Our ref : BR/3055/04/2011

Date : 4th of May 2011

To : SDV LOGISTIC (SINGAPORE) PTE. LTD.


7 Penjuru Close # 01-0, Singapore 608779
Attn. : Mr. Vincent Lau
C.c. : Mr. Raymond

SUMMARY OF QUOTATION
RE : SCHNEIDER NEW WAREHOUSE LOT 16

We thank you so much for your kind invitation to quote for the above mentioned and we take great
pleasure to submit here under our quotation for your kind consideration.

NO DESCRIPTION AMOUNT

WAREHOUSE BUILDING
I BUILDING WORKS $233,068.00
A PRELIMINARIES $1,500.00
B WORKS
FLOOR EPOXY SIKA, thick 4mm $118,820.00
C GYPSUM PARTITION for Office, Pantry, Server, Switch room $2,988.00
including painting
D Door complete set with door closer $2,100.00
E SHED AREA for Loading & unloading ( spandek + H beam) $91,200.00
H Beam 5x10" and C chanel 2x4"
F Smoking Shelter Area (18m x 3.3m) $4,500.00
G Drainage for Canopy, L = +/- 90 M' $5,400.00
H Casting concrete for smoking area (18 x 3.3m) $2,360.00
I Casting concrete for shelter canopy area $1,640.00
= 2 x ((7.2x5.7)/2) = 2 x 20.5 = 41 M2
J Casting concrete Kanstin. H = 250mm $1,560.00
= 2 x (7.2+5.7) = 2x12.9m = 25.8 M'
K Hack exixting kanstin + throw/unload soil $1,000.00

TOTAL $233,068.00
ROUNDED $233,000.00

Say : Singapore Dollars Two Hundred Thirty Three Thousand Only

Trusting the above quotation meets your requirements and looking forward to your early reply
Time of Completion : 4 - 6 week
Validity : 30 (thirty) day
Term of Payment : No Down Payment
balance in 30 days after job completion

Yours faithfully,
PT. BUMI RAYA

YURISTO, S.E. / TOTO


Managing Director
+6282 171 323 999
NO DESCRIPTION UoM Unit Price Quantity
Estimate

WAREHOUSE BUILDING
I BUILDING WORKS
A PRELIMINARIES Ls $1,500.00 1
B WORKS
FLOOR EPOXY SIKA, thick 4mm, 4 layer M2 $65.00 1,828
Qty = (30mx43m) + (12.5mx43m)
C GYPSUM PARTITION for Office area M2 $18.00 166
Server room = 2.7x3m = 8.1 m2
Pantry rrom = (1.8+3x3m) = 14.4 m2
Meeting room = (2.5+6.5) x3m = 27m2
Office room = (4.5+6.5) x 3m = 33m2
Swith Room =(3.5+6) x 3m = 30m2
Admin room = (3+6) x 3m = 27 m2
Prayer room =( 2.5+4) x 4m = 26m2
D Door ( complete set + door closer ) Set $300.00 7
E Canopy Area = 48 x 19m = 912 m2 M2 $100.00 912
F Smoking Area = 18 X 3.3m = 59.4m2 M2 $75.00 60
G Drainage for Canopy, L = +/- 90 M', rebar T 8 M' $60.00 90
30cm x 25/50 cm drain, with K 300 concrete, thick = 15cm
H Casting concrete for smoking area (18 x 3.3m), thick 15mm M2 $40.00 59
and rebar T 8
I Casting concrete for shelter canopy area M2 $40.00 41
= 2 x ((7.2x5.7)/2) = 2 x 20.5 = 41 M2
J Casting concrete Kanstin. H = 250mm M' $60.00 26
= 2 x (7.2+5.7) = 2x12.9m = 25.8 M'
K Hack exixting kanstin + throw/unload soil Ls $500.00 Ls