You are on page 1of 6

OXFAM TBN20 – Introduction to Contracting Out Works (version 7), 21/04/09

Introduction to contracting out PH engineering


works and contract management

This Technical Brief provides an introduction to contracting out PHE works and the subsequent management
of such contracts for engineers, logisticians and project managers.

Introduction implementation-management phase, but in spite of this,


issues relating to managing large works contracts need to
The objective of the guide is to provide advice on be fully considered in the planning & design phase. In
successful implementation of any large construction other words, Oxfam must carefully consider if, they have
contracts related to public health engineering works. The the capacity to embark on a complex construction project
following key steps must be adhered to, to ensure a on the one hand, and if local conditions allow the
successful outcome to the contract management process: successful achievement of the project activities on the
• Planning the full contract document other hand.
Typically Oxfam’s capacity will be affected by staff
• Procurement - Selection of contractors through availability for the entire duration of the project and
tender process those staff having the required capacities to manage the
• Implementation - Advice and supervision during the construction contract both technically and
implementation phase administratively.
Typical local conditions undermining the activities are the
• Completion – Supervising the handover process
absence of experienced construction companies, the
It is essential that the person managing the contract complexity of works, the lack of equipment, the required
process, not only follows the key process steps, but also materials being unavailable and logistics constraints.
liaises closely with the project technical team, the When the conditions are particularly favourable, Oxfam
logistics team, the Oxford logistics team and the Oxford should consider the participation of beneficiaries for
PHE Advisory team. labour intensive activities and may manage the works
through in-house resources; when conditions are
Good Practice - Management Considerations adverse, Oxfam will probably hire external consultants,
award international contracts, or even choose alternative
6.1
It is very important that the same person follows up solutions to building.
the contract implementation from start to finish. It is
always advisable to use a worksite register where all
6.2
important decision and remarks are kept throughout Keys steps in successful
the contract implementation. contract management
Let’s consider the key steps of a construction activity:

The objective of successful Step 1 – Planning


contract management 1. Prior planning, well-defined procedures, and
protocols may prevent poor project performance.
The objective of successful contract management is to
ensure the successful implementation of large Not only does the project process itself need
construction contract for public health engineering works. planning, but also the individual activities forming
part of the process also need planning. Procedures
The contract should be designed so as to contribute to
good management practice and by so doing reduce the and protocols refer to systems in place for dealing
incidence of disputes and improve the overall with recurring issues (like the requisitioning of
administration and management of the contract process. materials). It is not enough to have such systems in
Clear objectives are important in large-scale projects. place, but everyone needs to know that they are
Without clear objectives responses to changed there and how to use them.
circumstances may lead to the project going off in 2. Seasonal factors need to be considered in all
undesirable directions. projects, as there might only be certain activities
Given the project cycle consists of identification, planning that can be undertaken at particular times of the
& design, implementation & management, and year.
evaluation, contract management is part of the

OXFAM Technical Brief – introduction to contracting out works 1


OXFAM TBN20 – Introduction to Contracting Out Works (version 7), 21/04/09

3. Verify the proposed technical design has been Good Practice – Quality Testing
elaborated by the project technical team in e.g. for the construction of a tank: concrete
collaboration with local partners such as public works resistance test (at 7, 14 and 28 days) means taking
departments, water departments and other relevant special sample of concrete each time a batch of
government actors. concrete is prepared.
4. Check the “contract model” required by the e.g. a pipe pressure test, between 2 valves, may be
Donor, or in vigour in the country where the works undertaken each time a section of pipeline is
will be implemented. Verify the proposed contract is completed.
appropriate; Oxfam has pre-established agreements e.g. water quality testing may be undertaken when a
with key donors such as ECHO, and Oxfam’s own borehole is drilled.
procedures will normally satisfy such donor
requirements. The Logistics Team in Oxford can 11. A decision will need to be taken on the working
advise and answer any doubts about other “non- currency, (local currency, USD, Euro or GBP), to be
traditional” donors, and whether a particular contract used in the contract documents. This decision will be
format meets a specific donor requirement – taken in accordance to local practice.
logadvise@oxfam.org.uk If you have doubts, ask. 12. Types of financial and performance guarantees
The standard Oxfam Terms & Conditions for should be specified as a function of the prevailing
contracts is available via the Oxfam Intranet site. norms in the country where the PH works are to be
implemented.
LINK: new page Intranet (Standard Contracts, etc)
13. The contract shall be drafted with the aim of
5. The estimate of quantity of different works identifying roles and responsibilities of all parties in
should be calculated as precisely as possible as this each circumstance (ex.: what happens when the
will minimise amendments to the contract and Contractor does not perform? When should Oxfam
variation orders. The same applies to rate pay? What responsibility has Oxfam towards the land
analysis. This work should be undertaken in close Owner? Who can legally represent the parties? Who
collaboration with the project technical team. endorses the technical compliance of works?).
6. Get a Confidential Cost Estimate to ensure the 14. The eventual owner, public works departments,
price quoted is within a sensible range. water departments and other relevant government
7. While estimating the project completion time, a actors, should be closely consulted and involved in
project implementation schedule should be preparing the contract documents.
prepared and all factors that could delay the project.
A risk register approach may be considered? This Step 2 – Procurement - Selection of a
work should be undertaken in close collaboration Contractor through a tender process:
with the project technical team, as they will be
1. Treating all Tenderers equally is a key
responsible for the day-to-day supervision of works.
component of the tendering process. For example, it
LINK: new page Intranet (Standard Contracts, etc) is of paramount importance distributing the same
pieces of information to all Tenderers at the same
8. A decision should be taken on whether to use only
time. Communications in writing must be preferred
national contractors, or a mix of national and local
over verbal informal approaches.
contractors, given Oxfam’s community based
2. The work should be tendered out with Contract
approach to PH work. Such consultations should be
Manager advising on the tender process to be
undertaken in collaboration with all the main actors.
followed. Donors, such as the EU, may have their
9. The contract document, which mainly contains
own tender guidelines, if so, copies of the guidelines
conditions of contract, bank guarantee, bills of
must be obtained.
quantity (BOQ), specifications and drawings
3. The first contact with construction companies is
should be prepared, in close collaboration with the
through an invitation (restricted tender) or a public
project technical team, considering local prevailing
advertisement (open tender) for Tenderers to take
norms and other legal requirements. Clauses will
part respectively in a pre-qualification exercise or
include financial, administrative and technical
an open tender process.
issues. Wherever possible, quality testing, either
4. The tender dossier shall explain the project in detail.
under the responsibility of the Contractor or Oxfam,
If necessary, pre-bid meetings can be organised,
should be scheduled or considered in the overall
ensuring that all interested Tenderers receive exactly
costing.
the same information.
10. While preparing the conditions of contract, the local
5. The bid should contemplate mechanisms for the
prevailing rules and regulations (including tax related
purchase of major construction materials if any (e.g.
issues) should be considered; both logistics and
large water pipes, generators, submersible pumps,
finance should be consulted before finalising it. It
etc.), especially if international procurement is
may be necessary to consult a lawyer (locally or
required. The offer shall clearly state whether the
internationally) to ensure the documentation is
Government, or Oxfam, or Third Parties need to
legally sound.

OXFAM Technical Brief – introduction to contracting out works 2


OXFAM TBN20 – Introduction to Contracting Out Works (version 7), 21/04/09

cooperate in the procurement process (e. g. for eventual owner should be fully involved in the
import taxes). procurement process, as this may avoid import
6. A panel shall conduct the selection process using a taxes.
range of pre-established criteria.
Step 3a - Implementation, during
Good Practice - The Offer (the Bid) construction phase
Typically, an offer from a Contractor must include 1. In the field, if there is a variation from original plans,
details of the following: a variation order should be prepared explaining the
- Declaration of acceptance of tender conditions reasons for this. This then needs to be approved by
- Power of attorney the Contract Manager in collaboration with the
- Site visit certificate project Technical Team and other key actors. Field
- General information about the company support visits to verify the facts on the ground may
- Organisation chart be necessary.
- Technical qualification certificates 2. All conditions of the contract must be fully agreed,
- Similar construction experience analysed and carefully complied with by both the
Employer and the Contractor.
- Personnel to be employed on the contract
- CV of key personnel
Tips for maintaining a good working
- Work plan
relationship with the Contractor.
- Consortium’s ways of working & roles (if applicable)
- Priced bill of quantities and financial bid - One clear line of communication (don’t give order to
- Bank details workers, go through the line defined at beginning of
works)
- List of equipment to be made available on the
contract - No surprise or changing decision at last minute
(prior notice with time to adapt)
7. The Contractor shall be carefully selected on the
- Always remember that the contractor has to make
money and don’t like to feel he’s loosing
basis of the sealed bid it has submitted or any other
- It can be “give and take on” what’s important to
accountable fact. Relevant considerations that do not
Oxfam and the contractor.
arise from the bid can be acknowledged by the Panel
- Consider the impact of decisions & changes on cost,
in the Tender Evaluation Report (e. g.: past
time & quality of the works, as well as the interest
experience with Oxfam, or with other organizations,
of each party (humanitarian project needs,
not mentioned by the Tenderer). Considerations not reputation, etc.)
mentioned in the tender Evaluation Report cannot
influence the selection. The selection must be based 3. Close coordination among the Contractor, Oxfam GB
on objective, substantiated facts. and the eventual Owner is very important and all
8. The eventual owner, public works departments, attempts should be made to ensure that a good
water departments, other government actors, and/or working relation exists among all these. The Contract
other key stakeholders should be involved in the Manager may also need to liaise with key Donors on
selection process. the contract management process. However it is
important to clearly define the communication
Good Practice – Selection criteria channels between actors that are non-signatory to
the contract. In principle external information, or
- Previous similar experience request, or complaint should go through the Contract
- Type and number of equipment (compressors, Manager before reaching the Contractor.
vehicles, etc. need to be verified) and human 4. The person managing the works is strongly
resources. Those at full disposal of the project recommended use of a worksite register, with
should be distinguished from those to be shared
numbered and maybe multi-layered pages. The
with other activities of the Contractor
register should be kept by, where remarks,
- References (name and contacts should be given).
warnings, decisions taken and other information may
- Up to date to any taxes and social obligation within
be recorded while conducting joint monitoring visits
local laws and Oxfam code of conduct
(Manager + Technician + Contractor). Even
- Duration and beginning date of works contestations may be registered. Those permitted to
write notes in the register should be clearly
9. When the selection process has been completed,
identified, in writing, in the register.
agreements will be made with the Contractor
5. It the event that the Contractor fails to comply with
regarding the best mechanisms for the purchase of
the conditions of contract, the Contract Manager
major construction materials (e.g. large water pipes,
must advise on the necessary steps to be taken to
generators, submersible pumps, etc.) especially if
facilitate the contractor’s work. The Contract
international procurement is required and such
Manager may be required to offer support to the
materials are not available locally or nationally. The

OXFAM Technical Brief – introduction to contracting out works 3


OXFAM TBN20 – Introduction to Contracting Out Works (version 7), 21/04/09

project technical team or to plan field support visits 3. When the works are completed, some contractual
in this eventuality. obligations still remain pending for a certain period
6. The Contract Manager must coordinate technical, of time (e.g.: retentions, warranties, final statement
financial and legal aspects of the activities. He shall of account, etc.). The Contract Manager shall ensure
be in continuous contact with the Technical Experts that those are correctly processed.
in order to ensure that the implementation of the 4. The eventual Owner of the works can be given the
works adheres to the technical aspects agreed in the responsibility to deal with the Contractor on issues
contract. such as retention money and any repair and
maintenance works necessary during the warranty
Step 3b - Reacting to problems of poor period. The Contract Manager should advise the
performance Owner on ways of implementing this strategy.
5. The Contract Manager should advise on the
In the eventuality of poor works progress, due to bad
handover process and issuing the final completion
performance by the Contractor, or due to force majeure,
certificate.
a number of measures should have been foreseen in the
contract, such as: 6. The handover is tripartite: the Contractor handovers
the facilities to Oxfam; Oxfam handovers the
• Suspending the works,
facilities to the Owner. It is very important to ensure
• Offsetting Contractors claims against those of Oxfam the responsibilities of Oxfam and the Owner with
GB,
reference to the settlement of last payments,
• Holding payments, guarantees and retentions. Maximum efforts must be
• Rejecting the final technical report and demanding a paid to meet Owner’s satisfaction on the works
new report, quality (through all contract stages and this starts
• Enforcing financial penalties, before the contract / definition of works’ quality) and
• Enforcing recovery of amounts due, achievement of the expected project goals.
• Awarding the execution of the undone works to third 7. It is highly advisable to ask the Owner to state its
parties at Contractor’s cost, full satisfaction of the works done in the handover
• Seizing the financial guarantees, documents.
• Terminating the contract.
The roles and responsibilities of
Step 4 - Completion Oxfam Staff
Typically, the following Oxfam staff will be involved in
1. Payments are usually scheduled at the completion of
one way or another in the contracting out process and
an agreed percentage of works done, or at major
any of them could be the Contract Manager:
milestones of the construction. Certificates of
completion shall be signed before these payments
Country Programme Manager
are done. That applies to both partial achievements
Main role Main responsibility
(i.e.: certificate of provisional acceptance) and
Legally responsible for Legally and financially
end of works (i. e.: certificate of final OGB in the country. responsible, as well as
completion). responsible for overseeing all
OGB staff.
Good Practice – Scheduling Payments
It is useful to have sufficient money remaining to be Project Manager
paid at the end of all works that are dependant on final Main role Main responsibility
quality testing. This remaining % should be enough to Overseeing the project Budgetary responsibility
fund, partially or totally, any corrective works that have staff and project
to be done on what the Contractor has achieved. Not management
only considering the end of works, but each time
payments are scheduled; when possible some quality Public Health Engineer
testing and report should be attached, in particular Main role Main responsibility
with pipe networks. Technical supervision Technical designs and
specifications.
Technical reports of works
2. Before issuing a final completion certificate, the
achievements
Contract Manager shall check all works together with
the project Technical Team, the Contractor and the
Logistics Manger/Officer
eventual Owner. Only after the inspection process Main role Main responsibility
should the final completion certificate be issued. Technical supervision Tender management
Any testing scheduled in the contract should be
conducted in presence of the above-mentioned Finance Manager/Officer
parties. They shall sign the test result report(s) and Main role Main responsibility
attach them to the completion certificate. Financial supervision Payments

OXFAM Technical Brief – introduction to contracting out works 4


OXFAM TBN20 – Introduction to Contracting Out Works (version 7), 21/04/09

Skills and competences required Legal action?


for a Contract Manager A contract is a legal document, and in the event of
disputes, such disputes will have to be settled according
• A suitable qualification in a discipline relating to
to the law.
managing legal, administrative, technical and
financial issues. Contracts usually specify which is the law applicable in
• Preferably, at least two years’ practical experience of case of disputes; most likely it is the one where the
managing large tenders in developing countries. obligation has to be met. That is quite clear where the
• Proven practical experience of managing large contract pertains works, but it can be more vague in the
contracts in developing countries. case of a supplies contract. In that case, the law
applicable is usually the one of the country of residence
• Good knowledge of Donor’s procurement rules.
of the part who has to provide the service.
• Awareness of community based approaches.
• The ability to present concise reports, sometimes at Whether to sue at law or not is a decision to be taken at
short notice, reflecting the problems and possible the highest Oxfam levels. In fact, a legal action may take
solutions for particular situations. a period far longer than the presence of the Oxfam staff
in the country and can require significant efforts. At the
• Diplomacy, tact and administrative skills in order to
same time, Oxfam GB devotes its resources to the
work with people at managerial and, on occasions,
Beneficiaries and cannot renounce its claims.
senior government levels. The person should also be
at ease in working with local people. Whatever decision is taken in this regard, it is the duty of
• Well developed interpersonal and team skills and the Contract Manager to ensure that all facts, in every
proven ability to be flexible in demanding situations. moment, have been properly documented and the
• Sympathy with the aims and objectives of Oxfam and documentation itself has been filed.
to Oxfam’s equal opportunity and gender policies.
Health and Safety Issues
Types of contracts • Health and safety issues must be dealt with
and provisions made for every activity such as
A reminder of the different types of contracts: solid waste management, hand-dug wells, spring
development, drilling, vector control, etc. Staff must
SUPPLIES CONTRACT = covers the purchase, leasing, be properly trained and have the correct protective
rental or hire purchase, with or without the option to buy clothing, and sites must be properly marked and
the products. cordoned off at all times to prevent accidents.
WORKS CONTRACT = covers the execution of buildings • Personal Protective Equipment is considered a
or other such civil engineering structures. Health and Safety matter.
SERVICES CONTRACT = covers technical assistance, • Each work site should have basic first aid kit and
studies and performances that do not include supply of someone who knows how to use it.
goods and execution of works.

More details on the different types of contract can be Further information


found in the Logistics Procurement Manual, or by
following the link: A PRACTICAL GUIDE TO THE ENGINEERING AND
CONSTRUCTION CONTRACTS, Seminar Notes, London
LINK: existing Logs Proc Manual page on intranet. Business School (2003).

Mandatory Requirements in Public Health Engineering


Programmes, Oxfam GB (2008).
Sizes of contract
For large works contracts, the Oxfam GB lawyer in Oxford Oxfam GB Logistics Procurement Manual (2008).
should be consulted as a matter of routine, to ensure hyperlink: to existing Logs Proc Manual page on
that Oxfam is as fully protected, as possible, from intranet.
litigious actions. A “large works contract” can mean any
works contract that is over GBP 100,000.
The Oxfam GB legal services can be contacted on any
contract related issue at the following e-mail:
Legal team – e-address

OXFAM Technical Brief – introduction to contracting out works 5


OXFAM TBN20 – Introduction to Contracting Out Works (version 7), 21/04/09

Terminology the contracting Authority when the


retention was intended to be released.
100% of final retention
Owner Who has a right of property (ex.: on the Retention Amount deducted, usually in form of a
construction land)
guarantee, from each interim payment
Contracting Entity awarding the contract
Authority - due to the Contractor. Payable to the
Employer Contracting Authority when the
Contractor Who agreed with the Contracting Contractor does not fulfil its obligations
Authority to undertake an activity in during the maintenance. Usually 10% of
return for a financial consideration each instalment
General Contractor in charge of the execution of Certificate of Certification on works executed and
Contractor provisional accepted by the Contracting Authority
the works as well as the supervision and acceptance –
overall coordination provisional
Sub Executes works and/or provides the completion
Contractor Contractor with services/supplies, as certificate
authorized by OGB Certificate of Certificate stating that the works are
Resident Represents the Owner's interests during final completed. At this stage the entire site
Engineer the construction phase completion is usually handed over to Contracting
Contract Manages the contract Authority
Manager Maintenance Period of time during which the
Project Calculates works executed and gives period Contractor must amend every defect of
Supervisor instructions to the Contractor the works. The period starts from the
Surveyor Prepares drawings defining existing site date of certificate of acceptance of the
conditions and site boundaries pertaining works
Quantity Contributes to drawing the confidential Worksite Document endorsed by the Project
surveyor cost estimate and calculating the works register Supervisor; lists all site activities and
executed instructions to Contractors in
Clerk of Inspects works, quality of materials etc. chronological order. It may also include
works during the construction. Often resident additional reports as a Register Of
on a site Accesses to the site
Tender notice Public invitation (an advertisement) by Variation – Changes in work authorised by the
the Contracting Authority to submit order change Contracting Authority Representative.
offers for undertaking a certain Such changes were not foreseen among
performance the tasks originally assigned to the
Tender Bank guarantee, banker’s draft or Contractor. The latter is usually bound
guarantee - certified cheque, or irrevocable letter of to execute them at the price fixed into
bid bond – bid credit issued by a bank or a insurance the original bill of quantities, unless they
security
company. Payable to the contracting exceed a certain limit (usually 15%).
Authority when the Tenderer withdraws When they exceed the limit, the Parties
its offer after the submission deadline. may agree new prices
Usually small % of confidential estimate. As built Drawing prepared after construction,
Released when the contract is signed drawing that describe the actual construction
and the performance guarantee issued Addendum Document modifying the terms and
Advance Bank guarantee, banker’s draft or conditions of a contract
guarantee – certified cheque, or irrevocable letter of Final Issued some time after the final
advance bond credit issued by a bank or a insurance statement of certificate of final completion, this
company. Payable to the contracting account document certifies the amounts due for
Authority when the Contractor does not the complete settlement of all financial
fulfil its obligations after having received aspects
an advance payment. 100% of advance Power of Declaration stating who can act on
payment. Released when job done is attorney behalf of a company
valued 100% of advance Specifications Technical and performance
Performance Bank guarantee, banker’s draft or specifications.
guarantee – certified cheque, or irrevocable letter of Confidential Assessment of cost presumably involved
performance credit issued by a bank or a insurance Cost Estimate
bond in the activity. Used as a reference for
company. Payable to the contracting evaluating the bids
Authority when the Contractor does not Site visit Statement of survey performed by the
fulfil its obligations after having received certificate Tenderer to the construction site
an advance payment. Usually 10% of Priced Bill of List of materials needed for the
contract. Released with the final Quantities construction with individual costs
statement of account
Retention Bank guarantee, banker’s draft or
guarantee – certified cheque, or irrevocable letter of
retention credit issued by a bank or a insurance
bond
company when the Contractor requests
payment of final retention. Payable to

OXFAM Technical Brief – introduction to contracting out works 6

You might also like