Professional Documents
Culture Documents
This guide form specification covers the basic design and functional requirements for medium voltage
padmounted fixed capacitor bank switchgear. It is provided as a guide to assist in the specification of
medium voltage capacitor bank switchgear and is intended as a supplement to single line diagrams and
data sheets for non open rack switchgear design projects.
This specification contains the general requirements for padmounted capacitor bank switchgear as well as
associated control and accessory equipment. The general specification along with the detail specification
establishes the minimum requirements for this project. If there is a discrepancy between the single line diagram/s
and the detailed specifications, the detailed specifications shall take precedence.
All components are enclosed in an all-welded compartmentalized steel enclosure. The bank shall come fully
assembled and ready for interconnection. All exceptions to this specification shall be clearly stated with your bid.
If no exceptions are taken, the bid should include the phrase "no exceptions have been taken".
PART 1 – GENERAL
1.1 SCOPE
A. The manufacturer shall furnish new [5kV] [15kV] [25kV] class padmounted switchgear complete with
components, accessories and services as described herein and as shown on the contract drawings.
B. The padmounted switchgear shall have a rating of [5kV] [15 kV] [25kV], [600A] [1200A] with [X]
kVAR at [X] elevation. The switchgear shall meet outdoor standards as defined in section 1.2 of this
specification.
1. If elevation is great than 3300 feet, please specify if the de-rating is taken into account.
1.3 QUALIFICATIONS
A. The manufacturer of this equipment shall have produced similar electrical equipment for a minimum
period of ten (10) years. When requested by the Engineer, an acceptable list of installations with similar
equipment shall be provided demonstrating compliance with this requirement.
B. For all equipment specified herein, the manufacturer shall have a quality system that is ISO 9001
certified.
1.4 SUBMITTALS
A. Submittal for Approval: [X] copies shall be submitted to the Owner/Engineer for approval.
1. Submittal for Approval, includes (but not limited to) the following:
a. Master drawing index.
b. Enclosure types and details.
c. Outline and general arrangement drawing showing elevations, dimensions, clearances,
shipping sections, and weights of each assembled section.
d. Floor plan drawing showing locations for anchor bolts and leveling channels.
e. Bus configuration with current rating, size, and number of conductors in each bus run,
including phase, neutral, and ground conductors of main and branch buses.
2.1 MANUFACTURERS
A. Switchgear Manufacturers: Subject to compliance with requirements, provide products by:
1. Shallbetter Inc.
2. ____________________
3. Engineering approved alternative.
The listing of specific manufacturers above does not imply acceptance of their products that do not
meet the specified ratings, features and functions. Manufacturers listed above are not relieved from
meeting these specifications in their entirety.
2.2 RATINGS
A. System Voltage: Furnish one (1) padmounted capacitor bank as follows:
1. [X] kVAR, [X] Volts, [X] kV BIL, 3 phase, [50] [60] Hertz, [Grounded WYE] [Un Grounded WYE]
[Double WYE] [Delta] Connected, [X] Amps available short circuit current [asymmetrical]
[symmetrical].
2. The equipment shall be factory assembled and tested prior to shipment and, in general, consist of the
following:
2.9 SHIPMENT
A. Ship F.O.B. [Destination] [Shipping Point].
3.1 EXAMINATION
A. The contractor shall examine elements and surfaces where switchgear will be installed for compliance
with installation tolerances, required clearances, and other conditions affecting performance. Proceed
with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. It is the intent of this specification that the installing contractor performs all receiving, unloading, storage
and installation of the equipment. The contractor shall receive, store, set, and assemble individually
shipped sections of switchgear to form complete units, and install and attach to the main switchgear units
any breakers, relays, meters, or other miscellaneous devices shipped separately. The contractor shall
make all internal wiring interconnections necessary for a complete assembly of the switchgear unit.
B. Bus joints at shipping splits shall be made by the contractor. All bus conductor joints and taps shall be
carefully made and insulated by qualified personnel in strict accordance with manufacturer’s instructions.
All bolted connections between sections of current-carrying bus shall be tightened down to torque values
recommended by the manufacturer prior to energizing.
C. If storage is required…Store equipment in a clean, dry place. Protect from weather, dirt, fumes, water,
construction debris, and physical damage. During temporary storage and after installation of the
switchgear, the contractor shall install and provide temporary 120-V power to space heaters furnished
with the switchgear. The contractor shall secure and connect permanent power to the heaters before
completion of the job.
D. The contractor shall install all equipment per the manufacturer’s instructions, contract drawings and
National Electrical Code.
E. The switchgear unit shall be set level and plumb on embedded steel floor channels with foundation bolts
furnished, installed, and grouted by this contractor as shown on the Contract Drawings. The contractor
shall furnish all shims necessary to comply with these requirements. Before switchgear units are anchored
in place, the location, elevation, and degree of plumbness shall be checked by the contractor’s surveyors
and shall be accurate to within 1/8 inch in all directions.
F. The switchgear shall be secured to the floor channels by welding or bolting at the front and rear. After the
switchgear has been installed and secured to the floor, the contractor shall touch up all spots where
original factory paint was scratched or burned off during welding.
G. Upon completion of all installation work by the contractor, as specified, the switchgear unit shall be
cleaned with a vacuum cleaner to remove all dust and debris from the inside of the switchgear enclosure.
The switchgear units shall remain tightly closed to keep out any additional dust or debris until turned over
for installation of conduit, installation and termination of power and control cable, testing and
energization. Cleaning equipment shall not be used in such a manner as to damage instruments, relays, or
other parts
H. The contractor shall be responsible for installing the medium voltage padmounted capacitor bank
switchgear. The equipment shall be installed and checked in accordance with the manufacturer’s
recommendations. The contractor shall be responsible for all final power and communications
terminations, conduit stub-up coordination, conduit and wire, bolting to pads, rigging, joining of shipping
splits including control wiring, and standby assistance during commissioning for the following owner
purchased equipment. NOTE: Actual commissioning (including final check of terminations, start-up and
testing of equipment) will be performed by the manufacturer’s start-up technician. This shall include but
not limited to:
1. Checking to ensure that the pad location is level to within 0.125 inches per three foot of distance
in any direction.
2. Checking to ensure that all bus bars are torqued to the manufacturer’s recommendations.
3. Checking the assembling of all shipping sections, removal of all shipping braces and checking the
shipping split mechanical and electrical connections.
3.4 WARRANTY
A. Switchgear warranty shall be as follows:
1. The manufacturer shall warrant the switchgear against all defective parts and workmanship for a
period of twelve (12) months from the date of start-up (not to exceed eighteen (18) months from
the date of shipment).
2. For these purposes, date of start-up is defined as the date when the manufacturer's authorized
service engineer starts the equipment and certifies that it is in proper working order per contract.
3. All warranty and liability claims shall be subject to manufacturer's standard terms and conditions.