Changes Comparison Between Master Programme Rev 3 & Rev 4


Activity ID Description Original REV3 Start REV3 Finish REV4 Start REV4 Finish Variance - REV3/4
Duration Finish Date

The Minton Condominum Master Programme Rev 4 267 29-Sep-10 29-Jul-11 29-Sep-10 08-Aug-11 -8

General 0 31-Mar-11 31-Mar-11 06-May-11 06-May-11 -31

Keydate / Milestone 0 31-Mar-11 31-Mar-11 06-May-11 06-May-11 -31


6 Phase 1 Forecast Completion Date (Piling)-Contractual Completion Date is 17 Feb 2011 0 31-Mar-11 06-May-11 -31
Utilities And Road Diversion 31 17-Mar-11 16-Apr-11 24-Mar-11 28-Apr-11 -10

Diversion Of Existing Service Road 31 17-Mar-11 16-Apr-11 24-Mar-11 28-Apr-11 -10


Road Diversion @ Hougang St 11 31 17-Mar-11 16-Apr-11 24-Mar-11 28-Apr-11 -10
333 Part 7 - Road filter lane & island construction 19 17-Mar-11 02-Apr-11 24-Mar-11 14-Apr-11 -10
335 Landscape works 12 04-Apr-11 16-Apr-11 15-Apr-11 28-Apr-11 -10
Construction Stage 267 29-Sep-10 29-Jul-11 29-Sep-10 08-Aug-11 -8

Piling / CBP And Soil Levelling 186 29-Sep-10 31-Mar-11 29-Sep-10 06-May-11 -31
Piling Test 112 18-Nov-10 31-Mar-11 24-Dec-10 06-May-11 -31
Working Load Test 112 18-Nov-10 31-Mar-11 24-Dec-10 06-May-11 -31
1135 Working Load Test At Blk 10c & 10d 112 18-Nov-10 31-Mar-11 24-Dec-10 06-May-11 -31
1136 Working Load Test At Blk 12b & 12c 43 10-Feb-11 31-Mar-11 12-Mar-11 30-Apr-11 -26
1138 Working Load Test At Blk 14 & 14a 33 22-Feb-11 31-Mar-11 24-Mar-11 30-Apr-11 -26
1140 Working Load Test At B1a Basement 24 18-Mar-11 31-Mar-11 04-Apr-11 30-Apr-11 -26
CBP Wall Installation 43 20-Jan-11 14-Mar-11 20-Jan-11 18-Apr-11 -30
1143 Capping Beam Construction (BLK 8) 43 20-Jan-11 14-Mar-11 20-Jan-11 18-Apr-11 -30
Working Piles Installation 155 29-Sep-10 31-Mar-11 29-Sep-10 29-Apr-11 -25
1153 Piling Works - Blks 10c And 10d 155 29-Sep-10 31-Mar-11 29-Sep-10 29-Apr-11 -25
1158 Basement 1a Piling Works 112 09-Nov-10 22-Mar-11 09-Nov-10 22-Apr-11 -27
1154 Piling Works - Blks 12b And 12c 88 07-Dec-10 22-Mar-11 07-Dec-10 22-Apr-11 -27
1156 Piling Works - Blks 14 And 14a 51 19-Jan-11 22-Mar-11 19-Jan-11 22-Apr-11 -27
Tower Blocks 163 28-Jan-11 29-Jul-11 28-Jan-11 08-Aug-11 -8
Temporary Lifting & Transpotati on Facil ities 12 12-May-11 26-May-11 21-May-11 04-Jun-11 -8
Tower Crane 12 12-May-11 26-May-11 21-May-11 04-Jun-11 -8
Blks 10c And 10d (Tc5) 0 26-May-11 26-May-11 04-Jun-11 04-Jun-11 -8
1172 Starting Of Tower Crane Inst al lation 0 26-May-11 04-Jun-11 -8
Blks 14 And 14a (Tc4) 0 12-May-11 12-May-11 21-May-11 21-May-11 -8
1184 Starting Of Tower Crane Inst al lation 0 12-May-11 21-May-11 -8
Structural Works 163 28-Jan-11 29-Jul-11 28-Jan-11 08-Aug-11 -8
Substructure Construction 163 28-Jan-11 29-Jul-11 28-Jan-11 08-Aug-11 -8
Blks 10, 10a And 10b 89 28-Jan-11 04-May-11 28-Jan-11 14-May-11 -9
Blks 10 89 28-Jan-11 04-May-11 28-Jan-11 14-May-11 -9
1241 B1A & B2 Pile Cap Construction 36 28-Jan-11 14-Mar-11 28-Jan-11 02-Apr-11 -17
1242 Stump Column Construction to B1 Slab Level 9 11-Mar-11 21-Mar-11 29-Mar-11 07-Apr-11 -15
1243 Backfilling 2 22-Mar-11 23-Mar-11 08-Apr-11 09-Apr-11 -15
1244 B1 Lift Pit Construction ( BLK 10) 9 24-Mar-11 02-Apr-11 11-Apr-11 20-Apr-11 -15
1245 B1 Pilecap / Slab Construciton (BLK 10) 15 28-Mar-11 16-Apr-11 11-Apr-11 27-Apr-11 -9
1246 B1 Column / Wall Construction (BLK 10) 12 11-Apr-11 23-Apr-11 21-Apr-11 04-May-11 -9
1247 1st Storey Slab ( E-Deck) Construction (BLK10) 12 21-Apr-11 04-May-11 02-May-11 14-May-11 -9
Blks 10c And 10d 87 21-Apr-11 29-Jul-11 30-Apr-11 08-Aug-11 -8
1278 Excavation 24 21-Apr-11 18-May-11 30-Apr-11 27-May-11 -8
1279 Pile Hacking To Cut- Off Level 22 27-Apr-11 21-May-11 06-May-11 31-May-11 -8
1281 B1A Lift Pit Construction 21 02-May-11 25-May-11 11-May-11 03-Jun-11 -8
1280 M&E Under Ground Service Installation 66 09-May-11 22-Jul-11 18-May-11 01-Aug-11 -8
1282 Backfilling 15 12-May-11 28-May-11 21-May-11 07-Jun-11 -8
1283 B1A Pilecap / Basement Slab Construction 30 16-May-11 17-Jun-11 25-May-11 27-Jun-11 -8
1284 B1A Column / Wall Construction 24 02-Jun-11 28-Jun-11 11-Jun-11 07-Jul-11 -8
1286 Backfilling 6 25-Jun-11 01-Jul-11 05-Jul-11 11-Jul-11 -8
1287 1st Storey Slab ( E-Deck) Construction (Section Above B1A) 18 29-Jun-11 19-Jul-11 08-Jul-11 28-Jul-11 -8
1288 Ground Level Pilecap / 1st Storey Slab (E-Deck) Construction 24 02-Jul-11 29-Jul-11 12-Jul-11 08-Aug-11 -8
Blks 14 And 14a 87 07-Apr-11 15-Jul-11 18-Apr-11 26-Jul-11 -9
1333 Excavation 24 07-Apr-11 04-May-11 18-Apr-11 14-May-11 -9
1334 Pile Hacking To Cut- Off Level 22 13-Apr-11 07-May-11 23-Apr-11 18-May-11 -9
1336 B1A Lift Pit Construction 18 18-Apr-11 11-May-11 28-Apr-11 18-May-11 -6
1335 M&E Under Ground Service Installation 66 25-Apr-11 08-Jul-11 05-May-11 19-Jul-11 -9
1337 Backfilling 12 28-Apr-11 14-May-11 07-May-11 20-May-11 -5
1338 B1A Pilecap / Basement Slab Construction 30 02-May-11 04-Jun-11 11-May-11 13-Jun-11 -8
1339 B1A Column / Wall Construction 24 19-May-11 14-Jun-11 28-May-11 23-Jun-11 -8
1341 Backfilling 6 12-Jun-11 17-Jun-11 21-Jun-11 27-Jun-11 -8
1342 1st Storey Slab ( E-Deck) Construction (Section Above B1A) 18 15-Jun-11 05-Jul-11 24-Jun-11 14-Jul-11 -8
1343 Ground Level Pilecap / 1st Storey Slab (E-Deck) Construction 24 18-Jun-11 15-Jul-11 29-Jun-11 26-Jul-11 -9