 tonnes
= Rs 62.29 lakhs
Case 3
= 16.05* 9.50
= 152.49 tonnes
= Rs 60.99 lakh
1 6 1 64.86
2 6 16.39 62.29
3 6 16.05 61.00
Table:4
SELECTION OF SHELL
Here we are selecting case 3 because case 2 and case 1 are more expensive.
3m
8 mm
2.5m
10 mm
12 mm 2.5 m
14mm 1.5 m
14 mm 1m
As per table 3.1 of API 650 the minimum annular plate thickness is 6 mm.
Here we provide 8 mm thick plate for annular plate, since it has to withstand the entire load
carried from the shell.
Radial width is calculated using 2 methods and the greater value is selected.
1st method
According to API 650, the minimum radial width is the sum of the projection from outer
surface of the shell plate, dimension between the inner surface of the shell plate and lap
joint, lap of the annular and bottom plate and the 1st shell course thickness.
The minimum projection from outer surface of the shell plate = 65 mm (min50mm)
610mm (min600)
2nd method
The minimum radial width is given by the formula R = (215tb)/ (HG) 0.5
It is based on peak guest velocity averaged over a short time interval of about 3 seconds
and corresponds to mean heights above ground level in an open terrain.
Section modulus required for primary girder =D2H2/17 * (V/160)2 cm³ (API 650
3.9.6.1)
H = Height of tank shell, including any free board provided above the maximum
filling height = 14 m
(The section is taken as per cl 3.9.7.6.2 and cl 3.9.7.7 of API 650.pg 3-44)
= 333 mm
Moment of inertia
So design is feasible (as per API requirements Zxx should be greater than
section modulus Z
8 mm 8 mm
650 mm
227
mm
666 mm
The primary wind girder is provided as a walkway at a distance of 1000 mm from the top.
Transformed shell
As per API codes the transformed shell shall be calculated as the change in actual width of
each shell course into a transformed width of shell course having a top shell thickness by
the equation.
Where;
= 8 - 2 = 6 mm
SHELL OPENINGS
BOLTS
Number of bolts = 28 mm
Diameter of bolts = 20 mm
Diameter of hole = 24 mm
NOZZLE
One yield nozzle and one suction nozzle are provided for the tank. They are fixed in the
bottom shell courses. Also three nozzles for water draw off and two nozzles for roof drain are
provided. According to BPCL requirements, the size of nozzle are selected as
Yield nozzle size = 200mm
Suction nozzle size = 350 mm
SUCTION NOZZLE
Two water drains are provided to the tank. These are fixed at 180 degrees apart
on the bottom shell course.
One or two draw off sumps are provided at the bottom plate in order to stop the
water content in the product and to remove it
Cooling water system is provided with the tank as per OISD codes. The cooling
water is sprayed onto the tank with the help of nozzles.
INPUT DATA
Type of tank: Fixed cone roof
Diameter of tank: 36m
Height of tank: 14m
Height of wind girder from bottom: 10.61m
Maximum operating height = 14m
Design code OISD 116
CALCULATIONS
D, diameter of the tank = 36m
The cooling water is sprayed on the tank with the help of nozzles on two sets of pipelines
around the shell as per the new design aspects.
Since OISD specifies a minimum of 3 liters has to be sprayed per minute per unit area of the
shell, the total amount of water required = 1583 * 3
= 4748 lr/min
Considering pressure losses in the pipes connecting the rig and the water tank,operating
pressure of the nozzle is calculated to be between 1.5 to 3.5 kgicm^2.
Ring no:1
Ring no:2
The nozzles are provided around the shell in an identical manner above top set of nozzle , but
just below the secondary wind grider. Nozzle is separated by a distance of 2.4m on the ring.
Q/4 = 3052/4
= 763 lr/min
Q/4 = 3052/4
= 763 lr/min
Area A = ᴨd2/4
Let d = diameter of the ring
DESIGN OF ROOF
For designing the roof the combination of live load + dead load < 2.2
i.e. 0.46 + 0.58919 < 2.2
INSPECTION PROCEDURE
Before commencing the inspection of a tank, all detail given in its history card
and records shall be gone thoroughly.
VISUAL INSPECTION
1. Protective coatings
Condition of paint shall be checked visual for rust spots, mechanical damage, blisters
and film lifting.
2. Roof plates
Roof plates shall be inspected for defects like pin holes, weld cracks, pitting etc., at
water accumulated locations.
4. Tank pads
i) Tanks pads shall be visually checked for settlement, sinking, tilting, spalling, cracking and
general deteriorations.
ii) Proper sealing of opening between tank bottom and the concrete pad shall be checked (no
water shall flow under the tank bottom).
iii) Slops of tank pad shall be checked to ensure water drainage.
5. Anchor Bolts
Anchor bolts where ever provided shall be checked for tightness, and integrity by
hammer testing. These shall also be checked for thinning/bending. Deterioration of bolts is
an indication of excessive settlement. Concrete foundation at anchor bolt shall be checked for
cracks.
EXTERNAL INSPECTION
2. Tank Shell
• All the plates of first and second course of the shell thickness should
be surveyed.
• Three readings should be taken on one plate on all the courses along
the staircase and three compass directions. Bottom, middle and top
portion of the plates should be covered.
For tanks having light produces services like gasoline and naphtha,
pitting generally observed in the middle courses of shell. In such
cases, thickness survey should be more extensive on middle courses.
If significant internal corrosion of roof is observed, then top shell
courses should be examined for thickness. In case of eternally
insulated tanks, suitable inspection windows shall be provided to
facilitate wall thickness survey. For the tanks which are likely to have
water at the bottom, the bottom shell courses near the annular ring
welding joint should be thoroughly checked ultrasonically within 150
mm of the bottom plate.
3. Water Draw-off
The bottom plates of tank having water at bottom (such as crude oil)
shall be inspected visually in details for internal corrosion or pitting.
Drain sumps shall be carefully checked for cracks, pitting, leak in the
weld and measured in particular when corrosion at the underside of
the tank bottom plate has been suspected or found.
4. Linings
5. Roof Drains
They can be simple open drain pipes, swivel joints or flexible hose
should be removed.
Basic Process
Surface penetration and pre-cleaning.
Interpretation of indication.
Advantages
Easy to apply and cheap.
Interpretation is easier.
Disadvantages
Can detect only surface discontinuities.
The discontinuities lying in a direction transverse to the field will cause a leakage flux
to develop around it.
Fine magnetic powder is sprinkled on to this will adhere on the vincity of leakage
flux.
Materials Required
Magnetic yoke
Backlight source
Advantages
Can be used for surface and subsurface discontinuities up to 5 mm.
Interpretation easy
Disadvantages
Can be used only for ferrous metals.
Power requirement.
3. ULTRASONIC TESTING
Basic Process
Ultrasonic wave is propagated through the material.
Any change of medium reflects the waves due to change in acoustic impedance.
The amplitude and distance in the CRT will give an indication on the type and
position of defect.
4. RADIOGRAPHIC TESTING
Basic Process
It is a volumetric examinations using X-ray radiation or nuclear radiation that
penetrates through the specimen and produces an image on the film.
The absorption depends on the amount, density and atomic number of the material.
The image depends on the amount of transmitted rays that strikes the film.
Gamma ray sources contain radioactive isotopes of iridium 192 or cobalt 60.
Advantages
Disadvantages
CONCLUSION
As per the requirement of BPCL (Kochi Refinery), tank for storing furnace oil was
designed. The design was based on API 650 codes. Our design of tank include all main
parts such as fixed supported cone roof , shell plates , bottom and annular plates , wind