Professional Documents
Culture Documents
Montgomery County
Public Schools
Dr. Barker –
Independent Structural Town of
Consultant verifying
Blacksburg
OWPR’s methodology
OWPR MBP
Architects and Engineers Construction Manager
Investigation/Testing Findings
1. OWPR Facility Assessment Repairs necessary - (Category 1 Items)
• Visual inspection of building components and systems
• Floor elevation survey (documenting floor level and flatness)
2. Wall Settlement Data indicated no large voids under building. Data
• Electrical resistivity testing found four possible voids outside of the building. Test
• Used ground probes in a grid arrangement throughout the borings are recommended at these locations to
building and site to profile subsurface conditions determine if open voids are present.
• Test Borings
• Drilled test borings in several locations inside and outside of No unusual soil conditions and no unusual subsurface
building to identify soils and subsurface conditions findings, other than those at three locations where
underpinning can be installed.
3. Auditorium Structural System Repair Repairs necessary to Auditorium steel construction
• Forensic Engineer investigation of the gym collapse (FORCON) (similar to gym)
• Auditorium structural steel roof framing members and welds
• Used ultrasound to examine full-penetration welds
Ccr
Ccr
m
bedded medium-gray. fine- to medium-grained. locaJJy
Ccr crossbedded sandy dolomite and medium-gray. fine-
grained, rrKlssive dolomite. s. upper siliceous oolite and
-" " quartzose sandstone; discontinuous sandstone and sili-
_ (, ceous oolite near the middle; and basal {eldspathic
':i sandstone. Tellerina (F-946), an indicator or Tremp-
ealeau age. is found within one horizon. The upper
sandstone marker bed consists of about 10-20 feet
(3.1-6.1 m) of interbedded siliceous oolite and
medium-grained quartzose sandstone. The bm;al sand-
stone marker bed consists of about 10-20 feet (3.1 -
6.1 m) of predominantly light-gray, fine- to medium-
grained feic/$pathic sandstone interbedded with lesser
amounts of sandy dolomite. Total thickness is about
1200 feet (366 m). The soil is characterized by a thick
(10-20 feet; 3.1-6.1 m) colluvial mantle with abundant
siliceous oolite, sandstone, and chert detritus overlying
ATS International
a thick brown subsoil and saprolite. Advanced Technical Services
www.ats-intl.com
Summary of Karst Formation
• Limestone or dolomite
slowly dissolves away,
forming cave passages and
natural conduits for water
flow
ATS International
Advanced Technical Services
www.ats-intl.com
Sinkhole Formation- Cover Subsidence
ATS International
Advanced Technical Services
www.ats-intl.com
Sinkhole Formation- Cover Collapse
Overburden
~mostry day)
ATS International
Advanced Technical Services
www.ats-intl.com
Types of Karst Features
r •
.-
-"••
E
'0
•
-
8
(~
l ATS International
Advanced Technical Services
www.ats-intl.com
Resistivity Imaging for Identifying Karst
ATS International
Advanced Technical Services
www.ats-intl.com
Factors Effecting Resistivity
• Moisture
• Grain Size
• Mineral Content
ATS International
Advanced Technical Services
www.ats-intl.com
Voids
Sinkholes
Voids
ATS International
Advanced Technical Services
www.ats-intl.com
Cutters and Pinnacles
ATS International
Advanced Technical Services
www.ats-intl.com
Collected Data for 12 Resistivity Sections
i
(
I
..
ATS International
Advanced Technical Services
www.ats-intl.com
9
Results of Line 9
Line 9
possible fracture
zones
ATS International
Advanced Technical Services
www.ats-intl.com
5
Northeast bedro
Southwest ck
wall
Line 5
likely fracture
and/or solutional
zones
Tennis courts gymnasium
Line 1
/
/
/
/
McDONOUGH
M BP BOLYARD
PECK
/
/
McDONOUGH
M BP BOLYARD
PECK
• Various under-sized steel truss members • Reinforce with additional steel members
Cross Section of Failed Weld from Gym Truss Seat Auditorium Truss Seat
Note: A± 30’ length of the west wall of the auditorium exceeds the
maximum allowable height for its construction and will require steel
bracing to the roof framing. This work will be done when the
auditorium trusses are repaired and will be concealed above the
ceiling.
Questions about Auditorium Repairs
,/
/
MBP ~~H
Issue Solution
• Inadequate reinforcing steel within concrete beams • Carbon fiber reinforcement or additional steel
and concrete
• The two materials are combined, each material utilizing its best
properties
Basic Civil Engineering Principles
C
Continuous Reinforced Concrete Beam
IT IT IT IT IT
What happens if new supports are added between columns?
MBP
McDONOUGH
BOLYARD
PECK
Ian Wienholt
Business Development Manager
• 34 years of Concrete Repair and
Strengthening Experience
• Over 15,000 Repair Project
• Over 25,000 PT Projects
• 1,500 Employees
• 22 Offices- International
– UAE, UK, Saudi, China
General Repair Group:
Strengthening Division
Carbon Fiber Reinforced Polymer
Strengthening
Externally Bonded FRP Sheet
•Lightweight
To Date:
Nationwide ≈ 15-18M sqft installed
SPS ≈ 7M sqft installed on over 700 + projects
What Is FRP Flexural Strengthened R/C?
Yield
Tension Steel
FRP carries
TENSION
Positive Moment
What Is FRP Flexural Strengthened R/C?
Negative Moment
FRP carries
TENSION
TOP
Tension Steel
Yield
Concrete carries
Compression
COMPRESSION BOTTOM
Column
What Is FRP Shear Strengthened R/C?
“SHEAR”
Installation Step 1:
Surface Grinding/Shot Blasting
to Open Pores
Installation Step 2:
Remove Dust from Surface
Before After
Installation Step 3:
Epoxy Primer Application
Installation Step 4:
Epoxy Putty Trowel Applied
Installation Step 5:
Saturation Coat and CFRP
Installation Step 6:
Rib Roll & Final Saturation Coat
Installation Step 7:
Intumescent Topcoat
External Post Tensioning
Strengthening
External Post Tensioning
NEW LOAD
F
Live end
Dead end
F
Uplift
at Deviator
Flexural Strengthening Case Study
“Environmental” Overload
Tension Tension
“YIELD”
Flexural Strengthening Case Study
“Environmental” Overload
Flexural Strengthening Case Study
“Environmental” Overload
¼”
Amplitude
Dowel Insertion
Flexural Strengthening Case Study
“Environmental” Overload
Flexural Strengthening Case Study
“Environmental” Overload
Flexural Strengthening Case Study
“Environmental” Overload
Flexural Strengthening Case Study
“Environmental” Overload
Flexural Strengthening Case Study
“Environmental” Overload
Flexural Strengthening Case Study
“Environmental” Overload
43’
SCC Section Enlargement
Strengthening
Transfer Slab Cracking
/ I
Demo and Prep
2000
3000 Hilti Undercut
Studs Anchors
SCC Pumping Anyone???
40 Tons of 1100
Steel LF
Finished Product
185 CU YDS /
375 Tons of
Concrete
Finished Product
Estimated Cost of Beam Testing and Repairs
Subtotal Testing of Concrete Beams $ 679,000.00
Subtotal of Structural Repairs $ 3,400,000.00
Replace Roof after Repairs $ 715,000.00 Baker Roofingker Roofing
Subtotal of Structural Repairs & Testing $ 4,079,000.00
Contingency $ 1,423,680.00
Total $ 5,502,680.00
Questions about Concrete Beam Repairs
/
/
McDONOUGH
M BP BOLYARD
PECK
Concrete $ 1,020,386.00
Masonry $ 548,958.00
Metals $ 448,002.00
Wood & Plastics $ 9,042.00
Thermal & Moisture Protection $ 236,398.00
Doors & Windows $ 112,361.00
Finishes $ 295,720.00
Equipment $ 1,271,599.00
Elevator $ 50,000.00
Plumbing, Heat, Ventilation & Air Conditioning $ 1,460,794.00
Electrical $ 876,003.00
Sub Total Construction $ 6,944,520.00
Permits $ 12,900.00
A/E Fees $ 1,041,700.00
Cost Estimating $ 14,000.00
Geotechnical & Structural Tests $ 100,000.00
Engineering & Special Testing $ 40,000.00
Quality Assurance & Testing Fees $ 17,200.00
Construction Management $ 300,000.00
Sub Total Fees & Soft Cost $ 1,525,800.00
Total $ 8,470,320.00
10 % Contingently included in all items above
This estimate incudes cost to rebuild the entire lower level foundation, structure, exterior and interior walls
Questions about Gym Replacement Estimate
,/
/
MBP ~~H
Subtotal Testing of Concrete Beams $ 679,000.00
General & Mech. Services
1. Category 1 Items from OWPR Facility Assessment $ 141,000.00 (GMS)
Subtotal of Structural Repairs $ 4,027,000.00
Subtotal of Structural Repairs & Testing $ 4,706,000.00
Contingency $1,423,680
Gym Replacement Estimated Cost $ 8,470,320
Testing, Repairs, and Gym Replacement $ 14,850,000
Schedule
Pro ct
Repair of Wall
Repair of
Settlement in Repair Deficient
Repair
Boiler Room, ncrete Gym
from OWPR Auditorium Roof
Auto Shop, and (including Replacement
Facility Structural Steel
Wood Working testing)
Assessment
o
"...
o
N
/ "...
"...
o
N
N
"...
MBP
McDONOUGH
BOLYARD
PECK
Replace Heating, Ventilation, Air Conditioning $ 3,300,000.00
Replace Fire Alarm $ 265,000.00
Upgrade Plumbing Fixtures to ADA Requirements $ 200,000.00
Sub Total Building Infrastructure Upgrades $ 3,765,000.00
Replace Vinyl Floor Tile $ 256,000.00
Replace Carpet $ 91,000.00
Paint Interior Walls $ 418,000.00
Replace Ceiling Grid and Tiles $ 418,000.00
Replace Auditorium Seating $ 210,000.00
Sub Total Finishes Replacement $ 1,393,000.00
Replace Furniture and Upgrade Technology $ 1,500,000.00
Add Sprinkler System $ 838,000.00
Sub Total Upgrades $ 7,496,000.00
BHS Existing Mechanical
• Heating Plant – Two 250 BHP, dual fuel, Scotch Marine 2-pass fire tube boilers,
original
• Heating Distribution – Primary pumps, 20 HP centrifugal. Secondary pumps: several
inline pumps.
• Cooling Plant – Two 325 Ton variable speed Centrifugal Chillers with forced draft
cooling towers, new.
• Cooling Distribution – Primary pumps, 50 HP centrifugal. Secondary pumps: several
inline pumps.
• Auditorium – Four pipe with Air Handling Units.
• Classrooms – Four Pipe unit ventilators in exterior Classrooms. Variable Air Volume
Boxes with hot water heat in interior classrooms
• Administration - Variable Air Volume Boxes with hot water heat.
• Library – Four pipe with Air Handling Units.
• Vo. Tech – Four Pipe air handling units with hot water reheat.
• Band/Coral – Four Pipe air handling units with hot water reheat.
• Cafeteria / Kitchen - Four pipe with Air Handling Units and unit ventilators.
DOAU – Dedicated Outdoor Air Unit
Work that can be Done to Improve Interior
Environment and Building Operations
Description Estimate
Replace Heating, Ventilation, Air Conditioning $ 3,300,000.00
Replace Fire Alarm $ 265,000.00
Upgrade Plumbing Fixtures to ADA Requirments $ 200,000.00
Sub Total Building Infrastructure Upgrades $ 3,765,000.00
Replace Vinyl Floor Tile $ 256,000.00
Replace Carpet $ 91,000.00
Paint Interior Walls $ 418,000.00
Replace Ceiling Grid and Tiles $ 418,000.00
Replace Auditorium Seating $ 210,000.00
Sub Total Finishes Replacement $ 1,393,000.00
Replace Furniture and Upgrade Technology $ 1,500,000.00
Add Sprinkler System $ 838,000.00
Sub Total Upgrades $ 7,496,000.00
Questions/Discussions
/
/