You are on page 1of 12

Slope Stability and Methods of Increasing the Factor of Safety

By Steve Yaeger
ECI 281a
University of California, Davis
Department of Civil and Environmental Engineering

Introduction

Slope stability is one of the fundamental problems faced on a consistent basis by the
majority of practicing Geotechnical Engineers. This is why slope stability analysis is
emphasized both at the undergraduate and more so at the graduate level of Geotechnical
studies. Currently one can find and use multiple computer programs to perform anything
from integration and analysis of seepage through a section of an earth dam to an analysis
of the stability of a slope. It is in some ways it could be considered engineering by
Windows. Computers and computer programs are a very large part of current
engineering practice. So much so that it is very easy to forget the engineering principles
on which the programs are founded.

This paper serves to review and summarize some of the simpler techniques for the
analysis of slope stability as well as their applications and limitations.
This paper will also review techniques for increasing the factor of safety of unstable
slopes including the use of tiebacks, and the construction of stone columns. A case study
of the Forks of Butte project that used tiebacks as a stabilization method will also be
reviewed.

Techniques of Slope Stability Analysis

The following analysis techniques will be reviewed in this section:

1) Ordinary Method of Slices.


2) Simplified Janbu Method.
3) Simplified Bishop Method.
All of the above methods of analysis divide a slide mass into a number of slices and
analyze the individual slices as seen in Figure 1. Dividing up the soil mass into a number
of slices allows one to accommodate differing slide mass geometries, stratified soils
within the mass and external loads.

Figure 1 – Illustration of Division of Sliding Mass into Slices (Abramson et al., 1996).

F = Factor of Safety ZL = left interslice force


Sa = available strength ZR = right interslice force
Sm = mobilized strength θL = left interslice force angle
Uα = pore water force θR = right interslice force angle
Uβ = surface water force hL = height of force ZL
W = weight of slice hR = height of for ZR
N’ = effective normal force α = inclination of slice base
Q = external surcharge β = inclination of slice top
kv = vertical seismic coefficient h = average height of slice
kh = horiz. seismic coefficient hc = height of centroid of slice

Figure 2 – Forces acting on a typical slice. (Abramson et al., 1996)


Ordinary Method of Slices

This method assumes that the resultant of interslice forces is inclined such that it is
parallel to the base of the slice. This assumption does not satisfy interslice force
equilibrium. Please see the following equations derived from Figure 2 and the above
assumption:
N ' = −U α − k hW sin α + W (1 − k v ) cos α + U β cos( β − α ) + Q cos(δ − α )

The mobilized shear strength at the base of each slice is determined using the following
equation:
C + N ' tan φ
Sm =
F
The moment equilibrium of the slices about a common center of the circular failure
surface is
n

∑ M o = ∑ [W (1 − k v ) + U β cos β + Q cos δ ]R sin α


i =1

n
− ∑ [U β sin β + Q sin δ ]( R cos α − h)
i =1

n n
− ∑ [ S m ]R + ∑ [k hW ( R cos α − hc )] = 0
i =1 i =1

If the factor of safety F is assumed to be the same for all of the slices then the following
can be derived:
n

∑ (C = N ' tan φ )
F= i =1
n

∑A
i =1
1 − A2 + A3

A1 = (W (1 − k v ) + U β cos β + Q cos δ ) sin α


h
A2 = (U β sin β + Q sin δ )(cos α − )
R
hc
A3 = k hW (cos α − )
R
Simplified Janbu Method

The simplified Janbu Method assumes zero interslice shear forces and does not satisfy
moment equilibrium. However, the simplified Janbu method does satisfy vertical force
equilibrium and overall horizontal force equilibrium.

The normal effective stress at the base of each slice can be determined with the following
equations:
− U α cos α − S m sin α + W (1 − k v ) + U β cos β + Q cos δ
N'=
cos α
The overall horizontal force equilibrium for the slide mass is determined from the
following:
n n

∑ [ FH ]i = ∑ [( N '+U α ) sin α + Wk h + U β sin β ]


i =1 i =1
n
C + N ' tan φ
+ ∑ [Q sin δ − cos α ] = 0
i =1 F
It then follows that the Factor of Safety F can be determined with the following equation:
n

∑ [C + N ' tan φ ] cosα


F= i =1
n

∑A
i =1
4 + N ' sin α

A4 = U α sin α + Wk h + U β sin β + Q sin δ

The Simplified Janbu Method does not satisfy moment equilibrium for the slide mass, as
mentioned earlier. Therefore, Janbu performed more rigorous solutions and compared
the result to those found using his simplified method. He then presented the following
chart as seen in Figure 3 to correct for his over-determined solution.
Figure 3 – Janbu’s Correction factor for his simplified method

FJanbu= fo * Fcalcualted

Simplified Bishop Method

The Simplified Bishop assumes zero interslice shear forces, satisfies moment equilibrium
around the center of a circular failure surface and satisfies vertical force equilibrium.

The moment equilibrium of the sliding mass is given by the following:


n

∑ M o = ∑ [W (1 − k v ) + U β cos β + Q cos δ ]R sin α


i =1
n
− ∑ [U β sin β + Q sin δ ]( R cos α − h)
i =1
n n
− ∑ [ S m ]R + ∑ [k hW ( R cos α − hc )] = 0
i =1 i =1

The factor of safety, F, can be determined from the following:


n

∑ C + N ' tan φ
F= i =1
n

∑A
i =1
5 − A6 + A7

A5 = (W (1 − k v ) + U β cos β + Q cos δ ) sin α


h
A6 = (U β sin β + Q sin δ )(cos α − )
R
hc
A7 = k hW (cos α − )
R
The vertical effective stress at the base of the slice can be determined by summing the
vertical forces:
1 C sin α
N'= [W (1 − k v ) − − U α cos α + U β cos β + Q cos δ ]
mα F
tan α tan φ
mα = cos α [1 + ]
F

Bishops Simplified Method does not satisfy horizontal force equilibrium for one of the
slices and can only be applied to circular surfaces. As can be seen from the simplicity of
the above equations the method is very easy and can provide results within five percent
of those found with more rigorous methods.

The methods described above are very simple, however with simplicity comes
limitations. Failure is assumed to begin when the factor of safety on the failure surface is
equal to one therefore the stress-strain relationship is neglected (i.e. the methods to not
allow for strain hardening of the soil.) The methods mentioned above also assume a
constant factor of safety along the failure surface. This error in this assumption is
amplified when there are different soils along the failure plane.

Methods of Increasing the Factor of Safety

It is very well known fact that slopes fail. They fail for a variety of reasons. One may be
excavation of the toe of an embankment removing the balancing moment of the slope and
causing failure. Another could be an increase in pore pressure along the failure plane and
a corresponding decrease in vertical effective stress and a loss of strength.

There have been methods developed to help stabilize failing slopes and reinforce slopes
that could fail. This section will discuss two techniques that are used to reinforce existing
failures, installation of tiebacks and the installation of stone columns. It will be seen that
these methods can be very effective, if utilized correctly, stabilizing existing failures and
increasing the strength of slopes on the verge of failing.
Tiebacks

The concept of tiebacks is basically that one carries the lateral earth pressure with a “tie”.
The tie transfers the lateral load of the soil to a zone of soil or rock located beyond the
failure plane as can be seen in Figure 4.

Figure 4 – Illustration of Tieback Mode of Stabilization

The following design guideline should be used when working with tiebacks:
1) Tiebacks are typically installed in cohesionless soils
2) Typically have a design load of 50-130 tons (for ease of installation and size of
equipment required.
3) The length if the tieback should be selected such that the anchorage zone is
beyond the original failure plane.
4) Shallow failure surfaces typically only require one row of tiebacks.
5) The inclination of the tiebacks should be between 10 and 30 degrees from the
horizontal.
6) There should be a minimum of 15 feet of overburden above the zone of
embedment.
7) All permanent tiebacks should be corrosion resistant.
Stone Columns

Stone columns increase the factor of safety by two means:


1) Increases the average shear resistance of a soil by displacing or replacing the soil
with a series of gravel columns. (Reference Figure 5)
2) Columns act as a drain to decrease the effective stress in the soil and thereby
increase the strength along the failure surface.

According to Abramson et al. (1996) stone columns should be used in soils with shear
strengths in the range of 200-1000lb/ft2. Soils in the lower range of these limits may not
provide enough lateral support and thus the soil will consume too much stone to make the
method cost effective. Soils in the higher range may not benefit from the placement of
stone columns.

Figure 5 – Use of Stone Columns to Stabilize Slopes


The interested reader is encouraged to reference Abramson et al. (1996) for design
techniques.
Case Study
This case history takes us to Northern California, approximately 30 miles east of Chico,
California, to the Forks at Butte hydroelectric project. The project site was located on a
large landslide deposit (a section through the deposit along with the construction
alterations can be seen in Figure 6.)
Figure 5 – Section of Existing Site Conditions Prior to Remediation

As can be seen in Figure 5 the activities until failure included installation of a tensar wall
and excavation of the area at the top of the wall along with the installation of tiebacks to
support the new face of the slope. Slope movement was detected with the use of slope
inclinometers. All construction activity halted when slope movement was detected.

As can be seen in figure 5 the reason for movement was due to the excavation of the toe
of the slope causing an unbalance in the moment of the slope. Tiebacks were install to
maintain the face of the cut in slope however as seen in figure 5 they were useless in
increasing the factor of safety of the slope due to the fact that they did not extend beyond
the failure plain.

After considerable analysis it was determined to increase the factor of safety with a
combination of techniques. The first was using a buttress fill at the toe of the large slope
as can be seen in Figure 6. This technique was not discussed in this paper however is
pretty simple to see that by placing the buttress fill one is increasing the balancing
moment of the slope similar to replacing what was excavated in this application. The
second was the installation of additional tiebacks.

Figure 6 – Section of Site after Remediation


Five additional rows of tieback were installed above the cut slope that extended into the
bedrock underlying the site. Five additional rows of tiebacks were also placed at the very
bottom toe of the slope and were also embedded in the underlying bedrock.

Figure 7 – Slope Inclinometer Data


As can be seen from the slope inclinometer data in Figure 7 the remediation activities
were successful. Upon completion the movement ceased.
Conclusions
This paper has discussed methods of analytical analysis of the factor of safety of slopes
along with methods of increasing the factor of safety and finally a case study
demonstrating the effectiveness of one of the remediation techniques.

Currently there are several slope stability analysis computer programs on the market that
can analyze much more complex slopes and conditions then any gifted engineer could all
in a matter of seconds. It then becomes the engineer’s responsibility to examine the
output and determine if the program was effective in its analysis. Most of the time the
computer will be right if all of the parameters have been specified correctly. One still
needs to check.

The methods of analysis are useful for that purpose, to anticipate the solution prior to
running the program. After all this author would content that if you can’t estimate the
solution prior to letting something else do it for you then you have no business trying to
solve the problem.

Methods of increasing the factor of safety were also discussed. There will always be
circumstances as illustrated in the previous case study where construction activities begin
and unbalance a slope or disturb and existing failure. Those mistakes can be costly and
life threatening. It then becomes essential to be able to fix the problem. The methods
discussed along with countless others can and should be utilized in practice to save not
only ongoing construction sites but existing structures as well.

References

Powrie, William (1997), Soil Mechanics Concepts and Applications, E&FN Spon,
London, England

Abramson, Lee W., Lee, Thomas S., Sharma, Sunhill, Boyce, Glenn M. (1996), Slope
Stability and Stabilization Methods, John Wiley & Sons, Inc., New York, New York.
Klein, S.J., Hughes, D.K. (1992) Slope Stabilization at the Forks of Butte Project,
Stability and Performance of Slopes and Embankments – II, Geotechnical Special
Publication No. 31, Session 7

You might also like