Professional Documents
Culture Documents
1.0 INTRODUCTION
This report is into two chapters, the first chapters outlines the
importance and aim of SIWES, it gives an over view of the
company’s profile and a good representation of the organizational
structure of the management. The second chapter describes the
various industrial equipments, their mode of operation, how there
are troubleshot and repaired. Chapter three treats the
procedures for conduit wiring a with emphases on the working of
the electrical lighting arrestors and earth pit while the last is the
conclusive chapter which highlights the skills I acquired by virtue
of my training, the challenges I encountered and possible
recommendations.
1
1.1 OBJECTIVE OF SIWES
FIELDS OF ACTIVITIES
2
• Oil and gas upstream and mid stream prospects
• Infrastructure
• Civil works.
• Project management
SECTIONS
• Welding section
• Mechanical/automobile section
3
• Carpentry section
• Account department
• Store department
Chairman
Director
Quality Mngr. Maintenance Mngr. Utility Mngr. Store Mngr. Acc Mngr. Admin Mngr. Marketing Mngr.
Security Officer.
4
Senior officer Maintenance Engr. Utility Engr. Senior officer Acc. Officer Admin Officer Marketing Officer
Asst. Officer
Officer Fore man Sub. Asst. Engr. Officer Cashier Asst. Admin Officer
Officer Security Guards
CHAPTER TWO
5
2.0 WELDING MACHINE:
6
welding machine is as simple as cleaning it and allowing
the wire feed freely.
II. Look out for the tip near the wire exist inside the gun. A
worn out tip doesn’t allow the electricity to efficiently hit
and this creates a lot more work on the job. Burn back
can cause a bad wire.
III. Inspect the ground clamp, when the part of the clamp is
coated with oxide, electrons can’t ready transfer. A bad
ground clamp can cause a lot of resistances and change
the way current comes back to the machine.
2.2 GENERATOR:
7
Figure 1; Lincoln SA-200 generator set
8
Figure 2; lincoln SA- 200 exciter.
Facing the machine from the front the parts are named as follows:
9
The exciter coils and the poles pieces form electromagnets. When
DC current flows through the exciter coil, the magnetic fields
produced by the exciter coils are broken by the winding on the
exciter armature producing approximate 115 volts DC at full RPM.
The faster the engine turns the more voltage the exciter
produces.
In fig c below, the wiring diagram, you will see that there are two
halves of the exciter circuits. The exciter generator produces 115
volts DC that is fed to the auxiliary power outlet and to the main
exciter shunt coils. This DC current is varied by the fine current
control rheostat (like a valve) then fed into the main exciter
shunts coils. This controls the strength of the magnetic field,
which controls the amount of welding current that is a variable .A
fault in either circuit or the machine will not weld if the failure is
in the exciter shunt circuit the generator can still produce power.
This can be verified by checking the auxiliary with a meter, light
10
or a grinder if you can grind but not weld the exciter shunt coil is
faulty.
I. Reach under the exciter armature and locate the black and
blue leads, the wire should be connected with a butt splice
or bolted together. If they are spliced or connected with bolt
and nut, you must break this wire apart. It’s only then will
you be able to check the coils separately.
II. To check the exciter field coils, remove both exciter brush
from their holders and make sure they do not touch anything
while making measurement with the VOM on the lowest
resistance scale you can use, check resistance between the
right brush lead to each to the separated wire. If the wire is
11
good, one wire will show resistance, the other will not, this is
normal. The resistance should be approximately 130-170
ohms. If you get no resistance go to the next higher range
(make sure you do not touch the lead with your hand else
you could be reading the resistance of your body.)
III. The next thing to check is the resistance from each coil leads
to the outside terminal (it may have a red wire attached) of
the fine current control rheostat. One of the wires will show
continuity, between the lead and the rheostat. Both
measurements should be identical.
V. If the coils check out ok, then the exciter armature will be
the next to be suspected.
13
The exciter field coils are held in place with solid iron “pole
piece”. The special pieces of iron do more than just hold the
exciter coils in place. They retain a small amount of residual
magnetism just a bit. They hold a small amount of residual
magnetism to provide “self-excitation” so the exciter will
start generating current from a dead start. The pole piece
can lose their magnetism as the unit sits idle for a long
period to time and there is no easy test to detect the loss.
When the exciter field coils, the brushes, and the exciter
armature check out, the only thing left to do is “flash the
field”. This is normally done with a 12 volts car battery, not
with standing in front of the machine in a trench coat. This is
how it is done:
14
there will e strong spark the field poles will be
“flashed”.
15
The other machine that we repair and service at the work shop
includes; grinding and cutting machine. They are mostly used by
the welders, carpenters, panel beater and on rear occasion by
electricians. They are used for cutting metals, woods, smothering
rough surface, cutting almond cables etc.
CHAPTER THREE
Metal and plastic conduit can be bent in the jobsite to allow neat
installation without excessive number of manufactured fittings.
This is particularly advantageous when following irregular or
curved building profile. Conduit wiring is more expensive than
other forms of electrical wiring. One major disadvantage of the
type of wiring is that it doesn’t dissipate heat as readily as those
installed in open wiring. Therefore it is advised that the current
capacity of each the conductor be reduced.
18
It is sometimes called thin wall. It is commonly use instead of
GRC as it is less costly and much lighter, though it is damage
easy.
V. ALUMINUM CONDUIT
20
access for pulling wires and space for splicing. Condulets are in
various types, moisture rating and materials including galvanized
steel, aluminum and PVC. Some of the Condulets includes L-
shaped bodies, T-shaped bodies and –shaped bodies. The figure
below show some fittings for PVC wiring.
21
Piping is mostly done before plastering or decking, in cases
where the piping is done before plastering is done, then the
walls have to be broken and holes bored through which the
pipes will pass. When passing a pipe through a junction, the
PVC pipe needs to be bent using a bending spring, also if the
lent of the pie will not reach to its destination, couplings and
adhesive gums are used to extend the length. It is important
to note that during pipe, outlet boxes for switches, lightning
sockets are connected.
This is done after the piping activity. Here the major tools used
are; scaffold, fishing tape, wires of various sizes depending on
the circuit being wired. The table below shows the sizes of
cables used in some wiring units.
Table3.0
22
3.5 SURFACE MOUNTING RACE WAY/ TRUNKING
• Positive conductor
• Negative conductors
• Copper plate
• Plate connectors
• GI pipr ¾
• PVC pipe(1)
• Earth pit
• Charcoal
• Bentonate powder
24
used to deliver faulty current to it. In the lightening protection,
the role of the earthening system is to dissipate the lightening
current into the earth as quick as possible whilst minimizing the
ground potential rise and maximizing the potential fall off from
the current injection pit.
• Rod material
• Couplers
• Driving equipments
25
• Wires
i. The location of the pit should be such where the soil has
reasonable chances of becoming moist. This is because low earth
26
resistance is required to give effective earthling protection to
electrical fittings and a moist soil has such quality.
iii. Earth plates and earth wires must be of the same metal.
iv. Wood coal powder (charcoal) and salt must be filled in the
earth pit around the earth pipe or plate.
CHAPTER FOUR
CONCLUSION
27
By virtue of this training I received, I have acquired the
following skills from my SIWES work place.
28
4.1 Problems encountered my SIWES.
29
4.3 Advice For Future Participants
30