You are on page 1of 1

3G - RFI CHECKLIST

Site Name: - RFI date :(MM/DD/YY) :-

Site ID:- Lat/Long:-

Owner name: –
Sharing with:-
IP Name:-
Address (with PIN code) :

Site Contact Person Name/Number : -


Site Properties
AMSL:------------------------------------------------
Tower type (GBT/RTT/Pole) -----------------
Tower Height: ---------------------------------
Building height (in case of RTT/Pole): ------
Site type: Indoor/outdoor---------------------
Exiting 2G BTS type (ID cabinet/OD cabinet/stack/wall/pole: ----------------
Propose
d date
Ite Not of
m appli complet
No. Description Yes No cable ion Remarks
1 Type of EB connection ( 3 ph/1 Ph) and Rating
1a If EB power not available, tentative date of EB availability
2 poles installed, verticality checked
Space available for RRU on existing GSM Pole ( For BBU+ OD RRU
3
solution)
4 Vertical RF feeder cable ladder installed properly
Is horizontal tray from hatch plate to tower/pole mounts installed and
5
vertical supports grouted properly
6 Space available against Solution finalized.
7 Space Available For New Feeder Routing (HCT)
8 Free Holes available in hatch plate for feeder/Power/Optical cable
9 Hatch plate installed properly, sealed & hole available
10 Is the alarm box installed with 4 Krone blocks, Ext alarms connected
11 ID Ladder available for Feeder & Cable routing
12 PIU unit installed & commissioned, DG automation done
13 DC Power plant & Battery installed, commissioned, labeled Battery : 600AH
14 Site taken over by O&M operator O&M agency :
15 DC MCB Availability 32A & 16A for Node-B
16 Cables from PP to DCDB are as per the specified size.
17 Space Available for Installing Additional MCB Inside DCDB
18 Feeder Cable Grounding points availability in EGB (2nos with nuts& Bolts)
BTS & Surge arrestor grounding points availability in IGB (6nos with nuts&
19
Bolts) ensure all bus bar connected to earth pit
20 Space available on OD Platform / Cage For Mounting IP 55 rack
Space available on Tower Top Platform or Tower Top Leg for 3G BTS
21
Installation
Separate pole mounts installed as per RF Plan for 3G at required height
22
and azimuth.
Is Transmission rack installed for MW and MUX requirement and space Space available-As
23
available for VF Required.
Number of MCB
24 Separate TX MCB available for MUX and MW as per requirements shared. and rating- As
Required
25 Ear thing resistance…….. ohms Ohms………
Note:

Agency Name:- Site Representative Name:-


Engineer name:- Contact Number:--------
Contact Number:-- Signature:------------------
Signature :- RFI Accepted Date: -------

You might also like