User Guide
i
1. Main Window .............................................................................................................................. 1
1.1.
Main Window ....................................................................................................................................................1
1.2. Main Window Menu .........................................................................................................................................2
2. Project .......................................................................................................................................... 4
2.1. Project Data .......................................................................................................................................................4
2.2. Open a Project ...................................................................................................................................................5
2.3. Save Project .......................................................................................................................................................5
2.4. Save Project with a Different Code and/or Version Number ........................................................................5
2.5. Save Project without Cost.................................................................................................................................5
2.6. Create New Project ...........................................................................................................................................6
2.7. Project Baseline .................................................................................................................................................7
2.8. Project Shortcut Menu......................................................................................................................................7
2.9. Comparing Projects ..........................................................................................................................................7
2.10. Projects Comparison Setup Dialog Window...................................................................................................8
2.11. Hide Project Comparison .................................................................................................................................9
2.12. Inserting a Project as a Subphase ....................................................................................................................9
2.13. Project Properties Dialog Window ..................................................................................................................9
2.14. Projects and Documents Dialog Window ......................................................................................................10
2.15. Change Project Data Date ..............................................................................................................................12
2.16. Target Finish....................................................................................................................................................12
2.17. Project Target Finish Setup............................................................................................................................12
2.18. Storage..............................................................................................................................................................12
2.19. Storage Properties Dialog Window................................................................................................................12
3. Object ......................................................................................................................................... 14
3.1. Object ...............................................................................................................................................................14
3.2. Internal Database ............................................................................................................................................14
3.3. Objects List Dialog Window...........................................................................................................................14
3.4. Object Properties Dialog Window .................................................................................................................14
3.5. Choose Objects Dialog Window .....................................................................................................................14
3.6. Adding Objects ................................................................................................................................................15
3.7. Delete Object....................................................................................................................................................15
3.8. List ....................................................................................................................................................................15
3.9. List with Sort Option, List with Sort and Search Options...........................................................................16
4. Project Presentations ................................................................................................................ 17
4.1. Project Views ...................................................................................................................................................17
4.2. Activity and Resource Gantts.........................................................................................................................17
4.2.1. Working with Gantt Charts ......................................................................................................................17
4.2.2. Gantt Diagram Shortcut Menu .................................................................................................................19
4.2.3. Gantt Chart Column Shortcut Menu.........................................................................................................19
4.2.4. Scaling Tool .............................................................................................................................................20
4.2.5. Activity Gantt ...........................................................................................................................................20
4.2.6. Resource Gantt .........................................................................................................................................28
4.3. Work Breakdown Structure...........................................................................................................................36
4.3.1. WBS .........................................................................................................................................................36
4.3.2. Work Breakdown Structure Main Menu ..................................................................................................36
4.3.3. WBS, OBS AND PBS Options Dialog Window......................................................................................38
4.4. Organizational Breakdown Structure ...........................................................................................................38
4.4.1. OBS ..........................................................................................................................................................38
4.4.2. Organizational Breakdown Structure Main Menu....................................................................................39
4.4.3. WBS, OBS AND PBS Options Dialog Window......................................................................................42
4.5. Activity Network .............................................................................................................................................43
4.5.1. Activity Network......................................................................................................................................43
4.5.2. Activity Network Main Menu ..................................................................................................................44
4.5.3. Activity Network Options Dialog Window..............................................................................................46
4.5.4. Activity Network Shortcut Menu .............................................................................................................46
4.5.5. Graphical Presentation of Activities and Phases in Activity Network .....................................................46
4.5.6. Presentation Level in Activity Network ...................................................................................................47
ii
4.5.7. Show Level Dialog Window in Activity Network ...................................................................................47
4.5.8. Shape Setup Dialog Window....................................................................................................................47
4.6. Linear Diagram ...............................................................................................................................................48
4.6.1. Linear Diagram.........................................................................................................................................48
4.6.2. Linear Diagram Main Menu.....................................................................................................................49
4.6.3. Linear Diagram Options Dialog Window.................................................................................................51
4.6.4. Linear Diagram Print Preview Window ...................................................................................................52
4.6.5. X-axis Setup Dialog Window...................................................................................................................53
5. Breakdown Structures.............................................................................................................. 54
5.1. WBS Definition................................................................................................................................................54
5.2. OBS Definition.................................................................................................................................................54
5.3. Create Breakdown Structures........................................................................................................................54
5.4. Full Structure...................................................................................................................................................54
5.5. Project Structures List Dialog Window.........................................................................................................55
5.6. Structure Properties Dialog Window ............................................................................................................56
6. Phases ......................................................................................................................................... 57
6.1. Phase Properties Dialog Window...................................................................................................................57
6.2. Edit Phase in Activity Gantt...........................................................................................................................58
6.3. Update Phase by Selected Project ..................................................................................................................58
6.4. Convert Phase to Activity ...............................................................................................................................58
6.5. Phases in Activity Gantt..................................................................................................................................58
6.5.1. Add phase in Activity Gantt .....................................................................................................................58
6.6. Edit Phase in Activity Gantt...........................................................................................................................59
6.6.1. Delete Phase in Activity Gantt .................................................................................................................59
6.6.2. Phase Shortcut Menu in Activity Gantt ....................................................................................................59
6.6.3. Shortcut Menu of Group of Selected Phases in Activity Gantt ................................................................61
6.7. Update Phase by Selected Project ..................................................................................................................62
6.7.1. Copy Phase in Activity Gantt ...................................................................................................................62
6.7.2. Move Phase in Activity Gantt ..................................................................................................................63
6.8. Convert Phase to Activity ...............................................................................................................................63
6.9. Phases in Breakdown Structures ...................................................................................................................63
6.9.1. Add Phase in WBS View .........................................................................................................................63
6.9.2. Edit Phases in WBS View ........................................................................................................................64
6.9.3. Delete Phase in WBS................................................................................................................................64
6.9.4. Phase Shortcut Menu in WBS View.........................................................................................................64
6.9.5. Exclude Phase from WBS in WBS View .................................................................................................64
6.10. Phases in Activity Network.............................................................................................................................65
6.10.1. Add Phase in Activity Network................................................................................................................65
6.10.2. Edit Phase in Activity Network ................................................................................................................65
6.10.3. Delete Phase in Activity Network ............................................................................................................65
6.10.4. Phase Shortcut Menu in Activity Network...............................................................................................66
6.10.5. Move Phase in Activity Network .............................................................................................................66
7. Activities..................................................................................................................................... 67
7.1. Activity .............................................................................................................................................................67
7.2. Activities Table ................................................................................................................................................67
7.3. Activity Properties Dialog Window ...............................................................................................................69
7.4. DPH Activity Type ..........................................................................................................................................72
7.5. ASAP (As Soon As Possible)...........................................................................................................................73
7.6. ALAP (As Late As Possible) ...........................................................................................................................73
7.7. NET (Not Earlier Than)..................................................................................................................................73
7.8. NLT (Not Later Than) ....................................................................................................................................73
7.9. Activity Group Properties Dialog Window ...................................................................................................73
7.10. Interruptible Activities....................................................................................................................................73
7.11. Add New Activity in Activities Table.............................................................................................................74
7.12. Edit Activity in Activities Table .....................................................................................................................75
7.13. Delete Activity in Activities Table..................................................................................................................75
7.14. Activities in Activity Gantt .............................................................................................................................75
7.14.1. Add New Activity in Activity Gantt.........................................................................................................75
7.14.2. Edit Activity in Activity Gantt .................................................................................................................75
iii
7.14.3. Delete Activity in Activity Gantt..............................................................................................................76
7.14.4. Activity Shortcut Menu in Activity Gantt ................................................................................................76
7.14.5. Shortcut Menu of Group of Selected Activities in Activity Gantt............................................................77
7.14.6. Copy Activity in Activity Gantt ...............................................................................................................78
7.14.7. Move Activity in Activity Gantt...............................................................................................................79
7.14.8. Convert Activity to Phase.........................................................................................................................79
7.14.9. Change Activity and Phase Dialog window .............................................................................................79
7.15. Activities in Activity Network ........................................................................................................................80
7.15.1. Add New Activity in Activity Network....................................................................................................80
7.15.2. Edit Activity in Activity Network ............................................................................................................81
7.15.3. Delete Activity in Activity Network ........................................................................................................81
7.15.4. Activity Shortcut Menu in Activity Network ...........................................................................................81
7.15.5. Shortcut Menu of Highlighted Activities in Activity Network ................................................................81
7.15.6. Move Activity in Activity Network..........................................................................................................81
8. Calendars ................................................................................................................................... 83
8.1. Project Calendars............................................................................................................................................83
8.2. Calendars Table...............................................................................................................................................83
8.3. Weeks Table.....................................................................................................................................................84
8.4. Calendar Exceptions Table.............................................................................................................................85
8.5. Calendar Properties Dialog window..............................................................................................................85
8.6. Creating Project Calendars............................................................................................................................86
8.7. Week Properties Dialog window ....................................................................................................................86
8.8. Calendar Exception Properties Dialog window............................................................................................87
9. Links........................................................................................................................................... 89
9.1. Links Table ......................................................................................................................................................89
9.2. Link Properties Dialog Window.....................................................................................................................89
9.3. Creating New Links ........................................................................................................................................90
9.4. Edit Link in Links Table.................................................................................................................................90
9.5. Delete Link in the Links Table .......................................................................................................................91
9.6. Lag ....................................................................................................................................................................91
9.7. Finish – Start....................................................................................................................................................91
9.8. Finish – Finish..................................................................................................................................................92
9.9. Start – Finish....................................................................................................................................................92
9.10. Start – Start .....................................................................................................................................................92
9.11. Diagram of Preceding and Succeeding Activities .........................................................................................92
9.11.1. Links Diagram..........................................................................................................................................92
9.11.2. Links Diagram Shortcut Menu .................................................................................................................93
9.11.3. Activity Shortcut Menu in Links Diagram ...............................................................................................93
10. Resources ................................................................................................................................... 94
10.1. Resource ...........................................................................................................................................................94
10.2. Resources Table...............................................................................................................................................94
10.3. Resource Properties Dialog Window .............................................................................................................95
10.4. Add Resource in Resources Table..................................................................................................................97
10.5. Edit Resource in Resources Table..................................................................................................................98
10.6. Delete Resource in Resources Table ..............................................................................................................98
10.7. Search for Resource Overloads......................................................................................................................98
10.8. Overloaded Resources Dialog Window .........................................................................................................99
10.9. Resources in Resource Gantt..........................................................................................................................99
10.9.1. Add Resource in Resource Gantt..............................................................................................................99
10.9.2. Edit Rsource in Resource Gantt..............................................................................................................100
10.9.3. Delete Resource in Resource Gantt ........................................................................................................100
10.9.4. Resource Shortcut Menu in Resource Gantt...........................................................................................100
10.9.5. Shortcut Menu of Group of Selected Resources in Resource Gantt .......................................................101
10.9.6. Move Resource in Resource Gantt .........................................................................................................101
11. Departments ............................................................................................................................ 102
11.1. Department Properties Dialog Window ......................................................................................................102
11.2. Departments in Resource Gantt...................................................................................................................103
11.2.1. Add Department in Resource Gantt........................................................................................................103
iv
11.2.2. Edit Department in Resource Gantt........................................................................................................103
11.2.3. Delete Department in Resource Gantt ....................................................................................................103
11.2.4. Department Shortcut Menu in Resource Gantt.......................................................................................104
11.2.5. Shortcut Menu of Group of Selected Departments in Resource Gantt ...................................................105
11.2.6. Move Department in Resource Gantt .....................................................................................................105
11.3. Departments in OBS .....................................................................................................................................105
11.3.1. Add Department in OBS View...............................................................................................................105
11.3.2. Edit Department in OBS View ...............................................................................................................105
11.3.3. Delete Department in OBS View ...........................................................................................................106
11.3.4. Department Shortcut Menu in OBS View ..............................................................................................106
11.3.5. Exclude Department from OBS..............................................................................................................106
12. Multi-resources........................................................................................................................ 107
12.1. Multi-resource ...............................................................................................................................................107
12.2. Multi-resource Properties Dialog Window .................................................................................................107
12.3. Add Multi-resource in Multi-resources Table ............................................................................................108
12.4. Edit Multi-resource Properties in Multi-resources Table..........................................................................108
12.5. Delete Multi-resource in Multi-resources Table.........................................................................................108
13. Resource Skills......................................................................................................................... 109
13.1. Resource skills ...............................................................................................................................................109
13.2. Resource Skills Table ....................................................................................................................................109
13.3. Resource Skill Properties Dialog Window ..................................................................................................109
13.4. Add Resource Skills in Resource Skills Table.............................................................................................110
13.5. Edit Resource Skills in Resource Skills Table.............................................................................................111
13.6. Delete Resource Skills in Resource Skills Table .........................................................................................111
14. Teams ....................................................................................................................................... 112
14.1. Team ...............................................................................................................................................................112
14.2. Team Assignment Monitoring Dialog Window ..........................................................................................112
14.3. Team Assignment Properties Dialog Window ............................................................................................113
14.4. Team Assignment to a Group of Activities Dialog window .......................................................................114
14.5. Team Shortcut Menu in Activity Gantt.......................................................................................................114
15. Assignments ............................................................................................................................. 115
15.1. Assignment.....................................................................................................................................................115
15.2. Resource Assignments Table ........................................................................................................................115
15.3. Replace Assignments.....................................................................................................................................117
15.4. Replace Assignments Dialog Window .........................................................................................................117
15.5. Fixed Assignment Cost..................................................................................................................................118
15.6. Work Load.....................................................................................................................................................118
15.7. Resource-Hours .............................................................................................................................................118
15.8. Assignment Shortcut Menu in Resource Gantt Diagram ..........................................................................118
15.9. Resource Assignments...................................................................................................................................119
15.9.1. Resources Assignment in Activities Table .............................................................................................119
15.9.2. Resource Assignment Properties Dialog Window..................................................................................119
15.9.3. Resource Assignment to a Group of Activities Dialog Window ............................................................120
15.9.4. Resources Assignment in Activity Gantt................................................................................................121
15.9.5. Resource Assignment Shortcut Menu in Activity Gantt ........................................................................121
15.9.6. Resources Assignment in Activity Network...........................................................................................122
15.9.7. Resource Assignment to a Group of Activities Dialog Window ............................................................122
15.10. Multi-resource Assignments .........................................................................................................................123
15.10.1. Multi-resource Assignment in Activities Table......................................................................................123
15.10.2. Multi-resource Assignment Properties Dialog Window.........................................................................123
15.10.3. Multi-resource Assignment to a Group of Activities Dialog window ....................................................124
15.10.4. Multi-resource Assignment in Activity Gantt ........................................................................................125
15.10.5. Multi-Resource Assignment Shortcut Menu in Activity Gantt ..............................................................126
15.10.6. Multi-resource Assignment in Activity Network ...................................................................................126
15.11. Resource Skill Assignments..........................................................................................................................126
15.11.1. Resource Skill Assignment in Activities Table ......................................................................................126
15.11.2. Resource Skill Assignment Properties Dialog Window .........................................................................127
15.11.3. Resource skill Assignment to a Group of Activities Dialog window .....................................................127
v
15.11.4. Resource Skill Assignment in Activity Gantt.........................................................................................128
15.11.5. Resource Skills Assignment in Activity Network ..................................................................................128
15.11.6. Resource Skill Assignments in Resource Gantt Shortcut Menu.............................................................129
15.11.7. Fixing Resource Skill Assignments........................................................................................................129
15.12. Team Assignments.........................................................................................................................................129
15.13. Team Assignment Properties Dialog Window ............................................................................................129
15.14. Team Assignment to a Group of Activities Dialog Window ......................................................................130
15.15. Team Shortcut Menu in Activity Gantt.......................................................................................................131
16. Excluded Objects..................................................................................................................... 132
16.1. Excluded Structure Objects .........................................................................................................................132
16.2. Exclude Activity from WBS .........................................................................................................................132
16.3. Exclude Resource from OBS in Resource Gantt ........................................................................................132
16.4. Exclude Phase from WBS in Activity Gantt ...............................................................................................133
16.5. Exclude Department from OBS in Resource Gantt ...................................................................................133
17. Cost Components .................................................................................................................... 134
17.1. Cost Components...........................................................................................................................................134
17.2. Cost Components Table................................................................................................................................135
17.3. Cost Component Properties Dialog Window ..............................................................................................136
17.4. Add Cost Component in Cost Components Table......................................................................................137
17.5. Edit Cost Component in Cost Components Table......................................................................................138
17.6. Delete Cost Component in Cost Components Table ..................................................................................138
18. Materials .................................................................................................................................. 139
18.1. Material..........................................................................................................................................................139
18.2. Materials Table..............................................................................................................................................139
18.3. Material Properties Dialog Window............................................................................................................140
18.4. Add Material in the Materials Table ...........................................................................................................141
18.5. Edit Material in the Materials Table ...........................................................................................................141
18.6. Delete Material in the Materials Table........................................................................................................142
19. Material and Cost Component Consumptions..................................................................... 143
19.1. Cost Components Standard Page.................................................................................................................143
19.2. Materials Standard Page ..............................................................................................................................144
19.3. Fixed Material Consumption and Fixed Cost Component Expenditure ..................................................145
19.4. Profile of Fixed Material Consumption (or Cost Component Expenditure)............................................146
19.5. Material Consumption Setup in Activity Gantt..........................................................................................146
19.6. Material Consumption Setup in Resource Gantt .......................................................................................147
19.7. Material Consumption Setup in Activities Table .......................................................................................147
19.8. Material Consumption Setup in Resources Table ......................................................................................148
19.9. Material Consumption Setup in Assignments Table..................................................................................149
19.10. Material Consumption Setup in Activity Network.....................................................................................149
19.11. Costs Setup in Activity Gantt .......................................................................................................................150
19.12. Costs Setup in Resource Gantt.....................................................................................................................151
19.13. Costs Setup in Activities Table.....................................................................................................................151
19.14. Costs Setup in Resources Table....................................................................................................................152
19.15. Costs Setup in Materials Table ....................................................................................................................153
19.16. Assignment Cost Setup .................................................................................................................................153
19.17. Costs Setup in Activity Network ..................................................................................................................154
20. Scheduling................................................................................................................................ 155
20.1. Performing Schedule Calculation ................................................................................................................155
20.2. Scheduling Options Dialog Window ............................................................................................................155
20.3. Choose Objects for Leveling Dialog Window .............................................................................................157
20.4. Structures List Dialog Window....................................................................................................................157
20.5. Work Load Calculation for All Activity Assignments with Preset Duration and Productivity .............158
21. Filters........................................................................................................................................ 159
21.1. Filters..............................................................................................................................................................159
21.2. Filters Dialog Window ..................................................................................................................................160
vi
21.3. Simple Filter Dialog Window .......................................................................................................................161
21.4. Complex Filter Dialog Window....................................................................................................................161
22. Formulae .................................................................................................................................. 163
22.1. Formulae ........................................................................................................................................................163
22.2. Formulae Creation Dialog Window.............................................................................................................163
22.3. Formula Creation Dialog Window...............................................................................................................164
22.4. Mathematical Operators...............................................................................................................................164
22.5. Functions........................................................................................................................................................165
23. Centers ..................................................................................................................................... 167
23.1. Centers ...........................................................................................................................................................167
23.2. Resource Centers Table ................................................................................................................................167
23.3. Resource Center Properties Dialog Window ..............................................................................................168
23.4. Cost Centers Table ........................................................................................................................................168
23.5. Cost Center Properties Dialog Window ......................................................................................................169
23.6. Material Centers Table .................................................................................................................................170
23.7. Material Center Properties Dialog Window ...............................................................................................171
24. Cost periods ............................................................................................................................. 172
24.1. Cost Periods ...................................................................................................................................................172
24.2. Cost Component Periods Properties Dialog Window ................................................................................173
24.3. Material Cost Period Properties Dialog Window .......................................................................................174
24.4. Resource Cost Period Properties Dialog Window ......................................................................................174
25. Overtimes................................................................................................................................. 176
25.1. Overtime.........................................................................................................................................................176
25.2. Overtime Properties Dialog Window...........................................................................................................176
26. Risk Analysis ........................................................................................................................... 178
26.1. Risk Analysis..................................................................................................................................................178
26.2. Success Probabilities Trends ........................................................................................................................179
26.3. Success Probability Calculation Dialog Window........................................................................................181
27. Monitoring of Project Execution ........................................................................................... 183
27.1. Monitoring Project Performance.................................................................................................................183
27.2. Monitoring .....................................................................................................................................................184
27.2.1. Monitoring Table....................................................................................................................................184
27.2.2. Add Phase to Monitoring Table (Include in Monitoring) Dialog Window ............................................186
27.2.3. Include in Monitoring (Add Activities to Monitoring Table) Dialog Window ......................................186
27.2.4. Activity Monitoring Dialog Window .....................................................................................................187
27.2.5. Resource Assignment Monitoring Dialog Window................................................................................188
27.3. Team Assignment Monitoring Dialog Window ..........................................................................................189
27.4. Performance Archive ....................................................................................................................................190
27.4.1. Performance Archive..............................................................................................................................190
27.4.2. Actual Period Properties Dialog Window ..............................................................................................191
27.4.3. Import Performance Data from Another Project ....................................................................................192
27.4.4. Update Actual Material Consumption in Performance Archive.............................................................193
27.4.5. Update Actual Cost Component Expenditure in Performance Archive .................................................193
28. Documents, Tables and Reference-Books ............................................................................. 195
28.1. Notes Standard Page .....................................................................................................................................195
28.2. Documents......................................................................................................................................................195
28.2.1. Working with Documents.......................................................................................................................195
28.2.2. General Document..................................................................................................................................197
28.2.3. Create Reference-book from Project Table ............................................................................................197
28.2.4. Open a Document...................................................................................................................................197
28.2.5. Create New Document ...........................................................................................................................197
28.2.6. Save Document.......................................................................................................................................198
28.2.7. Document Properties Dialog Window....................................................................................................198
28.2.8. Document Shortcut Menu.......................................................................................................................199
vii
28.2.9. Data Transfer between Documents.........................................................................................................200
28.2.10. Data Transfer Options Dialog Window..................................................................................................200
28.3. Tables .............................................................................................................................................................201
28.3.1. Working with Tables ..............................................................................................................................201
28.3.2. Table Setup Dialog Window ..................................................................................................................203
28.3.3. Table Row Shortcut Menu......................................................................................................................203
28.3.4. Table Column Shortcut Menu ................................................................................................................204
28.3.5. Column Codes ........................................................................................................................................204
28.3.6. Column Properties Dialog Window .......................................................................................................205
28.3.7. Delete Table Column..............................................................................................................................207
28.3.8. Empty Table Column Shortcut Menu.....................................................................................................207
28.3.9. Table Cell Shortcut Menu ......................................................................................................................207
28.3.10. Fields Available Dialog Window ...........................................................................................................207
28.3.11. User Columns Properties Dialog Window .............................................................................................208
28.3.12. User Columns Properties Dialog Window .............................................................................................209
28.4. Reference Books ............................................................................................................................................209
28.4.1. Choosing Objects from Reference-book Dialog Window ......................................................................209
28.4.2. Cost Components Reference-book .........................................................................................................210
28.4.3. 'Materials' Reference-book .....................................................................................................................210
28.4.4. 'Resources' Reference-book....................................................................................................................211
28.4.5. 'Multi-resources' Reference-book...........................................................................................................212
28.4.6. Multi-resource Properties in Reference-books Dialog Window.............................................................213
28.4.7. 'Resource Skill' Reference-book.............................................................................................................214
28.4.8. Resource Skill Properties in Reference-book Dialog Box......................................................................214
28.4.9. Resource Assignment Productivities Reference-book............................................................................215
28.4.10. Resource Assignment Work Loads Reference-book ..............................................................................215
28.4.11. 'Resource Assignment Cost and Materials Requirements' Reference-book ...........................................216
28.4.12. 'Resource Assignment Cost and Materials Requirements' (per Volume unit) Reference-book..............216
28.4.13. 'Resource Assignment Cost and Materials Requirements' (Fixed per Quantity) Reference-book..........217
28.4.14. Corporate Reference Books....................................................................................................................218
29. Reports and Diagrams ............................................................................................................ 220
29.1. General Reports and Diagrams....................................................................................................................220
29.1.1. Reports ...................................................................................................................................................220
29.1.2. Report Parameters Wizard......................................................................................................................222
29.1.3. Diagrams and Histograms in Gantt Diagrams ........................................................................................225
29.1.4. Diagram Settings Dialog Window..........................................................................................................227
29.1.5. Diagram Properties Dialog Window ......................................................................................................229
29.2. Earned Value Analysis..................................................................................................................................230
29.2.1. Earned Value Analysis ...........................................................................................................................230
29.3. Success Probabilities Trends ........................................................................................................................232
29.3.1. Success Probabilities Report Settings Dialog Window ..........................................................................232
29.3.2. Success Probabilities Diagram Options Dialog Window .......................................................................235
29.4. Variance Trends ............................................................................................................................................237
29.5. Project Truncation ........................................................................................................................................237
29.5.1. Project Truncation by Period Dialog Window .......................................................................................237
30. Report Templates.................................................................................................................... 238
30.1. Report Template............................................................................................................................................238
30.2. Report Version and Period Dialog Window................................................................................................238
30.3. General Report Templates ...........................................................................................................................238
30.3.1. Standard Report Templates ....................................................................................................................238
31. Scripts....................................................................................................................................... 240
31.1. Scripts Table ..................................................................................................................................................240
31.2. Script Dialog Window ...................................................................................................................................240
31.3. Insert Command Dialog Window ................................................................................................................241
31.4. Script Command Arguments Dialog Window ............................................................................................242
31.5. Script History Dialog Window .....................................................................................................................243
31.6. Script Commands..........................................................................................................................................243
31.6.1. About Script Commands ........................................................................................................................243
31.6.2. CLOSE ...................................................................................................................................................244
viii
31.6.3. CREATEDOCDB ..................................................................................................................................244
31.6.4. CREATEDOCTEXT..............................................................................................................................244
31.6.5. CREATEDOCHTML.............................................................................................................................244
31.6.6. CREATEDOCNEW ...............................................................................................................................245
31.6.7. CREATEPROJDB..................................................................................................................................245
31.6.8. CREATEPROJFILE...............................................................................................................................245
31.6.9. CREATEPROJMPX ..............................................................................................................................245
31.6.10. CREATEPROJMSP ...............................................................................................................................246
31.6.11. CREATEPROJNEW ..............................................................................................................................246
31.6.12. CREATEPROJP3E ................................................................................................................................246
31.6.13. DOCAPPLYCOLUMNS .......................................................................................................................246
31.6.14. DOCAPPLYCURRPROJ.......................................................................................................................246
31.6.15. DOCAPPLYDOC ..................................................................................................................................247
31.6.16. DOCAPPLYPROJ..................................................................................................................................247
31.6.17. DOCAPPLYPROJTAB..........................................................................................................................247
31.6.18. DOCCLOSE...........................................................................................................................................248
31.6.19. DOCDBEXPORT ..................................................................................................................................248
31.6.20. DOCFILEEXPORT................................................................................................................................248
31.6.21. DOCHTMLEXPORT.............................................................................................................................248
31.6.22. DOCRUNFORMULA............................................................................................................................249
31.6.23. DOCSAVE .............................................................................................................................................249
31.6.24. DOCSAVEAS ........................................................................................................................................249
31.6.25. DOCSETKEYFIELD .............................................................................................................................249
31.6.26. DOCSETPROP ......................................................................................................................................249
31.6.27. DOCTEXTEXPORT..............................................................................................................................250
31.6.28. OPENDOC .............................................................................................................................................250
31.6.29. OPENPROJ ............................................................................................................................................250
31.6.30. PROJAPPLYREF...................................................................................................................................251
31.6.31. PROJAPPLYREFTAB...........................................................................................................................251
31.6.32. PROJCALCCOST..................................................................................................................................251
31.6.33. PROJCALCPROB..................................................................................................................................251
31.6.34. PROJCALCRES.....................................................................................................................................252
31.6.35. PROJCALCRISK...................................................................................................................................252
31.6.36. PROJCALCSCHED...............................................................................................................................252
31.6.37. PROJCALCSCHEDRES........................................................................................................................252
31.6.38. PROJCLOSE ..........................................................................................................................................252
31.6.39. PROJCOMPAREBASEPROJ ................................................................................................................252
31.6.40. PROJCOMPAREPROJ ..........................................................................................................................252
31.6.41. PROJCOPYPHASEASPROJ .................................................................................................................253
31.6.42. PROJDBEXPORT..................................................................................................................................253
31.6.43. PROJDELCOMPARE............................................................................................................................253
31.6.44. PROJDELPROB ....................................................................................................................................253
31.6.45. PROJDELRISK......................................................................................................................................253
31.6.46. PROJEVACALCPFOPER .....................................................................................................................253
31.6.47. PROJEVACALCPFPHASE...................................................................................................................254
31.6.48. PROJEVACALCPFWBS.......................................................................................................................254
31.6.49. PROJFILEEXPORT...............................................................................................................................254
31.6.50. PROJFOLDOPER ..................................................................................................................................254
31.6.51. PROJFOLDRES.....................................................................................................................................254
31.6.52. PROJIMPORTFACT .............................................................................................................................255
31.6.53. PROJINSPROJASPHASE .....................................................................................................................255
31.6.54. PROJINSPROJASPHASEDOWN.........................................................................................................255
31.6.55. PROJMAKEEVAREPOPER .................................................................................................................255
31.6.56. PROJMAKEEVAREPPHASE...............................................................................................................256
31.6.57. PROJMAKEEVAREPWBS...................................................................................................................256
31.6.58. PROJMAKESPENDREPDEPT .............................................................................................................256
31.6.59. PROJMAKESPENDREPDEPTPATT ...................................................................................................256
31.6.60. PROJMAKESPENDREPOBS ...............................................................................................................257
31.6.61. PROJMAKESPENDREPOBSPATT .....................................................................................................257
31.6.62. PROJMAKESPENDREPOPER.............................................................................................................257
31.6.63. PROJMAKESPENDREPOPERPATT...................................................................................................257
31.6.64. PROJMAKESPENDREPPHASE ..........................................................................................................258
31.6.65. PROJMAKESPENDREPPHASEPATT.................................................................................................258
ix
31.6.66. PROJMAKESPENDREPRES................................................................................................................258
31.6.67. PROJMAKESPENDREPWBS ..............................................................................................................258
31.6.68. PROJMAKETRENDREPASSIGN ........................................................................................................258
31.6.69. PROJMONITORAPPLY .......................................................................................................................259
31.6.70. PROJMONITORDBEXPORT ...............................................................................................................259
31.6.71. PROJMONITORDBIMPORT ...............................................................................................................259
31.6.72. PROJMONITORFILEEXPORT ............................................................................................................259
31.6.73. PROJMONITORFILEIMPORT.............................................................................................................259
31.6.74. PROJMPXEXPORT ..............................................................................................................................259
31.6.75. PROJMSPEXPORT ...............................................................................................................................260
31.6.76. PROJP3EEXPORT ................................................................................................................................260
31.6.77. PROJRUNFORMULATAB...................................................................................................................260
31.6.78. PROJSAVE ............................................................................................................................................261
31.6.79. PROJSAVEAS .......................................................................................................................................261
31.6.80. PROJSENDFTP .....................................................................................................................................261
31.6.81. PROJSETBASEPROJ ............................................................................................................................261
31.6.82. PROJSETCOMPARE ............................................................................................................................262
31.6.83. PROJSETCOMPARECOMMON ..........................................................................................................262
31.6.84. PROJSETCOMPARECOMMONALL ..................................................................................................262
31.6.85. PROJSETCOMPARECOST ..................................................................................................................262
31.6.86. PROJSETCOMPARECOSTALL ..........................................................................................................263
31.6.87. PROJSETCOMPARECOSTCENT........................................................................................................263
31.6.88. PROJSETCOMPARECOSTCENTALL ................................................................................................263
31.6.89. PROJSETCOMPAREMAT ...................................................................................................................263
31.6.90. PROJSETCOMPAREMATALL............................................................................................................263
31.6.91. PROJSETCOMPAREMATCENT .........................................................................................................263
31.6.92. PROJSETCOMPAREMATCENTALL .................................................................................................264
31.6.93. PROJSETEVAREP ................................................................................................................................264
31.6.94. PROJSETEVAREPCOMMON..............................................................................................................264
31.6.95. PROJSETEVAREPCOST......................................................................................................................264
31.6.96. PROJSETEVAREPCOSTCENT............................................................................................................265
31.6.97. PROJSETEVAREPMAT .......................................................................................................................265
31.6.98. PROJSETEVAREPMATCENT.............................................................................................................265
31.6.99. PROJSETGANTTOPER........................................................................................................................265
31.6.100. PROJSETGANTTRES...........................................................................................................................266
31.6.101. PROJSETMONITORFILEIMPORT......................................................................................................266
31.6.102. PROJSETMPXEXPORT .......................................................................................................................266
31.6.103. PROJSETOPTPROJ...............................................................................................................................267
31.6.104. PROJSETP3EEXPORT .........................................................................................................................267
31.6.105. PROJSETPESSPROJ .............................................................................................................................267
31.6.106. PROJSETPRECPROJ ............................................................................................................................267
31.6.107. PROJSETPROBPROJ............................................................................................................................268
31.6.108. PROJSETPROP......................................................................................................................................268
31.6.109. PROJSETRISK ......................................................................................................................................268
31.6.110. PROJSETRISKCOMMON ....................................................................................................................269
31.6.111. PROJSETRISKCOST ............................................................................................................................269
31.6.112. PROJSETRISKCOSTCENT..................................................................................................................269
31.6.113. PROJSETRISKMAT..............................................................................................................................269
31.6.114. PROJSETRISKMATCENT ...................................................................................................................270
31.6.115. PROJSETSCHED ..................................................................................................................................270
31.6.116. PROJSETSCHEDCOST ........................................................................................................................271
31.6.117. PROJSETSCHEDCOSTCENT ..............................................................................................................271
31.6.118. PROJSETSCHEDMAT..........................................................................................................................271
31.6.119. PROJSETSCHEDMATCENT ...............................................................................................................271
31.6.120. PROJSETSCHEDRES ...........................................................................................................................272
31.6.121. PROJSETSCHEDRESALL ...................................................................................................................272
31.6.122. PROJSETSPENDREP............................................................................................................................272
31.6.123. PROJSETSPENDREPADDCOLUMN..................................................................................................273
31.6.124. PROJSETSPENDREPCOLRESET........................................................................................................273
31.6.125. PROJSETSPENDREPCOMMON .........................................................................................................273
31.6.126. PROJSETSPENDREPCOMMONALL..................................................................................................274
31.6.127. PROJSETSPENDREPCOST .................................................................................................................274
31.6.128. PROJSETSPENDREPCOSTALL..........................................................................................................274
x
31.6.129. PROJSETSPENDREPCOSTCENT .......................................................................................................274
31.6.130. PROJSETSPENDREPCOSTCENTALL ...............................................................................................274
31.6.131. PROJSETSPENDREPMAT...................................................................................................................274
31.6.132. PROJSETSPENDREPMATALL ...........................................................................................................275
31.6.133. PROJSETSPENDREPMATCENT ........................................................................................................275
31.6.134. PROJSETSPENDREPMATCENTALL.................................................................................................275
31.6.135. PROJSETSPENDREPPAR....................................................................................................................275
31.6.136. PROJSETSPENDREPRES ....................................................................................................................276
31.6.137. PROJSETSPENDREPRESALL.............................................................................................................276
31.6.138. PROJSETSPENDREPRESCENT ..........................................................................................................276
31.6.139. PROJSETSPENDREPRESCENTALL ..................................................................................................276
31.6.140. PROJSETSPENDREPRESCENTCOMMON........................................................................................277
31.6.141. PROJSETSPENDREPRESCOMMON ..................................................................................................277
31.6.142. PROJSETSPENDRESET.......................................................................................................................277
31.6.143. PROJSETTRENDREPCOMMON.........................................................................................................277
31.6.144. PROJSETTRENDREPCOMMONALL .................................................................................................278
31.6.145. PROJSETTRENDREPCOST.................................................................................................................278
31.6.146. PROJSETTRENDREPCOSTALL .........................................................................................................278
31.6.147. PROJSETTRENDREPCOSTCENT ......................................................................................................278
31.6.148. PROJSETTRENDREPCOSTCENTALL...............................................................................................278
31.6.149. PROJSETTRENDREPMAT ..................................................................................................................278
31.6.150. PROJSETTRENDREPMATALL ..........................................................................................................279
31.6.151. PROJSETTRENDREPMATCENT........................................................................................................279
31.6.152. PROJSETTRENDREPMATCENTALL ................................................................................................279
31.6.153. PROJTABDBEXPORT..........................................................................................................................279
31.6.154. PROJTABDOCCOPY............................................................................................................................280
31.6.155. PROJTABFILEEXPORT.......................................................................................................................280
31.6.156. PROJTABHTMLEXPORT....................................................................................................................281
31.6.157. PROJTABTEXTEXPORT .....................................................................................................................282
31.6.158. PROJVERINC........................................................................................................................................283
31.6.159. RECEIVEPROJFTP ...............................................................................................................................283
31.6.160. SAVEALL..............................................................................................................................................283
31.6.161. SETCOPYPROJ.....................................................................................................................................283
31.6.162. SETCURRDOC......................................................................................................................................284
31.6.163. SETCURRPROJ.....................................................................................................................................284
31.6.164. SETDISTRPROJ ....................................................................................................................................284
31.6.165. SETDOCAPPLY....................................................................................................................................285
31.6.166. SETFILEEXPIMP..................................................................................................................................285
32. Signals ...................................................................................................................................... 285
32.1. Signals.............................................................................................................................................................285
32.2. Signals Table..................................................................................................................................................286
32.3. Signal Properties Dialog Window ................................................................................................................286
32.4. Interval Properties Dialog Window .............................................................................................................286
33. Group Work on the Project ................................................................................................... 288
33.1. Group Work on the Project..........................................................................................................................288
33.2. User Properties Dialog Window...................................................................................................................288
33.3. Add Users.......................................................................................................................................................289
33.4. Edit User Properties......................................................................................................................................289
33.5. Delete a User ..................................................................................................................................................289
34. Access Rights ........................................................................................................................... 291
34.1. Access Rights Properties Dialog Window ...................................................................................................291
34.2. User Identification.........................................................................................................................................292
34.3. Change Password Dialog Window ...............................................................................................................292
35. Project Portfolio ...................................................................................................................... 293
35.1. Project Portfolio ............................................................................................................................................293
35.2. Workıng with Project Portfolios ..................................................................................................................293
35.3. Project Portfolio Properties Dialog Window ..............................................................................................294
35.4. Project Properties in a Portfolio Dialog Window .......................................................................................294
xi
35.5. Resource Assignments to Projects ...............................................................................................................295
35.6. Project Registry Table ..................................................................................................................................295
35.7. Project Portfolios Shortcut Menu ................................................................................................................296
35.8. Multiproject Properties in a Portfolio Dialog Window..............................................................................296
35.9. Multiprojects in Portfolios Shortcut Menu .................................................................................................298
35.10. Project in a Portfolio Shortcut Menu ..........................................................................................................298
35.11. Project Gantt .................................................................................................................................................299
35.11.1. Project Gantt...........................................................................................................................................299
35.11.2. Project Gantt Options Dialog Window...................................................................................................299
35.11.3. Project Gantt Main Menu .......................................................................................................................300
35.11.4. Project Gantt Tools Panel.......................................................................................................................302
35.11.5. Workıng wıth Project Gantt Diagrams ...................................................................................................303
35.12. PBS .................................................................................................................................................................304
35.12.1. Hierarchical Structure of Projects...........................................................................................................304
35.12.2. PBS.........................................................................................................................................................304
35.12.3. Pbs Tools Panel ......................................................................................................................................305
35.12.4. Hierarchy of Projects Main Menu ..........................................................................................................305
35.12.5. Multiprojects in Hierarchy of Projects (PBS) Shortcut Menu ................................................................306
35.12.6. Projects Shortcut Menu in PBS ..............................................................................................................306
36. Data Export-Import................................................................................................................ 308
36.1. Import / Export from Files Dialog Window ................................................................................................308
36.2. Spider Project File Export into MPX-File Dialog Window .......................................................................309
36.3. Table Export Options Dialog Window ........................................................................................................309
36.4. Project Import-Export ..................................................................................................................................310
36.4.1. Create Project from Database .................................................................................................................310
36.4.2. Create Project from MS Project Database ..............................................................................................311
36.4.3. Create Project from Primavera P3E Database ........................................................................................311
36.4.4. Create Project from CSV and MPX Files...............................................................................................311
36.4.5. Export Project to Database .....................................................................................................................312
36.4.6. Export Project to Primavera P3e Database.............................................................................................312
36.4.7. Export Project to MS Project..................................................................................................................312
36.4.8. Export Project to CSV-Files...................................................................................................................313
36.4.9. Export Project to MPX-file ....................................................................................................................313
36.5. Document Import-Export.............................................................................................................................313
36.5.1. Create Document from Database............................................................................................................313
36.5.2. Import Document from File....................................................................................................................314
36.5.3. Export Project Table to Database ...........................................................................................................314
36.5.4. Exporting Tables into Files ....................................................................................................................315
36.6. Monitoring Data Import-Export..................................................................................................................315
36.6.1. Performance Data Import Options Dialog Window ...............................................................................315
36.6.2. Import Performance Data from Database ...............................................................................................315
36.6.3. Import Performance Data from Files......................................................................................................315
36.6.4. Export Performance Data to Database....................................................................................................316
36.6.5. Export Performance Data to Files ..........................................................................................................316
36.7. Working with Databases...............................................................................................................................316
36.7.1. Create Document from Database Dialog Window .................................................................................316
36.7.2. Create Project from Database Dialog Window.......................................................................................317
36.7.3. Export Project to Database Dialog Window...........................................................................................318
36.7.4. Export Document to Database Dialog Window .....................................................................................319
36.7.5. Export Performance Data to Database Dialog Window .........................................................................319
36.7.6. Import Performance Data from Database Dialog Window.....................................................................320
36.7.7. Export to Database .................................................................................................................................321
37. Exchange of Projects via the Internet ................................................................................... 323
37.1. Project Exchange Using Ftp-servers............................................................................................................323
37.2. Ftp-servers Setup...........................................................................................................................................323
37.3. Upload (Send) Project / Portfolio to Ftp-server..........................................................................................324
37.4. Import Project from Ftp-server ...................................................................................................................324
37.5. Filters for Projects on Ftp-server Dialog Window .....................................................................................326
37.6. Filters for Projects on Ftp-server Properties Dialog Window...................................................................326
xii
38. E-mail ....................................................................................................................................... 327
38.1. Send E-mail....................................................................................................................................................327
38.2. Sending E-mails Dialog Window..................................................................................................................327
39. Attached Documents ............................................................................................................... 328
39.1. Attach Document...........................................................................................................................................328
39.2. Attach Folder .................................................................................................................................................328
39.3. Insert Object Dialog Window.......................................................................................................................329
39.4. ‘OLE-object and Folder’ Standard Page ....................................................................................................329
40. Printing .................................................................................................................................... 331
40.1. Print Preview Window..................................................................................................................................331
40.2. Print Properties Dialog Window..................................................................................................................331
40.3. Print Templates .............................................................................................................................................332
40.4. Print Template Properties Dialog Window.................................................................................................332
40.5. Print Patterns Table......................................................................................................................................333
41. Options ..................................................................................................................................... 334
41.1. Spider Project Parameters Dialog Window ................................................................................................334
41.2. Color Setup Dialog Window.........................................................................................................................335
41.3. Color Selection Dialog Window ...................................................................................................................336
41.4. Object Color Dialog Window .......................................................................................................................336
41.5. Fonts Setup Dialog Window .........................................................................................................................336
41.6. Printer and Page Setup Dialog Window......................................................................................................337
41.7. Time Scale Dialog Window...........................................................................................................................338
41.8. Template Dialog Dindow ..............................................................................................................................338
41.9. Replication Options Dialog Window ...........................................................................................................339
41.10. Column Name Postfixes Setup .....................................................................................................................339
42. Miscellaneous........................................................................................................................... 341
42.1. Help ................................................................................................................................................................341
42.2. Priority ...........................................................................................................................................................341
42.3. Type ................................................................................................................................................................341
42.4. Float................................................................................................................................................................341
42.5. Keyboard Hot Keys .......................................................................................................................................342
42.6. Cursor Types .................................................................................................................................................343
42.7. Dialog Windows.............................................................................................................................................343
42.8. Text Object Dialog Window .........................................................................................................................343
42.9. Search and Replace Dialog Window............................................................................................................344
42.10. Mini-Calendar Dialog Window ....................................................................................................................345
42.11. ANSI Codes....................................................................................................................................................345
42.12. Journal of Actions .........................................................................................................................................345
42.13. Protocol Table................................................................................................................................................346
xiii
Main Window
1. Main Window
1.1.
Main Window
Main program window consists of three parts. Left part (Projects) contains icons, titles and version numbers of all opened
projects.
Window’s central part shows code and title of selected project and contains data and views of corresponding project. They
are basically grouped as:
Diagrams: Activity Gantt, Resource Gantt, WBS Chart, OBS Chart, Activity Network, Linear Diagram
Costs: Cost Components, Cost Centers, Cost Component Periods,
Activities: Activities, Links
Resources: Resources, Multi-resources, Resource skills, Resource Centers, Resource Periods, Overtiems, Resource
Production.
Assignments: Resource Assignments, Multi resource Assignments, Resource Skill Assignments, Team Assignments.
Materials: Materials, Material Centers, Material Periods, Material Sets.
Calendars: Calendars, Weeks, Calendar Exceptions.
Performance: Monitoring, Performance Archive.,
Group Work: Users, Access Rights,
Filters Formulae Scripts: Filters, Formulas, Scripts.
Templates: Report Templates, EVA Report Templates, Trend Report Templates, Print Templates, Variance Report
Templates.
Other: Passport, Corporate Reference-books,
Success Probability Trends, Variance Trends, Protocol of Actions, User Fields, Signals
If the current project is a portfolio of projects following items will also be available:
Diagrams: Project Gantt
Assignments: Resource Assignments to projects
Other:Project Register
Window’s right part (Documents) contains list of codes and titles of opened documents. Documents of different types
have specific icons.
To select a project or document click its name with a left mouse button. Icon of selected item will be highlighted with grey
color. Double click opens project or document in a new window.
To move between opened windows press F6 (go to next window) or Ctrl-F6 (go to previous window). F5 key maximizes
or restores active window size.
1
Main Window
Create Document –
New – creates new document file;
From File – creates document from CSV-files;
From Data Base – creates project from database;
Create Portfolio –
New – creates new portfolio file;
From CSV-Files – creates document from CSV-files;
From Data Base – creates project from database;
Open – invokes projects and documents dialog window, where you can select a file to open;
Download from FTP server – lets receive files from FTP server;
Save All – saves all opened projects and documents;
Script
Create – opens script creation dialog window to create edit and save scripts without opening a project or
document;
Execute from File – allows to choose and execute a previously saved script;
Execute Favourite Script – executes the script, which was previously created and chosen as favourite.
Exit – shuts down the program. If you have unsaved projects or documents, you will be prompted to save them (or
quit without saving, or cancel exit).
This menu also contains the list of documents and projects which were opened lately or working.
"P" symbol is put before projects and "d" symbol before documents
Options
Parameters – lets you customize Spider Project options in the options dialog window;
Colors – lets you customize colors in the colors dialog window;
Fonts – lets you customize fonts in the fonts dialog window;
Printer and Page – lets you customize paper size, orientation and margins in the page setup dialog window, as well
as to define default printer and sep its properties;
Log Setup – invokes log setup window.
Replication – opens a dialog window of replication properties, where you can set options for deletion of unused
project objects during copying and distribution of projects;
FTP-servers – lets you add, delete and edit ftp-server accounts properties.
Window
Close All – closes all opened documents and activates Main Window
2
Main Window
Cascade – arranges all opened projects and documents windows on the screen to make all of them visible even
partially.
Tile – arranges all opened projects and documents windows on the screen to make them no overlapping.
Next Window – makes next opened window active.
Previous Window – makes previous opened window active.
Maximize/Restore – maximizes opened window size on the screen or restores it to original size.
Maximize/Restore All – maximizes all opened windows size on the screen or restores them to original size.
Main Window – makes main window active.
List of opened projects and documents: project (or document) name; project (or document) code; for opened
projects – type of data window.
E.g
MyProject [Code1] Activity Gantt
Reference-book [Ref1]
3
Project
2. Project
2.1. Project Data
4
Project
5
Project
2. In any project window (except Linear Diagram) goto menu Project -> Save without Cost;
or
Invoke project shortcut menu on project icon (in left window area - Projects) in Main program window with a right
mouse button click and select Save without Cost;
3. You will be prompted to save current project version first. Press OK to save current project and continue or press
Cancel to stop action.
4. Projects and documents dialog window will appear (if you pressed OK on the previous step). Enter code and/or
version number of new project file and press OK.
You initial project will be saved without cost data to a new project version or with a new code.
When you press OK button, Activity Gantt diagram of new project will open.
By default new project contains:
- One work breakdown structure (with a status of Responsibility structure), consisting of one phase with one activity;
- One organizational breakdown structure (with a status of Responsibility structure), consisting of one department;
- One cost component;
- One calendar;
- Two weeks: blank and 40-hours working week;
- Project Data Date is equal to current time; target finish date equals to data dare plus one month (by default);
6
Project
- One user, ‘Project Administrator’ with ‘Administrator access rights’, corresponding to full access rights to all project
objects. Administrator access rights cannot be changed; and user ‘Project Administrator’ cannot be deleted.
You can create unlimited number of projects in Spider Project. Each project can have up to 676 versions (with the same
project code). If you need to have more than 676 project versions, the project code should be changed.
Note that: You cannot create a project with the same name and code as opened project.
7
Project
Project version being compared is called Current. Project version being compared with, is called Original.
Project comparison can be done in activity gantt or resource gantt by selecting items With Baseline or With Other Project
from Comparison menu.
If With Baseline is selected, active project will be compared with project baseline. When With Other Project option is
selected, projects and documents dialog window will be invoked to select code and version of the project being compared
with. Click OK to finalize selection.
The following Gantt table columns contain activities and assignments comparison results:
- Original Duration (Duration Hours [Original] column) is activity duration (or assignment activity duration) in original
version;
- Original Total Cost (Total Cost [Original] column) is activity cost (or cost of work of resource that has been assigned to
this activity) in original version;
- Original Resource Hours (Resource Hours [Original] column) are resource hours assigned to perform this activity in
original version;
- Original Start (Start [Original] column) is date the activity starts (or the date working period begins for resource
assigned to this activity) in original version;
- Original Finish (Finish [Original] column) is date the activity finishes (or date working period ends for resource
assigned to this activity) in original version;
- Original Volume (Volume [Original] column) is activity volume (or part of activity volume performed by resource) in
original version;
- OCWP (Original Cost of Work Performed) (OCWP) is activity cost in original version;
- OCV (Original Cost Variance) (OCV) is variance in actual activity cost in comparison with original version. It equals to
difference between OCWP and actual activity cost in current version (Total Cost [Actual] column)
- Completion Variance (Completion Variance, Days column) is difference between dates of ASAP activity (or assignment)
finish in current and original versions (in days);
- Start Variance, Days is the difference between dates of ASAP activity (or resource assigned) start in current and original
versions (in days);
- Duration Variance, Days is the difference between activity (or assigned resource work) duration in current and original
versions (in days).
If the listed columns are not seen, invoke Column shortcut menu, and select Show Columns. Fields available dialog window
will be invoked to select Comparison (on the right side). When the list of fields appears, select field(s) to be inserted into
table and click OK.
Materials cost and consumption can also be reflected in Gantt table. For this, select Materials on the right side of fields
available dialog window, and select Original as materials expense type below.
After comparison is finished, objects (phases, activities, departments, and resources) of original version are shown as gray
shadows in gantt charts.
While comparing projects, in this dialog window set up the activity fields, on which the comparison will be performed.
Select the group of fields, from the very left side of the dialog window, among the following ones: General, Cost
components, Cost centers, Materials, Material centers and Material sets. For each group, available fields' list will represent
the ones available within this group. First highlight the required fields (by which ones the comparison will be realized) and
then, include them, to the Fields for comparison list on the right, by using >> button. To remove any fields from the Fields
for comparison list, highlight them and, click << button.
To decide which group of fields will be involved in comparison, check on the object names in the list below the frame.
Comparison will not be performed by the objects that are checked off.
Show this window before comparison option sets up whether this dialog window will be shown before comparison is started.
If this option was checked off, select Comparison -> Comparison Setup from Gantt diagram menu to invoke this dialog
window.
8
Project
9
Project
If it is required only to change storage, without changing code and version, it is necessary to double click in Storage floor and
to choose the necessary storage from the opened list.
In Project Portfolio frame the portfolio whose structure includes the given project is selected by using Change button (only
Professional and Desktop versions support portfolios).
The project portfolio is underlined in given window to calculate the project schedule in view of other portfolio projects (for
this, in scheduling settings without resource restrictions dialog window and in scheduling settings with resource restrictions
dialog window it is necessary to include the corresponding option to Consider Portfolio Schedule).
Number of linked OLE-objects contains number of other applications documents attached to the project.
To set up minimum activity float, use Activity is critical if its float is not greater than… field. Minimum activity float makes
the activity critical, when reached. If you leave field empty or enter the value 0 (zero), all activities with no float will be
considered critical.
Code and name of manager, who opened active project are reflected in Current User field in the bottom of the dialog
window.
In Notify managers about works if less than … days left field, how many days before it is necessary to notify users at the
beginning and the end of phases to which manager is assigned can be set.
In Notify resources about works if less than … days left field, how many days before it is necessary to notify resources on the
beginning and end of activities to which they are assigned can be set.
If it is needed to Send notifications, it is necessary to choose corresponding item in activity gantt main menu or in the menu
of any other project representations. Before sending, it is necessary to make sure, that in user properties dialog window and in
resource properties dialog window, e-mail addresses of users, to whom notifications should be send, are set.
To edit the properties of a previously saved project, choose Project -> Properties from any project window or cause shortcut
menu on project pictogram in main program window and choose Properties.
Allows opening and saving documents and projects and contains the following fields and options:
Object group option: Projects or Documents. Each group contains storages by default.
Projects group contains the following storages:
- Working;
10
Project
Storage frame contains storages list. Each storage has its path to files (disk location). To change path, click Properties button
and edit storage properties in the invoked storage properties dialog window.
To create a new storage, use Add button. Storage properties dialog window will be invoked to select new storage’s name and
path to files.
Note that: properties dialog window will be opened automatically for newly created object only if you have selected to Open
properties for new created objects in the spider project parameters dialog window. Otherwise newly created object will be
saved with default parameters.
To delete storage, click Remove button. Files contained in the removed storage will not be deleted from the project. Standard
storages cannot be removed.
Type/Code/Name is the list of project or document codes and names.
Version/Date is the list of highlighted document’s / project’s versions and its last update dates.
Search allows finding projects or documents from list by realizing a search by code or name.
Reverse version order option allows sorting document / project version numbers in descending order.
Code is the text field with document/project code Code is a sequence of characters, unique for each document/project. Code
is made of letters, numbers, and special characters (#$%&@_-~) without spaces, and is case sensitive.
Version is the text field with document/project version.
Notes - text field to view comments to the highlighted document / project version (if there are any).
Close window on document opening option – if selected – closes the dialog window after Open button is clicked.
Open opens selected document / project from the highlighted storage.
11
Project
Delete deletes highlighted document / project from storage. Corresponding warning message will appear if the document is
already in use: Cannot delete project or document while it is open.
Close closes the dialog window without any changes in documents /projects.
Help invokes context help.
2.18. Storage
Storage is a directory where documents and projects are located. You can set up storage name and full path to files location in
storage properties dialog window for several storages.
For example, "Working" is the storage name and d:\spider\projects\ is the directory path to storage location. Alternatively,
\\host\d\Spider\archive where host is the computer name in local network, and Spider\archive reflects file location.
By default, the following standard storages exist in the software and can not be deleted:
- Working;
- Fragment Library;
- Centre;
- Reference-books;
- Reports; and
- Other.
Set up and edit storage properties in storage properties dialog window .
There is a Backup folder inside each storage. If Create Backup Copy option is activated in spider project parameters dialog
window, previous version of every project file will be saved in Backup folder with each file Save.
12
Project
13
Object
3. Object
3.1. Object
Spider Project works with different objects, such as activities, phases, resources, materials, links, cost components,
resource skills, multi-resources, and departments.
All objects have certain characteristics, or properties. E.g., activities are characterized by duration, name, code, links with
other activities, resources assigned to its execution. At the same time resource is characterized by activity it was assigned.
You can view and edit characteristics of objects in properties dialog windows, specific for object types. These dialog
windows can be generally called from shortcut menus (item Properties), that in turn are invoked with a right mouse button
click on the object (or in tables – on object row number).
With opened object dialog window properties, you can view properties of another object of the same type if you select
another one from the list. E.g., Materials Table contains a list of all materials; double click on one of them to open dialog
window of its properties; leaving dialog window opened click on another material from the list – dialog window will
display properties of material, selected last. Similarly, you can move between different activities properties’ dialog
windows in Activities Table, Activity Gantt and so on.
Dialog windows of object properties contain buttons OK, Cancel, Apply and Help:
- OK – applies changes made and closes dialog window;
- Cancel – allows to discard changes and close dialog window;
- Apply - applies changes made and leaves dialog window opened; it is useful if changes to several object are to be made;
- Help – displays current object help window.
14
Object
Type is a field selected by clicking Select type field button. Select from the list containing all selected type objects given in
the field below.
In By type frame, click All option if objects in the list on the left (for example, Resources in Resources selecting dialog
window) do not need to be sorted by type. Click Selected type only option to sort objects in the list so that only selected type
objects are shown.
In By filter frame, click All option if objects in the list on the left do not need to be filtered. And click Selected filter only
option to filter objects in the list through highlighted filter.
If both options are activated (when you select Selected type only and Selected filter only simultaneously) only objects fitting
both criteria will be shown in the list.
3.8. List
There are two types of lists in Spider Project Software: for single choices and for multiple choices of elements from the list.
15
Object
While highlighting elements in list, you will either be allowed to highlight only one element (single element highlighting) or
as many as you want (multiple elements highlighting).
To highlight multiple elements, left click element’s name in the list, as you would highlight a single element. In the lists,
allowing multiple element highlighting, all clicked elements will stay highlighted. In the list allowing single element
highlighting, highlighting will slide from one element to the other.
To cancel highlighting of the element, simply click once again on its name in the list.
3.9. List with Sort Option, List with Sort and Search Options
List with sort option is a list with objects sorted in alphabetical order (For example, Fields list, Objects list, etc.). All lists of
that type have Name and Code search options on the bottom . If you select Code option, objects in the list will be sorted by
codes, and if you select Name option, objects in the list will be sorted by names.
List with sort and search options is a list with sort option and a text field added in the bottom of it. To find an object in the
list, start typing its name in the Search text field. While text is being typed in, list will be automatically moving closer to
desired object name.
16
Spider Project User GuideProject Presentations
4. Project Presentations
4.1. Project Views
Project views allows project to be presented in following ways:
- Activity Gantt;
- Resource Gantt;
- WBS (Work Breakdown Structure);
- OBS (Organizational Breakdown Structure);
- Activity Network; and
- Linear Diagram.
Also an additional Project gantt exists in Spider project software to represent project portfolios.
17
Spider Project User GuideProject Presentations
You can add or delete resources in Resource Gantt: invoke shortcut menu with a right mouse button click on
corresponding resource row number and select New Resource or Delete. If you choose to add a new resource - resource
properties dialog window for this resource would appear. You can also add or delete departments: invoke shortcut menu
with a right mouse button click on corresponding department row number and select New Department or Delete. New
departments can be created on The Same Level of organizational breakdown structure (with respect to department where
shortcut menu was invoked) or One Level Lower (new department would become subordinate with respect to department
where shortcut menu was invoked)– select desired option from menu. If you choose to add new department - department
properties dialog window for this department would appear.
Editing phase and activities structure in Activity Gantt (i.e. work breakdown structure) is performed mostly the same way.
To add activity open shortcut menu with a right mouse button click on activity row number, choose New Activity, set
initial data in activities properties dialog window, and press OK. Default activity duration is 5 days, and default volume is
100 units. To delete activity click with a right mouse button on activity row number and choose Delete from the shortcut
menu. To add a phase open shortcut menu with a right mouse button click on phase row number, choose New Phase and
select position of new phase in WBS with respect to the current phase: One Level Lower or The Same Level. To delete a
phase click its row number with a right mouse button and choose Delete from the shortcut menu.
Note that: all activities of deleted phase will be also deleted from the project.
In graphic area of Activity Gantt links between activities are displayed with arrows from lower side of proceeding to upper
side of succeeding activities. Links of Start-Start and Start-Finish types are drawn from left sides of activity bars and links
of Finish-Finish and Finish-Start – from right sides. In graphic area of Activity Gantt, you can perform following actions:
- Establishing a new link between two activities. To do this, move mouse pointer to the bar of predecessor activity in
logical relationship between two activities. After cursor changes to cursor of link press left mouse button and
move cursor to the second (successor) activity and then release mouse button. link properties dialog window will
appear for a newly established link (only if you have selected to Open properties for new created objects in the Spider
Project Parameters Dialog window, Otherwise, new link will be saved with default parameters).
- Deleting or editing an existing link. To do this, move mouse pointer to the bar of predecessor activity in logical
relationship between two activities. After cursor changes to cursor of link press left mouse button and move
cursor to the second (successor) activity and release mouse button. Shortcut menu will be invoked for existing link.
This shortcut menu consists of two items: Properties – opens link properties dialog window, and Delete – removes
current link.
- Changing activity duration. To do this, move mouse pointer to the end of activity bar. After cursor changes to cursor of
duration, press left mouse button and change activity duration. This action can only be performed for activities of
Duration type.
- Set Start Not Earlier Than constraints on activity performance schedule (planned activity start date cannot be earlier
than the date set). Move mouse pointer to the beginning of activity; after cursor changes to not earlier than cursor press
left mouse button and move activity bar.
Gantt diagram graphic area heading represents the time scale, which can be edited in time scale dialog window, which is
invoked either by double click or right mouse click on it.
Mouse cursor changes its appearance in graphic area of Gantt diagram to following types of cursors:
- Not earlier than – on the left side of activity;
- Duration – on the right side of activity;
- Link (Spider) – on activity bar.
You can view, create and edit different centers from menu Project -> Data -> Material Centers / Resource Centers / Cost
Centers in corresponding tables (Material Centers Table, Resource Centers Table, and Cost Centers Table)
18
Spider Project User GuideProject Presentations
Different diagrams and histograms can be placed in the lower part of Gantt diagrams, e.g. resource work load diagram,
diagrams of costs and material consumption, earned value analysis diagrams, resource overloads bar, success probability
trends. Diagrams can be drawn for whole project or separate project phases and activities. Go to menu Reports -> General
reports -> Diagram to create diagram for whole project. Diagram details can be specified in opened Diagram settings
dialog window. To create diagram for selected phase or activity invoke corresponding shortcut menu with right mouse
button click on corresponding row number, select General reports -> Diagram and specify diagram details.
Success probability trends diagram and earned value analysis diagram can also be created for whole project or separate
project phases and activities: select menu Reports -> Success probability trends -> Diagram (or Reports -> Earned value
analysis -> Diagram).
You can customize view of created diagrams, edit content and delete diagrams. To perform these actions invoke diagram
shortcut menu with a right mouse button click on diagram and select:
- Properties – to customize view of created diagrams in properties dialog window;
- Contents – to specify content to display on the diagram in Diagram settings dialog window;
- Delete – to remove the diagram.
Note that: Opened baseline project version (if it was opened), should be saved, before creating earned value analysis
diagram.
Resource overloads bar is displayed for all resources of the whole project: select Reports -> Resource overloads bar.
See Reports for detailed description of reports in Gantt diagrams.
19
Spider Project User GuideProject Presentations
- Repeat Search / Replace - repeats search or replace with the settings of previously performed Search / Replace
starting from the next cell;
- Sort hierarchically by column - sorts rows by selected column in ascending order with existing phase hierarchy
taken into consideration.
Note that you would not be able to undo current action with standard Undo option! That's why we recommend to
generate WBS codes before you perform sorting in Gantt chart. In this case you would be able to restore original
phases and activities order according to WBS codes. To generate WBS codes goto menu Gantt -> Generate WBS
codes (in activity gantt or resource gantt).
- Filter by values filters the selected column by the selected fields among the frame Conditions on the right side of the
invoked box. Previous selected filters can be cancelled by clicking in the option box Cancel Previous Filter
- New field - creates new user field and opens Column properties dialog window
- Delete field - deletes field from internal database.
- Note that only user defined fields can be deleted.
Scaling tool is an interactive tool that smoothly changes scale for diagrams or any objects shown in graphic part of the
window. Scale icon is displayed on each window toolbar (in WBS , OBS and PBS toolbars, only if Tree type is selected).
To change the scale of diagram left click scale pointer and drag it to left or right. Alternatively, you can press to the left or
right arrow buttons on the Scaling tool to change the scale of your diagram. Minimum scale corresponds to the most left
pointer position and the maximum - corresponds to the most right.
Activity Gantt is the main project view where initial data on project activities, phases, and assignments can be entered.
Activity Gantt window opens first when you open or create project file.
By default new project contains following objects in Activity Gantt:
- One activity named ‘Activity 1’ with 5 days duration;
- One ‘No Name’ phase, including Activity 1.
You can change current work breakdown structure (WBS) of the project in WBS dialog window: select item Project from
the main menu and choose WBS.
Displayed structure contains all assigned resources, multi-resources, teams and resource skills to activities.
You can add, delete and convert activities and phases in Activity Gantt.
To add activity open shortcut menu with a right mouse button click on activity row number, choose New Activity, set
initial data in activities properties dialog window, and press OK. Default activity duration is 5 days, and default volume is
100 units. To delete activity click with a right mouse button on activity row number and choose Delete from the shortcut
menu. To convert an activity to phase, select Convert to Phase from the shortcut menu invoked for corresponding activity.
New phase will inherit former activity name and code (if the last one was unique) and contain former activity with
corresponding assignments.
Project phases can be added and deleted almost the same way as activities. To add a phase open shortcut menu with a right
mouse button click on phase row number, choose New Phase and select position of new phase in WBS with respect to the
current phase: One Level Lower or The Same Level. To delete a phase click its row number with a right mouse button and
choose Delete from the shortcut menu. Note that: all activities of deleted phase will also be deleted from the project. To
convert a phase to an activity (this action can be performed with a phase containing one activity only) select Convert to
Activity option from the shortcut menu invoked on phase row number. New activity will inherit name and code (if the last
one was unique) from the former phase and all assignments of activity comprising former phase.
20
Spider Project User GuideProject Presentations
logical relationship between two activities. After cursor changes to cursor of link press left mouse button and
move cursor to the second (successor) activity and then release mouse button. link properties dialog window will
appear for a newly established link (only if you have selected to Open properties for new created objects in the Spider
Project Parameters Dialog window; Otherwise, new link will be saved with default parameters and you can edit its
properties later).
- Deleting or editing an existing link. To do this move mouse pointer to the bar of predecessor activity in logical
relationship between two activities. After cursor changes to cursor of link press left mouse button and move
cursor to the second (successor) activity and release mouse button. Shortcut menu will be invoked for existing link.
This shortcut menu consists of two items: Properties – opens link properties dialog window, and Delete – removes
current link.
- Changing the duration of an activity. To do, this move the mouse pointer to the end of activity bar. After, the cursor
will change to cursor of duration, then press left mouse button and change activity duration. This action can be only
performed for activities of the Duration type.
- Set Start Not Earlier Than constraints on activity performance schedule (planned activity start date cannot be earlier
than the date set). Move mouse pointer to the beginning of activity; after cursor changes to not earlier than cursor press
left mouse button and move activity bar.
You can change Properties of activities, phases and assignments in Activity Gantt from the shortcut menu, invoked on
row number of corresponding object.
Description of possible actions, available in Activity Gantt and Resource Gantt see in Gantts diagram Description.
21
Spider Project User GuideProject Presentations
- Links;
- Milestones;
- Multi-Resources and Skills;
- Idle Assignments; checking this box hides assignments of resources and multi-resource not participating in activity
execution. ‘Idle’ means that the resource assignment has scheduled quantity (column Quantity [Scheduled]) and
remaining duration (column Duration, Hours [Remaining]) equal to zero. Idle assignments can exist in teams and
resource skills if resources were not assigned to activity execution after schedule calculation.
- All but assignments; checking this box hides all project phases and activities; only resources assignments would be
displayed. Phase and activity names are displayed in table area of Activity Gantt in columns Activity Name for the
report ‘Gantt of Assignments’ and Phase Name for the report ‘Gantt of Assignments’.
- OLE objects; icon defines whether documents of other applications (Word, Excel etc.) are attached to the
document. Double click on this field opens dialog window of corresponding object properties on OLE objects and
Folder page.
22
Spider Project User GuideProject Presentations
- Notes - A field that lets users to provide an object with notes and explanations. Double click on this field opens
corresponding object properties dialog window on Notes page.
- Short name – should an object have too long name, you can set shorter name as alternative to full name.
- Unique Assignment Code - Unique code, automatically generated according to activity code, resource code and
Assignment Index, connected by underline symbol;
- Assignment Index - editable number to be added to assignment Code to ensure its uniqueness to activity several times
(for example, the same resource as part of different resource skills or multi-resources assigned to activity).
- Manager – list of users’ codes, separated by commas. These managers participate in group work on the project
(distribution and consolidation of project phases and subphases);
- Start – activity start date or assigned resource work start date. If an activity has not actually started, this field would be
equal to Start [ASAP]. If activity is already being executed and performance data is added to monitoring, this field
would be equal to Start [Actual].
- Finish – activity finish date or assigned resource work finish date. If an activity has not actually finished, this field
would be equal to Finish [ASAP]. If activity has already been executed and performance data has been added to
monitoring, this field would be equal to Finish [Actual].
- Duration, Days [Remaining] – remaining activity duration or assigned resource work duration in days according to
calculated schedule; for phases: Duration, Days [Remaining] is a value calculated as phase Duration, Hours
[Remaining] divided by mean working day according to phase calendar;
- Duration, Hours [Remaining] – remaining activity duration or assigned resource work duration in hours according to
calculated schedule; for phases Duration, Hours [Remaining] is calculated since the start of first activity comprising
phase till the end of the last activity less duration of non-working periods.
- Duration, Hours [Actual] - total actual phase, activity or assigned resource work duration in hours according to
included performance data;
- Duration, Hours [Cumulative] – sum of actual and remaining activity duration or assigned resource work duration in
hours;
- Number of Working Days [Remaining] – a whole number of working days, required to complete activity (phase,
resource assignment) according to the current schedule calculated; the number of days is rounded up; a day is counted
as working if it contains at least one second of working time.
- Volume [Remaining] – remaining activity work volume or part of work to be performed by the resource.
- Volume [Actual] - actual work volume performed or part of work performed by the resource according to included
performance data;
- Volume [Cumulative] – sum of actual and remaining activity volume;
- Volume unit –activity units (e.g.,’m2’, ‘pieces’);
- Total Cost [Remaining] – remaining activity cost;
- Float, hours; Float, days – activity or resource assignment float duration in hours or days.
- Quantity [Scheduled] – estimated number of resources, required for activity execution;
- Quantity- user assigned number of resources for activity execution;
- Quantity [Minimal] – minimal number of resources assigned to activity execution; this value can be entered for
assignments with Variable quantity and Work load enabled in the assignment properties dialog window. Minimal
quantity value participates in calculation of resources quantity, assigned to activity (Quantity [Scheduled])
- Calendar –calendar code, according to which phase, activity is executed or resource is executing activity.
- Productivity – productivity of one resource unit per hour (i.e. number of activity volume units, that current resource can
execute per hour)
- Work Load – work load of one resource unit, assigned to activity execution. Work load is set in percent of resource
working time that the resource is to spend on activity execution. By default work load is equal to 100%.
- Work Load [Scheduled] – calculated work load coefficient for one resource unit, assigned to activity execution. If
resource is assigned to activity execution as part of multi-resource, its scheduled work load would be equal to resource
work load multiplied by multi-resource work load;
- Work Load [Minimal] – minimal work load coefficient for one resource unit, assigned to activity execution; this value
can be entered for assignments with Variable quantity and Work load enabled in the assignment properties dialog
window. Minimal Work Load value participates in calculation of resources quantity, assigned to activity (Work Load
[Scheduled])
- Total Duration of Teams, hours; Total Duration of Teams, days – total duration (in hours or days) of work time of all
teams, assigned to activity.
23
Spider Project User GuideProject Presentations
- Volume Percent [for Teams] – percent of activity work, performed by the team assigned;
- Priority – defines the order of phases and activities performance and resources assignment in resource constrained
scheduling. Activities and phases with higher priority (i.e., greater value) are performed earlier; resources with higher
priority are assigned earlier.
- Start [ASAP] (as soon as possible) – the earliest possible point in time on which activity can start or assigned resource
can start work, based on the network logic and any schedule constraints. ASAP Start dates can change as the project
progresses and changes are made to the project plan.
- Finish [ASAP] (as soon as possible) - the earliest possible point in time on which activity can finish or assigned
resource can finish work, based on the network logic and any schedule constraints. ASAP Finish dates can change as
the project progresses and changes are made to the project plan.
- Start [ALAP] (as late as possible) – the latest possible point in time on which an activity may begin or assigned
resource may start work without delaying the project finish date.
- Finish [ALAP] (as late as possible) – the latest possible point in time on which an activity can be completed or
assigned resource finish work without delaying the project finish date.
- Start [Actual], Finish [Actual] – activity (assigned resource work) actual start and finish dates according to included
performance data;
- Start [NET], Finish [NLT] –constraint on the start (not earlier than) and finish (not later than) dates of activity
execution. You can set or change dates in these fields by direct entering or in Calendar dialog window (invoked by
double click).
- Total Cost [Actual] - actual cost of work performed (or resource work) according to included performance data;
- Total Cost [Cumulative] – equals to actual cost plus remaining cost;
- Start [Critical], Finish [Critical], Total Cost [Critical] – critical activity (or phase, or assignment) start, finish dates
and total cost; these values are used in risk analysis;
- Start [Buffer], Finish [Buffer] – buffer values, used in risk analysis; buffer equals to difference between critical and
remaining (ASAP) values;
- Total Cost [Buffer] - difference between critical and remaining cost;
- Finish [Target], Total Cost [Target] – defined activity target finish date and total cost; these values are required for
estimation of probabilities in success probabilities calculation;
- Finish [Target Probability] – probability of completing the activity up to target finish date;
- Total Cost [Probability] - probability of meeting activity target total cost;
- Start [Original]; Finish [Original] – activity start and finish dates in original project version (see projects comparison
for details);
- Duration, Hours [Original]; Volume [Original]; Total Cost [Original] – activity duration (in hours), volume (in
corresponding units) and total cost in original project version (see projects comparison for details);
- Completion Variance, Days – difference in ASAP finish dates of current and original project versions’ activities (or
assignments) in days (see projects comparison for details);
- OCWP – Original Cost of Work Performed, cost of work performed according to original project version;
- OCV – Original Cost Variance, variance of performed work cost in comparison to original project version. Equals to
difference between OCWP and actual cost of work performed (Total Cost [Actual]);
- Resource-Hours [Remaining] – remaining planned volume of resource-hours of phases, activities and resource
assignments (in resource-hours). ‘Assignment resource-hours’ can be calculated as assignment duration multiplied by
resource work load and multiplied by the number of assigned resources. ‘Activity resource-hours’ can be calculated as
sum of all corresponding assignments’ resource-hours
- Resource-Hours [Actual] - actual volume of resource-hours of phases, activities and resource assignments (in resource-
hours).
- Resource-Hours [Cumulative] – sum of actual and remaining resource-hours;
- User defined fields;
- Fields with fixed, remaining and actual consumption of all materials (and material centers) and expenditures of cost
components (and cost centers); their profiles.
24
Spider Project User GuideProject Presentations
WBS – allows to switch between work breakdown structures, to create new and edit existing project WBS in
project structures list dialog window.
Properties – opens project properties dialog window for review and edit.
Passport – opens project passport window.
Data – contains list of project data. Selecting each item opens corresponding dialog window or table for review
and edit.
Views – contains list of project views.
Monitoring – opens monitoring table.
Send Notifications – sends the information about beginning and end of works in phases and activities, to managers
responsible for the phases and to assigned resources. The number of days, for which the managers and resources
should be informed before, must be defined in the project properties dialog window and in the user properties
dialog window and resource properties window. It is necessary to indicate e-mail addresses and to activate and
define the option to Notify managers / resources about works if less than…days left.
Next View, Previous View– lets move between left toolbar buttons, corresponding to project data and views.
Open (F12) – opens projects and documents dialog window;
Save (Ctrl +S)– saves project.
Save As – opens projects and documents dialog window; lets save opened project with different code, version
number or to different Storage folder.
Save Without Costs – saves project without costs data deleting activity, material and resource costs.
Check Data Integrity – achieves testing correctness and consistency of the information of project.
Create Standard Reference-Book – opens create standard reference-books dialog window , which allows creating
reference-books, on the basis of the calculated or actual information of the projects.
Export –
Into CSV-files – saves active project as text files of CSV format.
Into Data Base – saves active project to DBF file (see Project Export to Database for details);
Into MPX-file – saves active project to MPX file format .
Into MS Project – exports current project to MS Project and opens it;
Primavera database – exports current project to Primavera P3e database. Version 3 and Version 4 options
are available.
Upload to FTP-Server – opens FTP servers dialog window; select desired FTP server and press Send to send
project.
Send by E-mail – sends the current project via e-mail.
Close – closes current project file and removes project icon from the main window.
Gantt
Print Preview – opens print preview window.
Options – opens Activity Gantt diagram options dialog window, where you can customize diagram view in graphic
area.
Load Configuration – restores order of columns, their width in table area and time scale in graphic area from
configuration file (*.stc); all columns created by user (and not described in configuration file) in current project
will be hidden and can be unhidden later through Show Columns (Ins) command from the shortcut menu (invoked
with right mouse button click on columns name) or from main menu Edit item.
Save Configuration – saves order of columns, their width in table area and time scale in graphic area to
configuration file (*.stc).
Export Table to file – exports the table part of the Gantt diagram of activities into the CSV (Comma Separated
Value) type files or HTML.
Export Table to Data Base – exports table to data base.
Export Table to Excel – exports table to excel.
Export Table to CSV-file – exports to CSV or HTML file
Copy as a new Document – copies table of gantt as a new reference-book.
Edit
25
Spider Project User GuideProject Presentations
Calculations
Scheduling Options – opens dialog window where you can specify scheduling options.
Scheduling – performs schedule calculation not taking into account any existing resources constraints.
Resource Constrained Scheduling – performs resource constrained scheduling, i.e. taking into account availability
of required amount of resources, materials and financing.
Cost and Materials Calculation Options – calculates
Cost and Materials Calculation – calculates (recalculates) costs, materials requirements and resources work load
according to current schedule.
Calculations EVA Columns – calculates EVA and then displays calculated parameters values in corresponding
gantt columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding option
to Calculate EVA columns).
Calculations Resource Center Columns – calculates values in Resource Centers (Quantity) and Resource Centers
(Workload) columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding
option to Callculate columns in Resource Center frame).
Resource Peak Work Load - calculates (recalculates) resources work load on activities assignments.
Phase, Department and Resource Dates – calculates phases start and finish dates; calculates dates of work start and
finish for departments and resources.
Risk Analysis Options – opens dialog window where you can specify options of risk analysis.
Risk Analysis – performs risk analysis; risk analysis setup dialog window is invoked first.
26
Spider Project User GuideProject Presentations
Success Probability Calculation – opens dialog window (the same as in risk analysis) and performs probabilities
calculation of meeting target goals in Project Parameter Probability frame.
Recreate Success Probability Trends – recreates success probability trends on the set of projects selected in select
projects dialog window.
Hide Risk Analysis Results – undoes performed risk analysis.
Clear Success Probabilities Fields – clears data in field [Probability].
Report
Reports and Diagrams Templates:
Table – opens report templates list window where you can choose report template for table report.
Diagram – opens report templates list window where you can choose report template to create a diagram.
General Reports and Diagrams:
Table – creates report on the whole project data; opens Report settings dialog window.
Diagram – draws diagram on the whole project data in the lower part of Activity Gantt; opens Diagram
settings dialog window.
EVA Reports and Diagrams Templates:
Table – opens a dialog window with the list of EVA reports templates to choose the template on which the
new table report will be created
Diagram – opens a dialog window with the list of EVA reports templates to choose the template on which
the new diagram will be created
Earned Value Analysis:
Table – creates earned value analysis report; opens earned value analysis report properties dialog window
first.
Diagram – draws earned value analysis diagram in the lower part of Activity Gantt; opens earned value
analysis diagram properties dialog window first.
Success Probability Trends Templates:
Table – opens a dialog window with the list of Success probability trends reports templates to choose the
template on which the new table report will be created
Diagram – opens a dialog window with the list of Success probability trends reports templates to choose
the template on which the new diagram will be created
Success Probability Trends:
Table – creates success probability trends report on the whole project data; opens success probability
trends report properties dialog window first.
Diagram – draws success probability trends diagram in the lower part of Activity Gantt; opens success
probability trends diagram properties first.
Variance Trends Templates:
Table – opens a dialog window with the list of variance trends reports templates to choose the template on
which the new table report will be created
Diagram – opens a dialog window with the list of variance trends reports templates to choose the template
on which the new diagram will be created
Variance Trends:
Table – opens variance trends report settings dialog window to create a new table report for project.
Diagram – opens variance trends settings dialog window to create a new diagram for project.
Resource Overloads Bar – reflects the diagram of the Resource Overloads of the project (Searching for resource
overloads).
Resource Overloads Report – creates a table of report on the Resource Overloads. In the report besides the
overloaded resources activities to which these resources were assigned are also available to see.
Project Truncation – invokes the truncate project by period dialog window to set the period during which it is
necessary to obtain project truncation.
Comparison
With Baseline – performs comparison of opened project with its baseline project version.
27
Spider Project User GuideProject Presentations
With Other Project – performs comparison of opened project with another project selected in projects and
documents dialog window.
Recreate Variance Trends – recreates variance trends on the set of projects selected in select projects dialog
window.
Hide Comparison – undoes comparison.
Comparison Setup – opens dialog window and lets customize project comparison.
Window
Close All – closes all opened documents and activates Main Window
Cascade – arranges all opened projects and documents windows on the screen to make all of them visible even
partially.
Tile – arranges all opened projects and documents windows on the screen to make them no overlapping.
Next Window – makes next opened window active.
Previous Window – makes previous opened window active.
Maximize/Restore – maximizes opened window size on the screen or restores it to original size.
Maximize/Restore All – maximizes all opened windows size on the screen or restores them to original size.
Main Window – makes main window active.
List of opened projects and documents: project (or document) name; project (or document) code; for opened
projects – type of data window.
E.g.
MyProject [Code1] Activity Gantt
Reference-book [Ref1]
Resource Gantt diagram is a project view where working calendar of resources assigned to activities execution is
displayed.
You can switch between different organizational breakdown structures in Resource Gantt diagram: go to main menu and
select Project -> OBS, choose desired structure from the list in opened dialog window and press Switch to.
Bars displayed in graphic area of the diagram represent total resource and department work-time periods; bars start at
ASAP Start dates and finish at ASAP Finish dates.
28
Spider Project User GuideProject Presentations
You can add or delete resources in Resource Gantt: invoke shortcut menu with a right mouse button click on
corresponding resource row number and select New Resource or Delete. If you choose to add new resource - resource
properties dialog window for this resource would appear.
You can change assignments of a particular or several resources for another resource, multi-resource or resource skill. To
change assignments select appropriate resources, invoke shortcut menu and select Replace Assignment by option. Select
new assignment from the list of all assignments available. The list varies depending on selection you made: Resources,
Multi-Resources, or Resource Skills. To learn more, see Replacing Assignment.
You can also add or delete departments: invoke shortcut menu with a right mouse button click on corresponding
department row number and select New Department or Delete. New departments can be created on The Same Level of
organizational breakdown structure (with respect to department where shortcut menu was invoked) or One Level Lower
(new department would become subordinate with respect to department where shortcut menu was invoked)– select desired
option from menu. If you choose to add new department - department properties dialog window for this department would
appear.
To view or change properties of department, resource or assignments invoke shortcut menu with a right mouse button
click on corresponding object row number and select Properties or double click on corresponding object row number.
See Gantts diagrams Description for more details on available actions in Resource Gantt diagram.
29
Spider Project User GuideProject Presentations
might be different reasons for such situations. For example, if some resource in skill was assigned to an activity, but later
on was used for another activity with higher priority, this resource would be considered ‘idle’ for the activity.
- All but assignments – sets to show assignments only;
Keep as it is, if selected, keeps the same level of OBS.
- Keep as it is / Expand to:
- Assignments expands resource structure in resource gantt to assignments so that departments, resources, and
assignments are presented.
- Resources expands resource structure to resources, so that departments and resources are presented.
- Level activates field to enter presentation level number. If non-existing level is entered, a corresponding message
will appear.
Columns frame contains Default order and width option to set up default columns set.
To change height of rows you can define Number of rows in cells. If you select two and more rows per cell, additional
information (specified in field Data on Diagram of the frame Show) would be displayed above resources and department
bars.
Hierarchic indent size – lets you set indent in hierarchy of department, resources and assignments. 10 is set by default (2 -
20).
Time Scale Setup button opens time scale dialog window where you can set up the time frame for diagram presentation.
30
Spider Project User GuideProject Presentations
Upload to FTP-Server – opens FTP servers dialog window; select desired FTP server and press Send to send
project.
Send by E-mail – sends the current project via e-mail.
Close – closes current project file and removes project icon from the main window.
Gantt
Print Preview – opens print preview window.
Options – opens Activity Gantt diagram options dialog window, where you can customize diagram view in graphic
area.
Load Configuration – restores order of columns, their width in table area and time scale in graphic area from
configuration file (*.stc); all columns created by user (and not described in configuration file) in current project
will be hidden and can be unhidden later through Show Columns( Ins) command from the shortcut menu (invoked
with right mouse button click on columns name) or from main menu Edit item.
Save Configuration – saves order of columns, their width in table area and time scale in graphic area to
configuration file (*.stc).
Export Table to file – exports the table part of the resources Gantt into the CSV (Comma Separated Value) type
files or HTML.
Export Table to Data Base – exports table to data base.
Export Table to Excel – exports table to excel.
Export Table to CSV-file – exports to CSV or HTML file.delete
Copy as a new Document – copies table of gantt as a new reference-book.
Edit
Undo Last Action – undoes last action.
Protocol of Actions – opens protocol of actions table.
Formulae – opens dialog window to create, edit and apply of formulas.
Script
Create – opens Script dialog window where you can enter, edit and execute scripts;
Execute from File – lets you execute script stored in text file.
Execute– lets you execute a script from the list of previously created ones.
Execute Favourite Script– lets you execute the script, which was previously created and chosen as
favourite.
Show Columns –opens fields' list dialog window; lets you select hidden columns (fields) to display before active
one.
Hide Column – hides selected columns (these columns are not actually deleted from internal database).
Autofit All Columns – resizes all columns in order to make their contents available to be seen completely.
Search / Replace – opens Search dialog window and starts context string search;
Repeat Search / Replace – repeats search of context string starting current cell.
Copy – copies selected rows or cells to the clipboard.
Cut – puts selected rows or cells to the clipboard. Objects are actually deleted from Activity Gantt only after Paste
command.
Paste – inserts objects from the clipboard: to current work breakdown structure or to selected cell. You can Paste
copied (or cut) activities and phases to selected phase:
- One Level Lower – choose this option to insert phase as a subphase of the current phase (or activity of current
phase). New phase will be placed next to selected.
- The Same Level - choose this option to insert phase of the project on the same level of WBS as the selected
phase. Phase of the first level cannot be added.
Select all – selects all rows of Activity Gantt.
Filter
Apply – opens filters dialog window where you can create, edit and apply filters.
Filter by Selected Rows – allows filtering out contents of table by the selected rows from the filters dialog window.
31
Spider Project User GuideProject Presentations
Calculations
Scheduling Options – opens dialog window where you can specify scheduling options.
Scheduling – performs schedule calculation not taking into account any existing resources constraints.
Resource Constrained Scheduling – performs resource constrained scheduling, i.e. taking into account availability
of required amount of resources, materials and financing.
Cost and Materials Calculation Options – calculates
Cost and Materials Calculation – calculates (recalculates) costs, materials requirements and resources work load
according to current schedule.
Calculations EVA Columns – calculates EVA and then displays calculated parameters values in corresponding
gantt columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding option
to Calculate EVA columns).
Calculations Resource Center Columns – calculates values in Resource Centers (Quantity) and Resource Centers
(Workload) columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding
option to Callculate columns in Resource Center frame).
Resource Peak Work Load - calculates (recalculates) resources work load on activities assignments.
Phase, Department and Resource Dates – calculates phases start and finish dates; calculates dates of work start and
finish for departments and resources.
Risk Analysis Options – opens dialog window where you can specify options of risk analysis.
Risk Analysis – performs risk analysis; risk analysis setup dialog window is invoked first.
Success Probability Calculation – opens dialog window (the same as in risk analysis) and performs probabilities
calculation of meeting target goals in Project Parameter Probability frame.
Recreate Success Probability Trends – recreates success probability trends on the set of projects selected in select
projects dialog window.
Hide Risk Analysis Results – undoes performed risk analysis.
Clear Success Probabilities Fields – clears data in field [Probability].
Report
Reports and Diagrams Templates:
Table – opens report templates list window where you can choose report template for table report.
Diagram – opens report templates list window where you can choose report template to create a diagram.
General Reports and Diagrams:
Table – creates report on the whole project data; opens Report settings dialog window.
Diagram – draws diagram on the whole project data in the lower part of Activity Gantt; opens diagram
settings dialog window.
EVA Reports and Diagrams Templates:
Table – opens a dialog window with the list of EVA reports templates to choose the template on which the
new table report will be created
Diagram – opens a dialog window with the list of EVA reports templates to choose the template on which
the new diagram will be created
Earned Value Analysis:
Table – creates earned value analysis report; opens earned value analysis report properties dialog window
first.
Diagram – draws earned value analysis diagram in the lower part of Activity Gantt; opens earned value
analysis diagram properties dialog window first.
Success Probability Trends Templates:
Table – opens a dialog window with the list of Success probability trends reports templates to choose the
template on which the new table report will be created
Diagram – opens a dialog window with the list of Success probability trends reports templates to choose
the template on which the new diagram will be created
Success Probability Trends:
32
Spider Project User GuideProject Presentations
Table – creates success probability trends report on the whole project data; opens success probability
trends report properties dialog window first.
Diagram – draws success probability trends diagram in the lower part of Activity Gantt; opens success
probability trends properties dialog window first.
Variance Trends Templates:
Table – opens a dialog window with the list of variance trends reports templates to choose the template on
which the new table report will be created
Diagram – opens a dialog window with the list of variance trends reports templates to choose the template
on which the new diagram will be created
Variance Trends:
Table – opens variance trends report settings dialog window to create a new table report for project.
Diagram – opens variance trends diagram settings dialog window to create a new diagram for project.
Resource Overloads Bar – reflects the diagram of the Resource Overloads of the project (see Searching for
resource overloads).
Resource Overloads Report – creates a table of report on the Resource Overloads. In the report besides the
overloaded resources activities to which these resources were assigned are also available to see.
Project Truncation – invokes the truncate project by period dialog window to set the period during which it is
necessary to obtain project truncation.
Comparison
With Baseline – performs comparison of opened project with its baseline project version.
With Other Project – performs comparison of opened project with another project selected in projects and
documents dialog window.
Recreate Variance Trends – recreates variance trends on the set of projects selected in select projects dialog
window.
Hide Comparison – undoes comparison.
Comparison Setup – opens dialog window and allows to customize project comparison.
Window
Close All – closes all opened documents and activates Main Window
Cascade – arranges all opened projects and documents windows on the screen to make all of them visible even
partially.
Tile – arranges all opened projects and documents windows on the screen to make them no overlapping.
Next Window – makes next opened window active.
Previous Window – makes previous opened window active.
Maximize/Restore – maximizes opened window size on the screen or restores it to original size.
Maximize/Restore All – maximizes all opened windows size on the screen or restores them to original size.
Main Window – makes main window active.
List of opened projects and documents: project (or document) name; project (or document) code; for opened
projects – type of data window.
E.g.
MyProject [Code1] Activity Gantt
Reference-book [Ref1]
33
Spider Project User GuideProject Presentations
Technical Support E-Mail - allows sending an E-mail to address smt@spiderproject.ru via Outlook Express to
receive technical support.
Information and News – opens the internet address http://www.spiderproject.ru/aboutus_e.php via default internet
browser to access latest news and information about Spider Project Management Technologies.
Installation Instruction – shows installation instructions, minimum and optimum system requirements.
Spider Project Update Site – allows updating current version of software. Note that Program must be closed before
applying updates.
About – displays brief information about current Spider Project program version and Spider Management
Technologies.
- OLE objects; icon defines whether documents of other applications (Word, Excel etc.) are attached to the
document. Double click on this field opens dialog window of corresponding object properties on OLE objects and
Folder page.
- Notes - A field that lets users to provide an object with notes and explanations. Double click on this field opens dialog
window of corresponding object properties on Notes page.
- Short name – should an object have too long name, you can set shorter name as alternative to full name.
- Unique Assignment Code - Unique code, automatically generated according to activity code, resource code and
Assignment Index, connected by underline symbol;
- Assignment Index - editable number to be added to assignment Code to ensure its uniqueness to activity several times
(for example, the same resource as part of different resource skills or multi-resources assigned to activity).
- Start –resource work start date. If an activity has not actually started, this field would be equal to Start [ASAP]. If
activity is already being executed and performance data is added to monitoring, this field would be equal to Start
[Actual].
- Finish –resource work finish date. If an activity has not actually finished, this field would be equal to Finish [ASAP]. If
activity has already been executed and performance data has been added to monitoring, this field would be equal to
Finish [Actual].
- Duration, Days [Remaining] – remaining resource work duration in days according to calculated schedule;
- Duration, Hours [Remaining] – remaining resource work duration in hours according to calculated schedule;
- Number of Working Days [Remaining] – a whole number of working days, required to complete department or
resource assignment work according to the current schedule calculated; the number of days is rounded up; a day is
counted as working if it contains at least one second of working time.
- Duration, Hours [Actual] - total resource work duration in hours according to included performance data;
- Duration, Hours [Cumulative] – sum of actual and remaining resource work duration in hours;
- Volume [Remaining] – remaining part of work to be performed by the resource.
- Volume [Actual] - actual part of work performed by the resource according to included performance data;
- Volume [Cumulative] – sum of actual and remaining activity volume;
34
Spider Project User GuideProject Presentations
35
Spider Project User GuideProject Presentations
- OCV – Original Cost Variance, variance of performed work cost in comparison to original project version. Equals to
difference between OCWP and actual cost of work performed (Total Cost [Actual]);
- Resource-Hours [Remaining] – remaining planned volume of resource-hours of resource assignments (in resource-
hours). ‘Assignment resource-hours’ can be calculated as assignment duration multiplied by resource work load and
multiplied by the number of assigned resources. ‘Activity resource-hours’ can be calculated as sum of all
corresponding assignments’ resource-hours
- Resource-Hours [Actual] - actual volume of resource-hours of resource assignments (in resource-hours).
- Resource-Hours [Cumulative] – sum of actual and remaining resource-hours;
- User defined fields;
- Fields with fixed, remaining and actual consumption of all materials (and material centers) and expenditures of cost
components (and cost centers); their profiles.
4.3.1. WBS
Each level has its own background color, which can be changed from main program window by clicking Colors icon on
the toolbar. Color setup dialog window will be invoked to select Gantt Hierarchy (background) from Group list on the left
and change the colors of corresponding levels from Item lists.
Phases contain sub-phases. All same-level sub-phases are located in one row with the corresponding parent phase located one
level above and centered relatively to its sub-phases. Arrows are drawn from the parent phase to its sub-phases.
To move phase within a level, drag and drop phase box to its new location.
Double clicking on the phase box invokes phase properties dialog window.
Edit diagram layout in diagram options dialog window, invoked by selecting item Options from Diagram menu. Set up
graphical presentation of WBS (Type) - Hierarchy or Tree.
When As Is field is selected, graphical presentation will be presented as it exists .If level of detail for the presentation is
needed to be defined, enter the lowest level number (to be presented in diagram), after selecting To Level option. For
example, if ‘2’ is entered, phases of 1st and 2nd levels will be shown.
Phase shortcut menu, which can be invoked by right clicking on it, contains the following options:
- Properties; to edit phase properties
- Reports and Diagrams Templates; to create general reports(on templates) for phases
- General Reports and Diagrams; to create general reports for phases
- New Phase to add a new phase one level lower or of the same level; and
- Delete to delete the phase.
36
Spider Project User GuideProject Presentations
37
Spider Project User GuideProject Presentations
Reference-book [Ref1]
Allows setting up WBS type, and lowest structure detail level of presentation in OBS (Organizational Breakdown Structure)
WBS (Work Breakdown Structure) or PBS (Project Breakdown Structure)
Select between Hierarchy and Tree options.
In To Level field enter the lowest level number to be presented in diagram. For example, if ‘2’ is entered, only phases of 1st
and 2nd levels will be shown. If ‘0’ is entered, all structure levels will be shown)
4.4.1. OBS
OBS displays organizational resource structure. Each department is represented by a rectangle with information specified
in the template. To view (edit) OBS template in template dialog window press Template button on the toolbar or select
menu Diagram -> Template.
Departments are displayed according to organizational hierarchy and are connected by arrows; colors of rectangles
represent departments’ level. You can define colors in dialog window from main program window menu Options ->
Colors.
Double click on department’s rectangle opens its properties dialog window; right mouse button click invokes shortcut
menu. To select (highlight) several departments press and hold Ctrl button and click with left mouse button on desired
departments’ rectangles.
To change order of departments of the same level point to department rectangle with left mouse button and drug it to new
location.
38
Spider Project User GuideProject Presentations
You can display all departments or departments up to certain level: press Options button on the toolbar (or select menu
Diagram -> Options) and specify the largest departments’ level to display (zero displays all departments).
39
Spider Project User GuideProject Presentations
Execute from File – lets you execute script stored in text file.
Execute– lets you execute a script from the list of previously created ones.
Execute Favourite Script– lets you execute the script, which was previously created and chosen as
favourite.
Show Columns –opens fields' list dialog window; lets you select hidden columns (fields) to display before active
one.
Hide Column – hides selected columns (these columns are not actually deleted from internal database).
Autofit All Columns – resizes all columns in order to make their contents available to be seen completely.
Search / Replace – opens Search dialog window and starts context string search;
Repeat Search / Replace – repeats search of context string starting current cell.
Copy – copies selected rows or cells to the clipboard.
Cut – puts selected rows or cells to the clipboard. Objects are actually deleted from Activity Gantt only after Paste
command.
Paste – inserts objects from the clipboard: to current work breakdown structure or to selected cell. You can Paste
copied (or cut) activities and phases to selected phase:
- One Level Lower – choose this option to insert phase as a subphase of the current phase (or activity of current
phase). New phase will be placed next to selected.
- The Same Level - choose this option to insert phase of the project on the same level of WBS as the selected
phase. Phase of the first level cannot be added.
Select all – selects all rows of Activity Gantt.
Filter
Apply – opens dialog window where you can create, edit and apply filters.
Filter by Selected Rows – allows filtering out contents of table by the selected rows from the filter dialog window
Restore – abolishes the action of the used filter.
Calculations
Scheduling Options – opens dialog window where you can specify scheduling options.
Scheduling – performs schedule calculation not taking into account any existing resources constraints.
Resource Constrained Scheduling – performs resource constrained scheduling, i.e. taking into account availability
of required amount of resources, materials and financing.
Cost and Materials Calculation Options – calculates
Cost and Materials Calculation – calculates (recalculates) costs, materials requirements and resources work load
according to current schedule.
Calculations EVA Columns – calculates EVA and then displays calculated parameters values in corresponding
gantt columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding option
to Calculate EVA columns).
Calculations Resource Center Columns – calculates values in Resource Centers (Quantity) and Resource Centers
(Workload) columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding
option to Callculate columns in Resource Center frame).
Resource Peak Work Load - calculates (recalculates) resources work load on activities assignments.
Phase, Department and Resource Dates – calculates phases start and finish dates; calculates dates of work start and
finish for departments and resources.
Risk Analysis Options – opens risk analysis dialog window where you can specify options of risk analysis.
Risk Analysis – performs risk analysis; risk analysis setup dialog window is invoked first.
Success Probability Calculation – opens a dialog window (same as in risk analysis) and performs probabilities
calculation of meeting target goals in Project Parameter Probability frame.
Recreate Success Probability Trends – recreates success probability trends on the set of projects selected in select
projects dialog window.
Hide Risk Analysis Results – undoes performed risk analysis.
Clear Success Probabilities Fields – clears data in field [Probability].
Report
40
Spider Project User GuideProject Presentations
41
Spider Project User GuideProject Presentations
Cascade – arranges all opened projects and documents windows on the screen to make all of them visible even
partially.
Tile – arranges all opened projects and documents windows on the screen to make them no overlapping.
Next Window – makes next opened window active.
Previous Window – makes previous opened window active.
Maximize/Restore – maximizes opened window size on the screen or restores it to original size.
Maximize/Restore All – maximizes all opened windows size on the screen or restores them to original size.
Main Window – makes main window active.
List of opened projects and documents: project (or document) name; project (or document) code; for opened
projects – type of data window.
E.g.
MyProject [Code1] Activity Gantt
Reference-book [Ref1]
Allows setting up WBS type, and lowest structure detail level of presentation in OBS (Organizational Breakdown Structure)
WBS (Work Breakdown Structure) or PBS (Project Breakdown Structure)
Select between Hierarchy and Tree options.
In To Level field enter the lowest level number to be presented in diagram. For example, if ‘2’ is entered, only phases of 1st
and 2nd levels will be shown. If ‘0’ is entered, all structure levels will be shown)
42
Spider Project User GuideProject Presentations
Activity Network displays phases and activities according to current work breakdown structure. You can change current
WBS in project structures dialog window: choose menu Project -> WBS and select desired structure to be displayed.
Each activity is displayed as a box (you can customize color and shape of activities boxes through shortcut menu invoked
with right mouse button click on corresponding boxes). To move activity bar across diagram click with left mouse button
on the grey rectangle in the upper part of bar and drag it to desired place.
Completed activities are dashed crosswise, while partially completed activities are crossed from upper left to lower right
bar angle.
Activity links are displayed as arrows. Outdoing links are drawn from upper sides of activity bars and incoming – to lower
sides of bars. Links from start and to start of activities are drawn from left sides of activities bars; links from finish and to
finish of activities are drawn from right sides of activities bars.
To display project phases on Activity Diagram press Show WBS button on the toolbar (or select menu Diagram -> Show
WBS). Phases are displayed as rectangles with corresponding activities inside.
To move phase bar across diagram click with left mouse button on phase name and drag it to desired place.
Moved phases and activities are positioned across the grid, which can be displayed pressing Show / Hide Grid button (or
select menu Diagram -> Options and check Show Grid box).
To highlight one or several activities click on desired activities with left mouse button keeping Ctrl keyboard button
pressed. Multiple clicks highlight or undo highlight of activity bar.
To move activity from one phase to another first enable phase display (press Show WBS button on the toolbar or select
menu Diagram -> Show WBS), then select activity by left mouse button (point to rectangle in the upper bar part) with Shift
keyboard button pressed, drag with mouse cursor to desired phase and release Shift and mouse buttons.
Double click on activity bar (or phase) invokes activity properties dialog window (or phase properties dialog window)
43
Spider Project User GuideProject Presentations
- To establish new link between activities perform a left click with mouse on preceding activity and keep mouse button
pressed until succeeding activity. Later you can specify link properties in opened dialog window. To edit or delete link
repeat this action (as if you wished to create link) and select from opened shortcut menu Properties or Delete. Note that
properties dialog window will be opened automatically for newly created object only if you have selected to Open
properties for new created objects in the Spider Project Parameters Dialog window. Otherwise, newly created object
will be saved with default parameters and you can edit them later
You can create or delete phases, subphases and activities in Activity Network diagram:
- To create new phase activity invoke phase shortcut menu with a right mouse button click on corresponding phase
name, select New Activity set properties in opened activity properties dialog window and press OK.
Note that properties dialog window will be opened automatically for newly created object only if you have selected to
Open properties for new created objects in the Spider Project Parameters Dialog window. Otherwise, newly created
object will be saved with default parameters and you can edit them later
- To create subphase inside phase invoke phase shortcut menu with a right mouse button click on corresponding phase
name, select New Phase, set properties in opened phase properties dialog window and press OK.
- To delete phase, subphase or activity invoke shortcut menu on corresponding object and select Delete.
You can customize the view of an Activity Network diagram:
- To specify colors of activity bars and phase rectangles select shortcut menu Color for corresponding object;
- To change shape of activities bars select Shape from shortcut menu of the corresponding object by right clicking on it.
- Main menu Diagram -> Template opens template dialog window and lets you customize text displayed in activities
bars.
- To hide or display activities on diagram press Show/Hide Activities button on the toolbar.
- To hide or display phases on diagram press Show/Hide Phases button on the toolbar.
- You can quickly find and highlight desired activity: press Highlight button on the toolbar –activities list dialog window
will open and let you choose activities (highlight on diagram). Selected activity will be positioned in the center of
diagram window. Button Cancel Highlight undoes selection of activities.
-
44
Spider Project User GuideProject Presentations
Into Data Base – saves active project to DBF file (see Project Export to Database for details);
Into MPX-file – saves active project to MPX file format .
Into MS Project – exports current project to MS Project and opens it;
Primavera database – exports exports current project to Primavera P3e database. Version 3 and Version 4
options are available.
Upload to FTP-Server – opens dialog window of FTP servers; select desired FTP server and press Send to send
project.
Send by E-mail – sends the current project via e-mail.
Close – closes current project file and removes project icon from the main window.
Diagram
Print Preview – opens print preview window.
Options – opens Activity Network options dialog window, where you can specify details of diagram, level of
activities to be displayed.
Template – opens template dialog window and lets you customize text displayed in activities windows.
Activities Only – displays only project activities and hides corresponding phases.
Dispose Activities by WBS – arranges activities according to current work breakdown structure. Corresponding
phases become hidden.
Show WBS – displays complete work breakdown structure, including phases and activities.
Edit
Undo Last Action – undoes last action.
Protocol of Actions – opens protocol of actions table.
Highlight – opens activities list dialog window and lets you choose which activities will be selected (highlighted on
diagram). Selected activity will be positioned in the center of diagram window.
Cancel Highlight – undoes selection of activities.
Filter
Apply – opens dialog window where you can create, edit and apply filters.
Filter by Selected Rows – allows filtering out contents of table by the selected rows from the filters dialog window.
Restore – abolishes the action of the used filter.
Window
Close All – closes all opened documents and activates Main Window
Cascade – arranges all opened projects and documents windows on the screen to make all of them visible even
partially.
Tile – arranges all opened projects and documents windows on the screen to make them no overlapping.
Next Window – makes next opened window active.
Previous Window – makes previous opened window active.
Maximize/Restore – maximizes opened window size on the screen or restores it to original size.
Maximize/Restore All – maximizes all opened windows size on the screen or restores them to original size.
Main Window – makes main window active.
List of opened projects and documents: project (or document) name; project (or document) code; for opened
projects – type of data window.
E.g
MyProject [Code1] Activity Gantt
Reference-book [Ref1]
45
Spider Project User GuideProject Presentations
Is invoked by clicking Options icon on activity network toolbar or by selecting Options from Diagram menu in Activity
Network and allows setting up options for Activity Network presentation. It contains the following options and fields:
- Show Activities, Show Phases, and Show Grid - buttons to select whether activities, phases, and grid will be shown in
Activity Network window.
- Show Level sets up level of presentation for the main structure phase. With number increased, structure is shown one
level deeper. Show Level can be defined in WBS view only.
- Compress option, switched on, locates phases and activities the way so there is no space between them.
46
Spider Project User GuideProject Presentations
In horizontal direction, activities are presented in diagram according to links between them. Each activity is moved by one
grid step from its preceding activities. In vertical direction, activities are moved down by one grid step from each other and
are presented in diagram according to their order in project activities list.
Dispose Activities by WBS
In horizontal direction, activities are presented the same way as in Activities Only. In vertical direction, activities are
presented in accordance with their belonging to phases. Main phase activities are shown first. Activities of main phase sub-
phases are shown one grid step lower and so on.
Show WBS
In horizontal direction, activities are presented the same way as in Activities Only, but they are included into rectangles each
representing phase. The rectangles are spread out vertically according to phases’ relative connection.
Note That: Same-level phases of are not located on one horizontal level, but are shifted in vertical direction.
Sets up level of presentation of phases in Activity Network and contains Show Level field and Compress option.
Enter level number in Show Level field. With number increased, structure is shown one level deeper. Show Level can be
defined in WBS view only.
Compress option, switched on, locates phases and activities the way so there is no space between them.
Allows editing shapes of graphical elements in activity network or links diagram, and contains the following:
- List of shapes is choice of three shapes to graphically present activity in diagram: rectangle, oval, and octahedron. After
clicking OK button, all highlighted elements will be changed to the selected shape.
- Default sets up activity shape (rectangle by default in Activity Network).
47
Spider Project User GuideProject Presentations
Is a compact and clear way to present project execution schedule. This option is unique for Spider Project Software. Diagram
clearly shows completion dependence on certain activity types according to their position in project metric.
Project metric is shown on X-axis [Metric] (in horizontal direction) of Linear Diagram and time is shown on Axis Y [Time]
(in vertical direction). Linear Diagram contains two parts:
- Diagram of dependence of activities dates from their location in project metric (top part of diagram); and
- Location of different activities types in project metric (bottom part).
Project metric is set up by user. Usually these are user-defined fields setting up work start and finish dates. Set up project
metric in linear diagram options dialog window.
If linear diagram has already been set up for open project, invoke Linear Diagram Options dialog window by clicking
Options icon on Linear Diagram toolbar or by selecting Options from Diagram menu in Linear Diagram window.
If linear diagram has not been set up yet, double click on Linear Diagram icon in main program window to invoke Linear
Diagram Options dialog window.
48
Spider Project User GuideProject Presentations
Linear Diagram Options dialog window allows selecting activities types. Select activity or phase types to be presented in the
diagram in Not Shown list and using >> button to move them to Shown list.
Move types in the opposite direction, from Shown to Not Shown list, by using << button. Switch between Activity Types and
Phase Types by selecting corresponding option above the lists.
Any activity or phase field can be used as Type field. By default, standard type field is used as Type field. Select field to be
Type field from a drop-down list in Field Used as Type field.
To import type names from reference-books with matching Type and TypeName fields, click Names from Reference-book.
Select line type and line color to represent highlighted activity or phase type in Linear Diagram by selecting desired line type
directly in Linear Diagram Options dialog window and desired color in the invoked Color dialog window.
Select dates and metric interval for Linear Diagram. If Whole Project option is selected, dates and metric interval will be set
up automatically.
Time per second field is intended for setting up diagram’s animation speed. Animation starts with click on Animate icon
on Linear Diagram toolbar. Animation builds the diagram according to project schedule and shows project execution in time.
When a rectangle with the left mouse button is drawn in diagram window, the selected area will be enlarged to the size of the
window to allow viewing any project part in detail. To come back to original diagram presentation, click Default Scale
icon on the toolbar.
49
Spider Project User GuideProject Presentations
Open – invokes projects and documents dialog window for browsing and opening projects or documents, saved on
disks.
Save – saves project.
Save as – opens projects and documents dialog window; lets save opened project with different code, version
number or to different Storage folder.
Save Without Costs – saves project without costs data, deleting activity, material and resource costs.
Check Data Integrity – achieves testing correctness and consistency of the information of project.
Create Standard Reference-Book – opens create standard reference-books dialog window , which allows creating
reference-books, on the basis of the calculated or actual information of the projects.
Export –
Into CSV-files – saves active project as text files of CSV format.
Into Data Base – saves active project to DBF file (see Project Export to Database for details);
Into MPX-file – saves active project to MPX file format .
Into MS Project – exports current project to MS Project and opens it;
Primavera database – exports current project to Primavera P3e database. Version 3 and Version 4 options
are available.
Upload to FTP-Server – opens dialog window of FTP servers; select desired FTP server and press Send to
send project.
Send by E-mail – sends the current project via e-mail.
Close – closes current project file and removes project icon from the main window.
Diagram
Print Preview – opens print preview window.
Options – opens linear diagram options dialog window, where you can customize diagram view.
Edit
Undo Last Action – undoes last action.
Protocol of Actions – opens protocol of actions table.
Default Scale – restores default scale of linear diagram;
Animate / Pause – starts / pauses displaying dynamics of project progress.
Window
Close All – closes all opened documents and activates Main Window
Cascade – arranges all opened projects and documents windows on the screen to make all of them visible even
partially.
Tile – arranges all opened projects and documents windows on the screen to make them no overlapping.
Next Window – makes next opened window active.
Previous Window – makes previous opened window active.
Maximize/Restore – maximizes opened window size on the screen or restores it to original size.
Maximize/Restore All – maximizes all opened windows size on the screen or restores them to original size.
Main Window – makes main window active.
List of opened projects and documents: project (or document) name; project (or document) code; for opened
projects – type of data window.
E.g.
MyProject [Code1] Activity Gantt
Reference-book [Ref1]
50
Spider Project User GuideProject Presentations
Project Scheduling Technique - opens a PDF document, which provides help about Project Scheduling techniques
written by V.I.Liberzon.
Data Base Structure - opens a PDF document with the list of tables and communications between them.
Technical Support E-Mail - allows to send an E-mail to address smt@spiderproject.ru via Outlook Express to
receive technical support.
Information and News – opens the internet address http://www.spiderproject.ru/aboutus_e.php via default internet
browser to access latest news and information about Spider Project Management Technologies.
Installation Instruction – shows installation instructions, minimum and optimum system requirements.
Spider Project Update Site – allows updating current version of software. Note that Program must be closed before
applying updates.
About – displays brief information about current Spider Project program version and Spider Management
Technologies.
Allows setting up linear diagram properties and contains the following options:
- Activity Types and Phase Types options allow selecting whether activity types or phase types will be shown in Not Shown
and Shown lists below.
- Field used as type is drop-down list of activity types to select a type to be used as Type field.
- Not Shown list contains all activities or phases not reflected in Linear Diagram.
- Shown list contains all activities or phases reflected in Linear Diagram.
- >> and << buttons allow moving activities or phases between Shown and Not Shown lists. Highlight the phases to be
moved with left mouse button click and use >> and << buttons to move them between lists.
- Names from Reference-book button selects field types importing from document where Type and TypeName fields exist.
- Appearance frame contains:
- Name field reflects activity or phase name highlighted in Shown list.
- Line Type choice and Color choice set up line type and line color of highlighted activity or phase presentation in
Linear Diagram.
51
Spider Project User GuideProject Presentations
- Animation frame contains Time per second drop-down list allowing selecting project time to correspond to one second of
animated project presentation.
- Axis Y [Time] frame contains From and To text fields to set up project time interval to be reflected on diagram vertical
axis Y. Double click in the fields invokes mini-calendar dialog window to set date and time. If whole project is desired to
be reflected in Linear Diagram, click Whole Project button. Time interval will be calculated automatically.
- Activity field for X-axis frame contains Start and End drop-down lists of all user-defined activity fields from activities
table to set up start and finish points for all lines in Linear Diagram.
- X-axis [Metric] frame contains From and To text fields to set up project metric interval to be reflected on diagram
horizontal X-axis. Setup button invokes X-axis setup dialog window.
- OK closes the dialog window saving all the changes made.
- Cancel closes the dialog window without saving the changes.
- Help invokes context help.
Allows seeing how Linear Diagram will look on paper when printed. The following buttons are displayed on the toolbar:
Properties invokes Print properties dialog window to set up Title, footers and headers.
Drop-down list allows selecting Linear diagram scale in print preview window and when printed.
52
Spider Project User GuideProject Presentations
Example 2. Markers are of Text type, and list contains two elements:
- 0 – zero
- 10 – ten.
53
Breakdown Structures
5. Breakdown Structures
5.1. WBS Definition
Work Breakdown Structure is a deliverable-oriented hierarchical decomposition of the work to be executed by the project
team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the
project. Each descending level represents an increasingly detailed definition of the project work. The WBS is decomposed
into workpackages. The deliverable orientation of the hierarchy includes both internal and external deliverables. (PMBOK 3rd
Edition)
Activity is a component of work performed during the course of a project. Phase is a collection of logically related project
activities, usually culminating in the completion of a major deliverable. Project Phases are mainly completed sequentially but
can overlap in some project situations. Phases can be subdivided to subphases and then components. The lowest level phases
(called work packages) are comprised of activities. This hierarchy, if the project portions of the project are divided into
phases, is contained in the work breakdown structure. A project phase is a component of a project life cycle. A project phase
is not a project management process group.
54
Breakdown Structures
Project structures list dialog window to can be used to view, create and edit project work breakdown structures (when
invoked in Activity Gantt) organizational breakdown structures (when invoked in Resource Gantt) and project breakdown
structures (when invoked from projects portfolio)
The structures list is presented in list form with two columns: Properties and Name (Code). In column Properties attributes of
structure are displayed:
- attribute Full;
- attribute Responsible.
Frame Create Structure contains buttons to create, copy and update structures:
- New button opens structure properties dialog window to deifne its properties, then creates another structure consisting
only from operations of the project, but not grouped on phases / departments.
- Copy Filtered button allows to create structure in view of the filter applied to WBS allocated in the given window.
- Button Copy Filtered allows creating structure in view of the filter applied to gantt diagram structure selected in the given
window.
- Button Copy allows creating new structure as a full copy of the structure selected in the list of project structures.
- With buttons Create by codes and Create by codes from structure create structure by codes dialog window will be
invoked to choose fields, by which sequences the new structure will be grouped. Create by codes will allow to group
structure on codes of selected fields. Create by codes from structure will allow to group new structure on values of structure
phase fields selected in given window, and in Code floor structure code of initial structure on which fields of phases is
grouped will be displayed.
55
Breakdown Structures
Button Properties invokes structure properties dialog window to edit the structure, chosen from the list, and allows to commit
notes. Notes to selected structure are displayed under the list.
Removing a structure can be realized by pressing button to Delete. At removal of structures elements entering into its
structure, (phases, resources or departments) will not be deleted. It is possible to cancel the removal of structure - Protocol of
actions.
The button Update by codes allows to update the chosen structure in case new operations have been added, activity
characteristics are changed, phases referece-book is changed or it is necessary to change fields on which the given structure
has been grouped.
Press Switch to button to make selected structure active.
You can view and edit structure properties in this dialog window:
- Name;
- Code;
- Status,
- Notes;
Status shows whether structure is currently Responsibility structure or not. To set current structure to be a responsibility one
press Make it responsibility structure button.
Checkbox Make Full lets you specify whether current structure is complete or not. Incomplete structures contain excluded
objects (phases, activities).
56
Phase
6. Phases
6.1. Phase Properties Dialog Window
Dialog window contains pages: Data, Activities, Phases, Notes standard page, and OLE-objects and Folder standard page.
Page Data
- Name - phase title.
- Code - A sequence of characters that should be unique for each project phase. Code is made up by letters, figures and
special characters (#$%&@_-~) without spaces and is case sensitive.
- Type – default field for organizing of data transfer from reference-books for changing of phase properties.
- Short Name – phase short name;
- Priority – defines the order of phases performance in resource constrained scheduling. Phases with higher priority (i.e.,
greater value) are performed earlier.
- Calendar - calendar, used for estimation of phase duration in days. To change phase calendar press Choose button,
select desired calendar from the list and press OK.
- ASAP Start (as soon as possible) – the earliest possible point in time on which phase can start, based on the network
logic and any schedule constraints. ASAP Start dates can change as the project progresses and changes are made to the
project plan.
- ASAP Finish (as soon as possible) - the earliest possible point in time on which phase can finish, based on the network
logic and any schedule constraints. ASAP Finish dates can change as the project progresses and changes are made to the
project plan.
- ALAP Start (as late as possible) – the latest possible point in time on which a phase may begin without delaying the
project finish date.
- ALAP Finish (as late as possible) – the latest possible point in time on which a phase can be completed without
delaying the project finish date.
- Level – phase level in Work Breakdown Structure (WBS).
- Bar color – opens bar color dialog window for phase on Activity Gantt diagram.
- Calculate Variance Trends – allows to receive the table report or the diagram on variance trends after comparison of
the current project version with base version.
- Sum Volumes – allows to summarize operation volumes which are a part of the given phase. The total volume will be
displayed at line with the phase after calculation of expenses.
- Managers – list of persons, participating in management of current project phase. In group work on project, each phase
can have one or several managers, one of them must be responsible for this project phase performance. Actuality of
project information is maintained through distribution and consolidation of subprojects List of managers can be edited
with Add and Delete buttons. Each phase have a responsible manager, assigned by Responsible button. Responsible
manager is listed first and his or her name is marked with an asterisk. Consolidation of subprojects is performed from
Outbox folder (or FTP server) of responsible managers. Other managers will only receive project data after distribution
of subprojects. Outbox (for consolidation) and Inbox (for distribution) folders (or FTP server name) are set for each
manager in Users Table.
Page Activities
Included activities - list of phase activities, actually participating in project.
- New – adds new activity to phase.
- Properties – displays properties window of selected activity.
- Delete – deletes selected activity from the project.
- Exclude – moves selected activity to the list of excluded activities.
57
Phase
Page Sub-Phases
- New – adds new subphase to phases.
- Delete – deletes selected subphases from project.
- Exclude – excludes selected sub-phases from structure (phases cannot be excluded from structure of the responsibility
as it should be full). At exception of sub-phases from current structure, objects of the bottom hierarchy (activity) level
of are excluded, and empty sub-phases can be removed from structure. The excluded objects can be included in current
structure subsequently.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
During update, all activities of the current main project phase are replaced with activities from selected project. Activity
links in updated phase are restored according to their codes only for activities existing in selected project. Resources,
materials, cost components, multi-resources, resource skills and other objects of both projects are combined while
nonexistent objects are added to the main project. Uniqueness of objects’ codes is checked automatically. Total quantity of
both projects objects’ units is set to maximum value in the main project.
58
Phase
2. Select New Phase –> One Level Lower or The Same Level.
3. In the invoked Phase properties dialog window, set up new phase properties such as Name, Code, Type, select Calendar
and Managers. ASAP Start, ASAP Finish, ALAP Start, and ALAP Finish dates are automatically set up equaled to the
current project time.
Note that properties dialog window will be opened automatically for newly created phase only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created phase
will be saved with default parameters and you can edit its properties in Phase properties dialog window, invoked with
right mouse button click on corresponding phase row number.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details)
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
59
Phase
- Diagram – opens diagram settings dialog window to create diagram on selected phase;
- EVA Reports and Diagrams Templates:
- Table – opens report templates list window where you can choose report template for EVA table report
- Diagram – opens report templates list window where you can choose report template to create EVA diagram.
- Earned Value Analysis:
- Table – creates earned value analysis. In opened dialog window you can set properties for report.
- Diagram – creates earned value analysis diagram of current phase. In opened dialog window you can
customize diagram properties.
- Success Probability Trends Templates
- Table – opens report templates list window where you can choose report template for success probability
trends table report
- Diagram – opens report templates list window where you can choose report template to create success
probability trends diagram.
- Success Probability Trends:
- Table – creates success probability trends report on selected phase. You can customize report properties in
opened Success probabilities diagram options dialog window.
- Diagram – adds diagram of success probability trends to Activity Gantt diagram window. In opened dialog
window you can customize diagram properties.
- Variance Trends Templates:
- Table – opens report templates list window where you can choose report template for variance trends table
report
- Diagram – opens report templates list window where you can choose report template to create variance trends
diagram.
- Variance Trends:
- Table – creates variance trends report on selected phase. You can customize report properties in opened
variance trends diagram options dialog window.
- Diagram – adds diagram of variance trends to activity Gantt diagram window. In opened dialog window, you
can customize diagram properties.
- Update phase by selected project – replaces selected phase with another project. You must first select a project in the
main window If two projects are incompatible (for example, have different number of work breakdown structures) you
will receive corresponding error message.
- Copy phase as new project – creates a new project from selected phase.
- Insert project as new phase:
- One Level Lower – choose this option to add a project (selected in projects and documents dialog window) as a
subphase of the current phase. New phase will be placed next to the phase selected with right mouse button.
- The Same Level – choose this option to add a project (selected in projects and documents dialog window) as a
phase of the project. New phase will be placed on the same level of WBS as the phase selected with right
mouse button. Phase of the first level cannot be added.
- Distribute Subprojects – distributes subprojects to managers, assigned to phases.
- Consolidate Subprojects – consolidates subprojects from phase managers.
- Exclude – moves a phase to the list of excluded objects.
- Include:
- One Level Lower – choose this option to insert a phase or activity, selected in excluded objects dialog window,
inside current phase. Inserted objects will be listed first within the phase.
- The Same Level – choose this option to insert phase or activity, selected in excluded objects dialog window, on
the same level of WBS. Objects will be placed next to the current phase. Objects on the first level cannot be
inserted.
- Copy – copies selected phase to the clipboard.
- Cut – puts selected phase to the clipboard. You can insert a phase from the clipboard on the same or one level lower in
WBS.
- Paste
60
Phase
- One Level Lower – inserts activities or phase (with corresponding activities) from the clipboard inside the
current phase.
- The Same Level - inserts activities or phase (with corresponding activities) from the clipboard on the same
level of WBS. Phase cannot be inserted to the first level of WBS.
- Convert to Activity –converts current phase to activity. This action can be performed with a phase containing one
activity only. New activity will inherit name and code (if the last one was unique) from the former phase and all
assignments of activity comprising former phase.
- Convert to Phase- converts selected phases to phases by adding a new operation into the selected phase.
- New phase
- One Level Lower - adds new subphase to the current phase.
- The Same Level – adds new phase on the same level of WBS as the current phase. Another first level phase
cannot be added.
- New Activity – adds new activity to the current phase.
- Delete - deletes current phase from the project.
61
Phase
- Diagram – opens variance trends diagrams on templates dialog window to create diagram on phases.
- Variance Trends
- Table – creates variance trends report on phases.
- Diagram – creates variance trends diagram on phases
- Exclude – moves selected phases to the list of excluded objects.
- Copy – copies selected phases to the clipboard.
- Cut – puts selected phases to the clipboard. You can later insert these phases from the clipboard inside certain phase or
on the same level of WBS as the phase, on which shortcut menu was invoked.
- Convert to Phase –converts selected phases to phases by adding a new operation into the selected phase.
- Delete - deletes selected phases from the project.
During update, all activities of the current main project phase are replaced with activities from selected project. Activity
links in updated phase are restored according to their codes only for activities existing in selected project. Resources,
materials, cost components, multi-resources, resource skills and other objects of both projects are combined while
nonexistent objects are added to the main project. Uniqueness of objects’ codes is checked automatically. Total quantity of
both projects objects’ units is set to maximum value in the main project.
62
Phase
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
63
Phase
will be saved with default parameters and you can edit its properties in Phase properties dialog window, invoked with
right mouse button click on corresponding phase row number.
4. Click OK.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
64
Phase
3. Invoke shortcut menu (with a right mouse button click on phase row number) on one of the phases to be removed
from WBS and select Exclude.
1. In Activity Network window, click icon on Activity Network toolbar to switch on Show WBS option, which allows
phases to be represented in diagram.
Invoke Phase shortcut menu with the right mouse button click on phase box. If phases are not seen in Activity Network, click
icon on Activity Network toolbar to switch on Show WBS icon, which allows phases to be presented in diagram.
2. Select New Phase option.
3. In the invoked Phase properties dialog window, set up new phase properties such as Name, Code, Type, select Calendar
and Managers. ASAP Start, ASAP Finish, ALAP Start, and ALAP Finish dates will automatically be set up equaling to
the current project time.
Note that properties dialog window will be opened automatically for newly created phase only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created phase
will be saved with default parameters and you can edit its properties in Phase properties dialog window, invoked with
right mouse button click on corresponding phase row number.
4. To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
1. In Activity Network window, click icon on Activity Network toolbar to switch on Show WBS option, which allows
phases to be presented in diagram.
2. Invoke Phase shortcut menu with the right mouse button click on phase box and select Delete. If phases are not seen in
Activity Network, click icon on Activity Network toolbar to switch on Show WBS option, which allows phases to be
presented in diagram.
When you confirm deletion, program will delete the phase. All activities included in the phase, will be deleted from the
project, as well.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
65
Phase
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
66
Activity
7. Activities
7.1. Activity
A component of work performed during the course of a project.
Activity is the lowest level of work breakdown structure element to which resources, cost components and materials can
be assigned.
Activities Table contains a list of project activities with following columns (fields):
- Code –A sequence of characters that should be unique for each project activity. Code is made up by letters, figures and
special characters (#$%&@_-~) without spaces and is case sensitive.
- Name – full activity name.
- Type DPH defines DPH activity type – duration, productivity, hammock or milestone.
- Type – default field for organizing of data transfer from reference-books for changing of activity properties. Activities
with similar characteristics (e.g. sharing materials consumption, having the same cost components) can have the same
Type. E.g., activity ‘construction of brick wall’ can have type ‘BRICK_WALLS’, or ‘BW’.
- Interruptability – defines, whether splits in activity performance are enabled or not.
- ASAP, ALAP preferable time of activity performance – either ‘as soon as possible’ or ‘as late as possible’.
- Folder - full path to attached folder, that may be used to store files with referential information for current object.
Double click on the cell in this column allows defining the folder path or open the folder (if its path has already been
defined).
- OLE objects; icon defines whether documents of other applications (Word, Excel etc.) are attached to an activity.
Double click on this field opens activity properties dialog window on OLE objects and Folder page.
- Notes - A field that lets users to provide an activity with notes and explanations.
- Short name – should activity have too long name, you can set shorter name as alternative to full names.
- Start – activity start date. If an activity has not actually started, this field would be equal to Start [ASAP]. If activity is
already being executed and performance data is added to monitoring, this field would be equal to Start [Actual].
- Finish – activity finish date. If an activity has not actually finished, this field would be equal to Finish [ASAP]. If
activity has already been executed and performance data has been added to monitoring, this field would be equal to
Finish [Actual].
- Duration, Days [Remaining] – remaining activity duration in days according to calculated schedule;
- Duration, Hours [Remaining] – remaining activity duration in hours according to calculated schedule;
- Volume [Remaining] – remaining work volume in corresponding units.
- Volume unit –activity units (e.g.,’m2’, ‘pieces’);
- Total Cost [Remaining] – remaining activity cost;
- Float, hours; Float, days – activity float duration in hours or days.
- Calendar –calendar code, according to which activity is executed.
- Number of Working Days [Remaining] – a whole number of working days, required to complete activity according to
the current schedule calculated; the number of days is rounded up; a day is counted as working if it contains at least one
second of working time.
- Priority – defines the order of activities performance in resource constrained scheduling. Activities with higher priority
(i.e., greater value) are performed earlier.
- Total Duration of Teams (hours), Total Duration of Teams (days) – total duration (in hours or days) of work time of all
teams, assigned to activity.
- Start [ASAP] (as soon as possible) – the earliest possible point in time on which activity can start, based on the
network logic and any schedule constraints. ASAP Start dates can change as the project progresses and changes are
made to the project plan.
67
Activity
- Finish [ASAP] (as soon as possible) - the earliest possible point in time on which activity can finish, based on the
network logic and any schedule constraints. ASAP Finish dates can change as the project progresses and changes are
made to the project plan.
- Start [ALAP] (as late as possible) – the latest possible point in time on which an activity may begin without delaying
the project finish date.
- Finish [ALAP] (as late as possible) – the latest possible point in time on which an activity can be completed without
delaying the project finish date.
- Start [Actual], Finish [Actual] – activity actual start and finish dates according to included performance data;
- Start [NET], Finish [NLT] –constraint on the start (not earlier than) and finish (not later than) dates of activity
execution. You can set or change dates in these fields by direct entering or in Calendar dialog window (invoked by
double click).
- Duration, Hours [Actual] - total actual activity duration in hours according to included performance data;
- Volume [Actual] - actual work volume performed (in corresponding units) according to included performance data;
- Total Cost [Actual] - actual cost of work performed according to included performance data;
- Total Cost [Cumulative] – equals to actual cost plus remaining cost;
- Start [Critical], Finish [Critical], Total Cost [Critical] – critical activity start, finish dates and total cost; these values
are used in risk analysis;
- Start [Buffer], Finish [Buffer], Total Cost [Buffer] – buffer values, used in risk analysis;
- Finish [Target], Total Cost [Target] – defined activity target finish date and total cost;
- Finish [Target Probability] – probability of completing the activity up to target finish date;
- Total Cost [Probability] - probability of meeting activity target total cost;
- Start [Original]; Finish [Original] – activity start and finish dates in original project version (see projects comparison
for details);
- Duration, Hours [Original]; Volume [Original]; Total Cost [Original] – activity duration (in hours), volume (in
corresponding units) and total cost in original project version (see projects comparison for details);
- Completion Variance, Days – difference in ASAP finish dates of current and original project versions’ activities (or
assignments) in days (see projects comparison for details);
- OCWP – Original Cost of Work Performed, cost of work performed according to original project version;
- OCV – Original Cost Variance, variance of performed work cost in comparison to original project version. Equals to
difference between OCWP and actual cost of work performed (Total Cost [Actual]);
- User defined fields;
- Fields with fixed, remaining and actual consumption of all materials (and material centers) and expenditures of cost
components (and cost centers) their profiles.
To add an activity in Activities Table:
1. Press Insert button,
or
invoke row shortcut menu and choose New,
or
select menu item Edit -> New;
2. New activity properties dialog window would appear; enter activity details and press OK.
Note that properties dialog window will be opened automatically for newly created object only if you have selected to
Open properties for new created objects in the Spider Project Parameters Dialog window. Otherwise, newly created object
will be saved with default parameters and you can edit them later.
To edit existing activity properties double click on corresponding activity row number, or invoke shortcut menu on
corresponding activity and choose Properties.
To delete an activity in Activities Table: select activity row with left mouse button click and press Delete button,
or invoke shortcut menu and choose Delete, or select menu item Edit -> Delete.
Note that: To delete several activities select desired rows with left mouse button clicks (keeping Ctrl button pressed) first,
then perform one of the actions, described above for deleting of single activity.
(See general description of tables in Spider Project for common rules of working with tables).
68
Activity
Shortcut menu can be invoked for several selected activities. In this case menu will contain items:
- Properties – allows you to edit DPH Type ASAP ALAP Interruptibility add new or replace existing assignments for
selected activities in Assignments dialog window. You can add/edit team, resource, multi-resource or resource skills
assignments. Also Materials and Material Sets can be edited from the invoked window. All changes in this windows
will be applied to all activities selected.
- Resource Work Load Calculation;
- Fix Resource Skill Assignments;
- Delete.
To cancel last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Dialog window lets you to set or change activity properties and contains following pages:
- Initial Data
- Calculated Data
- Links
- Assignments
- Standard page of Materials
- OLE-objects and Folder standard page
69
Activity
- Resource Production
- Standard page of Cost Components
- Standard page of Material Sets
- Standard Page of Notes
70
Activity
Page Links
Consists of two similar areas: Preceding Activities and Succeeding Activities – to display lists of preceding and succeeding
activities as referred to established logical relationships to/from the current activity.
You can add new or delete existing activities from the list with the aid of Add and Delete buttons in corresponding area
(i.e., to add preceding activity press Add button in the upper area - Preceding Activities; to delete succeeding activity select
desired activity with a left mouse button in the lower area - Succeeding Activities and press Delete button). When you
press Add button activities list dialog window appears; select required activity, press OK and set link properties in invoked
dialog window.
You can view and customize link in link properties dialog window: select desired preceding or succeeding activity with a
left mouse button and press Properties button.
You can move to preceding or succeeding activity by selected desired activity in the list and pressing Go button. Thus it is
possible to move across the chain of linked activities. Each passage to another activity displays its properties in dialog
window and highlights this activity in Activity Gantt (network diagram or Activities Table).
Type, Calendar and Lag are displayed under the list of activities (if the list consists of more than one activity – these
properties are displayed for activity, selected with a mouse click).
To plot preceding and succeeding activities diagram (links diagram) press Diagram button.
Page Assignments
You can view and edit activity resources assignments on this page.
List of assignments shows type (Team, Multi-resource, Resource Skill or Resource), code and name for each activity
assignment. Team assignment is displayed first in the list with its structure organized hierarchically with indents. E.g.,
team may contain multi-resources that in turn consist of resources. In this case multi-resources will be displayed with
indents regarding to team and resources – with indent regarding to parent multi-resources.
List of assignments contains all existing activity assignments with notes, specific for assignment type:
- Resource assignments (‘Resource’, resource name, resource code)
- Multi-resource assignments (‘Multi-resource’, multi-resource name, multi-resource code)
- Skill assignments (‘Skill’, skill name, skill code)
- Team assignments (‘Team’, team name, team code)
Team assignments are shown first in the list. Assignments comprising corresponding team assignments are shown next.
Each activity assignment type has a certain set of fields displayed below the list of assignments. Select assignment with a
left mouse button to view or edit these fields:
- Duration, Volume – these fields are displayed for selected team assignments;
- Quantity, Productivity, Type, Work Load - are displayed for selected multi-resource assignments;
- Type (‘By Quantity’ or ‘By Productivity’), Quantity (for ‘By Quantity’ type resource skills) or Productivity (for ‘By
Productivity’ type resource skills) - are displayed for selected resource skill assignments;
- Quantity, Productivity, Priority, Work Load, Type, Scheduled Quantity, Calendar, Fixed Cost, Resource-hours,
Remaining Cost - these fields are displayed for selected resource assignments.
You can add assignments to activity with the help of buttons in the Add frame. The set of available buttons in the frame
(Resource, Multi-resource, Skill or Team) depends upon the selected parent object in the list of assignments:
- all buttons are available when Team is selected from the list;
- all except Skill button are available when skill is selected;
- all except Skill and Multi-resource buttons are available when multi-resource is selected.
To add Team, Multi-resource, Resource Skill of resources or Resource press corresponding button:
- Team button assigns new team for activity execution and adds it to assignments hierarchy;
- Resource Skill button opens a dialog window for selecting skills (or skills) to be assigned – select required skill(s) and
press OK. Selecting one skill opens properties dialog window for the resource skill being assigned where required type
(‘By Quantity’ or ‘By Productivity’) and quantity (for ‘By Quantity’ type) or productivity (for ‘By Productivity’ type)
can be set. Selecting several skills automatically sets skill assignment type to ‘By Quantity’ and quantity equal to one
for all newly added skills (you can edit these assignments later if required).
71
Activity
- Multi-resource button opens a dialog window for selecting multi-resource (or multi-resources) to be assigned – select
required multi-resource(s) and press OK. Selecting one multi-resource opens properties dialog window for the multi-
resource being assigned where required quantity, productivity and other characteristics can be set. With box Variable
quantity and Work Load checked quantity of multi-resource is automatically set to minimal value = 1. Selecting several
multi-resources automatically sets quantity equal to ‘1’ for all newly added multi-resources (you can edit these
assignments later if required).
- Resource button adds new resource to assignments hierarchy depending on the parent object selected – to Team, Multi-
resource or Skill assignments. Pressing Resource button opens a dialog window for selecting resource (or resources) to
be assigned – select required resource(s) and press OK. Selecting one resource opens properties dialog window for the
resource being assigned where required quantity, productivity and other characteristics can be set. Selecting several
resources automatically sets quantity equal to one for all newly added resources (you can edit these assignments later if
required).
72
Activity
Activity of Milestone type is activity of zero duration used to reflect certain event that is important to control project
execution.
Properties dialog window of a group of activities allows editing certain properties of selected activities. To invoke this dialog
window select several activities in Activities Table or Activity Gantt, click with a right mouse button on one of selected rows
and choose Properties from opened dialog window.
In current dialog window you can:
- set DPH activity type – Duration, Productivity, Hammock or Milestone for selected activities;
- set method of schedule calculation for these activities – ASAP or ALAP;
- set whether these activities should be Interruptible or Not Interruptible (see Interruptible activities for details on this
option).
- assign calendars to this group of activities.
73
Activity
If Interruptible option was not selected, resource assigned to activity cannot be used for other activities before this activity is
finished. If several teams are assigned to activity, interruption can be done within one-team work only.
Note That: Even uninterruptible activity with several teams will have interruptions between different teams work.
For example:
Activity1 has priority ‘1’ and Resource1 assigned to it. This activity is Interruptible.
Activity3 has priority ‘2’, and Resource1 is also assigned to it.
If – when performing Resource Constrained Scheduling –Allow performance interruptions option in Scheduling Options
dialog window is filled in, the resulting schedule will be as in the graph above: Activity1 was interrupted because of non-
sufficient Resource1 which was sent to Activity3 (with higher priority). Then Activity1 was continued.
Using interruptible activity helps to have optimized schedules. If Allow performance interruptions option had been switched
off in the example, you would get the following schedule:
74
Activity
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
For further information see working with tables.
75
Activity
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
76
Activity
- Diagram – adds diagram of success probability trends to Activity Gantt diagram window. In opened dialog
window you can customize properties of diagram.
- Variance Trends Templates
- Table – opens variance trends reports on templates dialog window to create table report on activity.
- Diagram – opens variance trends diagrams on templates dialog window to create diagram on activity.
- Variance Trends
- Table – creates variance trends report on activity.
- Diagram – creates variance trends diagram on activity
- Exclude – moves current activity to the list of excluded objects.
- Include – lets insert a phase or activity, selected in excluded objects dialog window, into WBS.
- Copy – copies selected activity to the clipboard.
- Cut – puts selected activity to the clipboard. You can later insert activity from the clipboard inside certain phase or next
to certain activity.
- Paste - inserts activities from the clipboard next to the activity, on which shortcut menu was invoked, or places them
first inside phase, on which shortcut menu was invoked.
- Convert to phase – converts current activity to phase;
- New Activity – adds new activity and places it next to the activity, on which shortcut menu was invoked.
Note that properties dialog window will be opened automatically for newly created object only if you have selected to
Open properties for new created objects in the Spider Project Parameters Dialog window. Otherwise, newly created
object will be saved with default parameters and you can edit them later
- Delete - deletes current activity from the project.
77
Activity
- Table – creates earned value analysis. In opened dialog window you can set properties for report.
- Diagram – creates earned value analysis diagram of current activity. In opened dialog window you can
customize properties of diagram.
- Success Probability Trends Templates
- Table – opens a dialog window with the list of templates to create a report on templates for selected activity;
- Diagram – opens a dialog window with the list of templates to create a diagram on templates for selected
activity.
- Variance Trends Templates
- Table – opens variance trends reports on templates dialog window to create table report on selected activities.
- Diagram – opens variance trends diagrams on templates dialog window to create diagram on selected
activities.
- Variance Trends
- Table – creates variance trends report on selected activities.
- Diagram – creates variance trends diagram on selected activities.
- Resource Work Load Calculation – performs calculation of all assigned to activity resources work load with respect to
defined duration and resources productivities.
- Fix Resource Skill Assignments – allows fixing resource assignments to currently selected activities. I.e. only resources
(from the list of resourced comprising resource skills assigned) selected by Spider Project to activity execution will be
left as activity assignments and all idle resources will be removed from current activity assignments.
- Exclude – moves selected activities to the list of excluded objects.
- Copy – copies selected activities to the clipboard.
- Cut – puts selected activities to the clipboard. You can later insert these activities from the clipboard inside certain
phase or next to certain activity.
- Convert to Phase – converts selected activities to phases.
- Delete - deletes selected activities from the project.
Activities can be copied from one phase to another only in Activity Gantt. To perform that:
1. Select activities by clicking row numbers, while holding Ctrl key. Selected activities will stay highlighted in gray.
2. Invoke Activity shortcut menu with the right mouse button click on one of the highlighted row numbers and select Copy.
Highlighted activities will be copied on clipboard.
3. If you want to insert copied activity inside a phase, invoke Phase shortcut menu on the phase inside of which you want to
copy the activity, and select Paste ->One Level Lower.
If copied activities need to be inserted on the same level as a certain phase, invoke Phase shortcut menu and select Paste -
>The Same Level. In result, copied phases will be inserted behind the highlighted phase. if the phase is first-level phase, a
corresponding message will appear.
If you want to insert (paste) activity after another activity, invoke Activity shortcut menu by clicking its row number and
select Paste.
In order to maintain element codes uniqueness, Change Activity and Phase Dialog window will be invoked to allow you to
change codes or multiply the copied element. Otherwise, original activity will have the same code as the pasted activity. Or,
as an option, you can multiply activity parameters to a coefficient, if you use original activity as sub-phase. Change Activity
and Phase Dialog window contains the following fields:
- Replace from field indicates number of code symbol starting with which the code will be changed. And the text shown in
symbol by field will be the new initial to replace the old code. For example, if original code of activity or phase was 1020
and, as it is shown in the example window, it is requested to Replace from 3rd symbol by 50, a new code will become
1050.
- Add prefix sets up prefix that would be added in front of all activity codes.
- Add postfix sets up postfix that would be added in the end of all activity codes.
78
Activity
- Multiply by coefficient means that old activities’ volumes; activities durations, costs, and material consumption will be
multiplied to this coefficient (equals 1 by default).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
79
Activity
Change of codes is customized in Copied activity and phase codes and Original activity and phase codes frames (Note these
changes apply only to the current project and do not affect source project file):
1. Copied activity and phase codes frame – refers to the project that is being inserted as phase (source).
Replace from .. symbol - indicates starting position in activity/phase codes to change code from. Text, entered into by
field will replace the old code. For example, if activity code in the source project was ‘1020’ (in the project being
inserted) and, as it is shown in the example window, it is requested to Replace from 3 symbol by 50 - the resulting code
would be ‘1050’ (in the current project) after insertion.
Add prefix sets up prefix to be added to all inserted activity/phase codes.
Add postfix sets up postfix to be added to all inserted activity/phase codes.
In Copied activity volume, duration, cost and material expenditure frame, coefficient Multiply by means that volumes,
durations, and expenditures in the source project (being inserted) would be multiplied to this coefficient (equals 1 by
default) after insertion into the current project.
2. Original activity and phase codes frame – refers to the current project, where another project is inserted to (destination).
If you use only these parameters (leaving fields in the Copied activity and phase codes frame blank) – codes in the
project being copied (source) as phase to the current project would be preserved and codes in the current project
(destination) would be changed.
Replace from .. symbol - indicates starting position in activity/phase codes to change code from. Text, entered into by
field will replace the current code. For example, if original activity or phase code (in the current project) was ‘1020’ and
it is requested to Replace from 3 symbol by 50, the resulting code would be ‘1050’ (in the current project) after insertion.
Add prefix sets up prefix to be added to all activity/phase codes in the current project (codes in the inserted phase would
be preserved from the inserted source project).
Add postfix sets up postfix to be added to all activity/phase codes in the current project (codes in the inserted phase
would be preserved from the inserted source project).
1. In Activity Network window, click icon on activity network toolbar to switch on Show WBS option to see phases in
the window.
2. Invoke phase shortcut menu by right clicking on the phase box, to which new activity is being added.
3. Select New Activity.
4. In the invoked activity properties dialog window, set up the following new activity properties:
Code;
80
Activity
Name;
Volume (100.00 by default);
Duration (5 days or 40 hours by default); and
DPH Type (Duration by default).
Note that: properties dialog window will be opened automatically for newly created activity only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created
activity will be saved with default parameters.
5. Click OK.
If activities are not shown in Activity Network, click Show/Hide Activities icon on Activity Network toolbar.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
81
Activity
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
82
Calendar
8. Calendars
8.1. Project Calendars
All activities, resources, phases, departments and links can have individual calendars.
- Activity calendar defines time periods when activity can be performed;
- Resource calendar defines time periods when resource can be engaged on activity execution;
- Phase and Department calendars are used for calculation of work duration in days according to formula: working
duration in hours divided by mean working day according to phase/department calendar.
- Link calendar serves for calculation of link lag.
Teams have no special calendars. Team calendar is calculated as intercept of activity calendar and team resources
calendars.
Each project has main calendar, which is used as default calendar for newly created objects. To set properties of main
calendar:
1. Open Calendars Table;
2. Select calendar that should be main, invoke shortcut menu with right mouse button on calendar row number and
choose Properties;
3. Press Make Main button; ensure that Status of the calendar becomes ‘Main’;
4. Press OK button.
Defining calendar properties consists of two parts: setting standard calendar week and identifying periods (exception
periods) when work should be performed according to other week calendars.
You can create unlimited number of calendars. To edit calendar properties open Calendars Table from main program
window or from menu item Project -> Data -> Calendars.
Contains all project calendars data and contains the following columns (fields) by default:
- Code is a sequence of characters, unique for each calendar. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Name is a calendar name.
- Average Working day in Hours is mean working day in main calendar week. It equals total number of working hours
divided to number of working days in main week.
- Number of Working days is number of working days in main calendar week. A day is considered a working day if at least
one minute of it was used as working period.
- Total Number of working hours is total number of working periods in week (in hours).
- Notes contains comments to calendar (if any). Double click on the cell invokes Calendar properties dialog window
opened on notes standard page.
- Main shows if calendar is selected as main calendar.
- Main Week Code is code of main week.
- Main Week Name is name of main week
- MN (Monday), TU (Tuesday), WN (Wednesday), TH (Thursday), FR (Friday), ST (Saturday), and SU (Sunday) are fields
containing number of working periods for corresponding day of main week.
- User-defined columns.
Working with this table is made by the general rules, identical for all tables of the project.
Calendar shortcut menu
Calendar shortcut menu is invoked with the right mouse button click on calendar row number and contains the following
options:
83
Calendar
- Properties invokes Calendar properties dialog window allowing you editing calendar properties.
- New allows creating new calendar by evoking Calendar properties dialog window and adds new row in Calendars table.
Note that properties dialog window will be opened automatically for newly created calendar only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created
calendar will be saved with default parameters and you can edit its properties in Calendar properties dialog window,
invoked with right mouse button click on corresponding week row number.
- Delete deletes highlighted calendar and a corresponding row in Calendars table.
When several rows are highlighted simultaneously, shortcut menu contains Delete option only.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Weeks table contains all project weeks' data and has following columns (fields) by default:
- Code is a sequence of characters, unique for each week. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Name is a week name.
- Average Working Day in Hours is mean working day of the week. It equals total number of working hours divided to
number of working days in the week.
- Number of Working Days is number of working days in the week. A day is considered a working day if at least one
minute in that day was a working period.
- Total Number of Working Hours is total number of working periods in the week (in hours).
- Working Day Beginning by Default is field used to conveniently edit working periods in the table. By default, working
day start is 8 A.M. When value in this column is changed, start time will not automatically change in work schedule by
day columns (1-Monday, 2-Tuesday, etc.). To update start time in these columns, reenter total number of working periods
in 1-MN, 2-TU, and other columns.
- Notes contains comments to the week (if any). Double click on the cell invokes Week properties dialog window opened
on notes standard page.
- MN (Monday), TU (Tuesday), WN (Wednesday), TH (Thursday), FR (Friday), ST (Saturday), and SU (Sunday) columns
contain number of working hours for a corresponding day of the week. Changes made in this column will change total
working period duration for corresponding day.
- 1-Monday, 2-Tuesday, 3-Wednesday, 4-Thursday, 5-Friday, 6-Saturday, and 7-Sunday columns contain working period's
schedules for a corresponding day of the week. If there are several working periods in one day, use semicolon to separate
them; and use a dash to separate working period start time and finish time (for example, 8:00-13:00; 14:00-19:00).
- User-defined columns.
Row shortcut menu
Row shortcut menu is invoked with the right mouse button click on row number and contains the following options:
- Properties invokes Week properties dialog window to edit week properties.
- New allows creating new week by evoking Week properties dialog window and adds new row in Weeks table.
Note that properties dialog window will be opened automatically for newly created week only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created week
will be saved with default parameters and you can edit its properties in Week properties dialog window, invoked with
right mouse button click on corresponding week row number.
- Delete deletes highlighted week and a corresponding row in the table.
When several rows are highlighted simultaneously, shortcut menu contains Delete option only.
84
Calendar
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Working with this table is made by the general rules, identical for all tables of the project.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
When several rows are highlighted simultaneously, shortcut menu contains Assign to All Calendars and Delete options.
85
Calendar
Data page
This page contains calendar’s Name, Code, and Status.
Status field indicates whether calendar is the main project calendar. Main calendar is used as default calendar for newly-
created objects: activities, phases, links, etc. To make an active calendar main, click Make Main button.
Main Week frame contains main week properties. To select the main week, click Select button. Dialog window which
contains all project weeks will be invoked. Once you have chosen the main week, its properties will be shown in Main Week
frame.
Exceptions frame contains a list of periods with different working weeks (usually blank weeks with "0" (zero) working hours
per week). Previously added calendar exceptions can be assigned to calendars by clicking Add button and selecting the
calendar exception from the list and finalizing by OK button. Several exceptions can be assigned to calendars. To assign all
exceptions to the calendar press Select All.
Unselect All button executes the command to unselect all exceptions. To add a new calendar exception, click New and select
required calendar exception period from the list of existing periods (which were previously created in calendar exceptions
table). You can edit calendar exception properties such as Name, Code, Start, Finish dates, and others. Highlight calendar
exception, and click Properties button to edit properties in invoked calendar exception properties dialog window. To remove
selected the calendar exception from current calendar, click Delete (calendar exception will not be actually deleted from
calendar exceptions table).
Note That: changes made to calendar exception period affect its properties in the project globally (as if you changed calendar
exception in calendar exceptions table).
86
Calendar
Data page
- Name is a week name.
- Code is a sequence of characters, unique for each project week. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Working hours (total) is the total number of working periods in the week (in hours).
- Number of Working days is the number of working days. A day is considered a working day if at least one minute of it
was a working period.
- Average Working day in hours is calculated by dividing Working hours (total) to Number of Working days.
- Working day beginning by default is the beginning working time for all working days in hour format. Enter this option if
every working day begins at the same time.
- MN (Monday), TU (Tuesday), WN (Wednesday), TH (Thursday), FR (Friday), ST (Saturday), and SU (Sunday) are fields
for day-by-day working periods entry. If there are several working periods in a working day, separate them with
semicolon; and use dash to separate working period start and finish time. For example, 8:00 - 13:00; 14:00 - 19:00.
Note that: working periods within one day must be ordered in ascending mode; periods must not overlap.
Sets up calendar exception properties and contains Data page and notes standard page.
Data page
87
Calendar
88
Link
9. Links
9.1. Links Table
Contains properties of links between project activities in the following standard columns (fields) for each link:
- Code of preceding activity.
- Code of succeeding activity.
- Name of preceding activity.
- Name of succeeding activity.
- Notes contain comments to the link. Double click in the cell invokes link properties dialog window opened on notes
standard page.
- Type sets up link type from reference-books. Double click in the cell invokes link properties dialog window opened on
the Data page, where link type may be changed by selecting it from the list.
- Lag Type indicates type of lag: either Time or Volume.
- Lag contains lag value.
- Lag Unit sets up lag measurement unit (Hours or Days for Time lag). Lag unit can be changed in Link properties dialog
window invoked by double click in Lag Unit cell.
- Lag Calendar is a drop-down list of lag calendar codes.
- Link Type indicates how strong the link is, out of two options: Not Earlier Than or Strict. Severity switches from one
type to another with double click in the cell.
- User-defined fields (columns).
Working with this table is made by the general rules, identical for all tables of the project.
Link row shortcut menu
Shortcut menu in Links table which is invoked by right clicking on row number contains the following options:
- Bar Color defines the color of the link which will be shown in gantt charts.
- Properties invokes link properties dialog window to edit link properties.
- Delete deletes highlighted link and its corresponding row from Links table.
To cancel the last action performed, select items Edit -> Undo last action from the menu or press button (see Undo for
more details).
When several rows are highlighted simultaneously, shortcut menu contains only Delete option.
Since user is not allowed to add new rows in Links table, Add option is absent in shortcut menus.
89
Link
After cursor changes to cursor of link press left mouse button and move cursor to the second (successor) activity and
release mouse button. link properties dialog window will be invoked to enter link properties.
Note that: properties dialog window will be opened automatically for newly created link only if you have selected to Open
properties for new created objects in the spider project parameters dialog window. Otherwise newly created link will be
saved with default parameters.
If a link between these two activities already exists, a shortcut menu with Properties and Delete options will appear.
Selecting Properties will invoke link properties dialog window. Delete button will delete the existing link.
Activities would be re-arranged according to the links established only after project schedule is recalculated.
To cancel the last action performed, select Edit -> Undo last action from the menu or press button (see Undo for more
details).
Note That: it is not possible to create a link from activity to itself, and while create a link between activities if there is already
a link between them in opposite direction; a corresponding error message will appear.
90
Link
Alternatively, link properties can be edited directly in cells of Links table. To perform this, double click a corresponding cell,
edit contents, and press Enter key on the keyboard.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Working with this table is made by the general rules, identical for all tables of the project.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
9.6. Lag
In addition to the type of logical relationship (link) between activities (Finish - Start, Finish - Finish, Start - Finish or Start -
Start) you can specify lag:
- Time lag - time period between the moment when dependency requirements (preceding event) are accomplished and
succeeding event (e.g. succeeding activity start or finish) may occur;
- Volume lag - specifies the amount of work that should be done on preceding activity to allow the following activity
to start.
Lag can be positive (delay) or negative (lead). Lag is a modification of a logical relationship that directs a delay in the
successor activity. A negative lead is equivalent to a positive lag.
Time Lag
Has different meaning for each type of link between activities:
For Finish-Start link type: sets up time interval (according to its own calendar) between preceding activity finish and current
activity start.
For Finish-Finish link type: sets up time interval (according to its own calendar) between preceding activity finish and current
activity finish.
For Start-Start link type: sets up time interval (according to its own calendar) between preceding activity start and current
activity start.
For Start-Finish link type: sets up time interval (according to its own calendar) between preceding activity start and current
activity finish.
Lag Calendar can be specified in Link Properties dialog window.
Volume Lag
Is set up for Start-Start and Start-Finish link types only. Means that next activity can only start after a set-up lag volume is
accomplished for current activity.
91
Link
Finish-to-Finish — is the logical relationship between activities when preceding activity must be completed before the
completion of the succeeding activity.
Start-to-Finish — is the logical relationship between activities when preceding activity must be started before the
completion of the succeeding activity.
Start-to-Start — is the logical relationship between activities when preceding activity must be started before the start of the
succeeding activity.
92
Link
For further information on working with links diagram, see Activity Network.
Right clicking on window parts, where there is no activity invokes links diagram shortcut menu containing Create Preceding
Activity and Create Succeeding Activity options.
Right clicking on activity boxes invokes activity shortcut menu in links diagram containing Properties, Bar Color, Shape,
and Delete options.
- Properties invokes activity properties dialog window.
- Bar Color invokes object color dialog window allows to set up activity box color in the diagram. If several activity boxes
are highlighted simultaneously, selected color will be applied to all of them.
- Shape changes the shape of activity boxes in shapes dialog window. If several activity boxes are highlighted
simultaneously, selected shape will be applied to all of them.
Delete deletes the activity from the project. If several activity boxes are highlighted simultaneously, all of them will be
deleted from diagram and from the project. To cancel the last action performed select menu item Edit -> Undo last action or
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
93
Resource
10. Resources
10.1. Resource
Resources are skilled human resources (specific disciplines either individually or in crews or teams), equipment, services,
supplies, commodities, materiel, budgets, or funds. Resources are used to perform activities in the project. There are
resources of renewable and non-renewable type. Renewable resources are resources available to be used after they were
already used on activity. For example, grader, crane, worker or driver. These resources are called Resources in Spider
Project.
Non-renewable resources are resources used up on one activity. For example, bricks, concrete, energy. These resources are
called Materials in Spider Project.
To perform activity, resource should be assigned to it. Use Activity properties dialog window to assign resource to activity.
Includes all project resources data and contains the following columns (fields) by default:
- Code is a sequence of characters, unique for each resource. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Name is resource name.
- Type is resource type usually used in connection with reference-books.
- Notes contains comments to material (if any). Double click in the cell invokes Resource properties dialog window
opened on notes standard page.
- Folder is a field containing full path to attached folder.
- OLE objects field contains icon if any other applications documents are attached to the material. Double click in the
cell invokes Resource properties dialog window opened on the OLE-objects and Folder standard page.
- Short Name contains shorter resource name.
- Quantity is available resource quantity.
- Quantity [Scheduled] is maximum resource quantity to be used in the project at the current moment.
- Calendar is calendar code the resource operates under.
- Total Cost [Remaining] is remaining scheduled cost of work of all resource units in the project.
- Total Cost [Actual] is actual cost of work of all resource units in the project.
- Total Cost [Cumulative] is total cost of work of all resource units in the project (equals to Total Cost [Remaining] +
Total Cost [Actual]).
- Duration, Hours [Remaining] is remaining resource work duration (according to its own calendar) in the whole project,
in hours.
- Duration, Days [Remaining] is remaining resource work duration (according to its own calendar) in the whole project, in
days.
- Duration, Hours [Actual] is actual resource work duration in the whole project, in hours.
- Start is resource work start date.
- Finish is resource work finish date.
- Float, Days and Float, Hours resource reserve in days and hours, respectively.
- Start [ASAP] is as soon as possible start date resource starts working in remaining part of the project.
- Finish [ASAP] is as soon as possible finish date of resource work in the project.
- Start [ALAP] is as late as possible start date resource starts working in remaining part of the project.
- Finish [ALAP] is as late as possible finish date of resource work in the project.
94
Resource
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
95
Resource
Dialog window of Resource Properties lets view and edit properties of resources. Dialog window consists of following
pages: Data, Assignments, Materials standard page, Cost Components standard page, Material Sets, Resource
Production, Cost Periods, Overtime, Resource Centers, Notes standard page , OLE-objects and Folder standard page.
Page Data
- Name –name of resource;
- Code – A sequence of characters that should be unique for each project resource. Code is made up by letters, figures
and special characters (#$%&@_-~) without spaces and is case sensitive.
- Short Name – you can define short name for the resource;
- Type – default field for organizing of data transfer from reference-books. Corresponds to current resource type.
- Quantity – available quantity of current resource;
- Calendar – calendar, according to which the resource can execute activities. To change resource calendar press select
button and select required calendar in the list.
- Start; Finish – start and finish dates of resource work in the project;
- ASAP Start, ASAP Finish – start and finish dates of resource assignment, calculated according to ASAP method, i.e.
dates are scheduled as soon as possible keeping all constraints satisfied.
- ALAP Start, ALAP Finish – start and finish dates of resource assignment, calculated according to ALAP method, i.e.
dates are scheduled as late as possible without delaying the project finish date.
- Float (hours) - resource assignment float in hours.
- Float (days) - resource assignment float in days.
- Duration, hours; Duration, days – remaining scheduled duration of resource work in the project in hours and in days.
- Actual Start - actual start of resource work in the project;
- Actual Finish - actual finish of resource work in the project;
- Scheduled Quantity – estimated maximal number of resource units, required for project execution;
- Actual Duration – actual duration of resource work in the project in hours;
- E-mail address – a resource‘s e-mail address of a for sending notifications
- Notify before start and finish of the works – selecting this option will allow to notify a resource at the beginning and at
the end of works on operations to which it is appointed.
- Bar Color – defines the bar color of the resource in chart.
Page Assignments
Lets you control resource assignments to activities. List contains all activities, to which the resource is assigned. Group of
fields below activities list present summary of resource assignment:
- Quantity – number of resource units, assigned to activity execution;
- Type - default field for organizing of data transfer from reference-books;
- Priority – priority of assignment (is used for resources belonging to resource skills) - defines the order of resources
assignment in resource constrained scheduling. Resources with higher priority (i.e., greater value) are assigned first;
- Calendar – calendar code on which the resource assigned to activity execution works.
- Resource Hours – resource labor expenditures assigned to activity execution in resource-hours.
- Productivity – productivity of one resource unit per hour (i.e. number of activity volume units that current resource can
execute per hour)
- Work Load – work load of one resource unit in percent of total resource working time that the resource is to spend on
activity execution. By default, workload is equal to 100%.
- Scheduled Quantity - estimated number of resource units, required to perform activity.
- Remaining Cost – estimated remaining cost of resource work on current activity assignment;
- Fixed Cost – fixed cost of resource work on current activity assignment;
To view or edit resource assignment on an activity select required activity and press Properties button.
To remove assignment of the resource select required activity and press, Delete button.
96
Resource
To cancel resource production on certain activities select corresponding activities in the list and press Delete.
Page Overtime
You can create and edit resource overtime periods on this page.
The list of Overtimes contains existing overtime periods’ names and codes for the current resource.
Button Add lets you add new overtime period. Note you can only add overtime periods previously defined in the Overtime
table.
Button Properties lets you edit overtime period properties in the overtime properties dialog window: overtime name, code
and overtime calendar.
Button Delete lets you delete selected overtime.
97
Resource
- Select New from Resource shortcut menu invoked with the right mouse button click on resource row number; or
- Hit Insert key on the keyboard; or
- Click on empty gray area below the table with the right mouse button and select New option in the invoked shortcut
menu.
Note that properties dialog window will be opened automatically for newly created resource only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created
resource will be saved with default parameters and you will have to invoke resource properties dialog window by double
click on new resource row number (or by selecting Properties from shortcut menu invoked with a right mouse button
click on new resource row number)
2. Set up new resource properties such as Name, Code, Type, and Quantity (equals 1 by default) and click OK when
finished.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Working with this table is made by the general rules, identical for all tables of the project.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
3. Click Resource Peak Work Load icon on the toolbar. Resource Load bar will appear in the bottom of Gantt chart.
Green color on the bar represents resources working in normal load. Red color represents overloaded resources.
4. With the right mouse button, click on a red area and invoke the shortcut menu containing Search for Resource
Overloads and Delete Diagram options.
98
Resource
5. Select Search for Resource Overloads option to invoke Resource Overloads dialog window containing list of resources
overloaded in the period. Period is specified in Start and Finish fields. Clicking Filter Activities button will show only
activities in which the overloaded resources were used (activity gantt) or the highlighted resource and its assignments
(resource gantt). To restore full Gantt chart, select Restore from Filter menu in Gantt chart.
Contains list of overloaded resources for the moment of time pointed with cursor during search for overloads. Period start and
finish date and time are shown in the top part of dialog window, in Period from and to fields.
Close and Filter Activities buttons are located below the list. In activity gantt, clicking Filter Activities button will show only
activities in which the overloaded resources were used.
In resource gantt, clicking Filter Assignments button will show only the resource highlighted in the list in Resource
Overloads Dialog window, and its assignments.
To restore full Gantt chart, select Restore from Filter menu in Gantt chart.
Click Close to close the dialog window.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
99
Resource
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
100
Resource
- New Resource - lets add a new resource on the same level of OBS as resource, on which shortcut menu was invoked,
new resource will be placed next to the resource, on which shortcut menu was invoked.
- Replace Assignments by... – lets replace all assignments of the current resource with a different resource, resource skill
or multi-resource through replacing assignments dialog window;
- Convert to Department – converts the selected resource(s) to departments.
- Delete - deletes current resource from the project with all corresponding assignments.
You can perform actions on a group of selected resources through group shortcut menu: change Properties, Bar color,
Roll Up / Expand corresponding assignments; Exclude / Include, Cut, Delete resources or Replace assignments by… for
selected resource. Reports and Diagrams Templates and General Reports and Diagrams are also available to be
generated.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
101
Multi-Resource
11. Departments
11.1. Department Properties Dialog Window
Dialog window allows you to set department properties and contains following pages: Data, Resources, Departments,
Notes standard page, OLE-objects and Folder standard page.
Page Data
- Name – department’s name.
- Code - A sequence of characters that should be unique for each project department. Code is made up by letters, figures
and special characters (#$%&@_-~) without spaces and is case sensitive.
- Type – default field for organization of data transfer from reference-books for changing department properties.
- Short Name – department’s short name.
- Calendar– Calendar, used for calculation of department work duration in days. To change current department calendar
press Select button and choose one from the list of available calendars.
- ASAP Start (as soon as possible) – the earliest possible point in time on which resources comprising current department
can start working. ASAP Start dates can change as the project progresses and changes are made to the project plan.
- ASAP Finish (as soon as possible) - the earliest possible point in time on which resources comprising current
department can finish working. ASAP Finish dates can change as the project progresses and changes are made to the
project plan.
- ALAP Start (as late as possible) – the latest possible point in time on which resources comprising current department
may start working.
- ALAP Finish (as late as possible) – he latest possible point in time on which resources comprising current department
may finish working.
- Level – level of current department in organizational breakdown structure.
- Sum Volumes – allows to summarize the volumes, which are carried out by a resource, as a part of department. The
total volume will be displayed only after the calculation of expenses.
- Bar Color – defines the bar color of the department in graphical part of the Resource Gantt.
Page Resources
- Included Resources - list of resources comprising current department.
- New – adds new resource to department.
- Properties – displays properties window of selected department.
102
Multi-Resource
Page Departments
- New – adds a new department to current departments.
- Delete – deletes selected department from project.
- Exclude – moves department to the list of excluded objects (removes department from current organizational
breakdown structure). To exclude any department from the list responsibility structure must be full.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
103
Multi-Resource
- Invoke Department shortcut menu with the right mouse button click on department row number in table part of
resource gantt and select Delete; or
- Highlight department with the left mouse button click on department row number and press Delete key on the
keyboard.
When you confirm deletion, program will delete department. All resources included in the department will be deleted from
the project, as well.
If you highlight several departments, all of them will be deleted from the project. To perform this, hold Ctrl key and click
row numbers of departments you would like to delete – they will stay highlighted in gray –and follow one of the above-
described methods. Confirm group of objects deletion when a corresponding message appears.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
104
Multi-Resource
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
105
Multi-Resource
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
106
Multi-Resource
12. Multi-resources
12.1. Multi-resource
Multi-resource – is a steady group of resources that can work together only. Thus, multi-resources can be assigned to an
activity as part of one team only.
Examples of multi-resources:
- Excavator and operator;
- Brigade;
- Crew.
Multi-resource properties dialog window enables to view and edit information on current multi-resource, its composition
(participants), update multi-resource assignments.
This dialog window contains several pages: Data, Participants, Notes standard page, and OLE-objects and Folder
standard page.
Page Data
Lets to set multi-resources Name, unique Code and Type.
- Code - A sequence of characters that should be unique for each multi-resource. Code is made up by letters, figures and
special characters (#$%&@_-~) without spaces and is case sensitive.
- Type - default field for organizing of data transfer from reference-books for changing of object properties.
Page Participants
Contains a list of resources comprising current multi-resource. For each resource its name. code and units quantity in
multi-resource are displayed.
- Quantity – sets number of resource units in multi-resource;
- Add – lets you add new resources to multi-resource. Pressing Add button invokes dialog window with a list of project
resources. You can select one or several desired resources from the list with left mouse button and press OK. Note that
the same resource cannot be added twice to one multi-resource.
- Delete – removes selected resource from current multi-resource composition.
- Update content – enables update current multi-resource assignments globally in the project with new multi-resource
properties and composition. Note that historical project data cannot be updated, i.e. in ongoing project with included
performance data updating of multi-resources properties would not affect data before the project data date. Current
multi-resource activity assignments are updated with following peculiarities:
107
Multi-Resource
- Multi-resource assignments (quantity and composition of comprising resources) are not changed for completed
activities;
- Multi-resource assignments (quantity and composition of comprising resources) are changed for uncompleted
activities if resources comprising current multi-resource have not actually participated in activity execution.
Otherwise, if resources have already been involved on activity, their composition and quantity assigned would
be updated for further activity execution only (if resource was completely removed from the multi-resource its
name would still exist in the list of activities assignments with quantity set to zero).
To cancel last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
108
Resource Skill
- OLE Objects field contains icon if the skill has other applications documents attached to it. Double click in the cell
invokes resource skill properties dialog window opened on the OLE-objects and folder standard page.
- Notes contain comments to resource skill. Double click in the cell invokes Resource skills properties dialog window
opened on notes standard page.
- User-defined columns (fields).
Working with this table is made by the general rules, identical for all tables of the project.
Resource skill row shortcut menu
Row shortcut menu in Resource Skills table which is invoked by right clicking on the row number, contains the following
options:
- Properties invokes resource skills properties dialog window to edit properties.
- New creates a new resource skill with default options.
- Delete deletes all assignments in highlighted resource skill and their corresponding rows from resource skills table.
- Replace Assignment by allows selecting new assignment to replace existing one(s). Select new assignment from the list
of all assignments available. The list varies depending on selection you made: Resources, Multi-Resources, or Resource
Skills. To learn more, see Replacing Assignment.
- Update Content allows updating contents and assignments properties of highlighted resource skill.
- Delete Assignments deletes all assignments in highlighted resource skill, but resource skill itself remains in the project
and Resource Skills table.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
When several rows are highlighted simultaneously, shortcut menu contains the following options: Replace Assignment by,
Update Content, Delete Assignments, and Delete.
109
Resource Skill
Page Data
- Name - resource skill full name.
- Code - A sequence of characters that should be unique for each multi-resource. Code is made up by letters, figures and
special characters (#$%&@_-~) without spaces and is case sensitive.
- Type – type of the resource skill.
- Type DPH – shows that if the DPH type of the resource skill is calculated By Quantity or By Productivity.
Page Participants.
Contains a list of resources and multi-resources comprising current resource skill. List also contain resources comprising
multi-resources. For each item following details are displayed: type (resource or multi-resource); its name, code and
priority.
- Add frame – contain two buttons:
- Resource - lets you add new resources to resource skill;
- Multi-Resource - lets you add new multi-resources to resource skill;
Pressing these buttons invokes dialog window with a list of project resources (or multi-resource). You can
select one or several desired resources (or multi-resource) from the list with left mouse button and press OK.
Note that the same resource (or multi-resource) cannot be added twice to one resource skill.
- Delete – removes selected resource (or multi-resource) from current resource skill composition.
- Update content – enables update current resource skill assignments globally in the project with new properties and
composition. Note that historical project data cannot be updated, i.e. in ongoing project with included performance data
updating of resource skill properties would not affect data before the project data date. Current resource skill activity
assignments are updated with following peculiarities:
- resource skill assignments are not changed for completed activities;
- resource skill assignments are changed for uncompleted activities only if resources comprising current
resource skill have not actually participated in activity execution.
Otherwise, if resources have already been involved on activity, their composition and quantity assigned would
not be updated for further activity execution (even if resource was completely removed from multi-resource or
resource skill - assignments of this resource would not be removed; you can delete such assignments only
manually with subsequent lost of material consumed and cost components spent on these assignments).
- Delete skill assignments – removes all current resource skill assignments from the project.
- Priority – defines the order of current resource (multi-resource) assignment in resource constrained scheduling.
Resources (multi-resources) with higher priority (i.e., greater value) are assigned first. To view/change priority first
select resource (multi-resource) from the list with left mouse button click.
110
Resource Skill
1. Invoke new Resource Skill Properties dialog window by one of the following methods:
- Select New from shortcut menu invoked with the right mouse button click on material row number; or
- Hit Insert key on the keyboard; or
- Click on empty gray area below the table with the right mouse button and select New option in the invoked shortcut
menu.
Note that properties dialog window will be opened automatically for newly created resource skill only if you have
selected to Open properties for new created objects in the spider project parameters dialog window. Otherwise newly
created resource skill will be saved with default parameters and you will have to invoke Resource Skills Properties
dialog window by double click on new resource center row number (or by selecting Properties from shortcut menu
invoked with a right mouse button click on new resource skill row number)
2. Set up resource skill properties in the invoked Resource Skill properties dialog window and click OK.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To learn more about working with Resource skills table, see working with tables.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
111
Team
14. Teams
14.1. Team
Team is a group of resources that work together on activity assignment.
Teams can be assigned to activities independently. In different time periods different teams can be engaged in activity
performance what makes it possible to model shift work.
You can view and edit performance data of a team assigned to activity execution in this dialog window.
Title of dialog window contains team name and the name of activity, to which the team was assigned.
Page Data
Activity – name and code of activity, to which the team was assigned;
Team – name and code of assigned team;
Responsible – name of person responsible for activity execution;
Start; Finish – beginning and ending of monitored period (for which performance data is entered). You can edit dates in
these fields directly (click once with left mouse button, enter date and time in the following format: ‘DD.MM.YYYY
HH.SS’ and press Enter) or double click on the cell and select required date and time in opened calendar window.
Example of date and time cell value: 13.03.2003 08:00.
Frame Volume:
Before – scheduled part of activity volume (in activity volume units), that the team is assigned to perform (prior to
the Start date of monitoring period);
Done – actual volume of activity that the team performed during the monitored period.
By default, part of activity volume, scheduled for the team for monitored period, is displayed in this field. You can
correct this value according to actual volume, performed by the team.
Remaining - remaining part of activity volume (in activity volume units). By default, part of activity volume,
remaining after the monitored period, is displayed in this field. You can correct this value according to actually
remaining volume that the team would have to perform.
Frame Duration:
Before – scheduled time (in hours) that the team is assigned to spend on activity execution (prior to theStart date of
monitored period);
Done – actual resource-hours, spent by the team on activity execution.
Note that the value of actual resource-hours participate in automatic calculation of assignments’ cost (e.g.
resources that consume materials per hour of their work or spend cost components per hour of their work). By
112
Team
default, scheduled duration of team work for monitored period is displayed in this field. You can correct this value
according to actual resource-hours, spent by the team on activity execution.
Remaining - remaining duration of team work in hours. By default, scheduled duration of remaining team work is
displayed in this field. You can correct this value according to actually remaining duration of team work in hours.
Page Assignments
Page Assignments contains a list of resources, multi-resources and resource skills – assigned to activity execution as part
of current team.
You can view and edit properties of monitored resources assignment (also for resources comprising multi-resources and
resource skills): select required resource from the list and press Properties button.
To delete resource, multi-resource or resource skill assignments from monitoring (e.g. excluding resources that have not
actually participated in activity execution during monitored period) – select required object and press Delete button. Note
that deleted objects are excluded from current monitored period only.
You can set properties of team assignment in this dialog window. Team assignment dialog window consists of following
pages: Data, Assignments, Notes standard page,
Page Data:
- Name, Code – these fields set team name and code;
- Fixed – checking this box lets current team to perform only part of activity’s volume or duration.
You can assign team to carry out part of Productivity type activity work in two ways:
- In activity volume units: choose Fixed Activity Volume Unit option and specify amount of work to be
performed by current team in correspondent units in Volume field;
- In percent of total activity work: choose Fixed Activity Volume Percent option and specify percent of work to
be performed by current team.
Note that these checkboxes are disabled for all types of activities but Productivity.
To assign team to carry out part of Duration type activity specify duration in hours (field Duration (hours)) or in days
(field Duration (days)) that the team should be engaged in activity performance.
If you leave box Fixed unchecked activity teams would be assigned volume or duration automatically.
113
Team
This dialog window allows you to assign a team to a group of (selected) activities.
114
Assignment
15. Assignments
15.1. Assignment
Resource assignment to activity execution.
Resource Assignments Table contains list of all resources assignments to activities. By default, contains following
columns (fields):
- Code of Activity – code of activity to which current assignment was made;
- Code of Resource – code of resource, assigned to activity;
- Name of Activity – name of activity to which current assignment was made;
- Name of Resource – name of resource, assigned to activity;
- Variable Work Load and Number – defines whether coefficient of work load and number of assigned resources should
be calculated during schedule calculation;
- Type DPH defines DPH activity type – duration, productivity, hammock or milestone.
- Type – default field for organizing of data transfer from reference-books for changing of activity properties. Activities
with similar characteristics (e.g. sharing materials consumption, having the same cost components) can have the same
Type.
E.g., activity ‘construction of brick wall’ can have type ‘BRICK_WALLS’, or ‘BW’.
- Interruptability – defines, whether splits in activity performance are enabled or not.
- ASAP, ALAP preferable time of activity performance – either ‘as soon as possible’ or ‘as late as possible’.
- Folder - full path to attached folder, that may be used to store files with referential information for current assignment.
Double click on the cell in this column allows defining the folder path or open the folder (if its path has already been
defined).
- OLE objects; icon defines whether documents of other applications (Word, Excel etc.) are attached to an
assignment. Double click on this field opens resource assignment properties dialog window on OLE objects and Folder
page.
- Notes - A field that lets users to provide an assignment with notes and explanations. Double click on this field opens
resource assignment properties dialog window on Notes page.
- Unique Assignment Code - Unique code, automatically generated according to activity code, resource code and Index,
connected by underline symbol;
- Assignment Index - editable number to be added to assignment Code to ensure its uniqueness to activity several times
(for example, the same resource as part of different resource skills or multi-resources assigned to activity).
- Start – date, when assigned resource starts to execute the activity. If an activity has not actually started, this field would
be equal to Start [ASAP]. If activity is already being executed and performance data is added to monitoring, this field
would be equal to Start [Actual].
- Finish - date, when assigned resource finishes working on the activity. If an activity has not actually finished, this field
would be equal to Finish [ASAP]. If activity has already been executed and performance data has been added to
monitoring, this field would be equal to Finish [Actual].
- Duration, Days [Remaining] – remaining duration of resource work in days according to calculated schedule;
- Duration, Hours [Remaining] – remaining duration of resource work in hours according to calculated schedule;
- Volume [Remaining] – remaining work volume (in corresponding units) that the resource should perform.
- Volume unit –activity units (e.g.,’m2’, ‘pieces’);
- Total Cost [Remaining] – remaining costs of assigned resource work; include all cost components;
- Float, hours; Float, days – assignment float duration in hours or days.
- Quantity [Scheduled] – estimated number of resources, required for activity execution;
- Quantity- user assigned number of resources for activity execution;
115
Assignment
- Quantity [Minimal] – minimal number of resources assigned to activity execution; this value can be entered for
assignments with Variable quantity and Work load enabled in the assignment properties dialog window. Minimal
quantity value participates in calculation of resources quantity, assigned to activity (Quantity [Scheduled])
- Productivity – productivity of one resource unit per hour (i.e. number of activity volume units, that current resource can
execute per hour)
- Work Load – work load of one resource unit, assigned to activity execution. Work load is set in percent of resource
working time that the resource is to spend on activity execution. By default work load is equal to 100%.
- Work Load [Scheduled] – calculated work load coefficient for one resource unit, assigned to activity execution. If
resource is assigned to activity execution as part of multi-resource, its scheduled work load would be equal to resource
work load multiplied by multi-resource work load;
- Priority – defines the order of resources use on activity execution in resource constrained scheduling. Resources with
higher priority (i.e., greater value) are assigned first.
- Start [ASAP] (as soon as possible) – the earliest possible point in time on which resource can start to perform activity,
based on the network logic and any schedule constraints. ASAP Start dates can change as the project progresses and
changes are made to the project plan.
- Finish [ASAP] (as soon as possible) - the earliest possible point in time on which the resource can finish to perform the
activity, based on the network logic and any schedule constraints. ASAP Finish dates can change as the project
progresses and changes are made to the project plan.
- Start [ALAP] (as late as possible) – the latest possible point in time on which the resource can start to perform the
activity without delaying the project finish date.
- Finish [ALAP] (as late as possible) – the latest possible point in time on which the resource can finish to perform the
activity without delaying the project finish date.
- Start [Actual], Finish [Actual] – actual dates on which the resource started and finished activity execution according to
included performance data;
- Start [NET], Finish [NLT] –constraint on the start (not earlier than) and finish (not later than) dates of activity
execution, to which resource is assigned.
- Duration, Hours [Actual] - total actual activity duration in hours according to included performance data;
- Volume [Actual] - actual activity work volume performed (in corresponding units) according to included performance
data;
- Total Cost [Actual] - actual cost of resource work on the activity execution according to included performance data;
- Total Cost [Cumulative] – equals to actual cost plus remaining cost;
- Start [Critical], Finish [Critical], Total Cost [Critical] – critical activity start, finish dates and total cost; these values
are used in risk analysis;
- Start [Buffer], Finish [Buffer], Total Cost [Buffer] – buffer values, used in risk analysis;
- Start [Original]; Finish [Original] –start and finish dates of resource work on activity execution in original project
version (see projects comparison for details);
- Duration, Hours [Original]; Volume [Original]; Total Cost [Original] – duration of resource work (in hours), volume
that the resource is to perform (in corresponding units) and total cost resource work in original project version (see
projects comparison for details);
- Completion Variance, Days – difference in ASAP finish dates of the resource work in current and original project
versions in days (see projects comparison for details);
- OCWP – Original Cost of Work Performed, cost of resource work performed according to original project version;
- OCV – Original Cost Variance, variance of resource work cost in comparison to original project version. Equals to
difference between OCWP and actual cost of resource work (Total Cost [Actual]);
- User defined fields;
- Fields with fixed, remaining and actual consumption of all materials (and material centers) and expenditures of cost
components (and cost centers); their profiles.
To delete an assignment in assignments table: select assignment row with left mouse button click and press Delete button,
or
invoke shortcut menu by right clicking on row number and choose item to Delete,
or
select menu items Edit -> Delete.
116
Assignment
Note that: To delete several assignments select desired rows with left mouse button clicks (keep Ctrl button pressed) first,
then perform one of the actions, described above for deleting of single assignment.
To edit existing assignment properties double click on corresponding activity row number,
or
invoke shortcut menu by right clicking on row number and choose item Properties.
See general description of tables in Spider Project for common rules of working with tables.
Replace Assignments dialog window will be invoked. Select assignment you want to replace with from the list of
assignments available. The list would vary depending on selected option: Resources, Multi-Resources, or Resource Skills.
You can also edit assignment properties such as Quantity, Productivity, Work Load, Fixed Expenditure, and Expenditure
per Hour (for materials and cost components).
You can change assignments of a particular or several resources, multi-resources or resource skills for another resource,
multi-resource or resource skill. To change assignments, select appropriate resources (multi-resources or resource skills),
117
Assignment
invoke shortcut menu and select new assignment from the list of all assignments available. The list varies depending on
selection you made: Resources, Multi-Resources, or Resource Skills.
One or several assignments can be replaces with one assignment at a time. If several assignments are replaced each of
them will be replaced with a new assignment chosen (even for one activity).
You can replace assignments of one type only at a time, e.g. one or several resources – with one resource/multi-
resource/resource skill.
In Values frame, edit highlighted (i.e. selected) assignment values such as Quantity, Productivity, Work Load, Fixed
Consumption, Consumption per Hour and Consumption per Volume Unit. Choose from Leave as it is, Multiply by and
Make equal options. Leave as it is option will leave assignment’s values as they were. Multiply by option will multiply old
values of assignment parameters to the numbers you enter in the corresponding fields. Make equal option makes new
assignment values equal the numbers you have entered in the corresponding fields.
15.7. Resource-Hours
Resource-hours equal to the period (in hours) resource spends on activity execution.
Assignment resource-hours equal to resource work load multiplied by assignment duration and multiplied by the number of
resources assigned.
Activity resource-hours equal to the sum of all assignment resource-hours for all assignments in activity.
When several assignment rows are highlighted simultaneously, all of them will be deleted from the project.
To perform this, hold Ctrl key and click assignment row numbers to be deleted. They will stay highlighted in gray. Click
with the right mouse button one of the highlighted row numbers and shortcut menu containing Replace Assignments by
and Delete options will be invoked. Select Delete and confirm group of objects deletion when a corresponding message
appears.
118
Assignment
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Dialog window of Activity Resource Assignment Properties lets to view and edit assignment properties of resources
assigned to activity. Consists of the following pages: Data, Materials standard page, Cost Components standard page ,
Materials standard page Notes standard page , and OLE-objects and Folder standard page.
Page Data
- Activity, Resource – text fields, displaying names of activity and resource assigned to this activity.
- Button Properties, situated to the right of Activity and Resource fields, allows opening of corresponding dialog windows
of activity properties and resource properties.
- Code – Unique code, automatically generated according to activity code, resource code and Index, connected by
underline symbol.
119
Assignment
- Index – editable number to be added to assignment Code to ensure its uniqueness to activity several times.
- Quantity – quantity of resource units, assigned to activity.
- Productivity – productivity of one resource unit per hour (i.e. number of activity volume units that current resource can
execute per hour).
- Type – default field for organizing of data transfer from reference-books. Corresponds to current resource type.
- Work Load – work load of one resource unit in percent of total resource working time that the resource is to spend on
activity execution. By default work load is equal to 100%.
- Priority – priority of assignment (is used for resources belonging to resource skills) - defines the order of resources
assignment in resource constrained scheduling. Resources with higher priority (i.e., greater value) are assigned first
- Scheduled Quantity – estimated number of resource units, required to perform activity.
- ASAP Start, ASAP Finish – start and finish dates of activity assignment, calculated according to ASAP method, i.e.
dates are scheduled as soon as possible keeping all constraints satisfied.
- ALAP Start, ALAP Finish – start and finish dates of activity assignment, calculated according to ALAP method, i.e.
dates are scheduled as late as possible without delaying the project finish date.
- Float (hours) - activity assignment float in hours.
- Float (days) - activity assignment float in days.
- Resource-hours – amount of time (in hours) required for the resource to complete the activity; actually represents
calculated remaining resource-hours.
‘Assignment resource-hours’ can be calculated as assignment duration multiplied by resource work load and multiplied
by the number of assigned resources. ‘Activity resource-hours’ can be calculated as sum of all corresponding
assignments’ resource-hours.
- Variable quantity and work load frame – checking the box Variable quantity and work load enables to enter Minimal
quantity and/or Minimal work load. These values participate in calculation of resource work load coefficient and
quantity assigned to activity.
After schedule calculation, values of work load, quantity, productivity and duration of resource assignment are
displayed for each period of resource involvement in activity execution on page Periods.
If box Variable quantity and work load is unchecked values from Quantity and Work Load fields are used.
Page Periods.
If box Variable quantity and Work Load is checked on page Data, values of Work Load, Quantity, Productivity and
Duration of resource assignment are displayed for each period of selected resource involvement in activity execution. To
view these data select required resource assignment with a mouse click.
This dialog window allows you to assign a resource to a group of (selected) activities.
120
Assignment
To delete resource assignment from activity gantt, select Expand to Assignments by clicking icon on activity gantt
toolbar. Assignments will become shown in activity gantt. Select assignment you want to delete, invoke Assignment shortcut
menu with the right mouse button click on the row number, and select Delete.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
- Delete deletes assignment from the project. When several assignment rows are highlighted simultaneously, all of them
will be deleted from the project.
121
Assignment
To delete several assignments, hold Ctrl key and click assignment row numbers to be deleted. They will stay highlighted
in gray. Click with the right mouse button one of the highlighted row numbers and shortcut menu containing Replace
Assignment by… and Delete options will be invoked. Select Delete and confirm group of objects deletion when a
corresponding message appears.
To cancel last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Dialog window of Resource Assignment to a Group of Activities lets you make assignments simultaneously to a group of
activities. This option is especially useful to add the same assignment to several activities or to replace assignments.
122
Assignment
Dialog window contains a list of currently made assignments in this dialog window for selected group of activities
(existing individual activity assignments are not shown) – Type and Code of assigned teams, resources, multi-resources
and resource skills. Each time you open this dialog window (even repeatedly for the same group of activities) the list will
be shown empty until you add assignments.
Frame Add contains buttons, allowing you to add Resources, Multi-resources, Resource skills and Teams, to the list of
common assignments. Additional parameters can be set in opened dialog window after selecting of assignment type: team
dialog window, resource dialog window, multi-resource dialog window and resource skill dialog window.
Button Properties allows you to view and edit properties of the object selected from the list. Delete button removes
assignment from the list.
Frame Method allows you to choose desired method of adding assignments to the group of activities:
- Add new – adds assignments from the list to existing activities assignments (i.e., keeps existing and adds new). Note
that assignments are identified according to their codes and only assignments with missing codes are added
- Replace all – removes existing activities assignments and replaces them with assignments currenly entered to the list.
Note that: assignments already involved in activity execution can not be deleted and thus ‘replaced’.
Multi-resource assignment properties dialog window is invoked for multi-resources assigned to activities from activity
properties dialog window. Dialog window consists of following pages: Data, Components, Notes standard page, OLE-
objects and Folder standard page.
123
Assignment
Page Data
- Name – text fields, displaying names of multi-resource assigned to this activity.
- Code – multi-resource’s code.
- Quantity – quantity of multi-resource units, assigned to activity.
- Type – default field for organizing of data transfer from reference-books.
- Productivity – is the productivity of a multi-resource per hour. Duration of Productivity type activity is calculated
according to multi-resource productivity (ignoring productivities of comprising resources); if productivity for multi-
resource were not set it would be equal to sum of productivities of comprising resources.
- Work Load – work load of one multi-resource unit in percent of total multi-resource working time that the multi-
resource is to spend on activity execution.
- Scheduled quantity – estimated number of multi-resource units, required to perform activity.
- Priority – priority of assignment (is used for multi-resources belonging to resource skills) - defines the order of
resources assignment in resource constrained scheduling. Resources with higher priority (i.e., greater value) are
assigned first
- Variable quantity and Work load frame – checking box Variable quantity and work load enables entering of Minimal
quantity and/or Minimal work load. These values participate in calculation of multi-resource work load coefficient and
quantity assigned to activity and define the allowed range for these parameters.
After schedule calculation, values of workload, quantity, productivity and duration of multi-resource assignment are
displayed for each period of multi-resource involvement in activity execution on page Periods.
If box Variable quantity and work load is unchecked values from Quantity and Work Load fields are used.
Page Assignments
Contains a List of resources, comprising current multi-resource.
- Resource button allows adding new resource(s) to the current multi-resource assignment. Note that adding resources to
multi-resource assignment affects current assignment only and do not change composition of multi-resource globally in
the project (i.e. in the Multi-resources table and other assignments).
- Properties – invokes selected resource assignment properties dialog window.
- Delete – press this button to delete selected resource from assignment to current activity.
Page Notes
- Comments can be added to current Multi-resource Assignment on this page
124
Assignment
125
Assignment
Multi-Resource Shortcut Menu can be invoked with right mouse button click on row number corresponding to a multi-
resource.
- Properties – opens multi-resource assignment properties dialog window;
- Replace assignments by… – lets replace all assignments of the current multi-resource with a different multi-resource,
resource, or resource skill through replace assignments dialog window;
- Delete – deletes current multi-resource assignment.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
126
Assignment
You can set properties of resource skill assignment in this dialog window. Resource skill assignment dialog window
consists of following pages: Data, Components, Notes standard page.
Page Data:
- Name, Code, Type – these fields set resource skill name, code and type;
- Frame Type DPH lets to choose between two types of resource skill assignment:
- By Quantity – checking this box determines the program to search available resources in amount, specified in
Quantity field, among resources, comprising the skill;
- By Productivity - checking this box determines the program to search available resources with adequate
productivity (specified in Productivity field) among resources, comprising the skill.
Checking By Quantity box enables Quantity field, while checking By Productivity box - enables Productivity
field and lets to edit corresponding figures.
Page Participants.
Contains the list of multi-resources and resources, comprising current resource skill.
To add new resource or multi-resource to the current resource skill assignment, press Resource or Multi-resource buttons
to select new component. Note that changes made to the composition of resource skill on particular assignment would
affect neither resource skill composition in the Resource Skills Table, nor on other assignments.
You can remove selected multi-resources or resources from current assignment of resource skill – select required item and
press Delete button.
Update Content updates the content of all assignments of the selected resource skill.
Priority Resources (multi-resources) with higher priority of assignment (i.e. larger number of priority) are scheduled to
activity execution first (if they are not busy on others, e.g. higher priority, activities). Priority of resources (multi-
resources) assignments to current activity refers to current activity only.
When resource skill is assigned to activity execution, priorities of comprising resources (multi-resources) are initially set
to values specified for this resource skill. You can later change priorities of resources (multi-resources) assignments
manually for each activity.
127
Assignment
- By Productivity - checking this box determines the program to search available resources with adequate
productivity (specified in Productivity field) among resources, comprising the skill.
Checking By Quantity box enables Quantity field, while checking By Productivity box - enables Productivity
field and lets edit corresponding figures.
- Notes – allows you to enter notes to current assignment;
To delete resource skill assignment from activity gantt, select Expand to Assignments by clicking icon on activity gantt
toolbar. Assignments will be shown. Highlight resource assignment to be deleted, invoke Assignment shortcut menu with the
right mouse button click on its row number, and select Delete.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
128
Assignment
4. If several resource skills are highlighted simultaneously in Resource Skills dialog window, Resource Skill Assignment
dialog window will not open, and all resource skills will automatically be set up in quantity of 1.
5. To include new resource assignment data to the project, click OK in Activity Properties dialog window. All resource
skills assigned will automatically be added to Resource Skills table.
Change resource skill value in the bottom of Assignments page of Activity Properties dialog window. Or – when resource
skill is highlighted –click Properties to invoke Resource skill Assignment dialog window.
To delete resource skill assigned to activity, highlight it in the list on Assignments page of Activity Properties dialog window
and click Delete. After you confirm deletion, resource skill assignment will be deleted from the project, but the resource skill
will remain in the project.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
129
Assignment
You can set properties of team assignment in this dialog window. Team assignment dialog window consists of following
pages: Data, Assignments, Notes standard page,
Page Data:
- Name, Code – these fields set team name and code;
- Fixed – checking this box lets current team to perform only part of activity’s volume or duration.
You can assign team to carry out part of Productivity type activity work in two ways:
- In activity volume units: choose Fixed Activity Volume Unit option and specify amount of work to be
performed by current team in correspondent units in Volume field;
- In percent of total activity work: choose Fixed Activity Volume Percent option and specify percent of work to
be performed by current team.
Note that these checkboxes are disabled for all types of activities but Productivity.
To assign team to carry out part of Duration type activity specify duration in hours (field Duration (hours)) or in days
(field Duration (days)) that the team should be engaged in activity performance.
If you leave box Fixed unchecked activity teams would be assigned volume or duration automatically.
Hammock and Milestone type activities do not have Fixed option.
- ASAP Start, ASAP Finish – start and finish dates of assigned team work, calculated according to ASAP method, i.e.
dates are scheduled as soon as possible keeping all constraints satisfied.
- ALAP Start, ALAP Finish – start and finish dates of assigned team work, calculated according to ALAP method, i.e.
dates are scheduled as late as possible without delaying the project finish date.
- Float (hours) - activity assignment float in hours.
- Float (days) - activity assignment float in days.
Page Assignments
Contains list of team resource skills, multi-resource and resources – assigned to activity execution.
To add new resource(s), multi-resource(s) or resource skill(s) press the corresponding button in Add frame: Resource,
Multi-Resource or Resource Skill.
You can delete selected object from the list with Delete button or view its properties. Pressing Properties button invokes
corresponding resource skill assignment properties dialog window, multi-resource assignment properties or resource
assignment properties.
This dialog window allows you to assign a team to a group of (selected) activities.
130
Assignment
For activities of Duration type, you can assign a team to participate in part of activity duration execution: check box
Fixed and set required Duration (hours) value.
If box Fixed is unchecked, all assigned teams will participate in activity execution according to schedule calculated by
Spider Project.
131
Excluded Objects
132
Excluded Objects
133
Cost Component
134
Cost Component
Note That: Translate to unit recalculation will take effect only after recalculation of project costs.
Note That: if you set correction factor equals to zero, unit costs for all cost components and cost periods will be set to
zero after recalculation and you will loose all your unit cost data after if the project be saved.
Contains cost components data. When the project is first created, one cost component with code ‘1’, ‘Cost Component 1’
name, and unit cost equaling 1, is added to Cost Components table.
Cost components table contains the following standard fields (columns) for each cost component:
- Code is a sequence of characters, unique for each cost component. Code is made of letters, numbers, and special
characters (#$%&@_-~) without spaces, and is case sensitive.
- Name is a cost component name.
- Name for Columns is alternative cost component name to be shown in table columns.
For example, there are fixed costs columns in Activities table. These columns headers will be taken from Name for Columns
field of a corresponding cost component. If the field is left blank, headers will use cost component Name.
- Notes contains comments to cost component (if any). Double click in the cell invokes Cost Component properties dialog
window opened on notes standard page.
- Folder is a field containing full path to attached folder. Invoke Folder shortcut menu with the right mouse button click in
cells, containing:
- Select simplifies folder path entry evoking standard browsing window (or double click on cell).
- Edit allows path editing directly in cell (or press Enter key on the keyboard when the cell to edit is highlighted).
- Open opens attached folder.
- OLE objects field contains icon if any other applications documents are attached to cost component. Double click in
the cell invokes Cost Component properties dialog window opened on the OLE-objects and Folder standard page.
- Unit Cost is coefficient to use when cost component is included in total project expenditures and calculations.
- Consumption is the quantity of specific cost components spent in the project(it is reflected after conducting of calculating
the expenses)
- Income is the quantity of incomes of specific cost component in the project(it is reflected after conducting of calculating
the expenses)
- Total is the total quantity of incomes and expenditures of specific cost component in the project(it is reflected after
conducting of calculating the expenses)
- Discount Rate is assigned if it will be used with conducting of calculating the scale of economic effectiveness(see the cost
calculations and economic indices.)
- User-defined fields.
Note That: Starting with Version 8 of Spider Project, Initial Amount field was eliminated. When opening projects saved in
the older program versions, a milestone with Initial Amount name will be added in OBS and WBS main phases. This
milestone will have fixed cost component expense in the amount of Initial Amount.
Working with this table is made by the general rules, identical for all tables of the project.
Cost Component shortcut menu
Cost component shortcut menu is invoked with the right mouse button click on cost component row number and contains the
following options:
135
Cost Component
- Properties invokes Cost component properties dialog window to edit cost component properties.
- New allows creating new cost component by evoking Cost component properties dialog window and adds new row in
Cost components table.
- Delete deletes highlighted cost component and a corresponding row in Cost components table.
When several rows are highlighted simultaneously, shortcut menu contains Delete option only.
- Convert to unit. Unit cost of selected cost component will be set to 1 (and all cost periods' unit costs of selected cost
component will be set to 1 as well) and unit costs of all other cost components (and their cost periods' unit costs) will be
recalculated accordingly. E.g. for two cost components Materials_USD (with unit cost 1) and Materials_EUR (with unit
cost 1.1) Converting to Materials_EUR unit will recalculate Materials_EUR unit cost to 1 and Materials_USD unit cost
to 0.91 (=1/1.1). Correspondingly, cost center containing these two cost components expressed expenses in Dollars
before Convertion and will express expenses in Euro after such convertion.
After you invoke shortcut menu on certain cost component and choose Convert to unit you will be prompted to enter
Correction factor before recalculation is being performed. Correction factor - is a multiplier for all unit costs (and cost
periods' unit costs); correction factor is a fractional number. I.e. if you set correction factor to 2, unit cost of selected cost
component (the one you invoked shortcut menu on) and its cost periods' unit costs will be set to 2; unit costs for other
cost components and their cost periods will be calculated accordingly. By default correction factor is 1.
Note That: values of unit costs are presented according to the Number of digits after decimal point set in Spider Project
parameters dialog window.
Note That: after Convert to unit recalculation is performed, 'missing' cost periods will be automatically added to all cost
components and unit cost for these cost periods will be calculated. 'Missing' - means cost periods with starting date
existing for one cost component and non-existing for another.
Note That: if you set correction factor equal to zero, unit costs for all cost components and cost periods will be set to
zero after recalculation!
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Is an Object properties dialog window containing the following pages: Data page, Cost Centers Page, Notes standard
page, and OLE-objects and Folder standard page and Cost Periods page.
Data page
- Name is cost component name.
- Code is a sequence of characters, unique for each cost component. Code is made of letters, numbers, and special
characters (# $ % & @ _ - ~) without spaces, and is case sensitive.
136
Cost Component
- Name for Columns is a cost component name to be shown in costs table columns. If there are fixed costs columns in
Activities table, headers of these columns will be taken from Name for Columns for the field of a corresponding cost
component. If the field is left blank, headers will use cost component Name.
- Unit Cost is coefficient to use when cost component is included in total project expenses and calculations. Use ‘0’ Unit
Cost to exclude the cost component from final project calculations. Use negative Unit Cost value to show that this cost
component is related to project revenues.
- Discount Rate is set for use at calculation of expenses and economic parameters.
- Type the type of cost component usually used for communication with reference-books.
If the budget of the project is converted to unit (see Cost components) by any cost component unit cost of some cost
components can be left without change. For this purpose in the given window it is necessary to select option Not (to)
convert to unit.
Within the frame Formula it is possible to assign formulas by which the expenditure of this cost component will be
calculated. For this it is necessary to mark the option to Calculate by formula. After marking this option Edit button will
be activated in order to edit formulas. By pressing this button create formulae dialog window will be invoked.
Note that: Starting with Version 8 of Spider Project, Initial Amount field was eliminated. When opening projects saved in
the older program versions, a milestone with Initial Amount name will be added in OBS and WBS main phases. This
milestone will have fixed cost component expense for Initial Amount.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
137
Cost Component
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Working with this table is made by the general rules, identical for all tables of the project.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
138
Material
18. Materials
18.1. Material
Material is a nonrenewable resource. Examples of materials: concrete, bricks, wire, sand.
You can modulate materials production (delivery) by setting up negative material consumption.
Material consumption can be set up for:
- Activities;
- Resources; and
- Resource Assignments.
Materials production modeling
In Spider Project, you can modulate materials production (delivery) by setting up negative material consumption for activity.
By setting up materials production, Resource Constrained Scheduling can be performed by material constrains (select
Materials option in Scheduling Options dialog window for Resource Constrained Scheduling).
You can also optimize delivery scheme to optimize project finish dates.
Includes all project materials data and contains the following columns (fields) by default:
- Code is a sequence of characters, unique for each material. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive. .
- Name is material name.
- Name for Columns is material name to be reflected in table column headers. If this field remains empty, material Name
will be reflected in columns.
- Notes contains comments to material (if any). Double click in the cell invokes Material properties dialog window opened
on notes standard page.
- Folder is a field containing full path to attached folder. Invoke Folder shortcut menu with the right mouse button click in
cells, containing:
- Select simplifies folder path entry evoking standard browsing window (or double click on cell).
- Edit allows path editing directly in cell (or press Enter key on the keyboard when the cell to edit is highlighted).
- Open opens attached folder.
- OLE objects field contains icon if any other applications documents are attached to the material. Double click in the
cell invokes Material properties dialog window opened on the OLE-objects and Folder standard page.
- Unit
- Consumption
- Supply
- Total
- Discrete Consumption
- Backload Consumption
- User-defined fields.
Material unit costs by all cost components are also included in Materials table.
Note That: Starting with Version 8 of Spider Project Software, Initial Amount field was eliminated. When opening projects
saved in the older program versions, a milestone with Initial Amount name will be added in OBS and WBS main phases. This
milestone will have fixed cost component expense in the amount of Initial Amount.
Working with this table is made by the general rules, identical for all tables of the project.
139
Material
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
Is dialog window allowing editing material properties. Contains the following pages: Data, , Cost components, Cost
Centers Material Centers Notes standard page, and OLE-objects and Folder standard page and Cost Periods
Data page
- Name is material name.
- Code is a sequence of characters, unique for each material. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is material name to be reflected in table column headers. If this field remains empty, material Name
will be reflected in columns.
- Unit is unit for the material. For example, cubic meter, kilometer, square meter, liter, etc.
Note that: Starting with Version 8 of Spider Project, Initial Amount field was eliminated. When opening projects saved in
the older program versions, a milestone with Initial Amount name will be added in OBS and WBS main phases. This
milestone will have fixed cost component expense for Initial Amount.
140
Material
necessary to establish Discrete Consumption. Thus, the software will consider that the material can be spent by pieces at
schedule calculations and at generating reports.
Depending on a material, the consumption of 1, 5 units can mean or the charge of one unit, or two. The second button-
switch (Backload Consumption sets the way of expenditure in such cases). Selecting this option approximates the charge in
the smaller party, accordingly, unselecting - in greater.
Note that: For the materials spent discretely, it is necessary to set only integers fixed and actual. If the user will set the
fractional charge, the program will automatically approximate it at schedule calculations and at generating reports. Per hour
consumptions, can be set by fractional numbers.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
141
Material
To learn more about working with Materials table, see working with tables.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
142
Material and Cost Component Consumptions
Is included to Object properties dialog windows and allows editing costs properties. It contains:
- Add button invokes Cost Components properties dialog window containing list of all cost components available. Select
one or several cost components from the list and click OK. You will be returned to Cost Components page.
- List contains list of all cost components assigned to object.
- Fields located below the list vary depending on the edited object. (To delete cost component from the list, leave the fields
empty.)
In Activity properties dialog window
Fixed Cost (component) is Activity fixed cost, in units of highlighted cost component.
Fixed Cost (all components) is total activity fixed cost by all cost components (with their unit cost taken into consideration).
Hour Cost (component) is cost of one hour of activity duration, in units of highlighted cost component.
Hour Cost (all components) is total cost of one hour of activity duration by all cost components (with their unit cost taken
into consideration).
Volume Unit Cost (component) shows cost of unit of scheduled volume of operation in terms of the cost component chosen in
the list.
Volume Unit Cost (all components) shows total cost of unit of scheduled volume of operation on all cost components in view
of cost of their units.
Remaining Cost (component) is remaining activity cost, in units of highlighted cost component.
Remaining Cost (all components) is total remaining activity cost by all cost components (with their unit cost taken into
consideration).
Profile (component) – shows the charge of the chosen cost component in the beginning and the end of the period
Actual Cost (component) – is displayed after entering the monitoring information into the project and shows the actual charge
of a cost component.
143
Material and Cost Component Consumptions
Remaining Cost (component) is remaining resource cost, in units of highlighted cost component.
Remaining Cost (all components) is total remaining resource cost by all cost components (with their unit cost taken into
consideration).
Actual Cost (component) – is displayed after entering the monitoring information into the project and shows the actual charge
of a cost component a resource.
144
Material and Cost Component Consumptions
This page is a member of object properties dialog window and allows adding, editing, and deleting material consumptions for
activities, assignments, or resources.
- List contains the list of all materials assigned.
- Add allows to select a new material from materials list dialog window. Select material from the list and click OK.
- Fields in the bottom of window set up material consumption. If several materials are assigned, material consumption
fields correspond to the highlighted material.
To delete a material (remove it from current assignment), leave fields for material consumption empty or enter value "0"
(zero).
Material consumption fields vary, depending on object properties dialog window, where the Materials standard page is
opened:
145
Material and Cost Component Consumptions
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
146
Material and Cost Component Consumptions
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
147
Material and Cost Component Consumptions
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
148
Material and Cost Component Consumptions
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
149
Material and Cost Component Consumptions
4. Open Materials page and click Add button. This will invoke Materials dialog window containing list of all materials
available. Select one or several materials from the list and click OK. You will be returned to Materials page. Set up the
following properties for new material(s) consumption in the bottom of the page:
- Fixed cost
- Consumption per hour.
- Per Volume Unit
5. Click OK.
Note That: Material consumption by resource cannot be edited directly in Activity Network.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
150
Material and Cost Component Consumptions
1. Click Expand to Assignments icon on activity gantt toolbar to make assignments be seen in activity gantt.
2. Invoke Assignment properties dialog window with double click on assignment row number or by selecting Properties
from Assignment shortcut menu invoked with the right mouse button click on assignment row number.
3. Open Cost Components page and click Add button. This will invoke Cost Components dialog window containing the list
of all cost components available. Select one or several cost components from the list and click OK. You will be returned
to Cost Components page. Set up the following properties for new cost component(s) in the bottom of the page:
- Assignment fixed cost; and
- Hour Cost
- Volume Unit Cost.
4. Click OK
Alternatively, cost can be set up directly in cells of table part of activity gantt. To perform this, double click a corresponding
cell, edit contents, and press Enter key on the keyboard.
Note That: Resources and materials cost cannot be edited directly in cells of table part of activity gantt.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
1. Click Expand to Assignments icon on resource gantt toolbar to make assignments be seen in resource gantt.
2. Invoke Assignment properties dialog window by double click on assignment row number or by selecting Properties from
Assignment shortcut menu invoked with the right mouse button click on assignment row number.
3. Open Cost Components page and click Add button. This will invoke Cost Components dialog window containing the list
of all cost components available. Select one or several cost components from the list and click OK. You will be returned
to Cost Components page. Set up the following properties for new cost component(s) in the bottom of the page:
- Assignment fixed cost; and
- Hour Cost.
4. Click OK
Alternatively, cost components can be set up directly in cells of table part of resource gantt. To perform this, double click a
corresponding cell, edit contents, and press Enter key on the keyboard.
Note That: Activities and materials costs cannot be edited directly in cells of table part of resource gantt.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
151
Material and Cost Component Consumptions
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
152
Material and Cost Component Consumptions
11. Click Properties button. This will invoke Resource Assignment properties dialog window.
12. Open Cost components page.
13. Click Add button. This will invoke Cost components dialog window containing list of all cost components available.
Select one or several cost components from the list and click OK. You will be returned to Cost components page. Set up
the following properties for new cost component(s) in the bottom of the page:
- Fixed cost; and
- Hour Cost
- Volume Unit Cost.
14. Click OK.
Note That: Activities and materials costs cannot be set up directly in resources table.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
153
Material and Cost Component Consumptions
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
154
Scheduling
20. Scheduling
20.1. Performing Schedule Calculation
Scheduling is process of project performance scheduling.
Set up constrains and optimization method in scheduling options dialog window.
Scheduling can be done using one of the four methods, which vary in the resulting schedule and calculation time:
- Standard is the quickest method used in all Western project management programs. This method performs scheduling
based on activity priorities set up in scheduling options dialog window.
- Advanced is method delivering more optimal schedule, but it takes longer time to calculate.
- Optimization is method using special algorithms during scheduling and, therefore, requiring a significant calculation time
due to large number of iterations performed.
- Previous version support is scheduling method with first priority set up on the activities sequence as in the project’s
previous version. When this method is selected, define previous version to be used to continue activities.
Previous support version allows you to avoid negative consequences of schedule changes. For example, if during project
performance a contract for materials delivery was signed, changes in schedule might involve fines or other problems.
Spider Project software gives you advantage of calculating resource constrained scheduling leveled by materials or cost
components: make selections in Scheduling Options dialog window.
Scheduling might be interrupted for the following reasons:
- There are obvious mistakes in project initial data (for example, negative activity volume);
- There are mismatches in project data (for example, resource quantity in assignment exceeds total quantity of that
resource in the project);
- There is attempt to use more material or cost component than available.
If scheduling was interrupted, a corresponding message will appear.
To start scheduling, click Scheduling (without resource constrains) or Resource Constrained Scheduling icon on
Gantt diagram toolbar.
After scheduling is finished, recalculate Cost and Materials and Resource Peak Work Load. Click Cost and Materials
icon on the toolbar (or select Calculations -> Cost and Materials from Gantt diagram menu) to start costs and material
consumption calculation.
Click Resource Peak Work Load icon on the toolbar (or select Calculations -> Resource Peak Work Load from Gantt
diagram menu) to start peak project resources work loads calculation.
155
Scheduling
You can include different objects in resource constrained scheduling: Materials, Cost Components, Material Centers, Cost
Centers, Material Sets and Total Cost. Checking required checkboxes enables leveling of selected items.
To define objects for leveling press corresponding button, select required items from the total list in the left part of
invoked dialog window and move them to the right part with the help of arrow button:
- Resources to level – opens dialog window for selecting particular resources to be leveled
- Materials to level – opens dialog window for selecting particular materials to be leveled
- Cost Components – opens dialog window for selecting particular cost components to be leveled
- Material Centers – opens dialog window for selecting particular Material Centers to be leveled
- Cost Centers – opens dialog window for selecting particular cost centers to be leveled
- Material Sets – opens dialog window for selecting particular material sets to be leveled
To select work breakdown structure with required phase priorities press WBS for Phase Priorities button and select one
from the list in structures dialog window.
You can customize calculation process with the aid of additional checkboxes:
- Show Report – gives a report after calculation
- Apply Phase Priorities – enables phase priorities in schedule calculation
- Disable Splits – checking this box disables splits for schedule calculation for all interruptable activities
- Minimize Parallel Activities – enabling this option maximizes resource load on higher priority activities with variable
resource assignment (variable resource quantity and work load is set assignment properties dialog window).
- Without float calculation – calculates schedule ‘as late as possible’ (ALAP) and thus no floats are produced;
- Calculate recommended schedule – recommended schedule will be calculated and shown in black in graphical part of
Activity Gantt. Non-critical activities in recommended schedule are scheduled to ensure that they would not become
critical with the same probability as was set for timely completion of the whole project (phase) set in Risk analysis
dialog window.
- Consider Portfolio Schedule – If this option is selected, project schedule will be constructed in its interrelations view
with other portfolio projects, and also in view of other portfolio projects’ loading resources, materials and costs
distribution (if they are chosen for alignment)
- Allow performance interruptions not longer than – enables activity interruptions and sets maximum duration of
possible interruptions in hours or days.
- Continuous performance not less than – sets minimum duration (in hours or days) of uninterruptable activity
performance for interruptable activities.
156
Scheduling
- Detailed information – By selecting this option activity, phase, department, resources and assignments in graphic part
of gantt chart will be displayed not by continuous rectangulars (from the start before the end), but intermittent,
according to calendar working hours.
- Ignore preceding activity links if activity in progress – links to the operations in progress at schedule calculation will be
ignored
- Show this window before resource constrained scheduling – checking this box invokes scheduling options dialog
window each time resource constrained scheduling is performed
- Show this window before scheduling – checking this box invokes scheduling dialog window options each time
scheduling (without leveling) is performed.
All options set in this dialog window are stored in project file and restored after opening.
Allows selecting objects for leveling and is invoked from Scheduling Options dialog window (for Resource Constrained
Scheduling) by clicking Resource to level, Materials to level, Cost Components to level, Material Centers to level, or Cost
Centers to level and Material Sets to level buttons. Name of Select Objects for Leveling dialog window changes according to
what object was selected to level. If you click Materials to level, the dialog window name will be Select materials for
leveling, and it will contain materials in the lists.
The left list contains all selected category objects available in the project, and the right list contains objects to be leveled by.
After highlighting required objects, click >> button to move them from Resources to Resources to be leveled list, or use <<
to perform opposite action.
Use Search text field in the bottom of each list to search for certain objects in the list. Use Code and Name options to sort the
list by object codes or names, respectively.
Structures list dialog window can be opened from scheduling properties dialog window and lets you select source work
breakdown structure (WBS) for phase priorities: click with left mouse button on desired WBS and press OK button.
157
Scheduling
20.5. Work Load Calculation for All Activity Assignments with Preset
Duration and Productivity
This calculation is used for activities of Duration and Hammock types.
Calculates resource assignments work load so that, with productivities given, activity volume would be completely performed
during given activity duration. If this is not achievable, (resulting work load exceeds 100 %), corresponding error message
will appear.
If workload can be calculated, its amount will be entered in the corresponding activity assignment field.
158
Filters
21. Filters
21.1. Filters
Filtering is a quick and easy way to find and work with a subset of data. Filtering temporarily hides rows you do not want
to display. You can use filters in project tables (except monitoring table), Gantt charts and documents.
Spider Project lets you create and use two types of filters:
- Simple filter – logical expression, containing parameter and criteria, combined by comparison operator Less than, Less
than or Equal to, Greater than, Greater than or Equal to, Equal to, Not Equal to and Contains.
- Complex filter – combination of several other filters by logical operators: AND, OR, NOT.
Example of complex filter: (DurPlanD > 2) AND (DurPlanD < 10), where
DurPlanD – parameter - Activity duration in days [Remaining];
> - operator Greater than;
< - operator Less than;
2, 10 – criteria.
Current filter will select rows, corresponding to activities with remaining duration greater than 2 and less than 10 days.
159
Filters
New complex filter will be stored and its name will appear in the list of filters in filters dialog window.
Applying a Filter
Applying a filter to a table or a document temporarily hides all rows that do not meet filter criteria.
To apply a filter open filters dialog window (goto menu Filter -> Apply), select required filter from the list and press
Apply. The name of applied filter would appear in the window status bar (if no filter is applied you will see ‘Filter –
None’).
Only one simple or complex filter can be applied at the same time to a table or a document. Applied filter is stored within
a project or document. Its action can be canceled by applying another filter or selecting menu item Filter -> Restore.
Creating of a New Breakdown Structure from Filtered Activity Gantt or Resource Gantt Table
1. Apply filter to the table: open filters dialog window (goto menu Filter -> Apply), select required filter from the list
and press Apply.
2. Open structures list dialog window: in Activity Gantt goto menu Project -> WBS; in Resource Gantt goto menu
Project -> OBS;
3. Press button Copy Filtered.
160
Filters
Allows setting up simple filter and contains the following options and fields:
- Name field contains filter name.
- Field frame contains Name and Code fields to be used to filter data.
- Select button invokes fields available dialog window containing list of all available fields. Select one and click OK to
return back to Simple Filter dialog window.
- Condition and Value are text fields to set up filtering conditions.
If you leave Value field empty, ‘0’ will be used for numerical fields and empty cell for text fields. Empty Value field for date
fields can only be filtered with Equal to (resulting in no date) or Not Equal to (resulting in any date) conditions.
For date-time fields, you can use DataDate pseudo-variable for current project time. To set up time shift from the project
current time, add date shift (in days - negative or positive value) after DataDate, separated with space.
E.g. if you want to filter all activities that are scheduled to start within 5 days since current project time make a simple filter
with settings shown in the example.
Apply to Substring (For text fields only) frame lets you specify symbol number (Length) and starting symbol number (from)
to compare specified Field with entered Value. For example (as it is shown in the picture above), you can filter all activities
with codes, where the third symbol is less than ‘b’, i.e. is ‘a’. If Length is left blank it is assumed that you wish to search in
string (Field) from specified symbol number to the end of string. If field From is left blank search would be performed from
the first symbol.
161
Filters
162
Formulae
22. Formulae
22.1. Formulae
Formulae are instruments to calculate table column values. Formulae can be added in any project table (except for Monitoring
table) and document and will be applied to all shown rows (others, for example, can be hidden with filter).
Formula syntax
In Spider Project, formulae are made of column codes separated with mathematical operators. Formula starts with column
code the calculation is performed for, followed by equality sign and a mathematical expression. Mathematical expression
contains column codes, operator, and functions.
Creating formula
To add formula in table:
163
Formulae
164
Formulae
Logical Operators
and
Logical AND takes True meaning if both arguments are True, and takes False if at least of the arguments is False.
Example: (DurPlanD>10) and (DurPlanD<20). If scheduled duration is less than 10 and greater than 20, then this expression
becomes True.
or
Logical OR takes True meaning if at least one argument is True, and takes False if both arguments are False.
Example: (DurPlanD>10) or (DurPlanD<0). If scheduled duration is greater than 10 and less than 0, then this expression
takes True.
not
Logical NOT changes argument meaning to the opposite.
Example: NOT (VolPlan>2). If scheduled volume is greater than 2, resulting expression becomes False.
xor
Excepting OR takes True meaning if only one argument is True, and takes False meaning if both of the arguments are either
True or False.
Example: (VolPlan=2) xor (VolPlan=10). If scheduled volume equals 2 or 10, expression takes True meaning.
Comparative operators
Operator Meaning Example
= Equals to VolPlan = 2
!= Not equals to VolPlan != VolFact
< Less than CostPlan < 20
> Greater than DurPlanD > 2
<= Less than or equals to CostPlan <= CostFact
>= Greater than or equals to CostFact >= CostPlan
22.5. Functions
Logical functions
if (Logical expression, Meaning_if_True, Meaning_if_False)
Logical expression is any expression containing logical operators and comparative operators and taking True or False
meaning.
Meaning_if_True is resulting meaning of IF function when Logical expression was True.
Meaning_if_False is resulting meaning of IF function when Logical expression was False.
Example: VolPlan = if(VolPlan>100, 100, VolPlan). This formula checks meaning of scheduled activity volume. If
scheduled activity was greater than 100, formula would return its meaning as 100. If scheduled activity was less than 100, its
meaning would remain in table the same as it was before the formula was applied to it.
Mathematical functions
pow(Number, Power) raises Number into Power.
sqrt(Number) extracts square root from Number.
abs(Number) calculates Number’s module.
exp(Number) raises e number into power equaling Number
log(Number) calculates natural logarithm of Number.
sin(Angle_in_radians) calculates sine of Angle.
165
Formulae
166
Centers
23. Centers
23.1. Centers
There are three types of centers in the program:
- Material centers;
- Resource centers; and
- Cost centers.
Material centers are formed the same way: to group similar materials to get their joint consumption. For example, there are
different types of concrete in the project, but for some calculations the total concrete consumption is needed. Create Concrete
material center. All Material centers are saved in Material Centers table.
Resource centers are used to group resources of similar type to jointly analyze them. For example, there are three carpenters
in the project: Jack, Jim, and John, and you need to see joint work load parameters for carpenters. Create Carpenters resource
center including carpenters Jack, Jim, and John, to see joint parameters. All Resource centers are saved in Resource Centers
table.
Cost centers are created different way. Cost center might include materials and cost components and might be used to
summarize material consumption or material revenue (in monetary value) depending on the option selected in Cost Center
properties dialog window. For example, cost of putting up a brick wall within erecting a building project is needed to be
calculated. Create cost center including Cost Components – material cost and work cost, and Materials – bricks. All Cost
centers are saved in Cost Centers table
Contains all project resource centers data and includes the following columns (fields) by default:
- Name is a Resource center name.
- Code is a sequence of characters, unique for each resource center. Code is made of letters, numbers, and special
characters (#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is resource center name to be reflected in table column headers. If, for example, Name is too long, a
shorter name to be used in column headers, can be entered here. If this field remains empty, resource center Name will be
reflected in columns.
- Notes contains comments to resource center (if any). Double click in cell will invoke Resource Center properties dialog
window opened on the notes standard page.
- User-defined fields.
Resource Center shortcut menu
Row shortcut menu in Resource Centers table contains the following options:
- Properties invokes Resource Center properties dialog window to edit resource center’s properties
- New allows creating new resource center by evoking Resource Center properties dialog window and adds new row in
Resource Centers table.
Note that properties dialog window will be opened automatically for newly created Resource Center only if you have
selected to Open properties for new created objects in the spider project parameters dialog window. Otherwise newly
created Resource Center will be saved with default parameters and you will have to invoke Resource Center dialog
window by double click on new Resource Center row number (or by selecting Properties from shortcut menu invoked
with a right mouse button click on new Resource Center row number)
- Delete deletes highlighted resource center and a corresponding row in Resource Centers table.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
When several rows are highlighted simultaneously, row shortcut menu contains Delete option only.
167
Centers
Is one of object properties dialog windows containing Data and Components page and notes standard page.
Data page
- Name is a resource center name.
- Code is a sequence of characters, unique for each resource center. Code is made of letters, numbers, and special
characters (#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is resource center name to be reflected in table column headers. If this field remains empty, resource
center Name will be reflected in columns.
Components page
- List contains resources included in the center. A search can be realized by names or by codes
Add invokes object choice dialog window to add resources to the resource center. Select resources and click OK to add them
to the center.
Delete deletes highlighted resource from the center.
Notes page
- Notes contain any comments to resource center.
Contains all project cost centers data and includes the following columns (fields) by default:
- Name is a Cost center name.
- Code is a sequence of characters, unique for each cost center. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is cost center name to be reflected in table column headers. If, for example, Name is too long, a
shorter name to be used in column headers, can be entered here. If this field remains empty, cost center Name will be
reflected in columns.
- Notes contains comments to cost center (if any). Double click in cell will invoke Cost Center properties dialog window
opened on the notes standard page.
- Include Material Consumption Include Material Income by selecting any of these options material consumptions and/or
material incomes will be included in the cost center. Note that in the software the incomes based on materials are
simulated with the negative sign and expenditures with the positive.
- User-defined fields.
Cost Center shortcut menu
Row shortcut menu in Cost Centers table contains the following options:
168
Centers
- Properties invokes Cost Center properties dialog window to edit cost center ‘s properties.
- New allows creating new cost center by evoking Cost Center properties dialog window and adds new row in Cost
Centers table.
Note that properties dialog window will be opened automatically for newly created Cost Center only if you have selected
to Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created
Cost Center will be saved with default parameters and you will have to invoke Cost Center dialog window by double
click on new Cost Center row number (or by selecting Properties from shortcut menu invoked with a right mouse button
click on new Cost Center row number)
- Delete deletes highlighted cost center and a corresponding row in Cost Centers table.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
When several rows are highlighted simultaneously, row shortcut menu contains Delete option only.
Is dialog window containing the following pages: Data; Components; and notes standard page.
Data page
- Name is a cost center name.
- Code is a sequence of characters, unique for each cost center. Code is made of letters, numbers, and special characters
(#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is cost center name to be reflected in table column headers. If this field remains empty, cost center
Name will be reflected in columns.
- Include Material Consumptions and Include Material Income options show whether materials expenditure or revenues
will be taken into account in cost center.
Note That: Material incomes are entered as negative values and Material Consumption values are entered as positive.
Components page
Contains two lists:
- List of Cost components included in cost center. To add new cost component, click Add button and select cost
component from the invoked Cost Components dialog window containing the list of all cost components available. To
delete highlighted cost component from cost center, click Delete.
169
Centers
- List of Materials included in cost center. To add new material, click Add button and select material from the invoked
Materials dialog window containing the list of all materials available. To delete highlighted material from cost center,
click Delete.
Notes page
- Notes contains comments to cost center (if any). Double click in the cell invokes Cost Center properties dialog window
opened on notes standard page.
Contains all project material centers data and includes the following columns (fields) by default:
- Name is a Material center name.
- Code is a sequence of characters, unique for each material center. Code is made of letters, numbers, and special
characters (#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is material center name to be reflected in table column headers. If, for example, Name is too long, a
shorter name to be used in column headers, can be entered here. If this field remains empty, material center Name will be
reflected in columns.
- Notes contains comments to material center (if any). Double click in cell will invoke Material Center properties dialog
window opened on the notes standard page.
- User-defined fields.
170
Centers
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
When several rows are highlighted simultaneously, row shortcut menu contains Delete option only.
Is one of object properties dialog windows containing Data and Components page and notes standard page.
Data page
- Name is a material center name.
- Code is a sequence of characters, unique for each material center. Code is made of letters, numbers, and special
characters (#$%&@_-~) without spaces, and is case sensitive.
- Name for Columns is material center name to be reflected in table column headers. If this field remains empty, material
center Name will be reflected in columns.
- Include Material Consumptions, Include Material Income – after selecting these options material consumptions and
material incomes will be included in calculations.
Components page
- List contains materials included in the center. A search can be realized by names or by codes
- Add invokes project materials list of. Select material(s) from the list and click OK to add them to material center.
- Delete deletes highlighted material from the center.
Notes page
- Notes contain any comments to material center.
171
Cost periods
For example, you have project phase with one activity and with following properties:
- activity duration – 3 days;
- activity start date – September, 5 2003;
- activity fixed cost – 6 units of cost component ‘USD’;
- activity fixed material consumption – 6 units of material ‘Material 1’;
- ‘Material 1’ unit cost – 1 unit of ‘USD’;
- activity resource assignment: one ‘Resource 1’;
- ‘Resource 1’ hour cost – 1 unit of ‘USD’;
- both activity and resource have 7 days working calendar (working hours 8:00 – 16:00)
- ‘USD’ has following cost periods: (Date&Time of period Start – Unit Cost)
05.09.2003 00:00 – 1;
06.09.2003 00:00 – 2;
- ‘Material 1’ has following cost periods: (Date&Time of period Start – USD [Unit Cost])
05.09.2003 00:00 – 1;
07.09.2003 00:00 – 2;
- ‘Resource 1’ has following cost periods: (Date&Time of period Start – USD [per Hour])
05.09.2003 00:00 – 1;
05.09.2003 12:00 – 2;
06.09.2003 00:00 – 1;
06.09.2003 12:00 – 2;
Total activity cost in USD would constitute of fixed activity cost, material cost and assigned resource work cost:
172
Cost periods
Data page
- Cost Component – is cost component name for which cost period was created.
- Start – date and time of cost period start;
- Unit cost – of cost component for this cost period;
173
Cost periods
- Do not use in calculations – when this option will be selected this period will not be considered by the calculations of
expenditures.
Cost component cost period properties dialog window is an object properties dialog window containing following pages:
Data page, Cost Components page, Notes standard page. You can edit properties of cost period in this dialog window.
Data page
- Material - is material name for which cost period was created;
- Start – date and time of cost period start;
174
Cost periods
Data page
- Resource - is resource name for which cost period was created;
- Start – date and time of cost period start;
175
Overtimes
25. Overtimes
25.1. Overtime
Overtime lets you model extra resources costs for working overtime (i.e. per hour expenditure of cost component(s) by
resource in certain periods is increased by certain percent).
For example, if a driver is working in the night hours or weekends and standard per hour payment must be increased by e.g.
30%, you can use Overtime to model such situations:
1. Modeling of overtimes is started by creating a new week of resource total working schedule. This week must define daily
hours that the resource (e.g. driver) is allowed and is able to work including overtime periods (e.g. every day since 8 a.m.
until 6 p.m. except Sundays).
2. Overtime periods can be defined in an additional week (e.g. Monday – Friday since 4 p.m. until 6 p.m. and Saturday
since 8 a.m. until 6 p.m.). E.g.,
‘withOver’ – week with resource total working schedule (at standard payment as well as overtime hours with extra
payment);
‘Overtime’ - week defining overtime hours with extra payment.
3. On the next step you should create two new calendars - each containing previously created weeks as main weeks. E.g.,
4. Now you are ready to define overtime periods in the Overtime table: create new overtime period, set calendar (containing
overtime hours only) for it and define increase of cost component(s) expenditure per hour in percent (for each necessary
cost component)
5. Finally, when overtime periods are defined and extra payment is set, you can assign required resource main calendar
(containing total working hors) and overtime calendar (containing overtime hours with extra payment).
Dialog window of overtime periods lets you view and edit properties of overtimes. Dialog window contains following
pages:
Data, Cost Components, Notes standard page.
176
Overtimes
Page Data:
Name – overtime period name;
Code – unique code of overtime period
Calendar – calendar, used to calculate overtime costs. Use Choose button to select required calendar from the list.
177
Risk Analysis
In risk analysis dialog window you can set parameters required for risk analysis.
Frame Versions contain information about Optimistic, Probable and Pessimistic project versions. You can edit data on
each version name, code and storage folder name: press Select button and select appropriate project version in opened
projects and documents dialog window. Note that optimistic, probable and pessimistic project versions must already exist
before risk analysis performance.
Required probabilities of compliance with terms and budget are set in fields Duration and Cost in frame Required
Probability for (%).
To specify probabilities of compliance with materials, cost components, material centers cost centers and Material Sets
consumption:
1. Check box corresponding to needed cost type (under buttons Add and Delete): Materials, Cost Components,
Material Centers, Cost Centers, and Material Sets
selecting cost type in checkbox filters list of entered items according to this cost type.
2. Press Add button.
3. Select with left mouse button objects to be added from the list in opened dialog window and press OK.
4. Specify probabilities for each item in field Probability.
You can enable or disable calculation of critical costs for each cost type during risk analysis: check or uncheck appropriate
box in the upper part of the frame Required Probability for (%).
Critical schedule is calculated backward from project critical finish date calculated according to selected three versions
(optimistic, most probable and pessimistic) and selected probabilities of successful project completion. Alternatively,
critical schedule can be calculated backward from project (or phases) target finish date - if you check box Apply Target
Finish Dates in Target Finish column of Activity Gantt table. Frame Critical Schedule lets you specify which project
version would be used as source of activities duration in critical schedule calculation – Optimistic or Probable. Check
corresponding box in frame Most Probable.
Critical schedule shows as late as possible dates for activity execution according to risks reflected in three project versions
(optimistic, most probable and pessimistic) and selected probabilities of successful project completion. Thus delays of
178
Risk Analysis
even non-critical activities in critical schedule (scheduled for execution as late as possible) - will lead to delay in the
whole project execution.
If option Calculate recommended schedule is selected – recommended schedule will be calculated and shown in black in
graphical part of Activity Gantt.
Recommended schedule. Non-critical activities in recommended schedule are scheduled to ensure that they would not
become critical with the same probability as was set for timely completion of the whole project (phase).
You can calculate probabilities of compliance with established project finish date, budget, consumption of materials, cost
components, material centers and cost centers. To calculate probability:
1. Press Select Parameter button in Project Parameter Probability frame and specify needed item in opened fields'
list dialog window;
2. Enter Parameter Value;
3. Press Calculate Probability.
Checking box Show this window before risk analysis (enabled by default) displays current window each time risk analysis
is performed.
To make report on risk analysis check box Show Calculation Report.
2. Decide which parameters are important for the project and calculate corresponding probabilities of compliance with
one or several goals: target activities and phases finish dates; target costs of activities, phases and resources
assignments; target consumption (expenditure) of materials, cost components, material and cost centers. Success
probabilities calculation is recommended to perform in one of project versions (either of optimistic, probable or
optimistic).
Note that you should save project after success probabilities calculation for further creation of trends.
1) In frame Versions of success probability calculation dialog window specify actual project versions corresponding
to pessimistic, probable and optimistic estimates.
2) Calculation of probability of compliance with target activities and phases finish dates:
a. In Activity Gantt table set target activity or phase finish date in column Finish [Target].
To display this column choose Show Column from the shortcut menu invoked with right mouse button
click on column names in table part of diagram; check box Standard, select Finish [Target] and Finish
[Target Probability] with left mouse button from the list and press OK.
b. Go to menu Calculations -> Success Probability Calculation.
c. Check box Duration in Analyzed Parameters frame of opened success probability calculation dialog
window.
d. Press OK button.
179
Risk Analysis
e. Calculated value will appear in Finish [Target Probability] column of Activity Gantt table in row
corresponding to activity or phase.
3) Calculation of probability of compliance with target activities and phases costs:
a. In Activity Gantt table set target activity or phase costs in column Total Cost [Target].
To display this column choose Show Column from the shortcut menu invoked with right mouse button
click on column names in table part of diagram; check box Standard, select Total Cost [Target] and Total
Cost [Probability] with left mouse button from the list and press OK.
b. Go to menu Calculations -> Success Probability Calculation.
c. Check box Cost in Analyzed Parameters frame of opened success probability calculation dialog window.
d. Press OK button.
e. Calculated value will appear in Total Cost [Probability] column of Activity Gantt table in row
corresponding to activity or phase.
4) Calculation of probability of compliance with target consumption of materials, cost components, material and cost
centers:
a. In Activity Gantt table set values of target consumption of materials, cost components, material and cost
centers in corresponding columns: Material_Name [Target], Cost Component_Name [Target], Material
Center_Name [Target] and Cost Center_Name [Target]. (Column name is formed from the name of
material/cost component/material center/cost center and [Target])
To display these columns choose Show Column from the shortcut menu invoked with right mouse button
click on column names in table part of diagram; check box Materials and box Target, select with left
mouse needed materials from the list, and press OK. Repeat these actions display columns of target
consumption for cost components (check box Cost Components and box Target), material centers (check
box Material Centers and box Target) and cost centers (check box Cost Centers and box Target).
Then display columns of probabilities for all required materials, cost components, material and cost
centers: repeat the same actions as described above, checking box Probability (instead of Target).
b. Go to menu Calculations -> Success Probability Calculation.
c. Check box Materials (Cost Components, Material Centers, or Cost Centers) in Analyzed Parameters
frame of opened success probability calculation dialog window.
d. Press OK button.
e. Calculated value will appear in [Probability] columns of Activity Gantt table (e.g., Material_Name
[Probability], Cost Center_Name [Probability])
3. As the project progresses and performance data is added to monitoring, probabilities of compliance with target project
goals would change. Therefore, you need to recalculate success probabilities each time performance data has been
added.
1) Add performance data to one of three project versions (either of optimistic, probable or pessimistic). Save this
project file with a new version number;
2) Import performance data from the version with actual data (selected on the previous step) to other two project
versions:
a. Open Performance archive in project version to which performance data is to be imported;
b. Goto menu Table -> Import Performance from other Project;
c. Specify source project file (selected on step ‘3.1)’) and press OK;
d. Recalculate project expenditures by clicking Cost and Materials icon on the Gantt diagram toolbar.
e. Save project file with a new version number.
f. Repeat steps a-d for the third project version
3) To recalculate probabilities repeat step ‘2’. Perform recalculation in project version, selected on step ‘2’.
4. Building of success probabilities trends:
1) In Activity Gantt menu select Reports -> Success Probabilities Trends -> Table Report or Diagram;
2) In opened dialog window select group of parameters for report: General (Total Cost, Finish), or Cost Components,
or Cost Centers, or Materials, or Material Centers. Then select one or several items in the group with left mouse
button click and press >>. Selected items would appear in the right window of dialog window.
3) Press OK.
180
Risk Analysis
You can calculate probabilities of compliance with established project finish date, budget, consumption of materials,
cost components, material centers and cost centers. To calculate probability:
1. Press Select Parameter button in Project Parameter Probability frame and specify needed item in opened fields'
list dialog window;
2. Enter Parameter Value;
3. Press Calculate Probability.
181
Risk Analysis
Checking box Show this window before success probability calculation (enabled by default) will display current window,
each time when success probability calculation will be performed.
182
Monitoring of Project Execution
- Goto menu Monitoring -> Add activities or press Add activities button on the toolbar;
- You would be prompted to specify beginning and ending of monitoring period for activities/phases being added
– as described earlier. Complete editing dialog windows of including activities/phases to monitoring and press
OK button.
- Monitoring table will be opened and selected activities/phases would appear in the table with corresponding
WBS structure.
Note That: you can use both of the methods described to enter performance data into Monitoring table before the data is
transferred to Performance Archive.
Correction of performance data in Monitoring Table
After selected activities/phases are entered in Monitoring Table, Spider Project automatically calculates data for specified
monitoring period (material consumption, cost components expenditure, activity volumes performed and work duration
passed) according to the scheduled values.
If the project is being performed in accordance with the schedule, performance data can be transferred from Monitoring table
to Performance Archive with no changes. To do so in Monitoring table, click Transfer into Project button on the
toolbar or select Monitoring ->Transfer into Project menu. All transferred data will disappear from Monitoring table.
Note That: it is essential to manually recalculate the project after data transfer to Performance Archive
If actual performance data differs from the scheduled, you can edit performance data directly in the table or in corresponding
dialog windows (that can be invoked with double click on phases, activities or assignments). For more information see
detailed description of Monitoring table. To quickly edit performance data in the table format do the following:
1. For each activity, enter monitoring period start and finish dates. If these dates are missing, activity will not be included in
Performance Archive.
To simplify monitoring data entry, performed volumes and spent activity durations are automatically recalculated after
monitoring period start and finish dates are entered into Period Start and Period Finish columns.
183
Monitoring of Project Execution
After you finished entering monitoring data, save it to the project database by clicking Transfer into Project icon or
select menu item Monitoring -> Transfer into Project.
Then recalculate project schedule and expenditures by clicking the following icons on Gantt diagram toolbar in the following
order:
After performance data from Monitoring table is transferred to Performance Archive appearance of activity gantt diagram
changes: parts of activities, phases and assignments bars, corresponding to completed parts of work, would be highlighted
grey. Project data date would become equal to the ending of monitoring period.
27.2. Monitoring
Monitoring Table is aimed to enter data on project performance. To open the table in main program window or on the toolbox
in the left area of other opened windows press Monitoring icon; or goto menu Project -> Monitoring.
Monitoring Table presents activity structure with resources assignments and contains following columns:
- Level – object level in WBS;
- Code – code of activity to which current assignment was made; or code of resource, assigned to activity;
- Name – name of activity to which current assignment was made; or name of resource, assigned to activity;
- Start of Period – defines the start date of the period for which performance data is added to monitoring;
- Finish of Period – defines the end of the period for which performance data is added to monitoring;
- Responsible – person, responsible for execution of the activity;
- DPH Type - defines DPH type of activity or assignment – duration, productivity, hammock or milestone.
- Volume [Before] – scheduled activity volume or part of activity volume to be performed by the resource assigned;
- Volume [Done] – actual work volume performed (in corresponding units) or part of activity volume performed by the
resource (team, multi-resource or resource skill);
- Volume [Remaining] - remaining activity volume or part of activity volume to be performed by the resource.
- Duration [Before] – scheduled activity duration or resource work duration;
- Duration [Spent] – actual activity duration or resource work duration passed;
184
Monitoring of Project Execution
There are two ways of including project performance data in the Monitoring Table:
I. In activity gantt:
1) Select required phase or activity with a left mouse button click on corresponding row number. To select
several phases or activities press and hold Ctrl button and select required phases (or activities). Note that
you can select only activities or only phases at ones.
2) Invoke shortcut menu with a right mouse button click on one of the selected phases (activities) row
number; select Monitoring;
3) Specify period for monitoring in opened dialog window `Include in monitoring (fields From and To);
press OK.
4) Selected phases and activities would be added to the Monitoring Table and current work breakdown
structure would be preserved.
II. In the Monitoring Table:
1) Press Add Activities button on the toolbar or goto menu Monitoring -> Add Activities or press button
in tools bar;
2) Specify period for monitoring in opened include in monitoring dialog window (fields From and To);
3) Specify in frame Include Activities whether all incomplete activities (All) or only scheduled activities
(Scheduled) should be added and press OK.
4) Phases and activities would be added to the Monitoring Table and current work breakdown structure
would be preserved.
To remove phases or activities with corresponding assignments from the Monitoring Table invoke shortcut menu on
corresponding phase (activity) row number and select Exclude.
To edit actual performance data (e.g., consumption of materials and expenditure of cost components; monitoring period) in
actual period properties dialog window double click on corresponding row number,
or
invoke shortcut menu (with a right mouse button click on row number) and choose Properties.
Performance data can also be edited directly in corresponding fields of the Monitoring Table. In this case, it is strongly
recommended to change data in table rows from the left to the right to enable automatic recalculation of remaining activities
durations, material consumption, cost components expenditures etc.
To include performance data into the project press button Transfer into Project on the toolbar or goto menu Monitoring
-> Transfer into Project. All data from the Monitoring Table would be transferred to Performance Archive; completed
activities and completed parts of activities would be pained grey in activity gantt. Project data date would be set to the latest
date of actual activities start or finish.
After including performance data it is necessary to recalculate project schedule: activate activity gantt window, press
Scheduling or Resource Constrained Scheduling button on the toolbar; then press Cost and Materials button.
185
Monitoring of Project Execution
Allows including phases (and comprising activities) into Monitoring table. Phases and activities that are active during the
monitoring period will be included. To invoke, select Monitoring from Phase shortcut menu () activity gantt.
Note That: For activity, Include in Monitoring - Activity - dialog window will be invoked.
Set up monitoring period in From and To fields. Click Project Data Date button to set up From field equaling to the current
project time. Double click in the fields invokes Mini-calendar dialog window to simplify date and time entry.
In Include Activities frame, select Scheduled if only phases and activities either started or scheduled to start during the
monitoring period need to be included. If you want to include all activities in Monitoring table, select All.
In case All option is selected, activities started after the end of monitoring period might be reflected two ways:
1. Start of Period and Finish of Period field are left empty. Click Leave dates blank in Unscheduled Activities frame; or
2. Start of Period date equals to From field value, and Finish of Period depends on whether the scheduled activity duration
is longer than the monitoring period. If it is, then Finish of Period equals to To field value. If scheduled activity duration
is not longer than the monitoring period, than Finish of Period date will equal to activity finish date, and executed value
is set up as 100%. Select Assume that activities start during period being monitored option in that case.
Select Show assignments option to expand Monitoring table to assignments.
186
Monitoring of Project Execution
Dialog window of including activities to Monitoring table allows setting up Monitoring period of activity performance. To
invoke, select Monitoring from Activity shortcut menu in activity gantt.
Note That: For phase being included to monitoring, Include Phases in Monitoring dialog window will be invoked.
Set up monitoring Period in From and To fields. Click Project Data Date button to set up From field equaling to the current
project time. Double click in the fields invokes Mini-calendar dialog window to simplify date and time entry.
In Include Activities field can be choosed to include only Scheduled activities which are performed or started by the end of
the monitoring period or All. If All option is selected then Unscheduled Activities frame will be activated and Leave dates
blank or Assume that activities start during period being monitored options will be available to be chosen.
Select Show assignments option to expand Monitoring table to assignments.
Allows editing activity monitoring data and contains the following pages: Data; Assignments; Materials standard page; Cost
Components standard page and Material Sets standard page
Data page
Activity is name of activity being monitored.
Responsible is person responsible for activity performance.
Start and Finish are start and finish dates of monitoring period. Double click in the fields invokes Mini-calendar dialog
window to simplify date and time entry.
Volume frame
- Before is scheduled activity volume.
- Done is volume of activity performed.
- Remaining is remaining activity volume.
Duration frame
- Before is scheduled activity duration.
- Done is actual activity duration.
- Remaining is remaining activity duration.
Assignments page
Use this page to assign resources, multi-resources, skills, and teams to perform the activity, which were not initially
scheduled.
187
Monitoring of Project Execution
Add frame
Resource button assigns new resource to activity. Select resource from the dialog window invoked and click OK to return to
Assignments page.
Multi-Resource button assigns new multi-resource to activity. Select multi-resource from the dialog window invoked and
click OK to return to Assignments page.
Resource Skill button assigns a new resource skill to the activity. Select a resource skill from the dialog window invoked and
click OK to return back to Assignments page.
Team button assigns new resource team to activity. Team Monitoring dialog window is invoked by clicking this button.
Properties button is active for resources only. Clicking this button invokes Monitoring Assignment of resource dialog
window. Multi-Resource and Resource Skills properties are set up through setting up properties of resources included.
Types and number of fields with assignment parameters vary depending on the type of highlighted assignment: resource,
multi-resource, skill, or team, as follows:
- Resource: Quantity, Productivity, Priority, Work Load, Type, Scheduled Quantity, Calendar, Fixed Cost, Resource-
Hours, and Remaining Cost.
- Multi-resource: Quantity, Productivity, Priority, Work Load, Type, and Scheduled Quantity.
- Skill: Type and Quantity.
- Team: Duration and Volume.
(User-editable fields are shown here in blue).
Delete deletes highlighted assignment.
Is dialog window for editing monitoring data for resource assignment. Contains the following pages: Data; Materials standard
page Cost Components standard page, and Material Sets standard page
Data page
- Activity is name of activity being monitored.
- Resource is name of resource assigned to activity
- Responsible is a person responsible for activity performance.
- Start and Finish are start and finish dates of the period for which monitoring is performed. Double click in the fields
invokes Mini-calendar dialog window to simplify date and time entry.
188
Monitoring of Project Execution
Volume frame
Before is scheduled volume of resource work.
Done is performed volume of resource work.
Remaining is remaining volume of resource work.
Duration frame
Before is scheduled duration of resource work.
Done is performed duration of resource work.
Remaining is remaining duration of resource work.
Quantity frame
Scheduled is a scheduled quantity of the resource assigned.
Actual is actual quantity of the resource performing this activity.
Work load frame
Scheduled is a scheduled work load of the resource assigned.
Actual is actual work load of the resource performing this activity.
Productivity frame
Scheduled is a scheduled productivity of the resource assigned.
Actual is actual productivity of the resource performing this activity.
Resource-hours are actual hours of work of the resource for this assignment.
You can view and edit performance data of a team assigned to activity execution in this dialog window.
Title of dialog window window contains team name and the name of activity, to which the team was assigned.
Page Data
Activity – name and code of activity, to which the team was assigned;
Team – name and code of assigned team;
Responsible – name of person responsible for activity execution;
Start; Finish – beginning and ending of monitored period (for which performance data is entered). You can edit dates in
these fields directly (click once with left mouse button, enter date and time in the following format: ‘DD.MM.YYYY
189
Monitoring of Project Execution
HH.SS’ and press Enter) or double click on the cell and select required date and time in opened calendar window.
Example of date and time cell value: 13.03.2003 08:00.
Frame Volume:
Before – scheduled part of activity volume (in activity volume units), that the team is assigned to perform (prior to
the Start date of monitoring period);
Done – actual volume of activity that the team performed during the monitored period.
By default, part of activity volume, scheduled for the team for monitored period, is displayed in this field. You can
correct this value according to actual volume, performed by the team.
Remaining - remaining part of activity volume (in activity volume units). By default, part of activity volume,
remaining after the monitored period, is displayed in this field. You can correct this value according to actually
remaining volume that the team would have to perform.
Frame Duration:
Before – scheduled time (in hours) that the team is assigned to spend on activity execution (prior to theStart date of
monitored period);
Done – actual resource-hours, spent by the team on activity execution.
Note that the value of actual resource-hours participate in automatic calculation of assignments’ cost (e.g.
resources that consume materials per hour of their work or spend cost components per hour of their work). By
default, scheduled duration of team work for monitored period is displayed in this field. You can correct this value
according to actual resource-hours, spent by the team on activity execution.
Remaining - remaining duration of team work in hours. By default, scheduled duration of remaining team work is
displayed in this field. You can correct this value according to actually remaining duration of team work in hours.
Page Assignments
Page Assignments contains a list of resources, multi-resources and resource skills – assigned to activity execution as part
of current team.
You can view and edit properties of monitored resources assignment (also for resources comprising multi-resources and
resource skills): select required resource from the list and press Properties button.
To delete resource, multi-resource or resource skill assignments from monitoring (e.g. excluding resources that have not
actually participated in activity execution during monitored period) – select required object and press Delete button. Note
that deleted objects are excluded from current monitored period only.
Performance Archive contains records of project performance, added to monitoring. Performance Archive serves for
analysis and correction of performance data.
Note that after entering data directly in Performance Archive, remaining work volumes and activity durations are not
recalculated automatically.
Performance Archive table contains following columns (fields):
- Code of Activity – code of activity to which current assignment was made;
- Code of Resource – code of resource, assigned to activity;
- Name of Activity – name of activity to which current assignment was made;
- Name of Resource – name of resource, assigned to activity;
190
Monitoring of Project Execution
- Folder - full path to attached folder, that may be used to store files with referential information for current object.
Double click on the cell in this column allows defining the folder path or open the folder (if its path has already been
defined).
- OLE objects; icon defines whether documents of other applications (Word, Excel etc.) are attached to the object.
Double click on this field opens actual period properties dialog window on OLE objects and Folder page.
- Notes - A field that lets users to provide an assignment with notes and explanations. Double click on this field opens
actual period properties dialog window on Notes page.
- Start of Period – beginning of time period, for which performance data has been added to monitoring;
- Finish of Period – ending of time period, for which performance data has been added to monitoring;
- Volume [Actual] – actual work volume performed (in corresponding units);
- Duration, Hours [Actual] – actual duration of work performed (in hours);
- Resource-Hours [Actual] – actual volume of resource-hours. ‘Assignment resource-hours’ can be calculated as
assignment duration multiplied by resource work load and multiplied by the number of assigned resources. ‘Activity
resource-hours’ can be calculated as sum of all corresponding assignments’ resource-hours.
- Work Load [Actual] – actual work load of assigned resources in percent of their working time.
- Quantity [Actual] – number of resources, actually participated in activity execution;
- User defined fields.
- Fields with actual fixed and total consumption of all materials (and material centers) and expenditures of cost
components (and cost centers).
Rows (records) of Performance Archive table represent entered performance data on activities and corresponding resource
assignments. Data on activities and assignments is added each time, as performance data is added in monitoring table.
See general description of tables in Spider Project for common rules of working with tables.
You can import performance data from another project to Performance Archive: go to the menu Table -> Import
Performance from other Project, and specify source project (see Importing Performance Data from another Project.
To delete row from Performance Archive: select desired row with left mouse button click and press Delete button,
or
invoke shortcut menu and choose Delete,
or
select menu item Edit -> Delete.
To delete several rows select desired rows with left mouse button clicks (keeping Ctrl button pressed) first, then perform
one of the actions, described above for deleting of single row.
Note that: deleting of row with data on activity performance would also delete data on corresponding resource
assignments. Planned activity characteristics would not be restored automatically after deletion of data from Performance
Archive; you should restore them manually.
To edit actual consumption of materials and expenditure of cost components in actual period properties dialog window
double click on corresponding row number,
or
invoke shortcut menu and choose Properties.
Is dialog window with the following pages: Data, Materials standard page, and Cost components standard page, notes
standard page OLE-objects and Folder standard page and Material Sets standard page Allows editing activity properties in
Performance archive.
Monitoring data can be for activity or for assignment. Therefore, a row in Performance archive table might contain either
activity or assignment. Actual period properties dialog window varies depending on whether it was activity or assignment.
191
Monitoring of Project Execution
This dialog window is invoked with double click on activity row number or by evoking shortcut menu with the right mouse
click on row number.
Data page
- Activity contains activity name.
If the dialog window is invoked for resource assignment following additional fields will appear:
- Resource – the name of resource assigned to activity execution
- Quantity – actual quantity of resource, that performed activity
- Work load – actual work load coefficient
- Responsible is editable field with name of the person responsible for this activity performance.
- Start, Finish – start and finish date of monitored period
- Actual Volume – actual volume performed (in corresponding units)
- Actual Duration – actual duration of activity/assignment passed (in hours)
5. Recalculate project expenditures by clicking Cost and Materials icon on the Gantt diagram toolbar.
192
Monitoring of Project Execution
- If source project version has activities, initially absent in destination project version – these activities would be
automatically added to newly created phase ‘Unscheduled activities’ (with Code ‘$$$’) in all work breakdown
structures of destination project version. Links of these activities would not be imported.
During performance archive import from another project, success probability trends are also imported.
Note that: While importing performance, if in the imported performance archive there are resources which have not been
assigned on activities in the initial project, the program will automatically add corresponding assignments in the project to
which the monitoring information is imported.
Note that: if in the project, there is no operation from imported performance archive while importing monitoring
information it will be created and placed in a phase "Off-schedule activities" in each project WBS.
Note that: after importing monitoring information, it is necessary to check up in project properties dialog window
concurrence of current time in both projects (in initial and in imported).
193
Monitoring of Project Execution
assignment this cost component is assigned to. Note that there are two columns for each cost component: ‘Cost component
Name [Actual]’ is total actual cost component expenditure and ‘Cost component Name [Fixed Actual]’ is fixed expenditure
of this cost component and is part of actual expenditure.
194
Documents, Tables and Reference-Books
Allows to type in any notes or other texts to be attached to the object. Type the text in Notes text field.
28.2. Documents
195
Documents, Tables and Reference-Books
Each document can be viewed or edited in table format. You can also transfer data from document to project or another
document.
Note That: In Spider Project Software, there is also a document of a seperate type, called monitoring document exists. As the
given document is created after distributing monitoring data in the form of documents, type of such document is determined
automatically and to change it is not possible.
196
Documents, Tables and Reference-Books
Document containing general or custom information can be created from the main program window menu File -> Create
Document –> New.
Document properties dialog window will be invoked. By default, single No Name field is created in the new document and is
considered a key field. General document type is General document or reference-book. Any project report has the same type.
You can add new columns to the document (working with tables), change their properties (see Dialog window of column
properties, Dialog window of user-defined fields (advanced) ), and export data from general document to any project table.
197
Documents, Tables and Reference-Books
From the drop down menu you can select the type of the created document. General document or reference-book is set by
default.
Columns Options for Transfer Data button invokes data transfer options dialog window.
To save document within its window, select Save from Document menu or click Save icon on the toolbar or use hot key
(Ctrl + S).
To save document in main program window, invoke document shortcut menu right clicking on document’s icon/name in the
left part of main program window, and select Save.
Document will be saved without any changes on its code or version number.
You can view or edit following document properties in this window: Name, Code (document must have fields with unique
codes), Version, Notes and Type. Field Storage displays current document storage name
198
Documents, Tables and Reference-Books
Note That: In Spider Project Software, there is also a document of a separate type, called monitoring document exists. As the
given document is created after distributing monitoring data in the form of documents, type of such document is determined
automatically and to change it is not possible.
Column Options for Transfer Data opens a transfer settings dialog window in which it is possible to set, on what fields data
transfer is carried out, to change codes of transferable fields in the target table and others.
In some reference-books transfer data settings dialog windows have different appearance: «Links», «Assignments», «Multi-
resource Assignments», «Resource Skill Assignments», «Team Assignments», «Values of enumerated fields».
In Storage field the storage, where document is kept, is shown.
199
Documents, Tables and Reference-Books
- Properties invokes document properties dialog window to set up or edit document Code, Version, Storage, Name, Type,
and Notes.
- Open opens document.
- Save allows saving active document.
- Save As saves document with changes in project code and/or version number by evoking projects and documents dialog
window.
- Close closes active document.
200
Documents, Tables and Reference-Books
Sets up properties for data transfer and contains the following options:
Document field shows the name of the document.
Transfer to; field reflects; where to, the data will be transferred.
- Selected projects,
- Selected Documents,
- Columns of selected project tables,
- and Columns of selected documents are available options.
Method of data transfer
- Just transfer data to existing rows; means that new rows will not be created;
- If row does not exist - create a new one; means that if in the resulting document one of key type lines is missing, a row
will be added to copy corresponding original document row.
What to transfer field defines the elements to be transferred such like:
- Whole document; transfers the whole document without any exceptions
- Filtered data only; transfers the elements which are still remaining after filtering. A filter must be realized to make this
option available.
- Selected data only; transfers only previously selected field(s)
Column type; in this field depending on the transferred values the types of created columns are assigned. Numerical, Text or
Data-Time.
Fields used to link
- Transfer by key field
- Transfer by key fields for transfer data
With pressing button Columns Options for Transfer Data; Columns options for data transfer window will be invoked to edit
the necessary parameters of the transfer of data from the documents and the reference-books.
28.3. Tables
201
Documents, Tables and Reference-Books
- Point to required cell with left mouse button click, edit content and press Enter or click with left mouse button outside
the cell.
- Cells of data and time type can be edited directly in the cell (click once with left mouse button, enter date and time in
the following format: ‘DD.MM.YYYY HH.SS’ and press Enter) or in calendar window, invoked by double click on
corresponding cell. Example of date and time cell value: 06.03.2006 08:00.
Note that; Content of cell with calculated data cannot be changed. Contents of these fields are highlighted in dark blue
color. If it will be attempted to change such error message will appear; "This cell cannot be modified by user".
All changes made are stored in the Protocol Table and can be canceled.
1. You can save order of columns, their width and names to configuration file (*.stc)For this choose menu item Table
-> Save Configuration (in Gantt charts: Gantt -> Save Configuration).
2. Load Configuration – restores configuration from file (*.stc); all columns created by user (and not described in
configuration file) in current structure will be hidden.
3. To restore default order of columns press button on the toolbar (or go to menu Table (Gantt)-> Options) to
invoke table properties dialog window, check box Default order and width(Default order) in the frame Columns and press
OK. (
202
Documents, Tables and Reference-Books
- Select it with left mouse button click on corresponding row number and press Delete; or
- Invoke row shortcut menu and choose Delete;
- Select a row and goto menu Edit -> Delete.
You can select (highlight) unused project objects in the tables of resources, cost components, materials, multi-resources,
resource skills, calendars and weeks: goto menu Edit -> Select unused objects.
Each table has the table main menu and the tools panel
Allows setting up standard set of columns in the table and is invoked by selecting Options from Table menu or by clicking
Options icon on the toolbar.
Default order sets up default set of columns in the table.
To change table row height, change number in Number of rows in cells field.
If no rows have been selected(left mouse click below row numbers) shortcut menu will contain only one option: New
(Insert).
If several rows have been selected shortcut menu will contain option Delete and some additional options, specific for the
table, where shortcut menu has been evolved. See description of corresponding shortcut menus for more details.
To see what other options are available in row shortcut menus, select one of the following hyperlinks to tables:
Activities table;
Resources table;
Materials table;
Cost components table;
Calendars table;
Weeks table;
Calendar exceptions table;
Users table;
Access rights table;
Assignments table;
Links table;
203
Documents, Tables and Reference-Books
Multi-resources table;
Resource skills table;
Performance archive table;
Monitoring table;
Protocol table;
Resource centers table;
Material centers table;
Cost centers table;
Table of cost component periods;
Table of material cost periods;
Table of resource cost periods;
Overtime table;
Corporate reference-books table.
Table column shortcut menu is invoked by right clicking on table column header. This shortcut menu varies from table to
table, but the following options are present in all:
- Show Columns – invokes fields available dialog window containing list of all table columns. Highlight columns you
want to move and click OK. Selected columns to be inserted on the left from highlighted column.
- Hide Column – hides highlighted column without removing it from internal database.
- Autofit Column – fits the selected columns due to their contents in order to make all their contents completely visable.
- Properties – invokes column properties dialog window to edit column properties. This dialog window is also invoked by
double click on column header.
- Search / Replace – allows searching for the text entered in Find text field of invoked search dialog window.
- Repeat Search / Replace – repeats search of context string starting current cell.
- Sort by Column – sorts table rows by highlighted column (for example, alphabetically for text fields).
- Sort by Multiple Columns – allows sorting data on several columns of tble by opening the dialog window of sort by
multiple columns
- Unsort – cancels all previously made sorting
- Filter by Values – filters the selected columns by selected value and condition
- New Field – allows creating new field in internal database – and adding a new table column. Set up new field properties
in invoked field properties dialog window and click OK. Note that properties dialog window will be opened
automatically for newly created field only if you have selected to Open properties for newly created objects in the spider
project parameters dialog window. Otherwise newly created field will be saved with default parameters.
- Delete Field – deletes field and column
- Note That: Only user-defined fields (columns) can be deleted.
204
Documents, Tables and Reference-Books
Is invoked from the right mouse button click menu on column header in any project table. The dialog window appearance
varies depending on whether column (field) is standard or user-defined.
For standard fields, the dialog window looks as follows:
205
Documents, Tables and Reference-Books
206
Documents, Tables and Reference-Books
Note that: Properties dialog window will be opened automatically for newly created field only if you have selected to
Open properties for new created objects in the spider project parameters dialog window. Otherwise newly created field
will be saved with default parameters.
207
Documents, Tables and Reference-Books
Fields' list dialog window is used for selection of fields from internal database.
List contains fields’ names, filtered by group, selected in Field Groups frame:
- Standard – all standard fields;
- User Defined – fields, created by users;
- Comparison – fields, presenting results of projects comparison;
- Materials – list of materials, existing in the project;
- Material Centers – list of material centers, existing in the project;
- Material Sets – list of material sets, existing in the project;
- Cost Components – list of cost components, existing in the project;
- Cost Centers - list of cost centers, existing in the project;
When fields' list dialog window is invoked in tables on Show Column command, you can define following consumption
types:
- For Materials, Material Sets and Cost Components: Remaining, Actual, Fixed, Per Hour, Profile, Critical,
Cumulative, Target, Probability, Original and Per Volume Unit.
- For Material Centers and Cost Centers: Remaining, Actual, Critical, Cumulative, Target, Probability, Original and
Per Volume Unit.
Selecting these checkboxes would insert corresponding columns into the table:
- Remaining – remaining consumption of selected material or expenditure of selected cost component;
- Actual – actually consumed amount of selected material or expenditure of cost component;
- Fixed – defined fixed consumption of selected material or expenditure of cost component;
- Per Hour - defined per hour consumption of selected material or expenditure of cost component;
- Profile – profile of selected material consumption or cost component expenditure;
- Critical – critical consumption of selected material or expenditure of cost component (is used in risk analysis);
- Cumulative - cumulative consumption of selected material or expenditure of cost component;
- Target - target consumption of selected material or expenditure of cost component (is used in risk analysis);
- Probability – probability of compliance with target consumption;
- Original - consumption of selected material or expenditure of cost component in original project version (see
project comparison)
- Per Volume Unit - consumption of the material, for per volume units
User defined fields can be deleted with the aid of Delete button.
Is invoked after inserting a new user defined field in a project table, then from Dialog window of column properties by
clicking Advanced. Allows you to set summing options for numerical user-defined fields.
208
Documents, Tables and Reference-Books
Is invoked after inserting a new user defined field in a project table, then from Dialog window of column properties by
clicking Advanced. Allows you to set summing options for numerical user-defined fields.
"Numerical field properties" frame
Activity value is the sum of assignment values – value of user-defined activity field will be a sum of values of all user-defined
assignments fields for this activity.
Phase value is the sum of activity values – value of user-defined phase field will be a sum of values of all activity fields for
this phase.
Resource value is the sum of assignment values – value of user-defined resource field will be a sum of values of all user-
defined assignments fields for this resource.
Department value is the sum of resource values – value of user-defined department field will be a sum of values of all
resource fields for this department.
"Assignment value is the value of" frame
Select a field that will be considered assignment (a user-defined assignment field). Select from Assignment itself, Resource,
and Activity options.
209
Documents, Tables and Reference-Books
In the list it is necessary to select lines with necessary objects and to press ОК. Besides, objects can be chosen By type or By
filter. Fields can be chosen by means of the button to Select type field. If options All is selected the full list of objects will be
displayed. If Selected type option is chosen in the list only objects of that type (which is chosen in the list of types at the left)
will be displayed.
If the option Selected filter only was selected, only the objects satisfying the filter condition (chosen in filters list) will be
displayed in the list, which is on the left.
Pressing button OK closes dialog window with applying changes.
Button Cancel closes dialog window, canceling all installations.
Help - invokes corresponding help window.
Contains Cost components data and has following standard fields (columns): Code, Name, Name For Columns, Folder,
Notes, and Unit Cost. Code is Key field by default.
Creating cost components reference-book will help you in two ways: 1) you will be able to quicker form cost components list
for new project; 2) you will be able to quickly update cost components in the existing projects when market or project
conditions change (for example, exchange rate changes).
To use reference-book to create new cost components list for new project or to add these cost components to existing project:
In Cost Components reference-book window, select Transfer -> To Selected Project -> Cost Components menu. Data
Transfer options dialog window will be invoked. Select If row does not exist – create a new one option.
If not all data from reference-book needs to be transferred, before making transfer as described above highlight in the
reference-book only those cost components you want to be transferred by clicking their column headers while holding Ctrl
key.
To update cost components, select Just transfer data to existing rows option in Data Transfer options dialog window.
When transfer from Cost Components reference-book to Cost Components table is performed, program matches key field
(Code by default) of all cost components in project and cost components from the reference. Once the match is found, values
of other fields of the matched cost component are transferred from the reference-book to the project.
Reference-book of ‘Materials’ can be used for quick update of materials properties or filling of Materials Table in a new
project. For example, the reference-book is useful for updating of changed material price.
210
Documents, Tables and Reference-Books
You can enter per unit cost of materials in the reference-book ‘Materials’:
1. Create reference-books from the table of cost components by entering menu item Table -> Copy as document in
Cost Components Table;
2. Select icon of a reference-book ‘Resources’ in the main program window with a single left mouse button click. If
there is no icon of desired reference-book you should first open it (or create new reference-book);
3. Perform data transfer from a reference-book of cost components to columns of reference-book ‘Materials’. In the
reference-book of cost components go to menu Transfer -> Transfer Data(To Columns of Selected Document).
Press OK in opened data transfer dialog window.
4. New columns (fields), corresponding to cost components would be added to the reference-book ‘Materials’ and
required codes would be set to these columns (fields).
5. You can enter values of per unit cost of materials in corresponding columns.
Reference-book ‘Resources’ can be used for quick update of resource properties or filling of Resources Table in a new
project. For example, the reference-book is useful for recalculating of actual resource assignment cost if per hour cost of
resource work changes.
By default reference-book table contains following columns (fields):
- Code – unique resource code (default key field);
- Name – resource name;
- Short Name – resource short name;
- Quantity – amount of resource units at disposal;
- Type – type of the resource.
You can enter per hour cost of resource work in the reference-book ‘Resources’:
1. Create reference-books from the table of cost components by entering menu item Table -> Copy as a new
document in the Cost Components Table;
2. Select icon of reference-book ‘Resources’ in the main program window with a single left mouse button click. If
there is no icon of desired reference-book you should first open it (or create new reference-book);
3. Perform data transfer from reference-book of cost components to columns of reference-book ‘Resources’. In the
reference-book of cost components goto menu Transfer -> To Columns of Selected Document. Press OK in opened
data transfer dialog window.
4. New columns (fields), corresponding to cost components would be added to the reference-book ‘Resources’ and
required codes would be set to these columns (fields).
211
Documents, Tables and Reference-Books
5. You can enter values of per hour cost of resource work in corresponding columns.
In the same way you can specify per hour materials consumption for resources:
1. Create new (as described earlier) or choose existing resources reference-book;
2. Perform data transfer from reference-book of materials to columns of reference-book ‘Resources’. In the reference-
book of materials goto menu Transfer -> To Columns of Selected Document. Press OK in opened data transfer
dialog window.
3. New columns (fields), corresponding to materials would be added to the reference-book ‘Resources’ and required
codes would be set to these columns (fields).
4. You can enter values of per hour material consumption for resources in corresponding columns.
You can recalculate actual assignments’ costs by data transfer from the reference-book ‘Resources’ to project performance
archive. Actual assignments’ costs would be recalculated as follows:
( Hour cost (from reference-book) * Duration [Actual] * Work Load [Actual] * Quantity [Actual] ) + Actual fixed
assignment cost (column [Fixed Actual] for corresponding cost component)
Note that: It is necessary to recalculate costs, materials requirements and resources work load – by pressing button on
the Activity Gantt toolbar or Resource Gantt toolbar (or select menu Calculations -> Cost and Materials) after data
transfer.
Multi-Resources Reference-book contains data on multi-resources in table format with following default fields:
- Code - A sequence of characters that should be unique for each project multi-resource. Code is made up by letters,
figures and special characters (#$%&@_-~) without spaces and is case sensitive.
- Name - multi-resource full name.
- Type – field, that can be used for organizing of data transfer from reference-books for changing of multi-resources
properties in projects. (Folder - full path to attached folder, that may be used to store files with referential information
for current multi-resource. Double click on the cell in this column allows defining the folder path or open the folder (if
its path has already been defined).
- Notes - A field that lets users provide current multi-resource with notes and explanations.
- Participants [Numbers and Codes] – field showing multi-resources composition in text format: amount of resource
units in current multi-resource and resource code, separated by space; data on different resources is separated by ‘|’
symbol.
- Participants [Names] – field with resources (comprising current multi-resource) names, separated by ‘|’ symbol.
It is strongly recommended to change multi-resource composition (participants and their quantity) in multi-resource
properties dialog window(that can be invoked by double click on corresponding multi-resource row number) and not
directly in the table fields! Note that changing codes of resources would affect data transfer from reference-book to the
project.
Multi-Resources Reference-books are useful for adding new multi-resources or changing composition of multi-resources
in projects through data transfer from the reference-book to Multi-resources Table.
To transfer data from current multi-resources reference-books:
212
Documents, Tables and Reference-Books
Page Data.
You can edit Name, Code and Type of multi-resource in corresponding fields.
If reference-book has no fields with codes Name , Code and Type - corresponding cells would become inaccessible.
Page Participants.
Contain list of resources comprising current multi-resource with quantities in resource units.
Button Add – opens list of available resources in reference-book . Choose desired resource(s), press OK and specify
quantity of each resource comprising current multi-resource in units of resource per multi-resource - in field Quantity
under the list.
To delete selected resource from current multi-resource press Delete button.
213
Documents, Tables and Reference-Books
Resource Skills Reference-book contains data on resource skills table about resource skills in table format with following
default fields:
- Code - A sequence of characters that should be unique for each project resource skill. Code is made up by letters,
figures and special characters (#$%&@_-~) without spaces and is case sensitive. Code is default key field.
- Name - resource skill’s full name.
- Folder - full path to attached folder, that may be used to store files with referential information for current resource
skill. Double click on the cell in this column allows defining the folder path or open the folder (if its path has already
been defined).
- Notes - A field that lets users provide current resource skill with notes and explanations.
- Participants [Types and Codes] – field, showing resource skill composition in text format. type and code, separated by
space; data on different resource skills is separated by ‘|’ symbol. Type can be ‘R’ (i.e., resource) or ‘M’ (i.e., multi-
resource)
- Participants [Names] – field, containing comprising resources and multi-resources names, separated by ‘|’ symbol.
Note That:It is strongly recommended to change resource skill composition (participants and their codes) in resource
skill properties dialog window (that can be invoked by double click on corresponding resource skill row number) and not
directly in the table fields! Note that changing codes of resources would affect data transfer from reference-book to the
project.
Resource Skill Reference-books are useful for adding new resource skills or changing composition of existing resource
skills in projects through data transfer from the reference-book to Resource Skills Table.
To transfer data from current resource skill reference-book:
1. Select destination project or document in the main program window;
2. Open source resource skill reference-book window;
3. Select with left mouse button resource skills for data transfer (press and hold Ctrl button to select several multi-
resources); do not select any to transfer all data;
4. Select Transfer from menu in resource skill reference-book window;
5. Choose destination type: To selected project; To selected document or To columns of selected document (See data
transfer dialog window and description of documents for more details)
6. Specify method of data transfer –
- Just transfer data to existing rows – to update data on existing resource skills in the destination
project/document
- If row does not exist - create a new one - to update data on existing resource skills and add new resource skills
to destination project/document
By default resource skill Code is used as the key field in data transfer: data is only updated in resource skills, whose codes
exactly match source resource skill codes. Composition of source resource skills is transferred to project Resource Skills
Table only in case destination project contain resources (and/or multi-resources) with codes matching source reference-
book resources (and/or multi-resources) codes.
Page Participants.
Contain list of resources and multi-resources comprising current resource skill with their priorities.
Frame Add contains two buttons, Resource and Multi-Resource – and lets you add new components to resource skill
through list of available resources (multi-resources) in reference-books . Choose desired resources (multi-resources), press
OK and specify priority of each component comprising current resource skill in field Priority under the list.
To delete a resource or multi-resource from current resource skill select desired component and press Delete button.
214
Documents, Tables and Reference-Books
Contains productivities of assignment type and has the following standard fields:
- Type is assignment type and is key field by default.
- Type Name is assignment type name.
- Productivity (volume per hour) is productivity of this type per hour.
During data transfer from this reference-book to assignments table, productivities of assignment type will be transferred to
the project.
Data from the reference-book can be transferred to projects or documents which are open in the main window. Parameters of
data transfer are set in data transfer dialog window, which can be opened from menu by Transfer -> Transfer Data (see.
Reference-books).
It is possible to transfer data, to a key field, or to transfer fields. Key and transfer fields can be set in data transfer dialog
window, and in column options for transfer data dialog window where it is necessary to specify, to which fields to transfer
data: to key fields or to transfer fields.
Contains work loads (in percent) of assignments types and has the following standard fields:
- Type is assignment type and is key field by default.
- Type Name is assignment type name.
- Work Load (%) is work load of this assignment type in percentages. By default, work load equals to 100%.
- During data transfer from this reference-book to Assignments table, assignment work load will be transferred only if its
Type in the reference-book equals to corresponding Type field in Assignments table.
Data from the reference-book can be transferred to projects or documents which are open in the main window. Parameters of
data transfer are set in data transfer dialog window, which can be opened from menu by Transfer -> Transfer Data (see.
Reference-books).
It is possible to transfer data, to a key field, or to transfer fields. Key and transfer fields can be set in data transfer dialog
window, and in column options for transfer data dialog window where it is necessary to specify, to which fields to transfer
data: to key fields or to transfer fields.
215
Documents, Tables and Reference-Books
Reference-book ‘Resource Assignment Cost and Materials Requirements’ contains data on fixed material consumption
and cost component expenditures on activities.
By default reference-book table contains following columns (fields):
- Type; Type Name – activity type (key field by default) and its name;
- Per Volume – amount of activity volume units, for which fixed material consumption and cost component expenditures
are assigned;
- Unit - activity volume units.
To enter fixed material consumption and cost component expenditures on activities it is necessary to add corresponding
columns (fields) and set special codes for them. You can perform this action by data transfer to columns of reference-book
(document):
1. reference-books from the tables of cost components and materials by entering menu item Table -> Copy as
document in Cost Components Table and Materials Table;
2. Select icon of reference-book ‘Resource Assignment Cost and Materials Requirements’ in the main program
window with a single left mouse button click. If there is no icon of desired reference-book you should first open it
(or create new reference-book);
3. Perform data transfer from reference-book of materials and reference-book of cost components to columns of
reference-book ‘Resource Assignment Cost and Materials Requirements’. In the reference-book of materials and
reference-book of cost components goto menu Transfer -> To Columns of Selected Document. Press OK in opened
data transfer dialog window.
4. New columns (fields), corresponding to materials and cost components would be added to the reference-book
‘Resource Assignment Cost and Materials Requirements’ and required codes would be set to these columns
(fields).
5. You can enter values of fixed material consumption and cost component expenditures on activities in
corresponding columns.
Later you can use reference-book ‘Resource Assignment Cost and Materials Requirements’ to enter or edit activity data on
material consumption and cost component expenditures. When data is transferred to Activities Table, values from
reference-book are recalculated according to following formula: value of fixed material consumption or cost component
expenditures (from reference-book) is divided by Per Volume field value (if the field is empty, it is considered to be ‘1’)
and multiplied by activity volume (from Activities Table).
Note that: It is necessary to recalculate schedule before data transfer from reference-book.
‘Resource Assignment Cost and Materials Requirements (per Volume Unit)’ reference-book contains data on fixed
material consumption and cost component expenditures on activities.
By default reference-book table contains following columns (fields):
- Type; Type Name – activity type (key field by default) and its name;
- Per Volume – amount of activity volume units, for which fixed material consumption and cost component expenditures
are assigned;
- Unit – activity volume units.
To enter fixed material consumption and cost component expenditures on activities it is necessary to add corresponding
columns (fields) and set special codes for them. You can perform this action by data transfer to columns of reference-book
(document):
1. Create reference-books from the tables of cost components and materials by entering menu item Table -> Copy as
document in Cost Components Table and Materials Table;
216
Documents, Tables and Reference-Books
2. Select icon of reference-book ‘Resource Assignment Cost and Materials Requirements (per Volume)’ in the main
program window with a single left mouse button click. If there is no icon of desired reference-book you should
first open it (or create new reference-book);
3. Perform data transfer from reference-book of materials and reference-book of cost components to columns of
reference-book ‘Resource Assignment Cost and Materials Requirements (per Volume)’. In the reference-book of
materials and reference-book of cost components goto menu Transfer -> To Columns of Selected Document. Press
OK in opened data transfer dialog window.
4. New columns (fields), corresponding to materials and cost components would be added to the reference-book
‘Resource Assignment Cost and Materials Requirements (per Volume)’ and required codes would be set to these
columns (fields).
5. You can enter values of fixed material consumption and cost component expenditures on activities in
corresponding columns.
Later you can use reference-book ‘Resource Assignment Cost and Materials Requirements (per Volume)’ to enter or edit
activity data on material consumption and cost component expenditures. When data is transferred to Activities Table,
values from reference-book are recalculated according to following formula: value of fixed material consumption or cost
component expenditures (from reference-book) is divided by Per Volume field value (if the field is empty, it is considered
to be ‘1’) and multiplied by activity volume (from Activities Table).
Note that: It is necessary to recalculate schedule before data transfer from reference-book.
Data from the reference-book can be transferred to projects or documents which are open in the main window. Parameters of
data transfer are set in data transfer dialog window, which can be opened from menu by Transfer -> Transfer Data (see.
Reference-books).
It is possible to transfer data, to a key field, or to transfer fields. Key and transfer fields can be set in data transfer dialog
window, and in column options for transfer data dialog window where it is necessary to specify, to which fields to transfer
data: to key fields or to transfer fields.
‘Resource Assignment Cost and Materials Requirements (fixed per quantity)’ Reference-book contains data on fixed
material consumption and cost component expenditures on activities.
By default reference-book table contains following columns (fields):
- Type; Type Name – activity type (key field by default) and its name;
- Per Number of Units – amount of resource units, on which fixed material consumption and cost component
expenditures are assigned;
To enter fixed material consumption and cost component expenditures on assignments it is necessary to add corresponding
columns (fields) and set special codes for them. You can perform this action by data transfer to columns of reference-book
(document):
1. Create reference-books from the tables of cost components and materials by entering menu item Table -> Copy as
document in Cost Components Table and Materials Table;
2. Select icon of reference-book ‘Resource Assignment Cost and Materials Requirements (per quantity)’ in the main
program window with a single left mouse button click. If there is no icon of desired reference-book you should
first open it (or create new reference-book);
3. Perform data transfer from reference-book of materials and reference-book of cost components to columns of
reference-book ‘Resource Assignment Cost and Materials Requirements (per quantity)’. In the reference-book of
materials and reference-book of cost components goto menu Transfer -> To Columns of Selected Document. Press
OK in opened data transfer dialog window.
4. New columns (fields), corresponding to materials and cost components would be added to the reference-book
‘Resource Assignment Cost and Materials Requirements (per quantity)’ and required codes would be set to these
columns (fields).
5. You can enter values of fixed material consumption and cost component expenditures on activities in
corresponding columns.
217
Documents, Tables and Reference-Books
Later you can use reference-book ‘Resource Assignment Cost and Materials Requirements (per quantity)’ to enter or edit
activity data on material consumption and cost component expenditures. When data is transferred to Assignments Table,
values from reference-book are recalculated according to following formula: value of fixed material consumption or cost
component expenditures (from reference-book) is divided by Per quantity field value (if the field is empty, it is considered
to be ‘1’) and multiplied by number of resources (from Assignments Table).
Note that: It is necessary to recalculate schedule before data transfer from reference-book.
Data from the reference-book can be transferred to projects or documents which are open in the main window. Parameters of
data transfer are set in data transfer dialog window, which can be opened from menu by Transfer -> Transfer Data (see.
Reference-books).
It is possible to transfer data, to a key field, or to transfer fields. Key and transfer fields can be set in data transfer dialog
window, and in column options for transfer data dialog window where it is necessary to specify, to which fields to transfer
data: to key fields or to transfer fields.
218
Documents, Tables and Reference-Books
To cancel last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
See Working with tables for more details on general approaches to working with Spider Project tables.
219
Reports and Diagrams
29.1.1. Reports
You can create following reports in Spider Project:
– General reports and diagrams on templates
– General reports and diagrams
– EVA reports and diagrams on templates
– EVA reports and diagrams
– Success probability trends on templates
– Success probability trends
– Resource overloads bar
– Resource overloads report
– Project truncation
See Table reports and diagrams on report templates for procedure of creating reports and diagrams on report templates.
General reports and diagrams can be created in Activity Gantt and Resource Gantt according to currently active structure
(WBS or OBS).
According to WBS, opened in Activity Gantt you can create following reports on the whole project, individual phases or
activities:
- Cumulative costs of phases, activities and the whole project;
- Durations, volumes and resource-hours of activities and phases;
- Cost of activities, phases and the whole project – according to individual cost components and cost centers;
- Materials consumption on activities, phases and for the whole project;
- Cumulative materials consumption of material centers;
- Resource hours of resources, assigned to activities execution.
According to OBS, opened in Resource Gantt you can create following reports on the whole project, individual departments
or resources:
- Cumulative costs of departments, resources and assignments;
- Working duration for departments and comprising resources;
- Work volumes and resource-hours;
- Individual resources work costs; cumulative costs or resources, comprising departments – in the context of
cost components and cost centers;
- Material consumption by resources and departments;
- Consumption of materials, organized in material centers;
- Resource hours of resources assigned to activities execution in resource-hours;
Report parameters can be specified and edited in Report settings dialog window.
220
Reports and Diagrams
a. Select required phase, department, activity, resource or assignment. To obtain report on the whole phase or
department (without detalization by comprising activities or resources or assignments) - leave only those
rows visible that correspond to desired level of detalization (hide/unhide assignments, fold/unfold phases or
departments, use filters);
b. Invoke shortcut menu by right mouse button click on corresponding row number and select General reports
and diagrams -> Table report or Diagram;
c. Select desired report template from the list and press OK.
3. Table report will be created in a new document (with name, code and version number defined in report template); a
diagram will be placed at the bottom of Gantt chart.
4. To make adjustments to report created - repeat steps 1 - 3.
5. To adjustments to diagram created - invoke shortcut menu on the graphic part of the diagram and select Properties,
Contents or Delete.
Note that you can temporarily store the list of parameters in your last report created: check box Do not clear parameters list
before new report creation in Spider Project parameters dialog window.
Report on earned value analysis – document with actual data and prognosis according to earned value analysis.
Parameters of earned value analysis are placed in report rows, while calculated values are in columns, corresponding to
dates.
You can make earned value analysis report on total cost, or selected cost component, material, material center or cost
center. Report on material and material center would be presented in corresponding material units.
Note that you should save baseline project version before earned value analysis.
221
Reports and Diagrams
Success Probability trends - is a method of project performance analysis. Probabilities of achieving target project finish
dates, target budget and target material consumption are analyzed in the course of project performance. Trends can be
obtained for such parameters as project finish date, total cost, project cost components, materials, cost centers and material
centers. Trends of these probabilities provide valuable information for project success estimates.
Reports can be created from Activity Gantt only.
To create report on the whole project:
1. Goto menu Report and select required report type;
2. Then select required report type and set report options.
3. Report would be opened in new window and icon of the report would appear in area Documents of the main program
window
To create a report on individual project phase, activity (in Activity Gantt) or assignment (for success probabilities trends):
1. Invoke shortcut menu with a right mouse button click on corresponding phase, activity or assignment row number;
2. Select required report type;
4. Then select Table Report. Depending on report type following dialog windows will open:
- earned value analysis report properties dialog window – for earned value analysis report;
- success probabilities trends dialog window – for success probabilities trends report;
- Report settings dialog window – for other types of reports.
5. Set required option in dialog window and press OK.
6. Report would be opened in new window and icon of the report would appear in area Documents of the main program
window
Resource overloads bar – see Diagrams section in diagrams and histograms in Gantt's diagrams.
Resource overloads report – can be created after calculating the schedule and contains data about overloaded resources (see
resources overloads report).
Project Truncation report–to create this report it is necessary to set its parameters in truncate project by period dialog
window.
To create reports and diagrams it is necessary to choose in gantt Main menu item Report and further the subitem
corresponding that kind of the report which is necessary.
After creating table report, its pictogram will be displayed in Documents window which is located in the main program
window Diagrams will displayed in the bottom part of gantt charts.
To create report on a separate activity, a phase, a resource or department (and in project gantt – on a separate project,
multiproject) it is necessary to invoke the shortcut menu on the row number of a row with an activity, a phase, etc. and to
choose corresponding item.
See description of Documents for details on working with reports.
222
Reports and Diagrams
On this step you can specify what creating parameter should refer to:
– Other, i.e. you can make report on selected activity, phase, resource or department;
– Resources;
– Resource Centers.
Choosing Resources or Resource centers will show a list of available resources and centers. You can select one (for table
reports and diagrams) or several items (for table reports only) and press Next > button to move to the next step.
223
Reports and Diagrams
Volume
– Cost Components – contains the list of cost components;
– Cost Centers – contains the list of cost centers;
– Materials – contains the list of materials;
– Material Centers – contains the list of material centers;
– Material Sets – contains the list of material sets;
Choosing Cost Components, Cost Centers, Materials, Material Centers, Material Sets or User Defined Gantt Fields will
show a list of available items. You can select one (for table reports and diagrams) or several items (for table reports only) and
press Next > button to move to the next step.
If parameter from the General group was selected on this step pressing Next > button will move you to the last page Finish.
Otherwise you will proceed to Set Parameters – Step 3 page.
Finish Page.
224
Reports and Diagrams
Pressing Next > finishes the wizard and returns you to the dialog where the wizard was started. Created parameter(s) will be
added to the list.
Pressing Cancel stops the wizard without adding report parameter.
Following diagram types are available in Activity Gantt and Resource Gantt:
- Resource work load diagram;
- Diagrams of costs and material consumption;
- Diagrams of volumes, durations and resource-hours;
- Earned value analysis diagrams;
- Resource overloads bar;
- Success probability trends.
Diagrams can be drawn for whole project or separate project phases or activities and are placed in the lower part of Gantt
diagrams. Go to menu Report -> General Reports and Diagrams -> Diagram to create diagram for whole project. To
create diagram for selected phase or activity (in Activity Gantt only) invoke corresponding shortcut menu with right
mouse button click on corresponding row number, select General Reports and Diagrams -> Diagram. Diagram details can
be specified in opened Diagram settings dialog window.
Success probability trends diagram and earned value analysis diagram can also be created for whole project (in Activity
Gantt only) or for separate project phases and activities: select menu Report -> Success ProbabilityTrends -> Diagram (or
Report -> Earned Value Analysis -> Diagram).
Resource overloads bar can be displayed for all resources of the whole project as green bar with red vertical lines
corresponding to periods of time, when resources are overloaded. To display resource overloads bar select Report ->
Resource Overloads Bar, then press button Resource peak workload (or select menu item Calculations -> Resource
Peak Workload) or Ctrl + F8 as hot key. Resource overloads bar shortcut menu (to invoke shortcut menu click with right
mouse button on Resource overloads bar) contains following items:
- Search for overloads – displays a list of overloaded resources in periods corresponding to the point where shortcut
menu was invoked.
- Delete Diagram –removes bar.
You can customize view of created diagrams of other types, edit content and delete diagrams. To perform these actions
invoke diagram shortcut menu with a right mouse button click on a diagram and select:
- Properties – allows to customize view of created diagrams in properties dialog window;
- Contents – allows to specify content to display on the diagram in Diagram settings dialog window;
- Update – recalculates the diagram according to the changes made in the project;
- Delete –removes the diagram.
225
Reports and Diagrams
Options of the above mentioned diagrams can be specified in Diagram settings dialog window.
226
Reports and Diagrams
Options of Earned value analysis diagram can be specified in Earned value analysis diagram setup dialog window.
Options of Success Probability Trends diagram can be specified in Success probabilities diagram options dialog window.
Frame Report Beginning and End allows to choose the period for which the report is created:
Whole Project – the report will be created under the whole project.
By selecting Selected Period option, in fields Start and Finish date and time of the beginning and the end of the period for
which the report is created (double click in this cell opens mini-calendar dialog window to set date and time easier) can be
set.
227
Reports and Diagrams
By selecting Shift from Data Date option, in fields Shift of Beginning and Shift of end the quantity of days added by current
time of the project to receive the certain interval of time for which the report will be created can be set.
Parameters to create the diagram are selected in this page. Choosing parameters is possible by group buttons: General; Cost
Components; Cost Centers; Materials; Material Centers, Material Sets and User Fields (only Numerical User Fields).
Depending on the chosen parameter the list of corresponding elements will be available to choose in the list which is located
on the left. This list can be sorted by Code and Name. From this list, move necessary elements to the list which is on the right
with button >> to complete selection. It is possible to include elements more than once to have their datas in multiple places.
Elements can be ordered in the list which is on the right. Chosen element can be moved downwards or upwards in the list by
using corresponding «Up» – «Down» buttons (fields will be displayed in diagram with this order).Button << will remove
selected objects from list.
Sort button opens parameter sorting setup dialog window, where you can select descending or ascending (if descending
option is not selected by default it will be sorted ascending) options to sort.
Note That: in choice of parameters Resources and Resource Centers in the left bottom corner Resources frame will be
accessible. Depending on, on what parameter the report will be generated, it is necessary to choose one of options Resource
Hours, Quantity, Resource Hours (Free), or Quantity (Free), and only then to transfer objects to the right field. Parameters
Resource Hours (Free), and Quantity (Free) display free quantity of the chosen resource or quantity free resource-hours.
Note That: option Total Cost becomes accessible in a choice of parameters Cost components, Materials and Material
Centers. When it will be selected data on the chosen parameter will be displayed in the report in base project currency (base
currency is the monetary unit in which final expenses of the project in view of cost component unit cost and cost component
cost periods and materials are considered).
Frame Parameter Type contains options: Total, Consumption, Income. Depending on which option is selected, in the report
final expenses on chosen parameters, only charges, or only incomes will be displayed accordingly.
Baseline allows to display inclusion of an option in the report data on the chosen parameters from the base version (before
generating reports on templates it is necessary to specify the baseline in project properties dialog window). The option should
be included before transferring parameter to the right field of the list of parameters.
Report Parameters Wizard button, located in the left top part, allows choosing and adding basic additional parameters to
report. As a result report becomes more detailed, as different types of data and various combinations will be incorporated in
it. Thus, use of additional parameters will allow receiving various reports.
Button Formulae invokes formulae creation dialog window
Frame By Period allows setting an interval of time for which report data will be generated. For example, period By weeks is
set by default. It means, that data will be included in the report on the chosen parameters per week.
Note That: If period By Weeks is chosen; in column headings, first day dates of each week (Monday) will be written. For
example: 02.02.2006; 09.02.2006 and so on. To display the name of last day of the week in document columns heading this
option must be included in Rows and Columns page (option: Use the last day of the week in column name)
Button Save as Report Template allows keeping settings of the created report in the EVA report templates table for
subsequent uses. In the opened dialog window a name and code for template should be set. It is possible to rename templates,
from EVA report templates table in their EVA report template properties dialog window.
228
Reports and Diagrams
If all required parameters were set for creating the report, then it is possible to press button Done which is located on the left
bottom of window.
If it is necessary to change some default report parameters, proceed to the next page with Next > button:
Diagram Page.
Diagram Height field allows setting height of the diagram to be created according to report template. Valid range is 20 – 600.
Color frames show current colors of the diagram when values are greater than 0 and lower than 0. To change the color press
Select button and select required color.
You can also change the title of the diagram as it would appear on the diagram – type required name in corresponding Name
field.
To move between Diagram and Parameters and Data pages use < Back and Next > (these are the default buttons of your
computer operating system so depending on the default language of your operating system name of these buttons may vary)
buttons at the bottom of the window.
Press OK button to create diagram according to settings made or press Cancel to quit without creating a diagram.
To invoke this option, first invoke diagram shortcut menu with the right mouse button click on diagram report in the bottom
of Gantt chart and select Properties. If no diagram report is shown there, request Diagram report from General Report
(available in both Gantt charts), Earned Value Analysis, Success Probability Trends (not available in resource gantt) and
Variance Trends, in Report menu.
This will invoke Diagram Properties dialog window allowing editing overall appearance of diagrams shown in Gantt charts.
Set up diagram height (in pixels) in Diagram Height field. The range is from 20 to 600.
Set up diagram color in Graphs frame. The color can be set up separately for each diagram. Highlight diagram’s name from
the list and click Change. Color dialog window , which is standard color-choosing window, will be invoked.
229
Reports and Diagrams
Set up diagram name in Name field by typing new name directly in the field.
Earned value analysis is a specific technique for measuring the performance of work and used to establish the performance
measurement baseline (PMB). It combines project scopes, costs, and time limits and helps project team to estimate project
execution process.
Earned value analysis is based on three basic parameters calculated for each activity:
2. Budgeted Cost of Work Scheduled (BCWS), or Planned Value is part of budgeted activity cost that should be used up
by the time according to basic plan. BCWS is also the authorized budget assigned to the scheduled work to be
accomplished for a schedule activity or work breakdown structure component.
3. Actual Cost of Work Performed (ACWP), or Actual Cost is actual expenditure on activity works finished by the
current moment of time. Total costs actually incurred and recorded in accomplishing work performed during a given
time period for a schedule activity or work breakdown structure component. ACWP can sometimes be direct labor
hours alone direct costs alone or all costs including indirect costs.
4. Budgeted Cost of Work Performed (BCWP), or Earned Value is budgeted cost of actually performed activity works.
BCWP is also the value of work performed expressed in terms of the approved budget assigned to that work for a
schedule activity or work breakdown structure component.
These are parameters used in different combinations to estimate actual project execution compared to the scheduled one. The
following indicators are used most frequently:
Original Cost Variance:
OCV = BCWP - ACWP
When used effectively, allows estimating cost variances and probability trends for individual activities as much as for
activities groups, phases, and project in general.
Cost Variance (%):
CV% = (OCV / ACWP) x 100
Cost Variance in percent is relative indicator showing what share of actual cost of work performed the cost variance takes.
Schedule Variance:
SV = BCWP - BCWS
230
Reports and Diagrams
Schedule Variance compares budgeted cost of work performed with budget. Instead of cost usually used as performance
characteristic, other important properties can be used in this equation: Volumes, Man-hours, Main materials. As Cost
Variance, Schedule Variance allows predicting in some early stages of project execution, negative and positive variances and
trends for single activities, phases, and the project in general.
Schedule Variance in percent:
SV% = (SV / BCWS) x 100
Schedule Variance in percent is relative indicator showing what share of budgeted costs Schedule Variance takes.
Cost Performance Index:
CPI = BCWP / ACWP
To predict and estimate project execution in cost terms, cost performance indexes is often used. It is budgeted and actual
costs of work performed ratio.
Cost Performance Index in percent:
CPI% = (BCWP / ACWP) x 100
Cost Performance Index can be calculated in percent.
In some applications, the following indicators are used to predict project completion date:
Schedule Performance Index:
SPI = BCWP / BCWS
Schedule Performance Index equaled to budgeted cost of work performed over budgeted cost ratio, characterizes work
completion term variance.
Schedule Performance Index in percent:
SPI% = (BCWP / BCWS) x 100
Schedule Performance Index can be calculated in percent.
The following indicators in Earned Value Analysis make up group of trend indicators:
Estimate to Completion:
ETC = ACWP + PF x (BAC - BCWP)
Estimate to Completion is sum of actual cost of work performed (ACWP) and budgeted cost of remaining work (BAC -
BCWP) multiplied by Performance Factor. BAC stands for Budget at Completion, which is sum of costs of all project work
according to baseline. Performance Factor value depends on subjective estimation of current cost variances of work and
shows how many times future actual expenditure will exceed budgeted ones.
If project team decides that current variance is of coincidental nature and that future cost of work will correspond to the
budgeted, Performance Factor equals to 1:
ETC = ACWP + (BAC - BCWP)
If current variances are expected to correspond with the future ones, Performance Factor is set up as inverse to Cost
Performance Index (CPI):
ETC = ACWP + (BAC - BCWP) / CPI
In other cases, Performance Factor is set up as some weighted value.
Variance at Completion:
VAC = BAC - ETC
Variance at Completion compares Budget at Completion (BAC) with Estimate to Completion (ETC).
Variance at Completion in percent:
VAC% = (VAC / ETC) x 100
Variance at Completion in percent shows what percent Variance at Completion is from Estimate to Completion.
To Complete Performance Index:
TCPI = ((BAC - BCWP) / (ETC - ACWP)) x 100
231
Reports and Diagrams
To Complete Performance Index shows what percent budgeted cost of remaining work is of the estimated one. In other
words, shows what effectiveness (in percent) should be applied to remaining work to reach Estimate to Completion value.
232
Reports and Diagrams
Page Parameters and Data– Success Probability Trends contains following fields:
- Report Name – name of report (by default corresponds to the name of project);
- Report Code – code of report (by default corresponds to the code of project);
- Report Version – version number of report (by default corresponds to the version number of project);
Frame Report Beginning and End allows to choose the period for which the report is created:
Whole Project – the report will be created under the whole project.
By selecting Selected Period option, in fields Start and Finish date and time of the beginning and the end of the period for
which the report is created (double click in this cell opens Mini-calendar dialog window to set date and time easier) can be
set.
By selecting Shift from Data Date option, in fields Shift of Beginning and Shift of end the quantity of days added by current
time of the project to receive the certain interval of time for which the report will be created can be set.
Parameters to create the diagram are selected in this page. Choosing parameters is possible by group buttons: General; Cost
Components; Cost Centers; Materials; Material Centers, Material Sets and User Fields (only Numerical User Fields).
Depending on the chosen parameter the list of corresponding elements will be available to choose in the list which is located
on the left. This list can be sorted by Code and Name. From this list, move necessary elements to the list which is on the right
with button >> to complete selection. It is possible to include elements more than once to have their data in multiple places.
Elements can be ordered in the list which is on the right. Chosen element can be moved downwards or upwards in the list by
using corresponding «Up» – «Down» buttons (fields will be displayed in diagram with this order).Button << will remove
selected objects from list.
Sort button opens parameter sorting setup dialog window, where you can select descending or ascending (if descending
option is not selected by default it will be sorted ascendingly) options to sort.
Button Save as Report Template allows keeping settings of the created report in EVA report templates table for subsequent
uses. In the opened dialog window a name and code for template should be set. It is possible to rename templates, from EVA
report templates table in their template properties dialog windows.
.
If all required parameters were set for creating the report, then it is possible to press button Done which is located on the left
bottom of window.
233
Reports and Diagrams
If it is necessary to change some default report, proceed to the next page with Next > button:
In frame Additional Fields for every object (Activities, Phases; Costs; Cost Centers etc) with Add button it is possible to
choose additional fields which will be displayed in the report (by default report will contain Code and Name fields).
Additional fields can be ordered in the list which is on the right. Chosen element can be moved downwards or upwards in the
list by using corresponding «Up» – «Down» buttons (fields will be displayed in report with this order).
Under additional fields list in Column Width floor width of each selected field in the report (column width can be changed
manually) is specified.
Remove button deletes selected fields from the report.
Field Data Columns Width allows changing width of the columns containing data, in the created report.
Field Number of rows in cells allows set number of rows in report cells.
In the left lower side of the window fields Rows and Columns are ordered. These fields contain the data:
- Object - these are the objects of report i.e., phase or the operation, on which the report will be created.
- Parameter - parameter, which will be used for creating the report on the object (for example, total cost, end etcetera).
- Date - when comparison of the current project version with baseline is spent and variance trend points are defined.
With buttons >> and << it is possible to transfer between fields. Next to each field also «up and down arrow» buttons are
located to change order of elements inside of each field. The relative positioning of these data determines appearance of the
report, which data will be transferred to report rows and which – to report columns.
In the right top part of window frame Row Colors is located, where is possible to choose what color in the report will
represent objects (Activities, Phases, etc.): According to Hierarchy or Custom.
According to Hierarchy - color of rows in the report will correspond to objects hierarchical color scale in gantt diagram;
Custom - allows changing object row color in the report by Select button. Default button returns color set of all objects to
program defaults.
- Delete Blank Rows – shows whether rows which are containing no data will be removed;
- Delete Blank Columns – shows whether columns which are containing no data will be removed;
234
Reports and Diagrams
- Additional Fields – whether additional fields (by default in the report there are additional fields Name and Code) will be
brought in the report;
- Autofit of Columns – whether there will be standard width of columns (set by default) or they will automatically fit,
depending on their data,
- Expand Centers – if as a parameter (chosen on page Parameters) Cost Centers or Material Centers are used, by choosing
this option in the report all objects which are a part of this center will be displayed and the line with the center will be
total for its cost components;
Note That: if it is necessary, to view the parameters on which report was created, it is necessary to select option to Keep
new report settings in Spider Project Parameters window.
Данное диалоговое окно предназначено для создания диаграммы трендов вероятности успеха.
Page Parameters and Data – Success Probability Trends contains following fields:
Diagram Name – the name of the diagram (by default corresponds to the name of object on which the diagram is created).
Frame Report Beginning and End allows to choose the period for which the diagram is created:
Whole Project – the report will be created under the whole project.
By selecting Selected Period option, in fields Start and Finish date and time of the beginning and the end of the period for
which the diagram is created (double click in this cell opens "Mini-calendar dialog window" to set date and time easier) can
be set.
By selecting Shift from Data Date option, in fields Shift of Beginning and Shift of end the quantity of days added by current
time of the project to receive the certain interval of time for which the diagram will be created can be set.
235
Reports and Diagrams
By means of group buttons, located below, the parameter on which the success probability trends diagrams will be created
gets out: General; Cost Components; Cost Centers; Materials; Material Centers; Material Sets and User Fields.(only
numerical)
Depending on the chosen parameter, in the left floor of a window there will be a list. In the appeared list it is necessary to
select the necessary object and to transfer it to the right field of list by means of the button >>. The list can be sorted on the
Code or the Name of object, by choosing the corresponding option under the list. Button << removes object from the right
field.
Success probability trends diagrams can be created at once on several parameters.
Properties button opens report parameters dialog window, where its possible to edit characteristics of selected parameter
from the list located on the right side. Sort button opens parameter sorting setup dialog window, where you can select
descending or ascending (if descending option is not selected by default it will be sorted ascendingly) options to sort.
Button Save as Report Template Allows keeping settings of the created diagram in the EVA report templates table for
subsequent use. In the invoked dialog window specify the name and the code for the template to be saved. It is possible to
rename the saved template anytime by opening it from EVA report templates table and evoking its properties.
If enough parameters were set by the user for construction of the diagram press Done button which is on the left bottom part
of page. The diagram will be created on the chosen parameters.
If it is necessary to change some default parameters of the diagram (the name of a parameter on the diagram, color and the
size of the diagram) with button > (text in this button will depend on your computer’s operating system’s default language)
the following page of dialog window opens:
Page Diagram
In field Diagram Height (20 – 600) it is possible to change the height of the formed diagram between values 20(min) and 600
(max).
In field Graphs its possible to change Color of diagram (with Select button) and name of the data on diagram (in field -
Name).
Button < (text in this button will depend on your computer’s operating system’s default language) returns to the previous
Parameters and Data page to re-edit any parameters of the diagram.
236
Reports and Diagrams
Button Done (text in this button will depend on your computer’s operating system’s default language) creates the diagram.
Note That: After the creating diagram, if it is necessary for the user, to be able to view again the parameters on which the
diagram was created, (on page Parameters and data) before the creation of the diagram it is necessary to select option in a to
Keep new report settings from Spider Project Parameters window.
237
Report Templates
Report version and period dialog window is opened before creating reports on templates in case Define version number and
report period option is enabled in report template properties dialog window.
Version field contains version number of the last report created. To replace existing report with a new one – leave Version
number unchanged. For a new Version number new report file will be created and its icon will appear in Documents section
of the main program window
Start and Finish fields allows to set report period starting and ending date and time.
238
Report Templates
Standard report templates have predefined name, code and parameters list; these properties of standard report templates
cannot be edited. You can edit other template properties in Report template properties dialog window.
Standard report templates are stored and can be edited in standard report templates table.
Total Cost standard template allows to receive the report only on total costs. In table reports created on other standard
patterns, data at once on all parameters of the chosen template, for example, on all cost components of the project, on all
materials of the project, on all resources of the project (by their quantity(amount), workload or overload) will be displayed.
Resources – Overloads standard pattern creates only table report, and to create diagram with it is not possible. On the rest of
templates it is possible to create both table reports and diagrams. Diagrams can be formed only on one parameter(the first in
parameters list).
On Data page of Resources – Overloads standard pattern there is an additional option to Expand Resource Overloads to
Assignments. At its inclusion, in the given report besides overloaded resources, names of activities where resources are
overloaded, will be displayed.
239
Script
31. Scripts
31.1. Scripts Table
In this table scripts are created and stored. By default contains following columns:
- Code – unique code of the script;
- Name – name of the script;
- Notes – comments to the script;
- Script – Contains the text of the given script. Double click in this table cell opens script properties dialog window on its
Data page;
- Favourite – In this field it is possible to promote one of scripts to "favourite" status. In the further usage this promotion
will allow to execute it from any program window by pressing {bmc Sp__0007.bmp} button which is located on tools
panels.
- User defined fields;
Working with this table is made by the general rules, identical for all tables of the project.
Shortcut menu of a selected group of rows contains only the items to Execute and Delete.
By means of Execute button it is possible to execute the selected group of scripts consistently (scripts will be executed with
the order; as they were selected in table lines).
240
Script
This dialog window is intended for creation and editing scripts. Using scripts will allow automating numerous performance
processes of set action sequences. The scripts dialog window is invoked from the main menu of any table or gantt chart (from
menu items Edit -> Script -> Create), and also from the main program window (from menu items File-> Script -> Create).
241
Script
Script command arguments dialog window is invoked from Add command dialog window when you insert script command
that has any arguments.
The appearance of the dialog window invoked is specific to command being inserted and contains all command arguments.
Arguments are arranged in different ways to ease the process of entering commands. For example, dialog window of
PROJSETSCHED command has the following view:
242
Script
Text fields (e.g. for Structure Code) allows either direct typing required values or choosing from alternatives available
(pressing Select button invokes corresponding dialog window). Fields with list boxes (e.g., Method of calculation) allows
selecting required value from the list. Fields with radio buttons (Yes, No) allows to select option required.
Brief description of the command can be found at the bottom of the window; detailed description can be accessed on pressing
Help button.
You can specify arguments required and press OK. Command with all entered arguments will appear in Script dialog
window. Pressing Cancel closes the Script command arguments dialog window without inserting command.
Script History Dialog window allows you to repeat script executed during current session of work with project file.
The list of date and time of scripts executed is shown in the Time frame.
Commands performed in each selected script are shown in the Script frame.
You can select required script in the Time frame and press OK button to insert commands from current script into the
window of Script dialog window for further editing and execution or saving script to file.
Button Cancel closes the dialog window.
If you perform a task repeatedly, you can automate this task with the aid of scripts. Script includes commands that perform
individual tasks. Commands generally refer to certain items in program menus or dialog windows.
For example, to create a new project with code ‘delivery’ and version #1 in your ‘Working’ storage, you can run following
script command:
CREATEPROJNEW ( delivery , 1 , Working );
Several commands can be performed one after another in one script, e.g.,
OPENPROJ (plant , 2 , Working );
PROJIMPORTFACT ( plant , 1 , Working );
PROJCALCSCHED ();
PROJCALCRES ();
PROJCALCCOST ();
PROJSAVEAS (plant , 3 , Working);
PROJCLOSE ();
243
Script
This script opens existing project with code ‘plant’ and version #2 from ‘Working’ storage, imports performance data from
another project (code ‘plant’ and version #1 from ‘Working’ storage), then recalculates project schedule, resource peak load
and project expenditures of cost components and materials, and finally saves project file with a new version number (#3)
and closes file.
Note that: If the script earlier has been kept in a text file, it can be started not only from a script dialog window, but also
from a command line. String to execute script from command line:
<name of Spider Project exe file> /s exec <full path to script file>, where
name of Spider Project exe file – is the name of Spider project executable file depending on the version installed
(e.g. sp.exe)
The script can be created or in a script creation dialog window, or in the project’s scripts table. You can enter scripts each
time directly or save them in text files for further use.
Besides, if the script is kept in scripts table it can be executed from any project table and from Gantt Charts.
31.6.2. CLOSE
31.6.3. CREATEDOCDB
CREATEDOCDB- create document from a database. Newly created document becomes current document afterwards.
31.6.4. CREATEDOCTEXT
CREATEDOCTEXT - create new document/reference-book from text file (CSV); it becomes current document
afterwards.
31.6.5. CREATEDOCHTML
CREATEDOCHTML - create new document/reference-book from HTML-file; it becomes current document afterwards.
244
Script
31.6.6. CREATEDOCNEW
31.6.7. CREATEPROJDB
CREATEPROJDB- create project from a database. Newly created project becomes current project afterwards.
31.6.8. CREATEPROJFILE
CREATEPROJFILE - create new project from text files of Spider Project format (it becomes 'current project'
afterwards)
31.6.9. CREATEPROJMPX
245
Script
31.6.10. CREATEPROJMSP
CREATEPROJMSP - create project from Microsoft Project database. Newly created project becomes current project
afterwards.
31.6.11. CREATEPROJNEW
31.6.12. CREATEPROJP3E
CREATEPROJP3E - create project from Primavera P3e database. Newly created project becomes current project
afterwards.
31.6.13. DOCAPPLYCOLUMNS
31.6.14. DOCAPPLYCURRPROJ
246
Script
31.6.15. DOCAPPLYDOC
31.6.16. DOCAPPLYPROJ
31.6.17. DOCAPPLYPROJTAB
247
Script
31.6.18. DOCCLOSE
31.6.19. DOCDBEXPORT
DOCDBEXPORT - export current document to a database.
31.6.20. DOCFILEEXPORT
31.6.21. DOCHTMLEXPORT
248
Script
31.6.22. DOCRUNFORMULA
DOCRUNFORMULA - execute calculation with formula in current document.
In Spider Project, formulas are made of column codes separated with mathematical operators. Formula starts with column
code the calculation is performed for, followed by equality sign and a mathematical expression. Mathematical expression
contains column codes, operator, and functions.
31.6.23. DOCSAVE
31.6.24. DOCSAVEAS
31.6.25. DOCSETKEYFIELD
31.6.26. DOCSETPROP
Syntax: DOCSETPROP (CODE : code, VER : ver, NAME: name, NOTES : notes, TYPE : type);
249
Script
type
code text document code
string
ver integer document version
name text document name
string
notes text notes to document
string
type text document type. Valid document types:
string COMMON – general document or reference-book;
MAT – materials;
RES – resources;
COST – cost components;
SPENDOPER – activity cost and material requirements (per volume);
PRODASSIGN – resource assignment productivities;
LOADASSIGN – resource assignment work load;
SPENDASSIGNVOL – resource assignment cost and material
requirements (per volume);
SPENDASSIGNNUM - resource assignment cost and material
requirements (per quantity);
RESPOOL – resource skill;
RESMULT – multi-resources.
31.6.27. DOCTEXTEXPORT
31.6.28. OPENDOC
31.6.29. OPENPROJ
250
Script
31.6.30. PROJAPPLYREF
31.6.31. PROJAPPLYREFTAB
31.6.32. PROJCALCCOST
31.6.33. PROJCALCPROB
251
Script
31.6.34. PROJCALCRES
31.6.35. PROJCALCRISK
31.6.36. PROJCALCSCHED
31.6.37. PROJCALCSCHEDRES
31.6.38. PROJCLOSE
31.6.39. PROJCOMPAREBASEPROJ
31.6.40. PROJCOMPAREPROJ
252
Script
31.6.41. PROJCOPYPHASEASPROJ
31.6.42. PROJDBEXPORT
PROJDBEXPORT - export current project to a database.
31.6.43. PROJDELCOMPARE
31.6.44. PROJDELPROB
31.6.45. PROJDELRISK
31.6.46. PROJEVACALCPFOPER
PROJEVACALCPFOPER - calculate default performance factor for earned value analysis report for activity;
253
Script
31.6.47. PROJEVACALCPFPHASE
PROJEVACALCPFPHASE - calculate default performance factor for earned value analysis report for phase;
31.6.48. PROJEVACALCPFWBS
PROJEVACALCPFWBS - calculate default performance factor for earned value analysis report for WBS;
31.6.49. PROJFILEEXPORT
31.6.50. PROJFOLDOPER
31.6.51. PROJFOLDRES
254
Script
31.6.52. PROJIMPORTFACT
31.6.53. PROJINSPROJASPHASE
31.6.54. PROJINSPROJASPHASEDOWN
31.6.55. PROJMAKEEVAREPOPER
PROJMAKEEVAREPOPER - create earned value analysis report for activity; created report becomes current
document afterwards.
255
Script
31.6.56. PROJMAKEEVAREPPHASE
PROJMAKEEVAREPPHASE - create earned value analysis report for phase; created report becomes current document
afterwards.
31.6.57. PROJMAKEEVAREPWBS
PROJMAKEEVAREPWBS - create earned value analysis report for WBS; created report becomes current document
afterwards.
31.6.58. PROJMAKESPENDREPDEPT
PROJMAKESPENDREPDEPT - create general report for department; created report becomes current document
afterwards.
31.6.59. PROJMAKESPENDREPDEPTPATT
PROJMAKESPENDREPDEPTPATT - create general report for department according to report template. Created
document (report) becomes active afterwards.
256
Script
31.6.60. PROJMAKESPENDREPOBS
PROJMAKESPENDREPOBS - create general report for OBS; created report becomes current document afterwards.
31.6.61. PROJMAKESPENDREPOBSPATT
PROJMAKESPENDREPOBSPATT - create general report for OBS according to report template. Created document
(report) becomes active afterwards.
31.6.62. PROJMAKESPENDREPOPER
PROJMAKESPENDREPOPER - create general report for activity; created report becomes current document afterwards.
31.6.63. PROJMAKESPENDREPOPERPATT
PROJMAKESPENDREPOPERPATT - create general report for activity according to report template. Created
document (report) becomes active afterwards.
257
Script
31.6.64. PROJMAKESPENDREPPHASE
PROJMAKESPENDREPPHASE - create general report for phase; created report becomes current document afterwards.
31.6.65. PROJMAKESPENDREPPHASEPATT
PROJMAKESPENDREPPHASEPATT - create general report for phase according to report template. Created document
(report) becomes active afterwards.
31.6.66. PROJMAKESPENDREPRES
PROJMAKESPENDREPRES - create general report for resource; created report becomes current document afterwards.
31.6.67. PROJMAKESPENDREPWBS
PROJMAKESPENDREPWBS - create general report for WBS; created report becomes current document afterwards.
31.6.68. PROJMAKETRENDREPASSIGN
PROJMAKETRENDREPASSIGN - create success probabilities trend report for activity resource assignment;
created report becomes current document afterwards.
258
Script
31.6.69. PROJMONITORAPPLY
31.6.70. PROJMONITORDBEXPORT
PROJMONITORDBEXPORT - export monitoring table data from the current project to a database.
31.6.71. PROJMONITORDBIMPORT
PROJMONITORDBIMPORT- import monitoring data to the current project from a database.
31.6.72. PROJMONITORFILEEXPORT
PROJMONITORFILEEXPORT - exports project monitoring table to text file (Spider Project format).
31.6.73. PROJMONITORFILEIMPORT
PROJMONITORFILEIMPORT - imports project monitoring table from text file (Spider Project format).
31.6.74. PROJMPXEXPORT
259
Script
31.6.75. PROJMSPEXPORT
PROJMSPEXPORT - export current project to Microsoft Project database.
31.6.76. PROJP3EEXPORT
PROJP3EEXPORT - export current project to Primavera P3e database.
31.6.77. PROJRUNFORMULATAB
PROJRUNFORMULATAB - execute calculation with formula in project table.
260
Script
In Spider Project, formulas are made of column codes separated with mathematical operators. Formula starts with column
code the calculation is performed for, followed by equality sign and a mathematical expression. Mathematical expression
contains column codes, operator, and functions.
31.6.78. PROJSAVE
31.6.79. PROJSAVEAS
31.6.80. PROJSENDFTP
PROJSENDFTP - send project to ftp-server.
31.6.81. PROJSETBASEPROJ
261
Script
31.6.82. PROJSETCOMPARE
Syntax: PROJSETCOMPARE (COMMON : common, COST : cost, COSTCENT : costcent, MAT : mat,
MATCENT : matcent);
31.6.83. PROJSETCOMPARECOMMON
31.6.84. PROJSETCOMPARECOMMONALL
31.6.85. PROJSETCOMPARECOST
262
Script
31.6.86. PROJSETCOMPARECOSTALL
31.6.87. PROJSETCOMPARECOSTCENT
31.6.88. PROJSETCOMPARECOSTCENTALL
31.6.89. PROJSETCOMPAREMAT
31.6.90. PROJSETCOMPAREMATALL
31.6.91. PROJSETCOMPAREMATCENT
263
Script
31.6.92. PROJSETCOMPAREMATCENTALL
31.6.93. PROJSETEVAREP
31.6.94. PROJSETEVAREPCOMMON
PROJSETEVAREPCOMMON - set general field code for earned value analysis report;
31.6.95. PROJSETEVAREPCOST
PROJSETEVAREPCOST - set cost component code for earned value analysis report;
264
Script
31.6.96. PROJSETEVAREPCOSTCENT
PROJSETEVAREPCOSTCENT - set cost center code for earned value analysis report;
31.6.97. PROJSETEVAREPMAT
31.6.98. PROJSETEVAREPMATCENT
PROJSETEVAREPMATCENT - set material center code for earned value analysis report;
31.6.99. PROJSETGANTTOPER
Syntax: PROJSETGANTTOPER (STRUCT : struct, PHASE : phase, OPER : oper, ASSIGN : assign, LEVEL :
level);
265
Script
31.6.100. PROJSETGANTTRES
Syntax: PROJSETGANTTRES (STRUCT : struct, DEPT : dept, RES : res, LEVEL : level);
31.6.101. PROJSETMONITORFILEIMPORT
PROJSETMONITORFILEIMPORT - set options for monitoring table import from text files (Spider Project format).
31.6.102. PROJSETMPXEXPORT
266
Script
31.6.103. PROJSETOPTPROJ
31.6.104. PROJSETP3EEXPORT
PROJSETP3EEXPORT - set export options to Primavera P3e database.
31.6.105. PROJSETPESSPROJ
31.6.106. PROJSETPRECPROJ
267
Script
31.6.107. PROJSETPROBPROJ
31.6.108. PROJSETPROP
Syntax: PROJSETPROP (CURTIME : curtime, DIRFIN : dirfin, CODE : code, VER : ver);
31.6.109. PROJSETRISK
PROJSETRISK - set options for risk analysis and success probability calculation;
Syntax: PROJSETRISK (FIN : fin, TOTALCOST : totalcost, COST : cost, COSTCENT : costcent, MAT : mat,
MATCENT : matcent, PROBOPT : probopt, USEDIRFIN : usedirfin, RECTIME : rectime);
268
Script
calculation
usedirfin Y or N apply target finish dates
rectime Y or N defines whether recommended schedule should be calculated
31.6.110. PROJSETRISKCOMMON
PROJSETRISKCOMMON - set required probabilities of meeting project duration and total cost;
31.6.111. PROJSETRISKCOST
PROJSETRISKCOST - set codes and required probabilities of meeting project cost components consumption;
31.6.112. PROJSETRISKCOSTCENT
PROJSETRISKCOSTCENT - set codes and required probabilities of meeting project cost centers consumption;
31.6.113. PROJSETRISKMAT
PROJSETRISKMAT - set codes and required probabilities of meeting project materials consumption;
269
Script
100 goals;
31.6.114. PROJSETRISKMATCENT
PROJSETRISKMATCENT - set codes and required probabilities of meeting project material centers consumption;
31.6.115. PROJSETSCHED
Syntax: PROJSETSCHED ( STRUCT : struct, PRIOR : prior, TYPE : type, MINPARALL : minparall, DIRFORW :
dirforw, PRIOR : prior, ORDERASC : orderasc, SPLITDIS : splitdis, BREAKMAX : breakmax, BREAKMAXDAY :
breakmaxday, BREAKMAXDUR : breakmaxdur, WORKMIN: workmin, WORKMINDAY : workminday, WORKMINDUR :
workmindur, TOTALCOST : totalcost, COST : cost, COSTCENT : costcent, MAT : mat, MATCENT : matcent,
WITHOUTFLOAT : withoutfloat );
270
Script
31.6.116. PROJSETSCHEDCOST
31.6.117. PROJSETSCHEDCOSTCENT
31.6.118. PROJSETSCHEDMAT
31.6.119. PROJSETSCHEDMATCENT
271
Script
31.6.120. PROJSETSCHEDRES
31.6.121. PROJSETSCHEDRESALL
31.6.122. PROJSETSPENDREP
Syntax: PROJSETSPENDREP (PERIOD : period, FROMTO : fromto, DATEFROM : datefrom, DATETO : dateto,
CUMULATIVE : cumulative, ACTUAL : actual, PLAN : plan, USERFIELDS : userfields, REVPOSITIVE : revpositive,
DELBLANKROW : delblankrow, DELBLANKCOL : delblankcol, TOTAL : total, DATE : date, HLACTUAL : hlactual,
NAME : name, CODE : code, VER : ver, ROWCOL : rowcol, WIDTH : width, AUTOFIT : autofit, LOWEST : lowest);
272
Script
31.6.123. PROJSETSPENDREPADDCOLUMN
PROJSETSPENDREPADDCOLUMN - add fields to general report.
31.6.124. PROJSETSPENDREPCOLRESET
PROJSETSPENDREPCOLRESET – clear the list of additional fields for general report.
31.6.125. PROJSETSPENDREPCOMMON
273
Script
31.6.126. PROJSETSPENDREPCOMMONALL
31.6.127. PROJSETSPENDREPCOST
31.6.128. PROJSETSPENDREPCOSTALL
31.6.129. PROJSETSPENDREPCOSTCENT
31.6.130. PROJSETSPENDREPCOSTCENTALL
31.6.131. PROJSETSPENDREPMAT
274
Script
31.6.132. PROJSETSPENDREPMATALL
31.6.133. PROJSETSPENDREPMATCENT
31.6.134. PROJSETSPENDREPMATCENTALL
31.6.135. PROJSETSPENDREPPAR
Composition and order of arguments are arbitrary. Each argument can be specified only once.
275
Script
(Abbreviations: CostTotal – Total Cost; DurSum – Duration (hours); VolSum – Volume; WorkLoadSum – Resource-
hours; Number – Quantity)
31.6.136. PROJSETSPENDREPRES
31.6.137. PROJSETSPENDREPRESALL
31.6.138. PROJSETSPENDREPRESCENT
31.6.139. PROJSETSPENDREPRESCENTALL
276
Script
31.6.140. PROJSETSPENDREPRESCENTCOMMON
PROJSETSPENDREPRESCENTCOMMON - set parameter: resource center general field for general report.
31.6.141. PROJSETSPENDREPRESCOMMON
31.6.142. PROJSETSPENDRESET
31.6.143. PROJSETTRENDREPCOMMON
PROJSETTRENDREPCOMMON - set general field codes for success probabilities trend report;
277
Script
31.6.144. PROJSETTRENDREPCOMMONALL
PROJSETTRENDREPCOMMONALL - set all general fields to participate in success probabilities trend report;
31.6.145. PROJSETTRENDREPCOST
PROJSETTRENDREPCOST - set cost component codes for success probabilities trend report;
31.6.146. PROJSETTRENDREPCOSTALL
PROJSETTRENDREPCOSTALL - set all cost components to participate in success probabilities trend report;
31.6.147. PROJSETTRENDREPCOSTCENT
PROJSETTRENDREPCOSTCENT - set cost center codes for success probabilities trend report;
31.6.148. PROJSETTRENDREPCOSTCENTALL
PROJSETTRENDREPCOSTCENTALL - set all cost centers to participate in success probabilities trend report;
31.6.149. PROJSETTRENDREPMAT
278
Script
31.6.150. PROJSETTRENDREPMATALL
31.6.151. PROJSETTRENDREPMATCENT
PROJSETTRENDREPMATCENT - set material center codes for success probabilities trend report;
31.6.152. PROJSETTRENDREPMATCENTALL
PROJSETTRENDREPMATCENTALL - set all material centers to participate in success probabilities trend report;
31.6.153. PROJTABDBEXPORT
PROJTABDBEXPORT - export current project table to a database.
279
Script
31.6.154. PROJTABDOCCOPY
PROJTABDOCCOPY - copies a table from current project as Spider Project document. Document becomes current
document afterwards.
31.6.155. PROJTABFILEEXPORT
PROJTABFILEEXPORT - exports a table from current project to text file (Spider Project format).
280
Script
31.6.156. PROJTABHTMLEXPORT
281
Script
31.6.157. PROJTABTEXTEXPORT
282
Script
31.6.158. PROJVERINC
31.6.159. RECEIVEPROJFTP
RECEIVEPROJFTP- receive project from ftp-server. Received project becomes current project afterwards.
31.6.160. SAVEALL
31.6.161. SETCOPYPROJ
SETCOPYPROJ - set options of copied (i.e. source) and original (i.e. destination) activities and phases change;
(Activity Gantt; Copying Activities in Activity Gantt)
Syntax: SETCOPYPROJ (OFROM : ofrom, OREPL : orepl, OPREF : opref, OPOST : opost, CMULT : cmult,
CFROM : cfrom, CREPL : crepl, CPREF : cpref, CPOST : cpost);
283
Script
31.6.162. SETCURRDOC
31.6.163. SETCURRPROJ
SETCURRPROJ - set current project;
31.6.164. SETDISTRPROJ
284
Script
31.6.165. SETDOCAPPLY
31.6.166. SETFILEEXPIMP
SETFILEEXPIMP - set options of export-import to/from text files (CSV) and Spider Project files;
32. Signals
32.1. Signals
In the user fields it is possible to mark cells with markers of various colors and shapes, which notify that the various values in
the given floor get in the certain intervals. A set of intervals, to each appointed a certain color, is called Signal.
The signal, in particular, can be used for tracking deviations from the base plan. In this case in signal properties, what color
corresponds to this or that time interval of a deviation from the base plan, is shown. For example, the deviation of less than
one day can be marked with green color, a deviation about three days - yellow, and deviations more than three days - red.
To set basic characteristics of a signal include option Signal type in columns properties dialog window of user fields, which
shows, that values in the given field are transformed to the markers of a signal. Then press button Select to choose a
previously created signal from the list and a kind of marker from «Markers» window.
Signals are created and edited in signals table. To set and change the characteristics of each signal is possible in signal
properties dialog window or in columns properties dialog window.
Note That: Signals and markers can be created and selected only for user fields.
285
Script
Working with this table is made by the general rules, identical for all tables of the project.
The shortcut menu of a row consists of following items:
Properties – opens signal properties dialog window to edit signal properties.
New – creates a new signal.
Delete – deletes the signal and its line from the table.
Shortcut menu of a selected group of rows contains only the item Delete.
This dialog window is intended for editting signal properties and consists of following pages:
- Data;
- notes standard page.
Page Data
Name – name of the signal.
Code – unique code of the signal.
In Intervals field intervals of numbers (to each of them a certain color is appropriated) which refers to signal as a set are
displayed..
To create a new interval use Add button, which opens interval properties dialog window. In the given window interval
beginning and the color appropriated to it are shown.
Properties button opens interval properties dialog window to edit its characteristics.
Button Delete, deletes the created interval.
In Color field color of the selected interval is shown.
286
Script
If no color is desired to be used press None button. Thus the marker of the inverval will also not be displayed.
287
Group Work on the Project
Dialog window sets properties for persons taking part in current project management. Dialog window includes following
pages: Data, Access Rights, Phases Notes, OLE-objects and Folder.
Page Data
Sets users Name, Code and one of possible Connection Methods: Local network or FTP-server. You can Select paths to
folders (or name of FTP-server) in fields Inbox (for distribution) and Outbox (for consolidation).
Actuality of project information in group work on the project is maintained through distribution and consolidation of
subprojects. Folder (or FTP-server) Inbox (for Distribution) receives phases for the current manager (defined in phase
properties dialog window) after the procedure of distribution of subprojects. Manager should save revised project in
Outbox (for Consolidation). During consolidation phases are read from Outbox (for Consolidation) of responsible
managers, set in phase properties dialog window.
288
Group Work on the Project
With enabled option Send the whole project by distribution current user will receive the whole project file after
distribution; nevertheless during consolidation only phases that the current user is responsible for will be taken.
If box Send the whole project by distribution is checked, current user will be send the whole project even if the user is
assigned as a Manager to a single phase. Nevertheless the user will be able to read and write data according to access
rights set for this user.
Use E-mail by distribution - the file with the project will be sent to user on the electronic mail. The address of electronic
mail is assigned in field e-mail address. If you fill fields of user E-mail address– the user will automatically receive
notification of successful completion and start of project distribution if Notify before Start and Finish of Works option is
selected.
User can also send email from the users table.
Note that: you can set the same paths of folders (or names of FTP-servers) for Inbox (for Distribution) and Outbox (for
Consolidation).
Page Phases
On this page, phase users can be appointed. In Structure field, the structure in which the given user will be appointed is
selected from project structures drop-down list. The phases list of the chosen structure is displayed hierarchically in the
floor located below. Add button appoints the chosen user as selected phase’s manager. The button Responsible
appropriates to the appointed manager the status responsible of the phase. Delete button removes user from purpose as the
manager of the selected phase.
289
Group Work on the Project
290
Access Rights
Access rights properties dialog window lets you view and edit access rights templates to project objects (on corresponding
pages): Data; Cost Components; Materials ; Resources; Reference-books; Actual Performance; Notes; Weeks, Calendars,
Exceptions; Users; WBS; Phases;. Created access rights templates can be assigned to project users.
Page Data – you can set Name and Code of access rights template on this page.
Page Notes – you can add comments to current access rights template on this page.
Other pages of dialog window represent groups of project objects, for which you can set access rights. Lists of all project
groups’ objects contain code and name of the object and type of access:
Full rights, full access for reading and changing project/portfolio objects and their properties
Only from corporate reference-books changing project/portfolio objects is possible only in by corporate reference-books
application.
View only – only viewing project/portfolio objects and their properties without any opportunity to change them (it will be
impossible to change or remove object properties)
By default (for newly created access rights template), access is set to ‘full rights’.
The list can be sorted by Code or by Name (check corresponding box below the list).
To change access rights:
On pages Resources, Weeks, Calendars and Exceptions, Users, Reference-books, Performance Archive access right will
be applied to all objects contained in corresponding project tables (for example, access rights set on page Resources, will be
applied to all resources stored the resources table)
On pages Materials, Cost Components, WBS (also in PBS and Multiprojects – in project portfolios), Without dependence
from the chosen variant of access rights for these objects, it is possible to establish an option to Hide. If on these pages one or
several objects will be chosen from the list and the option to hide will be selected for them, the information on the latent
objects will be inaccessible for users to whom the given access rights are appropriated. The button All the same equally
allows to establish or remove an option to Hide for all objects from the list on corresponding page.
291
Access Rights
On page Phases, besides Full access rights, for one or several phases chosen from the hierarchical list, the option View only
similarly is established and the button All the same equally is used.
Note that: Setting access rights is possible only for the phases included in responsibility structure .
When authorization dialog window is invoked, type in User name and Password and click OK. The project will not be
opened if password entered is incorrect.
To change password: enter old password in field Old, enter new password in fields New and Confirm and press OK. To
cancel the action press Cancel button.
292
Project Portfolio
When projects are already added into projects portfolio structure and the portfolio is calculated, the further work with a
portfolio is conducted as follows:
1. If in a portfolio of projects it is necessary to receive only the summary information on portfolio, to count terms of
multiprojects, costs under all projects, total resource loadings, and also to receive reports under all projects
(multiprojects), it is enough only to update the information on projects, by choosing corresponding items in the main
menu of Project Gantt: Portfolio – > Update Portfolio. Thus for updating the information it is possible to choose the
Current Version of projects (specified in a portfolio), or the New Version (having last version number among the kept
versions of each of projects).
2. If changes are brought directly in portfolio schedule, it is necessary to update the information on projects (Update
Portfolio) all over again and then to Consolidate Projects, by choosing (Portfolio – > Consolidate Projects). By this,
Project Gantt, where all projects of a portfolio will be hierarchically grouped on phases of various levels will open. After
modification it is necessary to Distribute projects (by choosing in Gantt Diagram items Portfolio – > Distribute projects).
At project distribution the sub items Current Version or the New Version means a choice, whether to update existing
(specified in a portfolio) versions, or to keep under new version number.
Each project of the portfolio can be opened separately, by evoking its shortcut menu in Project Gantt and choosing item to
Open. Item to Select Project from the same menu allows to replace the corresponding project in the portfolio with another
one.
293
Project Portfolio
This window is opened automatically at the creation of a project portfolio (in main program window choose items File –>
Create Portfolio –> New from the menu).
In the invoked window Name, Code, Version and, Data Date, Target Finish, Notes of the portfolio are set. In Storage field
storage, where the portfolio is, displayed.
By choosing option Show hours and minutes, in corresponding table cells and in portfolio dialog windows fields both date,
and time will be displayed. If not - only date.
In Baseline frame, Code and Version number of base protfolio is shown. The base version is set in a projects and documents
dialog window which is opened by Change button. In Storage field the storage, where the portfolio is kept, is displayed.
In Number of linked OLE objects frame number of documents of other appendices attached to the portfolio is displayed.
Activities will be considered critical if their floats in hours will be less than the amount in field Activity is critical if its float is
not greater than _ hours. If this field will be left empty, or its value will be set equal to 0, than all the activities without a
reserve, will be considered critical.
Name and the code of the manager and their access rights to the protfolio are displayed in the bottom part of the given dialog
window.
To edit portfolio properties afterwards choose items Project –> Properties from menu(from any window of a portfolio item)
or from main program window right click on the portfolio and choose Properties option from the invoked shortcut menu.
294
Project Portfolio
Represents a dialog window, which is intended for editing project properties in a portfolio, with following pages:
- Data,
- standard page of OLE-objects and folder,
- notes standard page.
Page Data
- Name – name of the project in the portfolio.
- Code – unique code of the project in the portfolio.
- In Project frame, Code and Version of the project are displayed, with the name of its Storage, which indicates the storage
where the project file is. The project can be replaced by Select button, and choosing the required project from the
invoked window. If only the storage needs to be changed without changing the code and the version, then a double-click
on the Storage field will invoke storages list to select a new one. Storages can be added and removed from projects and
documents dialog window. If it is required to change only storage of the reference-book, without changing its code and
version, it is necessary to double click with left mouse button in Storage floor and to choose the necessary storage from
the opened list.
- Calendar – displays the code and the name of the calendar, on which the duration of project (in days) is considered. To
change the calendar, choose Select option, choose the required calendar from the invoked list and press ОК.
- Manager– displays the name of the manager, assigned in the analogue field of project passport. To replace the manager
press Select button and than choose the new one from the opened portfolio users list window and by press OK button.
- Bar Color – changes project’s bar color on the graphical part of project gantt (object color dialog window will be
invoked)
- Project name, Project code – name and code of the project to which the resource is assigned.
- Resource name, Resource code – name and code of resource.
- Quantity [Scheduled] – scheduled (calculated) quantity of resource.
- Type – type of resource.
- Start [ASAP], Finish [ASAP] – start and finish dates of resource work in the project, received by ASAP schedule
calculation method.
- Start [ALAP], Finish [ALAP] – start and finish dates of resource work in the project, received by ALAP schedule
calculation method.
- Float Hours, Float Days – assignments reserves in hours and days, respectively.
- Resource Hours [Remaining] – remaining scheduled assignment labour hours in resource -hours.
- User defined fields.
Working with this table is made by the general rules, identical for all tables of the project.
- Code – code of the project in the registry table and in the project portfolio.
- Name – full name of the project.
- Notes – comments to the project.
- Project Code – unique code of the project included in the portfolio.
- Version – version number of the project included in the portfolio.
- Location – way to the folder (to a place on a disk or server) where the project is stored.
295
Project Portfolio
- Attached Documents [OLE] – if any OLE document was attached to the project, in this table field (also in a similar field
of project gantt) there will be a sign. Double click in this table cell invokes a project properties in a portfolio dialog
window, opening on its ole-objects and folder page.
- Project Data Date – status project date (scheduled works beginning date) from which there is a forwards calculation of
project schedule.
- Priority – is used at the schedule calculation in view of phases priorities. At assembly of a portfolio the priorities of
projects specified in a given floor become priorities of the created phases.
In columns Bussiness Unit, Budget Unit, Sponsor, Manager, Technical Manager, Project Type, Short Description, Status
additional project characteristics are displayed.
In columns NPV (Net Presented Value), IRR (Internal Return Rate), Payback Date and Expenses values of preliminary
calculated economic parameters of the project are displayed. After comparison of the current project with the base version or
with other project of value of economic parameters of the initial project are displayed in columns NPV [Baseline], IRR
[Baseline], Payback Date [Baseline] and Expenses [Baseline].
Working with this table is made by the general rules, identical for all tables of the project.
Shortcut menu of a selected group of rows contains only the items to Open and Delete.
296
Project Portfolio
Page Data
- Name – name of the multiproject.
- Code – unique code of the multiproject in Project Portfolio.
- Level – level of the multiproject in the hierarchical structure of projects.
- Type – type of the multiproject for the connection with the reference-books.
- Short Name – brief name of the multiproject.
- Priority – priority of the multiproject.
- Calendar – calendar, by which multiproject duration will be calculated in the days. To change the calendar press
Select button and choose new calendar from the list and press OK.
- ASAP Start – the earliest date of the beginning ASAP of the project, in a multiproject.
- ASAP Finish – the latest date of the end ASAP of the project, in a multiproject.
- ALAP Start – the earliest date of the beginning ALAP of the project, in a multiproject.
- ALAP Finish – latest date of the end ALAP of the project, in a multiproject.
In the Manager field name of the manager is reflected (with Select button it is possible to replace manager, by selecting him
in the opened project portfolio users list window)
Bar Color – changes the bar color of multiproject on the graphic part of projects Gantt (in this case object color dialog
window will be invoked)
Page Projects
- Included Projects – list of projects, included in multiproject.
- New – to add new projects to multiproject.
- Properties – to invoke properties dialog window of chosen project.
- Delete – to delete chosen project from projects portfolio.
- Exclude –to exclude selected project from the structure and to transfer into excluded projects list.
- Excluded Projects – list of projects, excluded in multiproject.
- Include – to return excluded projects back to included list.
- Properties – to invoke the properties dialog window of chosen project.
- Delete – to delete chosen project from portfolio.
Page Multiprojects
Contains a list of multiprojects from lower levels to higher ones.
- New – to add new multiprojects.
- Delete – to delete chosen project from portfolio.
- Exclude – to exclude selected multiprojects from structure (multiprojects can not be excluded from responsibility
structure, since it must be complete). With the exception of multiprojects from the current structure, the objects of the
lower level of (projects) hierarchy are excluded, and empty multiprojects can be removed from the structure. Excluded
objects can be subsequently included in the current structure.
297
Project Portfolio
If several lines will be selected in Gantt diagram, shortcut menu will consist:
Open, Reports and Diagram Templates (Table; Diagram), General Reports and Diagrams (Table; Diagram),Copy, Cut,
Paste and Remove from portfolio.
298
Project Portfolio
The basic project and multiproject characteristics are set and edited in project in a portfolio properties dialog window and
multiproject in a portfolio properties dialog window respectively.
These dialog windows open by double clicking on the row number of a line with a project/multiproject (or by choosing
Properties item in the shortcut menu of the project/multiproject).
This dialog window is intended for editting project gantt settings and can be opened by pressing {bmc Sp__0003.BMP}
button which is located in project gantt tools panel by choosing items Gantt –> Options from menu
In frame Show there are following options:
- «ALAP» Schedule – displays multiprojects and projects in the form of empty rectangulars according to Start «ALAP»
and Finish «ALAP» (see ALAP) dates in project gantt.
- Horizontal grid and Vertical grid – switches on /switches off display of horizontal and vertical grids respectively.
Data on diagram – option, which allows displaying chosen data on Gantt chart. Data should be specified by user with Select
button.
299
Project Portfolio
Data of the chosen field will be displayed on Gantt chart near to graphic representation of projects and multiprojects. Field
Name is selected by default.
Frame Hide:
- Projects – projects will be hidden if this option is selected.
- Multiprojects – multiprojects will be hidden if this option is selected.
Keep, as it is – does not change the elaboration detail level project gantt.
Expand to: allows setting an elaboration detail level for structure of projects:
Projects – displays structure up to projects, i.e. in project gantt both multiprojects, and projects are displayed.
- - Level – displays structure of projects up to a level specified in a floor, located on the right. At introduction of
wrong value the corresponding message stands out: "Invalid Value!"
Frame Columns:
Selecting option Default order and width establishes standard column setting in a table part of gantt chart which is formed at
the creation of a project portfolio.
Option Number of rows in cells is used for changing height of lines in a table part of Gantt charts.
In field Hierarchic indent size the size of hierarchical spaces in screen pixels (by default from 2 up to 20) for Name and
Short Name fields of gantt chart and account tables is set. For other text fields, spaces can be set in properties dialog window
of each field.
Button Time Scale Setup invokes time scale dialog window for adjusting project portfolio graphic display.
300
Project Portfolio
Gantt
Print Preview – opens print preview window.
Options – opens Activity Gantt diagram options dialog window, where you can customize diagram view in graphic
area.
Load Configuration – restores order of columns, their width in table area and time scale in graphic area from
configuration file (*.stc); all columns created by user (and not described in configuration file) in current project will
be hidden and can be unhidden later through Show Columns (Ins) command from the shortcut menu (invoked with
right mouse button click on columns name) or from main menu Edit item.
Save Configuration – saves order of columns, their width in table area and time scale in graphic area to configuration
file (*.stc).
Export Table to file – exports the table part of the Gantt diagram of activities into the CSV (Comma Separated
Value) type files or HTML.
Export Table to Data Base – exports table to data base.
Export Table to Excel – exports table to excel.
Export Table to CSV-file – exports to CSV or HTML file.delete
Copy as a new Document – copies table of gantt as a new reference-book.
Edit
Undo Last Action – undoes last action.
Protocol of Actions – opens protocol of actions table .
Formulae – opens dialog box to create, edit and apply of formulae.
Script
Create – opens Script dialog window where you can enter, edit and execute scripts;
Execute from File – lets you execute script stored in text file.
Execute– lets you execute a script from the list of previously created ones.
Execute Favourite Script– lets you execute the script, which was previously created and chosen as
favourite.
Show Columns –opens fields' list dialog window ; lets you select hidden columns (fields) to display before active
one.
Hide Column – hides selected columns (these columns are not actually deleted from internal database).
Autofit All Columns – resizes all columns in order to make their contents available to be seen completely.
Search / Replace – opens Search dialog window and starts context string search;
Repeat Search / Replace – repeats search of context string starting current cell.
Copy – copies selected rows or cells to the clipboard.
Cut – puts selected rows or cells to the clipboard. Objects are actually deleted from Activity Gantt only after Paste
command.
Paste – inserts objects from the clipboard: to current work breakdown structure or to selected cell. You can Paste
copied (or cut) activities and phases to selected phase:
- - One Level Lower – choose this option to insert phase as a subphase of the current phase (or activity of
current phase). New phase will be placed next to selected.
- - The Same Level - choose this option to insert phase of the project on the same level of WBS as the
selected phase. Phase of the first level cannot be added.
Select All – selects all rows of Activity Gantt.
Filter:
Apply – opens dialog window where you can create, edit and apply filters.
Filter by Selected Rows – allows filtering out contents of table by the selected rows from the filters dialog window.
Restore – abolishes the action of the used filter.
Calculations.
Cost and Materials Calculation Options – calculates
Cost and Materials Calculation – calculates (recalculates) costs, materials requirements and resources work load
according to current schedule.
Calculations EVA Columns – calculates EVA and then displays calculated parameters values in corresponding gantt
columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding option to
Calculate EVA columns).
Calculations Resource Center Columns – calculates values in Resource Centers (Quantity) and Resource Centers
(Workload) columns (preliminary in cost calculation settings dialog window it is necessary to select corresponding
option to Callculate columns in Resource Center frame).
Resource Peak Work Load - calculates (recalculates) resources work load on activities assignments.
Phase, Department and Resource Dates – calculates phases start and finish dates; calculates dates of work start and
finish for departments and resources.
Report
301
Project Portfolio
302
Project Portfolio
Besides, in each project table window there is an additional tools panel located on the left side. This panel consists of
corresponding project data and representations buttons to switch quickly in other project table or representation.
Project Gantt consists of two parts: table (text information), displaying project structure which is a part of Project Portfolio,
and Gantt Charts (graphical information).
The structure of projects, displayed on Project Gantt, is the current structure. The current structure can be changed, by
choosing Portfolio item, from Project Gantt main menu, and then the sub item PBS. In the opened dialog window specify
necessary structure to display, and press Switch to button.
For convenience work with hierarchical structure of projects in the table parts next to the row numbers + and – signs are
located, allowing to toggle on or off to view the sub-elements of the corresponding element.
The arrangement of columns, their width and name can be kept in a separate file, by saving the configuration. Thus all the
installations made in Gantt diagram settings dialog window also are kept. To save a configurations:
1. From the main menu choose items Gantt –>Save Configuration. In the opened window specify a name for the file
and press Save.
2. 2. Previously saved configuration can be loaded, by choosing items
Gantt –>Load Configuration in the main menu.
Note that: it is possible to load a configuration in Gantt Chart, which was saved in other table, document or reference-book
(see working with tables).
In Gantt Chart, it is possible to select the objects located at the same level of hierarchical structure: only multiprojects or only
projects. For this purpose, keep Ctrl button pressed and select with row numbers of desired objects with left mouse button. At
attempt of selecting simultaneous objects of different type the corresponding error message will appear.
If on row number of any object in the table part of Gantt, right click action will be performed, shortcut menu of object will be
invoked:
Shortcut menu of a project in a portfolio;
Shortcut menu of a multiproject in a portfolio.
303
Project Portfolio
At the top of the graphic part of Gantt Chart, time scale is located. Right clicking will invoke time scale properties dialog
window to adjust it.
In the graphic part of Gantt Chart objects are displayed by rectangulars of the certain color from ASAP Start to ASAP Finish
(see. ASAP).
From the main menu and by hot keys of Gantt Chart tools panel it is possible to:
- Calculate expenses;
- Calculate peak loading of resources;
- Calculate terms of phases, divisions and resources.
In Project Gantt it is possible to create only General reports and diagrams (see. Reports and Diagrams on Gantt Chart).
Besides this, diagrams and table reports can be created on previously created templates.
The created table report opens in a separate window, and its pictogram is displayed in the right part of the main program
window
The generated diagrams are displayed in the bottom part of Gantt Chart: resource overloads diagram, costs and materials
requirements diagram, volumes etc.
Reports and diagrams can be created or on the whole portfolio, or on its separate objects (on projects or multiprojects).
To create a report / diagram on the whole portfolio, choose items Report –> General Reports and Diagrams or Reports and
Diagrams Templates from Gantt Chart main menu, and set further report/diagram properties.
To create a report / diagram on a separate object, invoke object shortcut menu, where it is necessary to choose, necessary kind
of report / diagram.
Note that: indicator of an overload can be created only on all resources and for the whole portfolio. For this in Gantt Chart
main menu choose Report –> Resource Overloads Bar.
When a portfolio is saved, all unextracted diagrams will also be kept, and table reports can be kept as independent documents.
There are corresponding buttons for data and representations of portfolio, which are located on the left side. By means of
these buttons it is possible to switch quickly to other portfolio and Gantt Chart tables.
35.12. PBS
35.12.2. PBS
304
Project Portfolio
The hierarchy of projects can be edited by mouse. It is possible to drag multiprojects inside each level by clicking holding left
mouse button on it and leaving it free on the desired position. To move multiprojects to a below level, hold Shift key pressed -
Alt key to the same level.
If in PBS setup dialog window Tree-type hierarchy is selected (thus projects are represented in the form of rectangulars), the
Panel of tools contains a Scale for smooth change of display scale of PBS Arrow Type to change graphical type of arrows:
from Direct to Rooted and vice versa with each click on this icon.
305
Project Portfolio
306
Project Portfolio
Table – opens report parameters dialog window to create general reports on the multiproject.
Add Project – opens projects and documents dialog window to add project to portfolio.
Remove from portfolio – removes project from portfolio.
307
Data Export-Import
This dialog window is intended for adjustment of export/import of the project or the document into text files.
To simplify path entering, click Choose button, select folder with project text files in the invoked dialog window, and click
Open.
Exporting /importing a project is carried out only into CSV format text files. Exporting /importing tables can be made both
into CSV, and into HTML-files. The format of export/import can be selected in the given dialog window.
Click Change button and select new Text files delimiter from the invoked Spider Project Options dialog window.
Note That: To find out more about file formats, see Monitoring data format.
While exporting to CSV format, table columns are divided by tabs or other symbols chosen by the user (such format allows to
export any table documents to other programs: Word, Excel, Databases).
Format HTML (Hyper Text Marking Language) allows looking through a file in internet browsers without using Spider
Project Software.
Data divider in text files (by default - tabs) can be selected by button Change, opening Spider Project parameters dialog
window.
Format description of file import/export can be received, by pressing Format Description button.
Other settings in the given window are availavle only at export/import of tables (documents):
In First Lines frame, what fields properties of the table should be placed in a file at export / import can be set: Codes (unique
codes of fields), Types (type of each field), Names (the name of table fields). For example, if three options are all
included, in the created text document:
- In the first line Codes of all exported table fields will be displayed;
- In the second line - field Types: symbol S means String field type, and symbol N - Integer field type (if in this line at any
field, near to symbol S or N there is a second symbol K ,it means that the given field is a Key);
- In the third - Names of fields.
Other lines correspond to lines with data.
It is necessary to note, that at creation of a document from files it is necessary to set the same First lines, as in the imported
document.
308
Data Export-Import
In Decimal Digits frame, whether to export all figures after a comma or according to the adjustments made in Spider Project
parameters dialog window. is set.
Selecting Text in DOS codepage option means that the exported file will be kept in DOS coding (by default the text is kept in
Windows coding). During import (creation) of text files the given option is selected depending on in what coding the initial
information is kept.
The option to Export empty values as zeros is used only during export into a file and allows to choose, how table cells with
empty values will be displayed: will be left empty or instead of empty values "0" (zero) will be put down.
The option to Skip rows with empty codes is used only during creation (import) of projects or documents from files. When
this option is selected, lines which do not contain values in Code column will not be included in the created project or the
document.
This dialog window allows you to define options of Spider Project file export to MPX-file format.
If you click Use cost center as total cost option, cost calculated for the selected cost center will be included into MPX format
instead of total costs of phases and activities. Click Select button to select a cost center from the invoked Cost Centers dialog
window containing list of all cost centers available. After you select cost center and click OK, its name and code will appear
in Export into MPX format dialog window.
In Format modifications frame, MS Project (Standard modification) option is selected by default. If you select Primavera
format, WBS activity codes will be converted the following way: ‘0’ is added in code beginning and the last digit is ignored.
Note that after export to MPX-file following project data will be lost in exported file: materials, resource skills, multi-
resources and breakdown structures. Nevertheless all assignments of resources comprising multi-resources and resource skills
are transferred correctly.
If an activity had more than one team assigned, assignments of the first team would be exported to MPX-file. You would be
noticed of data loss in this case.
309
Data Export-Import
Table export options dialog window allows you to customize the set of Spider Project table columns to export to database.
Dialog window appears after selection of menu item Table -> Export table to Data Base.
You can choose to:
- Export only visible fields (checked by default);
- export all standard table fields (option Export only visible fields and all other options unchecked);
- export all standard table fields (option Export only visible fields unchecked) and export additional fields: Material
consumption, Set of materials consumption, Cost components spending, User fields.
Note That: for documents and reference books, where there is no opportunity to export user fields, window looks in another
way:
310
Data Export-Import
Note That: you must have database options set for the database that you are exporting Spider Project table to.
2.
3.
4. Specify path to MS Project database (*.mdb) file to be imported to Spider Project;
5. Press Import button.
Note that project created in MS Project must be saved to mdb-file (Microsoft Access Database) format before it can be
imported to Spider Project.
Note That: you must have database options set for the database that you are importing project from. In order to establish
initial connection to Primavera P3e database you must specify user name privuser and password privuser.
During Primavera P3e project import certain database fields (i.e. missing in Spider Project database structure) are transferred
to user-type fields (see Fields' list dialog window). These fields can be useful in some cases; e.g. to obtain the same activities
order as in Primavera P3e project you can sort activities in activity gantt by seq_num field.
311
Data Export-Import
312
Data Export-Import
Phases' rows will not be transferred to MPX-file. Information on materials, resource skills, multi-resources, and hierarchical
structures are lost during export to MPX-file.
All assignments, including assignments in resources skills and multi-resources, are exported.
If more than one team is assigned to activity, only first team’s assignments will be exported, and a corresponding message
will appear.
Spider Project objects are transferred to MPX-file with the following exceptions:
- Activity and phases codes are transferred to Text1 field;
- Total phases and activities costs by the first three cost components (as in Cost Components table with no filters or
sorting) are moved to Cost1, Cost2, and Cost3 fields, accordingly. And these costs total will be transferred to Cost field.
- Resource Type column is transferred to Text1 field;
- Activity Type column is transferred to Text2 field;
- Activity Name for Columns is transferred to Text3 field;
- Activity Volume Unit is transferred to Text4 field;
- Activity Volume is transferred to Number1 field; and
- Activity calendars are lost. All activities are performed by the main project calendar.
313
Data Export-Import
To import a document from text file, select Create Document –> From file option from File menu in main program window
Import from files dialog window will be invoked. Browse the file you want to import by using Choose button and click OK.
In the invoked window Path shows the directory of the document where it is located.Format can be CSV-file or HTML-file.
Any document in CSV format can be imported to Spider Project. Therefore, table documents created in other applications
(such as Microsoft Word, Excel or database programs) can be imported Spider Project.
If table with the same name already exists in the database, you will be prompted to replace existing table.
4. To close current dialog window and return to your project table press Exit.
Note That: you must have database options set for the database that you are exporting Spider Project table to.
314
Data Export-Import
CSV (Comma Separated Value) format saves table in a format, where its columns will be separated by TABS or any other
symbols (delimiters). This format allows exporting any table documents to other programs (such as Word, Excel, and
Databases). File extension of the files is .txt.
Delimiter can be changed in spider project options dialog window.
Documents saved in HTML format can be opened with internet browsers. Therefore, user will be able to access these
documents without using Spider Project software.
315
Data Export-Import
5. Recalculate project expenditures by clicking Cost and Materials icon on the Gantt diagram toolbar.
Note That: you must have database options set for the database that you are exporting Spider Project table to.
316
Data Export-Import
Frame Databases – contains a list of databases (column Database name) available for Spider Project use; you can select
required database from this list.
Frame Document contains the following buttons (which become active after a database has been selected and opened):
- Import – imports selected project from the database and opens Project Properties Dialog window.
- Delete – deletes selected project from the database.
Group Database contains the following buttons:
- Open – opens selected database and changes list Databases to Documents;
- Close – closes opened database and changes list Documents to Databases;
- Options – opens Database settings dialog window .
List Documents contains database tables; the list contains all database tables:
- documents and tables exported from Spider Project (see Export performance data to database , Export project table
to database , Export of Information to Database )
- a set of database tables created after Create [database] structure was performed (see Database settings )
- tables created in other applications.
Exit – closes dialog window.
317
Data Export-Import
Current dialog window is invoked from Main Window Menu File -> Create project -> From Data Base. In the dialog
window you can select database, project code and version number to create Spider Project project file from (see Create
project from database).
Note That: you must have database options set for the database that you are exporting Spider Project table to.
Frame Databases – contains a list of databases (column Database name) available for Spider Project use; you can select
required database from this list.
Frame Project – contains the following buttons (which become active after a database has been selected and opened):
- Import – imports selected database table as Spider Project document and opens document properties dialog window.
- Delete – deletes selected table from the database.
Frame Database contains the following buttons:
- Open – opens selected database and changes list Databases to Projects;
- Close – closes opened database and changes list Projects to Databases;
- Options – opens Database settings dialog window.
List Projects contains projects in selected database with their Code, Version [number] and [project] ]Name.
Exit – closes dialog window.
Current dialog window is invoked from any project window menu Project -> Export -> Into Data Base. In the dialog
window you can select database to export current project to (see Export project to database).
Note that you must have database options set for the database that you are exporting Spider Project table to.
Frame Databases – contains a list of databases (column Database name) available for Spider Project use; you can select
required database from this list.
Frame Project contains the following buttons (which become active after a database has been selected and opened):
- Export – exports current project to selected database.
- Delete – deletes selected project from the database.
Frame Database contains the following buttons:
- Open – opens selected database and changes list Databases to Projects;
- Close – closes opened database and changes list Projects to Databases;
- Options – opens Database settings dialog window.
List Projects contains projects in selected database with their Code, Version [number] and [project] ]Name.
318
Data Export-Import
Current dialog window is invoked from table menu Table -> Export table to Data Base (after you specify field types to
export in opened Table export options dialog window). In the dialog window you can select database to export current table
to (see Export project table to database).
Note That: you must have database options set for the database that you are exporting Spider Project table to.
Frame Databases – contains a list of databases (column Database name) available for Spider Project use; you can select
required database from this list.
Frame Document contains the following buttons (which become active after a database has been selected and opened):
- Export – exports table to selected database. If a database is already opened (button Open) pressing button "Export"
will add new table to selected database; if a database was not previously opened new table will be exported to
selected database and list Databases will change to Documents.
- Delete – deletes selected table from the database.
Frame Database contains the following buttons:
- Open – opens selected database and changes list Databases to Documents;
- Close – closes opened database and changes list Documents to Databases;
- Options – opens Database settings dialog window.
List Document contains database tables; the list contains all database tables:
- documents and tables exported from Spider Project (see Export performance data to database , Export project table
to database , Export of Information to Database )
- a set of database tables created after Create [database] structure was performed (see Database settings )
- tables created in other applications.
319
Data Export-Import
Frame Databases – contains a list of databases (column Database name) available for Spider Project use; you can select
required database from this list.
Frame Performance data contains the following buttons (which become active after a database has been selected and
opened):
- Export – exports performance data to selected database. If a database is already opened (button Open) pressing
Export will add new performance data to selected database; if a database was not previously opened new
performance data will be exported to selected database and list Databases will change to Performance data.
- Delete – deletes selected project performance data from the database.
Frame Database contains the following buttons:
- Open – opens selected database and changes list Databases to Performance data;
- Close – closes opened database and changes list Performance data to Databases;
- Options – opens Database settings dialog window.
List Performance data contains exported performance data from projects (project codes and version numbers) to selected
database.
Exit – closes dialog window.
Current dialog window is invoked from Monitoring Table -> Import from database. In the dialog window you can select
database to import performance data from (see Import performance data from database).
320
Data Export-Import
Note That: you must have database options set for the database that you are exporting Spider Project table to.
Frame Databases – contains a list of databases (column Database name) available for Spider Project use; you can select
required database from this list.
Frame Performance data contains the following buttons (which become active after a database has been selected and
opened):
- Import – imports performance data from selected project in opened database; you can specify options of import in
opened Import of performance data dialog window.
- Delete – deletes selected project performance data from the database.
Frame Database contains the following buttons:
- Open – opens selected database and changes list Databases to Performance data;
- Close – closes opened database and changes list Performance data to Databases;
- Options – opens Database settings dialog window.
List Performance data contains exported performance data from projects (project codes and version numbers) to selected
database.
If table with the same name already exists in the database, you will be prompted to replace existing table.
5. To close current dialog window and return to your project table press Exit.
321
Data Export-Import
2. Select menu item Table -> Export to Data Base (Note that you must have database options set for the database that you
are exporting Spider Project table to);
3. Monitoring table will be exported to selected database and the list of project codes and version numbers for which
performance data is stored in the current database will be opened in the export performance data to database dialog
window.
4. To close current dialog window and return to your project table press Exit.
322
Exchange of Projects via the Internet
Project saved on FTP-server becomes available for all users who have access to this server. Therefore, even if your computer
were off, users would have access to projects saved on the server.
Before sending projects to and receive projects from FTP-server, perform FTP-server Setup.
Allows setting up FTP-server properties. Is invoked in main program window by selecting FTP-Servers from
Options menu and after from FTP-Servers dialog window by clicking Add (for a new one)or Properties (to edit the existing
one) button. Contains the following options:
- Server Name;
- Host field contains path to a folder on the server;
- Port;
- User name; and
323
Exchange of Projects via the Internet
- Password.
Uploading a project / portfolio to FTP-server can be done from any program window (except for Linear Diagram).
To send from main program window, invoke Project shortcut menu with the right mouse button click on project’s icon/name,
and select Upload to FTP-server.
To send from any other program window (except Linear Diagram), select Upload to FTP-server from Project menu.
To upload a portfolio repeat the same actions on a portfolio.
The following dialog window will be invoked:
In the invoked dialog window, highlight FTP-servers where the project will be sent to and click Send. If you have Internet
access through telephone line, your Internet connection program window will be invoked and connection will start to be
developed. If you are connected through local network, immediate connection will be established.
324
Exchange of Projects via the Internet
2. Click icon on the toolbar or select Connect from Server menu. If you have Internet access through telephone line,
your Internet connection program window will be invoked and connection will start to be developed. If you are
connected through local network, immediate connection will be established. Connection to FTP-server is considered to
become successful when ‘You are not connected to the server’ message on the toolbar disappears. After the connection
was established, the program starts receiving information about available projects and will include them into Available
Projects table field on the left.
3. Highlight project you want to receive. Select several projects by holding Ctrl key.
4. Click > button. The selected projects will be moved to Projects selected for reception table field on the right. To move
all projects from Available projects list, click>> button.
5. Click Receive Projects to start project receiving.
6. After the process is finished, close Receiving Projects dialog window. This will automatically disconnect your computer
from FTP-server. All new files will be opened.
Sorting projects available on server
Projects listed in Available projects table field can be sorted by code, name, or version. Sorting starts with click on a
2. Create a new filter by clicking Add button or select existing filter from the list. This will invoke ‘Filters for Projects on
FTP-server properties dialog window to set up Name, Field, and sorting Sample.
3. Click on Apply button. Filter will be applied and it name will be displayed in Receiving projects dialog window.
Note That: To force the program to disconnect from FTP-server, click Disconnect icon on the toolbar.
Note That: After you have received projects from FTP-server, some other user might have updated the files on the server. If
you would like to receive updated version, click Refresh projects list icon on the toolbar or select Refresh projects list
from Server menu.
325
Exchange of Projects via the Internet
Is invoked from Receiving Projects dialog window and allows setting up filters to show only projects that meet filtering
criteria. Displays the following buttons:
Apply applies highlighted filter.
Add adds new filter by evoking Filter for Projects on FTP-server properties dialog window.
Delete deletes highlighted filter from the list.
Properties invokes Filter for Projects on FTP-server properties dialog window to edit highlighted filter’s properties.
Is invoked from ‘Filters for Projects on FTP-server dialog window when new filter is being added or properties of existing
filter are edited.
Name is filter name.
Field is a field to be used for filtering objects.
If Name or Code field are chosen as Field, set up Sample to be used in filtering: only projects with first symbols of the
selected field matching with the Sample will be included in the resulting list.
If Version is chosen as Field, set up a range of project versions to be included in the filtered list. If From field is left empty, it
is set up as 0; if To field is left empty, it is equaled to infinity by default.
326
E-mail
38. E-mail
38.1. Send E-mail
You can send e-mail message to users in the Users Table. To send e-mail:
1) Check that user you are going to send e-mail has defined E-mail address (in users properties dialog window)
2) Check that the name of SMTP Server used to send E-mail in spider project parameters dialog window is defined,
3) Invoke shortcut menu for the user or group of users whom you want to send e-mail and choose Send Mail option.
4) In opened send e-mail dialog window enter subject and the message body;
5) Press Send to send e-mail; Close – to cancel action
During sending e-mail Outgoing mail SMTP server name and return mail address correspond to those set for the user that
has currently opened the project file. (see User Identification for more details)
Note that users will be notified via e-mail for successful project data distribution for them.
The user has an opportunity to send messages by e-mail directly from Spider Project Software. For this purpose in Users
Table it is necessary to specify e-mail the address of all users, and in Spider Project Parameters Dialog window - SMTP
server used to send E-mail.
To create a message, it is necessary to invoke shortcut menu on users line(to whom the message will send) in users table than
In the shortcut menu to choose item to Send Mail. If the mail address for this user was not defined corresponding error
mesaage will appear. In this case invoke user properties dialog window and define E-mail address.
Field To indicates the address of user(it is filled automatically if it was defined before in user properties dialog window)
Subject and the Message fields indicate subject of e-mail and message to be sent, respectively.
If it is necessary to disconnect modem connection after the sending the message, option to Hang up at completion should be
selected.
Send – sends the message.
Close – closes window, without sending the message.
Help – causes help information on this dialog window.
327
Attached Documents
Insert Object dialog window is invoked next. Select between Create New and Create from file. The dialog window
appearance depends on choice you made. When Create New option is selected, dialog window contains list of object types.
Select type and click OK. When Create from file option is selected, dialog window contains path to disk location. Browse
button helps you to locate files easier. Click Link option if you want this OLE-object to be attached to the project, not
embedded into it. Click OK when finished.
To change name or any property of highlighted OLE-object, click Properties.
To delete highlighted OLE-object, click Delete. If OLE-object was of Linked type, only link to it will be deleted,
file/document itself will not be deleted.
328
Attached Documents
Allows setting up properties for object being inserted. Once this dialog window is invoked, its appearance depends on option
you select: Create New or Create from file.
When Create New option is selected, dialog window contains list of object types. Select type and click OK.
When Create from file option is selected, the dialog window contains path to disk location. Browse button helps you to locate
files easier. Click Link option if you want this OLE-object to be attached to the project, not embedded into it. Click OK when
finished.
This page is a part of Object properties dialog windows and allows attaching other applications’ documents (such as
Microsoft Word, Microsoft Excel, or database programs) as well as assigning an object a special folder to store referential
data. It contains the following fields:
329
Attached Documents
List shows all OLE-objects already attached to object. Double click on name will open OLE-object. If list is empty or you
would like to add new OLE-objects, click Add button.
- Add allows attaching new document. OLE object dialog window will be invoked. Type in new OLE-object name (OLE
object by default) and click OK.
- Insert Object dialog window will be invoked. Select between Create New and Create from file. The overall look of the
dialog window depends on choice made. When Create New option is selected, the dialog window contains object types
list. Select type and click OK. When Create from file option is selected, the dialog window contains path to disk location.
Browse button helps you to locate files easier. Click Link option if you want this OLE-object to be attached to the
project, not embedded into it. Click OK when finished. You will be returned to ‘OLE-object and Folder’ standard page.
- Create from Clipboard creates documents from the clipboard of Windows.
- Properties invokes Properties dialog window for highlighted OLE-object.
- Open opens highlighted OLE-object.
- Delete deletes highlighted OLE-object. If OLE-object was of Linked type, only link to it will be deleted, not the
file/document itself.
- Application is text field containing information on application program in which OLE-object was created.
- Creation time shows date and time when OLE-object was created.
- Attachment type shows whether OLE-object is Embedded into the project or Linked. The embedded document is
implemented into the project. The linked document is not saved within the project; only link is saved.
- Path shows path to file if OLE-Object is of Linked type.
- Attached folder frame refers to folder attached to object. It contains text field to enter full path to local or network folder,
Open and Select buttons. Attaching folder does not actually stores information from it in the project database, it only
points to a location where referential information to the current object can be stored. Only one folder can be attached to
program object. To simplify path entering, use Select button. To see the contents of attached folder, use Open button. To
delete folder attachment to the object, clear the path information from the text field.
330
Printing
40. Printing
40.1. Print Preview Window
In print preview window before printing, all pages of the document are displayed. They are displayed with fields, whose size
is set in Printer and Page window, which can be opened in main program window Window toolbar displays the following
icons:
Properties allow editing document printing properties by evoking print options dialog window.
Page Left, Page Right, Page Up, and Page Down allow previewing pages in a corresponding direction.
Each page has double numbering - matrix (numbers of horizontal and vertical numbers) and through (page serial number in
viewing window). For example, if the page has number 2 - 3 (6) it means, that the given page is in the second horizontal and
third vertical line, and its serial number is – six.
Pages to print can be chosen by cursor buttons on the keyboard, and also by left mouse button. It is necessary to keep Ctrl
button pressed while selecting multiple pages with mouse. Selected pages are highlighted round by a red frame, and current
page – by a double red frame.
If after pages are selected, mouse button will be pressed on any page with out keeping Ctrl button pressed all selections will
be canceled and selected page will be current. All selection is also is cancelled at the change Printing Scale and the first page
becomes current.
If on any previewed page mouse button will be double clicked Preview Scale will be set equal 100 %. Again clicking double
returns the previous scale.
Note That: Synchronize document print preview and changes in the document itself by opening both windows
simultaneously.
331
Printing
332
Printing
You can set and edit print template properties in this dialog window:
- page Data;
- notes standard page
Page Data contains following fields:
- Name - print template name;
- Code - unique print template code;
- Title - report name in the printed document;
- Scale (50-1000 %) - allows specifying scale of printed document.
- Subtitle - printed document subtitle;
- Left header, Right header, Left footer, Right footer – in these fields contents of top and bottom headlines are set and
edited;
In Diagram frame, on which page(s) to print diagrams can be set - on every page, on first page only or on last page only.
In Print frame it is possible to choose, which parts will be printed - graphic part (the given option is available only for gantt
diagrams), the left table part or the right table part.
333
Options
41. Options
41.1. Spider Project Parameters Dialog Window
Allows setting up spider project parameters and contains the following frames:
Text Import-Export frame defines text delimiter that will be used during export and import of project tables or
documents/reference-books into text (CSV) files. Delimiter choices are: Tab; Semicolon; Comma; Space; and Other. You can
enter symbols by their ANSI-codes in Other - field. ANSI-codes must be entered after a backslash. E.g., \35 - will set #
symbol as text delimiter.
Save and Open frame contains the following options:
- Create backup copy option, requests to save a backup copy to Backup folder of the corresponding storage every time
the project is saved.
- Reopen if file changed option, selected, offers to reopen the project file every time it was changed by another user in
network. Therefore, the project while being changed by one user (who has access), is constantly updated for other
users who opened the project in read-only mode. (Manager with full project access is given rights to read and write
project, while other users are given read-only accesses)
Undo frame sets up the number of Undo steps (number of rows in Protocol table). Enter the desired number in Depth text
field from 0 to 1000. Select Show notifications option if you want to be notified on each Undo action.
Appearance frame sets up the number of Digits after decimal point. Enter desired number of digits from 0 to 14 in the field (
value "3" is set by default.)
Pressing Material and Cost Column Names setup button opens postfixes of material and cost column names dialog window
where you can customize postfixes, added to the names of columns, corresponding to durations, volumes, expenditures of
cost components and materials.
Date -Time Format button invokes Date Time format window for setting date and time format. Date Delimiter frame allows
selecting the separator of dates -Point, Slash or Hyphen. Time Delimiter frame allows determining the time separator between
hours and minutes -Colon or Point.
- Open properties for new objects – checking this box will enable opening properties dialog window for newly created
objects (where you can enter required properties immediately after the object has been created). This option is disabled
334
Options
by default, so you can create multiple objects faster and define their properties later. Select this option if you wish to
enter properties for the newly created object immediately.
- Keep new report settings - this option lets you temporarily store the parameters list of the last general report or diagram
created in report settings dialog window or diagram settings dialog window, so that you can quickly modify them and
adjust your report or diagram. By default this option is disabled and parameters of the last report or diagram created are
not stored.
- Delete files into Recycle Bin – after selecting this option, deleted projects and documents will be placed into Recycle Bin
with the possibility of their subsequent restoration.
- Open the last active window when opening a project (else – Gantt Diagram) – when this option will be selected, the
project will be opened in the last table, on which user has worked before closing the program (the project must be saved
and closed). If this option will not be selected, projects will be opened on gantt chart as default.
- Highlight overloaded resources –overloaded resources will be highligted in resources table and in gantt diagram
- Highlight acitivites that violate links – if this option is activated, after entering monitoring data, activities that are
violating links between operations, will be highlighted on the graphic part of activity gantt.
STMP Server used to send E-mail field indicates the SMTP address of server.
If SMTP server requests authorization while sending messages by e-mail (via Spider Project Software), select SMTP server
requires authentication option, and enter Username and Password in the corresponding fields located below (User name and
Password)
- OK – saves changes and exits.
- Cancel – exits without applying any changes.
- Help – opens related help window.
This window allows setting up graphical element colors in program windows, and can be invoked in the main program
window by clicking Colors icon on the toolbar.
All elements are combined in groups listed in the left part of the dialog window, in Group frame. Colors can be selected
separately for each element.
For example, Network Diagram group contains Background, Text, Activities, Links, Phases, Selected, and Phase Title
elements. Current color of highlighted element is shown in Color field on the right. To change color for highlighted element,
click Change button. color window, which is a standard color-selecting window, will be invoked.
To return to program color defaults for an element, click Default button after selecting it. To return to default color scheme
for all items, click All by Default (replaces all new settings back with Spider Project Software defaults).
Apply button applies changes without closing Color Setup dialog window.
OK button closes dialog window with all changes saved.
Cancel button closes dialog window without any changes.
335
Options
Is a standard window allows setting up the color of a graphical object. To learn more about this window and its contents, first
click at the ‘?’ sign on the right corner top and then click to the window element of interest.
Allows changing object color from Standard color set up by default to any other. To change, select User defined option and
click Change button. Color dialog window, which is standard color-selecting window, is invoked.
If object currently is of user-defined color and you would like to return to by-default color, select Standard option and click
OK.
Current object color is shown in Color field.
336
Options
Is invoked from main program window by clicking Fonts icon on the toolbar. Allows setting up fonts in different
program windows.
All program elements are combined in groups listed in Group frame. Font can be set up for each element separately.
For example, Table group contains Title and Index, Data elements.
Element’s current font is shown in Font field on the right. To change highlighted element’s font, click Change button. Font
dialog window, which is a standard font-selecting window, is invoked.
Select font properties and click OK. You will be returned to Font Setup dialog window.
To return to default font, click Default button. To return to default font for all items, click All Default.
Apply button changes highlighted item’s font without closing Font Setup dialog window.
OK button closes dialog window, saving all changes.
Cancel button closes dialog window without changes saved.
337
Options
Allows setting up pager size, paper type, orientation (select between Portrait and Landscape), and margins of printed
document. To set up printer properties, click Printer button. Click ‘?’ in the top right corner of the dialog window to learn
more about this dialog window.
Time Scale Dialog window is invoked with double click (or right click) on the Time scale in graphic part of Gantts charts and
is used to set up the time frame for diagram presentation. The scale of the diagram also can be customized with the help of the
scaling tool.
From and To dates in the Scrolling range frame set the minimum period of the project that would be displayed in the
graphical part of the diagram at any scale, selected with the Scaling tool, and that can be scrolled. If you define the time
frame of the project in these date fields that is less than the whole project period, you will also be able to print this time frame
of the project only. If selected scale does not allow viewing the whole time frame in one window, you can scroll the window
with the help of horizontal scroll bar (located at the bottom of the diagram window).
Double click in From and To fields invokes mini-calendar dialog window to simplify date and time entry. You can also edit
dates in these fields manually.
Whole Project button automatically sets the time frame to the whole project duration.
Automatic scrolling range – checking this box enables automatic scrolling range. I.e. after schedule calculation scrollable
project time frame will correspond to the whole project duration. For better presentation results project time frame is
expanded one day ‘to the left’ and certain space (equal to 200 dots) ‘to the right’ – to ensure that existing notes on the
diagram fit space available.
Week’s Title frame contains options for presentation of weeks’ titles on the time scale in Gantt diagrams:
- First day of the week – weeks will have titles corresponding to the date of first days of weeks;
- Week’s number in a year – weeks will have titles corresponding to week’s number in a year;
- Week’s number in a month – weeks will have titles corresponding to week’s number in a month ;
Day’s Title frame contains options for presentation of days’ titles on the time scale in Gantt diagrams:
- Date – days will have titles corresponding to their calendar date;
- Day’s number in a year –days will have titles corresponding to their number in a year;
- Day’s number in a project - days will have titles corresponding to their number in current project;
As you change the scale of your diagram with the help of the Scaling tool, titles on the time scale will change to fit space
available.
If minimum scale is set – only year and comprising quarters will be displayed in the time scale. As you increase the scale of
your diagram, titles on the time scale will also change.
338
Options
Allows setting up a template, that could later be used for automatic text changes in activities, phases, and departments in one
of the following: activity network, OBS(Organizational Breakdown Structure), WBS (Work Breakdown Structure) or PBS
(Project Breakdown Structure) and can be invoked from their menus by pressing icon.
Prefix - allows entering the text you want to appear in front of each field name in Field field.
Field - field contains field names to be edited by template. Edit or add a field by clicking Select button. Select field name in
the invoked fields available dialog window and click OK.
Number of fields to be displayed in activity, phase, or department box depends on current scale in Activity Network, OBS,
WBS, or PBS and can equal 1, 3, or 5.
None option clears field from template canceling its presentation in diagram.
You can enable or disable deletion of unused project objects during phase copying as new project and distribution of
projects.
To enable deletion of unused objects check boxes, corresponding to required object types:
- Resources, Skills, Multi-Resources;
- Materials; Material Sets
- Cost Components;
- Calendars. Weeks and Exceptions
To view this dialog window before each distribution of projects or phase copying as new project leave Show options every
time box checked (is enabled by default).
339
Options
Main frame:
- Remaining – scheduled remaining volume, duration, expenditure;
- Actual – actually passed duration, performed volume, expenditure;
- Total (Actual plus remaining by schedule)
- Total in Compared Project – total volume, duration, or expenditure from the project being compared with.
Fixed frame:
- Fixed Remaining– fixed scheduled expenditure of cost components or materials;
- Fixed Actual - fixed actual expenditure of cost components or materials;
Other frame:
- Material Unit Cost
- Utilizing per hour – expenditure of cost components or materials per hour;
- Overtime Cost per Hour (Percents) (see Overtime )
- Per Volume Unit
Risk Analysis frame (see description of columns in Risk Analysis):
- Critical value
- Target Value
- Probability of Conformance to Targets
340
Options
42. Miscellaneous
42.1. Help
Contains context help for a program element where Spider Project Help button or Help icon was clicked.
42.2. Priority
Priority of Activities.
Priority is a number, reflecting the order of activities performance in resource constrained scheduling. Activities with
higher priority (i.e. larger number of priority) are performed earlier. For example, if two activities share the same limited
resource (with a workload of 100%), activity with higher priority would be scheduled first in resource constrained
scheduling.
Priority of Resources (Multi-resources) Inside Resource Skills.
Priorities of assignments are used in resource skills. Resources (multi-resources) with higher priority of assignment (i.e.
larger number of priority) are scheduled to activity execution first (if they are not busy on others, e.g. higher priority,
activities). Priority of resources (multi-resources) assignments to current activity refers to current activity only.
When a resource skill is assigned to activity execution, priorities of comprising resources (multi-resources) are initially set
to values specified for this resource skill. You can later change priorities of resources (multi-resources) assignments
manually for each activity.
Priority of Phases.
Priority is a number, reflecting the order of phase’s performance in resource constrained scheduling (with Use Phase
Priority option enabled). Phases with higher priority (i.e. larger number of priority) are performed earlier.
Priority of phase is similar to priority of activity, but is of major importance. Phases with higher priorities are scheduled
first irrespective of comprising activities priorities.
42.3. Type
Is standard field in activity, phase, resource, and assignment properties and is used in highlighting, sorting and working with
reference-books.
For all objects, except for resource assignments, there are no strict rules in creating type. For assignments, type is set up from
activity type for which resource is assigned, followed by underscore sign, and assigned resource type. For example, if activity
has Demo type and resource has "A" type, resource assignment will have Demo_A type.
If in reference-book Type field matches with project object type, data from reference-book can be exported to the project.
Type field is set up by default for project presentation in linear diagram.
42.4. Float
Activity Float.
Activity float is the amount of time that an activity may be delayed from its early start without delaying the project finish
date. Float is a mathematical calculation, and can change as the project progresses and changes are made to the project
plan. Activities with floats less than or equal to specified value, often zero, define project critical path and are called
critical activities. Execution delay of such activities leads to increase of project duration unless preventive measures are
undertaken (usually assignment of additional resources, increase of work load and so on).
Resource float.
Resource float defines time interval that the work of this resource may be delayed without delaying the project finish date.
341
Options
342
Options
Clock Cursor means user should wait till the program finishes operation.
Link Cursor means link from one activity to another can be created holding the left mouse button.
Title Cursor appears with the left mouse button click on column header and means the column can be moved to another
location by dragging and dropping.
Duration Cursor means activity duration can be changed by dragging it with the left mouse button click.
Not Earlier Than Cursor means activity start date and Not Earlier Than Start date can be changed by dragging it with
the left mouse button click.
343
Options
Allows inserting texts and is invoked by selecting Insert Text option in gantt diagram shortcut menu, both activity gantt and
resource gantt.
It contains text field for text editing and standard OK, Cancel, and Help buttons.
Allows searching texts in selected table columns or in entire table. To invoke this dialog window:
- Select (highlight) column;
- With the right mouse button click on column header, invoke Table Column shortcut menu; and
- Select Search / Replace option.
Alternatively you can invoke this dialog window from table menu: Edit -> Search / Replace
344
Options
Allows entering date and time into table cells and dialog window fields. Mini-Calendar dialog window is invoked by double
click on table cells of data type or in dialog window fields containing date.
Select month and year from the drop-down lists, or move through the list one by one using left/right arrows in the top part of
the dialog window (there are two sets of left/right arrows corresponding to months and years).
Hours and Minutes are given in drop-down lists in the bottom part of the dialog window. You can either type them in
directly, or select from the drop-down list.
Select a date with a single left mouse button click on corresponding number in the calendar., or double click on date to close
the dialog window and insert the date and time into table or dialog window field.
ANSI-code Symbol
33 !
34 "
35 #
36 $
37 %
38 &
59 ;
64 @
345
Options
Protocol table contains data on all actions (operations) performed by user and contains the following columns (fields) by
default:
- Operation is activity done with object (delete, add, or change value);
- Time is date and time of change;
- Object Name is name of changed object;
- Field Name is name of changed field;
- Old value is field value before it was changed;
- New value is current value in the field;
- User-defined fields.
To cancel the last action performed select menu item Edit -> Undo last action or press button (see Undo for more
details).
When several rows are highlighted simultaneously, shortcut menu contains Delete option only.
Since user is not allowed to add new row in Protocol table, shortcut menu lacks Add option.
346