FEDERAL BOULEVARD - ALAMEDA AVENUE TO 6TH AVENUE

WIDENING AND RECONSTRUCTION PROJECT March 2011

Project Overview Construction Phasing


On Monday, March 21st, the Colorado Department of Transpor- Once the utility and water quality work is complete, crews will
tation (CDOT) will begin a widening and reconstruction project begin the reconstruction and widening of Federal Boulevard.
on Federal Boulevard (State Highway 88) between Alameda Work will begin in the southbound lanes at 5th Avenue and
Avenue and 6th Avenue. move from north to south in two to three block increments.

The project will reconstruct and widen approximately one mile Once the widening and reconstruction is complete on the
of Federal Boulevard in concrete to accommodate an additional southbound lanes, crews will work in the northbound lanes
lane on northbound Federal Boulevard. When complete, there starting at Alameda Avenue and working south to north in two
will be three lanes in each direction with a raised median. In to three block increments.
addition, the traffic signals at the Federal Boulevard/1st Av-
enue and Federal Boulevard/2nd Avenue interchanges will be Crews will finish the project by constructing the raised median
replaced and sidewalks will be widened to eight feet to improve on Federal Boulevard.
safety for pedestrians.
What Improvements Will be Made at Barnum
Scott Contracting, Inc. is the contractor for this $7.8 million proj-
ect scheduled to be complete by the end of January 2013. The Park?
project is being funded by CDOT, the Federal Highway Admin- CDOT partnered with the City and County of Denver to
istration and the City and County of Denver. construct a water quality treatment facility in the southeast
corner of the park with man-made wetlands. The pedestrian/
bicycle trail around the lake will also be completed. Commonly
used areas of the park will not be impacted through this work.

Tentative Schedule
This is a tentative schedule of major milestones. The schedule is
subject to change:

March 2011- The project begins with utility relocation and


sanitary work

April 2011- Reconstruction and widening of southbound Federal


Boulevard begins at 5th Avenue working north to south

Fall 2011- Reconstruction and widening of northbound Federal


Boulevard begins at Alameda Avenue working south to north

Summer 2012- Construction of the raised median begins


The project will widen Federal Boulevard to accommodate an
additional lane on northbound Federal Boulevard. January 2013- Construction completed

What Work Will Take Place in March? Questions?


Before the widening and reconstruction of Federal Boulevard If you have questions about the project, please call the project
can begin, crews need to complete some utility relocation and hotline at (720) 215-1918.
drainage work as well as other preparatory work. Much of this
work will take place off of Federal Boulevard and near Barnum
Park. Project Updates
To receive e-mail updates about the project, visit
Some of the drainage work includes a new storm drain as well http://www.coloradodot.info and click on the cell phone icon in
as a sanitary sewer line. This work may require significant the upper right corner under the search function. From here,
weekend closures, but additional information will be released as you can select the list you would like to subscribe to including
the project progresses. the “Federal Blvd Widening” list under projects. For additional
information about the project, you can also visit the project web-
site at http://www.federalblvd.com/.
Traffic Impacts
Throughout the project, one lane of northbound and
southbound Federal Boulevard may be closed from 8:30 a.m.
to 3:30 p.m., Monday through Friday. Occasional weekend and
night work is possible. Delays are expected and alternate routes
are advised.