MATRIKS KEMAJUAN INFRASTRUCTURE WORKING GROUP

REPUBLIC OF KOREA – REPUBLIC OF INDONESIA/ROI-ROK


ECONOMIC COOPERATION JOINT TASK FORCE

Status March, 12th 2010

PROJECT STATUS MEETING AGENDA KOREA

ROAD (DITJEN BINA MARGA)

On Going Master Plan Arterial - Final Report scheduled to be In the future, for the purpose of
Projects Road Network di completed in April 2010. capacity building,
Pulau Sumatera 1. Korean consultants
- Training on Road Policy and
should be based in Indonesia
Technology has been conducted in
while undertaking a
February and March 2009 attended by
study/technical assistance.
representatives from Ministry of Public
Work, Bappenas and Local 2. Local
Government. consultant/counterpart to be
- Problem: Absence of local counterpart involved in the study and
creates communication problem with technical assistance activities.
the Korean Consultant who do not not
based in Indonesia.
Manado By Pass - Loan Agreement signed on October, - Acceleration of approval
Phase II 16th 2008 with the Loan Effective Date proceses by the EDCF.
of February, 23rd 2009 amounting to
US$ 16 million. - Agreed on the currency used
in the construction and
- Land aquicition completed by
consultancy contract
Provincial Government of Sulawesi
aggrement. process.
Utara

1/12
PROJECT STATUS MEETING AGENDA KOREA
- Procurement plan, procurement
schedule, REOI, RFP PC document
(revised) and criteria PQ evaluation
are submitted to EDCF and is now
waiting for EDCF approval

- Construction is scheduled to be
started in mid 2010

- Problem: BPK audit finding


recommends to use Indonesian rupiah
in the contract agreement as opposed
to Korean won. Meanwhile, the EDCF
guidelines requires to use Korean
Won.
Padang By Pass - FS Review conducted under EDCF - Agreement on the currency be
funding in 2007. used in construction and
consultancy contract
- No land acquisition is required -
- ODA Loan Agreement has been
discussed with Korean Export-Import
Bank

- Loan Agreement is being prepared bu


MoF and The EXIM Bank of Korea.

- Loan Agreement scheduled to be


signed in the 2nd quarter of 2010

2/12
PROJECT STATUS MEETING AGENDA KOREA

Gorontalo-Djalaludin - Proposed to be reincluded in


- FS completed under Korean funding in
Access Road to the Bappenas Blue Book
2008.
Airport 2010-2014 amounting to US$
- Korea consultant submitted Final 19 juta.
Feasibility Study Report to Ditjen Bina
Marga on February 28th 2008.

- Readiness criteria not been comply to


be inserted in the Blue Book 2010.
- Problem: land acquisition is on going

New Proposed Toll Road - Included in the Blue Book Revisi II - Agreement on the steps to be
Project Development of Solo- 2008 costing US$ 100 juta. taken to accelerate project
Kertosono implementation
- Minutes of Discussion to accelerate
the development of Solo-Kertosono
toll road signed in Indonesian-South
Korean Bilateral Consultation Meeting
on EDCF Loan in
- Land acquisition is partly completed
out of out of ±178 km of project length,
- In 2009, small construction work is
started, i.e. bridge construction to
ease access to the project site.
- On going review of Feasibility Study
by EDCF scheduled to be completed
in March 2010.

3/12
PROJECT STATUS MEETING AGENDA KOREA

- Proposed in the Blue Book 2010.


- Preparation readiness criteria.
- Preparation Land Acquisition and
Resettlement Action Plan (LARAP)
final document 2010.
Benoa Toll Road - Included in the Blue Book Revisi II Agreement on the steps to be
Development of 2008 costing US$ 127 millions. taken to accelerate project
Serangan – Tanjung implementation
- Land acquisition needed 7,5 km
- Access road with 2,8 km length have
been constructed by Local
Government.
- EDCF is reviewing FS and DED up to
March 2010.Followed by Loan
Agreement signed.
Construction of - Proposed in the Blue Book 2010. Agreement on the steps to be
Serangan-Tanjung taken to accelerate project
- Preparation of readiness criteria.
Benoa Bridge implementation
- Preparation of DED and final LARAP
document for 2010.
TRANSPORTATION

Proposed Project Intelligent Traffic - MoT has proposed to Bappenas to Agreement on the steps to be
System include this project in the Blue Book taken to accelerate project
2006-2009 for Korean funding. implementation
-
- Feasibility Study is on going by

4/12
PROJECT STATUS MEETING AGENDA KOREA

Vipothec Consulting(Korea)
- Revision of the Blue Book 2006-2009
Improvement and - Included in the Blue Book 2006-2009 Agreement on the steps to be
Development of Aids and ECDF Rolling Plan taken to accelerate project
to Navigation - Estimated Project cost USD 25 implementation
millions.
- FS has been conducted under ECDF
funding as requested by EDCF to
update JICA study 2002
WATER RESOURCES (DITJEN SUMBER DAYA AIR)
Commited Construction of - Land acquisition is on going, 72 Ha of - PPP study for water
Projects Karian Multipurpose 17.000 Ha required is completed. conveyance part is required
Dam
- DED completed by KOICA in 2006. - Clarity of Korean Government
- Environmental Impact Analysis and commitment to assist the
Land Acquisition and Resettlement project
Action Plan are completed.
- KOICA is commencing Master Plan
and Feasibility Study of The Karian
Dam Serpong Water Conveyance and
Supply System.
- Local governments are keen to
accelerate land acquisition, but they
need firm commitment from Korean
side that project will be funded

5/12
PROJECT STATUS MEETING AGENDA KOREA
Master Planning and - Proposed to be included in the Blue -
Feasibility Study of
The Karian Dam - Book 2010-2014
Serpong Water
Conveyance and
Supply System
- FS done by local consultant.
New Proposed Raw Water Availability of Technical Assistance
Project Infrastructure for - Proposed to be included in the Blue
Bandar Lampung City Book 2010-2014
Flood Control / - Included I the Blue Book 2010-2014. Availability of Technical Assistance
Drainage
Improvement for
Pekanbaru City and
Water Resources
Development of the
Siak River Basin in
Provinsi Riau
The Construction o Proposed to be included in the Blue Book Availability of Technical Assistance
Transfer Water 2010-2014.
Interbasin Cibatarua-
Cilaki Project West
Java
Comprehensive Proposed to be included in the Blue Book Availability of Technical Assistance
Study on Tondano- 2010-2014.
Likupang River Basi
Water Resources
Management in North
Sulawesi

6/12
PROJECT STATUS MEETING AGENDA KOREA

Preparation of a Included in the Blue Book 2010-2014. Availability of Technical Assistance


Databank for Coastal
Protection and
Management in
Jakarta
SPATIAL PLANNING (DITJEN PENATAAN RUANG)

Status of the The Formulation of - Included in the Blue Book 2008 and Availability of Technical Assistance
Project National Spatial have been proposed in the Blue Book
Planning Strategic 2010-2014
Development
- Project Title revision as agreed by
Framework
KOICA and Ditjen Penataan Ruang.
- TOR has been revised according to
the new title with the amount of USD 3
millions
Infrastructure Financing in Collaboration with Global Infrastructure Funding

Proposed Collboration of - Meeting and discussion between PT Preparatoin of MoU betweenPT


Collaboration Indonesia Sarana Multi Infrastruktur and Global Sarana Multi Infrastruktur and Global
Infrastructure Fund Infrastructure fund is on going Infrastructure Fund.
with Global
Infrastructure Fund - Discussions are in progress on
exchange of information on
infrastructure project, capacity
building, co financing, etc

7/12
8/12