EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Broom or Bell Finish- After the concrete has been placed, consolidated,
stricken-off, leveled, high/low spots eliminated and floated off with a bull
SAES-Q-001
A5 float, its surface can be given a coarse transverse scored texture by
Sec. 9.0
drawing a broom or burlap belt across the surface.
(ACI 301M-99, Sec. 5.3.4.2(d))
When not shown on IFC Drawings or Required by Project Specifications,
a Scratched Finish shall be applied on surfaces to receive bonded SAES-Q-001
A6
cementitious mixtures. Sec. 9.0
(ACI 301M-99 Sec. 5.3.4.2(j))
When not shown on IFC Drawings or Required by Project Specifications,
a Floated Finish shall be applied on surfaces to receive waterproofing, SAES-Q-001
A7
roofing, insulation, or sand-bed terrazzo. Sec. 9.0
(ACI 301M-99, Sec. 5.3.4.2(j))
When not shown on IFC Drawings or Required by Project Specifications
SAES-Q-001
A8 a Floated Finish shall be applied on walks, drives, steps, and ramps.
Sec. 9.0
(ACI 301M-99, Sec. 5.3.4.2(j))
When not shown on IFC Drawings or Required by Project Specifications,
a Trowel Finish shall be applied on walking surfaces in manufacturing, SAES-Q-001
A9
storage, warehousing or surfaces to receive a floor covering. (ACI 301M- Sec. 9.0
99, Sec. 5.3.4.2(j))
Initial floating shall be completed after concrete placement. (ACI 302.1R- SAES-Q-001
A10
01, Sec. 8.3.3) Sec. 9.0
The second floating operation shall take place after initial set but before
SAES-Q-001
A11 final set has occurred (usually performed using a power trowel with float
Sec. 9.0
shoes or a pan attached). (ACI 302.1R, Sec. 8.3.3)
Page 1 of 2
SAUDI ARAMCO ID/PID - 18-May-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Cast-In-Place Concrete Finishing and Curing Inspection SAIC-Q-1015 18-May-05 Civil
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
The use of any floating or troweling machine that has a water attachment
for wetting the concrete surface during finishing shall be prohibited
SAES-Q-001
A12 (Application of water during finishing can damage the top few millimeters
Sec. 9.0
of concrete, causing delamination).
(ACI 302.1R, Sec. 8.3.3)
B Curing Inspection
Maximum total dissolved solids in water used for moist curing shall not SAES-Q-001
B1
exceed 1000 parts per million. Sec. 10.2
Continuous water cure can be provided by covering with wet burlap and
plastic; The saturated burlap shall be covered with a plasticized sheet SAES-Q-001
B3
vapor barrier, minimum 0.15 mm (6 mils) in thickness (Polyethylene Sec. 10.4
Sheeting).
During the moist curing period, saturated cover materials should not be SAES-Q-001
B5
allowed to dry and absorb water from the concrete. (ACI 308, Sec. 2.5) Sec. 3.2
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 29 October 2003
Page 2 of 2