Company ABC follows the ASAP Methodology for SAP Implementation and Rollout programs.
However the methodology is customized to leverage the Company ABC Global Delivery Model
(GDM) and the requirements of the engagement. For the purpose of this engagement, only the
Project Preparation and Business Blueprint stages are in scope. However the complete
methodology is presented for a complete overview.
Company ABC has categorized the rollout track-wise as the Business Process Design, Technical
Requirements, Data Migration and Training Tracks. The Rollout Track will be governed by the
Company ABC Project Management Methodology. The subsequent sections explain the various
phases of project as proposed by Company ABC.
The proposed Company ABC approach involves appropriate pieces of the project work being
done at our offshore facilities. This approach differentiates Company ABC in that our mature
Global Delivery Model (GDM) allows us to do the work where it makes the most sense. Our
experience in delivering projects in this manner acknowledges that many ERP implementation
project activities require hands-on, face-to-face interaction onsite. There are, however, other
tasks which do lend themselves very readily to a combined onsite – offshore delivery model. The
Company ABC Global Delivery Model lowers cost, enhances quality and speeds time to
completion.
Phase 1: Project Preparation
The objectives of the Program Preparation phase involve aligning the program to the overall
organization strategy, drafting overall project plan, resources for various phases, and conducting
fit- gap analysis. The participants for this phase would be Company ABC and the client Team,
Business Process Owners and super users.
Develop roadmap
Identify Milestones
The objectives of the Business Blueprint phase are to lock down scope, define functional
specifications, define required customizations and prepare data migration plan.
The realization phase includes developing functional and technical specifications, work flow,
system test plans, baseline and the final configuration. Additional activities also include creation
of reports, forms; data cleansing, data migration and integration testing.
The final preparation involves validation of the solution design and development, extensive
testing across the complete business cycle, user acceptance testing and preparation for Go–live &
Support.
Go live & support involves transporting the customized system to the production environment
and monitoring the live system.
Training Methodology is an integral part of the ASAP methodology at different phases of the
project, namely Blue print, Realization, Final preparation & Go-Live support phases. Company
ABC facilitates the Training process for the project but the client is responsible for training the
users.
Provided below is the training methodology, that Company ABC follows for all its SAP
Implementation/ Rollout engagements. Company ABC proposes a Training spanning across the
entire SAP Rollout engagement. However considering the small number of users and already
existing template in Dubai, the training activities will be redefined after discussions with Mittal
Steel.
Training Project Phases Deliverables
• Hardware/software • Templates
requirements
• Identify tools
• Identify standards
Develop Program Pilot Program Design Program
• Course materials • Course pilots • Administer training data
base
• Exercises • Facilities/software tests
• Deliver courses
• Job aids • Train-the-trainer
• Course evaluations
• Training environment • End-user registration
• Course schedule
• Role/course mapping
Post Appraise Program Provide Ongoing Support
• Course evaluation • Maintenance processes
summaries
• Maintenance of training
• Recommendations for materials and data bases
improvement
• Transition to permanent
owners