Professional Documents
Culture Documents
By Steve Yaeger
ECI 281a
University of California, Davis
Department of Civil and Environmental Engineering
Introduction
Slope stability is one of the fundamental problems faced on a consistent basis by the
majority of practicing Geotechnical Engineers. This is why slope stability analysis is
emphasized both at the undergraduate and more so at the graduate level of Geotechnical
studies. Currently one can find and use multiple computer programs to perform anything
from integration and analysis of seepage through a section of an earth dam to an analysis
of the stability of a slope. It is in some ways it could be considered engineering by
Windows. Computers and computer programs are a very large part of current
engineering practice. So much so that it is very easy to forget the engineering principles
on which the programs are founded.
This paper serves to review and summarize some of the simpler techniques for the
analysis of slope stability as well as their applications and limitations.
This paper will also review techniques for increasing the factor of safety of unstable
slopes including the use of tiebacks, and the construction of stone columns. A case study
of the Forks of Butte project that used tiebacks as a stabilization method will also be
reviewed.
Figure 1 – Illustration of Division of Sliding Mass into Slices (Abramson et al., 1996).
This method assumes that the resultant of interslice forces is inclined such that it is
parallel to the base of the slice. This assumption does not satisfy interslice force
equilibrium. Please see the following equations derived from Figure 2 and the above
assumption:
N ' = −U α − k hW sin α + W (1 − k v ) cos α + U β cos( β − α ) + Q cos(δ − α )
The mobilized shear strength at the base of each slice is determined using the following
equation:
C + N ' tan φ
Sm =
F
The moment equilibrium of the slices about a common center of the circular failure
surface is
n
n
− ∑ [U β sin β + Q sin δ ]( R cos α − h)
i =1
n n
− ∑ [ S m ]R + ∑ [k hW ( R cos α − hc )] = 0
i =1 i =1
If the factor of safety F is assumed to be the same for all of the slices then the following
can be derived:
n
∑ (C = N ' tan φ )
F= i =1
n
∑A
i =1
1 − A2 + A3
The simplified Janbu Method assumes zero interslice shear forces and does not satisfy
moment equilibrium. However, the simplified Janbu method does satisfy vertical force
equilibrium and overall horizontal force equilibrium.
The normal effective stress at the base of each slice can be determined with the following
equations:
− U α cos α − S m sin α + W (1 − k v ) + U β cos β + Q cos δ
N'=
cos α
The overall horizontal force equilibrium for the slide mass is determined from the
following:
n n
∑A
i =1
4 + N ' sin α
The Simplified Janbu Method does not satisfy moment equilibrium for the slide mass, as
mentioned earlier. Therefore, Janbu performed more rigorous solutions and compared
the result to those found using his simplified method. He then presented the following
chart as seen in Figure 3 to correct for his over-determined solution.
Figure 3 – Janbu’s Correction factor for his simplified method
FJanbu= fo * Fcalcualted
The Simplified Bishop assumes zero interslice shear forces, satisfies moment equilibrium
around the center of a circular failure surface and satisfies vertical force equilibrium.
∑ C + N ' tan φ
F= i =1
n
∑A
i =1
5 − A6 + A7
Bishops Simplified Method does not satisfy horizontal force equilibrium for one of the
slices and can only be applied to circular surfaces. As can be seen from the simplicity of
the above equations the method is very easy and can provide results within five percent
of those found with more rigorous methods.
The methods described above are very simple, however with simplicity comes
limitations. Failure is assumed to begin when the factor of safety on the failure surface is
equal to one therefore the stress-strain relationship is neglected (i.e. the methods to not
allow for strain hardening of the soil.) The methods mentioned above also assume a
constant factor of safety along the failure surface. This error in this assumption is
amplified when there are different soils along the failure plane.
It is very well known fact that slopes fail. They fail for a variety of reasons. One may be
excavation of the toe of an embankment removing the balancing moment of the slope and
causing failure. Another could be an increase in pore pressure along the failure plane and
a corresponding decrease in vertical effective stress and a loss of strength.
There have been methods developed to help stabilize failing slopes and reinforce slopes
that could fail. This section will discuss two techniques that are used to reinforce existing
failures, installation of tiebacks and the installation of stone columns. It will be seen that
these methods can be very effective, if utilized correctly, stabilizing existing failures and
increasing the strength of slopes on the verge of failing.
Tiebacks
The concept of tiebacks is basically that one carries the lateral earth pressure with a “tie”.
The tie transfers the lateral load of the soil to a zone of soil or rock located beyond the
failure plane as can be seen in Figure 4.
The following design guideline should be used when working with tiebacks:
1) Tiebacks are typically installed in cohesionless soils
2) Typically have a design load of 50-130 tons (for ease of installation and size of
equipment required.
3) The length if the tieback should be selected such that the anchorage zone is
beyond the original failure plane.
4) Shallow failure surfaces typically only require one row of tiebacks.
5) The inclination of the tiebacks should be between 10 and 30 degrees from the
horizontal.
6) There should be a minimum of 15 feet of overburden above the zone of
embedment.
7) All permanent tiebacks should be corrosion resistant.
Stone Columns
According to Abramson et al. (1996) stone columns should be used in soils with shear
strengths in the range of 200-1000lb/ft2. Soils in the lower range of these limits may not
provide enough lateral support and thus the soil will consume too much stone to make the
method cost effective. Soils in the higher range may not benefit from the placement of
stone columns.
As can be seen in Figure 5 the activities until failure included installation of a tensar wall
and excavation of the area at the top of the wall along with the installation of tiebacks to
support the new face of the slope. Slope movement was detected with the use of slope
inclinometers. All construction activity halted when slope movement was detected.
As can be seen in figure 5 the reason for movement was due to the excavation of the toe
of the slope causing an unbalance in the moment of the slope. Tiebacks were install to
maintain the face of the cut in slope however as seen in figure 5 they were useless in
increasing the factor of safety of the slope due to the fact that they did not extend beyond
the failure plain.
After considerable analysis it was determined to increase the factor of safety with a
combination of techniques. The first was using a buttress fill at the toe of the large slope
as can be seen in Figure 6. This technique was not discussed in this paper however is
pretty simple to see that by placing the buttress fill one is increasing the balancing
moment of the slope similar to replacing what was excavated in this application. The
second was the installation of additional tiebacks.
Currently there are several slope stability analysis computer programs on the market that
can analyze much more complex slopes and conditions then any gifted engineer could all
in a matter of seconds. It then becomes the engineer’s responsibility to examine the
output and determine if the program was effective in its analysis. Most of the time the
computer will be right if all of the parameters have been specified correctly. One still
needs to check.
The methods of analysis are useful for that purpose, to anticipate the solution prior to
running the program. After all this author would content that if you can’t estimate the
solution prior to letting something else do it for you then you have no business trying to
solve the problem.
Methods of increasing the factor of safety were also discussed. There will always be
circumstances as illustrated in the previous case study where construction activities begin
and unbalance a slope or disturb and existing failure. Those mistakes can be costly and
life threatening. It then becomes essential to be able to fix the problem. The methods
discussed along with countless others can and should be utilized in practice to save not
only ongoing construction sites but existing structures as well.
References
Powrie, William (1997), Soil Mechanics Concepts and Applications, E&FN Spon,
London, England
Abramson, Lee W., Lee, Thomas S., Sharma, Sunhill, Boyce, Glenn M. (1996), Slope
Stability and Stabilization Methods, John Wiley & Sons, Inc., New York, New York.
Klein, S.J., Hughes, D.K. (1992) Slope Stabilization at the Forks of Butte Project,
Stability and Performance of Slopes and Embankments – II, Geotechnical Special
Publication No. 31, Session 7