Professional Documents
Culture Documents
INTRODUCTION where a uniform foundation rock foundation exists the pressure head
A detailed analysis of the control of seepage under concrete dams drops to a value close to the tailwater head at the line of drainage
has been presented in the First Rankine Lecture by Casagrande (1961) control wells and then remains constant.
from which these notes have been precised and all the figures are
taken. From a geotechnical point of view, once the competence of the ANALYSIS OF DRAINAGE
rock has been established the seepage below the foundations and Figure 2 shows the theoretical results for various locations of an
around the abutments is the most important factor requiring control. interface (rock to dam) horizontal drain upon the foundation uplift
The seepage loss is generally of secondary importance and in fact will pressures. The rock is assumed to be semi-infinite in extent, isotropic
generally be increased by the seepage controls. and the water flow to obey Darcy's law. The closer the drain is to the
heel the greater the reduction in uplift pressure, however the shape of
CONTROL OF SEEPAGE THROUGH ROCK the uplift pressures is considerable different to that normally assumed.
Control of seepage is achieved, in general, by both a grout curtain This is not surprising since a surface drain is hardly a good
under the dam 1.2 to 3 metres from its heel followed about 6 metres approximation to a line of deep penetrating wells.
further from the heel by a line of drainage wells. Single line grout
curtains are typically formed by grouting into 75 mm diameter
vertically drilled holes spaced at 1.5 metre centre to centre and 12 metre
deep with every third hole extended to 24 metres depth. Drainage wells
are similarly sized and spaced with a depth of 12 metres. A typical
example is shown in Figure 1 (Casagrande, 1961).
The designer should be aware that the surface layers of rock are
likely to be more permeable than the deeper layers and that the
hydrostatic pressures against the dam face are likely to open up rock
joints along the heel of dam. This may cause the full hydrostatic
pressure to act through the full depth of the pervious zone of the rock
(at the heel). If hydrostatic pressures exist below the heel throughout
the relatively pervious rock then the conditions shown in Figure 3 are
approximated. From this it is evident that the seepage control wells
should extend through the full depth of the pervious rock zone.
Figure 4. Theoretical uplift control from line drainage wells. Figure 7. Theoretical uplift for well water above tailwater.
Figure 5 gives theoretical solutions, developed with some simplifications ANALYSIS OF IMPERFECT CUT-OFFS
and the limitations of a/d < 3 and rw/a < 0.1, to the case of the drain water As mentioned earlier it is common to use a grout curtain in addition
level higher than the tailwater level. Two numerical solutions are given to the line of drain wells. Dachler (1936) presents a theory for an
in Figure 6. These solutions show that for practical spacing of the drain imperfect cut-off and Figure 8 gives solutions for this theory. The theory
wells (75 mm diameter holes on 1.5 or 3 metre spacing) and a well drain assumes that there are n equally spaced slits. Whether the imperfect slits
water level (elevation) equal to the tailwater level (elevation) the uplift are vertical or horizontal is of no theoretical significance. D is the total
pressures are only slightly increased (4.5% and 6.8% respectively). strata thickness, d is the (sum of) the thickness of the impermeable portion
of the strata giving W = D - d as the total thickness of the open space.
Then d/D = cut-off ratio, W/D = open space ratio, and Ec = the cut-off
efficiency and is defined as (q - qc)/q where q is the rate of flow without
a cut-off and qc is the rate of flow with a cut-off. Dachler's solution can
be simplified for W/D < 0.1 and the solution for B/D = 1 and two values
of n (n = 20 and 120) are shown in Figure 8. If n is large (n > 20) then
the efficiency, Ec decreases approximately inversely proportional with n
(the number of openings). (Note: This finding loses its validity when
dealing with thick walls).
Figure 7 gives the solution for the case of a well drain water elevation
controlled at a higher elevation than the tailwater elevation.
Other examples, shown in Figures 11, 12 13 and 14, and four case
examples from Terzaghi's private files are then describe to suggest that
grouting was not as effective as general thought. To quote Terzaghi
"many owners are penny-wise and pound-foolish by spending money on
grouting and then little or nothing on instrumentation to establish the
effectiveness of the grout curtain".
Figure 13. Data for Grande Coulee and Shasta Dams, Bureau of
Reclamation.
REFERENCES
Brahtz, J.H.A., (1936). "Pressures due to percolating water and their
influence upon stresses in hydraulic structures" Transactions 2nd
Congress Large Dams, Washington, 5:43-71
Casagrande, A., (1961). "Control of seepage through foundations
and abutments of dams", Geotechnique, 11:161-182.
Dachler, R., (1936). "Grundwasserstromung", Springer, Vienna,
p. 82. ("The flow of water in the ground").