You are on page 1of 3

Disaster Management in India Disaster Management Act 2005 stipulated

LESSONS LEARNT FROM preparation of a hierarchy of disaster


DISASTER MANAGEMENT OF In the backdrop of Orissa super cyclone, management plans at the National, State and
Gujarat earthquake and end of International District levels providing an opportunity to
RECENT DAM / EMBANKMENT Decade of Natural Disaster Reduction prepare holistic plans on disaster management
covering the entire disaster management cycle
BREAK EVENTS IN INDIA (IDNDR), Govt. of India recognized disaster
and integrating the macro level policy issues
management as a development issue.
with micro level issues of implementation
A number of important initiatives were taken converging resources available from various
up to mainstream disaster risk reduction into sources.
the process of development.
Through enactment, society indicates its
It was realized that “while hazards, both wishful thinking and provides legal frame work
natural or otherwise, are inevitable, the to achieve the objectives. Actual
disasters that follow need not be so and the achievement, however, depends on the
society can be prepared to cope with them detailing done or to be done in different
effectively whenever they occur” and called possible scenario. One such possible disaster
for a “multi-pronged strategy for total risk scenario pertains to dam/embankment break
management, comprising prevention, situations.
preparedness, response and recovery, on the
by one hand, and for initiating development Therefore, actual disaster management in
efforts aimed towards risk reduction and recent dam break situations have been
MUKESH KUMAR SINHA mitigation, on the other”. analysed to re-orient ourselves to deal with
B.Tech. (IIT/D), M.Tech.(Rock Mechanics), M.Sc.(Hydrology-Ireland) dam/embankment break scenario more
MEMBER (CIVIL), This paradigm shift led to enactment of effectively so that the people in the
Disaster Management Act, 2005 in India. downstream areas be assured of effective &
NARMADA CONTROL AUTHORITY,
timely action in emergency cases for
Government of India protection of their lives & properties.

PARECHU LANDSLIDE DAM BREACH


ANALYSIS OF RECENT DAM/ PARECHU LANDSLIDE DAM BREACH
EMBANKMENT BREAK EVENTS Risk Identification – Drastic reduction in
flow indicating formation of landslide dam.
A Landslide dam formed in June, 2004 on river
Four cases Risk Reduction/Mitigation - A multi-
Parechu at Ahli in Tibet (China) – 35 km from
Indo-China border disciplinary team comprising of officers from
- Parechu landslide dam (International), MHA, MoWR, MEA, CWC, GSI, NRSA,
The landslide dam burst on 25th June, 2005 CMRI was constituted. A dam break study
- Jaswant Sagar dam (State)
leading to a massive and sudden discharge of and stability analysis was also carried out for
water into Sutlej threatening the inhabited areas
- Pratapura dam (Municipal Corporation) Disaster Management Planning.
Risk Transfer – State Govt. sought the
- Narmada Main Canal (Ongoing Project) Central assistance. Sutlej Jal Vidyut Nigam
Ltd. – the owner of Nathpa Jhakri Project got
Six Stages of Disaster Management an insurance cover
Early Warning and Forecasting – A
- Risk Identification
system was established for round-the-clock
- Risk Reduction/Mitigation watch on the water level in the river. A
wireless network had been set up.
- Risk Transfer Emergency Response – People residing on
the banks of river upto the expected levels
- Early Warning and Forecasting
arrived at after dam break study + 3m was
- Emergency Response evacuated and brought in Relief Camps.
Recovery and Reconstruction – No life
- Recovery and Reconstruction was lost. Necessary reconstruction of
PARECHU LANDSLIDE DAM highways, bridges, etc. was carried out.
JASWANT SAGAR DAM JASWANT SAGAR DAM PRATAPPURA DAM
Risk Identification – Over 118 years old,  10m high earthen dam, 30 km east of Vadodara
 43.38m high earthen dam on Luni River in technology were not developed. Dam Safety
Pichyak village, around 70 kilometers away from Committee suggested remedial measures.  built in 1930 by Maharaja Sayajirao Gaekwad
Jodhpur district in Rajasthan former king of Vadaodara (Gujarat)
Risk Reduction/Mitigation - Due to lack of
funding on operation & maintenance head,  failed at around midnight of 30th June / 1st
 118 years old
repair / strengthening works could not be July, 2005 due to piping starting from 2 inch to 6
 breached on July 8, 2007 due to failure of the taken up ft. in diameter over a period of 10 hours.
150 feet long protection wall Risk Transfer – The Project Authority
had applied for financial assistance from  The primary reason was heavy rainfall to the
 causing a rise of four to ten feet in the water tune of 450mm in 24 hours, which caused sudden
State/Central Government rise in water level due to inadequate spillway
level of the river. 07 villages were affected
severely. The road and telecommunication for Early Warning and Forecasting –Leakage capacity.
these villages were totally cut off. spotted on 6th July, 2007. Ten army divers
were air dropped but force of water  Absence of surface or toe filter drain and dam
material being prone to piping caused upstream
prevented them from repairing the protection
slope to fail first, leading to total collapse of the
wall. Immediately local district authorities dam over a width of about 30m.
were informed.
Emergency Response – About 20000
people from the low-lying areas on the river
bank were evacuated.
Recovery and Reconstruction – Works
taken up for increasing spilling capacity and
strengthening dam section.

PRATAPPURA DAM NARMADA MAIN CANAL BREACH


NARMADA MAIN CANAL BREACH
Risk Identification – No risk was
Risk Identification – Over 75 years old,  A 21 metre breach on the right bank of anticipated.
technology were not developed. Dam Safety Narmada Main Canal in Mehsana District of Risk Reduction/Mitigation - Not relevant.
Panel suggested certain studies. Gujarat at 7:30 am on 11th June, 2008. Risk Transfer – Not relevant.
Risk Reduction/Mitigation - Since the  The adjoining villages evacuated by 10 am. Early Warning and Forecasting –The
studies were still in progress, no remedial Canal flow depth was more causing flowing of Project Authority had inspected the leakage
work was taken up. earth beneath concrete lining through crevices of the canal one day prior.
Risk Transfer – The Project Authority causing failure of earthen embankment. Emergency Response – Immediately after
had applied for financial assistance from
the news of breaching of canal, Ahmedabad
State/Central Government
fire brigade rushed with boats to the site for
Early Warning and Forecasting –When
rescue operations. Entire village was
piping was observed at about 2 pm on 30th
evacuated by 10 am. The head regulator of
June,2005, local villagers and site engineers
the canal was opened to reduce the water to
informed senior officers and local district
at least three feet. Excess water were diverted
authorities.
to the open fields
Emergency Response – District
Recovery and Reconstruction – Eight
authorities evacuated villagers and made
bulldozers were commissioned immediately to
arrangements for Relief Camps. The breach
to temporarily fill the breach. The breach was
section was immediately got repaired with
repaired and water supply resumed with
boulders to check further breaching.
effect in 10 days. A High Power Narmada
Recovery and Reconstruction – Works
Main Canal Re-examination Committee was
taken up for increasing spilling capacity and
also set up.
strengthening dam section.
ANALYSIS OF DISASTER MANAGEMENT CONCLUSIONS
RECOMMENDATIONS
 Parechu landslide dam breach Due to several initiatives taken by the
- International & monitored at Cabinet Central/State Government, the response
Secretariat Level mechanism, i.e., Emergency Response
- Not a single death in India where three  Disaster Management Plan (DMP) – a must
and Recovery & reconstruction has been
Chinese villages got washed away adequately strengthened.
- Very successful Disaster Management as  Ground level officials must be extensively
the sensitized & trained.
But there is a great need to sensitize
case was dealt at a very high level with
effective co-ordination amongst agencies. ground level officials on the fundamental  Emergency supplies and resources must be
aspects of disaster prevention, i.e., risk stocked.
 Pratappura dam breach identification, risk reduction / mitigation,
- suffered due to delay in repair / risk transfer and early warning systems.  The physical processes must be analysed
strengthening works probably due to lack properly to take adequate measures during
of attention being a municipal dam. As a result, failures continue to occur planning and design stages. There is a need to
strengthen these institutions.
resulting into huge loss.
 Jaswant Sagar Dam breach
 Greater recognition should be there to the
- poses vital question about ageing and lack
personnel whose timely preventive actions
of funding towards operation &
averted potential disasters.
maintenance in irrigation sector.
“prevention is better than cure” The policy makers and top management
 Narmada Main Canal Breach
should realize ‘a stitch in time saves nine’ and
- disaster may happen even when it is should pay greater attention towards preventive
least expected. actions.

THANK YOU

You might also like