In late’70s and early’80s Power generation and supply, particularly in West Bengal,
was passing through a severe critical situation. Very frequently there was a power
cuts & shortage of power supply. Industrial sectors were passing through an acute
production loss. Unrest ness among the workmen
started surfacing out. Pay cut is imposed.
Domestic and office fronts suffered badly due to
frequent & prolonged power cuts. There was a
chaotic condition in all works of life. Business
suffered. It is realized; frequent power cuts are the
prime reason for all these.

We anticipated proper & consistence Quality of Overhauling & Maintenance


work of Boilers in the Thermal Power plants are not carried out. Quality repair,
overhauling & maintenance were need of the hour.

With our knowledge, experience and expertise which we acquired while


executing overhauling, maintenance etc. work on behalf of M/s R.D.Steam
Engineering Co. (Pvt.) Ltd., we emerged out in 1982 as a direct executor to the
damage control in the Small, Medium & High generation capacity Power Plants.

We are glad to mention here that Boiler Directorate of West Bengal, vide its
office order no. L/1056 dated the 20th. March 1994, Registered our name for Repair,
Overhauling & Maintenance of Power Plant Boilers of any capacity.

We are covered under: -

 Employees Provident Fund Vide Account No.:- WB/34934


 E.S.I. Vide Code No. :- N-41/ 14271 – 102
 Service Tax Registration No. :- 918/MRS/SB02/KOL/05-06
 VAT Registration No. :- 19674806045

Contact Us

Proprietor : Mr. Ajit Kumar Das [9143336131]

Regd. Office : (Old) 215/2, (New) 259, Bipin Ganguly Road. Dum Dum. Kolkata.
West Bengal, India. Pin Code:- 700 030.
Office : (033) 2548 1698

Fax : (033) 2548 1698

BTPS : 9477240559 [ Mr. Amit Das]

DSP : 9474511671 [Mr. Soumen Kundu]

DPL : 9903491063 [Mr. Subash Manna]

IOCL : 9163216184 [Mr. Alok Brahma]


ENGINEERS AND TECHNICAL EXPERTS

 Mr. Arijit Das: MBA (Marketing & Finance) and B.Tech (Mechanical Engineer).

 Mr. Alok Biswas: Diploma (Mechanical Engineering).

 Mr. Soumen Kundu: Senior Supervisor.


10 years of experience in over-hauling & maintenance of large
and high-pressure boilers.

 Mr. Alok Brahma: Supervisor.


10 years of experience in over-hauling & maintenance of large
and high-pressure boilers.

 Mr. Amit Das: Supervisor.


4 years of experience in over-hauling & maintenance of large
and high-pressure boilers.

 Mr. Ajit Mahato: Supervisor.


10 years of experience in overhauling & maintenance of large
pressure Boilers.

 Mr. Subash Manna: Supervisor.


10 years’ experience in overhauling & maintenance of large
pressure Boiler.

In addition to above, we have highly qualified Engineers and Experts having vast knowledge
in the field of High Pressure & High capacity Thermal generation plants/ stations with
latest developments.

Quite a good number of highly experienced & certified Argon welders are in our possession.

Quite a good number of highly experienced & certified Carbon & Alloy Steel welders are
readily available with us.

Both the categories of welders are engaged throughout the year and carry out high pressure
welding jobs in tubes/vales/pipes in various power stations maintaining IB Regulations.
Semi-skilled and unskilled workmen are generally engaged from local areas.
TOOLS AND TACKLES

 Welding Generating Set : 15 Nos.


 Welding Transformer Set : 16 Nos.
 Winch – Electric – 3 Ton : 02 Nos.
 Winch – 2 ton – Complete with wire rope
Pulley block, snatch block etc. : 05 Nos.
 Winch – 3 – ton : 03 Nos.
 Winch – 5 - ton : 03 Nos.
 Chain Pulley Block :
a) 5 ton capacity : 10 Nos.
b) 3 ton capacity : 16 Nos.
c) 2 ton capacity : 20 Nos.
 Pull lift :
a) 1 ton capacity : 16 Nos.
b) 3 ton capacity : 10 Nos.
 Max Puller :
a) 3 ton capacity : 06 Nos.
b) 1 ton capacity : 10 Nos.
 Oxygen Gas Set : 30 Nos.
 Argon Welding Set with flow meter : 20 Nos.
 Wire Rope – (3/8”, ½”, 5/8” & ¼”) – : 3000ft. of each
size.
 Wire Pulley Block : Different sizes.
 Rope Pulley Block : Different sizes.
 Manila Rope : Different sizes.
 Hydraulic Pipe Bending Machine up to 3” O.D. : 01 No.
 Pneumatic Expander : 06 Nos.
 Various sizes of expanders complete : 20 Nos.
 Electric Bench grinding machine : 01 No.
 Wire Rope Slings : Various sizes.
 Hydraulic Jack :
25 ton capacity : 02 Nos.
5o ton capacity : 04 Nos.
 Screw Jack :
30 ton capacity : 08 Nos.
50 ton capacity : 04 Nos.
 Angular Grinder (AG-7) : 04 Nos.
 Angle Grinder (Blacker & Decker) : 06 Nos.
 Portable Grinding Machine (GQ-4) : 15 Nos.
 Flexible Grinding Machine (FF2) : 04 Nos.
 Vertical Grinding Machine : 01 No.
 Pistol Grinding Machine : 15 Nos.
 Electric Hand Drill Machine : 04 Nos.
 Stand Drill (5/8” to 1”) : 01 No.
 Ratchet Drill Machine : 02 Nos.
 Acetylene Regulator : 60 Nos.
 Oxygen Regulator : 60 Nos.
 Gas cutting Set : 30 Nos.
 Expander Machine -
– ½” : 06 Nos.
-2 ½” : 06 Nos.
-4” : 06 Nos.
 Boiler header milling cutter : 05 Nos.
 Pneumatic Grinder : 19 Nos.
 Pneumatic Rivet Gun complete : 03 Nos.
 Pistol drill : 04 Nos.
 Pneumatic Hand Drill : 06 Nos.
 Forge : 04 Nos.
 Vice : 09 Nos.
 Die : Various sizes.
 Tap : Various sizes.
 Magnetic base Dial Gauge : 05 Nos.
 Micrometer –
0” – 1” : 02 Nos.
0” - 2” : 02 Nos.
5” – 12” : 02 Nos.
 Vermeer Caliper -
8” : 02 Nos.
 Precision Level -
6” : 01 No.
8” : 01 No.
4” : 01 No.
 Spanner Ring, E.D., S.E. - Various sizes : 20 sets each.
 Dog Clip : Various sizes.
 Shackles : Various sizes.
 Reamer : Various sizes.
 Die nuts : Various sizes.
 Adjustable Reamer : 02 Nos.
 Pneumatic Operated Expander with Balance : 01 Set.
Performance: April, 2001 - March, 2011
TOTAL NO. OF WORK ORDER
15

13

12

9 9

5 5

April 2001 to April 2002 to April 2003 to April 2004 to April 2005 to April 2006 to April 2007 to April 2008 to April 2009 to April 2010 to
March 2002 March 2003 March 2004 March 2005 March 2006 March 2007 March 2008 March 2009 March 2010 March 2011
TOTAL WORK ORDER AMOUNT
Rs.1,29,48,562.00

Rs.1,03,85,798.75

Rs.69,45,798.00 Rs.71,20,648.00

Rs.61,23,356.40

Rs.52,19,350.00
Rs.48,77,495.00 Rs.48,19,267.00

Rs.19,01,541.00
Rs.15,30,250.00

April 2001 to April 2002 to April 2003 to April 2004 to April 2005 to April 2006 to April 2007 to April 2008 to April 2009 to April 2010 to
March 2002 March 2003 March 2004 March 2005 March 2006 March 2007 March 2008 March 2009 March 2010 March 2011
AVERAGE AMOUNT

Rs.11,53,977.64

Rs.9,75,499.00 Rs.9,63,853.40

Rs.8,63,237.47
Rs.7,91,183.11
Rs.7,45,621.43

Rs.5,34,292.15
Rs.5,10,279.70

Rs.3,82,562.50

Rs.2,37,692.63

April 2001 to April 2002 to April 2003 to April 2004 to April 2005 to April 2006 to April 2007 to April 2008 to April 2009 to April 2010 to
March 2002 March 2003 March 2004 March 2005 March 2006 March 2007 March 2008 March 2009 March 2010 March 2011
MAXIMUM AMOUNT OF A WORK ORDER
Rs.41,76,746.00
Rs.40,26,163.00

Rs.32,11,115.00

Rs.27,17,057.75

Rs.24,59,556.00

Rs.20,15,693.00
Rs.18,23,500.00

Rs.13,79,150.00

Rs.6,75,000.00
Rs.6,00,000.00

April 2001 to April 2002 to April 2003 to April 2004 to April 2005 to April 2006 to April 2007 to April 2008 to April 2009 to April 2010 to
March 2002 March 2003 March 2004 March 2005 March 2006 March 2007 March 2008 March 2009 March 2010 March 2011
MINIMUM AMOUNT OF A WORK ORDER

Rs.3,37,000.00

Rs.3,14,280.00

Rs.2,48,320.00

Rs.2,10,000.00

Rs.1,05,000.00 Rs.1,09,500.00 Rs.1,10,185.00

Rs.72,993.00

Rs.33,015.00
Rs.15,015.00

April 2001 to April 2002 to April 2003 to April 2004 to April 2005 to April 2006 to April 2007 to April 2008 to April 2009 to April 2010 to
March 2002 March 2003 March 2004 March 2005 March 2006 March 2007 March 2008 March 2009 March 2010 March 2011
WORK
60

54

50

40

30

24

20

10
6

1
0
Overhauling Repairing/ Replacement Fabrication/ Erection / Commissioning Pipe Line
WORK ON BOILER CAPACITY
16

14
14

12

10
9

2
1

0
110 MW 210 MW 250 MW
OVERALL PERFORMANCE
14000000

12000000

10000000

8000000

6000000

4000000

2000000

0
April 2001 to April 2002 to April 2003 to April 2004 to April 2005 to April 2006 to April 2007 to April 2008 to April 2009 to April 2010 to
March 2002 March 2003 March 2004 March 2005 March 2006 March 2007 March 2008 March 2009 March 2010 March 2011

Total No Of Job Order Total Amount Average Amount Maximun Amount Minimum Amount
CLIENTS OF A.D.ENTERPRISE
BTPS STPS
NO of Job First Job Last Job NO of Job First Job ast Job
39 Jan, 2000 May,2010 15 Jan,2002 July, 2008

DPL/ DPPS IOCL


NO of Job First Job Last Job NO of Job First Job Last Job
10 Feb,2005 Oct, 2010 6 July, 2008 Oct , 2010

Kesoram Rayon Scale Away (@ BTPS)


NO of Job First Job Last Job NO of Job First Job Last Job
5 July, 2005 July, 2010 2 Sept,2003 Oct,2005

DSP Shyam Sel Ltd


NO of Job First Job Last Job NO of Job First Job Last Job
2 July, 2008 July, 2008 1 May,2008 may, 2008

Jai Balaji India Ltd.(JBIL) Chinakuri


NO of Job First Job Last Job NO of Job First Job Last Job
1 Aug,2009 Aug,2009 1 April,2008 April,2008

Alstom (@ BTPS) Mc Nally (@ BTPS)


NO of Job First Job Last Job NO of Job First Job Last Job
1 Jan,2004 Jan, 2004 1 Nov,2002 Nov,2002

Wright & Co (@ BTPS)


NO of Job First Job Last Job
1 June,2004 June, 2004